Contract Page 1 of 2 C3.4 Part C3: Scope of Works General Construction Aspects Transnet Freight Rail Contract No. S.I.E 10032CIDB A division of Transnet Limited PARTICULAR / GENERIC SPECIFICATIONS BBB0041 version 4: Preparation of drawings for Transnet Freight Rail infrastructure. BBB0496 version 13: 3kV rectifier for traction substations. BBB0845 version 4: Requirements for metal oxide surge arresters without gaps for AC systems in accordance with gaps for AC systems in accordance with SANS 60099-4. BBB0937 version 4: Requirements for outdoor post type current transformers for traction and distribution substations. BBB1267 version 10: Requirements for outdoor alternating-current circuit breakers for traction and distribution substations. BBB1616 version 3: 450 Volt gas arrester sparkgap for traction power supplies. BBB2007 version 1: Environmental guidelines and specifications for electrical construction work. BBB2502 version 6: Requirements for battery charger for 3kV DC traction substations. BBB2721 version 10: AC primary circuit breaker control panel and AC/DC distribution panel for 3kV traction substations. BBB3005 version 1: 3kV DC under voltage relay manufacturing specification. BBB3059 version 1: 3kV DC traction substation earthing system for high voltage outdoor yards. BBB3139 version 1: Wave filter capacitors for 3kV DC substations. BBB3162 version 1: Wave filter inductors for 3kV DC substations. BBB3890 version 2: Requirements for a 1.8mHenry DC reactor for 3kV DC traction substations. BBB4724 version 4: Requirements for positive isolator for 3kV DC traction substations. "Preview Copy Only"

Transcript of Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification...

Page 1: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Contract Page 1 of 2 C3.4 Part C3: Scope of Works General Construction Aspects

Transnet Freight Rail Contract No. S.I.E 10032CIDB A division of Transnet Limited

PARTICULAR / GENERIC SPECIFICATIONS

BBB0041 version 4: Preparation of drawings for Transnet Freight Rail infrastructure.

BBB0496 version 13: 3kV rectifier for traction substations.

BBB0845 version 4: Requirements for metal oxide surge arresters without gaps for AC systems in accordance with gaps for AC systems in accordance with SANS 60099-4.

BBB0937 version 4: Requirements for outdoor post type current transformers for traction and distribution substations.

BBB1267 version 10: Requirements for outdoor alternating-current circuit breakers for traction and distribution substations.

BBB1616 version 3: 450 Volt gas arrester sparkgap for traction power supplies.

BBB2007 version 1: Environmental guidelines and specifications for electrical construction work.

BBB2502 version 6: Requirements for battery charger for 3kV DC traction substations.

BBB2721 version 10: AC primary circuit breaker control panel and AC/DC distribution panel for 3kV traction substations.

BBB3005 version 1: 3kV DC under voltage relay manufacturing specification.

BBB3059 version 1: 3kV DC traction substation earthing system for high voltage outdoor yards.

BBB3139 version 1: Wave filter capacitors for 3kV DC substations.

BBB3162 version 1: Wave filter inductors for 3kV DC substations.

BBB3890 version 2: Requirements for a 1.8mHenry DC reactor for 3kV DC traction substations.

BBB4724 version 4: Requirements for positive isolator for 3kV DC traction substations.

"Prev

iew C

opy O

nly"

Page 2: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Contract Page 2 of 2 C3.4 Part C3: Scope of Works General Construction Aspects

BBB5019 version 5: Requirements for traction transformers for 3kV DC traction substations in accordance with BS 171 and IEC 60076-1.

BBB5452 version 5: Spoornet requirements for the installation of electrical equipment for 3kV DC traction substations.

BBB7842 version 1: Outdoor, high voltage, alternating current disconnector combined with earthing switches.

BBB8204 version 2: Medium voltage distribution transformers in accordance with SANS 780.

BBC0198 version 1: Requirements for the supply of cables.

BBC0455 version 1: Eskom phase failure detection circuit.

BBC7616 version 1: Policy and guidelines for management of polychlorinated biphenyls in Transnet Freight Rail.

CEE.0023.90: Specification for installation of cables.

CEE.0045.2002/1: Painting of steel components of electrical equipment.

CEE.0099.2005: Specification for 3kV DC high speed circuit breakers for traction substations.

CEE.0177.86: Code of practice, earth systems for electric light and power and traction installations.

CEE.0224.2002: Drawings, catalogues, instruction manuals and spares lists for electrical equipment supplied under contract.

CEE.0227.95: The manufacture of 3kV DC breaker cells and trucks.

CEE.0229.95: Dry-out and regeneration of insulating oil and reclaiming and de-sludging of transformers.

S420 (1999): Specification for concrete work.

"Prev

iew C

opy O

nly"

Page 3: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A division of Transnet Limited Refurbishment of 3kV traction substations

Contract Page 1 of 1 C3 Part C3: Scope of Works

PART C3

SCOPE OF THE WORKS

CONTENTS Section Description

C3.1 DESCRIPTION OF THE WORKS

C3.2 ENGINEERING

C3.3 PROCUREMENT

C3.4 GENERAL CONSTRUCTION ASPECTS

C3.5 MANAGEMENT OF THE WORKS

C3.6 ENVIRONMENTAL REQUIREMENTS

C3.7 PARTICULAR SPECIFICATIONS

"Prev

iew C

opy O

nly"

Page 4: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A Division of Transnet Limited Refurbishment of 3kV DC traction substations

Contract Part C3: Scope of Works

Part C3: Scope of Works

"Prev

iew C

opy O

nly"

Page 5: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A division of Transnet Limited Refurbishment of 3kV traction substations

Contract Page 1 of 4 C3.1 Part C3: Scope of Works Description of the Works

Part C3

Section 1

DESCRIPTION OF THE WORKS

CONTENTS Item Description Page

1.1 EMPLOYER’S OBJECTIVE ................................................................................2

1.2 OVERVIEW OF THE WORKS .............................................................................2

1.3 EXTENT OF THE WORKS ..................................................................................2

1.4 LOCATION OF THE WORKS..............................................................................3

1.5 TEMPORARY WORKS .......................................................................................4

"Prev

iew C

opy O

nly"

Page 6: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A division of Transnet Limited Refurbishment of 3kV traction substations

Contract Page 2 of 4 C3.1 Part C3: Scope of Works Description of the Works

Part C3

Section 1

DESCRIPTION OF THE WORKS

1.1 EMPLOYER’S OBJECTIVE

1.1.1 The Employer’s objective is to totally refurbish traction substations on the KwaZulu Natal main line to reduce maintenance costs and improve the reliability of the network.

1.2 OVERVIEW OF THE WORKS

1.2.1 The contract covers the refurbishment / replacement of South Portal, Quail, Nottingham Road, Danskraal, Elandslaagte, Wasbank and Glencoe traction substations.

1.2.2 See drawings BBB8365, BBC0665, BBC0666, BBC0668, BBC0673, BBC0964 and BBC0968 for the existing site layouts.

1.2.3 It includes the design, supply, delivery, installation, test and commissioning of new indoor and outdoor plant as well as cabling, wiring and connections.

1.2.4 The work also includes alterations to the existing substation buildings.

1.2.5 The supply to all the substations is 88kV AC and is converted to an output (load) of 3kV DC traction.

1.3 EXTENT OF THE WORKS

1.3.1 Disconnect, dismantle and remove plant in the outdoor yard and inside the substation building as required. Plant identified for re-use (re-installed) shall be kept in a safe and secure place by the contractor. The specific requirements for the works are specified in Part C3.7.

1.3.2 Installation of the plant shall be as described in the Transnet Freight Rail specification BBB 5452.

1.3.3 Where conflicting requirements occur between any referenced drawings and / or specifications and Part C3, the requirements of Part C3 shall apply.

1.3.4 The substations shall be refurbished in total and none of the existing plant shall be re-used unless it is stated otherwise in the documentation.

1.3.5 The Contractor shall also be liable for any other additional requirements that may arise for the operation and protection of the substations.

1.3.6 All existing traction transformers shall be refurbished in total excluding the two at Danskraal. These shall be replaced with new 5MVA transformer.

1.3.7 Remove crusher stone up to ground level and refill the outdoor yard with new crusher stones.

1.3.8 All existing foundations not suitable or not identified for re-use shall be demolished to 100mm below surrounding ground level.

1.3.9 Replace complete earth mat and earthing of the substation.

1.3.10 Cast concrete foundations, gutters and aprons as specified.

"Prev

iew C

opy O

nly"

Page 7: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A division of Transnet Limited Refurbishment of 3kV traction substations

Contract Page 3 of 4 C3.1 Part C3: Scope of Works Description of the Works

1.3.11 Supply and install steelwork for lightning arrestors, AC disconnects, AC circuit breakers and current transformers as specified.

1.3.12 Supply and install outdoor and indoor plant and additions for the operation of the substation.

1.3.13 Supply and install new control and HV cables as required.

1.3.14 Connect and earth structures and plant as required.

1.3.15 All regenerative braking plant other than the HSCB shall be retained but incorporated in the schematic wiring diagrams and operation of the substation.

1.3.16 Renovate / refurbish the substation building.

1.3.17 Transportation of the old plant, which will not be re-used, to Transnet Freight Rail Infra maintenance depot in Ladysmith.

1.3.18 Remove and transportation of oil from OCBs and CTs to Transnet Freight Rail Infra maintenance depot in Ladysmith.

1.3.19 Provide drums for oil to be drained from the OCBs and CTs.

1.3.20 Replace/Repair fencing and gates as specified.

1.3.21 Transnet Freight Rail will be responsible for the fire fighting plant.

1.3.22 All tele-control plant shall be retained. All the functions and operation of the tele-control shall be tested as part of commissioning.

1.3.23 Test, commission and hand over the plant.

1.3.24 The works exclude work on Eskom structures.

1.3.25 A Contractor appointed by Eskom may be on site to do refurbishment of the Eskom plant in the substation yards.

1.3.25.1 Some coordination between Eskom, Transnet Freight Rail and the Contractor will have to be arranged when the Eskom contractor is on site. See Part C.3.7.

1.4 LOCATION OF THE WORKS

1.4.1 The locality of the works is at the following 3kV DC traction substations of Transnet Freight Rail;

1.4.1.1 South Portal

1.4.1.2 Quail

1.4.1.3 Nottingham Road

1.4.1.4 Danskraal

1.4.1.5 Elandslaagte

1.4.1.6 Wasbank

1.4.1.7 Glencoe

"Prev

iew C

opy O

nly"

Page 8: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A division of Transnet Limited Refurbishment of 3kV traction substations

Contract Page 4 of 4 C3.1 Part C3: Scope of Works Description of the Works

1.5 TEMPORARY WORKS

1.5.1 To enhance the operation of the network the substations shall operate as tie-stations as soon as possible. See Part C3 section 5 clauses 5.4.5 and 5.4.6.

END

"Prev

iew C

opy O

nly"

Page 9: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A division of Transnet Limited

Contract Page 1 of 4 C3.2 Part C3:Scope of Works Engineering

Part C3

Section 2

ENGINEERING

CONTENTS Item Description Page

2.1 DESIGN SERVICES AND ACTIVITY MATRIX ....................................................2

2.2 EMPLOYER’S DESIGN.......................................................................................2

2.3 DESIGN BRIEF ...................................................................................................2

2.4 DRAWINGS AND MANUALS..............................................................................2

2.5 DESIGN PROCEDURES .....................................................................................4

"Prev

iew C

opy O

nly"

Page 10: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A division of Transnet Limited

Contract Page 2 of 4 C3.2 Part C3:Scope of Works Engineering

Part C3 Section 2 ENGINEERING

2.1 DESIGN SERVICES AND ACTIVITY MATRIX

Activity Responsibility

Design and draw the layout for entire new installations based on the existing yard and plant layouts provided.

Contractor

Provide side elevation designs, of outdoor yards, for 88kV aerial busbar arrangement to indicate the clearances required.

Contractor

Design and draw the support structures for cable make-offs, AC disconnects, aerial busbars, primary circuit breakers, current transformers and surge arresters as required.

Contractor

Provide designs for concrete foundations for support structures for cable make-off, AC disconnects, aerial busbars, primary circuit breakers, current transformers and surge arresters as required.

Contractor

Design and draw EL&P layouts, cable routes, outdoor earthing and earth mat layouts.

Contractor

Preparation of as-built drawings for concrete foundations, support steel structures, plant layouts as well as wiring diagrams of power circuits, control and protection circuits.

Contractor

Approval of designs. Contractor

Sign-off contractor’s approved detail designs and drawings Employer

2.2 EMPLOYER’S DESIGN

2.2.1 Not applicable

2.3 DESIGN BRIEF

2.3.1 Designs shall be as per requirements specified in Part C3.7 Particular Specification.

2.4 DRAWINGS AND MANUALS

2.4.1 The requirements for drawings to be prepared by the contractor shall be in accordance with the requirements of Transnet Freight Rail’s specifications BBB0041 and CEE0224.

2.4.1.1 The number of complete sets of as built drawings, catalogues, maintenance and instruction manuals shall be 3 per substation. Each set shall include all wiring diagrams and layouts, quality control and quality assurance sheets, results of commissioning tests and measurements.

"Prev

iew C

opy O

nly"

Page 11: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A division of Transnet Limited

Contract Page 3 of 4 C3.2 Part C3:Scope of Works Engineering

2.4.2 DRAWINGS PROVIDED BY THE EMPLOYER

2.4.2.1 The drawings listed below are referred to and will be applicable to this contract. Copies of the drawings are available on the CD issued with this tender.

BBB0906 version 8: Spark gap assembly gas filled arrester.

BBB0938 version 9: Connection of high voltage surge arrester installed on cross arm.

BBB2566 version 2: Schematic diagram: Trip close indication.

BBB2929 version 1: Optic fibre receiver circuit diagram 3kV under voltage relay.

BBB2930 version 4: Optic fibre transmitter circuit diagram 3kV under voltage relay.

BBB2931 version 3: 3kV under voltage relay circuit diagram.

BBB2932 version 1: Voltage divider circuit diagram 3kV under voltage relay.

BBB2934 version 1: 3kV under voltage optic fibre receiver PC board and components layout.

BBB2935 version 2: 3kV under voltage optic fibre transmitter PC board and components layout.

BBB2942 version 2: General arrangement of high-tension divider board.

BBB3483 version 1: Wave filter harmonic coil carrier assembly 3kV DC substations.

BBB3484 version 1: Wave filter harmonic coil 3kV DC substations.

BBB3486 version 1: Inductance coils for resonant circuits 3kV DC substations.

BBB3487 version 1: Harmonic filter coils winding details 3kV DC substations.

BBB3620 version 5: 3kV DC earthing arrangement traction substations.

BBC0665 version 1: South Portal substation – Existing yard layout and equipment arrangement of 3kV DC traction substation for rebuild planning purposes.

BBC0666 version 1: Quail substation – Existing yard layout and equipment arrangement of 3kV DC traction substation for rebuild planning purposes.

BBC0668 version 1: Nottingham Road substation – Existing yard layout and equipment arrangement of 3kV DC traction substation for rebuild planning purposes.

BBB8365 version 1: Danskraal substation – Existing yard layout and equipment arrangement of 3kV DC traction substation for rebuild planning purposes.

BBC0964 version 1: Elandslaagte substation – Existing yard layout and equipment arrangement of 3kV DC traction substation for rebuild planning purposes.

"Prev

iew C

opy O

nly"

Page 12: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A division of Transnet Limited

Contract Page 4 of 4 C3.2 Part C3:Scope of Works Engineering

BBC0968 version 1: Wasbank substation – Existing yard layout and equipment arrangement of 3kV DC traction substation for rebuild planning purposes.

BBC0673 version 1: Glencoe substation – Existing yard layout and equipment arrangement of 3kV DC traction substation for rebuild planning purposes.

BBC5872 version 1: Dirt cover plate, direct tripping device BBT Secheron track breakers.

CEE-PA-19 AMD 26: Symbols for electrical installations.

CEE-PA-42 AMD 9: Symbols for distribution and transmission layouts.

CEE-PK-14 AMD 9: Electrical cable route marker.

CEE-TBD-7 AMD 10: 3kV DC earthing arrangement.

CEE-TBK-27: Control circuit diagram: No-Volt coil protection

CEE-TBP-33 AMD 3: DC Track breakers and track wiring diagram.

CEE-TBP-35 AMD 4: Connection diagram for HSCB & electronic control relay.

CEE-TBP-38 AMD 1: Schematic diagram of 3kV DC busbar under-voltage protection.

CEE-TBP-39 AMD 7: Schematic diagram: electronic closing and auto reclosing relay for 3kV HSCB.

CEE-TCK-1 SHT 1-7: Reactor, 184mH, 0.9mH, 1500A, Assembly

CEE-TDF-15 SHT 1: Sub yard security fence details. & SHT 2 AMD 1

CEE-TDF-16 AMD 2: Pre-stressed concrete palisade fencing, traction substation.

CEE-TU-41: Negative return cable, termination box.

CEE-TWN 32 SHT 2: Warning sign, Exposed live high voltage equipment.

CEE-TWN 36: Composite substation warning notice board.

JEE-TBB-159: Wave filter – 3kV, DC, Traction substation

2.5 DESIGN PROCEDURES

2.5.1 The Contractor shall note that the manufacture of any plant shall not take place prior to the sign off of the design drawings by the Supervisor.

2.5.2 Any drawing returned to the contractor for changes shall be re-submitted to Transnet Freight Rail within 21 days with appropriate changes endorsed.

END

"Prev

iew C

opy O

nly"

Page 13: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A division of Transnet Limited

Contract Page 1 of 2 C3.3 Part C3: Scope of Works Procurement

Part C3

Section 3

PROCUREMENT

CONTENTS Item Description Page

3.1 PREFERENTIAL PROCUREMENT.....................................................................2

3.2 SUBCONTRACTING...........................................................................................2

"Prev

iew C

opy O

nly"

Page 14: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A division of Transnet Limited

Contract Page 2 of 2 C3.3 Part C3: Scope of Works Procurement

Part C3 Section 3 PROCUREMENT

3.1 PREFERENTIAL PROCUREMENT

3.1.1 Transnet fully endorses and supports the Government’s Broad Based Black Economic Empowerment (BBBEE) Programme. We are strongly of the opinion that all South African Business Enterprises have an obligation to redress the imbalances of the past and Transnet will therefore prefer to do business with local business enterprises who share these same values.

3.1.2 To this end, Transnet will seriously reconsider continued business relationships with such enterprises that do not adhere to the principles of BBBEE. Transnet therefore encourages all suppliers to obtain accreditation from one of the reputable Accreditation Agencies. We would prefer our suppliers to have a BBBEE status of at least a level 5 or higher based on the DTI Scorecard. Transnet therefore urges suppliers to have themselves accredited by one of the various Accreditation Agencies available, who do their BBBEE ratings in accordance with the latest Codes Of Good Practice (released on 20 December 2005 and Gazetted on 9 February 2007).

3.2 SUBCONTRACTING

3.2.1 The Contractor will be required to provide a list of work, which they intend carrying out on a subcontracting basis, and work which they intend carrying out with their own permanent employees.

3.2.2 The Contractor will be required to provide a list of subcontractors they intend using to Transnet Freight Rail for approval.

3.2.3 The Contractor will be required to provide the necessary supervision and quality control for the work undertaken by the subcontractors.

3.2.4 The Contractor shall not take advantage of lack of pricing skills of emerging subcontractors, and obvious errors in pricing shall be pointed out and rectified to reflect reasonable prices for the work.

END

"Prev

iew C

opy O

nly"

Page 15: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A division of Transnet Limited

Contract Page 1 of 5 C3.4 Part C3: Scope of Works General Construction Aspects

Part C3

Section 4

GENERAL CONSTRUCTION ASPECTS

CONTENTS Item Description Page

4.1 WORKS SPECIFICATIONS ................................................................................2

4.1.1 STANDARD SPECIFICATIONS ......................................................................................... 2

4.1.2 PARTICULAR / GENERIC SPECIFICATIONS................................................................... 2

4.2 PLANT AND MATERIAL.....................................................................................4

4.3 CONSTRUCTION EQUIPMENT ..........................................................................4

4.4 EXISTING SERVICES .........................................................................................4

4.5 SITE ESTABLISHMENT......................................................................................4

4.5.1 SERVICES AND FACILITIES PROVIDED BY THE EMPLOYER ...................................... 4

4.5.2 FACILITIES PROVIDED BY THE CONTRACTOR............................................................. 4

4.6 SITE USAGE .......................................................................................................5

4.7 PERMITS AND WAYLEAVES.............................................................................5

4.8 ALTERATIONS, ADDITIONS, EXTENSIONS, AND MODIFICATIONS TO EXISTING WORKS..............................................................................................5

4.9 INSPECTIONS OF ADJOINING PROPERTIES ..................................................5

4.10 WATER FOR CONSTRUCTION PURPOSES .....................................................5

4.11 SURVEY CONTROL AND SETTING OUT THE WORKS....................................5

"Prev

iew C

opy O

nly"

Page 16: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A division of Transnet Limited

Contract Page 2 of 5 C3.4 Part C3: Scope of Works General Construction Aspects

Part C3 Section 4 GENERAL CONSTRUCTION ASPECTS

4.1 WORKS SPECIFICATIONS

4.1.1 STANDARD SPECIFICATIONS

4.1.1.1 The following standard specifications (latest version) will be applicable to this contract.

SANS 62271 – 100: High voltage Switchgear and control – gear part 100: High voltage alternating current circuit breakers.

SANS 10142 -1: Wiring code.

SANS 121: Hot dip galvanised coating for fabricated iron or steel articles.

SANS 60044 – 1: Current transformers.

SANS 156: Moulded-case Circuit Breakers.

SANS 780: Distribution Transformers.

SANS 1019: Standard voltages, currents and insulation levels for electricity supply.

SANS 1091: National Colour Standard.

SANS 1222: Enclosures for Electrical Equipment.

SANS 1339: Cross-Linked Polyethylene (XLPE) - Insulated electric cables for rated voltages (3,8/6,6kV to 19/33kV).

SANS 1431: Weldable structural steels.

SANS 1507: Electric cables with extruded solid dielectric insulation for fixed installations. (300/500V to 1900/3,300V) Part 1

4.1.2 PARTICULAR / GENERIC SPECIFICATIONS

4.1.2.1 The particular requirements are specified in the particular specification part C3.7.

4.1.2.2 The generic specifications listed below are referred to and will be applicable to this contract. Copies of the specifications are available on the CD issued with this tender. The specific requirements referred to in these specifications are specified in Part C3.7 Scope of Work.

BBB0041 version 4: Preparation of drawings for Transnet Freight Rail infrastructure.

BBB0496 version 13: 3kV rectifier for traction substations.

BBB0845 version 4: Requirements for metal oxide surge arresters without gaps for AC systems in accordance with gaps for AC systems in accordance with SANS 60099-4.

"Prev

iew C

opy O

nly"

Page 17: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A division of Transnet Limited

Contract Page 3 of 5 C3.4 Part C3: Scope of Works General Construction Aspects

BBB0937 version 4: Requirements for outdoor post type current transformers for traction and distribution substations.

BBB1267 version 10: Requirements for outdoor alternating-current circuit breakers for traction and distribution substations.

BBB1616 version 3: 450 Volt gas arrester sparkgap for traction power supplies.

BBB2007 version 1: Environmental guidelines and specifications for electrical construction work.

BBB2502 version 6: Requirements for battery charger for 3kV DC traction substations.

BBB2721 version 10: AC primary circuit breaker control panel and AC/DC distribution panel for 3kV traction substations.

BBB3005 version 1: 3kV DC under voltage relay manufacturing specification.

BBB3059 version 2: 3kV DC traction substation earthing system for high voltage outdoor yards.

BBB3139 version 1: Wave filter capacitors for 3kV DC substations.

BBB3162 version 1: Wave filter inductors for 3kV DC substations.

BBB3890 version 2: Requirements for a 1.8mHenry DC reactor for 3kV DC traction substations.

BBB4724 version 4: Requirements for positive isolator for 3kV DC traction substations.

BBB5019 version 5: Requirements for traction transformers for 3kV DC traction substations in accordance with BS 171 and IEC 60076-1.

BBB5452 version 5: Spoornet requirements for the installation of electrical equipment for 3kV DC traction substations.

BBB7842 version 1: Outdoor, high voltage, alternating current disconnector combined with earthing switches.

BBB8204 version 2: Medium voltage distribution transformers in accordance with SANS 780.

BBC0198 version 1: Requirements for the supply of cables.

BBC0455 version 1: Eskom phase failure detection circuit.

BBC7616 version 1: Policy and guidelines for management of polychlorinated biphenyls in Transnet Freight Rail.

CEE.0023.90: Specification for installation of cables.

CEE.0045.2002/1: Painting of steel components of electrical equipment.

CEE.0099.2010: Specification for 3kV DC high speed circuit breakers for traction substations.

"Prev

iew C

opy O

nly"

Page 18: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A division of Transnet Limited

Contract Page 4 of 5 C3.4 Part C3: Scope of Works General Construction Aspects

CEE.0177.86: Code of practice, earth systems for electric light and power and traction installations.

CEE.0224.2002: Drawings, catalogues, instruction manuals and spares lists for electrical equipment supplied under contract.

CEE.0227.95: The manufacture of 3kV DC breaker cells and trucks.

CEE.0229.95: Dry-out and regeneration of insulating oil and reclaiming and de-sludging of transformers.

S420 (1999): Specification for concrete work.

E4E Transnet (Aug 2006): Safety arrangement and procedural compliance with the occupational health and safety act (act 85 of 1993) and applicable regulations.

E7/1(July 1998): Specification for works on, over or adjacent to railway lines and near high voltage equipment.

4.2 PLANT AND MATERIAL

4.2.1 The Contractor shall supply all the plant to be built into the works. The Contractor shall provide written certification of compliance with specification of materials supplied by him.

4.3 CONSTRUCTION EQUIPMENT

4.3.1 Requirements for the equipment are covered in part C3.7 “Particular Specification”.

4.3.2 The Contractor shall supply all equipment necessary to perform the work.

4.4 EXISTING SERVICES

4.4.1 Reinstatement of services and structure damaged during construction. Any damage caused by the Contractor to Transnet Freight Rail’s property and services shall be rectified by the Contractor at his own costs and to the full satisfaction of the Supervisor.

4.4.2 The Contractor shall reconnect and test the Telecontrol panel at the substations.

4.4.3 The Contractor shall disconnect the Eskom tails from the Transnet Freight Rail disconnecting switch and reconnect after completion of construction and testing. An Eskom outage must be arranged prior to the work being done.

4.5 SITE ESTABLISHMENT

4.5.1 SERVICES AND FACILITIES PROVIDED BY THE EMPLOYER

4.5.1.1 The Employer will not provide any services or facilities for use by the Contractor.

4.5.2 FACILITIES PROVIDED BY THE CONTRACTOR

4.5.2.1 The Contractor shall be responsible for the site establishment and shall quote for it in the Activity Schedule, part C2.2

"Prev

iew C

opy O

nly"

Page 19: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A division of Transnet Limited

Contract Page 5 of 5 C3.4 Part C3: Scope of Works General Construction Aspects

4.5.2.2 The Contractor shall provide a site office (mobile) where the necessary documentation comprising of design and installation drawings, a copy of the contract, site diary, site instruction book, Risk and Safety file, latest approved programme and all other relevant documents shall be available at all times.

4.5.2.3 The Contractor shall provide the necessary facilities (table and chairs) to conduct site meetings in a suitable meeting environment.

4.5.2.4 No staff accommodation shall be allowed on site. Only a security guard to be provided by the Contractor to safeguard his equipment and plant will be allowed on site overnight. No consumption of alcohol by staff will be allowed on site.

4.5.2.5 The Contractor shall provide toilet facilities for use by his workmen. These toilet facilities shall be maintained in a clean and approved manner at all times during the construction period.

4.5.2.6 Temporary structures such as fencing, carports etc. shall be removed or demolished after completion of the works.

4.5.2.7 The Contractor shall apply for his own telephone, if required.

4.6 SITE USAGE

4.6.1 Not applicable

4.7 PERMITS AND WAYLEAVES

4.7.1 Not applicable

4.8 ALTERATIONS, ADDITIONS, EXTENSIONS, AND MODIFICATIONS TO EXISTING WORKS

4.8.1 Alterations to existing buildings shall be as per Part C3.7.

4.8.2 All existing obsolete foundations shall be demolished to 100mm below the surrounding ground level or removed completely if they obstruct new foundations in the high voltage yard.

4.9 INSPECTIONS OF ADJOINING PROPERTIES

4.9.1 None.

4.10 WATER FOR CONSTRUCTION PURPOSES

4.10.1 Transnet Freight Rail cannot guarantee the supply of water at the substation. In this regard the Contractor shall check during their pre-installation site visit for the availability. The Contractor shall carry all costs involved for such service should it be unavailable.

4.11 SURVEY CONTROL AND SETTING OUT THE WORKS

4.11.1 Not applicable

END

"Prev

iew C

opy O

nly"

Page 20: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A division of Transnet Limited

Contract Page 1 of 9 C3.5 Part C3: Scope of Works Management of the Works

Part C3

Section 5

MANAGEMENT OF THE WORKS

CONTENTS

Item Description Page

5.1 APPLICABLE SANS 1921 STANDARDS ...........................................................2

5.2 ASSOCIATED SANS 1921 SPECIFICATION DATA...........................................2

5.3 PARTICULAR/GENERIC SPECIFICATIONS......................................................4

5.4 PLANNING AND PROGRAMMING.....................................................................4

5.5 SEQUENCE OF THE WORKS ............................................................................4

5.6 SOFTWARE APPLICATION FOR PROGRAMMING ..........................................4

5.7 METHODS AND PROCEDURES ........................................................................4

5.8 QUALITY PLANS AND CONTROL.....................................................................5

5.9 ENVIRONMENT ..................................................................................................6

5.10 ACCOMMODATION OF TRAFFIC ON PUBLIC ROADS OCCUPIED BY THE CONTRACTOR ...................................................................................................6

5.11 OTHER CONTRACTORS ON SITE.....................................................................6

5.12 TESTING, COMPLETION, COMMISSIONING AND CORRECTION OF DEFECTS............................................................................................................7

5.13 RECORDING OF WEATHER ..............................................................................7

5.14 FORMAT OF COMMUNICATION........................................................................7

5.15 KEY PERSONNEL ..............................................................................................8

5.16 MANAGEMENT MEETINGS ...............................................................................8

5.17 FORMS FOR CONTRACT ADMINISTRATION...................................................8

5.18 DAILY RECORDS ...............................................................................................8

5.19 BONDS AND GUARANTEES .............................................................................8

5.20 PAYMENT CERTIFICATE...................................................................................9

5.21 PERMITS.............................................................................................................9

5.22 INSURANCE PROVIDED BY THE EMPLOYER .................................................9

5.23 HEALTH AND SAFETY.......................................................................................9

"Prev

iew C

opy O

nly"

Page 21: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A division of Transnet Limited

Contract Page 2 of 9 C3.5 Part C3: Scope of Works Management of the Works

Part C3 Section 5 MANAGEMENT OF THE WORKS

5.1 APPLICABLE SANS 1921 STANDARDS

5.1.1 The following parts of SANS 1921 and associated specification data is applicable:

5.1.2 SANS 1921-1-2004: Part 1: General Engineering and Construction Works.

5.1.3 SANS 1921-1-2004: Part 3: Structural Steelwork.

5.1.4 SANS 1921-1-2004: Part 6: HIV/AIDS awareness.

5.2 ASSOCIATED SANS 1921 SPECIFICATION DATA

5.2.1 ESSENTIAL DATA

5.2.1.1 The requirements for drawings, information and calculations for which the Contractor is responsible are:

5.2.1.1.1 The requirements for drawings are covered in part C3.2 “Engineering”.

5.2.1.1.2 There are no particular requirements for calculations.

5.2.1.2 The responsibility strategy assigned to the Contractor for the works is C.

5.2.1.3 The structural engineer is to be appointed by the Contractor.

5.2.1.4 Drawings and other information are to be submitted in accordance with the Contractor’s programme.

5.2.1.5 The samples of materials, workmanship and finishes that the Contractor is to provide and deliver to the Employer are as stated in the scope of work.

5.2.1.6 The fabrication drawings that the Contractor is to provide and deliver to the Employer are covered in part C3.2 “Engineering”.

5.2.1.7 The office accommodation, equipment, accommodation for site meetings and other facilities for use by the Employer and his agents are:

5.2.1.7.1 The Employer will not maintain any facilities on site.

5.2.1.7.2 All meetings called by the Employer will be held at one of the Employer owned offices to be announced.

5.2.1.8 The requirements for the provision and erection of sign boards are: None.

5.2.1.9 The requirements for the termination, diversion or maintenance of existing services are:

5.2.1.9.1 If in the execution of his duties, the Contractor finds that the existing services are in his way, he can seek permission from Transnet to divert or temporarily remove the services.

5.2.1.9.2 No Transnet service road shall be closed without the permission of Transnet.

5.2.1.10 Services that are known to exist on site are High and low voltage cables.

"Prev

iew C

opy O

nly"

Page 22: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A division of Transnet Limited

Contract Page 3 of 9 C3.5 Part C3: Scope of Works Management of the Works

5.2.1.11 The requirements for detection apparatus are: Cable locating equipment.

5.2.1.12 The additional health and safety requirements are:

5.2.1.12.1 The attention of the Contractor is drawn to “live” electrical overhead wires or underground cables existing in the area covered by this contract and the danger of coming in contact with such wires or piercing underground electrical cables, during excavations.

5.2.1.12.2 The Contractor shall make all his personnel aware of the danger of “live” electrical wires and cables as well as induced stray voltages from AC electrification into cables and equipment before commencing with the work.

5.2.1.12.3 The Contractor and each member of his personnel who may be required to enter high voltage substations for the purpose of performing work in terms of this contract must:

5.2.1.12.3.1 Observe Transnet Freight Rail’s Electrical Safety Instructions regarding the entry of personnel into all substations, control rooms and equipment sites accommodating equipment on which work must be preformed. Failure to comply with these requirements will render the Contractor liable for direct or indirect costs resulting from such negligence. It will be the Contractor’s responsibility to make sure that his personnel are in possession of these instructions.

5.2.1.12.3.2 Ensure that they are in possession / have completed the proper documents authorising them to enter high voltage substations of Transnet Freight Rail.

5.2.1.12.4 Whenever the Contractor or any member of his personnel enters a high voltage substation yard belonging to Transnet Freight Rail, he must enter his details and the reason for the visit in the substation logbook and sign it. Also see clauses C3.5.7.3 below and C3.5.7.12 below.

5.2.1.12.5 When the Contractor or any member of his personnel is about to leave the substation on completion of his duty he must complete the entry in the substation logbook.

5.2.1.12.6 Special care shall be exercised when welding or flame cutting operations occur and Contractors are required to provide suitable fire fighting equipment at close hand as prescribed by the Occupational Health and Safety Act, Act 85 of 1993.

5.2.1.12.7 The Contractor shall provide the necessary number of suitable first aid outfits, one set in the camp and one set at each working team. He shall maintain these outfits fully equipped at all times.

5.2.1.12.8 The Contractor’s staff shall always wear personal protective clothing when they are on site.

5.2.1.12.9 The Contractor shall report all accidents in writing to the Supervisor. Any accident resulting in the death of or injury to any person on the Works shall be reported within 24 hours of its occurrence, and any other accident shall be reported within 48 hours of its occurrence.

5.2.1.12.10 The works to be undertaken by nominated and selected sub-Contractors comprise: None.

5.2.2 VARIATIONS

5.2.2.1 Replace 4.1.7 with:

"Prev

iew C

opy O

nly"

Page 23: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A division of Transnet Limited

Contract Page 4 of 9 C3.5 Part C3: Scope of Works Management of the Works

The requirements for drawings shall be in accordance with Part C3.2 “Engineering”. Requirements for information and calculations shall be in accordance with the specification data.

5.3 PARTICULAR/GENERIC SPECIFICATIONS

5.3.1 Particular/generic specifications are listed in C3.4.

5.4 PLANNING AND PROGRAMMING

5.4.1 Transnet requires that the works be completed within 21 months from the starting date award of contract which shall include any statutory holidays falling within this period and shall exclude the period from 16 December to 5 January, both days included, if it falls within this period.

5.4.2 Where the whole of the works is awarded to one contractor, he shall employ two teams working simultaneously at two substations. Clauses 5.4.5 and 5.4.6 below will still apply.

5.4.3 The Contractor may offer a shorter completion period in his tender, which offer may be taken into consideration when adjudicating the tenders.

5.4.4 The works shall be completed according to the program of work to be submitted by the Contractor.

5.4.5 The period that the substations are off load shall be kept as short as possible and the Contractor shall concentrate on the installation of indoor equipment first to enable Transnet Freight Rail to operate the substation as a tie-station as soon as possible after the track breakers have been decommissioned. This will assist the network in handling the required load while the rest of the refurbishment is conducted.

5.4.6 No permits on two adjacent substations at any one time will be allowed.

5.4.7 The planning, programme and method statements are to comply with the following:

5.4.7.1 The programme shall show all the individual tasks, the critical path(s) as well as project and monthly milestones.

5.4.7.2 Items in the activity schedule shall be included in the programme.

5.5 SEQUENCE OF THE WORKS

5.5.1 The execution of the works shall be in accordance to the program to be submitted by the Contractor. Transnet Freight Rail shall approve such program.

5.6 SOFTWARE APPLICATION FOR PROGRAMMING

5.6.1 The Contractor to make use of Microsoft Project Software when compiling a program bar chart for installation of the works.

5.7 METHODS AND PROCEDURES

5.7.1 At the completion of the works the Contractor shall clear the site of any left over material to the satisfaction of the Supervisor. The site shall be left in the same or better condition than it was before.

"Prev

iew C

opy O

nly"

Page 24: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A division of Transnet Limited

Contract Page 5 of 9 C3.5 Part C3: Scope of Works Management of the Works

5.7.2 During the clearing of the site, great care shall be exercised by the Contractor when approaching the trees and shrubs at the site.

5.7.3 The Contractor shall comply with the requirements of Transnet specification E7/1 for “works on, over, under or adjacent to railway lines and near high voltage equipment”.

5.7.4 The Employer shall retain title to all material / plant that is being replaced. This material / plant shall be transported by the Contractor to the Ladysmith Maintenance Depot, providing it is not PCB contaminated.

5.7.5 Hours of work will be from 07h00 to 16h00 Mondays to Fridays.

5.7.6 On the Contractor’s request, work may be performed outside these normal working hours if permitted by the Supervisor.

5.7.7 The cost of the Employer’s supervision outside normal working hours, when requested by the Contractor, shall be recovered from the Contractor.

5.7.8 While at the construction site, the movements of the Contractor’s staff shall be restricted within the designated work area to avoid contact with high voltage electrical plant.

5.7.9 The Contractor shall give the Supervisor a notice of 3 working days before covering any excavations (this includes foundation excavations and cable trenches).

5.7.10 If any scaffolding is to be used, the Contractor shall appoint a competent and experienced person to supervise the erection and dismantling of the scaffolding. The appointment shall be made on a form similar to Annexure 3 contained in specification E4E (August 2006).

5.7.11 It shall be the responsibility of the Contractor to take care of the works, plant and material while under construction until takeover by the Employer.

5.7.12 The Contractor’s team supervisors could be requested to attend and pass the Transnet Freight Rail Electrical Safety training course and be authorised to supervise the Contractor’s staff whilst working in the substations on this contract. Transnet Freight Rail will arrange the course and further details will be communicated to the Contractor.

5.8 QUALITY PLANS AND CONTROL

5.8.1 The Contractor shall operate a quality management system.

5.8.2 Tenderers shall submit a detailed statement of their quality system with the tender which shall include the following:

5.8.2.1 Statement of quality management policy and objectives.

5.8.2.2 Statement of the quality control procedures that will apply to purchased materials.

5.8.2.3 Statement of the quality control plan for all components manufactured or supplied so that an inspection is carried out to ascertain conformance to the specification.

5.8.2.4 Statement of the quality control procedure that will apply to the installation on site.

5.8.2.5 The sole responsibility for ensuring that the components supplied conform to the specification shall rest with the Contractor. All major equipment shall be subject to quality control tests and inspections.

"Prev

iew C

opy O

nly"

Page 25: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A division of Transnet Limited

Contract Page 6 of 9 C3.5 Part C3: Scope of Works Management of the Works

5.8.3 The Contractor shall notify the supervisor of all inspections at least 7 working days in advance of such inspections. The Contractor shall have the relevant quality control plans available at inspections and tests.

5.8.4 Transnet Freight Rail reserves the right to inspect the equipment covered by this specification at any stage during manufacture and to be represented at any tests.

5.8.5 Where the contract provides for tests on the premises of the Contractor or of his Sub-Contractor or on site, the Contractor shall provide assistance such as labour, materials, electricity, fuel, stores, apparatus and instruments as may be a requisite and as may be reasonably demanded to carry out such tests efficiently.

5.8.6 As and when the equipment has passed these tests, the Supervisor shall furnish the Contractor with a certificate in writing to this effect.

5.8.7 If as a result of an inspection, examination or test, the Supervisor decides that the equipment is defective or not in accordance with the requirements, he shall notify the Contractor accordingly stating in writing his objections and reasons therefore. The Contractor shall timeously make good the defect to ensure that the equipment complies with the requirements.

5.8.8 Thereafter, if required by the Supervisor, the tests shall be repeated under the same terms and conditions save that all reasonable expenses to which Transnet Freight Rail may be put by the repetition of these tests will be deducted from the contract sum.

5.8.9 Unless the Supervisor otherwise directs, no plant or materials are to be delivered to site until the Supervisor issues an inspection certificate in respect of such plant or material. The Contractor shall be responsible for the reception of all plant and material delivered to site for the purpose of the contract.

5.8.10 Transnet Freight Rail reserves the right to conduct a quality assurance audit on the Contractor's quality control system at regular intervals.

5.8.11 If at any stage during manufacture, repair, installation or commissioning of equipment or material it becomes evident that the requirements of this specification are not being adhered to, Transnet Freight Rail reserves the right to halt such manufacture, repair, installation or commissioning until such time as the Contractor or his Sub-Contractor conforms to the requirements of this specification.

5.8.12 Details of any additional tests or inspections proposed by the Tenderer shall be attached and submitted with his tender.

5.9 ENVIRONMENT

5.9.1 These requirements are covered in Part C3.6 “ Environmental Requirements”

5.10 ACCOMMODATION OF TRAFFIC ON PUBLIC ROADS OCCUPIED BY THE CONTRACTOR

5.10.1 The Contractor shall obey normal traffic rules.

5.11 OTHER CONTRACTORS ON SITE

5.11.1 A Contractor appointed by Eskom may be on site to do refurbishment of the Eskom structures.

"Prev

iew C

opy O

nly"

Page 26: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A division of Transnet Limited

Contract Page 7 of 9 C3.5 Part C3: Scope of Works Management of the Works

5.12 TESTING, COMPLETION, COMMISSIONING AND CORRECTION OF DEFECTS

5.12.1 The Contractor shall perform all pre-commissioning tests, the Employer reserves the right to witness these tests. The Contractor shall supply all test equipment and instruments.

5.12.2 The Employer shall be notified at least 14 days prior to performing these tests.

5.12.3 The Employer will perform calibration and protection settings.

5.12.4 When the WORKS have been completed to the satisfaction of the Supervisor a Certificate of Completion stating the date on which the defects liability and maintenance period will commence, shall be given to the Contractor. Separate certificates of completion shall be given and separate dates of commencement of defects liability and maintenance periods determined for completed portions of the WORKS, in those cases where such portions are taken over by Transnet before completion of the Works as a whole.

5.12.5 The Works will not be acceptable by Transnet as complete until all defects of every kind have been made good to the satisfaction of the Supervisor.

5.12.6 The period of defects liability and maintenance stipulated in the Contract Data is twelve months unless a shorter period is approved by the Project Manager.

5.12.7 The defects liability and maintenance period commences only after the Certificate of Completion has been given to the Contractor. The Contractor is required at his cost, to make good all defects, all defective material and workmanship which may become apparent during the defects liability and maintenance period.

5.12.8 Should the Contractor fail to comply with the above provisions, Transnet may cause the required work to be carried out at the expense of the Contractor and may recover the cost thereof from the Contractor.

5.13 RECORDING OF WEATHER

5.13.1 These requirements are covered in the contract data.

5.14 FORMAT OF COMMUNICATION

5.14.1 The Contractor shall supply and have available on site at all times three A4 size triplicate carbon copy books, with detachable pages.

5.14.1.1 In one book site instructions will be recorded. Only the Project Manager or Supervisor will have the authority to issue site instructions to the Contractor. All instructions recorded shall be signed by the Supervisor and immediately acknowledged by the counter signature of the Contractor or his agent.

5.14.1.2 In the second book site activities will be recorded. Site diaries shall be forwarded to the Supervisor during monthly progress meetings.

5.14.1.3 The third book will be used as the Risk Register.

5.14.1.4 The above three books shall always be kept on site.

5.14.1.5 The original sheet of each set of three pages will be removed from the books and retained by the Project Manager. The Contractor may remove the second sheet but the third sheet shall be retained on site until completion of the works when it shall be handed to the Project Manager.

"Prev

iew C

opy O

nly"

Page 27: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A division of Transnet Limited

Contract Page 8 of 9 C3.5 Part C3: Scope of Works Management of the Works

5.15 KEY PERSONNEL

5.15.1 These requirements are covered in the contract data.

5.16 MANAGEMENT MEETINGS

5.16.1 SITE MEETINGS

5.16.1.1 A program for regular site meetings will be compiled by the Project Manager. At these meetings progress, financial, quality, site safety, site diary, site instructions and technical issues will be discussed.

5.16.2 RISK REDUCTION MEETINGS

5.16.2.1 These meetings can form part of the regular site meetings or be held as separate meetings. At these meetings compensation events, early warnings, contractual claims and the risk register will be discussed.

5.17 FORMS FOR CONTRACT ADMINISTRATION

5.17.1 Not applicable

5.18 DAILY RECORDS

5.18.1 The Contractor shall supply a triplicate carbon copy book to be used as a site diary for recording on a daily basis the date, state of the weather, work done each day, hours worked, number and grade of personnel that worked on site, Equipment on site, plant and material delivered to site and any delays or time lost with reasons.

5.18.2 The site diary shall always be kept in the Contractor’s site office. The original set of each set of three pages will be removed from the book and retained by the Project Manager. The Contractor may remove the second sheet but the third sheet shall be retained in the book on site until completion of the works when it shall be handed to the Project Manager.

5.19 BONDS AND GUARANTEES

5.19.1 Security in the amount equal to ten percent of the contract price, shall be provided by the Contractor for the due and faithful performance by him in terms of the contract. Such security shall be in the form of: -

5.19.1.1 Government or approved Municipal stocks in negotiable form, or

5.19.1.2 A Deed of Suretyship furnished by an approved bank, insurance or guarantee corporation in such form as may be prescribed by Transnet, provided however that the Project Manager may, upon written application by the Contractor, return to the Contractor the whole or part of such security held by Transnet when the retention money has reached an amount, which the Project Manager in his sole discretion considers sufficient for the protection of Transnet. Transnet is entitled to hold all or portion of the security until the completion of the contract and the expiry of the defects liability and maintenance period.

5.19.2 Five percent of the value of the work completed, as reflected by the nett monthly amounts certified for payment, will be retained by Transnet for the due and proper fulfilment of the contract, until such retention money is sufficient, in the opinion of the Project Manager, for the protection of Transnet. Transnet is entitled to hold all or portion of the retention money until the completion of the contract and the expiry of the defects liability and maintenance period.

"Prev

iew C

opy O

nly"

Page 28: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A division of Transnet Limited

Contract Page 9 of 9 C3.5 Part C3: Scope of Works Management of the Works

5.20 PAYMENT CERTIFICATE

5.20.1 On or after the assessment date, the Project Manager and the Contractor will together assess the progress on each item in the Activity Schedule and items shall be listed in quantities.

5.20.2 The Contractor shall then submit a VAT invoice and attach his Progress Certificate for payment by the Employer.

5.21 PERMITS

5.21.1 The Employer will issue the Contractor with a Site Access Certificate for entering the site. Transnet Freight Rail reserves the right to cancel an authorised work permit at any time, even during the period of such occupation or work permit.

5.22 INSURANCE PROVIDED BY THE EMPLOYER

5.22.1 Details of this are covered in the Contract Data.

5.23 HEALTH AND SAFETY

5.23.1 The Contractor shall comply with the requirements of the Transnet Health and Safety specification E4E (August 2006) by compiling a safety plan and completing the applicable Annexures similar to those in the above specification on his company’s letterheads.

5.23.2 The safety plan shall be based on a risk assessment done by a competent person in accordance with Act 85 of 1993.

5.23.3 The safety plan shall also incorporate a fall protection plan in accordance with Act 85 of 1993.

5.23.4 The requirements of specification E7/1 shall apply.

END

"Prev

iew C

opy O

nly"

Page 29: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A division of Transnet Limited

Contract Page 1 of 3 C3.6 Part C3: Scope of Works Environmental Requirements

Part C3

Section 6

ENVIRONMENTAL REQUIREMENTS

CONTENTS Item Description Page

6.1 ENVIRONMENTAL MANAGEMENT ...................................................................2

6.2 DISPOSAL AND TREATMENT OF OIL AND OIL FILLED CIRCUIT BREAKERS.........................................................................................................2

"Prev

iew C

opy O

nly"

Page 30: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A division of Transnet Limited

Contract Page 2 of 3 C3.6 Part C3: Scope of Works Environmental Requirements

Part C3

Section 6

ENVIRONMENTAL REQUIREMENTS

6.1 ENVIRONMENTAL MANAGEMENT

6.1.1 The requirements of specification BBB2007 shall apply.

6.1.2 The Transnet Freight Rail Infrastructure Depot will arrange for an Environmental Specialist to visit all the substations after contract completion and issue a letter stating that the sites are clean and in an environmentally sound condition. This is required by the Rail Safety Regulator.

6.2 DISPOSAL AND TREATMENT OF OIL AND OIL FILLED CIRCUIT BREAKERS

6.2.1 The collection, handling and disposal of oil from the OCBs from the substation shall be done in a safe and environmentally sound manner.

6.2.1.1 Unless any equipment to be replaced containing oil is clearly certified PCB free, the contractor shall test or make arrangements for the testing of the circuit breaker oil for Polychlorinated Biphenyls (PCBs) before replacing the OCBs and submit the results to Transnet Freight Rail.

6.2.1.2 This will be done by first conducting preliminary screening chlorine tests and where the levels of chlorine presence are above 50ppm, further detailed PCB tests and analyses shall be conducted.

6.2.1.3 The units with levels of contamination less than 20ppm Chlorine shall be disposed of following the normal disposal procedure.

6.2.1.4 Any units with residual PCB pollution, or oils contaminated to a level greater than 50ppm shall be treated as PCB items.

6.2.2 Equipment and oil with a PCB content of between 20 and 49 PPM is classified as ‘mildly contaminated’ and shall be properly identified, i.e. marked with yellow stickers, and disposed of as contaminated.

6.2.3 In case of PCB items being identified, handling and disposal of the equipment shall be done in accordance to specification BBC7616.

6.2.4 Approved degreasing agents on concrete surfaces shall be used, if required.

6.2.5 The costs for the screening chlorine test and provisional analyses of oils and soil for PCB’s, the tests and analysis of soil to determine tph levels where spillages has occurred, must be furnished by the tenderers in Part C2.2 “Activity Schedule”.

6.2.5.1 The Tenderer shall provide a provisional method statement and cost for the legal disposal of PCB items, such methodology and costing becoming applicable only in the event of PCB items requiring disposal, as specified, being required.

6.2.6 The old circuit breakers that are not contaminated shall be transported by the contractor to the Transnet Freight Rail Ladysmith Infrastructure depot and scrapped by Transnet Freight Rail following normal procedures. (The depot may keep old OCB parts as spares as deemed necessary).

"Prev

iew C

opy O

nly"

Page 31: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A division of Transnet Limited

Contract Page 3 of 3 C3.6 Part C3: Scope of Works Environmental Requirements

6.2.7 The disposal of any PCB items shall be by thermal destruction method; encapsulation method is not permitted.

END

"Prev

iew C

opy O

nly"

Page 32: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A Division of Transnet Limited

Contract Page 1 of 22 C3.7 Part C3: Scope of Works Particular Specifications

Part C3

Section 7

PARTICULAR SPECIFICATION FOR THE REFURBISHMENT OF SOUTH PORTAL, QUAIL, NOTTINGHAM ROAD, DANSKRAAL, ELANDSLAAGTE, WASBANK AND GLENCOE TRACTION

SUBSTATIONS.

CONTENTS Item Description Page

7.1 88KV AC HIGH VOLTAGE PLANT .....................................................................3

7.1.1 HIGH VOLTAGE METAL OXIDE SURGE ARRESTERS ................................................... 3

7.1.2 HIGH VOLTAGE AC DISCONNECTOR AND EARTHING SWITCH ................................. 3

7.1.3 HIGH VOLTAGE AC PRIMARY CIRCUIT BREAKERS...................................................... 3

7.1.4 MAIN CURRENT TRANSFORMERS.................................................................................. 4

7.1.5 TRACTION TRANSFORMERS........................................................................................... 4

7.2 3KV DC PLANT ...................................................................................................6

7.2.1 OUTDOOR TO INDOOR CONNECTIONS......................................................................... 6

7.2.2 3KV RECTIFIER PLANT ..................................................................................................... 6

7.2.3 DC SMOOTHING/FILTERING PLANT................................................................................ 6

7.2.4 3KV DC POSITIVE ISOLATOR AND EARTHING SWITCH............................................... 7

7.2.5 TRACK FEEDER HIGH SPEED CIRCUIT BREAKERS..................................................... 7

7.2.6 MODULAR TYPE STEEL HOUSED HIGH SPEED CIRCUIT BREAKERS ....................... 8

7.2.7 REGENERATIVE BRAKING PLANT .................................................................................. 8

7.2.8 3KV DC POSITIVE FEEDER CABLES............................................................................... 8

7.2.9 SUBSTATION NEGATIVE RETURN .................................................................................. 9

7.3 AUXILIARY POWER SUPPLIES.........................................................................9

7.3.1 AC AUXILIARY SUPPLY SERVICE CONDITION .............................................................. 9

7.3.2 SUPPLY FROM AUXILIARY TRANSFORMERS ............................................................. 10

7.3.3 AUTOMATIC CHANGE OVER.......................................................................................... 11

7.4 SUBSTATION CONTROL AND LOW VOLTAGE DISTRIBUTION ...................11

7.4.1 SUBSTATION PANELS .................................................................................................... 11

7.4.2 LIGHTING AND POWER POINTS.................................................................................... 11

7.5 BATTERY ..........................................................................................................12

7.6 BATTERY CHARGERS.....................................................................................12

7.7 CABLING, BUSBARS AND WIRING ................................................................12

7.8 SUBSTATION PROTECTION AND EARTHING................................................13

7.8.1 PROTECTION RELAYS.................................................................................................... 13

7.8.2 AC EARTH LEAKAGE CURRENT TRANSFORMERS .................................................... 14

"Prev

iew C

opy O

nly"

Page 33: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A Division of Transnet Limited

Contract Page 2 of 22 C3.7 Part C3: Scope of Works Particular Specifications

7.8.3 INDOOR AND OUTDOOR EARTHING ............................................................................ 15

7.9 CIVIL AND BUILDING WORK...........................................................................15

7.9.1 YARD PREPARATION...................................................................................................... 15

7.9.2 FENCING AND GATES .................................................................................................... 15

7.9.3 FOUNDATIONS ................................................................................................................ 16

7.9.4 STEELWORK.................................................................................................................... 17

7.9.5 SUBSTATION BUILDING ................................................................................................. 17

7.10 DETAILS OF SPECIFIC WORK REQUIRED PER SUBSTATION.....................19

7.10.1 SOUTH PORTAL............................................................................................................... 19

7.10.2 QUAIL................................................................................................................................ 19

7.10.3 NOTTINGHAM ROAD....................................................................................................... 20

7.10.4 DANSKRAAL..................................................................................................................... 20

7.10.5 ELANDSLAAGTE.............................................................................................................. 20

7.10.6 WASBANK......................................................................................................................... 20

7.10.7 GELNCOE......................................................................................................................... 21

7.11 DRAWINGS .......................................................................................................21

7.12 TRAINING..........................................................................................................21

7.13 GENERAL .........................................................................................................21

"Prev

iew C

opy O

nly"

Page 34: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A Division of Transnet Limited

Contract Page 3 of 22 C3.7 Part C3: Scope of Works Particular Specifications

Part C3 Section 7 PARTICULAR SPECIFICATION FOR THE REFURBISHMENT OF SOUTH PORTAL, QUAIL, NOTTINGHAM ROAD, DANSKRAAL, ELANDSLAAGTE, WASBANK AND GLENCOE TRACTION SUBSTATIONS.

7.1 88KV AC HIGH VOLTAGE PLANT

7.1.1 HIGH VOLTAGE METAL OXIDE SURGE ARRESTERS

7.1.1.1 The Contractor shall supply and install surge arresters, as per Transnet Freight Rail's specification BBB 5452 clause 10.0, BBB 0845 and drawing no. BBB 0938, on the incoming side of the AC disconnector and earthing switch and on the primary side of the main traction transformers, at all the substations.

7.1.1.2 Surge arresters shall be connected directly to the aerial feed and not by means of a jumper to the aerial feeder.

7.1.2 HIGH VOLTAGE AC DISCONNECTOR AND EARTHING SWITCH

7.1.2.1 The Contractor shall supply and install new outdoor high voltage AC disconnector switches combined with an earthing switch as per Transnet Freight Rail's specification BBB 5452 clause 11.0 and BBB 7842 at Nottingham Road, Danskraal, Wasbank and Glencoe substations.

7.1.2.2 These AC disconnecting switches shall be installed between the Eskom 88kV aerial busbar and the primary circuit breaker.

7.1.2.3 The disconnecting switches shall have auxiliary contacts for interlocking with the primary circuit breaker as per Transnet Freight Rail’s specification BBB 7842 clauses 7.11.

7.1.3 HIGH VOLTAGE AC PRIMARY CIRCUIT BREAKERS

7.1.3.1 The Contractor shall supply and install new Primary Circuit Breakers (PCB’s) as per Transnet Freight Rail's specification BBB 5452 clause 12.0 and BBB 1267 at Danskraal and Glencoe substations.

7.1.3.2 The Contractor shall be responsible for the removal, safeguarding and reinstallation of the existing high voltage AC primary circuit breakers at Nottingham Road (1) and Wasbank (2).

7.1.3.2.1 The Contractor shall however be responsible for the excavation and casting of new foundations.

7.1.3.3 The circuit breakers shall be installed with the mechanism box of the breaker facing the traction transformer.

7.1.3.4 The Contractor shall cast a 75mm thick concrete slab between the pedestal foundations to provide for a secure standing surface. The top of the slab shall be at the same level as the top of the pedestal foundations.

7.1.3.5 Notwithstanding the clearances quoted in specification BBB 1267 clause 5.0, Transnet Freight Rail requires safe working clearances whereby when in a safe working position and moving to and from it, no person with outstretched arms, or any part of his body or the tools or plant he is handling, comes to within 1,7m from exposed live conductors.

"Prev

iew C

opy O

nly"

Page 35: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A Division of Transnet Limited

Contract Page 4 of 22 C3.7 Part C3: Scope of Works Particular Specifications

7.1.3.5.1 In order to achieve this, a barrier shall be provided and installed into the top of the circuit breaker mechanism box, if necessary.

7.1.4 MAIN CURRENT TRANSFORMERS

7.1.4.1 The Contractor shall supply and install current transformers (CT’s) as per Transnet Freight Rail's specification BBB 5452 clause 13.0 and BBB 0937 as follows:

Substation Name Number of CT’s

South Portal 2

Quail 2

Nottingham Road 4

Danskraal 6

Elandslaagte 2

Wasbank 2

Glencoe 6

7.1.4.2 The Contractor shall be responsible for the removal, safeguarding and reinstallation of the existing main current transformers at Wasbank (4).

7.1.4.2.1 The Contractor shall however be responsible for the excavation and casting of new foundations.

7.1.4.3 The current transformers shall be installed on the traction transformer side of the primary circuit breakers.

7.1.4.4 Each current transformer shall have two identical cores for metering.

7.1.4.5 The current transformers shall each have the following ratings:

7.1.5 TRACTION TRANSFORMERS

7.1.5.1 REFURBISHMENT

7.1.5.1.1 The Contractor shall refurbish the existing traction transformers on site paying special attention to the following items:

1 Re-gasket Primary Bushings & fit new cone rubbers

2 Re-gasket Secondary Bushings & fit new cone rubbers

3 Re-gasket Tertiary bushings

4 Replace gaskets on Tap Switch (Top mounted)

5 Re-gasket inspection covers

6 Repair Buccholz relay gas valve

7 Re-gasket Buccholz relay

8 Replace Breather complete with crystals

9 Repair Leaks on stop cocks

10 Repair Leaks on sampling cock

11 Chemically clean and paint tank

12 Chemically treat polluted ballast.

13 Treat rust

CT Cores (No. of cores) Ratio VA Rating Voltage

Protection (1) 50/5 15 88 kV

Metering (2) 50/1 5 88 kV

"Prev

iew C

opy O

nly"

Page 36: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A Division of Transnet Limited

Contract Page 5 of 22 C3.7 Part C3: Scope of Works Particular Specifications

14

Oil regeneration as per specification CEE.0229:

• Before starting work on the main transformers, oil samples must be taken to do/check, Dissolved Gas Analysis, Karl Fischer- water content, Dielectric strength – kV/mm, Acidity and PCB content.

• The next step would be to drain present oil and thereafter circulate hot oil to rid the unit of Sludge and refill with Re-generated oil (SANS 555 compliant).

• Oil samples must again be taken after the process and be certified.

• All certificates shall be submitted to Transnet Freight Rail.

15 Top up with oil

16 Repair oil temperature probe pocket

17 Repair leaks on radiator fins/valves (LV side)

18 Repair leaks on radiator fins/valves (HV side)

19 Repair Radiator drain plugs

20 Install flexible leads on main busbars (laminated flexibles)

21 Treat plinth for oil pollution.

22 Spray clean and repaint conservator tank. Colour to be white.

23 Clean sight glass on conservator tank.

24 Repair stop cocks

25 Paint busbars designated colours

26 Supply and install new insulation under the transformer.

7.1.5.1.2 Capacitive bushings on the traction transformers at South Portal, Quail, Nottingham Road and Elandslaagte shall be replaced.

7.1.5.1.3 All oil regeneration tests shall be done by an SANAS accredited laboratory.

7.1.5.1.4 The existing transformer plinths shall be properly cleaned and painted white.

7.1.5.1.5 Vector groups, voltages etc. of the existing transformers are listed below. Substation Name

Unit Serial No Make Prim kV

Sec V Vector Group

Tertiary Winding V

A 921300T04.4 OERLIKON 88 2x3x1370 Dyy - SOUTH PORTAL

B 921300T03.4 OERLIKON 88 2x3x1370 Yyy -

A 921300T03.5 OERLIKON 88 2x3x1370 Yyy - QUAIL

B 921300T04.5 OERLIKON 88 2x3x1370 Dyy -

A 921300T04.3 OERLIKON 88 2x3x1370 Dyy - NOTTINGHAM ROAD B 921300T03.3 OERLIKON 88 2x3x1370 Yyy -

A 1712-2 ENGLISH ELECTRIC 88 6x2346 Dzn

- DANSKRAAL

B 1712-1 ENGLISH ELECTRIC 88 6x2346 Yzn

-

A 921300T04.2 OERLIKON 88 2x3x1370 Yyy - ELANDSLAAGTE

B 921300T03.2 OERLIKON 88 2x3x1370 Dyy -

A 81-17040 AEG 88 2x3x1365 Dyy 2360 WASBANK

B 81-17031 AEG 88 2x3x1365 Yyy 2360

A 81-17042 AEG 88 2x3x1365 Dyy 2360 GLENCOE

B 81-17033 AEG 88 2x3x1365 Yyy 2360

"Prev

iew C

opy O

nly"

Page 37: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A Division of Transnet Limited

Contract Page 6 of 22 C3.7 Part C3: Scope of Works Particular Specifications

7.1.5.2 NEW TRACTION TRANSFORMER

7.1.5.2.1 The Contractor shall be responsible for the removal of the existing traction transformers and the supply and installation of new traction transformers as per Transnet Freight Rail's specification BBB 5452 clause 14 and BBB 5019, at Danskraal substation.

7.1.5.2.2 The transformers shall have a 6-phase output configuration for full wave 12 pulse rectification.

7.1.5.2.3 The rating of the new transformer shall be as follows:

Substation Winding Power MW Voltage(kV) Group Tap Changer

High Voltage 4.95 88 ± 2 x 2.5% Y Off load

Low Voltage 2 x 1,975 1,220/1,220 d/y - Danskraal Unit A & B

Tertiary 0,1 2,360 yn -

7.1.5.3 The vector group of the new traction transformer shall be Yd11Yy0Yyn0.

7.1.5.4 The Contractor shall be responsible to transport the existing main traction transformers from Danskraal to the maintenance depot in Ladysmith and the new traction transformers to Danskraal.

7.2 3KV DC PLANT

7.2.1 OUTDOOR TO INDOOR CONNECTIONS

7.2.1.1 The Contractor shall supply and install new anode wall plates and bushings as per Transnet Freight Rail's installation specification BBB 5452 clause 33 at all the substations.

7.2.2 3KV RECTIFIER PLANT

7.2.2.1 The Contractor shall supply and install a 5 MW rectifier per unit, in accordance with specification BBB 5452 clause 18.0 and BBB 0496, in South Portal, Quail, Nottingham Road, Danskraal, Wasbank and Glencoe substations.

7.2.2.2 Rectifiers shall comply with the following:

7.2.2.2.1 Rectifiers offered shall be on Transnet Freight Rail’s approved list of rectifiers.

7.2.2.2.2 All components, especially diodes shall be easy accessible for maintenance and replacement purposes.

7.2.2.2.3 Snubber circuits shall be properly sealed.

7.2.2.2.4 The rectifiers at Elandslaagte shall be retained but upgraded to 5MW and be fitted with fuses to comply with the latest requirements as specified in BBB 0496.

7.2.3 DC SMOOTHING/FILTERING PLANT

7.2.3.1 3KV DC REACTOR

7.2.3.1.1 The existing reactor coils in South Portal, Quail, Nottingham Road, Elandslaagte, Wasbank and Glencoe shall be re-used.

7.2.3.1.2 The coils shall be inspected, cleaned and repainted with a non conductive paint.

7.2.3.1.3 The ratings of the coils are shown in the table below.

"Prev

iew C

opy O

nly"

Page 38: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A Division of Transnet Limited

Contract Page 7 of 22 C3.7 Part C3: Scope of Works Particular Specifications

7.2.3.1.4 The Contractor shall supply and install new reactor coils as per Transnet Freight Rail's specification BBB 5452 clause 19.0 and BBB 3890 at Danskraal substation.

7.2.3.1.5 The rating for the new reactor coils shall be sufficient for a 5MVA substation.

7.2.3.2 WAVE FILTER PLANT

7.2.3.2.1 The Contractor shall supply and install new wave filter plant at all substations, as per Transnet Freight Rail's specification BBB 5452 clause 20.0, BBB 3139 for capacitors and BBB 3162 for inductor coils.

7.2.3.2.2 The existing wave filter rooms shall be used unless the plant could be relocated to improve safety, security or maintenance actions.

7.2.3.2.3 All wall bushings for conductors into the wave filter rooms shall be replaced.

7.2.3.2.4 Each unit shall consist of the following components for filtering 6th harmonic multiples:

COMPONENTS and RATINGS QUANTITY

Capacitors

10 Micro Farad 2

20 Micro Farad 1

50 Micro Farad 3

Inductors

2.814 mH for 6th harmonic 1

1.173 mH for 12th harmonic 1

1,564 mH for 18th harmonic 1

1.759 mH for 24th harmonic 1

7.2.3.2.5 For the connections refer to drawing no. JEE-TBB-159.

7.2.4 3KV DC POSITIVE ISOLATOR AND EARTHING SWITCH

7.2.4.1 The Contractor shall supply and install new positive isolators and earthing switches, as per Transnet Freight Rail's specification BBB 5452 clause 21.0 and BBB 4724, at South Portal, Quail, Nottingham Road, Danskraal, Wasbank and Glencoe substations.

7.2.5 TRACK FEEDER HIGH SPEED CIRCUIT BREAKERS

7.2.5.1 The Contractor shall supply and install new 3kV DC high speed circuit breakers (HSCB) as per Transnet Freight Rail's specifications CEE-0099 and BBB 5452 clause 25.0 and 27.0 as follows:

Substation Name Existing Rating

South Portal 1.80mH/1000A (A unit) 1.76mH/1000A (B unit)

Quail 1.82mH/1000A (for A & B units)

Nottingham Road 1.76mH/1000A (for A & B units)

Danskraal 1.75mH/1000A (A unit) 1.74mH@1000A (B unit)

Elandslaagte 1.82Mh/1000A (for A & B units)

Wasbank 1.75mH/1000A (for A & B units)

Glencoe 1.78mH/1000A (A unit) 1.77mH@1000A(B unit)

"Prev

iew C

opy O

nly"

Page 39: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A Division of Transnet Limited

Contract Page 8 of 22 C3.7 Part C3: Scope of Works Particular Specifications

7.2.5.1.1 This includes the circuit breakers for the regenerative braking plant.

7.2.6 MODULAR TYPE STEEL HOUSED HIGH SPEED CIRCUIT BREAKERS

7.2.6.1 The Contractor shall supply and install new modular type, steel truck and cells as per Transnet Freight Rail's specifications CEE-0227 and BBB 5452 clause 26.0 as follows:

7.2.6.1.1 This includes the truck and cells for the regenerative braking plant.

7.2.6.2 One high speed circuit breaker cell in each substation shall be fitted with a second earthing switch to earth the positive busbar. The earthing contacts shall be visible when applying the earth.

7.2.6.2.1 This earthing switch shall be robust and lockable in both positions (earthed and not earthed) and interlocked with the HSCB and PCB to prevent accidental earthing of the live busbar.

7.2.6.2.2 The shutter gear shall be robust and mechanically locked to prevent it from opening while the truck is withdrawn from the cell.

7.2.7 REGENERATIVE BRAKING PLANT

7.2.7.1 All regenerative braking plant other than the HSCB shall be retained but incorporated in the operation of the substation and included in the schematic wiring diagrams.

7.2.7.2 Indications to and controls from the tele-control plant shall also be incorporated and tested.

7.2.8 3KV DC POSITIVE FEEDER CABLES

7.2.8.1 The Contractor shall supply and install a 3kV DC positive feeding arrangement as per Transnet Freight Rail's installation specification BBB 5452 clause 37.0 at all the substations consisting of the following:

7.2.8.1.1 New feeder cables from positive isolators to HSCBs.

Substation Name Number of HSCB’s Required

South Portal 5

Quail 5

Nottingham Road 5

Danskraal 8

Elandslaagte 4

Wasbank 5

Glencoe 5

Substation Name Number of HSCB Truck & Cells Required

South Portal 5

Quail 5

Nottingham Road 5

Danskraal 8

Elandslaagte 4

Wasbank 5

Glencoe 5

"Prev

iew C

opy O

nly"

Page 40: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A Division of Transnet Limited

Contract Page 9 of 22 C3.7 Part C3: Scope of Works Particular Specifications

7.2.8.1.2 New feeder cables from the HSCBs to the track switches as follows:

7.2.8.1.3 The positive feeder cables between the HSCB and the track switches at Quail, Nottingham Road and Danskraal shall be retained. The position of the new track breakers shall be aligned to ensure that the cable lengths are sufficient.

7.2.8.1.4 The Contractor shall allow for new cable from the regeneration HSCB to the existing regeneration plant depending on the layout of the new plant and the length of the existing cable.

7.2.9 SUBSTATION NEGATIVE RETURN

7.2.9.1 The Contractor shall supply and install new substation negative return system as per Transnet Freight Rail's installation specification BBB 5452 clause 36.0 at all substations consisting of the following:

7.2.9.1.1 Negative return cables/busbars from the traction transformer to the negative busbar.

7.2.9.1.2 Negative return cables from the negative busbar to the negative return manhole as follows:

7.2.9.2 All new terminations and connections.

7.2.9.3 Replace all negative return busbars, steelwork, foundations and insulators.

7.2.9.4 The negative return circuit shall be insulated from general earth to prevent stray negative return currents.

7.3 AUXILIARY POWER SUPPLIES

7.3.1 AC AUXILIARY SUPPLY SERVICE CONDITION

7.3.1.1 The auxiliary supply is derived from an auxiliary step down transformer connected to either a tertiary winding within the traction transformer or from the secondary of the traction transformer.

Substation Name Length of Positive Cable Required (doubled-up)

South Portal 360

Quail Retain existing

Nottingham Road Retain existing

Danskraal Retain existing

Elandslaagte 567

Wasbank 612

Glencoe 444

Substation Name Length of Negative Cable Required (double-up)

South Portal Retain existing

Quail Retain existing

Nottingham Road 100

Danskraal Retain existing

Elandslaagte 100

Wasbank 30

Glencoe 35

"Prev

iew C

opy O

nly"

Page 41: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A Division of Transnet Limited

Contract Page 10 of 22 C3.7 Part C3: Scope of Works Particular Specifications

7.3.1.2 Under traction load, i.e. an electric train drawing power from the substation, the AC waveform is distorted due to harmonics created by the traction rectifier. The Total Harmonic Distortion which can be expected is up to 27 %.

7.3.1.3 A typical voltage waveform, which can be expected, is shown in figure 1 and its corresponding frequency spectrum (FFT) is shown in figure 2.

7.3.1.4 All plant connected to and supplied from the auxiliary supply shall be designed and manufactured to operate under the characteristics of above quality of supply conditions.

7.3.2 SUPPLY FROM AUXILIARY TRANSFORMERS

7.3.2.1 The Contractor shall supply and install new auxiliary transformers as per Transnet Freight Rail's installation specification BBB 5452 clause 15.0 and 16.0 and BBB 8204 at all the substations.

"Prev

iew C

opy O

nly"

Page 42: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A Division of Transnet Limited

Contract Page 11 of 22 C3.7 Part C3: Scope of Works Particular Specifications

7.3.2.2 Where the auxiliary transformer is protected by a barrier, the barrier shall be insulated from earth and connected to the AC earth leakage current transformer.

7.3.3 AUTOMATIC CHANGE OVER

7.3.3.1 The Contractor shall supply and install an automatic change over facility in all substations.

7.3.3.2 The changeover shall automatically disconnect the auxiliary transformer of unit “A” from its load when the AC supply from unit “A” is not available. The control system shall then connect the supply from the auxiliary transformer of unit “B” to the auxiliary loads in the substation.

7.3.3.3 When the supply from the auxiliary transformer of unit “A” is restored and it can supply the load, the change over shall automatically disconnect the supply from the auxiliary transformer of unit “B” and connect the supply from the auxiliary transformer of unit “A” to the load.

7.3.3.3.1 The auxiliary transformer of unit “A” shall therefore supply the load under normal operating conditions and the supply from unit “B” shall be the alternative supply.

7.3.3.4 The design of the changeover system shall be such that back energising of the traction transformer via the auxiliary transformer will not be possible during operation of the change over control panel. Relays and contactors shall be electrically and mechanically interlocked to ensure that the two supplies will not be paralleled at any one time.

7.3.3.5 The change over facility with indication lamps shall be incorporated in the substation AC / DC distribution panel.

7.4 SUBSTATION CONTROL AND LOW VOLTAGE DISTRIBUTION

7.4.1 SUBSTATION PANELS

7.4.1.1 The Contractor shall supply and install new AC primary circuit breaker control panels and AC / DC distribution panels, complete with all protection and control relays, alarms and indications as well as measuring instruments, wiring etc. as per Transnet Freight Rail's installation specifications BBB 5452 clause 22 and BBB 2721, at South Portal, Quail, Nottingham Road, Danskraal, Wasbank and Glencoe substations.

7.4.1.2 Indications for ‘SF6 low gas’ lockout as well as ‘Spring- Charged and Discharged’ shall be provided on the circuit breaker control panels.

7.4.1.3 The Contractor shall incorporate the controls and wiring schematic diagrams of the 88 kV Eskom motor operated disconnects (MOD) in the primary circuit breaker control panels to enable the MODs to be electrically operated from the circuit breaker control panel. The controls and indications shall also be wired to the tele-control panel to enable the MODs to be electrically operated from remote by Transnet Freight Rail Electrical Control.

7.4.1.4 Interlocking with the traction substation primary circuit breakers shall be provided such that the links may not be operated with the primary circuit breaker in the closed position. This interlocking shall also be provided in the control of the primary circuit breakers of the 11 kV substations.

7.4.2 LIGHTING AND POWER POINTS

7.4.2.1 The electrical light & power installation shall be renewed as per Transnet Freight Rail's installation specification BBB 5452 clause 45.0 at all the substations.

"Prev

iew C

opy O

nly"

Page 43: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A Division of Transnet Limited

Contract Page 12 of 22 C3.7 Part C3: Scope of Works Particular Specifications

7.4.2.2 The Contractor shall supply and install outdoor security lights as per Transnet Freight Rail's installation specification BBB 5452 clause 45.8. on each side of the substation building at all substations.

7.4.2.3 The Contractor shall issue a Certificate of Compliance (COC) for each substation and submit a copy thereof to the Supervisor.

7.5 BATTERY

7.5.1 The Contractor shall supply and install new Plantè batteries as per Transnet Freight Rail's specification BBB 5452 clause 23.0 at all the substations.

7.5.2 The battery capacity shall be no less than 100AH. The Contractor shall however ensure that the ampere-hour rating is adequate to cater for requirements in the substation.

7.6 BATTERY CHARGERS

7.6.1 The Contractor shall supply and install new battery chargers as per Transnet Freight Rail's specification BBB 5452 clause 24.0 and BBB 2502, at South Portal, Quail, Nottingham Road, Danskraal, Wasbank and Glencoe substations.

7.6.2 Analogue meters are preferred.

7.7 CABLING, BUSBARS AND WIRING

7.7.1 The Contractor shall remove all existing cables and busbars and supply and install new cables and busbars as per Transnet Freight Rail's installation specification BBB 5452 clause 33.0 and 34.0. at all the substations. This includes the cables between the plant and the tele-control panel.

7.7.2 All HV clamps, cables etc. shall be from a Transnet Freight Rail approved supplier. The Supervisor shall approve these prior to installation.

7.7.3 All dissimilar metal connections (Cu to Al) shall be made using bi-metallic clamps that are specifically designed and manufactured to make these type of connections (ad hoc fabricated clamps are not acceptable)

7.7.4 All copper connections to steel (galvanised) shall be tinned.

7.7.5 The cable routes shall be as indicated on the Contractor’s approved layout design. No deviations will be permitted without approval from the Supervisor.

7.7.6 Existing cable markers may be re-painted and re-used.

7.7.7 The Contractor shall supply and install additional cable markers if necessary in accordance with drawing CEE-PK-14.

7.7.8 Cables inside the substation building shall be laid in the existing concrete cable trenches or as per the approved design.

7.7.8.1 All trenches shall be covered with chequered plates. The Contractor shall modify the existing plates or supply new / additional plates where necessary.

7.7.8.2 The chequered plates shall be at the same level as the rest of the substation floor. The Contractor shall cut all slots for emerging cables. These slots shall be neatly cut and smoothed to avoid damage to cables.

"Prev

iew C

opy O

nly"

Page 44: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A Division of Transnet Limited

Contract Page 13 of 22 C3.7 Part C3: Scope of Works Particular Specifications

7.7.8.3 All un-used trenches shall be filled, compacted and covered with a concrete slab. The finished floor level shall be the same level as the surrounding floor.

7.7.9 Where trenches inside the buildings are not provided or not suitably close to plant, cables shall be routed in new PVC surface mounted channels having removable covers.

7.7.9.1 These channels shall be wall mounted and shall be of sufficient size to easily house the cables.

7.7.9.2 These channels shall not be laid on floors over access ways.

7.7.10 Alternatively, cable trays may be used. Cable trays for indoor installation shall be galvanised type O-line PT38 or similar.

7.7.11 The cables shall be fixed to the cable trays using cable ties.

7.7.12 Cables and/or supports that are attached by adhesives are not acceptable.

7.7.13 All cables and wires shall be provided with identification tags at terminations and shall be marked as reflected on the cable and wiring diagrams.

7.7.14 All cables shall terminate in compression type glands. Cable glands shall be metal construction and shall be installed complete with neoprene shrouds.

7.7.15 The Contractor shall supply and install sleeve pipes where cables enter buildings through walls. Pipes shall be sealed off at both ends after installation to make them vermin proof.

7.7.16 Cable joints will not be permitted. The Contractor shall supply busbars and cables that are long enough for each application.

7.7.17 All cables shall be terminated and connected to a terminal strip inside panels.

7.7.18 All relays, cables, terminal strips, switches, indicating lights, and control push buttons, etc. which are mounted in or on panels, shall be suitably labelled to clearly indicate their function. The labels shall be engraved with white lettering on a black background and permanently fixed with miniature screws or rivets.

7.7.19 All cabling and wiring shall be in accordance with SANS 10142 and CEE.0023.90.

7.7.20 Armouring of cables shall not be used for earthing purposes or any return circuit but shall be bonded to earthed metal by means of a suitable gland. An earth conductor shall be provided in each cable for earthing purposes. Should an earth conductor not be available a separate earth conductor shall be installed to adequately carry the maximum calculated earth fault current.

7.8 SUBSTATION PROTECTION AND EARTHING

7.8.1 PROTECTION RELAYS

7.8.1.1 The Contractor shall supply and install the protection plant in accordance with the relevant specifications supplied. Proper operation of the protection system including the tripping and lockout functions as well as interlocking required shall be ensured.

7.8.1.2 Under Voltage relays shall be installed in all substations as per Transnet Freight Rail's installation specification BBB 5452 clause 28.

7.8.1.3 The Contractor shall supply and install Eskom phase failure detection relays and interlocking at all substations.

"Prev

iew C

opy O

nly"

Page 45: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A Division of Transnet Limited

Contract Page 14 of 22 C3.7 Part C3: Scope of Works Particular Specifications

7.8.1.4 The Contractor shall replace the automatic reclosing feature with a DC Feeder Protection Relay at all the substations.

7.8.1.4.1 The relay is required to operate in conjunction with the 3kV DC High Speed Circuit Breaker.

7.8.1.4.2 The main functions of the relay is to be used as:

7.8.1.4.2.1 Protection of the overhead track equipment.

• Automatic line test function to determine if any fault is on the system and to prevent auto reclosing.

• Over current protection (I2t and di/dt discrimination).

• Under voltage protection.

• Frame fault protection.

• Thermal protection of the Overhead Track.

7.8.1.4.2.2 Control of the breaker.

• Auto re- closure in the event of no fault on the system.

• Auxiliary contacts.

• Serial Communication port (RSR232/RSR485).

7.8.1.4.2.3 As a measurement/condition monitoring device on each track circuit.

• Measure Current (DC)

• Measure Voltage (DC)

• Measure Energy kWh (Export and Import)

• Counting all Energy operations (Condition Monitoring).

7.8.1.4.3 The relay must operate from a 110 Volt DC supply.

7.8.1.4.4 If resistors, potential dividers and current transducers are used the clearance and insulation levels for 3kV DC must be adhered to. It should also be noted due to spacing the size (physical) of the resistor used for testing the line shall be limited to (Length 600 mm x Width 400mm x Height 500 mm).

7.8.1.5 The existing Transnet Freight Rail metering shunt may be re-used.

7.8.2 AC EARTH LEAKAGE CURRENT TRANSFORMERS

7.8.2.1 The Contractor shall supply and install one AC earth leakage CT as per Transnet Freight Rail's installation specification BBB 5452 clause 17.0 for each unit in all the substations.

7.8.2.2 The AC earth leakage CTs shall be installed in the mechanism box or inside a suitable enclosure attached to the support steel structures of the PCBs.

7.8.2.3 The Contractor shall verify that the CT ratios and other ratings are suitably matched for the protection of the substation.

"Prev

iew C

opy O

nly"

Page 46: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A Division of Transnet Limited

Contract Page 15 of 22 C3.7 Part C3: Scope of Works Particular Specifications

7.8.2.4 The AC earth leakage current transformers shall have the following ratings:

7.8.3 INDOOR AND OUTDOOR EARTHING

7.8.3.1 The Contractor shall supply and install indoor and outdoor earthing (including new earth mat) as per Transnet Freight Rail's installation specifications BBB 5452 clauses 29.0 and 30.0, BBB 3059 and drawings BBB 3620 and CEE-TBD-7.

7.8.3.2 The star/neutral point of the auxiliary transformers shall be connected to the DC earth leakage busbar. The tank shall be connected to the 3kV DC negative busbar.

7.8.3.3 All gate switches and spark gaps shall be replaced.

7.9 CIVIL AND BUILDING WORK

7.9.1 YARD PREPARATION

7.9.1.1 Remove all crusher stone. Crusher stone may be spread on the service road to improve access to site.

7.9.1.2 The Contractor shall remove the existing skid rails and foundations (except those suitable for reuse).

7.9.1.3 The Contractor shall level and compact the soil to 98% MOD AASHTO before excavations for cable trenches and foundations commence.

7.9.1.4 The Transnet Freight Rail yard shall be levelled in such a way to prevent standing water.

7.9.1.5 Storm water drains shall be provided where necessary to ensure that water drains away from buildings and the outdoor yard.

7.9.1.6 After the completion of all foundations and earth works the Contractor shall apply weed killer to the entire yard within the substation perimeter fence at all the substations.

7.9.1.6.1 The type of weed killer to be used and the method of application shall comply with the environmental safety standards. Transnet Freight Rail must first approve the weed killer and application method before it is applied.

7.9.1.7 The Contractor shall then lay crusher stone as per Transnet Freight Rail's installation specification BBB 5452 clause 43. Crusher stone shall however cover the entire substation yards.

7.9.2 FENCING AND GATES

7.9.2.1 The Contractor shall supply and install new perimeter fence and gates as per Transnet Freight Rail's installation specification BBB 5452 clauses 41 and 42 at all the substations.

7.9.2.2 The new perimeter fence shall be the hot dipped galvanised steel palisade option.

7.9.2.3 The Contractor shall supply and install a new 1,8m high chain linked (diamond mesh) fence and gate between the Transnet Freight Rail and Eskom yards.

CT Core Ratio VA

Rating Voltage (V)

Accuracy class

Accuracy Limit Factor

Protection (1) 100/5 10 1 000 10P 5

"Prev

iew C

opy O

nly"

Page 47: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A Division of Transnet Limited

Contract Page 16 of 22 C3.7 Part C3: Scope of Works Particular Specifications

7.9.2.4 The Contractor shall replace the existing regenerative plant perimeter fence and gate with a 1,8m high chain linked (diamond mesh) fence at all the substations.

7.9.2.4.1 The fences shall be made vermin proof to prevent small rodents from entering the regenerative braking yard.

7.9.2.5 The Contractor shall replace the existing fence and gate between the building and perimeter fence as per Transnet Freight Rail's installation specification BBB 5452 clause 41 and 42 at all substations.

7.9.2.6 The Contractor shall replace the existing safety barriers in the outdoor yard at Nottingham Road, Elandslaagte, Wasbank and Glencoe substation. The existing gates in the barriers shall be repaired, cleaned, rust treated and painted with undercoat and two final coats.

7.9.2.7 The Contractor shall supply and install safety barriers, including gates, in the outdoor yard at Danskraal.

7.9.2.8 The Contractor shall cast a concrete apron of 150mm x 300mm under the Transnet Freight Rail's perimeter fence and between the building and perimeter fence of all the substations.

7.9.2.9 All metal parts of fences and gates shall be effectively earthed. These parts shall be electrically connected to the earth mat with flexible conductors.

7.9.2.10 Transnet Freight Rail will provide the padlocks for the locking of the gates.

7.9.3 FOUNDATIONS

7.9.3.1 All outdoor traction plant shall be aligned along the same centre lines for each unit.

7.9.3.2 The Contractor shall be responsible for the design, excavations and casting of all foundations for the plant to be installed (including negative return busbar foundations).

7.9.3.3 The foundation and steel structural designs shall be certified by a Professional Engineer or Technologist registered with the Engineering Council of South Africa (ECSA) in the relevant disciplines. These designs shall be submitted for sign off before this portion of civil work is commenced.

7.9.3.4 New foundations, where required, shall be installed as per Transnet Freight Rail's installation specification BBB 5452 clause 39.0.

7.9.3.5 The Contractor shall supply and install sleeve pipes in the new foundations to prevent cables to be laid on the foundation over access ways.

7.9.3.6 Foundations not suitable for reuse shall be demolished to 100mm below surrounding ground level.

7.9.3.7 All concrete work shall be in compliance with specification S420 (1999).

7.9.3.8 The Contractor shall determine the exact foundation and steelwork requirements. The Contractor shall also carry out his own survey in regard to soil types and their load bearing capacity.

7.9.3.9 Tenderers must ensure that adequate provision (financial as well as time) has been made for excavations in a range of soil types.

"Prev

iew C

opy O

nly"

Page 48: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A Division of Transnet Limited

Contract Page 17 of 22 C3.7 Part C3: Scope of Works Particular Specifications

7.9.3.10 The Contractor shall be responsible for all concrete cast. He shall arrange for taking concrete test cubes and testing thereof by an accredited test laboratory.

7.9.3.10.1 Full records of test results shall be submitted to the Supervisor.

7.9.3.10.2 If ready-mix concrete is used, the Contractor shall submit certificates confirming the strength of concrete to the Supervisor.

7.9.3.10.3 On no account shall water be added to a concrete mix after test cubes have been taken as the addition of water to a concrete mix reduces the strength significantly.

7.9.4 STEELWORK

7.9.4.1 The Contractor shall be responsible for all the steel support structures required for the new plant as per Transnet Freight Rail's specification BBB 5452 clause 40.0.

7.9.4.2 The number of steel support structures required for Current Transformers (CT’s) and Primary Circuit Breakers (PCB’s) are as follows.

Substation Name Steel supports structures

required for CT’s Steel supports structures

required for PCB’s.

South Portal 2 0

Quail 2 0

Nottingham Road 4 0

Danskraal 6 2

Elandslaagte 2 0

Wasbank 6 2

Glencoe 6 2

7.9.4.3 The Contractor shall paint all painted steel structures as per Transnet Freight Rail's specification BBB 5452 clause 44.0.

7.9.4.4 The Contractor shall dismantle and remove all existing steel support structures not to be reused.

7.9.4.5 The manufacture of any steelwork shall not take place prior to the signing off of the drawings by the Supervisor.

7.9.4.6 Transnet Freight Rail shall inspect all steelwork at the manufacturer’s works prior to dispatch.

7.9.4.7 All fasteners (nuts & bolts) shall be secured using flat or bevelled washers, as necessary, as well as lock washers.

7.9.5 SUBSTATION BUILDING

7.9.5.1 The Contractor shall dismantle and remove all existing plant in the building.

7.9.5.2 The Contractor shall refurbish the entire substation building at all the substations.

7.9.5.3 The Contractor shall install all new plant that is replacing the plant that is currently accommodated in the breaker house at Glencoe substation in the main/rectifier building.

7.9.5.4 The breaker house at Glencoe substation shall be demolished to 100mm below ground level and the rubble removed from site.

"Prev

iew C

opy O

nly"

Page 49: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A Division of Transnet Limited

Contract Page 18 of 22 C3.7 Part C3: Scope of Works Particular Specifications

7.9.5.5 The roofs, down pipes and gutters shall be replaced with chromadeck roofs, down pipes and gutters at South Portal, Danskraal, Wasbank and Glencoe. Whirly bird type ventilation fans (two per unit) shall be installed in the new roofs to improve ventilation.

7.9.5.5.1 At Nottingham Road the roof shall be retained but whirly bird type ventilation fans (two per unit) shall be installed to improve ventilation.

7.9.5.6 The Contractor shall supply and install at least 1 supply air ventilation fan and filter unit per substation unit to maintain a positive pressure in the substation building. These shall be installed at all the substations.

7.9.5.6.1 Large ventilation openings shall be bricked up and converted to suit the new ventilation system.

7.9.5.6.2 The existing wooden doors/vents on the outside of the ventilation chambers shall be replaced with security barriers.

7.9.5.7 The large double entrance door and all the external doors to the substation shall be replaced with roll-up doors.

7.9.5.7.1 The large roll-up doors shall be fitted with a pedestrian insert.

7.9.5.8 Transnet Freight Rail shall approve the type of roll-up doors offered by the Contractor prior to purchasing.

7.9.5.9 The third entrances to the substation buildings as well as all existing vents shall be bricked-up.

7.9.5.10 All interior doors shall be fully operational and fitted with new locks.

7.9.5.11 The substation floors shall be chopped up and a new 75mm thick substation floor shall be laid at South Portal, Quail, Nottingham Road, Danskraal, Wasbank and Glencoe substations.

7.9.5.12 The substation floors shall be painted with epoxy non-slip paint.

7.9.5.13 The Contractor shall refurbish the wave filter room doors at South Portal, Quail and Nottingham Road substations (repair, clean, paint with an under coat and two coats of paint).

7.9.5.14 The Contractor shall replace the wave filter room doors at Danskraal, Elandslaagte, Wasbank and Glencoe substations.

7.9.5.15 Refurbish mechanical/electrical interlocking on the wave filter room door at all the substations.

7.9.5.16 Clean existing and install new water drains and gutters as required to ensure that rain water runs away from the building and substation yard at all the substations.

7.9.5.17 The Contractor shall supply and install a new 1 000 litre rain water tank feeding from the gutters at all the substations. Tanks shall be installed on a concrete foundation.

7.9.5.18 All damaged window panes shall be replaced. All window frames shall be repaired, surfaces prepared, cleaned and painted.

"Prev

iew C

opy O

nly"

Page 50: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A Division of Transnet Limited

Contract Page 19 of 22 C3.7 Part C3: Scope of Works Particular Specifications

7.9.5.19 The Contractor shall repair all cracks and holes in walls. Plastered surfaces shall then be scraped and cleaned before at least one coat of primer/under coat and 2 final coats of paint is applied. These also apply to external plastered plinths, window surrounds, lintels etc.

7.9.5.20 The Contractor shall supply and install a new extractor fan and filter system in the battery room. The fan shall provide adequate airflow to prevent the build-up of gasses from the batteries.

7.9.5.21 The Contractor shall supply and install a new water basin in the battery room.

7.9.5.22 The Contractor shall ensure that the building is vermin proof.

7.9.5.23 The Contractor shall ensure that the aesthetic appearance of the substations are restored giving special attention to the following:

7.9.5.23.1 Cleaning old paint from the face brick walls.

7.9.5.23.2 Levelling of uneven surfaces (building floors, surrounding ground etc).

7.9.5.23.3 Removing traces of all previously demolished plant, fences and gates (brackets, bolts, light fittings, conduit pipes, cables etc.).

7.9.5.23.4 Incidental repairs to fences and gates.

7.9.5.24 The Contractor shall install warning signs (No WW 23), supplied by Transnet Freight Rail, in accordance with Transnet Freight Rail’s drawing CEE-TWN-32 sht 2 of 9 for exposed live high voltage plant on the perimeter fence of the substations.

7.9.5.25 “Composite substation warning notice boards” in accordance with Transnet Freight Rail’s drawing CEE-TWN-36 shall be supplied by Transnet Freight Rail and fitted by the Contractor on each half of the substations’ gates as well as access doors of the substations’ control buildings.

7.10 DETAILS OF SPECIFIC WORK REQUIRED PER SUBSTATION

The detail specified below will be required at each substation as listed.

7.10.1 SOUTH PORTAL

7.10.1.1 Apart from the foundations of existing plant to be removed the following old foundations and brick works shall also be removed:

7.10.1.1.1 1 x 3.5m x 3.5m

7.10.1.1.2 1 x 0.9m x 0.5m

7.10.1.1.3 3m x 2m (small building)

7.10.1.2 A length of 12m of old skid rail shall be removed.

7.10.1.3 The support posts and gates of the safety barriers in outdoor yard shall be cleaned and rust treated and painted with undercoat and two final coats.

7.10.2 QUAIL

7.10.2.1 Apart from the foundations of existing plant to be removed the following old foundations shall also be removed:

"Prev

iew C

opy O

nly"

Page 51: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A Division of Transnet Limited

Contract Page 20 of 22 C3.7 Part C3: Scope of Works Particular Specifications

7.10.2.1.1 3 x 0.75m x 0.9m

7.10.2.2 Tele-control plant to be relocated to new position.

7.10.2.3 A length of 11m of old skid rail shall be removed.

7.10.2.4 The support posts and gates of the safety barriers in outdoor yard shall be cleaned and rust treated and painted with undercoat and two final coats.

7.10.3 NOTTINGHAM ROAD

7.10.3.1 Apart from the foundations of existing plant to be removed the following shall also be removed:

7.10.3.1.1 2 x 0.5m x 0.5m

7.10.3.1.2 1 x 0.8m x 0.8m

7.10.3.1.3 2 x 0.9m x 0.5m (old gantry foundations)

7.10.3.2 Remove old gantry steelwork.

7.10.3.3 Resurface the concrete ramp in front of the main entrance.

7.10.3.4 Install “unit B” earth leakage in a suitable enclosure.

7.10.3.5 Existing roll-up door to be refurbished and seal installed to prevent dust entering underneath.

7.10.3.6 Replace the barge boards.

7.10.4 DANSKRAAL

7.10.4.1 Apart from the foundations of existing plant to be removed the following shall also be removed:

7.10.4.1.1 2 x 0.9m x 0.5m (old gantry foundations)

7.10.4.1.2 2 x 2.5m x 5.0m (old transformer plinths)

7.10.4.1.3 2.0m x 2.0m (small room on main road side of building)

7.10.4.1.4 2.0m x 6.0m (old slab)

7.10.4.2 Remove old gantry steelwork.

7.10.4.3 The Contractor shall be responsible for the removal of all steel structures and foundations of the current 88kV feeding arrangement.

7.10.5 ELANDSLAAGTE

7.10.5.1 A length of 42m of old skid rail shall be removed.

7.10.6 WASBANK

7.10.6.1 Apart from the foundations of existing plant to be removed the following shall also be removed:

7.10.6.1.1 2 x 0.6m x 0.8m

"Prev

iew C

opy O

nly"

Page 52: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A Division of Transnet Limited

Contract Page 21 of 22 C3.7 Part C3: Scope of Works Particular Specifications

7.10.6.1.2 2 x 1.2m x 1.2m

7.10.6.2 The Contractor shall supply and install new double gates between the substation building and perimeter fence to improve the access to the yard.

7.10.7 GELNCOE

7.10.7.1 Apart from the foundations of existing plant to be removed the following shall also be removed:

7.10.7.1.1 2 x 0.6m x 0.9m

7.10.7.2 A length of 39m of old skid rail shall be removed.

7.10.7.3 The Contractor shall supply and install a new ladder to the wave filter room.

7.10.7.4 The Contractor shall supply and install new concrete slabs to cover the water trench at the office entrance.

7.11 DRAWINGS

7.11.1 The Contractor shall prepare and supply, within 21 working days after completion of a substation, a full set of as-built drawings to the Supervisor for sign-off.

7.11.2 The following drawings are required for each substation:

7.11.2.1 Schematic diagrams of the entire substation wiring.

7.11.2.2 Drawings for all plant, their support structures and foundations.

7.11.2.3 Indoor - EL&P layout.

7.11.2.4 Indoor – Plant layout.

7.11.2.5 Outdoor – Plant layout.

7.11.2.6 Outdoor – Cable layout in yard.

7.11.2.7 Outdoor – Earthing layout in yard.

7.11.2.8 Outdoor – Side view for clearances between plant.

7.12 TRAINING

7.12.1 The Contractor shall provide training to technicians in all aspects of maintenance, fault finding and operation of plant supplied and installed.

7.12.2 Training shall be sufficient to enable the technicians to do fault finding to component level.

7.12.3 The training course shall include a theoretical as well as a practical component.

7.12.4 Details of training content and period shall be submitted with tenders. One training session shall be offered before commissioning. The session to accommodate up to five (5) people.

7.13 GENERAL

7.13.1 All old/removed/obsolete plant will remain the property of Transnet Freight Rail.

"Prev

iew C

opy O

nly"

Page 53: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A Division of Transnet Limited

Contract Page 22 of 22 C3.7 Part C3: Scope of Works Particular Specifications

7.13.2 The Contractor shall not demolish the old plant but shall dismantle it and transport it to the maintenance Depot.

7.13.3 Care shall be taken not to damage old plant when dismantled such that it can be reassembled if required.

7.13.3.1 Tenderers shall include the transport costs in their tenders.

END

"Prev

iew C

opy O

nly"

Page 54: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail 1

A Division of Transnet Ltd SPECIFICATION E4.B

(November 1996)

(REGISTRATION NO.1990/000900/06)

TRADING AS TRANSNET FREIGHT RAIL

MINIMUM COMMUNAL HEALTH REQUIREMENTS IN AREAS OUTSIDE THE JURISDICTION OF A

LOCAL AUTHORITY: TEMPORARY FACILITIES FOR CONTRACTOR'S PERSONNEL

1. CAMPS

1.1 Prior to the erection of any camp, the Contractor shall submit to the Technical Officer, for

his approval, details of his proposals as to the site, water supply, sanitation, and size and

type of buildings. Where the site is on private land, the Contractor shall submit the written

approval for the use of the site of the relevant statutory authority and of the owner and

occupier of the land (as applicable).

1.2 Camps must not be erected on land infested with field rodents.

1.3 Adequate drainage shall be provided to carry off storm and waste water.

1.4 Buildings shall be built to a neat and orderly pattern.

1.5 All buildings shall have smooth, hard, impervious floors, graded to provide effective

drainage and to permit washing.

1.6 Camps shall be maintained by the Contractor at his own expense in a clean and tidy

condition. The Contractor shall take such steps as the Technical Officer and

landowner/occupier may demand to prevent the creation of a nuisance.

1.7 When so instructed by the Technical Officer, the Contractor shall, at his own expense,

erect suitable screens between the camp and any public road, thoroughfare or railway line.

1.8 After removal of a camp, the Contractor shall, at his own expense, restore the site to its

original condition to the satisfaction of the Technical Officer and of the landowner and

occupier where the site is on private land.

"Prev

iew C

opy O

nly"

Page 55: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail 2

A Division of Transnet Ltd SPECIFICATION E4.B

(November 1996)

2. HOUSING

2.1 Every living room shall have cross ventilation, both constant and occasional. Where only

one window is provided, it shall not be in the same wall as the door.

2.2 Dimensions of living rooms shall be sufficient to allow 3.5 square metres of floor area and

11 cubic metres of air space for each person over the age of 10 years. The floor area of

any living room shall not be less than 7,8 square metres.

2.3 Flat-roofed quarters shall have a minimum roof height of 3 metres above floor level. For

quarters with pitched roofs, the wall height shall be not less than 2,6 metres above the

floor with a minimum height above floor of 3 metres at the top of the pitch.

2.4 Doors shall not be less than 2m x 0,75m and must be halved.

2.5 Windows of each living room shall have an area not less than one twelfth of the floor area

and shall be capable of opening to at least half their full area.

2.6 In areas where malaria is prevalent, doors and windows must be fitted with gauze screens.

2.7 Cooking shelters shall comprise roofed structures, three sides of which shall be enclosed

by a weatherproof material, approved by the Technical Officer to a height of at least 1m

above ground level.

2.7.1 Sleeping quarters shall not accommodate more than 8 persons per room.

2.7.2 Pegboards shall be carried on metal or concrete supports and shall be separated

by partitions not less than 0,4 metres high extending to within 150mm of the end

of the bunk. Pegboards shall be removable for cleaning.

3. WATER SUPPLY AND ABLUTION FACILITIES

3.1 The Contractor shall ensure that an adequate and conveniently situated supply of potable

water is provided.

3.2 Separate buildings for ablution facilities shall be provided. Where approval has been

obtained for the housing of both males and females, separate facilities for each sex shall

be provided. The proportion shall be 1 cubicle for 20 persons.

3.3 Waste water shall be hygienically disposed of.

4. SANITATION

4.1 Separate buildings for latrine facilities shall be provided. Where housing are provided for

both males and females, separate facilities for each sex shall be provided. The

proportions shall be at least one squatting seat for every 15 persons or less in the case of

pit latrines, or one for every 10 persons or less in case of pail latrines.

"Prev

iew C

opy O

nly"

Page 56: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail 3

A Division of Transnet Ltd SPECIFICATION E4.B

(November 1996)

Latrines shall be fly proof and sited at least 10 metres from any other building, and shall

not face on any public road, thoroughfare, railway line or residential property. Pits shall not

be less than 2,5 metres deep and sited not less than 120 metres from nearest

underground water source.

4.2 Latrines shall be so constructed, situated and maintained, and night soil so disposed of as

to prevent access by animals, breeding of flies, pollution of streams and domestic water

supplies, and other nuisances. Where a night soil removal service is operated by a

competent authority, use of such service shall be obligatory, and the use of pit latrines and

atria pits will not be permitted.

4.3 At least one refuge bin of adequate size with close fitting lid shall be provided for each

building. Refuse bins shall be emptied and cleaned out daily.

4.4 Labour shall be employed on camp sanitation duties on the following basis:-

4.4.1 Where the number of persons living at the camp is 20 or less - one unit.

4.4.2 For additional numbers over 20 living at the camp - one unit per 100 or part

thereof.

4.5 Unless refuse is removed by a competent authority, it shall be disposed of in pits and

covered over daily with a layer of earth or ash of sufficient thickness to prevent

depredations by rodents and the breeding of flies.

4.6 Adequate measures shall be taken against all vermin and insects responsible for the

spread of disease. Any instructions of a competent health authority shall be carried out

promptly and implicitly.

4.7 Buildings and bed boards shall be treated whenever necessary with an approved

insecticide.

4.8 The Contractor shall permit and facilitate inspection of the camp and structures on the site

by the staff of Transnet or any other competent authority, and shall comply with any

reasonable request by such staff or any other competent authority to eliminate any

unsanitary condition.

4.9 Any outbreak of infectious disease shall immediately be reported telephonically and

confirmed in writing to the Technical Officer.

4.10 The keeping of animals of any sort is not permitted.

4.11 The Contractor shall have on hand at the camp the necessary tools, disinfectants and

cleaning materials to maintain and clean the sanitary facilities.

"Prev

iew C

opy O

nly"

Page 57: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail 4

A Division of Transnet Ltd SPECIFICATION E4.B

(November 1996)

5. RATIONS

Rations, where supplied by the Contractor, shall be stored in a suitable and rodent proof building

with sufficient shelving.

ooOoo

"Prev

iew C

opy O

nly"

Page 58: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail E.4E Transnet (August 2006) A Division of Transnet Ltd

Page 1 of 11

TRANSNET LIMITED

(Registration no. 1990/000900//06)

SAFETY ARRANGEMENTS AND PROCEDURAL COMPLIANCE

WITH THE OCCUPATIONAL HEALTH AND SAFETY ACT

(ACT 85 OF 1993) AND APPLICABLE REGULATIONS

1. General 1.1 The Contractor and Transnet Limited (hereinafter referred to as “Transnet”) are

individual employers, each in its own right, with their respective duties and obligations set out in the Occupational Health and Safety Act, Act 85 of 1993 (the Act) and applicable Regulations.

1.2 The Contractor accepts, in terms of the General Conditions of Contract and in terms

of the Act, his obligations as an employer in respect of all persons in his employ, other persons on the premises or the Site or place of work or on the work to be executed by him, and under his control. He shall, before commencement with the execution of the contract work, comply with the provisions set out in the Act, and shall implement and maintain a Health and Safety Plan as described in the Construction Regulations, 2003 and as approved by Transnet, on the Site and place of work for the duration of the Contract.

1.3 The Contractor accepts his obligation to complying fully with the Act and applicable

Regulations notwithstanding the omission of some of the provisions of the Act and the Regulations from this document.

1.4 Transnet accepts, in terms of the Act, its obligations as an employer of its own

employees working on or associated with the site or place of work, and the Contractor and Project Manager or his deputy shall at all times, co-operate in respect of the health and safety management of the site, and shall agree on the practical arrangements and procedures to be implemented and maintained during execution of the Works.

1.5 In the event of any discrepancies between any legislation and this specification, the

applicable legislation will take precedence.

2. Definitions 2.1 In this Specification any word or expression to which a meaning has been assigned in

the Construction Regulations, shall have the meaning so assigned to it, unless the context otherwise indicates: -

2.2 The work included in this Contract shall for the purposes of compliance with the Act

be deemed to be "Construction Work", which, in terms of the Construction Regulations, 2003 means any work in connection with: - (a) the erection, maintenance, alteration, renovation, repair, demolition or

dismantling of or addition to a building or any similar structure;

"Prev

iew C

opy O

nly"

Page 59: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail E.4E Transnet (August 2006) A Division of Transnet Ltd

Page 2 of 11

(b) the installation, erection, dismantling or maintenance of fixed plant where such

work includes the risk of a person falling; (c) the construction, maintenance, demolition or dismantling of any bridge, dam,

canal, road, railway, runway, sewer or water reticulation system or any similar civil engineering structure; or

(d) the moving of earth, clearing of land, the making of an excavation, piling, or

any similar type of work;

2.3 “competent person” in relation to construction work, means any person having the knowledge, training and experience specific to the work or task being performed: Provided that where appropriate qualifications and training are registered as per the South African Qualifications Authority Act, 1995 these qualifications and training shall be deemed to be the required qualifications and training;

2.4 “contractor” means principal contractor and “subcontractor” means contractor as defined by the Construction Regulations, 2003.

2.5 “fall protection plan” means a documented plan, of all risks relating to working from an elevated position, considering the nature of work undertaken, and setting out the procedures and methods applied to eliminate the risk;

2.6 “health and safety file” means a file, or other record in permanent form, containing the information required to be kept on site in accordance with the Act and applicable Regulations;

2.7 “Health and Safety Plan ” means a documented plan which addresses the hazards identified and include safe work procedures to mitigate, reduce or control the hazards identified;

2.8 “Risk Assessment” means a programme to determine any risk associated with any hazard at a construction site, in order to identify the steps needed to be taken to remove, reduce or control such hazard;

2.9 “the Act” means the Occupational Health and Safety Act No. 85 of 1993.

3. Procedural Compliance 3.1 The Contractor who intends to carry out any construction work shall, before carrying

out such work, notify the Provincial Director in writing if the construction work:-

(a) includes the demolition of a structure exceeding a height of 3 metres; or (b) includes the use of explosives to perform construction work; or

(c) includes the dismantling of fixed plant at a height greater than 3m,

and shall also notify the Provincial Director in writing when the construction work exceeds 30 days or will involve more than 300 person days of construction work and if the construction work:- (a) includes excavation work deeper than 1m; or

"Prev

iew C

opy O

nly"

Page 60: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail E.4E Transnet (August 2006) A Division of Transnet Ltd

Page 3 of 11

(b) includes working at a height greater than 3 metres above ground or a landing.

3.2 The notification to the Provincial Director shall be on a form similar to Annexure A of the Construction Regulations, 2003, also shown in Annexure 1 of this Specification. The Contractor shall ensure that a copy of the completed notification form is kept on site for inspection by an inspector, Project Manager or employee.

3.3 The Contractor shall, in accordance with the Act and applicable Regulations, make all

the necessary appointments of competent persons in writing on a form similar to Annexure 2 of this Specification and deliver copies thereof to the Project Manager. Copies should also be retained on the health and safety file.

3.4 Subcontractors shall also make the above written appointments and the Contractor

shall deliver copies thereof to the Project Manager. 3.5 In the case of a self-employed Contractor or any subcontractor who has the

appropriate competencies and supervises the work himself, the appointment of a construction supervisor in terms of regulation 6.1 of the Construction Regulations, 2003 will not be necessary. The Contractor shall in such a case execute and sign a declaration, as in Annexure 3, by which he personally undertakes the duties and obligations of the "Chief Executive Officer" in terms of section 16(1) of the Act.

3.6 The Contractor shall, before commencing any work, obtain from the Project Manager

an access certificate as in Annexure 4 executed and signed by him, permitting and limiting access to the designated site or place of work by the Contractor and any subcontractors under his control.

3.7 Procedural compliance with Act and Regulations, as above, shall also apply to any

subcontractors as employers in their own right. The Contractor shall furnish the Project Manager with full particulars of such subcontractors and shall ensure that they comply with the Act and Regulations and Transnet's safety requirements and procedures.

4. Special Permits

Where special permits are required before work may be carried out such as for hotwork, isolation permits, work permits and occupations, the Contractor shall apply to the Project Manager or the relevant authority for such permits to be issued. The Contractor shall strictly comply with the conditions and requirements pertaining to the issue of such permits.

5. Health and Safety Programme 5.1 The Tenderer shall, with his tender, submit a Health and Safety Programme setting

out the practical arrangements and procedures to be implemented by him to ensure compliance by him with the Act and Regulations and particularly in respect of: -

(i) The provision, as far as is reasonably practical, of a working environment that is

safe and without risk to the health of his employees and subcontractors in terms of section 8 of the Act;

"Prev

iew C

opy O

nly"

Page 61: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail E.4E Transnet (August 2006) A Division of Transnet Ltd

Page 4 of 11

(ii) the execution of the contract work in such a manner as to ensure in terms of

section 9 of the Act that persons other than those in the Contractor's employment, who may be directly affected by the contract work are not thereby exposed to hazards to their health and safety;

(iii) ensuring, as far as is reasonably practical, in terms of section 37 of the Act that

no employee or subcontractor of the Contractor does or omits to do any act which would be an offence for the Contractor to do or omit to do.

5.2 The Contractor's Health and Safety Programme shall be based on a risk assessment

in respect of the hazards to health and safety of his employees and other persons under his control that are associated with or directly affected by the Contractor's activities in performing the contract work and shall establish precautionary measures as are reasonable and practical in protecting the safety and health of such employees and persons.

5.3 The Contractor shall cause a risk assessment contemplated in clause 5.2 above to be

performed by a competent person, appointed in writing, before commencement of any Construction Work and reviewed during construction. The Risk Assessments shall form part of the Health and Safety programme to be applied on the site and shall include at least the following: (a) The identification of the risks and hazards that persons may be exposed to;

(b) the analysis and evaluation of the hazards identified; (c) a documented Health and Safety Plan, including safe work procedures to

mitigate, reduce or control the risks identified; (d) a monitoring and review plan.

5.4 The Health and Safety Plan shall include full particulars in respect of: -

(a) The safety management structure to be instituted on site or place of work and the names of the Contractor's health and safety representatives and members of safety committees where applicable;

(b) the safe working methods and procedures to be implemented to ensure the

work is performed in compliance with the Act and Regulations;

(c) the safety equipment, devices and clothing to be made available by the Contractor to his employees;

(d) the site access control measures pertaining to health and safety to be

implemented; (e) the arrangements in respect of communication of health and safety related

matters and incidents between the Contractor, his employees, subcontractors and the Project Manager with particular reference to the reporting of incidents in compliance with Section 24 and General Administrative Regulation 8 of the Act and with the pertinent clause of the General Conditions of Contract forming part of the Contract and

"Prev

iew C

opy O

nly"

Page 62: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail E.4E Transnet (August 2006) A Division of Transnet Ltd

Page 5 of 11

(f) the introduction of control measures for ensuring that the Safety Plan is

maintained and monitored for the duration of the Contract. 5.4 The Health and Safety programme shall be subject to the Project Manager's approval

and he may, in consultation with the Contractor, order that additional and/or supplementary practical arrangements and procedures be implemented and maintained by the Contractor or that different working methods or safety equipment be used or safety clothes be issued which, in the Project Manager's opinion, are necessary to ensure full compliance by the Contractor with his obligations as an employer in terms of the Act and Regulations. The Project Manager or his deputy shall be allowed to attend meetings of the Contractor's safety committee as an observer.

5.5 The Contractor shall take reasonable steps to ensure that each subcontractor’s Health

and Safety Plan is implemented and maintained on the construction site: Provided that the steps taken, shall include periodic audits at intervals mutually agreed to between the them, but at least once every month.

5.6 The Contractor shall stop any subcontractor from executing any construction work,

which is not in accordance with the Contractor’s, and/or subcontractor’s Health and Safety Plan for the site or which poses a threat to the health and safety of persons.

5.7 The Contractor shall ensure that a copy of the Health and Safety Plan is available on

site for inspection by an inspector, Project Manager, agent, subcontractor, employee, registered employee organisation, health and safety representative or any member of the health and safety committee.

5.8 The Contractor shall consult with the health and safety committee or, if no health and

safety committee exists, with a representative group of employees, on the development, monitoring and review of the Risk Assessment.

5.9 The Contractor shall ensure that all employees under his control are informed,

instructed and trained by a competent person regarding any hazard and the related work procedures before any work commences, and thereafter at such times as may be determined in the Risk Assessment.

5.10 The Contractor shall ensure that all subcontractors are informed regarding any hazard

as stipulated in the Risk Assessment before any work commences, and thereafter at such times as may be determined in the Risk Assessment.

5.11 The Contractor shall ensure that all visitors to a construction site undergoes health

and safety induction pertaining to the hazards prevalent on the site and shall be provided with the necessary personal protective equipment.

6. Fall Protection Plan

6.1 In the event of the risk and hazard identification, as required in terms of clause 5.3 of this Specification, revealing risks relating to working from an elevated position the contractor shall cause the designation of a competent person, responsible for the preparation of a fall protection plan;

"Prev

iew C

opy O

nly"

Page 63: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail E.4E Transnet (August 2006) A Division of Transnet Ltd

Page 6 of 11

6.2 The Contractor shall implement, maintain and monitor the fall protection plan for the

duration of Contract. The Contractor shall also take such steps to ensure the continued adherence to the fall protection plan.

6.3 The fall protection plan shall include:-

(a) A Risk Assessment of all work carried out from an elevated position; (b) the procedures and methods to address all the identified risks per location;

(c) the evaluation of the employees physical and psychological fitness necessary

to work at elevated positions;

(d) the training of employees working from elevated positions; and

(e) the procedure addressing the inspection, testing and maintenance of all fall protection equipment.

7. Hazards and Potential Hazardous Situations

The Contractor and the Project Manager shall immediately notify one another of any hazardous or potentially hazardous situations which may arise during performance of the Contract by the Contractor or any subcontractor and, in particular, of such hazards as may be caused by the design, execution and/or location and any other aspect pertaining to the contract work.

8. Health and Safety File 8.1 The Contractor shall ensure that a health and safety file is opened and kept on site

and shall include all documentation required as per the Act and applicable regulations, and made available to an inspector, the Project Manager, or subcontractor upon request.

8.2 The Contractor shall ensure that a copy of the both his Health and Safety Plan as well

as any subcontractor’s Health and Safety Plan is available on request to an employee, inspector, contractor or the Project Manager.

8.3 The Contractor shall hand over a consolidated health and safety file to the Project

Manager upon completion of the Construction Work and shall in addition to documentation mentioned in the Act and applicable Regulations include a record of all drawings, designs, materials used and other similar information concerning the completed structure.

"Prev

iew C

opy O

nly"

Page 64: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail E.4E Transnet (August 2006) A Division of Transnet Ltd

Page 7 of 11

ANNEXURE 1

OCCUPATIONAL HEALTH AND SAFETY ACT, 1993

Regulation 3(1) of the Construction Regulations

NOTIFICATION OF CONSTRUCTION WORK

1(a) Name and postal address of principal contractor:

___________________________________________________________________ (b) Name and tel. no of principal contractor’s contact person:

___________________________________________________________________

2. Principal contractor’s compensation registration number: _____________________________

3.(a) Name and postal address of client:

___________________________________________________________________ (b) Name and tel no of client’s contact person or agent: ____________________________________________________________________

4.(a) Name and postal address of designer(s) for the project:

___________________________________________________________________ (b) Name and tel. no of designer(s) contact person: ___________________________________________________________________ 5. Name and telephone number of principal contractor’s construction supervisor on site

appointed in terms of regulation 6(1). ___________________________________________________________________

6. Name/s of principal contractor’s construction sub-ordinate supervisors on site

appointed in terms of regulation 6(2). ____________________________________________________________

7. Exact physical address of the construction site or site office:

___________________________________________________________________ 8. Nature of the construction work:

___________________________________________________________________ ___________________________________________________________________ ___________________________________________________________________ ___________________________________________________________________ ___________________________________________________________________ 9. Expected commencement date: _______________________ 10. Expected completion date: ___________________________

"Prev

iew C

opy O

nly"

Page 65: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail E.4E Transnet (August 2006) A Division of Transnet Ltd

Page 8 of 11

11. Estimated maximum number of persons on the construction site:

_______________________ 12. Planned number of contractors on the construction site accountable to the principle

contractor: ___________________ 13. Name(s) of contractors already chosen. ___________________ ___________________ ___________________ ___________________ ___________________ ___________________ ___________________ _______________________ _________________

Principal Contractor Date _______________________ _________________

Client Date * THIS DOCUMENT IS TO BE FORWARDED TO THE OFFICE OF THE

DEPARTMENT OF LABOUR PRIOR TO COMMENCEMENT OF WORK ON SITE.

* ALL PRINCIPAL CONTRACTORS THAT QUALIFY TO NOTIFY MUST DO SO EVEN IF ANOTHER PRINCIPAL CONTRACTOR ON THE SAME SITE HAD DONE SO PRIOR TO THE COMMENCEMENT OF WORK.

"Prev

iew C

opy O

nly"

Page 66: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail E.4E Transnet (August 2006) A Division of Transnet Ltd

Page 9 of 11

ANNEXURE 2

(COMPANY LETTER HEAD)

OCCUPATIONAL HEALTH AND SAFETY ACT, 1993 (ACT 85 OF 1993) :

SECTION/REGULATION: __________________________________________

REQUIRED COMPETENCY: ________________________________________ In terms of ________________________________________ I,

representing the Employer) do hereby appoint

As the Competent Person on the premises at

(physical address) to assist in compliance with the Act and the applicable Regulations. Your designated area/s is/are as follows :-

Date : ____________________________________

Signature :- ____________________________________

Designation :- _______________________________

ACCEPTANCE OF DESIGNATION

I, do hereby accept this Designation and

acknowledge that I

understand the requirements of this appointment.

Date : ____________________________________

Signature :- ____________________________________

Designation :- ________________________________

"Prev

iew C

opy O

nly"

Page 67: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail E.4E Transnet (August 2006) A Division of Transnet Ltd

Page 10 of 11

ANNEXURE 3

(COMPANY LETTER HEAD)

OCCUPATIONAL HEALTH AND SAFETY ACT, 1993 (ACT 85 OF 1993) :

DECLARATION In terms of the above Act I,

am personally assuming the duties

and obligations as Chief Executive Officer, defined in Section 1 of the Act and in terms of Section 16(1), I will, as far as is reasonably practicable, ensure that the duties and obligations of the Employer as contemplated in the above Act are properly discharged.

Signature :- ____________________________________

Date : ____________________________________

"Prev

iew C

opy O

nly"

Page 68: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail E.4E Transnet (August 2006) A Division of Transnet Ltd

Page 11 of 11

ANNEXURE 4

(LETTER HEAD OF BUSINESS DIVISION OR UNIT OF TRANSNET LIMITED)

SITE ACCESS CERTIFICATE Access to : (Area)

Name of Contractor/Builder :-

Contract/Order No.:

The contract works site/area described above are made available to you for the carrying out of associated works In terms of your contract/order with

(company)

Kindly note that you are at all times responsible for the control and safety of the Works Site, and for persons under your control having access to the site. As from the date hereof you will be responsible for compliance with the requirements of the Occupational Health and Safety Act, 1993 (Act 85 of 1993) as amended, and all conditions of the Contract pertaining to the site of the works as defined and demarcated in the contract documents including the plans of the site or work areas forming part thereof.

Signed : ____________________________________ Date : __________________-

_______________________

PROJECT MANAGER

ACKNOWLEDGEMENT OF RECEIPT

Name of

Contractor/Builder :-

I,

do hereby acknowledge and accept

the duties

and obligations in respect of the Safety of the site/area of Work in terms of the

Occupational Health and Safety Act; Act 85 of 1993.

Name : _____________________________ Designation : ______________

Signature : _________________________________ Date : _________

"Prev

iew C

opy O

nly"

Page 69: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail E7/1 (July 1998) A Division of Transnet Ltd

TRANSNET SOC LIMITED

(REGISTRATION NO.1990/000900/06)

TRADING AS

TRANSNET FREIGHT RAIL

ADDENDUM NO. 1 TO THE E 7/1 (JULY 1998)

SPECIFICATION FOR WORKS ON, OVER, UNDER OR ADJACENT TO RAILWAY LINES AND NEAR

HIGH VOLTAGE EQUIPMENT.

Clause 13 Blasting.

Delete this clause in its entirety

Clause 17 General.

Sub-clause 17.1

Include the words "on request only" after the word "contract" in the fourth line.

Clause 27 Blasting.

Delete this clause in its entirety

"Prev

iew C

opy O

nly"

Page 70: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail E7/1 (July 1998)

A Division of Transnet Ltd

TRANSNET LIMITED (REGISTRATION NO.1990/000900/06)

E7/1 (July 1998)

SPECIFICATION FOR WORKS ON, OVER, UNDER OR ADJACENT TO RAILWAY LINES AND NEAR

HIGH VOLTAGE EQUIPMENT

(This Specification shall be used in Transnet Contracts)

"Prev

iew C

opy O

nly"

Page 71: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail 2 E7/1(July 1998)

A Division of Transnet Ltd

CONTENTS

CLAUSE DESCRIPTION PAGE NO'S

1. DEFINITIONS 3

PART A - GENERAL SPECIFICATION

2. Authority of officers of Transnet 4

3. Contractor's representatives 4

4. Occupations and work permits 4

5. Speed restrictions and protection 5

6. Roads on Transnet property 5

7. Clearances 5

8. Stacking of material 5

9. Excavation, shoring, dewatering and drainage 5

10. Falsework for structures 6

11. Piling 6

12. Underground services 6

13. Blasting 6

14. Rail trolleys 7

15. Signal track circuits 7

16. Penalty for delays to trains 7

PART B - ADDITIONAL SPECIFICATION FOR WORK NEAR HIGH-VOLTAGE

ELECTRICAL EQUIPMENT

17. General 8

18. Work on buildings of fixed structures 8

19. Work done on or outside of rolling stock, including loading and unloading 8

20. Use of equipment 9

21. Carrying and handling material and equipment 9

22. Precautions to be taken when erecting or removing

poles, antennae and trees 10

23. Use of water 10

24. Use of construction plant 10

25. Work performed under dead conditions under cover

of a work permit 10

26. Traction return circuits in rails 11

27. Blasting 11

28. High-voltage electrical equipment not maintained

and/or operated by Transnet 11

ANNEXES

1. Horizontal clearances 1 065 mm gauge

2. Vertical clearances 1 065 mm gauge

3. Clearances 610 mm gauge

4. Platform clearances "Prev

iew C

opy O

nly"

Page 72: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail 3 E7/1(July 1998)

A Division of Transnet Ltd

1 DEFINITIONS The following definitions shall apply : Authorised Person. A person whether an employee of Transnet or not, who has been specially

authorised to undertake specific duties in terms of Transnet Freight Rail's publication SAFETY INSTRUCTIONS: HIGH-VOLTAGE ELECTRICAL EQUIPMENT, and who holds a certificate or letter of authority to that effect.

Barrier. Any device designed to restrict access to "live" high-voltage electrical equipment. Bond. A short conductor installed to provide electrical continuity. Contractor. Any person or organisation appointed by Transnet to carry out work on its behalf. Dead. Isolated and earthed. Electrical Officer (Contracts). The person appointed in writing by the responsible Electrical

Engineer in Transnet as the person who shall be consulted by the Contractor in all electrical matters to ensure that adequate safety precautions are taken by the Contractor.

Executive Officer. The person appointed by Transnet from time to time as the Executive Officer to

act according to the rights and powers held by and obligations placed upon him in terms of the Contract.

High-Voltage. A voltage normally exceeding 1 000 volts. Live. A conductor is said to be "live" when it is at a potential different from that of the earth or any

other conductor of the system of which it forms a part. Near. To be in such a position that a person's body or the tools he is using or any equipment he is

handling may come within 3 metres of live exposed high-voltage electrical equipment. Occupation. An authorisation granted by Transnet for work to be carried out under specified

conditions on, over under or adjacent to railway lines. Occupation Between Trains. An occupation during an interval between successive trains. Project Manager. The person or juristic person appointed by Transnet from time to time as the

Project Manager, to administer the Contract according to the powers and rights held by and obligations placed upon him in terms of the Contract.

Responsible Representative. The responsible person in charge, appointed by a contractor, who

has undergone specific training (and holds a certificate) to supervise staff under his control to work on, over, under or adjacent to railway lines and in the vicinity of high-voltage electrical equipment.

Supervisor. The person or juristic person appointed by Transnet from time to time as the

Supervisor, to administer the Contractor's performance and execution of the Works according to the powers and rights held by and obligations placed upon the Supervisor in terms of the Contract.

Total Occupation. An occupation for a period when trains are not to traverse the section of line covered by the occupation.

Work on. Work undertaken on or so close to the equipment that the specified working clearances

to the live equipment cannot be maintained. Work Permit. A combined written application and authority to proceed with work on or near dead

electrical equipment.

"Prev

iew C

opy O

nly"

Page 73: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail 4 E7/1(July 1998)

A Division of Transnet Ltd

PART A - GENERAL SPECIFICATION

2. AUTHORITY OF OFFICERS OF TRANSNET

2.1 The Contractor shall co-operate with the officers of Transnet and shall comply with all instructions

issued and restrictions imposed with respect to the Works which bear on the existence and

operation of Transnet's railway lines and high-voltage equipment.

2.2 Without limiting the generality of the provisions of 2.1, any duly authorised representative of

Transnet, having identified himself, may stop the work if, in his opinion, the safe passage of trains

or the safety of Transnet assets or any person is affected. CONSIDERATIONS OF SAFETY

SHALL TAKE PRECEDENCE OVER ALL OTHER CONSIDERATIONS.

3. CONTRACTOR'S REPRESENTATIVES

3.1 The Contractor shall nominate Responsible Representatives of whom at least one shall be

available at any hour for call-out in cases of emergency. The Contractor shall provide the

Supervisor with the names, addresses and telephone numbers of the representatives.

3.2 The Contractor guarantees that he has satisfied himself that the Responsible Representative is

fully conversant with this specification and that he shall comply with all his obligations in respect

thereof.

4. OCCUPATIONS AND WORK PERMITS

4.1 Work to be done during total occupation or during an occupation between trains or under a work

permit shall be done in a manner decided by the Supervisor and at times to suit Transnet

requirements.

4.2 The Contractor shall organise the Works in a manner, which will minimise the number and duration

of occupations and work permits required.

4.3 Transnet will not be liable for any financial or other loss suffered by the Contractor arising from his

failure to complete any work scheduled during the period of an occupation or work permit.

4.4 The Contractor shall submit to the Supervisor, in writing, requests for occupations or work permits

together with details of the work to be undertaken, at least 14 days before they are required.

Transnet does not undertake to grant an occupation or work permit for any particular date, time or

duration.

4.5 Transnet reserves the right to cancel any occupation or work permit at any time before or during

the period of occupation or work permit. If, due to cancellation or change in date or time, the

Contractor is not permitted to start work under conditions of total occupation or work permit at the

time arranged, all costs caused by the cancellation shall be born by the Contractor except as

provided for in clauses 4.6 to 4.8.

4.6 When the Contractor is notified less than 2 hours before the scheduled starting time that the

occupation or work permit is cancelled, he may claim reimbursement of his direct financial losses

caused by the loss of working time up to the time his labour and plant are employed on other work,

but not exceeding the period of the cancelled occupation or work permit.

4.7 When the Contractor is notified less than 2 hours before the schedule starting time, or during an

occupation or work permit, that the duration of the occupation or work permit is reduced, he may

claim reimbursement of his direct financial losses caused by the loss of working time due to the

reduced duration of the occupation or work permit.

4.8 Reimbursement the Contractor for any loss of working time in terms of 4.6 and 4.7, shall be subject

to his claims being submitted within 14 days of the event with full details of labour and plant

involved, and provided that the Supervisor certifies that no other work on which the labour and

"Prev

iew C

opy O

nly"

Page 74: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail 5 E7/1(July 1998)

A Division of Transnet Ltd

plant could be employed was immediately available.

4.9 Before starting any work for which an occupation has been arranged, the Contractor shall obtain

from the Supervisor written confirmation of the date, time and duration of the occupation.

4.10 Before starting any work for which a work permit has been arranged, the Responsible

Representative shall read and sign portion C of form No. T.1276 signifying that he is aware of the

limits within which work may be undertaken. After the work for which the permit was granted has

been completed, or when the work permit is due to be terminated, or if the permit is cancelled after

the start, the same person who signed portion C shall sign portion D of the T.1276 form, thereby

acknowledging that he is aware that the electrical equipment is to be made "live". The Contractor

shall advise all his workmen accordingly.

5. SPEED RESTRICTIONS AND PROTECTION

5.1 When speed restrictions are imposed by Transnet because of the Contractor's activities, the

Contractor shall organise and carry out his work so as to permit the removal of the restrictions as

soon as possible.

5.2 When the Supervisor considers protection to be necessary the Contractor shall, unless otherwise

agreed, provide all protection including flagmen, other personnel and all equipment for the

protection of Transnet's and the Contractor's personnel and assets, the public and including trains.

Transnet will provide training free of charge of the Contractor's flagmen and other personnel

performing protection duties. The Contractor shall consult with the Supervisor, whenever he

considers that protection will be necessary, taking into account the minimum permissible

clearances set out in appendixes 1 to 4.

5.3 The Contractor shall appoint a Responsible Representative to receive and transmit any instruction,

which may be given by Transnet personnel providing protection.

6. ROADS ON TRANSNET PROPERTY

The provision of clause 25 of the E.5, General Conditions of Contract, or clause 23 of the E.5

(MW), General Conditions of Contract for Maintenance Works, shall apply to the use of existing

roads on Transnet's property.

7. CLEARANCES

7.1 No temporary works shall encroach on the appropriate minimum clearances set out in Annexure 1

BE97-01 Sheets 1,2, 3 and 5 of 5.

8. STACKING OF MATERIAL

8.1 The Contractor shall not stack any material closer than 3 m from the centre line of any railway line

without prior approval of the Supervisor.

9. EXCAVATION, SHORING, DEWATERING AND DRAINAGE

9.1 Unless otherwise approved by the Supervisor any excavation adjacent to a railway line shall not

encroach on the hatched area shown in Figure 1.

9.2 The Contractor shall provide at his own cost any shoring, dewatering or drainage of any excavation

unless otherwise stipulated elsewhere in the Contract.

"Prev

iew C

opy O

nly"

Page 75: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail 6 E7/1(July 1998)

A Division of Transnet Ltd

9.3 Where required by the Supervisor, drawings of shoring for any excavation under or adjacent to a

railway line shall be submitted and permission to proceed obtained, before the excavation is

commenced.

9.4 The Contractor shall prevent ingress of water to the excavation but where water does enter, he

shall dispose of it as directed by the Supervisor.

9.5 The Contractor shall not block, obstruct or damage any existing drains either above or below

ground level unless he has made adequate prior arrangements to deal with drainage.

10. FALSEWORK FOR STRUCTURES

10.1 Drawings of falsework for the construction of any structure over, under or adjacent to any railway

line shall be submitted to the Supervisor and his permission to proceed obtained before the

falsework is erected. Each drawing shall be given a title and a distinguishing number and shall be

signed by a registered professional engineer certifying that he has checked the design of the

falsework and that the drawings are correct and in accordance with the design.

10.2 After the falsework has been erected and before any load is applied, the Contractor shall submit to

the Supervisor a certificate signed by a registered professional engineer certifying that he has

checked the falsework and that it has been erected in accordance with the drawings. Titles and

numbers of the drawings shall be stated in the certificate. Notwithstanding permission given by the

Supervisor to proceed, the Contractor shall be entirely responsible for the safety and adequacy of

the falsework.

11. PILING

11.1 The Supervisor will specify the conditions under which piles may be installed on Transnet property.

12. UNDERGROUND SERVICES

12.1 No pegs or stakes shall be driven or any excavation made before the Contractor has established

that there are no underground services, which may be damaged thereby.

12.2 Any damage shall be reported immediately to the Supervisor, or to the official in charge at the

nearest station, or to the traffic controller in the case of centralised traffic control.

13. BLASTING

13.1 The provisions of clause 23 of the E.5, General Conditions of Contract or clause 21 of the E.5

(MW), General Conditions of Contract for Maintenance Work, shall apply to all blasting operations

undertaken in terms of the Contract.

13.2 The Contractor shall provide proof that he has complied with the provisions of clauses 10.17.1 to

10.17.4 of the Explosives Regulations (Act 26 of 1956 as amended).

13.3 Blasting within 500m of a railway line will only be permitted during intervals between trains. A

person appointed by the Supervisor, assisted by flagmen with the necessary protective equipment,

will be in communication with the controlling railway station.

Only this person will be authorised to give the Contractor permission to blast, and the Contractor

shall obey his instructions implicitly regarding the time during which blasting may take place.

13.4 The flagmen described in 13.3, where provided by Transnet, are for the protection of trains and

Transnet property only, and their presence does not relieve the Contractor in any manner of his

responsibilities in terms of Explosives Act or Regulations, or any obligation in terms of this

Contract.

"Prev

iew C

opy O

nly"

Page 76: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail 7 E7/1(July 1998)

A Division of Transnet Ltd

13.5 The person described in 13.3 will record in a book provided and retained by Transnet the dates and

times -

(i) when each request is made by him to the controlling station for permission to blast;

(ii) when blasting may take place;

(iii) when blasting actually takes place; and

(iv) when he advises the controlling station that the line is safe for the passage of trains.

13.6 Before each blast the Contractor shall record in the same book, the details of the blast to be

carried out. The person appointed by the Supervisor and the person who will do the blasting

shall both sign the book whenever an entry described in 13.5 is made.

13.7 The terms of clause 27 hereof shall be strictly adhered to.

14. RAIL TROLLEYS

14.1 The use of rail trolleys or trestle trolleys on a railway line for working on high voltage equipment

will be permitted only if approved by the Supervisor and under the conditions stipulated by him.

14.2 All costs in connection with such trolley working requested by the Contractor shall, unless

otherwise agreed, be borne by the Contractor, excluding the costs of any train protection

services normally provided free of charge by Transnet.

15. SIGNAL TRACK CIRCUITS

15.1 Where signal track circuits are installed, the Contractor shall ensure that no material capable of

conducting an electrical current makes contact between rails of a railway line/lines.

15.2 No signal connections on track-circuited tracks shall be severed without the Supervisor's

knowledge and consent.

16. PENALTY FOR DELAYS TO TRAINS

16.1 If any trains are delayed by the Contractor and the Supervisor is satisfied that the delay was

avoidable, a penalty will be imposed on the Contractor of R5 000 per hour or part thereof for the

period of delay, irrespective of the number of trains delayed.

"Prev

iew C

opy O

nly"

Page 77: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail 8 E7/1(July 1998) A Division of Transnet Ltd

PART B - ADDITIONAL SPECIFICATION FOR WORK NEAR HIGH-VOLTAGE

ELECTRICAL EQUIPMENT

17. GENERAL

17.1 This specification is based on the contents of Transnet Freight Rail's publication SAFETY

INSTRUCTIONS, HIGH-VOLTAGE ELECTRICAL EQUIPMENT, as amended, a copy of which

will be made available on loan to the Contractor for the duration of the contract. These

instructions apply to all work near live high-voltage equipment maintained and/or operated by

Transnet, and the onus rests on the Contractor to ensure that he obtains a copy.

17.2 The Contractor's attention is drawn in particular to the contents of Part I, Sections 1 and 2 of the

Safety Instructions : High-Voltage Electrical Equipment.

17.3 The Safety Instructions : High-Voltage Electrical Equipment cover the minimum safety

precautions which must be taken to ensure safe working on or near high-voltage electrical

equipment, and must be observed at all times. Should additional safety measures be

considered necessary because of peculiar local conditions, these may be ordered by and at the

discretion of the Electrical Officer (Contracts).

17.4 This specification must be read in conjunction with and not in lieu of the Safety Instructions :

High-Voltage Electrical Equipment.

17.5 The Contractor shall obtain the approval of the Electrical Officer (Contracts) before any work is

done which causes or could cause any portion of a person's body or the tools he is using or any

equipment he is handling, to come within 3 metres of any live high-voltage equipment.

17.6 The Contractor shall regard all high-voltage equipment as live unless a work permit is in force.

17.7 Safety precautions taken or barriers erected shall comply with the requirements of the Electrical

Officer (Contracts), and shall be approved by him before the work to be protected is undertaken

by the Contractor. The Contractor shall, unless otherwise agreed, bear the cost of the provision

of the barriers and other safety precautions required, including the attendance of Transnet staff

where this is necessary.

17.8 No barrier shall be removed unless authorised by the Electrical Officer (Contracts).

18. WORK ON BUILDINGS OR FIXED STRUCTURES

Before any work is carried out or measurements are taken on any part of a building, fixed

structure or earthworks of any kind above ground level situated within 3 metres of live high-

voltage equipment, the Electrical Officer (Contracts) shall be consulted to ascertain the

conditions under which the work may be carried out.

18.2 No barrier erected to comply with the requirements of the Electrical Officer (Contracts) shall be

used as temporary staging or shuttering for any part of the Works.

18.3 The shuttering for bridge piers, abutments, retaining walls or parapets adjacent to or over any

track may be permitted to serve as a barrier, provided that it extends at least 2,5 metres above

any working level in the case of piers, abutments and retaining walls and 1,5 metres above any

working level in the case of parapets.

19. WORK DONE ON OR OUTSIDE OF ROLLING STOCK, INCLUDING LOADING OR

UNLOADING

19.1 No person shall stand, climb or work whilst on any platform, surface or foothold higher than the

normal unrestricted places of access, namely -

(i) the floor level of trucks;

"Prev

iew C

opy O

nly"

Page 78: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail 9 E7/1(July 1998) A Division of Transnet Ltd

(ii) external walkways on diesel, steam and electric locomotives, steam heat vans, etc. and

(iii) walkways between coaches and locomotives.

When in these positions, no person may raise his hands or any equipment or material he is

handling above his head.

19.2 In cases where the Contractor operates his own rail mounted equipment, he shall arrange for

the walkways on this plant to be inspected by the Electrical Officer (Contracts) and approved,

before commencement of work.

19.3 The handling of long lengths of material such as metal pipes, reinforcing bars, etc should be

avoided, but if essential they shall be handled as nearly as possible in a horizontal position

below head height.

19.4 The Responsible Representative shall warn all persons under his control of the danger of being

near live high-voltage equipment, and shall ensure that the warning is fully understood.

19.5 Where the conditions in 19.1 to 19.3 cannot be observed the Electrical Officer (Contracts), shall

be notified. He will arrange for suitable Safety measures to be taken. The Electrical Officer

(Contracts), may in his discretion and in appropriate circumstances, arrange for a suitable

employee of the Contractor to be specially trained by Transnet Freight Rail and at its costs, as

an Authorised Person to work closer than 3 metres from live overhead conductors and under

such conditions as may be imposed by the Senior responsible Electrical Engineer in Transnet.

20. USE OF EQUIPMENT

20.1 Measuring Tapes and Devices

20.1.1 Measuring tapes may be used near live high-voltage equipment provided that no part of any

tape or a person's body comes within 3 metres of the live equipment.

20.1.2 In windy conditions the distance shall be increased to ensure that if the tape should fall it will not

be blown nearer than 3 metres from the live high-voltage equipment.

20.1.3 Special measuring devices longer than 2 metres such as survey staves and rods may be used if

these are of non-conducting material and approved by the responsible Electrical Engineer in

Transnet, but these devices must not be used within 3 metres of live high-voltage equipment in

rainy or wet conditions.

20.1.4 The assistance of the Electrical Officer (Contracts) shall be requested when measurements

within the limits defined in 20.1.1 to 20.1.3 are required.

20.1.5 The restrictions described in 20.1.1 to 20.1.3 do not apply on a bridge deck between permanent

parapets nor in other situations where a barrier effectively prevents contact with the live high-

voltage equipment.

20.2 Portable Ladders

20.2.1 Any type of portable ladder longer then 2 metres may only be used near live high-voltage

equipment under the direct supervision of the Responsible Representative. He shall ensure that

the ladder is always used in such a manner that the distance from the base of the ladder to any

live high-voltage equipment is greater than the fully extended length of the ladder plus 3 metres.

Where these conditions cannot be observed, the Electrical Officer (Contracts) shall be advised,

and he will arrange for suitable safety measures to be taken.

21. CARRYING AND HANDLING MATERIAL AND EQUIPMENT

21.1 Pipes, scaffolding, iron sheets, reinforcing bars and other material, which exceeds 2 metres in

"Prev

iew C

opy O

nly"

Page 79: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail 10 E7/1(July 1998) A Division of Transnet Ltd

length, shall be carried completely below head height near live high-voltage equipment. For

maximum safety two or more persons so as to maintain it as nearly as possible in a horizontal

position should carry such material. The utmost care must be take to ensure that no part of the

material comes within 3 metres of any live high-voltage equipment.

21.2 Long lengths of wire or cable shall never be run out in conditions where a part of a wire or cable

can come within 3 metres of any live high-voltage equipment unless the Electrical Officer

(Contracts) has been advised and has approved appropriate safety precautions.

21.3 The presence of overhead power lines shall always be taken account of especially when

communications lines or cables or aerial cables, stay wires, etc. are being erected above

ground level.

22. PRECAUTIONS TO BE TAKEN WHEN ERECTING OR REMOVING POLES, ANTENNAE,

TREES ETC.

22.1 A pole may be handled for the purpose of erection or removal near high-voltage equipment

under the following conditions:

(i) If the distance between the point at which the pole is to be erected or removed and the

nearest live high-voltage equipment is more than the length of the pole plus 3 metres, the

work shall be supervised by the Responsible Representative.

(ii) If the distance described in (i) is less than the length of the pole plus 3 metres, the

Electrical Officer (Contracts) shall be consulted to arrange for an Authorised Person to

supervise the work and to ensure that the pole is earthed where possible. The pole shall

be kept in contact with the point of erection, and adequate precautions shall be taken to

prevent contact with live high-voltage equipment.

22.2 The cost of supervision by an Authorised Person and the provision of earthing shall, unless

otherwise agreed, be borne by the Contractor.

22.3 The provisions of clauses 22.1 and 22.2 shall also apply to the erection or removal of columns,

antennae, trees, posts, etc.

23. USE OF WATER

23.1 No water shall be used in the form of a jet if it can make contact with any live high-voltage

equipment or with any person working on such equipment.

24. USE OF CONSTRUCTION PLANT

24.1 "Construction plant" entails all types of plant including cranes, piling frames, boring machines,

excavators, draglines, dewatering equipment and road vehicles with or without lifting equipment.

24.2 When work is being undertaken in such a position that it is possible for construction plant or its

load to come within 3 metres of live high-voltage equipment, the Electrical Officer (Contracts)

shall be consulted. He will arrange for an Authorised Person to supervise the work and to

ensure that the plant is adequately earthed. The Electrical Officer (Contracts) will decide

whether further safety measures are necessary.

24.3 The cost of any supervision by an Authorised Person and the provision of earthing shall, unless

otherwise agreed, be borne by the Contractor.

24.4 When loads are handled by cranes, non-metallic rope hand lines shall be used, affixed to such

loads so as to prevent their swinging and coming within 3 metres of live high-voltage equipment.

24.5 Clauses 24.1 to 24.4 shall apply mutatis mutandis to the use of maintenance machines of any

nature.

"Prev

iew C

opy O

nly"

Page 80: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail 11 E7/1(July 1998) A Division of Transnet Ltd

25. WORK PERFORMED UNDER DEAD CONDITIONS UNDER COVER OF A WORK PERMIT

25.1 If the Responsible Representative finds that the work cannot be done in safety with the high-

voltage electrical equipment live, he shall consult the Electrical Officer (Contracts) who will

decide on the action to be taken.

25.2 If a work permit is issued the Responsible Representative shall -

(i) before commencement of work ensure that the limits within which work may be carried out

have been explained to him by the Authorised Person who issued the permit to him, and

that he fully understands these limits.

(ii) sign portion C of the permit before commencement of work;

(iii) explain to all persons under his control the limits within which work may be carried out, and

ensure that they fully understand these limits;

(iv) care for the safety of all persons under his control whilst work is in progress; and

(v) withdraw all personnel under his control from the equipment on completion of the work

before he signs portion D of the work permit.

26. TRACTION RETURN CIRCUITS IN RAILS

26.1 DANGEROUS CONDITIONS CAN BE CREATED BY REMOVING OR SEVERING ANY

BOND.

26.2 Broken rails with an air gap between the ends, and joints, at which fishplates are removed

under "broken bond" conditions, are potentially lethal. The rails on either side of an air gap

between rail ends on electrified lines shall not be touched simultaneously until rendered safe by

Transnet personnel.

26.3 The Contractor shall not break any permanent bonds between rails or between rails and any

structure. He shall give the Supervisor at least 7 days written notice when removal of such

bonds is necessary.

26.4 No work on the track which involves interference with the traction return rail circuit either by

cutting or removing the rails, or by removal of bonds shall be done unless the Electrical Officer

(Contracts) is consulted. He will take such precautions as may be necessary to ensure

continuity of the return circuit before permitting the work to be commenced.

27. BLASTING

27.1 The Contractor shall obtain the permission of the Electrical Officer (Contracts) before blasting,

and shall give at least 14 days notice of his intention to blast.

27.2 No blasting shall be done in the vicinity of electrified lines unless a member of Transnet's

electrical personnel is present.

27.3 The terms of clause 13 hereof shall be strictly adhered to.

28. HIGH-VOLTAGE ELECTRICAL EQUIPMENT NOT MAINTAINED AND/OR OPERATED BY

TRANSNET

Where the work is undertaken on or near high-voltage electrical equipment which is not

maintained and/or operated by Transnet, the Occupational Health and Safety Act No. 85 of

1993, and Regulations and Instructions, or the Mines Health and Safety Act (Act 29 of 1996),

shall apply.

"Prev

iew C

opy O

nly"

Page 81: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail 12 E7/1(July 1998) A Division of Transnet Ltd

Such equipment includes: -

(i) Eskom and municipal equipment;

(ii) the Contractor's own power supplies; and

(iii) electrical equipment being installed but not yet taken over from the Contractor.

"Prev

iew C

opy O

nly"

Page 82: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail 13 E7/1(July 1998) A Division of Transnet Ltd

"Prev

iew C

opy O

nly"

Page 83: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail 14 E7/1(July 1998) A Division of Transnet Ltd

"Prev

iew C

opy O

nly"

Page 84: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail 15 E7/1(July 1998) A Division of Transnet Ltd

"Prev

iew C

opy O

nly"

Page 85: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail 16 E7/1(July 1998) A Division of Transnet Ltd

"Prev

iew C

opy O

nly"

Page 86: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A division of Transnet Limited

Contract Page 1 of 2 C4 Part C4: Site Information

PART C4

SITE INFORMATION

CONTENTS Section Description

C4.1 DESCRIPTION OF THE EXISTING SITES

"Prev

iew C

opy O

nly"

Page 87: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A division of Transnet Limited

Contract Page 2 of 2 C4 Part C4: Site Information

Part C4 Section 1 SITE INFORMATION

C.4.1 DESCRIPTION OF THE EXISTING SITES

C.4.1.1 For the existing yard layout and plant arrangement please refer to drawings no.:

BBC0665 version 1 – South Portal substation

BBC0666 version 1 – Quail substation

BBC0668 version 1 – Nottingham Road substation.

BBB8365 version 1 – Danskraal substation

BBC0964 version 1 – Elandslaagte substation

BBC0968 version 1 – Wasbank substation

BBC0673 version 1 – Glencoe substation

"Prev

iew C

opy O

nly"

Page 88: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A Division of Transnet Limited

Contract

Part C4: Site Information

Part C4: Site Information

"Prev

iew C

opy O

nly"

Page 89: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail RFP No. S.I.E 10032CIDB A Division of Transnet Limited

Part T1 T1.2 Tendering procedures Tender Data

Part T1.2: Tender Data

"Prev

iew C

opy O

nly"

Page 90: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

"Prev

iew C

opy O

nly"

Page 91: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

"Prev

iew C

opy O

nly"

Page 92: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

"Prev

iew C

opy O

nly"

Page 93: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

"Prev

iew C

opy O

nly"

Page 94: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

"Prev

iew C

opy O

nly"

Page 95: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

"Prev

iew C

opy O

nly"

Page 96: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

"Prev

iew C

opy O

nly"

Page 97: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

"Prev

iew C

opy O

nly"

Page 98: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail RFP No. S.I.E 10032CIDB A Division of Transnet Ltd Refurbishment of 3kV substations

Part T1 Tendering procedures

Part T1

Tendering Procedures

"Prev

iew C

opy O

nly"

Page 99: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail RFP No. S.I.E 10032CIDB

A Division of Transnet Limited

Part T2

Returnable Documents

Part T2: Returnable documents

"Prev

iew C

opy O

nly"

Page 100: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

LindequeJ

[Pick the date]

TRANSNET LIMITED

EXECUTIVE SUMMARY 2010/2011

As at 1 April 2010

Transnet Procedure Manual Contract Works / Contractors Public Liability

Principal Controlled Insurance 2010 /2011

"Prev

iew C

opy O

nly"

Page 101: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Index

INTRODUCTION............................................................................................................................. 3 INSURANCE RESPONSIBILITIES ................................................................................................. 5 SUMMARY OF COVER - GENERAL.............................................................................................. 8 SUMMARY OF COVER - CONTRACT WORKS INSURANCE..................................................... 12 SUMMARY OF COVER - CONTRACTORS PUBLIC LIABILITY INSURANCE............................ 18 ADMINISTRATIVE PROCESS ..................................................................................................... 23 IMPORTANT CONSIDERATIONS................................................................................................ 26 CLAIMS PROCEDURE................................................................................................................. 28 AON SOUTH AFRICA - PERSONNEL ......................................................................................... 32 ANNEXURE 1 ............................................................................................................................... 33 Transnet Principal Controlled Construction Insurance Programme Contract Award Declaration (Part A) and Contract Completion Declaration (Part B) ANNEXURE 2 ............................................................................................................................... 34 Incident Advice Form ANNEXURE 3 ............................................................................................................................... 35 Annual Contract Works / Contractors Public Liability / Lateral Support Policy Wording ANNEXURE 4 ............................................................................................................................... 36 Annual Contractors Public Liability Policy Wording "P

review

Cop

y Only

"

Page 102: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 2 -

Introduction

"Prev

iew C

opy O

nly"

Page 103: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 3 -

Introduction TRANSNET LIMITED insure all Projects / Contracts on a Principal Controlled Insurance Programme basis (including the Assembly and/or Erection of Plant and Machinery) in respect of Contract Works and Contractors Public Liability.

Philosophy of the programme Transnet Limited and its Operating Divisions and Specialist Units wish to control the risk exposures in

this regard.

Transnet Limited, as a large organization, bulk-buys - resulting in preferential rates and cover.

Simplified administration.

Eliminates potential problems which usually occur when individual Contractors are responsible to arrange separate insurance.

Includes the Contractor and/or Subcontractors as an insured party.

� It is therefore important that Tender and eventual Contract documents

reflect the fact that Transnet as the Principal (i.e. the Employer) arranges certain covers which incorporates cover on behalf of Contractor’s

� and / or Subcontractor’s. � The concept does not relieve the contracting parties of their

responsibilities for, amongst others, care of the works and liabilities to third parties

"Prev

iew C

opy O

nly"

Page 104: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 4 -

Insurance Responsibilities

"Prev

iew C

opy O

nly"

Page 105: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 5 -

Insurance Responsibilities

1. Cover arranged by Transnet as the Principal (Employer)

1.1 Insurance Cover Applicable To All Contracts 1.1.1 Contract Works Cover Covering fortuitous physical loss or damage to the

works, temporary works and materials for incorporation into the works whilst in transit and whilst at the contract site.

Limited to R100,000,000 any one contract. (Inclusive

of VAT)

1.1.2 Contractors Public Covering legal liability arising out of or connection with

Liability Cover the performance of the works on the contract site or

sites designated by the Principal for purposes of the performance of the contract.

Limited to R10,000,000 any one occurrence.

1.1.3 Riot / Strike Cover Provided by:

(Contract Works) SASRIA (South African Special Risks Insurance

Association) in respect of risks with RSA. NASRIA (Namibian Special Risks Insurance

Association) in respect of risks within Namibia.

1.2 Additional Insurances (Optional)

1.2.1 Marine Transit Cover Covering imports until delivered and checked on site.

1.2.2 Project Delay Cover Covering consequential financial exposures due to

delays following indemnifiable loss or damage to the works.

1.2.3 Removal of Lateral Support Covering legal liability incurred in respect removal of or

weakening of or interference with support to land or property or buildings adjacent to, on or in the vicinity of the Contract site.

Limit of indemnity R25,000,000 any one occurrence.

"Prev

iew C

opy O

nly"

Page 106: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 6 -

� The above information (including limits of insurance purchased) should

be clearly spelt out in Tender and eventual Contract documentation including the deductible (excess) which are applicable and the fact that Contractor’s and/or Subcontractor’s are responsible for the deductible.

2. Cover to be arranged by Contractor’s/Subcontractor’s All Contractor’s/Subcontractor’s still remain fully responsible to arrange insurance in respect of the

following:

As prescribed by the Compensation for Occupational Injuries and Diseases Act No. 130 of 1993 as amended.

Employers Common Law Liability.

Own plant, machinery, equipment and tools.

Motor Vehicles Liability.

Professional Indemnity (Defective Design).

� This should also be clearly spelt out in Tender and eventual Contract

documentation.

3. Cover to be arranged by Consulting Engineers, Architects & Other Professionals

Professional Indemnity (defects in Design, Plan or Specification). Please ensure that Professional Service Providers do not contract out of their liability in this regard.

(Please refer to Transnet Group Insurance for recommendation and approved limits).

"Prev

iew C

opy O

nly"

Page 107: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 7 -

Summary of Cover

General

"Prev

iew C

opy O

nly"

Page 108: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 8 -

Summary of Cover

The Insured Parties Transnet Limited and / or its Affiliated / Subsidiary / Associated Companies as Principal or Employer.

All Contractor’s undertaking work for or on behalf of the Principal in execution of the Contract.

All Subcontractor’s employed by the Contractor and all other Subcontractor’s (whether nominated or otherwise) engaged in the fulfillment of the Contractor.

To the extent required by any Contract or Agreement suppliers manufacturers vendors or other persons engaged on the contract sites but only to the extent of loss damage or liability originating at the Contract Site (other than while the Property Insured is in transit) arising out of the performance of their Contract Site obligations.

Cover Contract Works – as detailed herein.

Contractors Public Liability – as detailed herein.

Insured Contracts

All contracts up to a maximum value of R100,000,000 (Inclusive of VAT)any one contract.

Limited to a maximum contract period of 36 months followed by a maximum Defects Liability / Maintenance period of 12 months.

Excluded Contracts Where the contract value exceeds R100,000,000 (Inclusive of VAT)

Where the contracted duration of the contract exceeds 36 months.

Where contracted Defects Liability / Maintenance period exceeds 12 months.

Contracts involving harbor wet risks*, dams, tunneling, mining, shaft sinking, underground work, quarrying, alterations to water courses being River Diversions or Coffer Dams.

Contracts outside of the territorial limits.

* NOTE

Harbor Wet Risks defined as:-

“Harbor Wet Risks shall mean all work entailing or involving work in or upon water whether partially or fully submerged such as but not limited to quay walls, seawalls, caissons, breakwaters, jetties, piers, deepening widening and dredging of ports and other off shore risks”

"Prev

iew C

opy O

nly"

Page 109: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 9 -

Contracts involving construction and erection of Petrochemical Plant(s) but this exclusion is limited to contracts involving Petrochemical Manufacturing Plant such as Sasol and the like

On an existing airport runway or airstrip or in or on any aircraft.

Contract Site Any location upon which the Insured Contract(s) is to be executed or carried out as more fully defined in the Insured Contract(s) documents together with so much of the surrounding area as may be designated for the performance of the Insured Contract(s).

Territorial Limits The Republic of South Africa and to the extent permitted by the applicable Insurance Acts the territories of Lesotho, Namibia, Swaziland, Botswana, Zimbabwe and Mozambique. N.B. In terms of local legislation enacted in some of the above territories it is required that insurance cover be placed within their local markets. It is therefore important that the Broker be advised timeously (prior to Tender documents being issued) should any contracts, whether as Principal or Contractor, take place in any of the above territories. If Contracts are to take place in any territories not listed above, the Broker also needs to be advised of same at feasibility stage.

Cover Limitations / Warranties

Unsealed / Unprimed Base Course Unsealed / unprimed base course – cover limited to a maximum of 5,000 metres.

Open Trench Open trench – cover limited to a maximum indemnity of 5,000 metres.

� It is essential that the above limitations are brought to the

attention of Contractor’s. Where this restriction is not practical, specific arrangements for cover can be made with Underwriters. They will, however, require detailed underwriting information and an additional premium may be charged.

"Prev

iew C

opy O

nly"

Page 110: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 10 -

Laid Pipes

Pipes with a diameter not exceeding 500mm, and all pipes intended for the transportation of Petroleum Products or Fuel Gasses irrespective of diameter, are to be end capped on the termination of each days work to avoid ingress of mud silt water debris detritus and the like.

Pipes with a diameter exceeding 500mm are to be capped on the termination of each days work with steel mesh to allow ingress of water to avoid floatation but avoiding ingress of large debris or detritus.

NB If above not conformed with cover is forfeited.

Rail Track Re-Profiling

- The maximum speed of any grinding unit shall not exceed 11.00km per hour.

- All Guards, Curtains, Spark Deflectors are to be in place and correctly positioned prior to the commencement of each grind.

- Maximum grinding distance in any one execution shall not exceed 10,000 metres.

- Any changes in prevailing weather conditions must be recorded and appropriate remedial action taken.

- The Insured Parties are to comply with all Fire Fighting requirements as set out in the Project Specification For Track Maintenance With An On Track Grinding / Profiling Machine and any amendments / deviations to this Project Specification are to be advised to the Insurer prior to work being undertaken.

NB If above not conformed with cover is forfeited.

� It is essential that the above Warranties are brought to the

attention of Contractor’s.

Used Plant – Basis of Loss Settlement

Insured property which has operated under service conditions prior to attachment of cover:-

Up to 5 years – cost of repair / reinstatement / replacement.

In excess of 5 years - agreed value (calculated on basis of each life year (or part thereof) on present day New Replacement Value reduced proportionally over 20 years subject to residual of 20%).

"Prev

iew C

opy O

nly"

Page 111: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 11 -

Claims Reporting All incidents that could give rise to claim under the Principal Controlled Insurances,

HAVE TO BE reported to the Broker / Insurer within a 90 (Ninety) day period.

Failing this, all benefits in terms of the Policy shall be voidable from date of occurrence.

All claims must be registered in terms of requirements applicable to Risk Console unique claim number condition.

� It is essential that the above Condition is brought to the attention

of Contractors in Tender / Contract Documents.

Rating Structure The rates include both Contract Works and Contractors Public Liability cover per current policy limits,

terms and conditions.

Minimum premium requirement are:- Track Re-profiling R8,000

Burning of Fire Breaks R8,000

Chemical Vegetation Control R4,000

Vegetation Rehabillitation R4,000

Ballast Tamping R4,000

Geotechnical & Exploratory R4,000

All Other R6,000

SASRIA R 500

(Above are inclusive of VAT)

To extend the contract period beyond 36 months will attract an additional premium.

(See Administrative Procedures herein).

"Prev

iew C

opy O

nly"

Page 112: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 12 -

Summary of Cover

Contract Works Insurance

"Prev

iew C

opy O

nly"

Page 113: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 13 -

1. Contract Works Insurance

Synopsis of Cover Fortuitous Physical loss of or damage: During dismantling of property in connection with the Insured Contracts.

Whilst in transit, including loading and unloading, or whilst temporarily stored at any premises en route to or from The Contract Site within the Territorial Limits;

During the preparation of The Contract Site and thereafter until the Property Insured has been officially accepted by the Employer and becomes his responsibility by means of a Notice of Completion Certificate or similar evidence of legal transfer of risk in the whole or permanent works under the Insured Contract to the Employer;

Where testing and commissioning of Property Insured is conducted by the Employer “completion” for purposes of this insurance to occur only after successful completion of all testing and commissioning of the whole of the permanent works under the Insured Contract;

Where the permanent property insurance arranged by the Employer indemnify the Insured for completed portions of the Property Insured prior to completion of the whole of the permanent works under the Insured Contract, this insurance in respect of such completed portions of the Property Insured shall cease except as provided below;

Work uncompleted or outstanding in terms of any certificate of completion, certificate of handover or similar document shall continue to be insured until its completion and the inception of the Contractual Defects Liability or Maintenance Period (as may be described in the Insured Contract) for such uncompleted or outstanding work where after the provisions of (g) below shall apply in respect of such work;

During the Contractual Defects Liability or Maintenance Period (as may be described in the Insured Contract) pertaining to any part of the permanent works but only in respect of loss or damage:

i) arising from a cause occurring prior to commencement of such period of maintenance or defects liability period

ii) arising from any act or omission of the Insured their Servants, Agents, Suppliers or Subcontractors in pursuance of the Insured’s obligations.

for which the Insured Contractor is responsible under the Contract. "P

review

Cop

y Only

"

Page 114: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 14 -

Contract Period Limitation

Maximum Contract period 36 months

Maximum Defects Liability / Maintenance Period 12 Months

Limits of indemnity

Contract Works (Any One Contract) R100,000,000

Work done on Marine vessels R10,000,000

Surrounding Property R10,000,000

Surrounding Property – Worked Upon R50,000,000

Surrounding Property – Watercraft R10,000,000

Removal to Gain Access R1,000,000

Documentation R100,000

Debris Removal R2,500,000

Claims Preparation Costs R500,000

Maximum testing / commissioning period 60 days

Maximum un-sealed / un-primed base course limitation 5,000 metres

Maximum open trench limitation 5,000 metres

"Prev

iew C

opy O

nly"

Page 115: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 15 -

Deductibles The deductible (excess) is the amount which the Contractor and/or Sub-Contractor is responsible for and this obligation must be reflected in the Tender and/or Contract Documents and the responsibility for same made clear. The deductibles apply to each and every occurrence and in respect of all Contracts. The deductibles are: Loss or damage arising out of major perils (where the term shall include storm, rain, tempest, wind, flood, theft and / or malicious damage, subsidence, collapse, earthquake, testing, commissioning R 25,000 Loss or damage arising from any other cause R 15,000 Removal of Debris R 25,000 Loss or damage to Surrounding Property R 25,000 Loss or damage to Surrounding Property – Worked Upon R 75,000 Loss or damage to Documentation R 5,000 Road Reserve / Servitude R250,000

"Prev

iew C

opy O

nly"

Page 116: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 16 -

All Contracts Entailing Trenching and / or Layer Works Following additional Deductibles apply over and above the aforestated deductibles: - i.e. in excess of 1,000 metres Up to a maximum of 3,000metres 20% of loss / minimum R50,000 Up to a maximum of 5,000metres 20% of loss / minimum R100,000

� It is essential that this is brought to the attention of Contractor’s.

Where this restriction is not practical, specific arrangements for cover can be made with underwriters. They will, however, require detailed underwriting information and an additional premium may be charged.

Property Insured The actual Contract Works and all material intended for incorporation into the Works (including Free Issue Material* the value of which has to be included in the Contract Value declared) and Temporary Works. N.B.

Temporary works does not include mobile plant, constructional aids, equipment, structures or works (not being part of the permanent works) which are not intended to be removed from the Contract Site on completion of the Contract (other than scaffolding shuttering and formwork as well as construction equipment specifically designed and/or constructed for the Insured Contract and which is not intended for immediate re-use on another contract) or have no residual value at completion of the Contract (other than scrap value), solely due to their specialised nature.

* Note: Where Transnet for the purposes of the Contract issues materials 'free of charge' to the Contractor such materials shall be and remain the property of the Transnet. Free Issue Material shall mean any material provided by or on Transnet's behalf which is to be used in the provision of the Service or incorporated into the Contract.

Main Exceptions The amount of the policy deductible.

Loss or damage of money or the like.

Aircraft, waterborne vessels or craft.

Construction plant, tools or equipment.

Losses by disappearance / shortage discovered by taking of routine inventory.

Defective material workmanship design plan or specification (but resultant damage covered).

"Prev

iew C

opy O

nly"

Page 117: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 17 -

Cost of re-design, improvement, betterment or alteration.

Consequential loss.

Liquidated damages or penalties for delay in connection with guarantee or performance or efficiency.

"Prev

iew C

opy O

nly"

Page 118: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 18 -

Air transit (unless in territorial limits).

Ocean transit or whilst in storage thereafter (unless immediately inspected by an independent party after offloading from vessel).

During the Contractual Defects Liability or Maintenance Period (as may be described in the Insured Contract) pertaining to any part of the permanent works but only in respect of loss or damage:

i) arising from a cause occurring prior to commencement of such period of maintenance or defects liability period

ii) arising from any act or omission of the Insured his Servants or Agents, in the course of the work carried out in pursuance of the Insured’s obligations with regard to maintenance under the Contract.

Wear, tear, gradual deterioration rust, corrosion or oxidation and normal up-keep.

Electrical or mechanical breakdown or explosion to machinery or plant which has operated under load conditions prior to commencement of the Insured Contract or which has occurred after the Testing / Commissioning Period specified in the Policy.

Damage to any property insured due to ingress of mud, silt, water, debris unless pipe ends have been sealed on termination of each days work by means of end caps as prescribed in the policy.

Damage to any unsealed / unprimed or base course in excess of limitations as stated in the policy.

Damage to any open trench in excess of the limitations as stated in the policy.

War, asbestos and nuclear risks.

Sinking (whether partial or in whole) of any watercraft arising out of or in consequence of any work undertaken below the load line ( international load line / plimsoll line).

"Prev

iew C

opy O

nly"

Page 119: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 19 -

Summary of Cover

Contractors Public Liability Insurance

"Prev

iew C

opy O

nly"

Page 120: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 20 -

2. Contractors Public Liability Insurance

Insured Contracts

All contracts up to a maximum value of R100,000,000 (Inclusive of VAT) any one contract.

Limited to a maximum contract period of 36 months followed by a maximum Defects Liability / Maintenance period of 12 months.

Synopsis of Cover Legal Liability to pay as compensation for and in consequence of: Accidental death of or injury to or illness or disease contracted by any person.

Accidental loss of / or physical damage to tangible property.

Occurring during the period of insurance and arising out of or in connection with the performance of the Insured Contract(s). First Party Property* Extension will apply to the Lateral Support policy extensions.

* Note: Coverage for the insured's personal and real property.

Type Of Contract All Contracts undertaken including:- Chemical Vegetation Control

Vegetation Rehabilitation

Ballast Tamping

Rail Track Re-profiling including the contract works

Burning of Fire Breaks

Geotechnical and Exploratory Works

N.B.

The above noted contract types attract specific differentiated rates and are insured by way of a separate policy.

"Prev

iew C

opy O

nly"

Page 121: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 21 -

Limits Of Indemnity

Contractors Public Liability R10,000,000 any one occurrence / unlimited for the Period of Insurance

Removal of Lateral Support R25,000,000 unlimited for the Period of Insurance (provided on request only

Statutory Legal Defence Costs R500,000 any one occurrence

Arrest / Assault / Defamation R500,000 any one occurrence

Emergency Medical Expenses R500,000 any one occurrence

Prevention of Access R500,000 any one occurrence

Trespass / Nuisance R500,000 any one occurrence

Claims Preparation Costs R500,000 any one occurrence

Deductibles The deductible (excess) is the amount which the Contractor and/or Sub-Contractor is responsible for and this obligation must be reflected in the Tender and/or Contract Documents and the responsibility for same made clear. The deductibles apply to each and every occurrence and in respect of all Contracts. The deductibles are: Loss of or damage to public utilities R25,000

Spread of fire R250,000

Spread of fire – track re-profiling R250,000

Loss of or damage to any other property R25,000

Loss of or damage arising from removal of lateral support R25,000

Loss of or damage arising from the burning of fire breaks R250,000

Loss of or damage arising out of vegetation control R250,000 ` including but not limited to the use of pesticides and or herbicides

"Prev

iew C

opy O

nly"

Page 122: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 22 -

Main Exceptions The amount of the policy deductible.

Death or injury to own employees.

Motor vehicle liabilities under legislation or as defined in Multi-lateral Motor Vehicles Accident Fund No. 93 of 1989 as amended.

Claims in connection with ownership or use of aircraft or watercraft.

Property belonging to the Insured or in his care custody and control (as defined in the Policy).

Property forming part of Contract Works.

Liquidated damages or penalties for delays or in respect of performance or efficiency guarantees.

Liability arising out of defects in workmanship materials design plan or specification in any part of the Property insured.

Arising from or in connection with design plan or specification.

Gradual pollution and contamination.

Sudden unintended and unforeseen seepage, pollution or contamination including the cost of removing, nullifying or cleaning up in respect of both ocean and harbour going watercraft outside of dry dock.

After completion and handover (inclusive of the contractual Defects / Maintenance period).

Punitive damages.

Ownership hiring or leasing of any airport or airstrip.

War, asbestos and nuclear risks.

Cover Limitations / Warranties

Rail Track Re-Profiling

- The maximum speed of any grinding unit shall not exceed 11.00km per hour.

- All Guards, Curtains, Spark Deflectors are to be in place and correctly positioned prior to the commencement of each grind.

- Maximum grinding distance in any one execution shall not exceed 10,000 metres.

- Any changes in prevailing weather conditions must be recorded and appropriate remedial action taken.

- The Insured Parties are to comply with all Fire Fighting requirements as set out in the Project Specification For Track Maintenance With An On Track Grinding / Profiling Machine and any amendments / deviations to this Project Specification are to be advised to the Insurer prior to work being undertaken.

NB: Failure to thoroughly pre-plan and document the safety measures to be adopted with specific regards tp

the incidence of fires being initiated during the execution of the work will invalidate indemnity provided in respect of fire arising out of track re-profiling works.

"Prev

iew C

opy O

nly"

Page 123: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 23 -

� It is essential that this requirement is brought to the attention of

Contractor’s. Where this restriction is not practical, specific arrangements for cover can be made with underwriters. They will, however, require detailed underwriting information and an additional premium may be charged.

Other Limitations

Indemnity for removal of lateral support is limited to R25,000,000.

If a higher limit of indemnity is required, the Employers Insurance Broker’s personnel needs to be advised and underwriting information will need to be provided in advance (i.e prior to Tender stage) and this will entail an additional premium.

"Prev

iew C

opy O

nly"

Page 124: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 24 -

Administrative Procedures

"Prev

iew C

opy O

nly"

Page 125: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 25 -

Administrative Procedures

Arranging Insurance cover The Operating Divisions and Specialist Units must Prior to the commencement of each Contract:- Complete the Declaration Form per Part A as per Annexure 1 herein.

Date and sign the Declaration Form.

Submit the Declaration Form to the Broker.

In addition, if the Declaration is being submitted after the commencement date, a separate letter is required stating that, after specific enquiry, The Insured is not aware of any incidents which may give rise to claim/s under this policy. (No Known Incidents Declaration).

On receipt of late declarations which are not accompanied by a “No Known Incidents Declaration”, the Insurance declaration will not be accepted and no cover will be in force.

Record the Declaration on the Contract Monthly Register and submit this Register at the end of each month to Transnet Group Insurance and the Broker.

On receipt of the Declaration Form the Broker will submit it to the Insurer and the following documents will be issued and provided to the Operating Divisions and Specialist Units:- An Insurance Certificate and a SASRIA Coupon evidencing cover.

A Debit Note in respect of the premiums due (based on agreed rates).

NB In terms of SASRIA Regulations, where the Contract Value exceeds R2 million, the physical address of the contract is mandatory. If no physical address i.e. where Track is being worked upon, the start and end points are required.

Prior to the expiry of each Declarations estimated completion date:- Confirm to the Broker that the contract will be completed on time.

On completion submit to the Broker a Declaration of the final contract value per Part B as per Annexure 1 herein.

NB If the original completion date is not going to be achieved, the period of insurance on the Declaration document will need to be extended and the Broker needs to be notified prior to original completion date.

The Operating Divisions and Specialist Units (prior to the expiry date of the certificate period) has to advise the Broker in writing to extend the period of insurance and provide the new estimated completion date.

NB If a completion date needs to be extended and the Broker is not advised prior to the original completion date, all SASRIA cover will cease on the originally declared completion date as there is no hold covered arrangement with SASRIA.

A new SASRIA Coupon will then only be issued for the extension period from the date when

the Insurer is advised in writing by the Broker. Under these circumstances the new SASRIA Coupon will be subject to an additional premium,

subject to the minimum premium.

"Prev

iew C

opy O

nly"

Page 126: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 26 -

This process needs to be followed by the Operating Divisions and Specialist Units until the time of completion is achieved. Once the Contract has been completed:- The Operating Divisions and Specialist Units have to declare the final contract value to the Broker per

Part B as per Annexure 1 herein.

The deposit premium will then be adjusted accordingly.

Failure by the Operating Divisions and Specialist Units to conform to the above procedure will result in cover being voided.

"Prev

iew C

opy O

nly"

Page 127: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 27 -

Contracts that require specific arrangements All contracts that fall outside the scope of this Principal Controlled Insurance Programme have to be advised to the Broker prior to Tender and specific “One Off” cover will need to be negotiated. These will be: Where the Contract Value exceeds R100,000,000 (Inclusive of VAT)

Where the Contracted period exceeds 36 months.

Where the Contracted Defects Liability Maintenance period exceeds 12 months.

Other excluded Contracts as described on Page 8 /9 herein.

Contracts involving harbor wet risks*, dams, tunneling, mining, quarrying, shaft sinking, underground work, alterations to water courses being river diversions or coffer dams.

Contracts outside of the Territorial Limits.

In this regard contact the Employers Insurance Broker’s personnel as detailed on Page 33 herein. Contracts where cover limitations will be exceeded or where cover warranties cannot be complied with need to be discussed with the Employers Insurance Broker’s personnel prior to contract award date to enable the Broker to make specific arrangements with Underwriters. This will however require detailed Underwriting Information and an additional premium may be charged.

� In order to ensure that Contractor’s and site staff are aware of

procedures a copy of this Procedure Manual must be supplied to the contract administrators and each Contractor on award of contract..

* Note: Harbour Wet Risks shall mean all work entailing or involving work in or upon water whether partially or fully submerged such as but not limited to quay walls, wharfs seawalls, caissons, breakwaters, jetties, piers, deepening or widening and dredging of ports and other off-shore risks

"Prev

iew C

opy O

nly"

Page 128: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 28 -

Important Considerations

"Prev

iew C

opy O

nly"

Page 129: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 29 -

Important Considerations Cognizance must be taken of the following important considerations:- For contracts involving assembly or erection of plant and machinery or repairs maintenance or

overhaul thereto, THE FULL NEW REPLACEMENT VALUE OF THE PLANT/MACHINERY involved must be declared AND NOT ONLY THE CONTRACT VALUE, for example.:

� Cranes (repairs or final assembly)

� Machinery being moved

� Maintenance or new works on existing Portnet Vessels whilst moored or in dry dock.

Specific arrangements are in place to cover certain contracts where the exposure to own damage (damage to the works) is nil or negligible, but where a high third party liability exposure exists. For example:

� Chemical control of vegetation

� Vegetation rehabilitation

� Ballast tamping

� Re-profiling of Track

� Burning of Fire Breaks

� Geotechnical and Exploratory Works

Contracts of this nature must be clearly identified on the Declaration Form.

Contract value must include the replacement value of any Free Issue Material provided.

VAT must be added to all contract value declarations in order to comply with local legislation.

All policy limits and deductibles are Vat inclusive.

"Prev

iew C

opy O

nly"

Page 130: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 30 -

Claims Procedure

"Prev

iew C

opy O

nly"

Page 131: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 31 -

Claims Procedure In the event of any incident or occurrence, which is likely, to give rise to a claim under the Insurance arranged by the Principal the following procedures shall be adhered to in addition to any statutory or other requirements contained in the Contract. All incidents that could give rise to claim under the Principal Controlled Insurances, HAVE TO BE reported to the Broker / Insurer within a 90 (Ninety) day period from date of loss. IMMEDIATELY advise Aon Construction & Engineering Risks (Attention Sandra Botha). At the same time complete the Incident Advice Form (Annexure 2 herein) and submit to Aon Construction & Engineering Risks. Losses involving theft or malicious damage must be reported to the police and a police reference

number obtained and recorded.

The Employer, Contactor(s) or Sub-Contractor(s) shall allow free access to Insurers’ Loss Adjuster(s) and / or Employer’s Insurance Broker for the purpose of investigation and assessing the loss or damage.

The Employer, Contractor(s) shall not deal direct with the Insurers other than by co-operating with their Loss Adjuster(s) and / or the Employers Insurance Broker.

No Admission of Liability shall be made by the Employer, Contractor(s) or Sub-Contractor(s) in the event of damage, loss or injury to third party property or persons.

Letters from claimants should be passed to Aon Construction & Engineering Risks as soon as possible via the Employer if necessary.

In the event of immediate repairs being necessary in the interest of safety, the Contractors may with the Employer’s permission proceed with such repairs.

The Employer shall immediately advise Sandra Botha at Aon Construction & Engineering Risks.

Other than in the circumstances described above the Contractor shall not proceed with the making good of any loss without the prior authorization of the Employer who shall advise the Insurer’s appointed Loss Adjuster(s) and Sandra Botha of Aon Construction & Engineering Risks.

Upon commencement of the making good of any loss, the Contractor shall keep separate records of the costs involved in making good such loss and these records must be authenticated by the Employer for submission to the Insurer’s or their Loss Adjuster(s). Such records shall include, inter alia, the entire cost of labour, materials, transport and equipment.

The basis upon which the Insurers will indemnify loss or damage is the cost of repair or replacement of the loss or damage including, inter alia, transport and overheads.

On completion of the making good of any loss the records of the costs involved having been authenticated by the Employer shall be sent to the Insurer’s via their Loss Adjuster(s) and copied to Aon Construction & Engineering Risks (Mrs. Sandra Botha) for processing. "P

review

Cop

y Only

"

Page 132: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 32 -

Upon the amount of the loss or damage being agreed upon by the Insurer’s Loss Adjuster(s) and the Contractor, an “Agreement of Loss” form will be signed by the Contractor and Employer.

The amount agreed upon by the Insurers, the Contractor and the Employer shall be paid by the Insurers to the Employer net of the deductible, who will arrange for the payment to be made to the Contractor as appropriate after deduction of the first amount payable.

� All incidents which could give rise to a claim under the insurances

arranged by the Principal / Employer must be notified to the Broker without delay, per the procedures set out above

"Prev

iew C

opy O

nly"

Page 133: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 33 -

Aon South Africa Personnel

Construction and Engineering Division

"Prev

iew C

opy O

nly"

Page 134: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 34 -

Aon South Africa Personnel Construction and Engineering Division Aon South Africa personnel are at all times available for advice, please feel free to contact :- ▪ George Davis Senior Accounts Executive Tel No. (011) 944 7103 Fax No. (086) 505 9558 E-Mail [email protected] ▪ Judy Bath Account Administrator Tel No. (011)944 7053 Fax No. (086)505 9553 E-Mail [email protected] ▪ Sandra Botha Claims Manager Tel No. (011)944-7118 Fax No. (086)556 7169 E-Mail [email protected]

"Prev

iew C

opy O

nly"

Page 135: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 35 -

Annexure 1

Transnet Principal Controlled Construction Insurance Programme Contract Award Declaration (Part A) And Contract Completion Declaration (Part B)

"Prev

iew C

opy O

nly"

Page 136: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

TRANSNET PRINCIPAL CONTROLLED INSURANCE PROGRAMME CONTRACT DECLARATION

CONTRACT NUMBER…………………………………………………………… PURCHASE ORDER NUMBER…………………………………………………

Send to Aon South Africa (Pty) Ltd From (Operating Unit/Specialist Div)……………………….. Construction and Engineering Postal Address …………………………………………….. PO Box 1874 ……………………………………………. Parklands .......................................................... 2121 Represented by .......................................................... Attention : Judy Bath E-Mail Address .......................................................... Tel No. (011) 944-7053 Tel No. .......................................................... Fax No. 086 505 9553 Fax No. .......................................................... E-Mail: [email protected]

PART A – CONTRACT AWARD INFORMATION

TYPE OF CONTRACT MARK WITH AN ‘X’ IF APPLICABLE:

LONG TERM MAINTENANCE / MULTIPLE WORKS CONTRACT with a SERVICE LEVEL AGREEMENT

OTHER

NAME OF CONTRACTOR

CONTRACT AWARD DATE

CONTRACT COMMENCEMENT DATE

EXPECTED CONTRACT COMPLETION DATE

DESCRIPTION OF CONTRACT WORKS

PHYSICAL ADDRESS WHERE CONTRACT IS TAKING PLACE (COMPULSARY FOR ALL CONTRACTS R2M AND OVER)

MAINTENANCE PERIOD (MONTHS)

CONTRACT VALUE AT AWARD

IF PLANT AND MACHINERY INCLUDE REPLACEMENT VALUE

ESTIMATED VALUE OF FREE ISSUED SUPPLIED TO CONTRACTOR

DOES THIS CONTRACT ENTAIL WORK IN RESPECT OF THE FOLLOWING CATEGORIES WHERE THE EXPOSURE TO OWN DAMAGE (DAMAGE TO WORKS) IS NIL OR NEGLIGIBLE [I] CHEMICAL CONTROL OF VEGETATION YES/NO [II] VEGETATION REHABILITATION YES/NO [III] BALLAST TAMPING YES/NO [IV] TRACK RE-PROFILING YES/NO [V] BURNING OF FIRE BREAKS YES/NO [VI] GEOTECHNICAL AND EXPLORATORY WORKS YES/NO

OPTIONAL INSURANCE REQUIRED

[I] IS REMOVAL OF LATERAL SUPPORT COVER REQUIRED? YES/NO [II] DOES THIS CONTRACT EVIDENCE AN EXPOSURE WHICH CAN BE COVERED BY PROJECT DELAY INSURANCE? YES/NO [III] WILL THE EMPLOYER/CONTRACTOR/SUB-CONTRACTOR MAKE ANY DIRECT IMPORTS OF REQUIREMENTS FOR THE CONTRACT THAT REQUIRE MARINE IMPORT INSURANCE? YES/NO IF SO DETAILS NEED TO BE PROVIDED TO THE BROKER SO THAT THIS FORM OF COVER CAN BE ARRANGED SIGNATURE …………………………………………………… DATE: ………………………………………………

"Prev

iew C

opy O

nly"

Page 137: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

TRANSNET PRINCIPAL CONTROLLED INSURANCE PROGRAMME CONTRACT COMPLETION DECLARATION

ORIGINAL CONTRACT NO. …………….. PURCHASE ORDER NO. …………………

PART B – CONTRACT COMPLETION DECLARATION

CONTRACT NUMBER

TITLE OF CONTRACT

CONTRACT COMPLETION DATE

ENDORSEMENT/CERTIFICATE NUMBER

EXPIRY OF MAINTENANCE PERIOD

FINAL CONTRACT VALUE

ACTUAL VALUE OF FREE ISSUE SUPPLIED TO CONTRACTOR

SIGNATURE:…………………………………………… DATE:……………………………………………………………..

"Prev

iew C

opy O

nly"

Page 138: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Aon Transnet PCI-Procedure Manual 2010 - 34 -

Procedure Manual Principal Controlled Insurance 2010

Annexure 2

Incident Advice Form

ALL INCIDENTS HAVE TO BE REPORTED WITHIN 90 DAYS OF OCCURRENCE

"Prev

iew C

opy O

nly"

Page 139: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

TRANSNET PRINCIPAL CONTROLLED INSURANCE PROGRAMME

INCIDENT ADVICE FORM TRANSNET UNIQUE CLAIM NUMBER ……………………………….....

Send to Aon South Africa (Pty) Ltd Construction and Engineering PO Box 1874 Parklands From .......................................................... 2121 Represented by .......................................................... Attention : Sandra Botha Tel No. (011) 944 7118 Tel No. .......................................................... Fax No. (086) 556 7169 Fax No. .......................................................... E-Mail: [email protected]

PRINCIPAL (PER CONTRACT DOCUMENT

CONTRACT NUMBER

ORIGINAL DECLARATON NO.

TITLE OF CONTRACT

ORIGINAL CONTRACT COMMENCEMENT DATE

DATE OF LOSS OR DAMAGE

DATED REPORTED TO SITE AGENT

REPORTED BY

REPORTED TO BY

DATE

LOCALITY OF INCIDENT

DETAILS OF HOW THE LOSS OR DAMAGE OCCURRED

DETAILS AND NATURE OF LOSS OR DAMAGE TO CONTRACT WORKS / TO THIRD PARTY PROPERTY

DETAILS OF OTHER DEATH OR INJURY TO PARTIES

ESTIMATED COST (SEPARATE RECORDS OF ALL COSTS MUST BE KEPT)

WHO OR WHAT APPEARS TO BE RESPONSIBLE FOR THE CAUSE OF THE LOSS / DAMAGE

PERSON WHOM ASSESSOR SHOULD CONTACT DESIGNATION:

TELEPHONE (LANDLINE) CELLPHONE NO. E-MAIL ADDRESS

ALL INCIDENTS HAVE TO BE REPORTED WITHIN 90 DAYS OF OCCURRENCE SIGNED BY: ………………………………………………………… SIGNATURE: ………………………………………….. COMPANY: ………………………………………………………. DATE: …………………………………………………..

"Prev

iew C

opy O

nly"

Page 140: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Annexure 3

Annual Contract Works & Contractors Public Liability And Lateral Support Policy Wording

"Prev

iew C

opy O

nly"

Page 141: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Aon Transnet-PCI-Procedure Manual 2010 -36 -

Annexure 4

Annual Contractors Public Liability Policy Wording

In respect of Contracts entailing:-

■ Chemical Vegetation Rehabilitation

■ Vegetation Rehabilitation

■ Ballast Tamping

■ Rail Track Re-Profiling

■ Burning of Fire Breaks

■ Geotechnical and Exploratory Works

"Prev

iew C

opy O

nly"

Page 142: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

LindequeJ

[Pick the date]

TRANSNET LIMITED

EXECUTIVE SUMMARY 2010/2011

As at 1 April 2010

Transnet Procedure Manual Contract Works / Contractors Public Liability

Principal Controlled Insurance 2010 /2011

"Prev

iew C

opy O

nly"

Page 143: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Index

INTRODUCTION............................................................................................................................. 3 INSURANCE RESPONSIBILITIES ................................................................................................. 5 SUMMARY OF COVER - GENERAL.............................................................................................. 8 SUMMARY OF COVER - CONTRACT WORKS INSURANCE..................................................... 12 SUMMARY OF COVER - CONTRACTORS PUBLIC LIABILITY INSURANCE............................ 18 ADMINISTRATIVE PROCESS ..................................................................................................... 23 IMPORTANT CONSIDERATIONS................................................................................................ 26 CLAIMS PROCEDURE................................................................................................................. 28 AON SOUTH AFRICA - PERSONNEL ......................................................................................... 32 ANNEXURE 1 ............................................................................................................................... 33 Transnet Principal Controlled Construction Insurance Programme Contract Award Declaration (Part A) and Contract Completion Declaration (Part B) ANNEXURE 2 ............................................................................................................................... 34 Incident Advice Form ANNEXURE 3 ............................................................................................................................... 35 Annual Contract Works / Contractors Public Liability / Lateral Support Policy Wording ANNEXURE 4 ............................................................................................................................... 36 Annual Contractors Public Liability Policy Wording "P

review

Cop

y Only

"

Page 144: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 2 -

Introduction

"Prev

iew C

opy O

nly"

Page 145: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 3 -

Introduction TRANSNET LIMITED insure all Projects / Contracts on a Principal Controlled Insurance Programme basis (including the Assembly and/or Erection of Plant and Machinery) in respect of Contract Works and Contractors Public Liability.

Philosophy of the programme Transnet Limited and its Operating Divisions and Specialist Units wish to control the risk exposures in

this regard.

Transnet Limited, as a large organization, bulk-buys - resulting in preferential rates and cover.

Simplified administration.

Eliminates potential problems which usually occur when individual Contractors are responsible to arrange separate insurance.

Includes the Contractor and/or Subcontractors as an insured party.

� It is therefore important that Tender and eventual Contract documents

reflect the fact that Transnet as the Principal (i.e. the Employer) arranges certain covers which incorporates cover on behalf of Contractor’s

� and / or Subcontractor’s. � The concept does not relieve the contracting parties of their

responsibilities for, amongst others, care of the works and liabilities to third parties

"Prev

iew C

opy O

nly"

Page 146: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 4 -

Insurance Responsibilities

"Prev

iew C

opy O

nly"

Page 147: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 5 -

Insurance Responsibilities

1. Cover arranged by Transnet as the Principal (Employer)

1.1 Insurance Cover Applicable To All Contracts 1.1.1 Contract Works Cover Covering fortuitous physical loss or damage to the

works, temporary works and materials for incorporation into the works whilst in transit and whilst at the contract site.

Limited to R100,000,000 any one contract. (Inclusive

of VAT)

1.1.2 Contractors Public Covering legal liability arising out of or connection with

Liability Cover the performance of the works on the contract site or

sites designated by the Principal for purposes of the performance of the contract.

Limited to R10,000,000 any one occurrence.

1.1.3 Riot / Strike Cover Provided by:

(Contract Works) SASRIA (South African Special Risks Insurance

Association) in respect of risks with RSA. NASRIA (Namibian Special Risks Insurance

Association) in respect of risks within Namibia.

1.2 Additional Insurances (Optional)

1.2.1 Marine Transit Cover Covering imports until delivered and checked on site.

1.2.2 Project Delay Cover Covering consequential financial exposures due to

delays following indemnifiable loss or damage to the works.

1.2.3 Removal of Lateral Support Covering legal liability incurred in respect removal of or

weakening of or interference with support to land or property or buildings adjacent to, on or in the vicinity of the Contract site.

Limit of indemnity R25,000,000 any one occurrence.

"Prev

iew C

opy O

nly"

Page 148: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 6 -

� The above information (including limits of insurance purchased) should

be clearly spelt out in Tender and eventual Contract documentation including the deductible (excess) which are applicable and the fact that Contractor’s and/or Subcontractor’s are responsible for the deductible.

2. Cover to be arranged by Contractor’s/Subcontractor’s All Contractor’s/Subcontractor’s still remain fully responsible to arrange insurance in respect of the

following:

As prescribed by the Compensation for Occupational Injuries and Diseases Act No. 130 of 1993 as amended.

Employers Common Law Liability.

Own plant, machinery, equipment and tools.

Motor Vehicles Liability.

Professional Indemnity (Defective Design).

� This should also be clearly spelt out in Tender and eventual Contract

documentation.

3. Cover to be arranged by Consulting Engineers, Architects & Other Professionals

Professional Indemnity (defects in Design, Plan or Specification). Please ensure that Professional Service Providers do not contract out of their liability in this regard.

(Please refer to Transnet Group Insurance for recommendation and approved limits).

"Prev

iew C

opy O

nly"

Page 149: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 7 -

Summary of Cover

General

"Prev

iew C

opy O

nly"

Page 150: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 8 -

Summary of Cover

The Insured Parties Transnet Limited and / or its Affiliated / Subsidiary / Associated Companies as Principal or Employer.

All Contractor’s undertaking work for or on behalf of the Principal in execution of the Contract.

All Subcontractor’s employed by the Contractor and all other Subcontractor’s (whether nominated or otherwise) engaged in the fulfillment of the Contractor.

To the extent required by any Contract or Agreement suppliers manufacturers vendors or other persons engaged on the contract sites but only to the extent of loss damage or liability originating at the Contract Site (other than while the Property Insured is in transit) arising out of the performance of their Contract Site obligations.

Cover Contract Works – as detailed herein.

Contractors Public Liability – as detailed herein.

Insured Contracts

All contracts up to a maximum value of R100,000,000 (Inclusive of VAT)any one contract.

Limited to a maximum contract period of 36 months followed by a maximum Defects Liability / Maintenance period of 12 months.

Excluded Contracts Where the contract value exceeds R100,000,000 (Inclusive of VAT)

Where the contracted duration of the contract exceeds 36 months.

Where contracted Defects Liability / Maintenance period exceeds 12 months.

Contracts involving harbor wet risks*, dams, tunneling, mining, shaft sinking, underground work, quarrying, alterations to water courses being River Diversions or Coffer Dams.

Contracts outside of the territorial limits.

* NOTE

Harbor Wet Risks defined as:-

“Harbor Wet Risks shall mean all work entailing or involving work in or upon water whether partially or fully submerged such as but not limited to quay walls, seawalls, caissons, breakwaters, jetties, piers, deepening widening and dredging of ports and other off shore risks”

"Prev

iew C

opy O

nly"

Page 151: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 9 -

Contracts involving construction and erection of Petrochemical Plant(s) but this exclusion is limited to contracts involving Petrochemical Manufacturing Plant such as Sasol and the like

On an existing airport runway or airstrip or in or on any aircraft.

Contract Site Any location upon which the Insured Contract(s) is to be executed or carried out as more fully defined in the Insured Contract(s) documents together with so much of the surrounding area as may be designated for the performance of the Insured Contract(s).

Territorial Limits The Republic of South Africa and to the extent permitted by the applicable Insurance Acts the territories of Lesotho, Namibia, Swaziland, Botswana, Zimbabwe and Mozambique. N.B. In terms of local legislation enacted in some of the above territories it is required that insurance cover be placed within their local markets. It is therefore important that the Broker be advised timeously (prior to Tender documents being issued) should any contracts, whether as Principal or Contractor, take place in any of the above territories. If Contracts are to take place in any territories not listed above, the Broker also needs to be advised of same at feasibility stage.

Cover Limitations / Warranties

Unsealed / Unprimed Base Course Unsealed / unprimed base course – cover limited to a maximum of 5,000 metres.

Open Trench Open trench – cover limited to a maximum indemnity of 5,000 metres.

� It is essential that the above limitations are brought to the

attention of Contractor’s. Where this restriction is not practical, specific arrangements for cover can be made with Underwriters. They will, however, require detailed underwriting information and an additional premium may be charged.

"Prev

iew C

opy O

nly"

Page 152: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 10 -

Laid Pipes

Pipes with a diameter not exceeding 500mm, and all pipes intended for the transportation of Petroleum Products or Fuel Gasses irrespective of diameter, are to be end capped on the termination of each days work to avoid ingress of mud silt water debris detritus and the like.

Pipes with a diameter exceeding 500mm are to be capped on the termination of each days work with steel mesh to allow ingress of water to avoid floatation but avoiding ingress of large debris or detritus.

NB If above not conformed with cover is forfeited.

Rail Track Re-Profiling

- The maximum speed of any grinding unit shall not exceed 11.00km per hour.

- All Guards, Curtains, Spark Deflectors are to be in place and correctly positioned prior to the commencement of each grind.

- Maximum grinding distance in any one execution shall not exceed 10,000 metres.

- Any changes in prevailing weather conditions must be recorded and appropriate remedial action taken.

- The Insured Parties are to comply with all Fire Fighting requirements as set out in the Project Specification For Track Maintenance With An On Track Grinding / Profiling Machine and any amendments / deviations to this Project Specification are to be advised to the Insurer prior to work being undertaken.

NB If above not conformed with cover is forfeited.

� It is essential that the above Warranties are brought to the

attention of Contractor’s.

Used Plant – Basis of Loss Settlement

Insured property which has operated under service conditions prior to attachment of cover:-

Up to 5 years – cost of repair / reinstatement / replacement.

In excess of 5 years - agreed value (calculated on basis of each life year (or part thereof) on present day New Replacement Value reduced proportionally over 20 years subject to residual of 20%).

"Prev

iew C

opy O

nly"

Page 153: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 11 -

Claims Reporting All incidents that could give rise to claim under the Principal Controlled Insurances,

HAVE TO BE reported to the Broker / Insurer within a 90 (Ninety) day period.

Failing this, all benefits in terms of the Policy shall be voidable from date of occurrence.

All claims must be registered in terms of requirements applicable to Risk Console unique claim number condition.

� It is essential that the above Condition is brought to the attention

of Contractors in Tender / Contract Documents.

Rating Structure The rates include both Contract Works and Contractors Public Liability cover per current policy limits,

terms and conditions.

Minimum premium requirement are:- Track Re-profiling R8,000

Burning of Fire Breaks R8,000

Chemical Vegetation Control R4,000

Vegetation Rehabillitation R4,000

Ballast Tamping R4,000

Geotechnical & Exploratory R4,000

All Other R6,000

SASRIA R 500

(Above are inclusive of VAT)

To extend the contract period beyond 36 months will attract an additional premium.

(See Administrative Procedures herein).

"Prev

iew C

opy O

nly"

Page 154: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 12 -

Summary of Cover

Contract Works Insurance

"Prev

iew C

opy O

nly"

Page 155: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 13 -

1. Contract Works Insurance

Synopsis of Cover Fortuitous Physical loss of or damage: During dismantling of property in connection with the Insured Contracts.

Whilst in transit, including loading and unloading, or whilst temporarily stored at any premises en route to or from The Contract Site within the Territorial Limits;

During the preparation of The Contract Site and thereafter until the Property Insured has been officially accepted by the Employer and becomes his responsibility by means of a Notice of Completion Certificate or similar evidence of legal transfer of risk in the whole or permanent works under the Insured Contract to the Employer;

Where testing and commissioning of Property Insured is conducted by the Employer “completion” for purposes of this insurance to occur only after successful completion of all testing and commissioning of the whole of the permanent works under the Insured Contract;

Where the permanent property insurance arranged by the Employer indemnify the Insured for completed portions of the Property Insured prior to completion of the whole of the permanent works under the Insured Contract, this insurance in respect of such completed portions of the Property Insured shall cease except as provided below;

Work uncompleted or outstanding in terms of any certificate of completion, certificate of handover or similar document shall continue to be insured until its completion and the inception of the Contractual Defects Liability or Maintenance Period (as may be described in the Insured Contract) for such uncompleted or outstanding work where after the provisions of (g) below shall apply in respect of such work;

During the Contractual Defects Liability or Maintenance Period (as may be described in the Insured Contract) pertaining to any part of the permanent works but only in respect of loss or damage:

i) arising from a cause occurring prior to commencement of such period of maintenance or defects liability period

ii) arising from any act or omission of the Insured their Servants, Agents, Suppliers or Subcontractors in pursuance of the Insured’s obligations.

for which the Insured Contractor is responsible under the Contract. "P

review

Cop

y Only

"

Page 156: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 14 -

Contract Period Limitation

Maximum Contract period 36 months

Maximum Defects Liability / Maintenance Period 12 Months

Limits of indemnity

Contract Works (Any One Contract) R100,000,000

Work done on Marine vessels R10,000,000

Surrounding Property R10,000,000

Surrounding Property – Worked Upon R50,000,000

Surrounding Property – Watercraft R10,000,000

Removal to Gain Access R1,000,000

Documentation R100,000

Debris Removal R2,500,000

Claims Preparation Costs R500,000

Maximum testing / commissioning period 60 days

Maximum un-sealed / un-primed base course limitation 5,000 metres

Maximum open trench limitation 5,000 metres

"Prev

iew C

opy O

nly"

Page 157: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 15 -

Deductibles The deductible (excess) is the amount which the Contractor and/or Sub-Contractor is responsible for and this obligation must be reflected in the Tender and/or Contract Documents and the responsibility for same made clear. The deductibles apply to each and every occurrence and in respect of all Contracts. The deductibles are: Loss or damage arising out of major perils (where the term shall include storm, rain, tempest, wind, flood, theft and / or malicious damage, subsidence, collapse, earthquake, testing, commissioning R 25,000 Loss or damage arising from any other cause R 15,000 Removal of Debris R 25,000 Loss or damage to Surrounding Property R 25,000 Loss or damage to Surrounding Property – Worked Upon R 75,000 Loss or damage to Documentation R 5,000 Road Reserve / Servitude R250,000

"Prev

iew C

opy O

nly"

Page 158: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 16 -

All Contracts Entailing Trenching and / or Layer Works Following additional Deductibles apply over and above the aforestated deductibles: - i.e. in excess of 1,000 metres Up to a maximum of 3,000metres 20% of loss / minimum R50,000 Up to a maximum of 5,000metres 20% of loss / minimum R100,000

� It is essential that this is brought to the attention of Contractor’s.

Where this restriction is not practical, specific arrangements for cover can be made with underwriters. They will, however, require detailed underwriting information and an additional premium may be charged.

Property Insured The actual Contract Works and all material intended for incorporation into the Works (including Free Issue Material* the value of which has to be included in the Contract Value declared) and Temporary Works. N.B.

Temporary works does not include mobile plant, constructional aids, equipment, structures or works (not being part of the permanent works) which are not intended to be removed from the Contract Site on completion of the Contract (other than scaffolding shuttering and formwork as well as construction equipment specifically designed and/or constructed for the Insured Contract and which is not intended for immediate re-use on another contract) or have no residual value at completion of the Contract (other than scrap value), solely due to their specialised nature.

* Note: Where Transnet for the purposes of the Contract issues materials 'free of charge' to the Contractor such materials shall be and remain the property of the Transnet. Free Issue Material shall mean any material provided by or on Transnet's behalf which is to be used in the provision of the Service or incorporated into the Contract.

Main Exceptions The amount of the policy deductible.

Loss or damage of money or the like.

Aircraft, waterborne vessels or craft.

Construction plant, tools or equipment.

Losses by disappearance / shortage discovered by taking of routine inventory.

Defective material workmanship design plan or specification (but resultant damage covered).

"Prev

iew C

opy O

nly"

Page 159: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 17 -

Cost of re-design, improvement, betterment or alteration.

Consequential loss.

Liquidated damages or penalties for delay in connection with guarantee or performance or efficiency.

"Prev

iew C

opy O

nly"

Page 160: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 18 -

Air transit (unless in territorial limits).

Ocean transit or whilst in storage thereafter (unless immediately inspected by an independent party after offloading from vessel).

During the Contractual Defects Liability or Maintenance Period (as may be described in the Insured Contract) pertaining to any part of the permanent works but only in respect of loss or damage:

i) arising from a cause occurring prior to commencement of such period of maintenance or defects liability period

ii) arising from any act or omission of the Insured his Servants or Agents, in the course of the work carried out in pursuance of the Insured’s obligations with regard to maintenance under the Contract.

Wear, tear, gradual deterioration rust, corrosion or oxidation and normal up-keep.

Electrical or mechanical breakdown or explosion to machinery or plant which has operated under load conditions prior to commencement of the Insured Contract or which has occurred after the Testing / Commissioning Period specified in the Policy.

Damage to any property insured due to ingress of mud, silt, water, debris unless pipe ends have been sealed on termination of each days work by means of end caps as prescribed in the policy.

Damage to any unsealed / unprimed or base course in excess of limitations as stated in the policy.

Damage to any open trench in excess of the limitations as stated in the policy.

War, asbestos and nuclear risks.

Sinking (whether partial or in whole) of any watercraft arising out of or in consequence of any work undertaken below the load line ( international load line / plimsoll line).

"Prev

iew C

opy O

nly"

Page 161: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 19 -

Summary of Cover

Contractors Public Liability Insurance

"Prev

iew C

opy O

nly"

Page 162: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 20 -

2. Contractors Public Liability Insurance

Insured Contracts

All contracts up to a maximum value of R100,000,000 (Inclusive of VAT) any one contract.

Limited to a maximum contract period of 36 months followed by a maximum Defects Liability / Maintenance period of 12 months.

Synopsis of Cover Legal Liability to pay as compensation for and in consequence of: Accidental death of or injury to or illness or disease contracted by any person.

Accidental loss of / or physical damage to tangible property.

Occurring during the period of insurance and arising out of or in connection with the performance of the Insured Contract(s). First Party Property* Extension will apply to the Lateral Support policy extensions.

* Note: Coverage for the insured's personal and real property.

Type Of Contract All Contracts undertaken including:- Chemical Vegetation Control

Vegetation Rehabilitation

Ballast Tamping

Rail Track Re-profiling including the contract works

Burning of Fire Breaks

Geotechnical and Exploratory Works

N.B.

The above noted contract types attract specific differentiated rates and are insured by way of a separate policy.

"Prev

iew C

opy O

nly"

Page 163: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 21 -

Limits Of Indemnity

Contractors Public Liability R10,000,000 any one occurrence / unlimited for the Period of Insurance

Removal of Lateral Support R25,000,000 unlimited for the Period of Insurance (provided on request only

Statutory Legal Defence Costs R500,000 any one occurrence

Arrest / Assault / Defamation R500,000 any one occurrence

Emergency Medical Expenses R500,000 any one occurrence

Prevention of Access R500,000 any one occurrence

Trespass / Nuisance R500,000 any one occurrence

Claims Preparation Costs R500,000 any one occurrence

Deductibles The deductible (excess) is the amount which the Contractor and/or Sub-Contractor is responsible for and this obligation must be reflected in the Tender and/or Contract Documents and the responsibility for same made clear. The deductibles apply to each and every occurrence and in respect of all Contracts. The deductibles are: Loss of or damage to public utilities R25,000

Spread of fire R250,000

Spread of fire – track re-profiling R250,000

Loss of or damage to any other property R25,000

Loss of or damage arising from removal of lateral support R25,000

Loss of or damage arising from the burning of fire breaks R250,000

Loss of or damage arising out of vegetation control R250,000 ` including but not limited to the use of pesticides and or herbicides

"Prev

iew C

opy O

nly"

Page 164: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 22 -

Main Exceptions The amount of the policy deductible.

Death or injury to own employees.

Motor vehicle liabilities under legislation or as defined in Multi-lateral Motor Vehicles Accident Fund No. 93 of 1989 as amended.

Claims in connection with ownership or use of aircraft or watercraft.

Property belonging to the Insured or in his care custody and control (as defined in the Policy).

Property forming part of Contract Works.

Liquidated damages or penalties for delays or in respect of performance or efficiency guarantees.

Liability arising out of defects in workmanship materials design plan or specification in any part of the Property insured.

Arising from or in connection with design plan or specification.

Gradual pollution and contamination.

Sudden unintended and unforeseen seepage, pollution or contamination including the cost of removing, nullifying or cleaning up in respect of both ocean and harbour going watercraft outside of dry dock.

After completion and handover (inclusive of the contractual Defects / Maintenance period).

Punitive damages.

Ownership hiring or leasing of any airport or airstrip.

War, asbestos and nuclear risks.

Cover Limitations / Warranties

Rail Track Re-Profiling

- The maximum speed of any grinding unit shall not exceed 11.00km per hour.

- All Guards, Curtains, Spark Deflectors are to be in place and correctly positioned prior to the commencement of each grind.

- Maximum grinding distance in any one execution shall not exceed 10,000 metres.

- Any changes in prevailing weather conditions must be recorded and appropriate remedial action taken.

- The Insured Parties are to comply with all Fire Fighting requirements as set out in the Project Specification For Track Maintenance With An On Track Grinding / Profiling Machine and any amendments / deviations to this Project Specification are to be advised to the Insurer prior to work being undertaken.

NB: Failure to thoroughly pre-plan and document the safety measures to be adopted with specific regards tp

the incidence of fires being initiated during the execution of the work will invalidate indemnity provided in respect of fire arising out of track re-profiling works.

"Prev

iew C

opy O

nly"

Page 165: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 23 -

� It is essential that this requirement is brought to the attention of

Contractor’s. Where this restriction is not practical, specific arrangements for cover can be made with underwriters. They will, however, require detailed underwriting information and an additional premium may be charged.

Other Limitations

Indemnity for removal of lateral support is limited to R25,000,000.

If a higher limit of indemnity is required, the Employers Insurance Broker’s personnel needs to be advised and underwriting information will need to be provided in advance (i.e prior to Tender stage) and this will entail an additional premium.

"Prev

iew C

opy O

nly"

Page 166: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 24 -

Administrative Procedures

"Prev

iew C

opy O

nly"

Page 167: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 25 -

Administrative Procedures

Arranging Insurance cover The Operating Divisions and Specialist Units must Prior to the commencement of each Contract:- Complete the Declaration Form per Part A as per Annexure 1 herein.

Date and sign the Declaration Form.

Submit the Declaration Form to the Broker.

In addition, if the Declaration is being submitted after the commencement date, a separate letter is required stating that, after specific enquiry, The Insured is not aware of any incidents which may give rise to claim/s under this policy. (No Known Incidents Declaration).

On receipt of late declarations which are not accompanied by a “No Known Incidents Declaration”, the Insurance declaration will not be accepted and no cover will be in force.

Record the Declaration on the Contract Monthly Register and submit this Register at the end of each month to Transnet Group Insurance and the Broker.

On receipt of the Declaration Form the Broker will submit it to the Insurer and the following documents will be issued and provided to the Operating Divisions and Specialist Units:- An Insurance Certificate and a SASRIA Coupon evidencing cover.

A Debit Note in respect of the premiums due (based on agreed rates).

NB In terms of SASRIA Regulations, where the Contract Value exceeds R2 million, the physical address of the contract is mandatory. If no physical address i.e. where Track is being worked upon, the start and end points are required.

Prior to the expiry of each Declarations estimated completion date:- Confirm to the Broker that the contract will be completed on time.

On completion submit to the Broker a Declaration of the final contract value per Part B as per Annexure 1 herein.

NB If the original completion date is not going to be achieved, the period of insurance on the Declaration document will need to be extended and the Broker needs to be notified prior to original completion date.

The Operating Divisions and Specialist Units (prior to the expiry date of the certificate period) has to advise the Broker in writing to extend the period of insurance and provide the new estimated completion date.

NB If a completion date needs to be extended and the Broker is not advised prior to the original completion date, all SASRIA cover will cease on the originally declared completion date as there is no hold covered arrangement with SASRIA.

A new SASRIA Coupon will then only be issued for the extension period from the date when

the Insurer is advised in writing by the Broker. Under these circumstances the new SASRIA Coupon will be subject to an additional premium,

subject to the minimum premium.

"Prev

iew C

opy O

nly"

Page 168: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 26 -

This process needs to be followed by the Operating Divisions and Specialist Units until the time of completion is achieved. Once the Contract has been completed:- The Operating Divisions and Specialist Units have to declare the final contract value to the Broker per

Part B as per Annexure 1 herein.

The deposit premium will then be adjusted accordingly.

Failure by the Operating Divisions and Specialist Units to conform to the above procedure will result in cover being voided.

"Prev

iew C

opy O

nly"

Page 169: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 27 -

Contracts that require specific arrangements All contracts that fall outside the scope of this Principal Controlled Insurance Programme have to be advised to the Broker prior to Tender and specific “One Off” cover will need to be negotiated. These will be: Where the Contract Value exceeds R100,000,000 (Inclusive of VAT)

Where the Contracted period exceeds 36 months.

Where the Contracted Defects Liability Maintenance period exceeds 12 months.

Other excluded Contracts as described on Page 8 /9 herein.

Contracts involving harbor wet risks*, dams, tunneling, mining, quarrying, shaft sinking, underground work, alterations to water courses being river diversions or coffer dams.

Contracts outside of the Territorial Limits.

In this regard contact the Employers Insurance Broker’s personnel as detailed on Page 33 herein. Contracts where cover limitations will be exceeded or where cover warranties cannot be complied with need to be discussed with the Employers Insurance Broker’s personnel prior to contract award date to enable the Broker to make specific arrangements with Underwriters. This will however require detailed Underwriting Information and an additional premium may be charged.

� In order to ensure that Contractor’s and site staff are aware of

procedures a copy of this Procedure Manual must be supplied to the contract administrators and each Contractor on award of contract..

* Note: Harbour Wet Risks shall mean all work entailing or involving work in or upon water whether partially or fully submerged such as but not limited to quay walls, wharfs seawalls, caissons, breakwaters, jetties, piers, deepening or widening and dredging of ports and other off-shore risks

"Prev

iew C

opy O

nly"

Page 170: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 28 -

Important Considerations

"Prev

iew C

opy O

nly"

Page 171: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 29 -

Important Considerations Cognizance must be taken of the following important considerations:- For contracts involving assembly or erection of plant and machinery or repairs maintenance or

overhaul thereto, THE FULL NEW REPLACEMENT VALUE OF THE PLANT/MACHINERY involved must be declared AND NOT ONLY THE CONTRACT VALUE, for example.:

� Cranes (repairs or final assembly)

� Machinery being moved

� Maintenance or new works on existing Portnet Vessels whilst moored or in dry dock.

Specific arrangements are in place to cover certain contracts where the exposure to own damage (damage to the works) is nil or negligible, but where a high third party liability exposure exists. For example:

� Chemical control of vegetation

� Vegetation rehabilitation

� Ballast tamping

� Re-profiling of Track

� Burning of Fire Breaks

� Geotechnical and Exploratory Works

Contracts of this nature must be clearly identified on the Declaration Form.

Contract value must include the replacement value of any Free Issue Material provided.

VAT must be added to all contract value declarations in order to comply with local legislation.

All policy limits and deductibles are Vat inclusive.

"Prev

iew C

opy O

nly"

Page 172: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 30 -

Claims Procedure

"Prev

iew C

opy O

nly"

Page 173: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 31 -

Claims Procedure In the event of any incident or occurrence, which is likely, to give rise to a claim under the Insurance arranged by the Principal the following procedures shall be adhered to in addition to any statutory or other requirements contained in the Contract. All incidents that could give rise to claim under the Principal Controlled Insurances, HAVE TO BE reported to the Broker / Insurer within a 90 (Ninety) day period from date of loss. IMMEDIATELY advise Aon Construction & Engineering Risks (Attention Sandra Botha). At the same time complete the Incident Advice Form (Annexure 2 herein) and submit to Aon Construction & Engineering Risks. Losses involving theft or malicious damage must be reported to the police and a police reference

number obtained and recorded.

The Employer, Contactor(s) or Sub-Contractor(s) shall allow free access to Insurers’ Loss Adjuster(s) and / or Employer’s Insurance Broker for the purpose of investigation and assessing the loss or damage.

The Employer, Contractor(s) shall not deal direct with the Insurers other than by co-operating with their Loss Adjuster(s) and / or the Employers Insurance Broker.

No Admission of Liability shall be made by the Employer, Contractor(s) or Sub-Contractor(s) in the event of damage, loss or injury to third party property or persons.

Letters from claimants should be passed to Aon Construction & Engineering Risks as soon as possible via the Employer if necessary.

In the event of immediate repairs being necessary in the interest of safety, the Contractors may with the Employer’s permission proceed with such repairs.

The Employer shall immediately advise Sandra Botha at Aon Construction & Engineering Risks.

Other than in the circumstances described above the Contractor shall not proceed with the making good of any loss without the prior authorization of the Employer who shall advise the Insurer’s appointed Loss Adjuster(s) and Sandra Botha of Aon Construction & Engineering Risks.

Upon commencement of the making good of any loss, the Contractor shall keep separate records of the costs involved in making good such loss and these records must be authenticated by the Employer for submission to the Insurer’s or their Loss Adjuster(s). Such records shall include, inter alia, the entire cost of labour, materials, transport and equipment.

The basis upon which the Insurers will indemnify loss or damage is the cost of repair or replacement of the loss or damage including, inter alia, transport and overheads.

On completion of the making good of any loss the records of the costs involved having been authenticated by the Employer shall be sent to the Insurer’s via their Loss Adjuster(s) and copied to Aon Construction & Engineering Risks (Mrs. Sandra Botha) for processing. "P

review

Cop

y Only

"

Page 174: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 32 -

Upon the amount of the loss or damage being agreed upon by the Insurer’s Loss Adjuster(s) and the Contractor, an “Agreement of Loss” form will be signed by the Contractor and Employer.

The amount agreed upon by the Insurers, the Contractor and the Employer shall be paid by the Insurers to the Employer net of the deductible, who will arrange for the payment to be made to the Contractor as appropriate after deduction of the first amount payable.

� All incidents which could give rise to a claim under the insurances

arranged by the Principal / Employer must be notified to the Broker without delay, per the procedures set out above

"Prev

iew C

opy O

nly"

Page 175: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 33 -

Aon South Africa Personnel

Construction and Engineering Division

"Prev

iew C

opy O

nly"

Page 176: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 34 -

Aon South Africa Personnel Construction and Engineering Division Aon South Africa personnel are at all times available for advice, please feel free to contact :- ▪ George Davis Senior Accounts Executive Tel No. (011) 944 7103 Fax No. (086) 505 9558 E-Mail [email protected] ▪ Judy Bath Account Administrator Tel No. (011)944 7053 Fax No. (086)505 9553 E-Mail [email protected] ▪ Sandra Botha Claims Manager Tel No. (011)944-7118 Fax No. (086)556 7169 E-Mail [email protected]

"Prev

iew C

opy O

nly"

Page 177: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 35 -

Annexure 1

Transnet Principal Controlled Construction Insurance Programme Contract Award Declaration (Part A) And Contract Completion Declaration (Part B)

"Prev

iew C

opy O

nly"

Page 178: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

TRANSNET PRINCIPAL CONTROLLED INSURANCE PROGRAMME CONTRACT DECLARATION

CONTRACT NUMBER…………………………………………………………… PURCHASE ORDER NUMBER…………………………………………………

Send to Aon South Africa (Pty) Ltd From (Operating Unit/Specialist Div)……………………….. Construction and Engineering Postal Address …………………………………………….. PO Box 1874 ……………………………………………. Parklands .......................................................... 2121 Represented by .......................................................... Attention : Judy Bath E-Mail Address .......................................................... Tel No. (011) 944-7053 Tel No. .......................................................... Fax No. 086 505 9553 Fax No. .......................................................... E-Mail: [email protected]

PART A – CONTRACT AWARD INFORMATION

TYPE OF CONTRACT MARK WITH AN ‘X’ IF APPLICABLE:

LONG TERM MAINTENANCE / MULTIPLE WORKS CONTRACT with a SERVICE LEVEL AGREEMENT

OTHER

NAME OF CONTRACTOR

CONTRACT AWARD DATE

CONTRACT COMMENCEMENT DATE

EXPECTED CONTRACT COMPLETION DATE

DESCRIPTION OF CONTRACT WORKS

PHYSICAL ADDRESS WHERE CONTRACT IS TAKING PLACE (COMPULSARY FOR ALL CONTRACTS R2M AND OVER)

MAINTENANCE PERIOD (MONTHS)

CONTRACT VALUE AT AWARD

IF PLANT AND MACHINERY INCLUDE REPLACEMENT VALUE

ESTIMATED VALUE OF FREE ISSUED SUPPLIED TO CONTRACTOR

DOES THIS CONTRACT ENTAIL WORK IN RESPECT OF THE FOLLOWING CATEGORIES WHERE THE EXPOSURE TO OWN DAMAGE (DAMAGE TO WORKS) IS NIL OR NEGLIGIBLE [I] CHEMICAL CONTROL OF VEGETATION YES/NO [II] VEGETATION REHABILITATION YES/NO [III] BALLAST TAMPING YES/NO [IV] TRACK RE-PROFILING YES/NO [V] BURNING OF FIRE BREAKS YES/NO [VI] GEOTECHNICAL AND EXPLORATORY WORKS YES/NO

OPTIONAL INSURANCE REQUIRED

[I] IS REMOVAL OF LATERAL SUPPORT COVER REQUIRED? YES/NO [II] DOES THIS CONTRACT EVIDENCE AN EXPOSURE WHICH CAN BE COVERED BY PROJECT DELAY INSURANCE? YES/NO [III] WILL THE EMPLOYER/CONTRACTOR/SUB-CONTRACTOR MAKE ANY DIRECT IMPORTS OF REQUIREMENTS FOR THE CONTRACT THAT REQUIRE MARINE IMPORT INSURANCE? YES/NO IF SO DETAILS NEED TO BE PROVIDED TO THE BROKER SO THAT THIS FORM OF COVER CAN BE ARRANGED SIGNATURE …………………………………………………… DATE: ………………………………………………

"Prev

iew C

opy O

nly"

Page 179: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

TRANSNET PRINCIPAL CONTROLLED INSURANCE PROGRAMME CONTRACT COMPLETION DECLARATION

ORIGINAL CONTRACT NO. …………….. PURCHASE ORDER NO. …………………

PART B – CONTRACT COMPLETION DECLARATION

CONTRACT NUMBER

TITLE OF CONTRACT

CONTRACT COMPLETION DATE

ENDORSEMENT/CERTIFICATE NUMBER

EXPIRY OF MAINTENANCE PERIOD

FINAL CONTRACT VALUE

ACTUAL VALUE OF FREE ISSUE SUPPLIED TO CONTRACTOR

SIGNATURE:…………………………………………… DATE:……………………………………………………………..

"Prev

iew C

opy O

nly"

Page 180: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Aon Transnet PCI-Procedure Manual 2010 - 34 -

Procedure Manual Principal Controlled Insurance 2010

Annexure 2

Incident Advice Form

ALL INCIDENTS HAVE TO BE REPORTED WITHIN 90 DAYS OF OCCURRENCE

"Prev

iew C

opy O

nly"

Page 181: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

TRANSNET PRINCIPAL CONTROLLED INSURANCE PROGRAMME

INCIDENT ADVICE FORM TRANSNET UNIQUE CLAIM NUMBER ……………………………….....

Send to Aon South Africa (Pty) Ltd Construction and Engineering PO Box 1874 Parklands From .......................................................... 2121 Represented by .......................................................... Attention : Sandra Botha Tel No. (011) 944 7118 Tel No. .......................................................... Fax No. (086) 556 7169 Fax No. .......................................................... E-Mail: [email protected]

PRINCIPAL (PER CONTRACT DOCUMENT

CONTRACT NUMBER

ORIGINAL DECLARATON NO.

TITLE OF CONTRACT

ORIGINAL CONTRACT COMMENCEMENT DATE

DATE OF LOSS OR DAMAGE

DATED REPORTED TO SITE AGENT

REPORTED BY

REPORTED TO BY

DATE

LOCALITY OF INCIDENT

DETAILS OF HOW THE LOSS OR DAMAGE OCCURRED

DETAILS AND NATURE OF LOSS OR DAMAGE TO CONTRACT WORKS / TO THIRD PARTY PROPERTY

DETAILS OF OTHER DEATH OR INJURY TO PARTIES

ESTIMATED COST (SEPARATE RECORDS OF ALL COSTS MUST BE KEPT)

WHO OR WHAT APPEARS TO BE RESPONSIBLE FOR THE CAUSE OF THE LOSS / DAMAGE

PERSON WHOM ASSESSOR SHOULD CONTACT DESIGNATION:

TELEPHONE (LANDLINE) CELLPHONE NO. E-MAIL ADDRESS

ALL INCIDENTS HAVE TO BE REPORTED WITHIN 90 DAYS OF OCCURRENCE SIGNED BY: ………………………………………………………… SIGNATURE: ………………………………………….. COMPANY: ………………………………………………………. DATE: …………………………………………………..

"Prev

iew C

opy O

nly"

Page 182: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Annexure 3

Annual Contract Works & Contractors Public Liability And Lateral Support Policy Wording

"Prev

iew C

opy O

nly"

Page 183: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Aon Transnet-PCI-Procedure Manual 2010 -36 -

Annexure 4

Annual Contractors Public Liability Policy Wording

In respect of Contracts entailing:-

■ Chemical Vegetation Rehabilitation

■ Vegetation Rehabilitation

■ Ballast Tamping

■ Rail Track Re-Profiling

■ Burning of Fire Breaks

■ Geotechnical and Exploratory Works

"Prev

iew C

opy O

nly"

Page 184: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

LindequeJ

[Pick the date]

TRANSNET LIMITED

EXECUTIVE SUMMARY 2010/2011

As at 1 April 2010

Transnet Procedure Manual Contract Works / Contractors Public Liability

Principal Controlled Insurance 2010 /2011

"Prev

iew C

opy O

nly"

Page 185: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Index

INTRODUCTION............................................................................................................................. 3 INSURANCE RESPONSIBILITIES ................................................................................................. 5 SUMMARY OF COVER - GENERAL.............................................................................................. 8 SUMMARY OF COVER - CONTRACT WORKS INSURANCE..................................................... 12 SUMMARY OF COVER - CONTRACTORS PUBLIC LIABILITY INSURANCE............................ 18 ADMINISTRATIVE PROCESS ..................................................................................................... 23 IMPORTANT CONSIDERATIONS................................................................................................ 26 CLAIMS PROCEDURE................................................................................................................. 28 AON SOUTH AFRICA - PERSONNEL ......................................................................................... 32 ANNEXURE 1 ............................................................................................................................... 33 Transnet Principal Controlled Construction Insurance Programme Contract Award Declaration (Part A) and Contract Completion Declaration (Part B) ANNEXURE 2 ............................................................................................................................... 34 Incident Advice Form ANNEXURE 3 ............................................................................................................................... 35 Annual Contract Works / Contractors Public Liability / Lateral Support Policy Wording ANNEXURE 4 ............................................................................................................................... 36 Annual Contractors Public Liability Policy Wording "P

review

Cop

y Only

"

Page 186: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 2 -

Introduction

"Prev

iew C

opy O

nly"

Page 187: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 3 -

Introduction TRANSNET LIMITED insure all Projects / Contracts on a Principal Controlled Insurance Programme basis (including the Assembly and/or Erection of Plant and Machinery) in respect of Contract Works and Contractors Public Liability.

Philosophy of the programme Transnet Limited and its Operating Divisions and Specialist Units wish to control the risk exposures in

this regard.

Transnet Limited, as a large organization, bulk-buys - resulting in preferential rates and cover.

Simplified administration.

Eliminates potential problems which usually occur when individual Contractors are responsible to arrange separate insurance.

Includes the Contractor and/or Subcontractors as an insured party.

� It is therefore important that Tender and eventual Contract documents

reflect the fact that Transnet as the Principal (i.e. the Employer) arranges certain covers which incorporates cover on behalf of Contractor’s

� and / or Subcontractor’s. � The concept does not relieve the contracting parties of their

responsibilities for, amongst others, care of the works and liabilities to third parties

"Prev

iew C

opy O

nly"

Page 188: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 4 -

Insurance Responsibilities

"Prev

iew C

opy O

nly"

Page 189: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 5 -

Insurance Responsibilities

1. Cover arranged by Transnet as the Principal (Employer)

1.1 Insurance Cover Applicable To All Contracts 1.1.1 Contract Works Cover Covering fortuitous physical loss or damage to the

works, temporary works and materials for incorporation into the works whilst in transit and whilst at the contract site.

Limited to R100,000,000 any one contract. (Inclusive

of VAT)

1.1.2 Contractors Public Covering legal liability arising out of or connection with

Liability Cover the performance of the works on the contract site or

sites designated by the Principal for purposes of the performance of the contract.

Limited to R10,000,000 any one occurrence.

1.1.3 Riot / Strike Cover Provided by:

(Contract Works) SASRIA (South African Special Risks Insurance

Association) in respect of risks with RSA. NASRIA (Namibian Special Risks Insurance

Association) in respect of risks within Namibia.

1.2 Additional Insurances (Optional)

1.2.1 Marine Transit Cover Covering imports until delivered and checked on site.

1.2.2 Project Delay Cover Covering consequential financial exposures due to

delays following indemnifiable loss or damage to the works.

1.2.3 Removal of Lateral Support Covering legal liability incurred in respect removal of or

weakening of or interference with support to land or property or buildings adjacent to, on or in the vicinity of the Contract site.

Limit of indemnity R25,000,000 any one occurrence.

"Prev

iew C

opy O

nly"

Page 190: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 6 -

� The above information (including limits of insurance purchased) should

be clearly spelt out in Tender and eventual Contract documentation including the deductible (excess) which are applicable and the fact that Contractor’s and/or Subcontractor’s are responsible for the deductible.

2. Cover to be arranged by Contractor’s/Subcontractor’s All Contractor’s/Subcontractor’s still remain fully responsible to arrange insurance in respect of the

following:

As prescribed by the Compensation for Occupational Injuries and Diseases Act No. 130 of 1993 as amended.

Employers Common Law Liability.

Own plant, machinery, equipment and tools.

Motor Vehicles Liability.

Professional Indemnity (Defective Design).

� This should also be clearly spelt out in Tender and eventual Contract

documentation.

3. Cover to be arranged by Consulting Engineers, Architects & Other Professionals

Professional Indemnity (defects in Design, Plan or Specification). Please ensure that Professional Service Providers do not contract out of their liability in this regard.

(Please refer to Transnet Group Insurance for recommendation and approved limits).

"Prev

iew C

opy O

nly"

Page 191: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 7 -

Summary of Cover

General

"Prev

iew C

opy O

nly"

Page 192: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 8 -

Summary of Cover

The Insured Parties Transnet Limited and / or its Affiliated / Subsidiary / Associated Companies as Principal or Employer.

All Contractor’s undertaking work for or on behalf of the Principal in execution of the Contract.

All Subcontractor’s employed by the Contractor and all other Subcontractor’s (whether nominated or otherwise) engaged in the fulfillment of the Contractor.

To the extent required by any Contract or Agreement suppliers manufacturers vendors or other persons engaged on the contract sites but only to the extent of loss damage or liability originating at the Contract Site (other than while the Property Insured is in transit) arising out of the performance of their Contract Site obligations.

Cover Contract Works – as detailed herein.

Contractors Public Liability – as detailed herein.

Insured Contracts

All contracts up to a maximum value of R100,000,000 (Inclusive of VAT)any one contract.

Limited to a maximum contract period of 36 months followed by a maximum Defects Liability / Maintenance period of 12 months.

Excluded Contracts Where the contract value exceeds R100,000,000 (Inclusive of VAT)

Where the contracted duration of the contract exceeds 36 months.

Where contracted Defects Liability / Maintenance period exceeds 12 months.

Contracts involving harbor wet risks*, dams, tunneling, mining, shaft sinking, underground work, quarrying, alterations to water courses being River Diversions or Coffer Dams.

Contracts outside of the territorial limits.

* NOTE

Harbor Wet Risks defined as:-

“Harbor Wet Risks shall mean all work entailing or involving work in or upon water whether partially or fully submerged such as but not limited to quay walls, seawalls, caissons, breakwaters, jetties, piers, deepening widening and dredging of ports and other off shore risks”

"Prev

iew C

opy O

nly"

Page 193: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 9 -

Contracts involving construction and erection of Petrochemical Plant(s) but this exclusion is limited to contracts involving Petrochemical Manufacturing Plant such as Sasol and the like

On an existing airport runway or airstrip or in or on any aircraft.

Contract Site Any location upon which the Insured Contract(s) is to be executed or carried out as more fully defined in the Insured Contract(s) documents together with so much of the surrounding area as may be designated for the performance of the Insured Contract(s).

Territorial Limits The Republic of South Africa and to the extent permitted by the applicable Insurance Acts the territories of Lesotho, Namibia, Swaziland, Botswana, Zimbabwe and Mozambique. N.B. In terms of local legislation enacted in some of the above territories it is required that insurance cover be placed within their local markets. It is therefore important that the Broker be advised timeously (prior to Tender documents being issued) should any contracts, whether as Principal or Contractor, take place in any of the above territories. If Contracts are to take place in any territories not listed above, the Broker also needs to be advised of same at feasibility stage.

Cover Limitations / Warranties

Unsealed / Unprimed Base Course Unsealed / unprimed base course – cover limited to a maximum of 5,000 metres.

Open Trench Open trench – cover limited to a maximum indemnity of 5,000 metres.

� It is essential that the above limitations are brought to the

attention of Contractor’s. Where this restriction is not practical, specific arrangements for cover can be made with Underwriters. They will, however, require detailed underwriting information and an additional premium may be charged.

"Prev

iew C

opy O

nly"

Page 194: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 10 -

Laid Pipes

Pipes with a diameter not exceeding 500mm, and all pipes intended for the transportation of Petroleum Products or Fuel Gasses irrespective of diameter, are to be end capped on the termination of each days work to avoid ingress of mud silt water debris detritus and the like.

Pipes with a diameter exceeding 500mm are to be capped on the termination of each days work with steel mesh to allow ingress of water to avoid floatation but avoiding ingress of large debris or detritus.

NB If above not conformed with cover is forfeited.

Rail Track Re-Profiling

- The maximum speed of any grinding unit shall not exceed 11.00km per hour.

- All Guards, Curtains, Spark Deflectors are to be in place and correctly positioned prior to the commencement of each grind.

- Maximum grinding distance in any one execution shall not exceed 10,000 metres.

- Any changes in prevailing weather conditions must be recorded and appropriate remedial action taken.

- The Insured Parties are to comply with all Fire Fighting requirements as set out in the Project Specification For Track Maintenance With An On Track Grinding / Profiling Machine and any amendments / deviations to this Project Specification are to be advised to the Insurer prior to work being undertaken.

NB If above not conformed with cover is forfeited.

� It is essential that the above Warranties are brought to the

attention of Contractor’s.

Used Plant – Basis of Loss Settlement

Insured property which has operated under service conditions prior to attachment of cover:-

Up to 5 years – cost of repair / reinstatement / replacement.

In excess of 5 years - agreed value (calculated on basis of each life year (or part thereof) on present day New Replacement Value reduced proportionally over 20 years subject to residual of 20%).

"Prev

iew C

opy O

nly"

Page 195: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 11 -

Claims Reporting All incidents that could give rise to claim under the Principal Controlled Insurances,

HAVE TO BE reported to the Broker / Insurer within a 90 (Ninety) day period.

Failing this, all benefits in terms of the Policy shall be voidable from date of occurrence.

All claims must be registered in terms of requirements applicable to Risk Console unique claim number condition.

� It is essential that the above Condition is brought to the attention

of Contractors in Tender / Contract Documents.

Rating Structure The rates include both Contract Works and Contractors Public Liability cover per current policy limits,

terms and conditions.

Minimum premium requirement are:- Track Re-profiling R8,000

Burning of Fire Breaks R8,000

Chemical Vegetation Control R4,000

Vegetation Rehabillitation R4,000

Ballast Tamping R4,000

Geotechnical & Exploratory R4,000

All Other R6,000

SASRIA R 500

(Above are inclusive of VAT)

To extend the contract period beyond 36 months will attract an additional premium.

(See Administrative Procedures herein).

"Prev

iew C

opy O

nly"

Page 196: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 12 -

Summary of Cover

Contract Works Insurance

"Prev

iew C

opy O

nly"

Page 197: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 13 -

1. Contract Works Insurance

Synopsis of Cover Fortuitous Physical loss of or damage: During dismantling of property in connection with the Insured Contracts.

Whilst in transit, including loading and unloading, or whilst temporarily stored at any premises en route to or from The Contract Site within the Territorial Limits;

During the preparation of The Contract Site and thereafter until the Property Insured has been officially accepted by the Employer and becomes his responsibility by means of a Notice of Completion Certificate or similar evidence of legal transfer of risk in the whole or permanent works under the Insured Contract to the Employer;

Where testing and commissioning of Property Insured is conducted by the Employer “completion” for purposes of this insurance to occur only after successful completion of all testing and commissioning of the whole of the permanent works under the Insured Contract;

Where the permanent property insurance arranged by the Employer indemnify the Insured for completed portions of the Property Insured prior to completion of the whole of the permanent works under the Insured Contract, this insurance in respect of such completed portions of the Property Insured shall cease except as provided below;

Work uncompleted or outstanding in terms of any certificate of completion, certificate of handover or similar document shall continue to be insured until its completion and the inception of the Contractual Defects Liability or Maintenance Period (as may be described in the Insured Contract) for such uncompleted or outstanding work where after the provisions of (g) below shall apply in respect of such work;

During the Contractual Defects Liability or Maintenance Period (as may be described in the Insured Contract) pertaining to any part of the permanent works but only in respect of loss or damage:

i) arising from a cause occurring prior to commencement of such period of maintenance or defects liability period

ii) arising from any act or omission of the Insured their Servants, Agents, Suppliers or Subcontractors in pursuance of the Insured’s obligations.

for which the Insured Contractor is responsible under the Contract. "P

review

Cop

y Only

"

Page 198: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 14 -

Contract Period Limitation

Maximum Contract period 36 months

Maximum Defects Liability / Maintenance Period 12 Months

Limits of indemnity

Contract Works (Any One Contract) R100,000,000

Work done on Marine vessels R10,000,000

Surrounding Property R10,000,000

Surrounding Property – Worked Upon R50,000,000

Surrounding Property – Watercraft R10,000,000

Removal to Gain Access R1,000,000

Documentation R100,000

Debris Removal R2,500,000

Claims Preparation Costs R500,000

Maximum testing / commissioning period 60 days

Maximum un-sealed / un-primed base course limitation 5,000 metres

Maximum open trench limitation 5,000 metres

"Prev

iew C

opy O

nly"

Page 199: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 15 -

Deductibles The deductible (excess) is the amount which the Contractor and/or Sub-Contractor is responsible for and this obligation must be reflected in the Tender and/or Contract Documents and the responsibility for same made clear. The deductibles apply to each and every occurrence and in respect of all Contracts. The deductibles are: Loss or damage arising out of major perils (where the term shall include storm, rain, tempest, wind, flood, theft and / or malicious damage, subsidence, collapse, earthquake, testing, commissioning R 25,000 Loss or damage arising from any other cause R 15,000 Removal of Debris R 25,000 Loss or damage to Surrounding Property R 25,000 Loss or damage to Surrounding Property – Worked Upon R 75,000 Loss or damage to Documentation R 5,000 Road Reserve / Servitude R250,000

"Prev

iew C

opy O

nly"

Page 200: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 16 -

All Contracts Entailing Trenching and / or Layer Works Following additional Deductibles apply over and above the aforestated deductibles: - i.e. in excess of 1,000 metres Up to a maximum of 3,000metres 20% of loss / minimum R50,000 Up to a maximum of 5,000metres 20% of loss / minimum R100,000

� It is essential that this is brought to the attention of Contractor’s.

Where this restriction is not practical, specific arrangements for cover can be made with underwriters. They will, however, require detailed underwriting information and an additional premium may be charged.

Property Insured The actual Contract Works and all material intended for incorporation into the Works (including Free Issue Material* the value of which has to be included in the Contract Value declared) and Temporary Works. N.B.

Temporary works does not include mobile plant, constructional aids, equipment, structures or works (not being part of the permanent works) which are not intended to be removed from the Contract Site on completion of the Contract (other than scaffolding shuttering and formwork as well as construction equipment specifically designed and/or constructed for the Insured Contract and which is not intended for immediate re-use on another contract) or have no residual value at completion of the Contract (other than scrap value), solely due to their specialised nature.

* Note: Where Transnet for the purposes of the Contract issues materials 'free of charge' to the Contractor such materials shall be and remain the property of the Transnet. Free Issue Material shall mean any material provided by or on Transnet's behalf which is to be used in the provision of the Service or incorporated into the Contract.

Main Exceptions The amount of the policy deductible.

Loss or damage of money or the like.

Aircraft, waterborne vessels or craft.

Construction plant, tools or equipment.

Losses by disappearance / shortage discovered by taking of routine inventory.

Defective material workmanship design plan or specification (but resultant damage covered).

"Prev

iew C

opy O

nly"

Page 201: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 17 -

Cost of re-design, improvement, betterment or alteration.

Consequential loss.

Liquidated damages or penalties for delay in connection with guarantee or performance or efficiency.

"Prev

iew C

opy O

nly"

Page 202: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 18 -

Air transit (unless in territorial limits).

Ocean transit or whilst in storage thereafter (unless immediately inspected by an independent party after offloading from vessel).

During the Contractual Defects Liability or Maintenance Period (as may be described in the Insured Contract) pertaining to any part of the permanent works but only in respect of loss or damage:

i) arising from a cause occurring prior to commencement of such period of maintenance or defects liability period

ii) arising from any act or omission of the Insured his Servants or Agents, in the course of the work carried out in pursuance of the Insured’s obligations with regard to maintenance under the Contract.

Wear, tear, gradual deterioration rust, corrosion or oxidation and normal up-keep.

Electrical or mechanical breakdown or explosion to machinery or plant which has operated under load conditions prior to commencement of the Insured Contract or which has occurred after the Testing / Commissioning Period specified in the Policy.

Damage to any property insured due to ingress of mud, silt, water, debris unless pipe ends have been sealed on termination of each days work by means of end caps as prescribed in the policy.

Damage to any unsealed / unprimed or base course in excess of limitations as stated in the policy.

Damage to any open trench in excess of the limitations as stated in the policy.

War, asbestos and nuclear risks.

Sinking (whether partial or in whole) of any watercraft arising out of or in consequence of any work undertaken below the load line ( international load line / plimsoll line).

"Prev

iew C

opy O

nly"

Page 203: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 19 -

Summary of Cover

Contractors Public Liability Insurance

"Prev

iew C

opy O

nly"

Page 204: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 20 -

2. Contractors Public Liability Insurance

Insured Contracts

All contracts up to a maximum value of R100,000,000 (Inclusive of VAT) any one contract.

Limited to a maximum contract period of 36 months followed by a maximum Defects Liability / Maintenance period of 12 months.

Synopsis of Cover Legal Liability to pay as compensation for and in consequence of: Accidental death of or injury to or illness or disease contracted by any person.

Accidental loss of / or physical damage to tangible property.

Occurring during the period of insurance and arising out of or in connection with the performance of the Insured Contract(s). First Party Property* Extension will apply to the Lateral Support policy extensions.

* Note: Coverage for the insured's personal and real property.

Type Of Contract All Contracts undertaken including:- Chemical Vegetation Control

Vegetation Rehabilitation

Ballast Tamping

Rail Track Re-profiling including the contract works

Burning of Fire Breaks

Geotechnical and Exploratory Works

N.B.

The above noted contract types attract specific differentiated rates and are insured by way of a separate policy.

"Prev

iew C

opy O

nly"

Page 205: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 21 -

Limits Of Indemnity

Contractors Public Liability R10,000,000 any one occurrence / unlimited for the Period of Insurance

Removal of Lateral Support R25,000,000 unlimited for the Period of Insurance (provided on request only

Statutory Legal Defence Costs R500,000 any one occurrence

Arrest / Assault / Defamation R500,000 any one occurrence

Emergency Medical Expenses R500,000 any one occurrence

Prevention of Access R500,000 any one occurrence

Trespass / Nuisance R500,000 any one occurrence

Claims Preparation Costs R500,000 any one occurrence

Deductibles The deductible (excess) is the amount which the Contractor and/or Sub-Contractor is responsible for and this obligation must be reflected in the Tender and/or Contract Documents and the responsibility for same made clear. The deductibles apply to each and every occurrence and in respect of all Contracts. The deductibles are: Loss of or damage to public utilities R25,000

Spread of fire R250,000

Spread of fire – track re-profiling R250,000

Loss of or damage to any other property R25,000

Loss of or damage arising from removal of lateral support R25,000

Loss of or damage arising from the burning of fire breaks R250,000

Loss of or damage arising out of vegetation control R250,000 ` including but not limited to the use of pesticides and or herbicides

"Prev

iew C

opy O

nly"

Page 206: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 22 -

Main Exceptions The amount of the policy deductible.

Death or injury to own employees.

Motor vehicle liabilities under legislation or as defined in Multi-lateral Motor Vehicles Accident Fund No. 93 of 1989 as amended.

Claims in connection with ownership or use of aircraft or watercraft.

Property belonging to the Insured or in his care custody and control (as defined in the Policy).

Property forming part of Contract Works.

Liquidated damages or penalties for delays or in respect of performance or efficiency guarantees.

Liability arising out of defects in workmanship materials design plan or specification in any part of the Property insured.

Arising from or in connection with design plan or specification.

Gradual pollution and contamination.

Sudden unintended and unforeseen seepage, pollution or contamination including the cost of removing, nullifying or cleaning up in respect of both ocean and harbour going watercraft outside of dry dock.

After completion and handover (inclusive of the contractual Defects / Maintenance period).

Punitive damages.

Ownership hiring or leasing of any airport or airstrip.

War, asbestos and nuclear risks.

Cover Limitations / Warranties

Rail Track Re-Profiling

- The maximum speed of any grinding unit shall not exceed 11.00km per hour.

- All Guards, Curtains, Spark Deflectors are to be in place and correctly positioned prior to the commencement of each grind.

- Maximum grinding distance in any one execution shall not exceed 10,000 metres.

- Any changes in prevailing weather conditions must be recorded and appropriate remedial action taken.

- The Insured Parties are to comply with all Fire Fighting requirements as set out in the Project Specification For Track Maintenance With An On Track Grinding / Profiling Machine and any amendments / deviations to this Project Specification are to be advised to the Insurer prior to work being undertaken.

NB: Failure to thoroughly pre-plan and document the safety measures to be adopted with specific regards tp

the incidence of fires being initiated during the execution of the work will invalidate indemnity provided in respect of fire arising out of track re-profiling works.

"Prev

iew C

opy O

nly"

Page 207: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 23 -

� It is essential that this requirement is brought to the attention of

Contractor’s. Where this restriction is not practical, specific arrangements for cover can be made with underwriters. They will, however, require detailed underwriting information and an additional premium may be charged.

Other Limitations

Indemnity for removal of lateral support is limited to R25,000,000.

If a higher limit of indemnity is required, the Employers Insurance Broker’s personnel needs to be advised and underwriting information will need to be provided in advance (i.e prior to Tender stage) and this will entail an additional premium.

"Prev

iew C

opy O

nly"

Page 208: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 24 -

Administrative Procedures

"Prev

iew C

opy O

nly"

Page 209: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 25 -

Administrative Procedures

Arranging Insurance cover The Operating Divisions and Specialist Units must Prior to the commencement of each Contract:- Complete the Declaration Form per Part A as per Annexure 1 herein.

Date and sign the Declaration Form.

Submit the Declaration Form to the Broker.

In addition, if the Declaration is being submitted after the commencement date, a separate letter is required stating that, after specific enquiry, The Insured is not aware of any incidents which may give rise to claim/s under this policy. (No Known Incidents Declaration).

On receipt of late declarations which are not accompanied by a “No Known Incidents Declaration”, the Insurance declaration will not be accepted and no cover will be in force.

Record the Declaration on the Contract Monthly Register and submit this Register at the end of each month to Transnet Group Insurance and the Broker.

On receipt of the Declaration Form the Broker will submit it to the Insurer and the following documents will be issued and provided to the Operating Divisions and Specialist Units:- An Insurance Certificate and a SASRIA Coupon evidencing cover.

A Debit Note in respect of the premiums due (based on agreed rates).

NB In terms of SASRIA Regulations, where the Contract Value exceeds R2 million, the physical address of the contract is mandatory. If no physical address i.e. where Track is being worked upon, the start and end points are required.

Prior to the expiry of each Declarations estimated completion date:- Confirm to the Broker that the contract will be completed on time.

On completion submit to the Broker a Declaration of the final contract value per Part B as per Annexure 1 herein.

NB If the original completion date is not going to be achieved, the period of insurance on the Declaration document will need to be extended and the Broker needs to be notified prior to original completion date.

The Operating Divisions and Specialist Units (prior to the expiry date of the certificate period) has to advise the Broker in writing to extend the period of insurance and provide the new estimated completion date.

NB If a completion date needs to be extended and the Broker is not advised prior to the original completion date, all SASRIA cover will cease on the originally declared completion date as there is no hold covered arrangement with SASRIA.

A new SASRIA Coupon will then only be issued for the extension period from the date when

the Insurer is advised in writing by the Broker. Under these circumstances the new SASRIA Coupon will be subject to an additional premium,

subject to the minimum premium.

"Prev

iew C

opy O

nly"

Page 210: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 26 -

This process needs to be followed by the Operating Divisions and Specialist Units until the time of completion is achieved. Once the Contract has been completed:- The Operating Divisions and Specialist Units have to declare the final contract value to the Broker per

Part B as per Annexure 1 herein.

The deposit premium will then be adjusted accordingly.

Failure by the Operating Divisions and Specialist Units to conform to the above procedure will result in cover being voided.

"Prev

iew C

opy O

nly"

Page 211: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 27 -

Contracts that require specific arrangements All contracts that fall outside the scope of this Principal Controlled Insurance Programme have to be advised to the Broker prior to Tender and specific “One Off” cover will need to be negotiated. These will be: Where the Contract Value exceeds R100,000,000 (Inclusive of VAT)

Where the Contracted period exceeds 36 months.

Where the Contracted Defects Liability Maintenance period exceeds 12 months.

Other excluded Contracts as described on Page 8 /9 herein.

Contracts involving harbor wet risks*, dams, tunneling, mining, quarrying, shaft sinking, underground work, alterations to water courses being river diversions or coffer dams.

Contracts outside of the Territorial Limits.

In this regard contact the Employers Insurance Broker’s personnel as detailed on Page 33 herein. Contracts where cover limitations will be exceeded or where cover warranties cannot be complied with need to be discussed with the Employers Insurance Broker’s personnel prior to contract award date to enable the Broker to make specific arrangements with Underwriters. This will however require detailed Underwriting Information and an additional premium may be charged.

� In order to ensure that Contractor’s and site staff are aware of

procedures a copy of this Procedure Manual must be supplied to the contract administrators and each Contractor on award of contract..

* Note: Harbour Wet Risks shall mean all work entailing or involving work in or upon water whether partially or fully submerged such as but not limited to quay walls, wharfs seawalls, caissons, breakwaters, jetties, piers, deepening or widening and dredging of ports and other off-shore risks

"Prev

iew C

opy O

nly"

Page 212: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 28 -

Important Considerations

"Prev

iew C

opy O

nly"

Page 213: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 29 -

Important Considerations Cognizance must be taken of the following important considerations:- For contracts involving assembly or erection of plant and machinery or repairs maintenance or

overhaul thereto, THE FULL NEW REPLACEMENT VALUE OF THE PLANT/MACHINERY involved must be declared AND NOT ONLY THE CONTRACT VALUE, for example.:

� Cranes (repairs or final assembly)

� Machinery being moved

� Maintenance or new works on existing Portnet Vessels whilst moored or in dry dock.

Specific arrangements are in place to cover certain contracts where the exposure to own damage (damage to the works) is nil or negligible, but where a high third party liability exposure exists. For example:

� Chemical control of vegetation

� Vegetation rehabilitation

� Ballast tamping

� Re-profiling of Track

� Burning of Fire Breaks

� Geotechnical and Exploratory Works

Contracts of this nature must be clearly identified on the Declaration Form.

Contract value must include the replacement value of any Free Issue Material provided.

VAT must be added to all contract value declarations in order to comply with local legislation.

All policy limits and deductibles are Vat inclusive.

"Prev

iew C

opy O

nly"

Page 214: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 30 -

Claims Procedure

"Prev

iew C

opy O

nly"

Page 215: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 31 -

Claims Procedure In the event of any incident or occurrence, which is likely, to give rise to a claim under the Insurance arranged by the Principal the following procedures shall be adhered to in addition to any statutory or other requirements contained in the Contract. All incidents that could give rise to claim under the Principal Controlled Insurances, HAVE TO BE reported to the Broker / Insurer within a 90 (Ninety) day period from date of loss. IMMEDIATELY advise Aon Construction & Engineering Risks (Attention Sandra Botha). At the same time complete the Incident Advice Form (Annexure 2 herein) and submit to Aon Construction & Engineering Risks. Losses involving theft or malicious damage must be reported to the police and a police reference

number obtained and recorded.

The Employer, Contactor(s) or Sub-Contractor(s) shall allow free access to Insurers’ Loss Adjuster(s) and / or Employer’s Insurance Broker for the purpose of investigation and assessing the loss or damage.

The Employer, Contractor(s) shall not deal direct with the Insurers other than by co-operating with their Loss Adjuster(s) and / or the Employers Insurance Broker.

No Admission of Liability shall be made by the Employer, Contractor(s) or Sub-Contractor(s) in the event of damage, loss or injury to third party property or persons.

Letters from claimants should be passed to Aon Construction & Engineering Risks as soon as possible via the Employer if necessary.

In the event of immediate repairs being necessary in the interest of safety, the Contractors may with the Employer’s permission proceed with such repairs.

The Employer shall immediately advise Sandra Botha at Aon Construction & Engineering Risks.

Other than in the circumstances described above the Contractor shall not proceed with the making good of any loss without the prior authorization of the Employer who shall advise the Insurer’s appointed Loss Adjuster(s) and Sandra Botha of Aon Construction & Engineering Risks.

Upon commencement of the making good of any loss, the Contractor shall keep separate records of the costs involved in making good such loss and these records must be authenticated by the Employer for submission to the Insurer’s or their Loss Adjuster(s). Such records shall include, inter alia, the entire cost of labour, materials, transport and equipment.

The basis upon which the Insurers will indemnify loss or damage is the cost of repair or replacement of the loss or damage including, inter alia, transport and overheads.

On completion of the making good of any loss the records of the costs involved having been authenticated by the Employer shall be sent to the Insurer’s via their Loss Adjuster(s) and copied to Aon Construction & Engineering Risks (Mrs. Sandra Botha) for processing. "P

review

Cop

y Only

"

Page 216: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 32 -

Upon the amount of the loss or damage being agreed upon by the Insurer’s Loss Adjuster(s) and the Contractor, an “Agreement of Loss” form will be signed by the Contractor and Employer.

The amount agreed upon by the Insurers, the Contractor and the Employer shall be paid by the Insurers to the Employer net of the deductible, who will arrange for the payment to be made to the Contractor as appropriate after deduction of the first amount payable.

� All incidents which could give rise to a claim under the insurances

arranged by the Principal / Employer must be notified to the Broker without delay, per the procedures set out above

"Prev

iew C

opy O

nly"

Page 217: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 33 -

Aon South Africa Personnel

Construction and Engineering Division

"Prev

iew C

opy O

nly"

Page 218: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 34 -

Aon South Africa Personnel Construction and Engineering Division Aon South Africa personnel are at all times available for advice, please feel free to contact :- ▪ George Davis Senior Accounts Executive Tel No. (011) 944 7103 Fax No. (086) 505 9558 E-Mail [email protected] ▪ Judy Bath Account Administrator Tel No. (011)944 7053 Fax No. (086)505 9553 E-Mail [email protected] ▪ Sandra Botha Claims Manager Tel No. (011)944-7118 Fax No. (086)556 7169 E-Mail [email protected]

"Prev

iew C

opy O

nly"

Page 219: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Procedure Manual Principal Controlled Insurance 2010 / 2011

Aon Transnet-PCI-Procedure Manual 2010 - 35 -

Annexure 1

Transnet Principal Controlled Construction Insurance Programme Contract Award Declaration (Part A) And Contract Completion Declaration (Part B)

"Prev

iew C

opy O

nly"

Page 220: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

TRANSNET PRINCIPAL CONTROLLED INSURANCE PROGRAMME CONTRACT DECLARATION

CONTRACT NUMBER…………………………………………………………… PURCHASE ORDER NUMBER…………………………………………………

Send to Aon South Africa (Pty) Ltd From (Operating Unit/Specialist Div)……………………….. Construction and Engineering Postal Address …………………………………………….. PO Box 1874 ……………………………………………. Parklands .......................................................... 2121 Represented by .......................................................... Attention : Judy Bath E-Mail Address .......................................................... Tel No. (011) 944-7053 Tel No. .......................................................... Fax No. 086 505 9553 Fax No. .......................................................... E-Mail: [email protected]

PART A – CONTRACT AWARD INFORMATION

TYPE OF CONTRACT MARK WITH AN ‘X’ IF APPLICABLE:

LONG TERM MAINTENANCE / MULTIPLE WORKS CONTRACT with a SERVICE LEVEL AGREEMENT

OTHER

NAME OF CONTRACTOR

CONTRACT AWARD DATE

CONTRACT COMMENCEMENT DATE

EXPECTED CONTRACT COMPLETION DATE

DESCRIPTION OF CONTRACT WORKS

PHYSICAL ADDRESS WHERE CONTRACT IS TAKING PLACE (COMPULSARY FOR ALL CONTRACTS R2M AND OVER)

MAINTENANCE PERIOD (MONTHS)

CONTRACT VALUE AT AWARD

IF PLANT AND MACHINERY INCLUDE REPLACEMENT VALUE

ESTIMATED VALUE OF FREE ISSUED SUPPLIED TO CONTRACTOR

DOES THIS CONTRACT ENTAIL WORK IN RESPECT OF THE FOLLOWING CATEGORIES WHERE THE EXPOSURE TO OWN DAMAGE (DAMAGE TO WORKS) IS NIL OR NEGLIGIBLE [I] CHEMICAL CONTROL OF VEGETATION YES/NO [II] VEGETATION REHABILITATION YES/NO [III] BALLAST TAMPING YES/NO [IV] TRACK RE-PROFILING YES/NO [V] BURNING OF FIRE BREAKS YES/NO [VI] GEOTECHNICAL AND EXPLORATORY WORKS YES/NO

OPTIONAL INSURANCE REQUIRED

[I] IS REMOVAL OF LATERAL SUPPORT COVER REQUIRED? YES/NO [II] DOES THIS CONTRACT EVIDENCE AN EXPOSURE WHICH CAN BE COVERED BY PROJECT DELAY INSURANCE? YES/NO [III] WILL THE EMPLOYER/CONTRACTOR/SUB-CONTRACTOR MAKE ANY DIRECT IMPORTS OF REQUIREMENTS FOR THE CONTRACT THAT REQUIRE MARINE IMPORT INSURANCE? YES/NO IF SO DETAILS NEED TO BE PROVIDED TO THE BROKER SO THAT THIS FORM OF COVER CAN BE ARRANGED SIGNATURE …………………………………………………… DATE: ………………………………………………

"Prev

iew C

opy O

nly"

Page 221: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

TRANSNET PRINCIPAL CONTROLLED INSURANCE PROGRAMME CONTRACT COMPLETION DECLARATION

ORIGINAL CONTRACT NO. …………….. PURCHASE ORDER NO. …………………

PART B – CONTRACT COMPLETION DECLARATION

CONTRACT NUMBER

TITLE OF CONTRACT

CONTRACT COMPLETION DATE

ENDORSEMENT/CERTIFICATE NUMBER

EXPIRY OF MAINTENANCE PERIOD

FINAL CONTRACT VALUE

ACTUAL VALUE OF FREE ISSUE SUPPLIED TO CONTRACTOR

SIGNATURE:…………………………………………… DATE:……………………………………………………………..

"Prev

iew C

opy O

nly"

Page 222: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Aon Transnet PCI-Procedure Manual 2010 - 34 -

Procedure Manual Principal Controlled Insurance 2010

Annexure 2

Incident Advice Form

ALL INCIDENTS HAVE TO BE REPORTED WITHIN 90 DAYS OF OCCURRENCE

"Prev

iew C

opy O

nly"

Page 223: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

TRANSNET PRINCIPAL CONTROLLED INSURANCE PROGRAMME

INCIDENT ADVICE FORM TRANSNET UNIQUE CLAIM NUMBER ……………………………….....

Send to Aon South Africa (Pty) Ltd Construction and Engineering PO Box 1874 Parklands From .......................................................... 2121 Represented by .......................................................... Attention : Sandra Botha Tel No. (011) 944 7118 Tel No. .......................................................... Fax No. (086) 556 7169 Fax No. .......................................................... E-Mail: [email protected]

PRINCIPAL (PER CONTRACT DOCUMENT

CONTRACT NUMBER

ORIGINAL DECLARATON NO.

TITLE OF CONTRACT

ORIGINAL CONTRACT COMMENCEMENT DATE

DATE OF LOSS OR DAMAGE

DATED REPORTED TO SITE AGENT

REPORTED BY

REPORTED TO BY

DATE

LOCALITY OF INCIDENT

DETAILS OF HOW THE LOSS OR DAMAGE OCCURRED

DETAILS AND NATURE OF LOSS OR DAMAGE TO CONTRACT WORKS / TO THIRD PARTY PROPERTY

DETAILS OF OTHER DEATH OR INJURY TO PARTIES

ESTIMATED COST (SEPARATE RECORDS OF ALL COSTS MUST BE KEPT)

WHO OR WHAT APPEARS TO BE RESPONSIBLE FOR THE CAUSE OF THE LOSS / DAMAGE

PERSON WHOM ASSESSOR SHOULD CONTACT DESIGNATION:

TELEPHONE (LANDLINE) CELLPHONE NO. E-MAIL ADDRESS

ALL INCIDENTS HAVE TO BE REPORTED WITHIN 90 DAYS OF OCCURRENCE SIGNED BY: ………………………………………………………… SIGNATURE: ………………………………………….. COMPANY: ………………………………………………………. DATE: …………………………………………………..

"Prev

iew C

opy O

nly"

Page 224: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Annexure 3

Annual Contract Works & Contractors Public Liability And Lateral Support Policy Wording

"Prev

iew C

opy O

nly"

Page 225: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Aon Transnet-PCI-Procedure Manual 2010 -36 -

Annexure 4

Annual Contractors Public Liability Policy Wording

In respect of Contracts entailing:-

■ Chemical Vegetation Rehabilitation

■ Vegetation Rehabilitation

■ Ballast Tamping

■ Rail Track Re-Profiling

■ Burning of Fire Breaks

■ Geotechnical and Exploratory Works

"Prev

iew C

opy O

nly"

Page 226: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

"Prev

iew C

opy O

nly"

Page 227: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

"Prev

iew C

opy O

nly"

Page 228: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

"Prev

iew C

opy O

nly"

Page 229: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

"Prev

iew C

opy O

nly"

Page 230: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

"Prev

iew C

opy O

nly"

Page 231: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

"Prev

iew C

opy O

nly"

Page 232: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

"Prev

iew C

opy O

nly"

Page 233: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

"Prev

iew C

opy O

nly"

Page 234: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

"Prev

iew C

opy O

nly"

Page 235: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

"Prev

iew C

opy O

nly"

Page 236: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

"Prev

iew C

opy O

nly"

Page 237: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

"Prev

iew C

opy O

nly"

Page 238: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

"Prev

iew C

opy O

nly"

Page 239: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

"Prev

iew C

opy O

nly"

Page 240: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

"Prev

iew C

opy O

nly"

Page 241: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

"Prev

iew C

opy O

nly"

Page 242: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

"Prev

iew C

opy O

nly"

Page 243: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

"Prev

iew C

opy O

nly"

Page 244: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

"Prev

iew C

opy O

nly"

Page 245: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

"Prev

iew C

opy O

nly"

Page 246: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

"Prev

iew C

opy O

nly"

Page 247: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail RFP No. S.I.E 10032CIDB A Division of Transnet Limited

Tender Tender Cover

TRANSNET SOC LIMITED (REGISTRATION NO.1990/000900/06)

TRADING AS

TRANSNET FREIGHT RAIL

NEC3 Engineering & Construction Contract (ECC3)

RFP NO. S.I.E 10032 CIDB

TENDER DOCUMENT FOR THE REFURBISHMENT OF SOUTH PORTAL, QUAIL, NOTTINGHAM ROAD, DANSKRAAL, ELANDSLAAGTE, WASBANK AND GLENCOE 3kV DC TRACTION SUBSTATIONS.

OPENS: 6 JUNE 2011

CLOSES: 26 JULY 2011 (10h00)

"Prev

iew C

opy O

nly"

Page 248: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail RFP No. SIE10032 A Division of Transnet Limited Refurbishment of 3Kv substations

Part T1 Page 1 of 4 T1.1 Tendering procedures Tender Notice and Invitation to Tender

PART T1: TENDERING PROCEDURES

T1.1 TENDER NOTICE AND INVITATION TO TENDER

RFP No. SIE10032CIDB Transnet Limited trading as Transnet Freight Rail invites tenders for the refurbishment of South Portal, Quail, Nottingham Road, Danskraal, Elandslaagte, Wasbank and Glencoe traction substations.

Tenderers should have a CIDB contractor grading designation of 8EP or higher. Potentially emerging enterprises (7EP PE) who satisfy criteria stated in the Tender Data may submit tender offers. Only Tenderers who are registered with the CIDB, are eligible to submit tenders The physical address for collection of tender documents is: Transnet Freight Rail, Tender Advice Centre, Ground Floor, Inyanda House 1, 21 Wellington Road, Parktown. Tender documents may be collected during working hours after 08h00 on Monday, 6th June 2011 and will only be available until 15h00 on Friday, 17th June 2011. Payment of an amount of R1000.00 (per set), (not refundable) is to be made to Transnet Freight Rail at the Standard Bank, account number 203158595, branch code 4805, reference no. RFP No. SIE10032CIDB. The official Bank receipt(s) franked with the official Bank stamp to be provided with the collection of a tender document. No tenders will be sold after 15h00 on Friday, 17th June 2011 deadline. Queries relating to the administrative issues of these documents may be addressed to: Me. Delisiwe Mngomezulu Tel No. 011- 5841129 Fax No. 011-7749602 E mail: [email protected] Or Mrs. Sarah Assegaai E-mail. [email protected] A compulsory three-day clarification meeting and site inspection with representatives of the Employer will take place at the Infrastructure Maintenance Depot, Lyell Road, Ladysmith on Tuesday, 21st June 2011, Wednesday, 22nd June 2011 and Thursday, 23rdJune 2011 starting at 09h00. The clarification meeting will be followed by compulsory site inspections of all substations. Tenderers without a valid tender document in their possession will not be allowed to attend this compulsory clarification meeting and site inspection. Tenderers shall be responsible for their own travel arrangements and cost regarding the site meeting and site inspection. Transnet reserves the right to accept the whole or any part of a tender. Transnet also reserves the right to negotiate terms and conditions with all, or a short-listed group of contenders, or the preferred tenderer, should it be deemed necessary. This tender closes punctually at 10h00 on Tuesday, 26th July 2011.

"Prev

iew C

opy O

nly"

Page 249: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail RFP No. SIE10032 A Division of Transnet Limited Refurbishment of 3Kv substations

Part T1 Page 2 of 4 T1.1 Tendering procedures Tender Notice and Invitation to Tender

Tenders may only be submitted on the tender documentation that is issued. Telegraphic, telephonic, facsimile and late tenders will not be accepted. Tenderers are warned that a tender will be liable for disqualification should any attempt be made by a Tenderer to either directly or indirectly to canvass any officer(s) or employees of Transnet Limited in respect of a tender between the date the tender is submitted and the date of the award. A Tenderer may, however, at any time communicate with the Chairperson of the Transnet Freight Rail Acquisition Council, at telephone no. 011 5449486 on any matter relating to his tender.

Envelopes must not contain documents relating to any tender other than that shown on the envelope. No slips are to be attached to the tender documents. Any additional conditions must be embodied in an accompanying letter. Alterations, additions or deletions must not be made by the Tenderer to the actual tender documents. Tenders submitted by Tenderers must be neatly bound and the inclusion of loose documents must be avoided.

Requirements for sealing, addressing, delivery, opening and assessment of tenders are stated in the Tender Data.

Compliance of tender(s) with Transnet's requirements is the sole responsibility of the Tenderer and any costs incurred in subsequent modifications to or replacement of equipment accepted by Transnet Limited in good faith on the grounds of certified compliance with specified standards by the contractor and in fact found to be inadequate in such respects, will be to the relevant Tenderer's account

BROAD-BASED BLACK ECONOMIC EMPOWERMENT (“BBBEE”)

TRANSNET fully endorses and supports the South African Government’s Broad-Based Black Economic Empowerment Programme and it is strongly of the opinion that all business enterprises have an equal obligation to redress the imbalances of the past. TRANSNET would therefore prefer to do business with business enterprises who share these same values and who are prepared to contribute to meaningful BBBEE initiatives (including and not limited to enterprise development, subcontracting and Joint Ventures) as part of their tender response.

Transnet would accordingly allow a “preference” in accordance with the 10% preference system, as per the Preferential Procurement Policy Framework Act 5 of 2000 (as amended) to companies who provide a BBBEE accreditation Certificate. All procurement and disposal transactions in excess of R30000 will be evaluated accordingly. All transactions below R30000 will as far as possible be earmarked for EME’s.

TRANSNET consequently urges Respondents (Large enterprises and QSE’s – see below) to have themselves duly accredited by any one of the Accreditation Agencies approved by SANAS (South African National Accreditation System, under the auspices of the DTI).

In terms of Government Gazette No. 32467, Notice No. 810 dated 31 July 2009, as from 1 February 2010 only BBBEE certificates issued by Accredited Verification Agencies of Verification Agencies that are in possession of a valid pre-assessment letter from South African National Accreditation System will be valid.

However accreditation certificates issued by non-accredited verification agencies before 01 February 2010 and which are still within their one (1) year validity period will still be acceptable, until their expiry date provided that the accreditation was done in accordance with the latest codes (i.e. those promulgated on 9 February 2007).

BBBEE Accreditation Certificates issued after the published date i.e. 01 February 2010, by a Verification Agency not approved by SANAS, will NOT be acceptable as from 01 February 2010.

"Prev

iew C

opy O

nly"

Page 250: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail RFP No. SIE10032 A Division of Transnet Limited Refurbishment of 3Kv substations

Part T1 Page 3 of 4 T1.1 Tendering procedures Tender Notice and Invitation to Tender

Enterprises will be rated by such Accreditation Agencies based on the following:

(a) Large Enterprises (i.e. annual turnover >R35 million):

� Rating level based on all 7 (seven) elements of the BBBEE scorecard

� Enterprises to provide BBBEE certificate and detailed scorecard (to be renewed annually)

(b) Qualifying Small Enterprises – QSE (i.e. annual turnover >R5 million but <R35 million):

� Rating based on any 4 (four) of the elements of the BBBEE scorecard

� Enterprises to provide BBBEE certificate and detailed scorecard (to be renewed annually)

(c) Exempted Micro Enterprises – EME (i.e. annual turnover <R5m are exempted from being rated or verified):

� Automatic BBBEE Level 4 rating, irrespective of race ownership, i.e. 100% BBBEE recognition

� Black ownership >50% or Black Women ownership >30% automatically qualify as Level 3 BBBEE rating, i.e. 110% BBBEE recognition

� EME’s should provide documentary proof of annual turnover (i.e. audited financials) plus proof of Black ownership if Black ownership >50% or Black Women ownership >30% (to be renewed annually) from their Auditors / Accounting Officers

In addition to the above, Respondents who wish to enter into a Joint Venture (JV) or subcontract portions of the contract to BBBEE companies must state in their Tenders / Proposals the percentage of the total contract value which would be allocated to such BBBEE companies, should they be successful in being awarded any business. A rating certificate in respect of such BBBEE JV-partners and/or sub-contractors, as well as a breakdown of the distribution of the aforementioned percentage allocation must also be furnished with the tender response to enable Transnet to evaluate / adjudicate on all tenders received on a fair basis.

Each Respondent is required to furnish proof of its BBBEE status (Certificate and Detailed Scorecard) and ensure that the documentation is valid at the date of Tender Submission as stipulated above to TRANSNET.

Failure to submit your BBBEE Certificate and Detailed Scorecard will result in a score of zero being allocated for BBBEE evaluation.

Turnover: Indicate your company’s most recent annual turnover:

R…………………………………………………………..

• If annual turnover <R5m, please attach auditors / accounting officers letter confirming annual turnover and percentage black ownership as well as Black Women ownership

• If annual turnover >R5m please attach BBBEE certificate and detailed scorecard from an accredited rating agency.

The DTI has created an online B-BBEE Registry (http://www.dti.gov.za) in order to provide a central and standardized source of the B-BBEE status of all entities, and to facilitate the flow of this information amongst entities by providing a Unique Profile Number (UPN) per each listing. Existing and prospective suppliers are therefore urged to list their B-BBEE status on the DTI Registry. Hence, entities verified by DTI, will receive the following benefits:

- Their BBBEE status will be verified and confirmed by the DTI, before listing on the Registry

"Prev

iew C

opy O

nly"

Page 251: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail RFP No. SIE10032 A Division of Transnet Limited Refurbishment of 3Kv substations

Part T1 Page 4 of 4 T1.1 Tendering procedures Tender Notice and Invitation to Tender

- Listing on the Registry will provide suppliers the option to market themselves on the DTI B-BBEE Opportunities Network. This is a search engine that is designed to help businesses find B-BBEE compliant entities who match specific requirements in terms of the nature of services/goods provided, region, B-BBEE status or other search criteria.

Transnet supports this DTI initiative and will use the DTI Registry to verify prospective and existing suppliers’ BBBEE credentials.

Kindly provide Transnet with your DTI B-BBEE UNIQUE PROFILE NUMBER with all tender submissions.

DTI BBBEE UNIQUE PROFILE NUMBER:

…………………………….……………………

Failure to submit your BBBEE information in terms of the above-mentioned clauses will result in a score of zero being allocated for BBBEE evaluation.

Suppliers and Tenderers are requested to duly complete the Supplier Declaration Form (SDF) and provide all the relevant supporting attachments as requested. Failure to provide the following may disqualify your tender submission:- 1. Duly completed SDF 2. Current tax clearance certificate

The Supplier and Tenderer shall furnish proof of the above to Transnet.

Transnet at its sole discretion may decide to allow certain price preferences in order to uplift the historically disadvantaged in terms of the PPPFA (Act 5 of 2000).

Transnet insists on honesty and integrity beyond reproach at all times and will not tolerate any form of improper influencing, bribery, corruption, fraud, or any other unethical conduct on the part of bidders/ Transnet employees. If, in the opinion of Transnet’s Chief Operating Officer, a tenderer/contractor/ supplier has or has caused to be promised, offered or given to any Transnet employee, any bribe, commission, gift, loan, advantage or other consideration, Transnet shall be entitled to revoke the tender / contract by following its internal policies that govern the Exclusion process. In such an event Transnet will be entitled to place any Tenderer/Contractor/Supplier who has contravened the provisions of Transnet’s business ethics on its List of Excluded Tenderers. This List will also be distributed to all other State Owned Enterprises and Government Departments.

Transnet invites its valued suppliers to report any allegations of fraud, corruption or other unethical activities to Transnet Tip-offs Anonymous, at any of the following addresses/contract numbers :-

• Toll free anonymous hotline – 0800 003 056

• Email – [email protected]

• Fax number – 0800 007 788

• Freepost DN 298, Umhlanga Rocks, 4320 CONFIDENTIALITY IS GUARANTEED. "P

review

Cop

y Only

"

Page 252: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A Division of Transnet Limited

Contract Page 1 of 3 C1.2 Part C1: Agreement and Contract Data Contract Data provided by Contractor

C1.2 CONTRACT DATA PROVIDED BY CONTRACTOR (ECC3)

Part Two – Data Provided by the Contractor

Completion of the data in full, according to the Options chosen, is essential to create a complete contract.

Statements given in all

contracts

(a) The Contractor is

Name . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Address . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

(b) The direct fee percentage is . . . . . . . . . . %

(c) The subcontracted fee percentage is . . . . . . . . . . %

(d) The working areas are the Site and . . . . . . . . . . . . . . . . . . . . .

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

(e) The key people are

(1) Name . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Job . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Responsibilities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Qualifications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Experience . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

(2) Name . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Job . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Responsibilities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

"Prev

iew C

opy O

nly"

Page 253: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A Division of Transnet Limited

Contract Page 2 of 3 C1.2 Part C1: Agreement and Contract Data Contract Data provided by Contractor

Qualifications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Experience . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

(3) Name . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Job . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Responsibilities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Qualifications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Experience . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

(4) Name . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Job . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Responsibilities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Qualifications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Experience . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

(f) The following matters will be included in the Risk Register

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Optional statements (a) If the Contractor is to provide Works Information for his design

The Works Information for the Contractor’s design is in

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

(b) If a programme is to be identified by the Contract Data.

The programme identified in the Contract Data is

"Prev

iew C

opy O

nly"

Page 254: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail Contract No. S.I.E 10032CIDB A Division of Transnet Limited

Contract Page 3 of 3 C1.2 Part C1: Agreement and Contract Data Contract Data provided by Contractor

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

(c) If the Contractor is to decide the completion date for the whole of the works

The completion date for the whole of works is

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

If Option A or B is used

Data for SSCC (a) The percentage for people overheads is ………..%.

(b) The published list of Equipment is the last edition of the list published by

…………………………………………

(c) The percentage for adjustment for Equipment in the published list is ……………….% (state plus or minus).

(d) The rates for other Equipment are Equipment size or capacity rate …………………… ……………… ……… …………………… ……………… ……… …………………… ……………… ……… …………………… ……………… ……… …………………… ……………… ……… (e) The hourly rates for Defined Cost of design outside the Working

Areas are category of employee hourly rate Senior Engineer ……………. Junior Engineer ……………. Draughtsperson ……………. Tracer ………….…

(f) The percentage of design overheads is ………………%

(g) The categories of design employees whose travelling expenses to

and from the Working Areas are included in Defined Cost are all of the categories listed above. "P

review

Cop

y Only

"

Page 255: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail RFP No. S.I.E 10032CIDB A Division of Transnet Limited Refurbishment of 3kV substations

Tender Page 1 of 34 T2.2 Part T2: Returnable Documents Returnable Schedules

T2.2 RETURNABLE SCHEDULES

• Certificate of Attendance at Clarification meeting

• Schedule of Tenderers experience

• Schedule of proposed Sub-Contractors

• Schedule of Plant and Equipment (Tools and Machinery)

• Foreign Exchange Rate Information

• Record of addenda to Tender Document

• Proposed amendments and qualifications

• Compulsory Enterprise Questionnaire

• Preferencing Schedule (direct preferences)

• Approach paper, which responds to the proposed scope of work

• Experience of key staff in the form of Curriculum Vitae.

• Certificate of authority for joint ventures (where applicable)

• Supplier Declaration form

• Transnet Limited: Contractual Safety clauses which will form part of any resulting contract

• Combined Technical Data Sheet of the following specifications:

1. BBB0041 version 4 10. BBB3162 version 1

2. BBB0496 version 13 11. BBB3890 version 2

3. BBB0845 version 4 12. BBB4724 version 4

4. BBB0937 version 4 13. BBB5019 version 5

5 BBB1267 version 10 14. BBB7842 version 1

6 BBB2502 version 6 15. BBB8204 version 2

7. BBB2721 version 10 16. CEE.0099.2010

8. BBB3005 version 1

9. BBB3139 version 1

• RFP Declaration form

"Prev

iew C

opy O

nly"

Page 256: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail RFP No. S.I.E 10032CIDB A Division of Transnet Limited Refurbishment of 3kV substations

Tender Page 2 of 34 T2.2 Part T2: Returnable Documents Returnable Schedules

Confirmation of attendance at the information session and the site visits at actual locations.

The signature of the Transnet representative below, confirms that the below mentioned individual attended the compulsory tender briefing session and is eligible to participate in the tender. I, _____________________________________ (name), a duly authorised representative of ___________________________________________________________ (company name), It is furthermore certified that the above named person, representing the above named company, has today :

• Attended the information session

• Is conversant with the requirements of the tender

• Is in possession of a complete set of the tender documents ____________________ _____________________________ Date Company Representative _____________________________ (Attendance at briefing session confirmed) Tender administrator _____________________________ (Attendance at South Portal substation) Transnet Representative _____________________________ (Attendance at Quail substation) Transnet Representative _____________________________ (Attendance at Nottingham Road substation) Transnet Representative _____________________________ (Attendance at Danskraal substation) Transnet Representative _____________________________ (Attendance at Elandslaagte substation) Transnet Representative _____________________________ (Attendance at Wasbank substation) Transnet Representative _____________________________ (Attendance at Glencoe substation) Transnet Representative NOTE: This fully signed certificate, MUST accompany your tender submission. Signature: _____________________________ Date _____________________

"Prev

iew C

opy O

nly"

Page 257: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail RFP No. S.I.E 10032CIDB A Division of Transnet Limited Refurbishment of 3kV substations

Tender Page 3 of 34 T2.2 Part T2: Returnable Documents Returnable Schedules

Schedule of the Tenderer’s Experience The following is a statement of similar work successfully executed by myself/ourselves:

Employer, contact

person and telephone number

Description of contract

Value of work inclusive of VAT

(Rand)

Date

completed

Signed ________________________ Date _____________________________ Name _________________________ Position _________________________ Tenderer _________________________________________________________________

"Prev

iew C

opy O

nly"

Page 258: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail RFP No. S.I.E 10032CIDB A Division of Transnet Limited Refurbishment of 3kV substations

Tender Page 4 of 34 T2.2 Part T2: Returnable Documents Returnable Schedules

Schedule of Proposed Sub-Contractors

We notify you that it is our intention to employ the following Sub-Contractors for work in this contract.

If we are awarded a contract we agree that this notification does not change the requirement for us to submit the names of proposed Sub-Contractors in accordance with requirements in the contract for such appointments. If there are no such requirements in the contract, then your written acceptance of this list shall be binding between us.

We confirm that all Sub-Contractors who are contracted to construct a house are registered as home builders with the National Home Builders Registration Council.

Name and address of proposed Sub-Contractor

Nature and extent of work Previous experience with Sub-Contractor.

1.

2.

3.

4.

5.

Signed

Date

Name

Position

Tenderer

"P

review

Cop

y Only

"

Page 259: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail RFP No. S.I.E 10032CIDB A Division of Transnet Limited Refurbishment of 3kV substations

Tender Page 5 of 34 T2.2 Part T2: Returnable Documents Returnable Schedules

Schedule of Plant and Equipment The following are lists of major items of relevant Equipment that I/we presently own or lease and will have available for this contract or will acquire or hire for this contract if my/our tender is accepted. (a) Details of major Equipment that is owned by and immediately available for this contract.

Quantity Description, size, capacity, etc.

Attach additional pages if more space is required.

(b) Details of major Equipment that will be hired, or acquired for this contract if my/our tender is acceptable.

Quantity Description, size, capacity, etc.

Attach additional pages if more space is required.

Signed

Date

Name

Position

Tenderer

"Prev

iew C

opy O

nly"

Page 260: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail RFP No. S.I.E 10032CIDB A Division of Transnet Limited Refurbishment of 3kV substations

Tender Page 6 of 34 T2.2 Part T2: Returnable Documents Returnable Schedules

FOREIGN EXCHANGE RATE INFORMATION REQUIRED TO BE FURNISHED BY TENDERERS. 1. Particulars of the exchange rate on which prices are based : ________________ (Foreign currency) equals R___________(South African currency) Note: Tenderers who offer imported material shall base their tenders on the selling

rate of exchange that ruling on the last working day of the month prior to the closing date of tenders.

2. The percentage of the tender prices which is to be remitted by the tenderers from South

Africa to another country is _______% of the f.o.b./c. and f./f.o.r. in bond price (delete those not applicable).

Note: (1) The percentage quoted above will be deemed to apply even though a

portion only of the item(s) tendered for is accepted.

(2) Adjustment in respect of variation in exchange rate will be allowed only on the percentage of the tendered price quoted above.

3. The tendered price shall be computed at the rate of exchange stated by the tenderer in

paragraphs 1 and 2 above as applied to the percentage of the tendered price quoted. 4. Transnet Freight Rail will accept for its account, in respect of such percentage of the

tendered price as will be affected by the rate of exchange, any variation between the rate mentioned in paragraph 1 above, and the rate ruling at the date when payment for the goods is made by Transnet Freight Rail; provided that if the Contractor is required to remit the whole or portion of the contract price to another country in payment for goods or portion thereof prior to receiving payment from Transnet Freight Rail, the date(s) of such remittance(s) shall be deemed to be the date(s) of payment by Transnet Freight Rail for the purposes of this paragraph.

5. In the absence of a specific indication by the Contractor at the time of tendering that the

proviso to paragraph 3 will apply, it will be assumed that the Contractor desires the adjustment to be effected by reference to the date on which actual payment is made by Transnet Freight Rail.

6. (a) The Contractor shall, if so required, furnish documentary proof to establish that the

percentage of the contract price specified by him in paragraph 2 has actually been remitted to another country and the rate of exchange at which that was done.

(b) Whenever the Contractor is required to remit the whole or portion of the contract price, to another country as contemplated in the proviso to paragraph 2 above, he shall notify Transnet Freight Rail forthwith and furnish documentary evidence of such remittance and of the rate of exchange at which that was done.

7. Invoices in respect of goods supplied must reflect the amount remitted or to be

remitted to another country and the amount to be retained in South Africa. 8. The contractor shall take out forward cover for all imported materials and

services within 14 days of award of the contract. Proof shall be submitted to the Project Manager/Manager in charge of the contract. The cost of forward cover shall be invoiced separate from the contract invoices and shall not be included in the tender price.

"Prev

iew C

opy O

nly"

Page 261: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail RFP No. S.I.E 10032CIDB A Division of Transnet Limited Refurbishment of 3kV substations

Tender Page 7 of 34 T2.2 Part T2: Returnable Documents Returnable Schedules

________________________ SIGNATURE OF TENDERER DATE:__________________ WITNESSES: 1.__________________________ 2.__________________________ ADDRESS: ___________________________________ ___________________________________ ___________________________________ ___________________________________

"Prev

iew C

opy O

nly"

Page 262: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail RFP No. S.I.E 10032CIDB A Division of Transnet Limited Refurbishment of 3kV substations

Tender Page 8 of 34 T2.2 Part T2: Returnable Documents Returnable Schedules

Record of Addenda to tender documents

We confirm that the following communications received from the Employer before the submission of this tender offer, amending the tender documents, have been taken into account in this tender offer:

Date Title or Details

1.

2.

3.

4.

5.

6.

7.

8.

9.

10.

Attach additional pages if more space is required.

Signed Date

Name Position

Tenderer

"Prev

iew C

opy O

nly"

Page 263: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail RFP No. S.I.E 10032CIDB A Division of Transnet Limited Refurbishment of 3kV substations

Tender Page 9 of 34 T2.2 Part T2: Returnable Documents Returnable Schedules

Proposed amendments and qualifications The Tenderer should record any deviations or qualifications he may wish to make to the tender documents in this Returnable Schedule. Alternatively, a tenderer may state such deviations and qualifications in a covering letter to his tender and reference such letter in this schedule. The Tenderer’s attention is drawn to clause F.3.8 of the Standard Conditions of Tender referenced in the Tender Data regarding the employer’s handling of material deviations and qualifications.

Page Clause or item Proposal

Signed Date

Name Position

Tenderer

"Prev

iew C

opy O

nly"

Page 264: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail RFP No. S.I.E 10032CIDB A Division of Transnet Limited Refurbishment of 3kV substations

Tender Page 10 of 34 T2.2 Part T2: Returnable Documents Returnable Schedules

Compulsory Enterprise Questionnaire

The following particulars must be furnished. In the case of a joint venture, separate enterprise questionnaires in respect of each partner must be completed and submitted.

Section 1: Name of enterprise: . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Section 2: VAT registration number. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Section 3: CIDB registration number: . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Section 4: Particulars of sole proprietors and partners in partnerships

Name* Identity number* Personal income tax number*

* Complete only if sole proprietor or partnership and attach separate page if more than 3 partners

Section 5: Particulars of companies and close corporations

Company registration number . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Close corporation number . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Tax reference number . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Section 6: Record in the service of the state

Indicate by marking the relevant boxes with a cross, if any sole proprietor, partner in a partnership or director, manager, principal shareholder or stakeholder in a company or close corporation is currently or has been within the last 12 months in the service of any of the following:

� a member of any municipal council

� a member of any provincial legislature

� a member of the National Assembly or the National Council of Province

� a member of the board of directors of any municipal entity

� an official of any municipality or municipal entity

� an employee of any provincial department, national or provincial public entity or constitutional institution within the meaning of the Public Finance Management Act, 1999 (Act 1 of 1999)

� a member of an accounting authority of any national or provincial public entity

� an employee of Parliament or a provincial legislature

If any of the above boxes are marked, disclose the following:

Status of service (tick appropriate column)

Name of sole proprietor, partner, director, manager, principal shareholder or stakeholder

Name of institution, public office, board or organ of state and position held

Current Within last 12 months

*insert separate page if necessary

Section 7: Record of spouses, children and parents in the service of the state

Indicate by marking the relevant boxes with a cross, if any spouse, child or parent of a sole proprietor, partner in

"Prev

iew C

opy O

nly"

Page 265: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail RFP No. S.I.E 10032CIDB A Division of Transnet Limited Refurbishment of 3kV substations

Tender Page 11 of 34 T2.2 Part T2: Returnable Documents Returnable Schedules

a partnership or director, manager, principal shareholder or stakeholder in a company or close corporation is currently or has been within the last 12 months been in the service of any of the following:

� a member of any municipal council

� a member of any provincial legislature

� a member of the National Assembly or the National Council of Province

� a member of the board of directors of any municipal entity

� an official of any municipality or municipal entity

� an employee of any provincial department, national or provincial public entity or constitutional institution within the meaning of the Public Finance Management Act, 1999 (Act 1 of 1999)

� a member of an accounting authority of any national or provincial public entity

� an employee of Parliament or a provincial legislature

Status of service (tick appropriate column)

Name of spouse, child or parent

Name of institution, public office, board or organ of state and position held

Current Within last 12 months

*insert separate page if necessary

The undersigned, who warrants that he / she is duly authorized to do so on behalf of the enterprise: i) authorizes the Employer to obtain a tax clearance certificate from the South African Revenue Services that my

/ our tax matters are in order; ii) confirms that the neither the name of the enterprise or the name of any partner, manager, director or other

person, who wholly or partly exercises, or may exercise, control over the enterprise appears on the Register of Tender Defaulters established in terms of the Prevention and Combating of Corrupt Activities Act of 2004;

iii) confirms that no partner, member, director or other person, who wholly or partly exercises, or may exercise, control over the enterprise appears, has within the last five years been convicted of fraud or corruption;

iv) confirms that I / we are not associated, linked or involved with any other tendering entities submitting tender offers and have no other relationship with any of the tenderers or those responsible for compiling the scope of work that could cause or be interpreted as a conflict of interest; and

iv) confirms that the contents of this questionnaire are within my personal knowledge and are to the best of my belief both true and correct.

Signed Date

Name Position

Enterprise name

"Prev

iew C

opy O

nly"

Page 266: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail RFP No. S.I.E 10032CIDB A Division of Transnet Limited Refurbishment of 3kV substations

Tender Page 12 of 34 T2.2 Part T2: Returnable Documents Returnable Schedules

Preferencing schedule where direct preferences are granted in respect of targeted enterprise status

1 Definitions

The following definitions shall apply to this schedule: Contractors registered as potentially emerging enterprises with the CIDB who are registered in

one contractor grading designation lower than that required in terms of above and who satisfy the following criteria : (7EP PE)

a) has professional and technical qualifications. b) has professional and technical competence. c) has managerial capacity, reliability and experience. d) has financial resources and good reputation. e) has plant and equipment. 1 Conditions associated with the granting of preferences

The tenderer, who being a Targeted Enterprise undertakes to: 1) not subcontract more than % of the Contract Price to non-Targeted Enterprises; 2) remain a Targeted Enterprise for the duration of the Contract; 3) accept the sanctions set out in Section 3 below should conditions 1 or 2 be breached; 4) complete the Tender Preference Claim Form contained in Section 4 below; and 5) complete a Targeted Declaration Affidavit and submit this with the tender.

3 Sanctions relating to breaches of preferencing conditions

The sanctions for breaching the preferencing conditions are:

1) termination of the Contract; or 2) a financial penalty payable to the Employer equal to 1,25 times the number of tender

evaluation points awarded in respect of the preference claimed, multiplied by the Contract Price exclusive of VAT, divided by 100.

4 Tender preference claim in respect of enterprise status or structure of the tendering

entity

I/we apply on behalf of my/our firm for the following preference:

The undersigned, who warrants that he / she is duly authorised to do so on behalf of the firm or sole proprieter confirms that he / she understands the conditions under which such preferences are granted and confirms that the tenderer satisfies the conditions pertaining to the granting of tender preferences.

Signature: ...............................................................................................................................………. Name: .......................................................................................................................................……… Duly authorised to sign on behalf of : ............................................................................................……… Telephone : ......................................................................

Fax : ................................................................................ Date : ...............................................................................

Category of Targeted Enterprise

Percentage of maximum tender evaluation points provided for in the Preferential Procurement Policy Framework Act (Act 5 of 2000)

Preference claimed for Targeted Enterprise status (Y=yes)

Guidance notes Definitions for Targeted Enterprises percentage = 20% Factor ≥ 1,25

Minimum points for quality =60

"Prev

iew C

opy O

nly"

Page 267: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail RFP No. S.I.E 10032CIDB A Division of Transnet Limited Refurbishment of 3kV substations

Tender Page 13 of 34 T2.2 Part T2: Returnable Documents Returnable Schedules

Evaluation Schedule: Approach paper

The approach paper must respond to the scope of work and outline the proposed approach / methodology including that relating to health and safety. The approach paper should articulate what value add the tenderer will provide in achieving the stated objectives for the project. The tenderer must as such explain his / her understanding of the objectives of the assignment and the Employer’s stated and implied requirements, highlight the issues of importance, and explain the technical approach they would adopt to address them. The approach paper should explain the methodologies which are to be adopted, demonstrate the compatibility of those methodologies with the proposed approach. The approach should also include a quality plan which outlines processes, procedures and associated resources, applied by whom and when, to meet the requirements and indicate how risks will be managed and what contribution can be made regarding value management. The tenderer must attach his / her approach paper to this page. The approach paper should not be longer than 8 pages. The scoring of the approach paper will be as follows:

Technical approach and methodology

Poor (score 40)

The technical approach and / or methodology is poor / is unlikely to satisfy project objectives or requirements. The tenderer has misunderstood certain aspects of the scope of work and does not deal with the critical aspects of the project.

Satisfactory (score 70)

The approach is generic and not tailored to address the specific project objectives and methodology. The approach does not adequately deal with the critical characteristics of the project. The quality plan, manner in which risk is to be managed etc is too generic.

Good (score 90)

The approach is specifically tailored to address the specific project objectives and methodology and is sufficiently flexible to accommodate changes that may occur during execution. The quality plan and approach to managing risk etc is specifically tailored to the critical characteristics of the project.

Very good (score 100)

Besides meeting the “good” rating, the important issues are approached in an innovative and efficient way, indicating that the tenderer has outstanding knowledge of state-of-the- art approaches. The approach paper details ways to improve the project outcomes and the quality of the outputs

The undersigned, who warrants that he / she is duly authorised to do so on behalf of the enterprise, confirms that the contents of this schedule are within my personal knowledge and are to the best of my belief both true and correct.

Signed Date

Name Position

Tenderer

"Prev

iew C

opy O

nly"

Page 268: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail RFP No. S.I.E 10032CIDB A Division of Transnet Limited Refurbishment of 3kV substations

Tender Page 14 of 34 T2.2 Part T2: Returnable Documents Returnable Schedules

Certificate of Authority for Joint Ventures

This Returnable Schedule is to be completed by joint ventures.

We, the undersigned, are submitting this tender offer in Joint Venture and hereby authorise Mr/Ms . . .

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . , authorised signatory of the company . . . . . . . . . . . . . . . .

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . , acting in the capacity of lead

partner, to sign all documents in connection with the tender offer and any contract resulting from it on

our behalf.

NAME OF FIRM ADDRESS DULY AUTHORISED

SIGNATORY

Lead partner

Signature. . . . . . . . . . . . .

Name ……..

Designation

Signature. . . . . . . . . . . . .

Name ……..

Designation

Signature. . . . . . . . . . . . .

Name ……..

Designation

Signature. . . . . . . . . . . . .

Name ……..

Designation

"Prev

iew C

opy O

nly"

Page 269: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail RFP No. S.I.E 10032CIDB A Division of Transnet Limited Refurbishment of 3kV substations

Tender Page 15 of 34 T2.2 Part T2: Returnable Documents Returnable Schedules

TTrraannssnneett SSuupppplliieerr DDeeccllaarraattiioonn//AApppplliiccaattiioonn

The Financial Director or Company Secretary Transnet Vendor Management has received a request to load your company on to the Transnet vendor database. Please furnish us with the following to enable us to process this request: 1. Complete the “Supplier Declaration Form” (SDF) on page 2 of this letter 2. Original cancelled cheque OR letter from the bank verifying banking details (with bank

stamp) 3. Certified copy of Identity document of Shareholders/Directors/Members (where applicable) 4. Certified copy of certificate of incorporation, CM29 / CM9 (name change) 5. Certified copy of share Certificates of Shareholders, CK1 / CK2 (if CC) 6. A letter with the company’s letterhead confirming physical and postal addresses 7. Original or certified copy of SARS Tax Clearance certificate and Vat registration certificate 8. A signed letter from the Auditor / Accountant confirming most recent annual turnover and

percentage black ownership in the company AND/OR BBBEE certificate and detailed scorecard from an accredited rating agency (SANAS member).

NB: ▪ Failure to submit the above documentation will delay the vendor creation process. ▪ Where applicable, the respective Transnet business unit processing your application may request further information from you. E.g. proof of an existence of a Service/Business contract between your business and the respective Transnet business unit etc.

IMPORTANT NOTES: a) If your annual turnover is less than R5 million, then in terms of the DTI codes, you are

classified as an Exempted Micro Enterprise (EME). If your company is classified as an EME, please include in your submission, a signed letter from your Auditor / Accountant confirming your company’s most recent annual turnover is less than R5 million and percentage of black ownership and black female ownership in the company AND/OR BBBEE certificate and detailed scorecard from an accredited rating agency (e.g. permanent SANAS Member), should you feel you will be able to attain a better BBBEE score.

b) If your annual turnover is between R5 million and R35million, then in terms of the DTI

codes, you are classified as a Qualifying Small Enterprise (QSE) and you claim a specific BBBEE level based on any 4 of the 7 elements of the BBBEE score-card, please include your BEE certificate in your submission as confirmation of your status. NB: BBBEE certificate and detailed scorecard should be obtained from an accredited rating agency e.g. permanent SANAS Member).

c) If your annual turnover is in excess of R35million, then in terms of the DTI codes, you are classified as a Large Enterprise and you claim a specific BEE level based on all seven elements of the BBBEE generic score-card. Please include your BEE certificate in your submission as confirmation of your status. NB: BBBEE certificate and detailed scorecard should be obtained from an accredited rating agency (permanent SANAS Member).

d) To avoid PAYE tax being automatically deducted from any invoices received from you,

you must also contact the Transnet person who lodged this request on your behalf, so as to be correctly classified in terms of Tax legislation.

e) Unfortunately, No payments can be made to a vendor until the vendor has been registered,

and no vendor can be registered until the vendor application form, together with its supporting documentation, has been received and processed.

f) Please return the completed Supplier Declaration Form (SDF) together with the

required supporting documents mentioned above to the Transnet Official who is intending to procure your company’s services/products in order that he/she should complete and Internal Transnet Departmental Questionnaire before referring the matter to the appropriate Transnet Vendor Master Office.

"Prev

iew C

opy O

nly"

Page 270: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail RFP No. S.I.E 10032CIDB A Division of Transnet Limited Refurbishment of 3kV substations

Tender Page 16 of 34 T2.2 Part T2: Returnable Documents Returnable Schedules

Regards, Transnet Vendor/Supplier Management [please substitute this with your relevant Transnet department before sending this document out]

SSuupppplliieerr DDeeccllaarraattiioonn FFoorrmm

Company Trading Name

Company Registered Name

Company Registration Number Or ID Number If A Sole Proprietor

Form of entity CC Trust Pty Ltd Limited Partnership Sole Proprietor

VAT number (if registered)

Company Telephone Number

Company Fax Number

Company E-Mail Address

Company Website Address

Bank Name Bank Account Number

Postal Address Code

Physical Address Code

Contact Person

Designation

Telephone

Email

Annual Turnover Range (Last Financial Year)

< R5 Million R5-35 million > R35 million

Does Your Company Provide Products Services Both

Area Of Delivery National Provincial Local

Is Your Company A Public Or Private Entity Public Private

Does Your Company Have A Tax Directive Or IRP30 Certificate

Yes No

Main Product Or Service Supplied (E.G.: Stationery/Consulting)

BEE Ownership Details

% Black Ownership

% Black women

ownership

% Disabled person/s ownership

Does your company have a BEE certificate Yes No

What is your broad based BEE status (Level 1 to 9 / Unknown)

How many personnel does the firm employ Permanent Part time

Transnet Contact Person

Contact number

Transnet operating division

Duly Authorised To Sign For And On Behalf Of Firm / Organisation

Name Designation

Signature Date

Stamp And Signature Of Commissioner Of Oath

Name Date

Signature Telephone No.

"Prev

iew C

opy O

nly"

Page 271: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail RFP No. S.I.E 10032CIDB A Division of Transnet Limited Refurbishment of 3kV substations

Tender Page 17 of 34 T2.2 Part T2: Returnable Documents Returnable Schedules

NB: Please return the completed Supplier Declaration Form (SDF) together with the required supporting documents mentioned above to the Transnet Official who is intending to procure your company’s services/products.

(Please tick as applicable) (* - Minimum requirements)

2.1 Indicate the business sector in which your company is involved/operating:

Agriculture Mining and Quarrying

Manufacturing Construction

Electricity, Gas and Water Finance and Business Services

Retail, Motor Trade and Repair Services

Wholesale Trade, Commercial Agents and Allied Services

Catering, accommodation and Other Trade

Transport, Storage and Communications

Community, Social and Personal Services

Other (Specify)

Principal Business Activity *

Types of Services Provided

Since when has the firm been in business?

2.2 What is your company’s annual turnover (excluding VAT)? *

<R20k >R20k <R0.3m

>R0.3m <R1m

>R1m <R5m

>R6m <R10m

>R11m <R15m

>R16m <R25m

>R26m <R30m

>R31m <R34m

>R35m

2.3 Where are your operating/distribution centres situated *

3. VENDOR OWNERSHIP DETAIL

(Please tick as applicable) (* - Minimum requirements)

3.1 Did the firm previously operate under another name? *

YES NO

3.2 If Yes state its previous name:*

Registered Name

Trading Name

3.3 Who were its previous owners / partners / directors?*

SURNAME & INITIALS ID NUMBERS

3.4 List Details of current partners, proprietors and shareholders by name, identity

2. VENDOR TYPE OF BUSINESS

"Prev

iew C

opy O

nly"

Page 272: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail RFP No. S.I.E 10032CIDB A Division of Transnet Limited Refurbishment of 3kV substations

Tender Page 18 of 34 T2.2 Part T2: Returnable Documents Returnable Schedules

number, citizenship, status and ownership as relevant: *

SURNAME & INITIALS

IDENTITY NUMBER

CITI- ZENSHIP

HDI

DIS -ABLED

GENDER DATE OF OWNERSHIP

% OWNE

D

% VOTIN

G

3.5 List details of current directors, officers, chairman, secretary etc. of the firm: *

SURNAME & INITIALS

IDENTITY NUMBER

TITLE DIS -ABLED

GENDER % OF TIME DEVOTED TO THE

FIRM

CONTACT NUMBER

3.6 List details of firms personnel who have an ownership interest in another firm: *

SURNAME & INITIALS

IDENTITY NUMBER

NAME & ADDRESS OF OTHER FIRM

TITLE IN OTHER FIRM

% OWNED TYPE OF BUSINESS OF OTHER FIRM

4. VENDOR DETAIL

(Please tick as applicable) (* - Minimum requirements)

4.1 How many personnel does the firm employ? *

BLACK WHITE COLOURED INDIAN OTHER TOTAL

Permanent

Part Time

4.1.1 In terms of above kindly provide numbers on women and disabled personnel? *

BLACK WHITE COLOURED INDIAN OTHER TOTAL

Women

Disabled

4.2 Provide Details of Contact Person/s Responsible for Broad Based Black Economic Empowerment (BBBEE) in the Company *

SURNAME INITIALS DESIGNATION TELEPHONE NO.

4.2.1 Is your company a value adding supplier (i.e. registered as a vendor under the VAT Act of 1991, where NPAT + total labour cost > 25% of total revenue)?

YES NO

4.2.2 Is your company a recipient of Enterprise Development Contributions?*

YES NO

4.2.3 May the above mentioned information be shared and included in Transnet Supplier Database for future reference? *

"Prev

iew C

opy O

nly"

Page 273: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail RFP No. S.I.E 10032CIDB A Division of Transnet Limited Refurbishment of 3kV substations

Tender Page 19 of 34 T2.2 Part T2: Returnable Documents Returnable Schedules

YES NO

4.2.4 If you are successful in the tender/contract (where applicable) and this is awarded to your company / organisation, will this have a positive impact on your employment plans? *

YES NO

4.2.5 If yes (above) kindly provide the following information:

BLACK WHITE COLOURED INDIAN OTHER TOTAL

Permanent

Part Time

4.2.6 In terms of above kindly provide numbers on woman and disabled personnel:

BLACK WHITE COLOURED INDIAN OTHER TOTAL

Women

Disabled

4.2.7 Are any of your members/shareholders/directors ex employees of Transnet?

YES NO

4.2.8 Are any of your family members employees of Transnet?

YES NO

4.2.9 If Yes to points 4.2.7 & 4.2.8, list details of employees/ex-employees

SURNAME & INITIALS

IDENTITY NUMBER

NAME & ADDRESS OF OTHER FIRM

TITLE IN OTHER FIRM

% OWNED TYPE OF BUSINESS OF OTHER FIRM

IInntteerrnnaall TTrraannssnneett DDeeppaarrttmmeennttaall QQuueessttiioonnnnaaiirree ((ffoorr ooffffiiccee uussee oonnllyy))

Section 1: To be completed by the Transnet Requesting / Sourcing Department

TFR TRE TPT TPL TNPA TRN

Create Amend Block Unblock

Once-Off / Emergency Request

Extend

Delete Undelete

Supplier’s trading name

Supplier’s registered name

Please indicate if the Supplier has a contract with sourcing Transnet OD Yes No

If yes please submit a copy of the letter of award

a) What is being procured from the supplier?

i. Products only Yes No

ii. Services only Yes No

iii. Labour only Yes No

iv. Mix of services and products Yes No

v. Mix of services and labour Yes No

b) If your answer is YES to questions II, III, IV or V in paragraph a) above, please indicate whether

the relevant PAYE questionnaires have been forwarded to the appropriate Transnet Operational Divisions’ decision making bodies / Strategic Supply Management team for a directive /decision on tax withholding from payments to this supplier.

Yes No

c) If your reply to (b) is “NO”, please furnish reasons :

"Prev

iew C

opy O

nly"

Page 274: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail RFP No. S.I.E 10032CIDB A Division of Transnet Limited Refurbishment of 3kV substations

Tender Page 20 of 34 T2.2 Part T2: Returnable Documents Returnable Schedules

d) Certification and Approval of proposed Vendor Creation/Unblocking/Other Changes by Transnet Official with Appropriate Delegated Authority :

I HEREBY CERTIFY THAT THE TRANSNET DETAILED PROCUREMENT PROCESS (DPP) / PROCUREMENT MECHANISM HAS IN ALL RESPECTS BEEN ADHERED TO AND I THEREFORE APPROVE THE PROPOSED VENDOR CREATION/APPROVAL/OTHER CHANGES TO BE EFFECTED ON THE VENDOR MASTER

Grade Date Signature

Y Y Y Y M M D D

Tel No: Fax No:

Section 2: To be completed by the BEE Department (this section is for Confirmation/Determining of BEE Status) NARROW BASED (NB) BROADBASED (BBBEE)

BEE O/S BWBE DPBE MR CONTB. LEVEL

EME: <R5m

QSE: >R5m <R35m

LARGE: >R35m

VALIDITY DATE

Name

Grade Date Signature

Y Y Y Y M M D D

Y Y Y Y M M D D

"Prev

iew C

opy O

nly"

Page 275: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail RFP No. S.I.E 10032CIDB A Division of Transnet Limited Refurbishment of 3kV substations

Tender Page 21 of 34 T2.2 Part T2: Returnable Documents Returnable Schedules

TRANSNET LIMITED / CONTRACTORS / SUB-CONTRACTORS CONTRACTUAL SAFETY CLAUSES WHICH WILL FORM PART OF ANY RESULTING CONTRACT

The parties agree on the following arrangements according to section 37 (2) of the Occupational Health and Safety Act, 1993 (Act 85 of 1993) to ensure compliance by the mandatory with provisions of the Act. 1) That the Contractor is an “employer” in his own right as defined in section 1 of Act 85

of 1993 and that he must fulfil all his obligations as an employer in terms of the Act. 2) The Contractor shall comply with the requirements of Act 85 of 1993 in its entirety. 3) Where special permits are required, such as electrical switching, hot work permits, etc.

the Contractor shall obtain them from a person designated by Transnet Limited for this purpose, and all requirements of the Contractor must rigidly comply with the permit.

4) The Contractor shall conduct a risk assessment of the work to be performed by a

competent person prior to the commencement of work, to identify risks and hazards that persons may be exposed to, analyse and evaluate identified hazards.

5) The Contractor shall have a documented Health and Safety Plan based on the risks

and hazards identified before commencement of work. 6) The Health and Safety Plan shall include the following:

6.1 The safety management structure to be instituted with all appointments in terms of the Act and Regulations

6.2 The safe working methods and procedures to be implemented to ensure work are performed in compliance to the Act.

6.3 The safety equipment, devices and clothing to be made available by the Contractor to his employees.

6.4 The site access control measures pertaining to health and safety to be implemented.

6.5 Control measures for ensuring that the Health and Safety Plan is maintained and monitored for the duration of the contract.

7) The Contractor shall ensure that all work is performed under the close supervision of a

person trained to understand the hazards associated with the work performed and who has authority to ensure that the necessary precautionary measures are implemented.

8) The Contractor must appoint a Health and Safety Co-ordinator to liaise with Transnet

Limited on matters pertaining to occupational health and safety. 9) The appointed Safety Co-ordinator must liaise at least once a week with the* Health

and Safety Section / Risk Manager /Occupational Risk Manager of Transnet Limited. 10) The Contractor shall furnish the* Health and Safety Section/ Risk Manager/

Occupational Risk Manager of Transnet Limited immediately with full particulars of any sub-Contractor which he may involve in the contract in order that the sub-Contractor himself can be made aware of all the clauses in this contract pertaining to health and safety.

"Prev

iew C

opy O

nly"

Page 276: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail RFP No. S.I.E 10032CIDB A Division of Transnet Limited Refurbishment of 3kV substations

Tender Page 22 of 34 T2.2 Part T2: Returnable Documents Returnable Schedules

11) The Contractor shall stop any sub-contractor from executing work which is not in accordance with the Health and Safety Plan or which poses a threat to health and safety of persons.

12) The Contractor shall ensure that all his employees and visitors undergoes health and

safety induction pertaining to the hazards prevalent, proof of such training must be kept on file.

13) In the event where the risk assessment reveals the risk relating to working from an

elevated position the Contractor shall cause the designation of a competent person, responsible for the preparation of a Fall Protection Plan.

14) The Fall Protection Plan shall include:

14.1 A risk assessment of all work carried out from an elevated position 14.2 Procedures and methods to address all the identified risks per location 14.3 Evaluation of employee’s physical and psychological fitness necessary to work at

elevated position. 14.4 The training of employees working from an elevated position. 14.5 Procedure addressing the inspection, testing and maintenance of all fall protection equipment.

15) The Contractor shall advise the * Health and Safety Section / Risk Manager/

Occupational Risk Manager of Transnet Limited of any hazardous situations which may arise from work being performed either by the Contractor or his sub-Contractor.

16) Copies of all appointments required by the act must be given to * Health and Safety

Section / Risk Manager / Occupational Risk Manager of Transnet Limited. 17) The Contractor shall ensure that a Health and Safety File is available which shall

include all documentation as required by the Act, copy of his and his Sub-Contractors Risk Assessment and Health and Safety Plan.

18) All incidents referred to in Section 24 of the Act involving the Contractor and his Sub-

Contractor on Transnet Ltd premises, shall be reported as prescribed. Transnet Ltd hereby obtains an interest in the issue of any investigation, formal inquiry conducted in terms of Section 31 and 32 of the Act into any incident involving the Contractor, his Sub-Contractor, any person or machinery under his control on Transnet Ltd premises.

19) No alcohol or any other intoxicating substance shall be allowed on Transnet Ltd

premises. The Contractor shall not allow anyone under or suspected to be under the influence of alcohol or any other intoxicating substance on Transnet Ltd premises.

20) Contractor to ensure its employees undergo medical surveillance as required by

legislation 21) Contractor will be required to provide monthly safety performance reports and statistics 22) A letter of good standing in terms of Section 80 (Employer to register with the

Compensation Commissioner) of the Compensation for Occupational Injuries and Disease Act 1993 (Act 130 of 1993) must also be furnished.

23) All clauses in the contract pertaining health and safety form an integral part of the

contract and if not complied with may be construed as breach of contract.

"Prev

iew C

opy O

nly"

Page 277: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail RFP No. S.I.E 10032CIDB A Division of Transnet Limited Refurbishment of 3kV substations

Tender Page 23 of 34 T2.2 Part T2: Returnable Documents Returnable Schedules

*As applicable

Tenderer OH & S Management System Questionnaire

This questionnaire forms part of TFR tender evaluation process and is to be completed by all Tenderer’s and submitted with their tender offer. The objective of the questionnaire is to provide an overview of the status of the Tenderer’s OH&S management system. Tenderers will be required to verify their responses noted in their questionnaire by providing evidence of their ability and capacity in relevant matters. TFR will verify accuracy of this information during the physical visit as part of the tender evaluation.

The information provided in this questionnaire is an accurate summary of the company's occupational health and safety management system.

Company Name:

Signed: Name:

Position: Date:

Tender Description:

Tender Number:

Tenderer OH&S Management System Questionnaire Yes No

1. OH&S Policy and Management

- Is there a written company health and safety policy? - If yes provide a copy of the policy

- Does the company have an OH&S Management system e.g NOSA, OHSAS, IRCA System etc - If yes provide details

- Is there a company OH&S Management System, procedures manual or plan? - If yes provide a copy of the content page(s)

- Are health and safety responsibilities clearly identified for all levels of Management and employees? - If yes provide details

2. Safe Work Practices and Procedures

- Are safe operating procedures or specific safety instructions relevant to its operations available? - If yes provide a summary listing of procedures or instructions

- Is there a register of injury document? If yes provide a copy

- Are Risk Assessments conducted and appropriate techniques used? - If yes provide details

"P

review

Cop

y Only

"

Page 278: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail RFP No. S.I.E 10032CIDB A Division of Transnet Limited Refurbishment of 3kV substations

Tender Page 24 of 34 T2.2 Part T2: Returnable Documents Returnable Schedules

3. OH&S Training

Describe briefly how health and safety training is conducted in your company:

- Is a record maintained of all training and induction programs undertaken for employees in your company? - If yes provide examples of safety training records

4. Health and Safety Workplace Inspection

- Are regular health and safety inspections at worksites undertaken? -If yes provide details

- Is there a procedure by which employees can report hazards at workplaces? - If yes provide details

5. Health and Safety Consultation

- Is there a workplace health and safety committee?

- Are employees involved in decision making over OH&S matters? - If yes provide details

- Are there employee elected health and safety representatives? - Comments

6. OH&S Performance Monitoring

- Is there a system for recording and analysing health and safety performance statistics including injuries and incidents? - If yes provide details

- Are employees regularly provided with information on company health and safety performance? - If yes provide details

Is company registered with workmen’s compensation and up to date? - If yes provide proof of letter of good standing

- Has the company ever been convicted of an occupational health and safety offence? - If yes provide details

Safety Performance Report Monthly DIFR for previous months

"Prev

iew C

opy O

nly"

Page 279: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail RFP No. S.I.E 10032CIDB A Division of Transnet Limited Refurbishment of 3kV substations

Tender Page 25 of 34 T2.2 Part T2: Returnable Documents Returnable Schedules

DIFR = Number of Disabling injuries x 200000 divided by number of man hours worked for the period _______________________ Signed (Tenderer)

Previous Year No of Disabling Injuries

Total Number of employees

DIFR per month

January

February

March

April

May

June

July

August

September

October

November

December

"Prev

iew C

opy O

nly"

Page 280: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail RFP No. S.I.E 10032CIDB A Division of Transnet Limited Refurbishment of 3kV substations

Tender Page 26 of 34 T2.2 Part T2: Returnable Documents Returnable Schedules

TECHNICAL DATA SHEETS TO SPECIFICATIONS

(To be filled in by the Tenderer)

1.0 BBB0041: PREPARATION OF DRAWINGS FOR TRANSNET FREIGHT RAIL INFRASTRUCTURE.

1.1 CAD Software: _______________________________________________________

2.0 BBB0496: 3KV RECTIFIER

2.1 Make and Manufacturer: ______________________________________________

2.2 Number of diodes per branch:___________________________________________

2.3 Type of Diode:_______________________________________________________

2.4 Full load current rating of diode. IFRMS: _____________________________________

2.5 Average current rating of diode IFAVM: _____________________________________________

2.6 Repetitive Peak Reverse Voltage of diode:_________________________________

2.7 Surge forward current 10milli seconds Sine Wave:___________________________

2.8 Method of cooling of rectifier:____________________________________________

2.9 Method of temperature sensing: __________________________________________

2.10 Type of insulation used for frame to the floor: ________________________________

2.11 Physical dimensions of rectifier unit Height: ______ Breadth: _______ Width:______

2.12 Names of suppliers where rectifier diodes can be sourced: _____________________

____________________________________________________________________

2.13 Method of correct torque adjustment for heat sinks:___________________________

___________________________________________________________________

2.14 Make and rating of fuses: ______________________________________________

3.0 BBB0845: HIGH VOLTAGE METAL OXIDE SURGE ARRESTORS

3.1 Type and make _______________________________________________________

3.2 Manufacturer of equipment _______________________________________________

3.3 Protection voltage rating of lightning surge ________________________________ kV

3.4 Impulse discharge current rating of lightning surge protectors _________________ kA

3.5 Make and type of protection against switching surges __________________________

4.0 BBB0937: CURRENT TRANSFORMERS (88kV)

4.1 DESIGN DETAIL

4.1.1 Manufacturers name: __________________________________________________

4.1.2 Highest voltage for equipment: ______________ kV

"Prev

iew C

opy O

nly"

Page 281: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail RFP No. S.I.E 10032CIDB A Division of Transnet Limited Refurbishment of 3kV substations

Tender Page 27 of 34 T2.2 Part T2: Returnable Documents Returnable Schedules

4.1.3 Nominal r.m.s voltage: ____________________ kV

4.1.4 Rated insulation level: ________________________ kV

4.1.5 Rated frequency: __________________________ Hz

4.2 DETAIL OF CURRENT TRANSFORMERS.

MEASURING CURRENT TRANSFORMERS

4.2.1 Transformation ratio: _________________

4.2.2 Rated secondary current: ________ Ampere

4.2.3 Rated secondary current: ____________ Ampere

4.2.4 Accuracy class: ________________

4.2.5 Rated Burden: _________________ VA

4.2.6 Rated short-time current: _________________kA for __________ seconds

PROTECTION CURRENT TRANSFORMERS

4.2.7 Transformation ratio: _________________

4.2.8 Rated primary current: ________ Ampere. Rated secondary current: ________ Ampere

4.2.9 Rated secondary current: ____________ Ampere

4.2.10 Accuracy class: ________________

4.2.11 Rated Burden: _________________ VA

4.2.12 Rated short-time current: _________________kA for __________ seconds

5.0 BBB1267: OUTDOOR HIGH VOLTAGE AC CIRCUIT BREAKERS

5.1 Make and manufacturer ___________________________________________

5.2 Rated Voltage _________________________________________ kV.

(Highest rated voltage for equipment)

5.3 Rated Insulation level _____________________________________________ kV.

(Rated lightning withstand Voltage)

5.4 Number of poles:________________________________

5.5 Rated short circuit breaking current ___________________________________ kA.

5.6 Rated normal current ___________________________________ A.

5.7 Breaker operating time:

5.7.1 Closing_________________________________________________________ ms.

5.7.2 Opening________________________________________________________ ms.

5.8 Number of operations after which breaker contact maintenance / measurement is required:

5.8.1 Under full load conditions__________________________________________

"Prev

iew C

opy O

nly"

Page 282: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail RFP No. S.I.E 10032CIDB A Division of Transnet Limited Refurbishment of 3kV substations

Tender Page 28 of 34 T2.2 Part T2: Returnable Documents Returnable Schedules

5.8.2 Under fault conditions _____________________________________________

5.9 First Pole to Clear Factor___________________________________________

5.10 DC control voltage: _______________________________________V

6.0 BBB2502: BATTERY AND BATTERY CHARGER

6.1 BATTERY

6.1.1 Manufacturer _______________________________________________

6.2 BATTERY CHARGER:

6.2.1 Manufacturer _______________________________________________

6.2.2 Supply voltage: _______________________________________________

6.2.3 Ampere hour rating: ___________________________________________

6.2.4 Construction:

Floor mounted: _____________YES / NO Wall mounted: _____________YES / NO

7.0 BBB2721: SUBSTATION PANELS

7.1 Manufacturer: _____________________________________________

7.2 Single AC primary circuit breaker control panel. _____________________YES/NO

7.3 Single AC/DC distribution panel. _________________________________YES/NO

7.4 Combination of 1.1 and 1.2 into one panel. _________________________YES/NO

7.5 DC earth leakage relay:

Fitted inside panel / external to panel. ____________________________

7.6 Nameplate of substation to be fitted on the panel. ___________________

8.0 BBB3005: 3kV DC UNDER VOLTAGE RELAY

8.1 Type (BBB3005 clause 2.0)____________________________________

8.2 Encapsulated Voltage Devider: _________________________________YES / NO

If Yes – Type of Resistors: _____________________________________

9.0 WAVE FILTER

9.1 BBB3139: Capacitors

9.1.1 Capacitance Value (CN): _______________________________________________

9.1.2 Capacitance Tolerance: _______________________________________________

9.1.3 Detailed Description of Capacitor: _______________________________________

9.1.4 Overall Mass of the Capacitor: __________________________________________

9.1.5 Overall Dimensions of the Capacitor: _____________________________________

9.1.6 Dielectric Insulating Medium: ___________________________________________

"Prev

iew C

opy O

nly"

Page 283: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail RFP No. S.I.E 10032CIDB A Division of Transnet Limited Refurbishment of 3kV substations

Tender Page 29 of 34 T2.2 Part T2: Returnable Documents Returnable Schedules

9.1.7 Container Material: ___________________________________________________

9.1.8 Rated Current in RMS (IN): _____________________________________________

9.1.9 Rated Voltage in RMS (UN): ____________________________________________

9.1.10 Rated Output (QN): ___________________________________________________

9.1.11 Temperature Category: _______________________________________________

9.1.12 Maximum Permissible AC Current: ______________________________________

9.1.13 Maximum Permissible AC Voltage: ______________________________________

9.1.14 Maximum Permissible Temperature: _____________________________________

9.1.15 Capacitor Losses: ____________________________________________________

9.1.16 Active Power: _______________________________________________________

9.1.17 Steady State Condition: _______________________________________________

9.1.18 Residual Voltage: ____________________________________________________

9.1.19 BIL (Bushing): _______________________________________________________

9.1.20 Life Expectancy: _____________________________________________________

9.2 BBB3162: Inductors

9.2.1 Inductor Tolerance (mH) at operational frequencies: _________________________

9.2.2 Max Nominal Inductance at operational frequencies: _________________________

9.2.3 Number of Turns (N): _________________________________________________

9.2.4 Rated Peak Current in Amperes (I): ______________________________________

9.2.5 Rated DC Current in Amperes (IN): _______________________________________

9.2.6 Overall Mass of the Inductor (kg):________________________ ________________

9.2.7 Overall Dimensions of the Inductor (mm): __________________________________

9.2.8 Max Ambient Temperature in °C (Ta):_____________________________________

9.2.9 Max Surface Temperature in °C (Ts): _____________________________________

9.2.10 Maximum Permissible Operational Temperature in °C: _______________________

9.2.11 Maximum Permissible AC Current in Amperes: ______________________________

9.2.12 Maximum Permissible AC Voltage in Volts: _________________________________

9.2.13 Maximum Energy Stored in Inductor at rated peak current (I): __________________

10.0 BBB3890: 3kV REACTOR

10.1 Manufacturers name:_________________________________________________

10.2 Inductance ________________________________________________________

10.3 Continuous Current rating______________________________________________

"Prev

iew C

opy O

nly"

Page 284: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail RFP No. S.I.E 10032CIDB A Division of Transnet Limited Refurbishment of 3kV substations

Tender Page 30 of 34 T2.2 Part T2: Returnable Documents Returnable Schedules

11.0 BBB4724: POSITIVE ISOLATOR

11.1 Manufacturers name:_________________________________________________

11.2 Continuous Current rating for:

11.2.1 Positive Isolator switch: _______________________________________________

11.2.2 Positive Isolator Earthing switch: ________________________________________

11.3 Mechanical Interlocking System Type (BBB4724 clause 6.37__________________

12.0 BBB5019: MAIN TRACTION TRANSFORMER

12.1 Manufacturers name_____________________________________________

12.2 TRANSFORMER DETAIL

12.2.1 Primary voltage rating: ___________________________________________kV

12.2.2 Secondary voltage rating: _________________________________________kV

12.2.3 Rated power: __________________________________________________MVA

12.2.4 Impedance %: __________________________________________________

12.2.5 Off circuit tap switch:

No of positions: ____________________ %Steps: _____________________

12.2.6 Vector group: ___________________________________________________

12.3 TANK AND TANK COVER

12.3.1 Free-breathing:_________________________________________________ Yes/No

12.3.2 Tank cover bolted to tank: ________________________________________ Yes/No

12.3.3 Radiators galvanised: ____________________________________________ Yes/No

12.3.4 Method of Cooling: ______________________________________________

12.3.5 Overall dimensions: Length________mm. Breadth______mm. Height________mm.

12.3.6 Winding material: HV_________________ LV_________________

12.3.7 Mass of core and windings: _____________________________________kg

12.3.8 Oil capacity:__________________________________________________ (Litres)

12.3.9 Mass of transformer complete with oil: ______________________________kg

12.3.10 Adjustable axial coils provided: ___________________________________ Yes/No

12.3.11 Type of breather and dehydrating agent ____________________________

The following information refers to the transformer when connected on the principal tapping and appropriate reference temperature for the class of insulation used.

12.3.12 Iron loss (Watts) :______________________________________________

12.3.13 Copper loss at full load: _____________________at__________________°C

12.3.14 Total load losses (Watts):____________________at __________________°C

"Prev

iew C

opy O

nly"

Page 285: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail RFP No. S.I.E 10032CIDB A Division of Transnet Limited Refurbishment of 3kV substations

Tender Page 31 of 34 T2.2 Part T2: Returnable Documents Returnable Schedules

12.3.15 Impedance at full load (%Z): _____________________________________

12.3.16 Reactance (% X): _____________________________________________

12.3.17 Regulation at full load at: 1.0 PF ________Percent, 0.8 PF _________ Percent at

_________°C

12.3.18 Efficiency at full load at: 1.0 PF ________Percent, 0.8 PF _________Percent at

________ °C

12.3.19 Temperature rise at rated voltage and power of:

Windings:______________°C

Top oil : _______________°C

13.0 BBB8204: AUXILLARY TRANSFORMER

13.1 Manufacturers name:___________________________________________

13.2 TRANSFORMER DETAIL

13.2.1 Type of transformer: Outdoor_______________ Indoor: ______________

13.2.2 Number of phases: Single phase ____________ Three phase: _____________

13.2.3 Rated power: _________________________________________________kVA

13.2.4 Impedance %: _______________________________________________

13.2.5 Primary voltage rating: _________________________________________kV

13.2.6 Secondary voltage rating: _______________________________________kV

13.2.7 Tapping switch.

No of positions: _________________ %Steps: ______________________

13.2.8 Vector group: ________________________________________________

13.2.9 Free Breathing: ______________________________________________Yes/No

13.2.10 Sealed _____________________________________________________Yes/No

13.2.11 Welded cover: ________________________________________________Yes/No

13.2.12 Method of Cooling:____________________________________________

13.2.13 Overall dimensions: Length______mm. Breadth______mm. Height_______mm

13.2.14 Winding material: HV_________________ LV_______________

13.2.15 Mass of core and windings : ____________________________________kg

13.2.16 Oil capacity:_________________________________________________(Litres)

13.2.17 Mass of transformer complete with oil:_____________________________kg

13.2.18 HV end turns insulation reinforced Yes/No

13.2.19 Type of breather and dehydrating agent: ____________________________

The following information refers to the transformer when connected on the principal tapping and appropriate reference temperature for the class of insulation used.

"Prev

iew C

opy O

nly"

Page 286: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail RFP No. S.I.E 10032CIDB A Division of Transnet Limited Refurbishment of 3kV substations

Tender Page 32 of 34 T2.2 Part T2: Returnable Documents Returnable Schedules

13.2.20 Iron loss (Watts) :______________________________________________

13.2.21 Copper loss at full load:_______________________at_________________°C

13.2.22 Total load losses (Watts):_____________________ at ________________ °C

13.2.23 Impedance at full load (percentage)_____________Z _________________ X

13.2.24 Regulation at full load at: 1.0 PF ______Percent, 0.8 PF ______ Percent at______°C

13.2.25 Efficiency at full load at: 1.0 PF ______Percent, 0.8 PF ______Percent at ______ °C

13.2.26 Temperature rise at rated voltage and power of:

Windings: _______________°C

Top oil: _________________°C

14.0 BBB7842: HIGH VOLTAGE AC DISCONNECTOR AND EARTHING SWITCH

DISCONNECTOR EARTHINGWITCH

14.1 Name of manufacturer. ……………………… ………………………..

14.2 Type number ……………………… ………………………..

14.3 Number of poles. ……………………… ………………………..

14.4 Indoor/Outdoor. ……………………… ………………………..

14.5 Rated voltage. ……………………… ………………………..

14.6 Rated insulation level. ……………………… ………………………..

14.6.1 Rated 1 minute power frequency withstand voltage. …………… ………..……

14.6.2 Rated lightning impulse withstand voltage. …………………. ………………………..

14.7 Rated frequency. ……………………… ..……………………….

14.8 Rated normal current. …………………….. .……………………….

14.9 Rated short circuit making current …………………….. …………………………

14.10 Rated short time withstand current ……………………… ………………………….

14.11 Mass of complete unit. ……………………… ……………………..…..

14.12 Minimum clearance in air:

14.12.1 Between poles. ……………………… ……………………….. .

14.12.2 To earth. ………………………. ………………………..

14.12.3 For isolating distance. …………................... ………………………..

14.13 Type of closing mechanism. ………………………. ………………………..

14.14 Height above ground of lowest HV connection.……………… ………………………..

DISCONNECTOR EARTHING WITCH

14.15 Length of insulator (taut string measurement) …….............. ………………………...

"Prev

iew C

opy O

nly"

Page 287: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail RFP No. S.I.E 10032CIDB A Division of Transnet Limited Refurbishment of 3kV substations

Tender Page 33 of 34 T2.2 Part T2: Returnable Documents Returnable Schedules

14.16 Type test certificate ……………………. …………………………

14.16.1 Testing authority ……………………. …………………………

14.16.2 Test number ……………………. ………………………….

14.17 Insulators:

14.17.1 Type test certificate number ……………………. ………………………….

14.17.2 Testing authority ……………………. …………………………..

15.0 CEE.0099.2010: 3kV DC HIGH SPEED CIRCUIT BREAKERS

15.1 Make and manufacturer: _______________________________________

15.2 Experience with tendered design of breaker: (CEE.0099.2002 Clause 9.1.3)

NUMBER SUPPLIED WHERE INSTALLED DATE SUPPLIED

___________________________________________________________________

___________________________________________________________________

___________________________________________________________________

___________________________________________________________________

15.3 Continuous current rating of breaker : ___________________________________

15.4 Rated voltage of breaker : _________________________________________

15.5 Mechanically latched Yes/No. _____________________________________

15.6 Magnetically latched Yes/No. _____________________________________

15.7 Main contact material ___________________________________________

15.8 Arcing contacts fitted Yes/No. ____________________________________

15.9 Contact material of main contact (or arcing contact, if fitted)

___________________________________________________________________

16.0 AUTOMATIC CHANGE-OVER

16.1 Make and manufacturer: _______________________________________

16.2 Physical dimensions and operating mass of unit:

Length___________________________mm. Height______________________mm.

Depth____________________________mm. Mass_______________________mm

16.3 Material of cabinet______________________

16.4 Manufacturer and type of miniature circuit breakers __________________________

16.5 Maximum continuous current rating of circuit breakers ________________________

16.6 Manufacturer and type of contactors ______________________________________

16.7 Maximum continuous current rating of contactors ________________________ Amps

"Prev

iew C

opy O

nly"

Page 288: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail RFP No. S.I.E 10032CIDB A Division of Transnet Limited Refurbishment of 3kV substations

Tender Page 34 of 34 T2.2 Part T2: Returnable Documents Returnable Schedules

16.8 Manufacturer and type of change-over timers ________________________________

16.9 Timing range of timers _____________________________________________ Seconds

17.0 STEEL ROLL-UP DOORS

17.1 Make and manufacturer _______________________________________________

TENDERER'S SIGNATURE .................................................... DATE: ........................………..

"Prev

iew C

opy O

nly"

Page 289: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet Freight Rail RFP No. S.I.E 10032CIDB A Division of Transnet Limited

Tender Page 1 of 1 Contents

CONTENTS

Document reference

Title: The refurbishment of South Portal, Quail, Nottingham Road, Danskraal, Elandslaagte, Wasbank and Glencoe 3kV DC traction substations.

No of pages

THE TENDER

Part T1 Tendering procedures

T1.1 Tender Notice and Invitation to Tender 5

T1.2 Tender Data 6

Part T2 Returnable documents

T2.1 List of Returnable Documents 3

T2.2 Returnable Schedules 14

THE CONTRACT

Part C1 Agreement and Contract Data

C1.1 Form of Offer and Acceptance and schedule of deviations

3

C1.2 Contract Data 15

C1.3 Form of Guarantee 5

C1.4 Adjudicator’s Appointment 11

Part C2 Pricing data

C2.1 Pricing Instructions 3

C2.2 Activity Schedules 15

Part C3 Scope of Work

C3 Scope of Work 46

Part C4 Site information

C4 Site Information 3

"Prev

iew C

opy O

nly"

Page 290: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Suppliers Code of Conduct

"Prev

iew C

opy O

nly"

Page 291: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

Transnet aims to achieve the best value for money when buying or selling goods and obtaining services. This, however, must be done in an open and fair manner that supports and drives a competitive economy. Underpinning our process are several acts and policies that any supplier dealing with Transnet must understand and support.

These are:

>> Transnet Procurement Policy - A guide for tenderers; >> Section 217 of the Constitution - the five pillars

of Public PSCM (Procurement and Supply Chain Management): fair, equitable, transparent, competitive and cost effective;

>> The Public Finance Management Act (PFMA); >> The Broad Based Black Economic Empowerment Act

(BBBEE); and >> The Anti-Corruption Act.

This code of conduct has been compiled to formally apprise Transnet Suppliers of Transnet’s expectations regarding behaviour and conduct of its Suppliers.

Prohibition of Bribes, Kickbacks, Unlawful Payments, and Other Corrupt Practices

Transnet is in the process of transforming itself into a self-sustaining State Owned Enterprise, actively competing in the logistics industry. Our aim is to become a world class, profitable, logistics organisation.As such, our transformation is focused on adopting a performance culture and to adopt behaviours that will enable this transformation.

Transnet will not participate in corrupt practices. Therefore, it expects its suppliers to act in a similar manner.

>> Transnet and its employees will follow the laws of this country and keep accurate business records that reflect actual transactions with, and payments to, our suppliers.

Suppliers Code of Conduct

"Prev

iew C

opy O

nly"

Page 292: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

>> Employees must not accept or request money or anything of value, directly or indirectly, from suppliers.

Employees may not recieve anything that is calculated to:

– Illegally influence their judgement or conduct or to influence the outcome of a sourcingactivity;

– Win or retain business or to influence any act or decision of any person involved in sourcing decisions; gain an improper advantage.

>> There may be times when a supplier is confronted with fraudulent or corrupt behaviour of Transnet employees. We expect our suppliers to use our “Tip-offs Anonymous” Hotline to report these acts - 0800 003 056.

Transnet is firmly committed to free and competitive enterprise.

>> Suppliers are expected to comply with all applicable laws and regulations regarding fair competition and antitrust practices

>> Transnet does not engage non-value adding agents or representatives solely for the purpose of increasing BBBEE spend (fronting).

Transnet’s relationship with suppliers requires us to clearly define requirements, to exchange information and share mutual benefits.

>> Generally, suppliers have their own business standards and regulations. Although Transnet cannot control the actions of our suppliers, we will not tolerate any illegal activities. "Prev

iew C

opy O

nly"

Page 293: Part C3- Generic · PARTICULAR / GENERIC SPECIFICATIONS ... BBB5452 version 5: ... Specification for installation of cables. CEE.0045.2002/1: ...

TIP-OFFS ANONYMOUS HOTLINE

0800 003 056

These include, but are not limited to:

– Misrepresentation of their product (origin of manufacture, specifications, intellectual property rights, etc);

– Collusion;– Failure to disclose accurate information

required during the sourcing activity (ownershipfinancial situation, BBBEE status, etc.);

– Corrupt activities listed above; and harassment, intimidation or other aggressive actions towards Transnet employees.

>> Suppliers must be evaluated and approved before any materials, components, products or services are purchased from them. Rigorous due diligence must be conducted and the supplier is expected to participate in an honest and straight forward manner.

>> Suppliers must record and report facts accurately, honestly and objectively. Financial records must be accurate in all material respects.

Conflict of Interest

A conflict of interest arises when personal interests or activities influence (or appear to influence) the ability to act in the best interests of Transnet. Examples are:

>> Doing business with family members. >> Having a financial interest in another company in

our industry.

Show that you support good business practice by logging onto

www.transnet-suppliers.net and completing the form.

This will allow us to confirm that you have received, and agree to, the terms and conditions set out in our Suppliers Code of Conduct."Prev

iew C

opy O

nly"