Piping Design Basis

download Piping Design Basis

of 26

Transcript of Piping Design Basis

  • PIPINGDESIGNBASIS

    PlantNo.

    DocIndex

    Disc.Code

    DocType

    Rev.No.

    X89 A PD DB A

    PD-X89-DB-0001

    JOBORDER:10-03157-0001 Page1of26MIDYANGASPROCESSINGFACILITIES

    CENTRAL&WESTERNREGIONSPROJECTDEPARTMENT/MIDYANGASPLANTPROJECTSDIVISION(MGPPD)

    BI-10-03157MIDYANGASPROCESSINGFACILITIES

    A 16-OCT-2013 ISSUEDFOR30%DETAILEDDESIGNREVIEW AKH DKD SB VK R

    REV. ISSUEDDATE DESCRIPTIONPREPARED

    BY(ENG)

    REVIEWEDBY

    (LEADENG)HOD PEM

    APPROVEDBY

  • PIPINGDESIGNBASIS

    PlantNo.

    DocIndex

    Disc.Code

    DocType

    Rev.No.

    X89 A PD DB A

    PD-X89-DB-0001

    JOBORDER:10-03157-0001 Page2of26MIDYANGASPROCESSINGFACILITIES

    INDEX

    1.0 SCOPE:-........................................... .......................................................................................5 2.0 PLOTPLAN:-....................................... ...................................................................................5 3.0 UNITPIPING:-..................................... ....................................................................................8 4.0 UNDERGROUND/BURIEDPIPING:-...................... ............................................................12 5.0 FLEXIBILITYANALYSISANDSUPPORTING:-............. .....................................................12 6.0 PIPINGMATERIALS:-................................ ..........................................................................17 7.0 THERMALINSULATIONOFPIPING,EQUIPMENT&VESSELS:- ...................................18 8.0 SURFACEPREPARATION,PAINTING/COATING&COLOURCOD ING:-......................19 9.0 CATHODIC-PROTECTIONFORUNDERGROUNDPIPINGSYSTEM:- .............................19 10.0 MISCELLANEOUS:-................................... ..........................................................................19 11.0 REFERENCES:-...................................... ..............................................................................20 12.0 ANNEXURES:-....................................... ...............................................................................24

  • PIPINGDESIGNBASIS

    PlantNo.

    DocIndex

    Disc.Code

    DocType

    Rev.No.

    X89 A PD DB A

    PD-X89-DB-0001

    JOBORDER:10-03157-0001 Page3of26MIDYANGASPROCESSINGFACILITIES

    ABBREVIATIONS:-

    AARH : ArithmeticAverageRoughnessHeightANSI : AmericanNationalStandardsInstituteAPI : AmericanPetroleumInstituteAS : AlloySteelASME : AmericanSocietyofMechanicalEngineersASTM : AmericanSocietyforTesting&Material sAWWA : AmericanWaterWorksAssociationBHN : BrinellHardnessNumberBS : BritishStandardBS : BoosterStationBW : ButtWeldCBD : ClosedBlowDownCS : CarbonSteelDPT/I/E : DyePenetrantTest/Inspection/Examina tionEFSW : ElectroFusionSeamWeldedEPCC : Engineering,Procurement.ConstructionandCommissi oningGC : GatheringCentreHAZID : HazardIdentificationIGC : InterGranularCorrosionISO : InternationalOrganizationforStandardizat ionLTA : Larsen&ToubroArabiamax. : Maximummin. : MinimumMOC : MaterialOfConstructionMOV : MotorOperatedValveMPT/I/E : MagneticParticleTesting/Inspection/ ExaminationMSS : ManufacturersStandardizationSocietyNB : NominalBoreNACE : NationalAssociationofCorrosionEngineer sNDT/I/E : NonDestructiveTesting/Inspection/Ex amination

    .

  • PIPINGDESIGNBASIS

    PlantNo.

    DocIndex

    Disc.Code

    DocType

    Rev.No.

    X89 A PD DB A

    PD-X89-DB-0001

    JOBORDER:10-03157-0001 Page4of26MIDYANGASPROCESSINGFACILITIES

    OD : OutsideDiameterP&ID : PipingandInstrumentationDiagramPFD : ProcessFlowDiagramPMS : PipingMaterialSpecificationPsi,g : PoundsperSquareInch,GaugePZV : PressureSafetyValvePUF : Poly-UrethaneFoamPWHT : PostWeldHeatTreatmentQRA : QualitativeRiskAnalysi sRF : RaisedFaceRP : RecommendedPracticeRTJ : RingTypeJointRTRP : ReinforcedThermosetting ResinPipeSCRD-M/F : Screwed-Male/FemaleSS : StainlessSteelSP : SpecialProducts/Stan dardPracticeSW : SocketWeldTPIA : ThirdPartyInspection AgencyU/G : UnderGroundUFD : UtilityFlowDiagramVMS : ValveMaterialSpecificationWN : WeldNeck

  • PIPINGDESIGNBASIS

    PlantNo.

    DocIndex

    Disc.Code

    DocType

    Rev.No.

    X89 A PD DB A

    PD-X89-DB-0001

    JOBORDER:10-03157-0001 Page5of26MIDYANGASPROCESSINGFACILITIES

    1.0SCOPE:-

    This Document briefly describes the basic requireme nts for the Design of Piping Systemscovered by ASME B31.3 for the project Midyan Proce ssing Facilities. This document isdeveloped based on feed Basis of Design: GE-E0010 a nd shall be adhered to during thecourse of Detail Engineering, Procurement, fabricat ion, Transportation, Erection, Installation,Testing,Inspection,Pre-commissioningandCommissi oning.

    GENERALDESIGNPHILOSOPHY :-

    2.0 PLOTPLAN:-

    2.1BasisofPlotPlan

    Layoutforthefacilityshallbedevelopedconsider ingtheinputsfromfollowingdocuments: OverallPlotPlan(PI-A100001.001Rev-0A) PlotPlanProcessArea(PI-A100001.002Rev-D) PlotPlanUtility&StorageArea(PI-A100001.003, Rev-C) PlotPlan-Flare&BurnPitArea(PI-A100001.004,Re v-D) PlotPlanSubstationArea(PI-A100001.006,Rev-B) PlotPlan-EvaporationPondsArea(PI-A100001.007, Rev-B) SitePlan-(PI-A100001.005,Rev-D) EquipmentList/Process&MechanicalDataSheets. BasicDesignData. QRArecommendations. StatutoryrequirementsofHSE,SeparationDistance sasperAramcoguidelines(SAES-

    B-005,SAES-054&SAES-B-055). SiteVisitReport.

    2.2ConsiderationsforthefinalizationofPlotPla n

    Followingaspectsshallbeaddressedduringplotpl an/equipmentlayoutdevelopment. 2.2.1 GeneralguidelinessetbySaudiAramcoEngi neering.

    StandardforPlantLayout(SAES-B-055)

  • PIPINGDESIGNBASIS

    PlantNo.

    DocIndex

    Disc.Code

    DocType

    Rev.No.

    X89 A PD DB A

    PD-X89-DB-0001

    JOBORDER:10-03157-0001 Page6of26MIDYANGASPROCESSINGFACILITIES

    Access,EgressandmaterialhandlingforPlantFac ilities(SAES-B-054) SpacinganddikingforAtmosphericandlowpressur etanks(SAES-B-005) ElectricalAreaClassification(SAES-B-068) DesignofPlantPiping(SAES-L-310) Any other applicable Saudi Aramco Engineering stan dards and specification and

    AmericanSocietyofMechanicalEngineers(ASME)Cod eASMEB31.3.

    2.2.2 Proper interconnection between equipment as per P&IDs to achieve the intendedprocessrequirementofnopocket,slope&freedrai ning.

    2.2.3 Process area battery limit shall be marked i n plot plan. All equipments handlinghydrocarbonsshallbe locatedwithin thisprocessa reabattery limit.All safetydistances fromthe process area battery limit to any other facilit y outside the process area shall be as perSAES-B-055guidelines.

    2.2.4 Minimizethequantityofexpensivepiping(s uperior&exoticmetallurgyandlarge/heavysizes&schedules).Theemphasisshallbetoavoidc riss-crossingoflines&theequipmentwithassociated piping shall be aligned to themain proc ess/ utility flowdirection and `incoming&outgoing processandutility streams.The samesha ll be verified through3DModel&modelreviewsessions.

    2.2.5 Erection & Construction requirement: Plant a ccess, Erection scheme, lay down area,cranepositioning& implicationofconstructionseq uence,arrival-at-siteofequipment/ModulesshallbeconsideredduringfinalizationofPlotPla n/equipment-layout,soas tohavesmooth&sequentialerection,mainlywithregardtoheavyeq uipment/over-dimensioned-consignments.

    2.2.6 SafetyRequirements:Thesafetynorms&me asuresshallbestrictlyadheredtoasperSaudiAramcostandardsandguidelinesand thosesug gestedby losspreventionengineer toensure safe work environment during all phases of p roject life cycle. Any otherrecommendation arising from HAZOP, SIL, Building Ri sk Assessment, Fire Risk analysis(FRA),FlareRadiationAnalysisshallalsobeimple mented.

    2.2.7 EyeWash & Safety Showers (EWSS) shall be pr ovided near the facilities involvingchemicalhandling.

  • PIPINGDESIGNBASIS

    PlantNo.

    DocIndex

    Disc.Code

    DocType

    Rev.No.

    X89 A PD DB A

    PD-X89-DB-0001

    JOBORDER:10-03157-0001 Page7of26MIDYANGASPROCESSINGFACILITIES

    2.2.8Constructability,Commissioning,Operation andMaintenanceRequirements:

    Overheadandsideclearancesforvessels,exchang ersandpumps. Provisionofexchangerstubebundlepullingarea. Horizontal & overhead clearances for easy movement of operating

    personnel/maintenancevehicles. -Barrel/Rotorremovalformultistagepumps. CraneapproachesforAir-Coolers/Compressors. Provisionofmonorail/E.O.Tforpumpsaspercontr actualrequirementofProjectScope. Alternateaccessforfirefighting.

    2.2.9 MidyanProcessingFacilitiesshallbemodu larbased,skidmountedunits.Modularunitsshall be shop fabricated, tested and pre commission ed to the extent feasible & within thelimitationofmodulesizesfromtransportationcons ideration.

    2.2.10TheoverallplotplanforMidyanProcessin gFacilitiesshallbedevelopedasperSaudiAramcoEngineeringStandardbyconsideringprevaili ngwinddirectionofWajehWNW.

    2.2.11Equipmentarrangement inprocessmodules hallbeprovidedwithadequatespace tofacilitate operation and maintenance and with minim um spacing requirement as per SaudiAramco Engineering Standard SAES-B-055, Layout of each module and spacing betweenmodules shall allowaccess for equipment from relev ant sides.Howeverall efforts shouldbemadetoimproveupontheaccessaisles/spaceinmod ulesw.r.t.feedlayout.

    2.2.12 Roadways inplantsandother facilities width,overheadclearances,shoulderwidthetc.shallbeprovidedinaccordancewithclause9. 5ofSAES-B-055.For access to tankageareashallprovidedinaccordancewithclause4.13 ofSAES-B-054.

    Spacing and diking for Atmospheric and low pressur e Tanks shall be as per SAES-B-005guidelines.Spacingbetweentanksandassociatedeq uipmentsshallbeasperclauseno.5.2of SAES-B-005. Table 1 shall be followed for minimu m distance requirement two tanks orbetweena tankandotherequipment.Dikingrequirem entshallbeguidedbyclauseno5.3ofSAES-B-005.Dykedesignandconstructionshallbea sperclause5.3.8ofSAES-B-005.

  • PIPINGDESIGNBASIS

    PlantNo.

    DocIndex

    Disc.Code

    DocType

    Rev.No.

    X89 A PD DB A

    PD-X89-DB-0001

    JOBORDER:10-03157-0001 Page8of26MIDYANGASPROCESSINGFACILITIES

    3.0 UNITPIPING:-

    3.1BasisofUnitPiping

    3.1.1 Followinginputsshallbethebasisofunit- piping.

    Overallplotplan EquipmentLayout. Structural&ArchitecturalBuildingDrawings. topographyoftheplant-site. Piping & Instrument Diagram (P&ID), Utility Flow D iagram (UFD) & Process Flow

    Diagram(PFD). Meteorological&Geo-technicaldata. LineDesignationTable. EquipmentData-Sheet&Setting-Plan. InstrumentData-Sheet. Piping&ValveMaterialSpecification(PMS&VMS). SpecificProject/Clientrequirements. SaudiAramcoEngineeringStandards&Specification s.

    3.1.2 Thedesignofplantpipingshallbeinacco rdancewithSAES-L-310.

    Thedesign&conceptualizationofUnit-Pipings hallbefocusedtowardsmeetingthe followingbasicobjectives:

    Process,P&IDandPFDrequirements&stipulations. Access to all operating-points including valves, s pacers & spades, strainers, sample-

    pointsandinstrumentations. Avoidunnecessarypockets, dead-ends&dead-legs. Piping runs shall beas short as

    possiblewithminimumnumberofelbows. Properaccessshallbeplannedw.r.t.`interrelate d-operating-pointsforspecificpurpose

    andforcontrol&maintenance.

  • PIPINGDESIGNBASIS

    PlantNo.

    DocIndex

    Disc.Code

    DocType

    Rev.No.

    X89 A PD DB A

    PD-X89-DB-0001

    JOBORDER:10-03157-0001 Page9of26MIDYANGASPROCESSINGFACILITIES

    Unobstructed & unhindered crane-access shall be pr ovided during construction &likewisemaintenance-vehicles,(hydraulic-cranes& fork-lifts)shallhave adequate-access/approachtocriticalequipmentduringplant -operation.

    Adequate access, egress and material handling for plant facilities shall always beprovided for process, operating & maintenance perso nnel within the unit/ plant inaccordance with SAES-B-054, SAES-J-003 and PIP PCCG N002. Howeverclearance/accesswithinthemodulesmaybecompromi sedinspecificcasetooptimizethemodule/skidsizewhichcanbereviewedduringm odelreviewsession.

    Adequate access to valves, instruments, nozzles et c shall be provided thoughplatforms, scaffolding, mobile stair, permanent lad ders for module and non modulepipinginlinewithPIPPNE0003andPIPPCCGN002.H oweversamecanbereviewedduringmodelreviewsessions.

    Trippinghazardsshallbeminimizedinmodules. Isolation,draining&venting,flushing&purging provisionsshallbeprovided. Piping connected to rotatingand reciprocatingequ ipment, pumpsetc. shall beasper

    SAES-L-310.

    3.2 Pipe-Rack/SleepersPiping

    3.2.1 ThePiperacksshallbe laidoutsuch that t heyshallprovide thenecessaryaccessforalloperationsandmaintenance.Theelevationsof i ntersectingpipewaysshallnormallybeatdifferentleveltoallowforfuturepiping.Aminim umof20%spaceofthetotalwidthofthepiperackshallbeearmarkedforfutureexpansiononthe piperack.

    3.2.2 Finfanexchangersshallbelocatedoverthe mainpiperack.

    3.2.3 Generallythehot linesandcold linesshall bekeptapart indifferentgroupsonarack-tier/sleeper.Predominantlyprocess linesandutili ty linesshallbekeptatdifferent tiers/levels.However incase if thesameisnotfeasibledueto layoutoranyotherconstraintprocessandutilitylinesshallbesegregated&groupedseparat elyonthesametier.

    3.2.4 Generallythebiggersize linesand linesre quiringexpansionloopshallbekeptnearertotherackcolumn/edgeofrackorsleeper.

  • PIPINGDESIGNBASIS

    PlantNo.

    DocIndex

    Disc.Code

    DocType

    Rev.No.

    X89 A PD DB A

    PD-X89-DB-0001

    JOBORDER:10-03157-0001 Page10of26MIDYANGASPROCESSINGFACILITIES

    3.2.5 Theminimumspacingbetweenlinessupported onsleepersorpiperackshallbeasperStandard drawing AC-036207. However in case of any space constraint, followingminimumspacingshallbeadoptedtofixthepipetopipein terdistances:

    Minimumspacing:ODofbiggersizeflange(Aspe rlinerating)+ODofsmallersizepipe+IndividualInsulationthicknessofpipes+25mmcl earance.

    3.2.6 Actual line spacing, especially at L bends and loop locations, shall take care of thethermal-growth (expansion/ contraction) of adjacent lines to allow clash-free thermal-displacements.

    3.2.7 Anchors on the pipe-racks/ sleepers are to b e provided on anchor-bays/ anchor-sleepers. As far as possible anchors shall be distr ibuted over two to three consecutivebays/sleepers.

    3.2.8 Small Bore piping shall generally be always grouped together for ease of supporting.Intermediate supports shall be considered in accord ancewith allowable basic span for smallborepipe,asapplicable.

    3.2.9 Theminimumsleeperheightshallbemaintain edas300mm.

    3.3 Relief/BlowDownSystemPiping

    3.3.1 ReliefSystem/Blowdownsystemdesignshall beasperSAES-F-007.

    3.3.2 Theminimumhorizontal spacing requiremen ts for flares shall be in accordancewithSAES-B-055

    3.3.3 Forburnpitflaresthelast100M(328ft )oftheflareheadersandauxiliarypipingshallbeburiedundergroundorprotectedbyradiationshi eldasperclause6.7.10ofSAES-F-007.

    3.3.4 Pressure relief valves, depressuring valve s and pressure control valves outlets shallenter the flareheader fromaboveandatanoblique angle to theheaderandshallbeasperAramcostandarddrawingAE-036550.

  • PIPINGDESIGNBASIS

    PlantNo.

    DocIndex

    Disc.Code

    DocType

    Rev.No.

    X89 A PD DB A

    PD-X89-DB-0001

    JOBORDER:10-03157-0001 Page11of26MIDYANGASPROCESSINGFACILITIES

    3.3.5 All piping (including headers between flare knockout drums and flares) shall be self-draining into the unit and/or flare knockout drums. Aminimum slope of 1:475 (21mm in 10meters)shallbemaintainedasperclause6.14.5of SAES-F-007.Flat expansion-loopshallbeprovided in horizontal plane as per requirement to accommodate thermal expansion. Thedesign-slopeshallbeensured throughout including flat-loop.Flareheadershallbesupportedonshoeofheightrangingfrom100mmminimumto35 0mmmaximum.

    3.3.6 Proper thermal analysis temperature shall be established including the possibility oftemperaturegradientalongthelinebeforeprovidin gexpansionloops.Effortsshallbemadetominimizethenumberofloops

    3.3.7 Pocketsintheflareheaderandblowdown systemshallbeavoided.

    3.3.8 Inlet and outlet piping of pressure relief valve shall be adequately supported to takecareofthereactionarythrustinducedbytherelie fvalveduringpopping.

    3.3.9 Reaction forces due to safety valve popping shall be ascertained in the connectedpiping according toAPIRP520, for systemsdischar ging to atmosphere. The effect of theseforces on the piping supports, anchors and the supp orting structure shall be adequatelyaddressed.

    3.4 Utility-Stations

    3.4.1 The requirement of utility-stations shall be in accordance with the P&IDs. Whererequiredformaintenanceorcleaningpurpose,utili tystationshallbeprovidedatgradetocovertheentireprocessareaandatworkinglevelsfore levatedequipment,wherenecessary.

    3.4.2 Utilitystationforwater&airshallbeloc atedsuchawaythatalltheequipmentshallbeapproachable from at least one utility station with a 15 mtr hose. The utility station shallgenerallybelocatedadjacenttopipe-rackcolumn.

    3.4.3 Clause18.4ofSAES-L-310shallbefollowed for typeofconnectorsandcolorcodeofthesame.

    3.4.4NitrogensupplyinUtilitystationsshall beincludedasrequiredbyprocess.

  • PIPINGDESIGNBASIS

    PlantNo.

    DocIndex

    Disc.Code

    DocType

    Rev.No.

    X89 A PD DB A

    PD-X89-DB-0001

    JOBORDER:10-03157-0001 Page12of26MIDYANGASPROCESSINGFACILITIES

    3.5 InstrumentAirPiping

    3.5.1 Allmainandbranchheadershallbeslopedm inimum64mmper30m(2.5 inchesper100 ft)and providedwith lowpointdrainasperC lauseno4.8.1.2ofSAES-J-901.Minimumsizeofinstrumentairpipeheadershallbe2ofs chedule40.

    3.5.2 Each branch header shall connect to the top of main header through a branch-line-size,fullboreisolationvalve.

    3.5.3 Supplytakeoffstoindividualinstrumentssh allconnecttothebranchheaderthroughatakeofflinesize,fullboreisolationvalve.

    3.5.4 Instrument air piping shall not be pockete d (i.e. shall not contain U sections).Howeverany specific caseof pocket formationdue t o layoutconstraint shall be reviewedforfurtherconsiderationcasetocasebasisandif foundunavoidableshallbeprovidedwithdrainvalve.

    3.5.5 Pipingmaterialforinstrumentairpipingsh allbegalvanized.

    3.6 FireFightingSystemPiping

    Piping system designated for fire protection water system in plant areas shall comply withSAES-B-017,foamsystemshallcomplywithSAES-B -018,portable,MobileandspecialfixedfirefightingequipmentshallcomplywithSAES-B-0 19.

    4.0 UNDERGROUND/BURIEDPIPING:-

    4.1 Underground or buried piping system shall be de signed in accordance to clause 13 ofSAES-L-310.

    5.0 FLEXIBILITYANALYSISANDSUPPORTING:-

    Flexibility analysis of all piping systems shall b e carried-out in accordance with ASME B31.3andSAES-L-120,SAES-L-310

  • PIPINGDESIGNBASIS

    PlantNo.

    DocIndex

    Disc.Code

    DocType

    Rev.No.

    X89 A PD DB A

    PD-X89-DB-0001

    JOBORDER:10-03157-0001 Page13of26MIDYANGASPROCESSINGFACILITIES

    5.1 PipeSupportingCriteria&GeneralGuidelines

    5.1.1 LoadConditions, as per clause 8, SAES-L -120 shall be used for performing stressanalysisandsupportingofpipingsystem.

    5.1.2 Pipesupportingshallpreferablyfollowth ebasicspanasgiveninAnnexure-I.ForsizesnotcoveredinAnnexure-I,basicspanshallbeesta blishedbasedonprojectrequirement.

    5.1.3 Pipingonrackorsleeper,shallbesupport edoneverygrid.Guidesshallbeprovidedonstraightrunofpipesat intervalsasspecifiedin Annexure-III,unlessspecificallybecomesnon-viableduetoflexibilityproblems.

    5.1.4 Additional supports, guides, anchors, spec ial supports like spring supports and swaybracesshallbeprovidedbasedupondetailedanalys isofpipingsystemtorestricttheforcesonnozzles of critical equipment like pumps, compresso rs, turbines, exchangers, air-coolers,columns&towersetc.

    5.1.5 A permanent support shall be provided for lines which do not need any supportingotherwise but require supporting duringmaintenance . This support shall be either resting orspring-support.

    5.1.6 Bare pipes of size 14NB and above shall b e supported by saddle type support withreinforcementpad.

    5.1.7Adequatecareshallbetakenforsmallb orebranching,(1andbelow).

    5.1.8 Wherever two phases with slug flow in pipin g is expected, piping design shall becheckedbydynamicstressanalysistopreventvib rations.

    5.1.9 Pipe support design shall be such that defl ection in piping systems due to sustainedloadsshallnotexceed15mm,betweentwoadjacents upports.Forsloped-lines,itshallbesuchthattheslopeismaintained.

    5.1.10 Averageinstallationtemperaturetobead optedforstress-analysiscalculationshallbe95F.

  • PIPINGDESIGNBASIS

    PlantNo.

    DocIndex

    Disc.Code

    DocType

    Rev.No.

    X89 A PD DB A

    PD-X89-DB-0001

    JOBORDER:10-03157-0001 Page14of26MIDYANGASPROCESSINGFACILITIES

    5.1.11 Longtrunionsupport(morethan500mmheig ht)shallbeavoidedasfaraspossible,sothatitwillnotcreateexcessivestressesatthea ttachmentweldstotherunpipe.A6mmweepholeshallbedrilledforalldummysupports.Thew eepholeshallbelocatednearthebaseplateforallverticaldummysupports,neartherunpipe at6oclockpositionforallhorizontaldummysupports.

    5.1.12 Piping passing through the structure or pas sing near the column etc. should haveadequatespacetoavoidrestrictionoflinemovemen tduringthermalexpansion. The gapshouldbesufficienttoavoidanyfoulingconsideri nginsulation.

    5.1.13 All pipe-supports shall be so designed that there is no undue tension on equipment flanges.

    5.1.14At any point of the piping system, and for any load combination, horizontaldisplacementshallbewithinthelimitspecifiedin clause6.2.1ofSABP-L-006.

    5.1.15Rodhangersshallbeavoideduseforlines 12NPSandlargerinliquidserviceormulti-phaseflow.Themaximumswingangleduetohorizont alpipemovementwillbe limited to 4degrees.Rodhangershallbeprovidedwithmeansfo rvertical adjustment.

    5.1.16 Springsupportsimmediatelydownstreamof rotatingequipmentwillbelimitedto 10-15%loadvariation.

    5.1.17 Springhangerassemblyshallbedesignedfo rsustainingthehydrotestload.

    5.2 FlexibilityAnalysis-GeneralGuidelines

    5.2.1 GeneralGuidelinesmentionedinclause5of SAES-L-120shallbefollowed.

    5.2.2 TherequirementsmentionedinSpecialRequir ementsclause9ofSAES-L-120shallbefollowed.However forpressure relief valveandde pressurizingsystemsDLF (DynamicLoadFactor)shallbetakenas2forloadcalculation.

    5.2.3 Nozzle loadevaluationforrotatingmachine ryequipmentshallbecheckedforoperatingconditionagainsttheallowableforcesandmoments oftheequipment.

  • PIPINGDESIGNBASIS

    PlantNo.

    DocIndex

    Disc.Code

    DocType

    Rev.No.

    X89 A PD DB A

    PD-X89-DB-0001

    JOBORDER:10-03157-0001 Page15of26MIDYANGASPROCESSINGFACILITIES

    5.2.4 Designofpipingsystemsshalltakeintoa ccountdifferentconditionsexpectedduringoperation,start-up,shut-down,coldbranchincase ofstandbypumpetc.

    5.2.5 Steamoutisnotapplicable.

    5.2.6 Whentheroutingofapipingsystemdoesn otinherentlyprovideadequateflexibility,thesameshall beprovided byadditional expansion-loop sor offsets.Bellowexpansion-jointsaretheleastpreferredmeansofprovidingrequisitefl exibility&theyshallnotbeusedwithoutpriorcompany/clientsapproval.

    5.2.7 DetailedPipingStressanalysis reports shal l includedetails asmentioned inSAES-L-120,AppendixA,CaseA.

    FormalPipingStressAnalysisreportsshallinclude thefollowing:

    1.Operating/designparameters. 2.Pipingisometricdrawingsshallincludethefol lowing a) Dimensions b) MaterialSpecifications c) Locationanddetailsofrestraints. 3.HandCalculation/CalculationperformedwithCA ESAR. 4.Referencedchartsortablesifused.

    5.3 CriteriaforAnalysis

    5.3.1 The requirements mentioned in clause 6 of SA ES-L-120 shall be followed forcategorizingthelinesinPipingFlexibilityAnalys is.

    5.3.2 Flangeleakagecheckisrequiredforthefol lowinglines:

    -ASMEPrRating 600#:26NB&above,exceptair&waterlines. -ASMEPrRating 900#:08NB&above,exceptairandwaterlines. Allothercriticallinesconnectedtosensitiveeq uipmentsuchasplate-finexchangers, cold

    boxes(sizes06NB&aboveandhavinganalysistemp .>250F&85F,analysis temperatureshallbeestablishedthrough

  • PIPINGDESIGNBASIS

    PlantNo.

    DocIndex

    Disc.Code

    DocType

    Rev.No.

    X89 A PD DB A

    PD-X89-DB-0001

    JOBORDER:10-03157-0001 Page16of26MIDYANGASPROCESSINGFACILITIES

    mutual consentwith the process department.However , analysis of flare line& calculation ofthermalgrowthoftallequipmentshallbeperformed asperprocessinput.

    5.3.4 The solar radiation temperature shall be con sidered for bare-lines, if the designtemperature is less than the solar temperature. The metal solar temperature shall beconsideredas160Fasperclause7.2bofSAES-L-1 20.

    5.3.5 Dynamic analysis shall be performed wherever two phase flow with slug in piping isexpected as per the process requirement. Fundamenta l frequency of piping system shall bewell above imposed frequencies, if any, to avoid re sonance. The minimum acceptablefrequencyforlineswithslugflowshallbe06Hz.

    5.3.6 WindAnalysiscriteria:

    Windanalysisshallbeperformedforthelineslis tedunder`staticanalysis,iftheyfallunderthefollowingcriteria:

    Anylineofsize 10NB,(includinginsulation,ifany)&routedat elevation 10m

    Windloadonpipingshallbecalculatedina ccordancewithASCE#07.

    Followingbasicwinddatashallbeconsideredfor wind-loadcalculationasperSAES-A-112forWajeh

    Max.Basicdesignwindvelocity=145km/hr.

    Windshapefactor=0.7

    Windexposure =C,asperASCE#07.

    Structuralclassification=2.0,Occupancycategor yIIasperASCE#07.

    5.3.7 SeismicAnalysiscriteria

    Seismic analysis shall be performed for the lines falling under the criteria of DetailedAnalysisasperchartB-1ofSAES-L-120

    Seismicloadonpipingshallbecalculated inaccordancewithASCE#07.

  • PIPINGDESIGNBASIS

    PlantNo.

    DocIndex

    Disc.Code

    DocType

    Rev.No.

    X89 A PD DB A

    PD-X89-DB-0001

    JOBORDER:10-03157-0001 Page17of26MIDYANGASPROCESSINGFACILITIES

    Following basic Seismic data shall be considered f or Seismic-load calculation as perSAES-A-112forWajeh

    ShortPeriodAcceleration(Ss)in%g =27.1

    1-secPeriodAcceleration(S1)in%g =7.0

    PeakGroundAccelerationin%g =10.8

    SiteClass =D

    ImportanceFactor =1,forOccupancyCategor yIIasperASCE#07

    SiteCoefficientFa =1.6asperASCE#07

    SiteCoefficientFv =2.4asperASCE#07

    ResponseModificationcoefficientR =12asper ASCE#07

    6.0 PIPINGMATERIALS:-

    SaudiAramcoEngineeringStandardSAES-L-132 shallbe followedasgeneralguidelines forMaterialSelection forPipingSystems.ProjectPipi ngMaterialspecificationsPD-X89-SP-1001andValveMaterialSpecificationPD-X89-SP-1002sha llbepreparedasperguidelinesSAES-L-105,SAES-L-108andallotherSAMSS,SAES,Piping Industrypractices(PIP),APIorASMEspecificationsspecifiedtherein.

    6.1 Pipethicknesscalculationshallbebasedonlined esignconditionsasperlinedesignationtableforfollowingcases:

    Forpipeclass6CS9P:Lines10"andabove.

    Forpipeclass15CS9P:Lines4"andabove.

    API 5L pipe used shall either be seamless or doubl e submerged arc welded withlongitudinalseam.

    Softseatedvalvesusedinprocessservicesshall beoffiresafedesign.

  • PIPINGDESIGNBASIS

    PlantNo.

    DocIndex

    Disc.Code

    DocType

    Rev.No.

    X89 A PD DB A

    PD-X89-DB-0001

    JOBORDER:10-03157-0001 Page18of26MIDYANGASPROCESSINGFACILITIES

    MiscellaneousRequirements:

    6.2 NDERequirements

    The general welding requirements for On-Plot Pipin g shall be as per SAES-W-011. Theminimum requirement ofNDE for various piping servi ces shall be in accordancewith clause17.5.2.1ofSAES-W-011.

    6.3 Inspection&Testing

    6.3.1 All itemsand theirpartsshallbesubjecte d toallmandatoryaswellassupplementary(whereverspecified)inspections,testsandchecks called-forintherespectivecodes/standards&specifications/datasheetsinlinewiththeinst ructionsofSAER-1972.

    6.3.2 All inspection and steel piping shall be per formed as per Saudi Aramco InspectionRequirementsForm175-03100.

    6.3.3 PressuretestingforPlantpipingshallc onformtoSAES-L-150,SAES-A-004&SAES-L-125.

    6.3.4 TheminimummandatoryrequirementforPMIsh allbeasperSAES-A-206.

    7.0 THERMALINSULATIONOFPIPING,EQUIPMENT&VESSE LS:-

    Minimummandatory requirements for design and inst allation of insulation shall be as perSAES-N-001&ProcessIndustryPipinginsulationdes ignGuidePIPINEG1000.

    Followingbasicinsulationmaterialtobeused.

    Hotinsulation:MineralFiber

    ColdInsulation:PolyurethaneFoam(PUF)

    However, Insulation thickness on piping shall be a s per the operating temperaturefurnishedinthelinedesignationtableissuedbyp rocessEngineeringGroup.

  • PIPINGDESIGNBASIS

    PlantNo.

    DocIndex

    Disc.Code

    DocType

    Rev.No.

    X89 A PD DB A

    PD-X89-DB-0001

    JOBORDER:10-03157-0001 Page19of26MIDYANGASPROCESSINGFACILITIES

    8.0 SURFACEPREPARATION,PAINTING/COATING&COLOUR CODING:-

    ExternalandInternalcoatingmaterialselections hallbeasperclause7ofSAES-H-001&clause5ofSAES-H-002. Surfacepreparationshall beasperclause8ofSAES-H-001.

    ForcolorcodingandmarkingforpipingSAES-B-067 shallbereferred.

    9.0 CATHODIC-PROTECTIONFORUNDERGROUNDPIPINGSYST EM:-

    Theburiedpiping(includingappurtenan ces)shallbecatholicallyprotectedasperSAES-X-600.

    10.0 MISCELLANEOUS:-

    10.1 Quality of water used for hydro testing shallmeet the requirements of Saudi EngineeringAramcoStandardSAES-A-007.Hydrostatictestwater smustbedisposedofinaccordancewith the requirements of SAEP-327 andSAES-A-103. A ll lines subjected to hydro testingshallbeprovidedwithhighpointhydro test venta nd lowpointhydro testdrain.Hydrotestvent and drain size shall be of . For pipe class 900 and above double isolation valveshallbeused.Gatevalveshallbeusedforhydrote stdrain/vent.HoweverallprocessdrainandventshallbeasperSaudiAramcostd.AC-03604 5.001.

    10.2 Allcleaning,flushingofpipingspoolsandsystems shallbeinaccordancewithclause15&AppendixAof SAES-L-350.

    Cleaning requirements in centrifugal compressors ( sales gas compressors and propanerefrigerationcompressor)shallbeasperClauseno .5.6ofSAES-K-402.

    Cleaning requirements in reciprocatingcompressors (recyclegascompressor )shallbeasperClauseNo. 6.16ofSAES-K-403.

    CleanlinessStandardforLube/SealOilandFluidP owerSystemsshallbeasperSAES-G-116.

  • PIPINGDESIGNBASIS

    PlantNo.

    DocIndex

    Disc.Code

    DocType

    Rev.No.

    X89 A PD DB A

    PD-X89-DB-0001

    JOBORDER:10-03157-0001 Page20of26MIDYANGASPROCESSINGFACILITIES

    ChemicalCleaningandFlushingofLube/SealOilan dFluidPowerSystemsshallbeasperSAEP-1028

    10.1 DesignandinstallationoffireproofingforPipe-Su pportsshallbeasperclause5.5ofSAES-B-006.

    10.2 SafetyidentificationandSafetycolorsshallconf ormtoSAES-B-067requirement.

    10.3 Followingequipmentsshallbeprovidedwithsuns hadeasperprojectrequirement.

    SalesGasCompressor PropanerefrigerationCompressor RecycleGasCompressor InstrumentAirCompressor FireWaterPumps DGSet BoosterPumps

    Mobilecraneshallbeavailableforanymaintenanc eworkfortheitemsserialno.atof.BoosterPumpsshall beprovidedwithEOTof3Tca pacity.

    11.0 REFERENCES:-

    It shall be noted that allCodes,Standards &Specifications referenced underneath shallbe invariably the latest revisionswithalladdendu ms,at the timeof `IssueofWork-Order/`Award-of-ContractfortheMidyanGasProcessingF acilities.

    11.1 SaudiAramcoEngineeringStandards:

    SAES-A-007 :HydrostaticTestingFluidsandLay- Upprocedures

    SAES-A-112 :MeteorologicalandSeismicDesignD ata

    SAES-A-202 :SaudiAramcoEngineeringDrawingPr eparation

    SAES-B-005 :SpacingandDikingforAtmospheric andLow-PressureTanks

    SAES-B-017 :FireWaterSystemDesign.

    SAES-B-018 :FoamSystems

    SAES-B-019 :Portable,MobileandSpecialFixed FirefightingEquipment

  • PIPINGDESIGNBASIS

    PlantNo.

    DocIndex

    Disc.Code

    DocType

    Rev.No.

    X89 A PD DB A

    PD-X89-DB-0001

    JOBORDER:10-03157-0001 Page21of26MIDYANGASPROCESSINGFACILITIES

    SAES-B-054 :Access,Egress,andMaterialsHandl ingforPlantFacilities

    SAES-B-055 :PlantLayout

    SAES-B-067 : SafetyIdentificationand SafetyColor

    SAES-B-068 :ElectricalAreaClassification

    SAES-B-069 :EmergencyEyewashesandShowers

    SAES-F-007 :SystemDesignCriteriaofFlares.

    SAES-G-116 :CleanlinessStandardforLube/Seal OilandFluidPowerSystems

    SAES-L-100 :ApplicableCodesandStandardsfor PressurePipingSystems

    SAES-L-101 :RegulatedVendorListforPipes,Fi ttingsandGaskets

    SAES-L-102 :RegulatedVendorListforValves

    SAES-L-105 :PipingMaterialSpecification.

    SAES-L-108 :SelectionofValves

    SAES-L-109 :SelectionofPipeFlanges,StudBol tsandGaskets

    SAES-L-110 :LimitationsonPipingJointsandCo mponents

    SAES-L-120 :PipingFlexibilityAnalysis

    SAES-L-125 :SafetyInstructionSheetforPiping andPipelines.

    SAES-L-130 :MaterialforLowTemperatureServic e

    SAES-L-131 :FractureControlofLinePipe

    SAES-L-132 :MaterialSelectionforPipingSyste m

    SAES-L-133 :CorrosionProtectionRequirementsf orPipelines/Piping

    SAES-L-136 :PipeSelectionandRestriction

    SAES-L-150 :PressureTestingofPlantandPipel ines

    SAES-L-310 :DesignofPlantPiping

    SAES-L-350 :ConstructionofPlantPipingSystem s

  • PIPINGDESIGNBASIS

    PlantNo.

    DocIndex

    Disc.Code

    DocType

    Rev.No.

    X89 A PD DB A

    PD-X89-DB-0001

    JOBORDER:10-03157-0001 Page22of26MIDYANGASPROCESSINGFACILITIES

    SAES-S-050 :SprinklerandStandpipeSystemsin Buildings

    SAES-S-070 :InstallationofUtilityPipingSyst ems

    SAES-J-700 :ControlValves.

    SAES-H-001 :CoatingSelectionandApplicationRe quirementsforIndustrialPlants andEquipments.

    SAES-H-002 :InternalandExternalCoatingsforS teelPipelinesandPipings

    SAES-H-101 :ApprovedProtectiveCoatingSystem.

    SAES-K-402 :CentrifugalCompressors

    SAES-K-403 :ReciprocatingCompressors

    SAES-L-610 :NonmetallicPipinginOil yWaterServices.

    SAES-W-011 :WeldingrequirementsforOn-PlotPip ing.

    SAES-N-001 :BasicCriteriaIndustrialInsulation .

    SAES-X-600 :CathodicProtectionforPlantFacil ities.

    11.2 SaudiAramcoMaterialStandard

    01-SAMSS-010 :FabricatedSteelPiping

    01-SAMSS-017 :AuxiliaryPipingforMechanicalEq uipments.

    11.3 SaudiAramcoEngineeringProcedures

    SAEP-110:SaudiAramcoStandardDrawings

    SAEP-1028:ChemicalCleaningandFlushingofLube/ SealOilandFluidPowerSystems

    11.4 SaudiAramcoBestPractice

    SABP-L-006:PipingStressAnalysisReview

    SABP-L-010:GuidelinesforEvaluatingPipeMovemen t

  • PIPINGDESIGNBASIS

    PlantNo.

    DocIndex

    Disc.Code

    DocType

    Rev.No.

    X89 A PD DB A

    PD-X89-DB-0001

    JOBORDER:10-03157-0001 Page23of26MIDYANGASPROCESSINGFACILITIES

    11.5 ProcessIndustryPractices

    PIPPNF0003 : ProcessIndustryPract ices-ProcessUnitandOffsitesLayout Guide

    PIPINEG1000 : InsulationDesignGuide

    11.6 ListofInternationalCodesandStandards:

    ASMESEC.II,Part-C: MaterialSpecifications: WeldingRods,Electrodes&Filler- Metals.

    ASMESEC.VIII : Rulesfortheconst ructionofPressureVessels.

    ASMESEC.IX : Welding&Brazingq ualifications.

    ASMEB31.3 : ProcessPiping.

    ASMEB16.5 : PipeFlangesandF langedFittings(NPSThruNPS24) ASMEB16.9 : FactoryMadeWroug htButtWeldedFittings

    ASMEB16.10 : Face-to-FaceandEn d-to-EndDimensionofValves

    ASMEB16.11 : ForgedFittings,So cketWeldedandThreaded

    ASMEB16.20 : MetallicGaskets

    ASMEB16.2 : Non-MetallicGaske ts

    ASMEB16.25 : ButtweldingEnds

    ASMEB16.47 : LargeDiameterStee lFlanges(NPS26ThruNPS60) APIRP520 : Selection,Sizin g&InstallationofPressureRelievingDevices inRefineries.

    APIStd.610 : CentrifugalPumps forPetroleum,HeavyDutyChemical&Gas IndustryService.

    APIStd.661 : AirCooledHeat Exchanger.

    APIStd.560 : FiredHeaters.

    NACEMR0175/ : Materialsforusein H2ScontainingenvironmentsinOil&Gas

  • PIPINGDESIGNBASIS

    PlantNo.

    DocIndex

    Disc.Code

    DocType

    Rev.No.

    X89 A PD DB A

    PD-X89-DB-0001

    JOBORDER:10-03157-0001 Page24of26MIDYANGASPROCESSINGFACILITIES

    ISO15156 Production/Refi neries

    11.7 ListofProjectSpecificationsandotherdocu ments:

    GE-E00010 : BasisofDesign

    PI-E00151 : SpecificationofPipingM aterials(Issuedfor90%Project Proposal) PD-X89-SP-1001 : PipingMaterialSpecif ication(PMS). PD-X89-SP-1002 : ValveMaterialSpecifi cation(VMS). CE-MFP-DB-4001 : Civil&Structuraldesi gnbasis.

    12.0 ANNEXURES:-

    (i).AnnexureI : Tableofbasic-spanfor pipes.(iii)AnnexureII : Verticalandhoriz ontalguide-spacings.

  • PIPINGDESIGNBASIS

    PlantNo.

    DocIndex

    Disc.Code

    DocType

    Rev.No.

    X89 A PD DB A

    PD-X89-DB-0001

    JOBORDER:10-03157-0001 Page25of26MIDYANGASPROCESSINGFACILITIES

    ANNEXURE-ITABLEOFBASIC-SPANFORPIPES.

    PipeType

    PipeSizeNB

    (Inch)

    SCH/THK(In)

    Pipe,Vapour&Insulation Pipe,Liquid&Insulation BarePipe,EmptyBarePipe&WaterFilled Pipe

    SizeNB

    (Inch)BasicSpan(L),meter BasicSpan(L),meter - -

    Upto175C

    176Cthru315C

    316Cthru400C

    Upto175C

    176Cthru315C

    316Cthru400C

    Span(L),m

    WeightKg/m

    Span(L),m

    WeightKg/m

    Carbon-Stee

    l/Alloy-Stee

    lSc

    hedu

    le-40

    ,Se

    ries

    SCH40 3.5 3.5 2.5 3.5 3.0 2.0 4.5 1.68 4.0 2.04 1 SCH40 4.5 4.0 3.0 4.5 3.5 3.0 5.0 2.52 4.5 3.07 11 SCH40 5.0 5.0 3.5 5.0 4.5 3.5 6.0 4.08 5.0 5.4 0 12 SCH40 5.5 5.0 3.5 5.0 4.5 3.5 6.5 5.47 5..5 7.6 5 22 SCH40 6.5 6.0 3.0 6.0 5.5 4.5 7.5 8.7 6.5 11.7 9 23 SCH40 7.5 6.5 5.5 6.5 6.0 5.0 8.0 11.35 6.5 16. 15 34 SCH40 8.0 7.5 6.5 7.5 7.0 6.0 9.0 16.2 7.5 24.4 5 46 SCH40 10.0 9.5 8.5 9.0 8.0 7.5 10.5 28.3 9.0 46 .70 68 SCH40 12.0 11.0 10.0 10.0 10.0 9.0 12.0 42.84 1 0.0 75.22 810 SCH40 13.5 13.0 12.0 11.5 10.5 10.5 14.0 60.74 11.5 111.90 1012 3/8w 14.5 13.5 13.0 12.0 11.5 11.0 15.0 74.40 12.0 147.50 1214 3/8w 15.0 14.5 13.5 12.0 12.0 11.5 16.0 82.5 12.5 172.05 1416 3/8w 16.0 15.5 14.5 13.0 12.5 12.0 17.0 94.5 13.0 213.15 1618 3/8w 17.0 16.5 15.0 13.5 13.0 12.0 18.0 106.5 13.5 258.30 1820 3/8w 18.0 17.5 16.0 14.0 13.5 12.5 19.0 118.5 14.0 307.50 2024 3/8w 20.0 19.0 17.5 14.5 14.5 13.0 21.0 142.5 15.0 418.20 24

    Carbon-Stee

    l/Alloy-Stee

    lSc

    hedu

    le-80

    ,Se

    ries

    SCH80 3.5 3.5 2.5 3.5 3.0 2.0 4.5 2.20 4.0 2.49 1 SCH80 4.5 4.0 3.0 4.5 3.5 3.0 5.0 3.25 4.5 3.72 11 SCH80 5.0 5.0 4.5 5.0 4.5 4.0 6.0 5.45 5.0 6.6 0 12 SCH80 6.0 5.0 4.5 5.5 5.0 4.0 6.5 7.53 6.0 9.45 22 SCH80 6.5 6.0 5.5 6.0 6.0 5.0 7.5 11.49 6.5 14 .25 23 SCH80 7.5 6.5 6.0 6.5 6.5 6.0 8.0 15.37 7.0 19. 66 34 SCH80 8.0 8.0 7.0 7.5 7.5 6.5 9.0 22.47 8.0 29. 94 46 SCH80 10.5 10.0 9.0 9.5 9.0 8.5 10.5 42.90 9.5 59.85 68 w 12.0 11.5 10.5 10.5 10.0 10.0 12.0 65.10 11 .0 94.80 810 w 13.5 13.0 12.0 11.5 11.5 10.5 14.0 82.20 1 2.0 130.69 1012 w 14.5 13.5 13.0 12.5 12.0 11.5 15.0 98.13 1 3.0 168.64 1214 w 15.0 14.5 13.5 13.0 12.5 12.0 16.0 108.15 13.5 194.40 1416 w 16.0 15.5 15.0 13.5 13.0 13.0 17.0 124.2 1 4.0 240.00 1618 w 17.5 17.0 16.0 14.5 14.0 13.5 18.0 140.25 14.5 286.64 1820 w 18.0 17.5 17.0 15.0 14.5 14.0 19.0 157.5 1 5.0 341.80 2024 w 20.0 19.0 18.5 16.0 15.0 15.0 21.0 188.25 16.0 458.44 24

    Stainless-Stee

    lSc

    hedu

    le-10

    S,Se

    ries

    1 10S 4.0 3.5 3.0 4.0 3.0 2.5 4.5 2.08 4.0 2.70 1 1 10S 5.0 4.5 3.0 4.5 4.0 3.0 5.5 3.12 5.0 4.57 12 10S 5.0 4.5 3.5 4.5 4.0 3.0 6.0 3.94 5.5 6.33 2 2 10S 6.5 5.5 4.5 5.5 5.0 4.5 7.0 5.26 6.0 8.85 23 10S 7.0 6.0 5.0 6.0 5.5 5.0 7.5 6.45 6.0 11.91 34 10S 7.5 7.0 6.0 6.5 6.0 6.0 8.0 8.34 7.0 17.67 46 10S 9.5 9.0 8.0 8.0 7.5 7.5 10.0 13.82 8.5 34.5 4 68 10S 11.0 10.5 10.0 10.95 9.5 8.5 11.5 19.94 10. 0 55.50 810 10S 12.5 12.0 11.0 10.5 10.0 9.5 13.0 27.83 11 .0 83.40 1012 10S 14.0 13.0 12.0 11.0 11.0 10.0 14.5 36.00 1 1.5 114.60 1214 10S 14.5 14.0 13.0 11.5 11.0 11.0 15.5 41.18 1 1.5 132.60 1416 10S 16.5 14.5 14.0 12.0 11.5 11.5 16.5 47.33 1 2.5 172.20 1618 10S 16.5 15.5 14.5 12.5 12.5 11.5 17.5 53.18 1 3.0 212.10 1820 10S 17.5 16.5 15.5 13.0 13.0 12.0 18.5 68.50 1 3.0 264.50 2024 10S 19.0 18.0 17.0 14.0 13.5 12.5 20.5 94.37 1 4.0 376.8 24

  • PIPINGDESIGNBASIS

    PlantNo.

    DocIndex

    Disc.Code

    DocType

    Rev.No.

    X89 A PD DB A

    PD-X89-DB-0001

    JOBORDER:10-03157-0001 Page26of26MIDYANGASPROCESSINGFACILITIES

    ANNEXURE-II

    VERTICALANDHORIZONTALGUIDESSPACING

    Pipesize(Inches)

    VerticalSpacing(m)

    HorizontalSpacing(m)Note-1

    16 61.5

    23

    8 1246810

    12

    18

    1214161820

    162426&above.

    GENERALNOTES:-

    1) Thesespacingsmaybevariedtosuitcolumnspac ingofpipe-rack.Theabovespacingisforstraightrunsofpipe&doesnotincludethe rmo-guideswhichareusedforcontrolofthermalmovements,asdecidedbythestress-grou p.

    2) Theguidespacingsfurnished/providedinthea bovetableareindicativeonly.