Panek Marseille
-
Upload
shankaranarayanan-gopal -
Category
Documents
-
view
223 -
download
0
Transcript of Panek Marseille
-
8/11/2019 Panek Marseille
1/28
NIVERSITY OFU DORTMUND
MILP Approach to the
Axxom Case Study
Sebastian Panek
-
8/11/2019 Panek Marseille
2/28
NIVERSITY OFU DORTMUND
Introduction
What is this talk about?
MILP formulation for the scheduling problem provided
by Axxom (lacquer production)
Whats new since our meeting in Sept. 02?
Improved model and solution procedure, new results
What about modeling TA as MILP?
This work is still in progress...
-
8/11/2019 Panek Marseille
3/28
NIVERSITY OFU DORTMUND
Overview
Short problem description
MILP formulation
Solution procedure Emprical studies
Conclusions
-
8/11/2019 Panek Marseille
4/28
NIVERSITY OFU DORTMUND
Short problem description
-
8/11/2019 Panek Marseille
5/28
NIVERSITY OFU DORTMUND
Additional problem
characteristics Additional restrictions for pairs of tasks:
start-start restrictions
end-start restrictions
end-end restrictions
Parallel allocation of mixing vessels
Machine allocation
allowed
interval
-
8/11/2019 Panek Marseille
6/28
NIVERSITY OFU DORTMUND
Problem simplifications
Labs are non-bottleneck resources, no exclusive
resource allocation is needed (provided by Axxom)
Individual colors for lacquers => many different
products
No batch merging is possible
Only few jobs exceeding max. batch capacity
Batch splitting is not considered
-
8/11/2019 Panek Marseille
7/28
NIVERSITY OFU DORTMUND
General approaches
For short-term scheduling problems in the processing
industry [Kondili,Floudas, Pantelides, Grossmann,...]:
State Task Networks (STN)
Resource Task Networks (RTN)
Early formulations: discrete time
Recent work: continuous time
Task 1
Task 2
State A
State B
State C1
1
1
1
-
8/11/2019 Panek Marseille
8/28
NIVERSITY OFU DORTMUND
General approaches (2)
Advantages:
Batch splitting/merging
Mass balances
Individual modeling of products
Restrictions on storages
Disadvantages:
Continuous and discrete time models tend to require many
points of time, number difficult to estimate Very detailed view of the problem not always necessary
Problem: large models, difficult to solve
-
8/11/2019 Panek Marseille
9/28
NIVERSITY OFU DORTMUND
Our approach: sequencing based
continuous time model Continuous time
Individual representation of time for machines
Focused on tasks and machines Products (states) are not considered explicitly
Fixed batch sizes(no merging and splitting of
batches)
Grows according to the number of tasks and not tothe time horizon
-
8/11/2019 Panek Marseille
10/28
NIVERSITY OFU DORTMUND
MILP formulation of the
continuous time model Real variables for starting and ending times of tasks
Binary variables for the machine allocation
task iis processed on machine k:
Binary variables for the sequencing of tasks task iis processed before task hon machine k:
ii es,
1ik
0,1 hikihk
-
8/11/2019 Panek Marseille
11/28
NIVERSITY OFU DORTMUND
Starting and ending times for
allocated machines Starting and ending dates for tasks ion machines k
Extra linear equations are needed to express
nonlinear products of binary and real variables
ikiik
ikiik
ee
ss
:
:
-
8/11/2019 Panek Marseille
12/28
NIVERSITY OFU DORTMUND
Restrictions on binary variables
Each task must be processed on 1 machine
If both tasks iand hare processed on machine kthen
either iis scheduled before hor vice versa
1k
ik
hkikhikihk
-
8/11/2019 Panek Marseille
13/28
NIVERSITY OFU DORTMUND
Sequencing restrictions
Tasks i, hprocessed on the same machine kmust
not overlap each other
Set iff task iis finished before task h
))(1(
))(1()1(
hkikihkhkik
hkikihkhkik
Mmse
MMse
1ihk
-
8/11/2019 Panek Marseille
14/28
NIVERSITY OFU DORTMUND
Objective function
Minimize too late and too early job completions
,0,max
0,maxmin
i
ii
i
ii
edeadline
deadlineeJ
-
8/11/2019 Panek Marseille
15/28
NIVERSITY OFU DORTMUND
Additional heuristics
1. Non-overtaking of non-overlapping jobs
2. Non-overtaking of equal-typed jobs (M. Bozga)
3. Earliest Due Date (EDD)
hkikhi sereleasedeadline thenif
hkikhihi setypetypedeadlinedeadline thenandif
hkikhi sedeadlinedeadline thenif
-
8/11/2019 Panek Marseille
16/28
NIVERSITY OFU DORTMUND
2-step solution procedure
1. Apply heuristics 3(EDD) by fixing some
variables
2. Solve the problem
3. Relax and fix some variables according to
heuristics 1+2
4. Solve the problem again reusing previous solutionas initial integer solution
-
8/11/2019 Panek Marseille
17/28
NIVERSITY OFU DORTMUND
How is the model influenced
by the heuristics?
N: #Tasks, M: #Machines
Most binary variables are variables.
Worst case: # variables = O(N2
M) (!!!)(i,h=1...N, k=1...M)
# real variables = ~2NM
But:
When using heuristics, many binary variables are fixedand disappear from the model.
We want to reduce O(N2M) to O(NM)! How that?
ihk
ihk
-
8/11/2019 Panek Marseille
18/28
NIVERSITY OFU DORTMUND
A little example:
1 machine, 4 jobs, 1 task/job
Job# 1 2 3 4
Release 0 1 1 3
Deadline 2 3 4 5
Type 1 1 2 2
ihk* **
* **
* * *
* * *
Matrix of
variablesi=1
2
3
4h=1 2 3
4
-
8/11/2019 Panek Marseille
19/28
NIVERSITY OFU DORTMUND
Heuristics #1
non-overlapping jobs
Job# 1 2 3 4
Release 0 1 1 3
Deadline 2 3 4 5
Type 1 1 2 2
ihk* 1*
* 1*
* * *
0 0 *
Matrix of
variablesi=1
2
3
4h=1 2 3
4
-
8/11/2019 Panek Marseille
20/28
NIVERSITY OFU DORTMUND
Heuristics #2
equal-typed jobs
Job# 1 2 3 4
Release 0 1 1 3
Deadline 2 3 4 5
Type 1 1 2 2
ihk1 1*
0 1*
* * 1
0 0 0
Matrix of
variablesi=1
2
3
4h=1 2 3
4
-
8/11/2019 Panek Marseille
21/28
NIVERSITY OFU DORTMUND
Heuristics #2
EDD
Job# 1 2 3 4
Release 0 1 1 3
Deadline 2 3 4 5
Type 1 1 2 2
ihk1 11
0 11
0 0 1
0 0 0
Matrix of
variablesi=1
2
3
4h=1 2 3
4
-
8/11/2019 Panek Marseille
22/28
NIVERSITY OFU DORTMUND
Empirical studies on the Axxom
Case Study
model scaled from 4up to 29jobs
Jobs in job table sorted according to deadlines
2-stage solution procedure (heuristics 3, 1+2) CPU usage limited to 20+20minutes
Measurement of solution time,
equations, real and binary variables,
objective values and bounds
Software: GAMS+Cplex
Hardware: 1.5 GHz Athlon, 1 GB Ram
-
8/11/2019 Panek Marseille
23/28
NIVERSITY OFU DORTMUND
Objective values
lower
bounds
integer
solutions
gap
-
8/11/2019 Panek Marseille
24/28
NIVERSITY OFU DORTMUND
Solution times
20 min.limit was
active for
>10 jobs
-
8/11/2019 Panek Marseille
25/28
NIVERSITY OFU DORTMUND
Variables and Equations
equations
total
variables
binary
variables
~50% of all
Variables!
U D
-
8/11/2019 Panek Marseille
26/28
NIVERSITY OFU DORTMUND
Gantt chart: 29 jobs
2h of computation time, first integer solution after few min.(node 173)
U D
-
8/11/2019 Panek Marseille
27/28
NIVERSITY OFU DORTMUND
22 jobs, moving horizon procedure
Horizon: 7 jobs, 16 steps a 25 minutes, 300 MHz machine
U D
-
8/11/2019 Panek Marseille
28/28
NIVERSITY OFU DORTMUND
Conclusions from empirical
studies
EDD heuristics at 1. stage helps finding integer solutions quickly
(even for large instances!)
2. stage usually cannot find better solutions (in short time)...
but the number of binary variables is significantly reduced fromO(N2M)to O(NM)without restricting the problem too much
for