Planned Islanding and Energy Storage at BC Hydro

26
1 Planned Islanding and Energy Storage at BC Hydro Workshop: International Smartgrid projects review December 10, 2010 Jaime Peralta M.Sc., P.Eng. Distribution Planning T&D Asset Investment Management BC Hydro

Transcript of Planned Islanding and Energy Storage at BC Hydro

Page 1: Planned Islanding and Energy Storage at BC Hydro

1

Planned Islanding and EnergyStorage at BC HydroWorkshop: International Smartgrid projects reviewDecember 10, 2010

Jaime Peralta M.Sc., P.Eng.Distribution PlanningT&D Asset Investment ManagementBC Hydro

Page 2: Planned Islanding and Energy Storage at BC Hydro

2

Agenda

• BC Hydro• Emerging Trends• Planned Islanding• Islanding Assessment & Tech. Req.• BCH Islanding Projects• Energy Storage• Conclusions & Future Challenges

Page 3: Planned Islanding and Energy Storage at BC Hydro

3

BC Hydro • Gov't Owned Crown Corp.

• 1.8 Million Customers

• 10 GW Domestic Peak Load

• Serves 94% of British Columbia

• Integrated G, T, & D Utility

• Aprox. 5,600 Employees

• 18,286 km transmission lines

• 225 Substations

• 1,300 Feeders• Overhead 48,000 km• Underground 8,500 km

• Voltages• D: 12, 25 kV• T: 60kV-500kV

• F2010 Normalized Reliability• SAIFI=1.52 Target = 1.27• CAIDI=2.28 hrs Target = 2.15 hrs• CEMI>=4 =13% Target = 8.5%

• Two-Step Residential Rate• Step 1 (up to 1,350 kWh) 5.91 cents/kWh • Step 2 (> 1,350 kWh) 8.27 cents/kWh• Calculated per billing cycle (typically 2 months)

Page 4: Planned Islanding and Energy Storage at BC Hydro

4

BC Hydro’s business environment

• Ageing utility infrastructure reliability

• Changing demographics knowledge retirement

• Customer expectations access to information, reliability

• Technology advances IEDs, telecom, data management, automation

• Climate change introduction of Clean Energy Act 2010 in BC• Vertical integration of BC Hydro with Transmission (BCTC)

• Self-sufficient by 2016

• Reduce future incremental demand by 66% through DSM

• Meet remaining demand through 93% clean or renewable

• Encourage fuel switching to reduce GHG

• Key projects not subject to BCUC ruling

• Encourage economic development through Clean Technology

Page 5: Planned Islanding and Energy Storage at BC Hydro

5

Emerging Trends• Going from Centralized Generation to Decentralized Gen.• Distributed Generation: Customer Owned Generation• High Penetration of DERs (multiple DGs, IPPs, PV clusters, wind

farms, etc.)• Active Network (Community Energy Storage, Planned Islanding,

Microgrids)

CHP

On-siteGen

PV Clusters

~

Distribution

Generation

Source: SMUD – Premier GardenCommunityEnergy

Systems

Page 6: Planned Islanding and Energy Storage at BC Hydro

6

Planned IslandingTwo approaches for islanding:

• Current practice – Protection against islandingDisconnect DG subsequent to fault or any other switching event and loss of grid, IEEE 1547

• Planned (intentional) islandingSupervised transitions to an island condition in order to allow DG continue operation and serve the local load (Ride-through – Scheduled/Black-start)

Islanded Section

DistributionLoad

PG

Distribution Feeders

DistributionSubstation

Page 7: Planned Islanding and Energy Storage at BC Hydro

7

Planned Islanding

• Why “Planned” Islanding?• To avoid safety concerns, and power quality issues

• When Planned Islanding? • Source is not secure: long transmission lines, long-duration interruptions• Opportunity to defer capital investments for reliability improvement• Special levels of reliability performance required by large customers

• PG Islanding Capability• Is the ability of a PG to continuously supply part of the distribution system that

is separated from the rest of T/D system• Electric supply must be safe, controlled, reliable, and provide acceptable power

quality (V, Hz)

Page 8: Planned Islanding and Energy Storage at BC Hydro

8

PG Islanding Assessment

• Feasibility of PG Islanding:• PG islanding capability• Cyclic generation output

PG output > feeder/area peak load (>4 months)

• Planned islanding strategyRide-through vs. black-start

• Significant reliability improvement (SAIDI)• No power quality issues• Reasonable system upgrades and costs• No operation and safety concerns• Special commercial, or contractual

considerations

Page 9: Planned Islanding and Energy Storage at BC Hydro

9

PGs Technical Requirements

• “Distribution Power Generator Islanding Guidelines”, BC Hydro, June 2006

• Load following capabilities• Generators with broader VAR control (power factor ±0.8)• Fast acting speed governor and exciter• Inertia and controls to pick up dead-feeder load• Black-start capability (scheduled islanding)• PG with sufficient excitation current to allow fault detection• Dual overcurrent protection settings (for parallel and islanded operation)• Capability to maintain power quality (Machines with large inrush current or

cyclic loads)• Operating data/status telemetry (no SCADA)

Page 10: Planned Islanding and Energy Storage at BC Hydro

10

BCH Upgrades & Requirements

• Feeder/area load > PG MVA rating/output if not, feeder sectionalization plan required

• Bi-directional line voltage regulators and fault detection elements• Voltage supervision at feeder substation CB (out-of-phase reclosing)• Reclosers upgrade (disable/delay reclosing function, replace to

electronic)• Line fuses upgrade (replace/relocate/remove)• PG real-time operating data/status at Control Centre and inter-operator

communications• PG commissioning tests for both grid-connected and islanded mode• System impact study (steady-state and dynamic) for islanding

operation, and DOO

Page 11: Planned Islanding and Energy Storage at BC Hydro

11

BC Hydro’s Islanding Projects

2x8 MW IPP hydro plant

Anti-islanding P&C

Golden Battery Storage Project

Fully automated islanding with multiple DERs(Microgrids)

Single DG islanding under operator control

Manual switching Remote control

DER automated islanding

Planned islanding guidelines

6 MW IPP hydro plant

10 MW IPP hydro plant

7.5 MW IPP hydro plant

DER

Inst

alla

tions

1995 2010

Intelligent microgrid research at BCIT

Off

Grid HARP: Integration of hydro plant, fuel

cell, diesel, control systems and flow battery

20052000 2012

Page 12: Planned Islanding and Energy Storage at BC Hydro

12

BC Hydro – Project 2, 2007

Monthly Back-up Capacity and Feeder Peak Demand

0

500

1,000

1,500

2,000

2,500

3,000

3,500

4,000

April

May

June July

Augu

st

Sept

embe

r

Oct

ober

Nov

embe

r

Dec

embe

r

Janu

ary

Febr

uary

Mar

ch

[kW

]

PG Firm Capacity Peak Demand

• 6 MW run-of-river IPP connected to a 25 kV feeder• Outages > 6 hours, from May to Sept. & affect 1,000 customers• Black-start, manual switching

Page 13: Planned Islanding and Energy Storage at BC Hydro

13

BC Hydro - Project 2, 2007

•Islanding study and test results:• Technical study performed by IPP

consultant and BCH• Load-bank used to test PG’s islanding

capability.• Load following and load pick-up

capability• EMTP simulations confirmed test

results• Load blocks (500-800kW) may be

picked up by PG • Installation of switches at BCH feeder.

Load-isolation switching points• BCH prepared PIR and DOO which

includes an islanding plan

0 5 10 15 20 25 30 35 40 45 500.9

0.92

0.94

0.96

0.98

1

1.02

1.04

1.06

1.08

1.1

TIME [S)

MA

CH

INE

SP

EE

D [P

U]

MACHINE SPEED RESPONSE TO A 500 kW LOAD STEP

Page 14: Planned Islanding and Energy Storage at BC Hydro

14

BC Hydro – Project 2, 2007

• Major Achievements:

• BCH successfully contracted an agreement with an existing IPP to provide emergency back-up

• Very few modifications and upgrades were required to implement the project

• One successful islanded operation occurred in 2008 (6hrs, 1000 customers)

• Significant customer reliability improvement (~50%)

BC Hydro Feeder SAIDI SAIFI CAIDI2008 3.77 5.05 0.752007 7.20 6.65 1.082006 34.16 8.87 3.852005 4.30 4.06 1.06

Page 15: Planned Islanding and Energy Storage at BC Hydro

15

BC Hydro – Project 3, 2010

• 10 MW run-of-river IPP connected to a 25 kV feeder

• Large industrial customer (~2 MW + 1 MW BCH customers)

• Black-start & ride-through, automated switching (reclosers)

PHRSUBST.

R-81133

R-9175

R-9176

PG

2 MW

SUB

R-4

R-2

R-1

R-3

Page 16: Planned Islanding and Energy Storage at BC Hydro

16

BC Hydro – Project 3, 2010

• Studies done in CYMDIST/CYMSTAB

Page 17: Planned Islanding and Energy Storage at BC Hydro

17

BC Hydro – Project 3, 2010Voltage:

Clearing Time Clearing Time % of Nominal Voltage Islanding Mode Normal Mode

V < 50% 0.16 sec 0.16 sec 50% < V < 85% 5.0 sec 2.0 sec 85% < V <90% 60.0 sec 2.0 sec 90% < V <106% Normal Operation Normal Operation 106% < V < 110% 60.0 sec 1.0 sec 106% < V < 120% 5.0 sec 1.0 sec V >= 120% 0.16 sec 0.16 sec

Frequency: Under Frequency

Limit Minimum Time Islanding Mode

Minimum Time Normal Mode

60.0-60.5 Hz Continuous Continuous 60.6-61.5 Hz 10 minute 3 minutes 61.6-61.7 Hz 1 minute 30 seconds 61.8-62.5 Hz 1 minute Instantaneous 62.6-67.0 Hz 10 seconds Instantaneous

Greater then 67.0 Hz Instantaneous Instantaneous

Over Frequency Limit Minimum Time Islanding Mode

Minimum Time Normal Mode

60.0-59.5 Hz Continuous Continuous 59.4-58.5 Hz 10 minute 3 minutes 58.4-57.9 Hz 1 minute 30 seconds 57.8-57.5 Hz 1 minute 7.5 seconds 57.4-56.9 Hz 10 seconds 45 cycles 56.8-56.5 Hz 10 seconds 7.2 cycles 56.4-53.0 Hz 10 seconds Instantaneous

Less than 53.0 Hz Instantaneous Instantaneous

• Special PQ requirements for islanding conditions: V, f, harmonics

Page 18: Planned Islanding and Energy Storage at BC Hydro

18

BC Hydro – Project 3, 2010

Page 19: Planned Islanding and Energy Storage at BC Hydro

19

BC Hydro – Energy Storage Project

• 2x1MW ESS in Golden/Field, 25 kV DS

• Constraint substation (peak shaving) and reliability (islanding)

• Contribution from NRCan through CEF

• ISD Sept. 2011

Page 20: Planned Islanding and Energy Storage at BC Hydro

20

• Peak shaving to mitigate capacity risk at Golden substation, includes demand response (~2 MW).

• Islanding to relieve poor reliability metrics at Field (~ 500kW)

GDN Peak Day Load ProfileBased on Winter 2008/2009 Data

-5000

0

5000

10000

15000

20000

25000

30000

35000

12:0

0 AM

1:00

AM

2:00

AM

3:00

AM

4:00

AM

5:00

AM

6:00

AM

7:00

AM

8:00

AM

9:00

AM

10:0

0 AM

11:0

0 AM

12:0

0 PM

1:00

PM

2:00

PM

3:00

PM

4:00

PM

5:00

PM

6:00

PM

7:00

PM

8:00

PM

9:00

PM

10:0

0 PM

11:0

0 PM

2008-12-16 2008-12-20Limit Projected F2013F2013 With 2x1 MVA Energy Storage Energy Storage Charge/Discharge

BC Hydro – Energy Storage Project

Page 21: Planned Islanding and Energy Storage at BC Hydro

21

BC Hydro – Energy Storage ProjectBusiness Case Development• Major costs:

• Battery units, Integration (PCS), P&C, Telecom

• Major benefits• Financial

• Savings of from deferred transformer upgrade costs• Avoided cost of 2 MW equivalent diesel generation for peak shaving and outage support• Leverage from Clean Energy Fund

• Non-financial• Improve reliability for the community of Field (eliminate estimated 80% of outages)• Mitigate risk of demand exceeding capacity at Golden substation• Avoid GHG emissions from use of emergency diesel generator back-up

• Long-term potential• Further benefit from deferred upgrade costs by relocating energy storage to another

capacity constrained substation • Gain critical knowledge in the use of storage technologies: for purposes of peak shaving,

reliability, integrating renewables, and managing multiple distributed resources.

Page 22: Planned Islanding and Energy Storage at BC Hydro

22

BC Hydro – Energy Storage Project

Procurement Process• Battery RFP

• Challenging to develop a specification given the lack of experience in this area• Used external expertise, Quanta Technology• Developed the spec based on functional requirements: Peak shaving & Islanding

• Received 5 responses with 5 different technologies• Lead-acid, Lithium Ion, Vanadium Flow batteries, NAS batteries, Zinc-air

• Integrator RFP• Schedule: Originally unable to post RFP for systems integrator until the battery

contract is complete.• One proponent

• Lessons learned

Page 23: Planned Islanding and Energy Storage at BC Hydro

23

BC Hydro – Energy Storage Project

Project Challenges• Non-technical

• Site selection: geotechnical instability, flooding risk, footprint• Parks Canada property• Community relationship and engagement• Whether conditions: extreme winter conditions challenge battery technologies • Environmental permitting• Internal (BHC) change management

• Technical• Telecommunications: remote location• Lack of standards: safety• P&C, difficult in a long feeder with several reclosers. Low fault contribution from the battery PCS• Smooth remote restoration (re-synch) from islanding operation• Batteries heating and cooling

Page 24: Planned Islanding and Energy Storage at BC Hydro

24

BC Hydro – Energy Storage Project

Project Outcomes• Performance measurement

• Project implementation metrics• Load profile data at batteries and Golden substation• Battery metrics: Efficiency, charge/discharge profiles• Reliability metrics for Field: CAIDI, SAIFI

• Deliverables• BC Hydro Storage Deployment and Integration Guideline 2013• BC Hydro Case Study Report 2014• Knowledge dissemination

• Potential project extensions• Demand response pilot programs• Integration of renewable distributed generation• Integration of energy management systems

Page 25: Planned Islanding and Energy Storage at BC Hydro

25

Conclusion and Future Challenges

• Planned Islanding for Reliability• DGs and IPPs

• Advanced Planned Islanding• Smartgrid (Automated) solutions• Several DER/Microgrid

• Utility-scale Energy Storage• Islanded operation for reliability• Peak shaving• Integration of renewable generation

• Planned Islanding guidelines/IEEE1547.4

Battery Storage

AMR AMR

Load Control

Page 26: Planned Islanding and Energy Storage at BC Hydro

26

Thanks!!

Email: [email protected]

Questions?