Pali Manganese Ore Deposit - Welcome to...
Transcript of Pali Manganese Ore Deposit - Welcome to...
PRE FEASIBILITY REPORT
of
Pali Manganese Ore Deposit
Located in Village-Pali, Tehsil- Parseoni, Dist-Nagpur,
Maharashtra
( Area – 4.80 Ha)
Submitted to
STATE LEVEL EXPERT APPRAISAL COMMITTEE (SEAC-I)
MINISTRY OF ENVIRONMENT & FOREST
GOVT. OF MAHARASHTRA
Project Proponent
Anil M Gupta & Others
AT & PO- Khapa- 441101
Dist.- Nagpur, Maharashtra
EIA Consultant
POLLUTION & ECOLOGY CONTROL SERVICES
Near Dhantoli Police Station, Dhantoli, Nagpur-440012 (Maharashtra)
Pre Feasibility Report of Pali Manganese Ore Deposit
1
1. EXECUTIVE SUMMARY
This Pre Feasibility Report has been prepared for the, Pali Manganese Ore
Deposit over an area of 4.80 hectares falling in Villages- Pali, Tehsil- Parseoni,
Dist-Nagpur, Maharashtra in accordance with the Notification of MoEF S.O. 1533
dated 14th September 2006.
In order to obtain environmental clearance as per the EIA Notification 2006 the
prefeasibility report is submitted along with the application Form 1. The project is
categorized as Category B under the schedule 1 (a).
Developmental activities like industries or mining project may cause temporary
damage to land, forest and induce changes in the quality of air, water, flora and
fauna of the area. But, there are has favorable effect of industrialization on social
development and progress of the Nation. For overall gain, it is necessary to strike
a balance between the two aspects of economy and ecology and ensure that
impacts on the environment are minimized with improvement in socio-economic
conditions. This is better achieved through a well-planned approach of EMP
relevant to the area under consideration.
Manganese ore is mostly used in Steel plants, Ferro-Manganese plants and
Manganese based chemicals and compounds for various applications. The high
manganese steel is very hard and resistant to wear and tear and is used for
making rock crushers, rail road, armor plates and burglar proof safes. It is also
used in dry batteries, animal feed, paint industries. The mine is developed as
opencast for the production of Manganese of 4,500 TPA capacity. Crusher of
adequate capacity has been suggested for aggregate production in desired sizes
as per the demand.
The area for which prospecting Report is prepared located in the jurisdiction of
village - Pali, Dist - Nagpur(MS) ' The applicant has been granted PL in the area by
State Govt' of Maharashtra for carrying out prospecting operation in the area for
Manganese ore over an area of 5'36 Ha' vide Govt. order no. PLS-1698
ll43ll7657ruDYOG - 9 dI' 21'07' 2003 and DGM order no. PLV-N - 3601200313840
dt' 20'09' 2003 valid for 2years from the date of agreement i.e. 26'4'2004'.
Pre Feasibility Report of Pali Manganese Ore Deposit
2
2. INTRODUCTION OF THE PROJECT / BACKGROUND INFORMATION.
i) Identification. of Project and Project Proponent
The Applicant, by the name Anil M Gupta & Others has praposed to plan
Manganese production of 4,500 TPA capacity. The applicant conducted
prospecting operations by way of pitting & establishes the presence of
Manganese mineralization in the area. The registered office of the company is
located in AT & PO – Khapa, District – Nagpur – 441 401. The applicant is a
private individual and legal heirs ate engaged in mining and trading of minerals.
Manganese ore is mainly used for steel making. The high manganese steel is
very hard and resistant to wear and tear and is used for making rock crushers,
rail road, armor plates and burglar proof safes. It is also used in dry batteries,
animal feed, paint industries. Thus the company plans to set up Manganese
mineralization of 4,500 TPA in Pali, Tehsil- Parseoni, Dist- Nagpur,
Maharashtra. In order to cater the requirement of Manganese, the company
decided to undertake manganese mine.
The company was granted the Government of Maharashtra for prospecting
License which was granted over and area of 5.36 Ha. vide Govt. order no. PLS-
1698/1431/7657/UDYOG – 9 dt. 21.07. 200F 3. It is to mention that the PL was
granted to M/s Mulchand Gupta & Sons but due to sudden demise of Mulchand
Gupta the PL was transferred to his legal heirs Anil M Gupta & Others of
Khapa,Dist – Nagpur(MS).
The area has been explored by detailed land survey, gridding, contouring,
levelling, surface geological mapping, drilling core drill holes, logging to running
meterage. The applicant conducted prospecting operations by way of pitting &
establish the presence of Manganese mineralization in the area. Accordingly the
applicant reduce the area to 4.80 Hr. & applied for M L Now, due to Amendment
of MM (D & R) Act,1957 on 12.01.2015 the provision of grant all Mining Leases
of Schedule minerals is made for 50 years without renewal condition as per
Section 8A(6) of Ammended MM ( D & R) Act,2015 . Now, there is further
amendment of MCR,1960 on 04.03.2016 as Minerals (Other than Atomic and
Hydrocarbon Energy Minerals) Concession Rules,2016.
Pre Feasibility Report of Pali Manganese Ore Deposit
3
Accordingly Mining Plan including Progressive Mine Closure Plan is prepared and
submitted Under Rule 17(3) of Minerals (Other Than Atomic and Hydrocarbon
Energy Minerals) Concession Rules,2016 as required for grant of mining lease for
50 years as per Section 8A(6) of MM ( D & R) Act,2015 .
Brief description of nature of the project
The present Pre Feasibility Report has been prepared for the Pali Manganese Ore
Deposit admeasuring an area of 4.80 Ha. The proposed area is having flat
topography and is covered with lateritic soil and overburden having thickness of
l.2m to 2.0m in the area. Pali and other villages are in the surrounding. The
proposed area is surrounded by agricultural land and forest land.
Pre Feasibility Report of Pali Manganese Ore Deposit
4
Key Plan of Pali Manganese Ore Deposit
The ore is extracted with the help of heavy machineries for digging, excavation
and removal of Ore, over burden and mine reject. All operations of mining,
including drilling, deep hole blasting, secondary blasting and/or plaster shooting,
excavation, loading & transportation on single shift basis, shall form the complete
mining operation.
The proposed area for which Prospecting Report is explored through trial pits
spread in the central and southern parts of the area and these pits clearly
indicates the types of formation and local geology of the area. The local
topography of the area is flat. Manganese ore and associated formation which
are occurring at Pali village is belonging to Sausar series' The Manganese deposit
is almost vertically dipping with dips from 60o to 65o towards south Strike
direction of the Manganese ore bed is East-west in the area as observed in the
trial Pits.
ii) Need for the project and its importance to the country and or region.
The company has since a plan of production of 4,500 TPA in the Village - Pali,
Tahsil – Parseoni, District- Nagpur of Maharashtra. In order to meet the
requirement of Manganese, the mining near by will be most suitable and
advantages not only in terms of less transportation of Manganese but also the
least environmental impact on the transportation route. Therefore the
proposed mining is best suited and will meet the manganese requirement for
8 years considering the estimated minable reserve with an annual production
of 4,500 TPA.
Manganese ore is mostly used in Steel plants, Ferro-Manganese plants and
Manganese based chemicals and compounds for various applications. The setting
of manganese mine will play significant role in development of the area in
particular and in general at reseal and state level due to the direct and indirect
employment and livelihood the local population civilization and industrialization.
Pre Feasibility Report of Pali Manganese Ore Deposit
5
iii) Demand Supply Gap.
Manganese ore is mostly used in Steel plants, Ferro-Manganese plants and
Manganese based chemicals and compounds for various applications. Its demand
in industrial and nearby areas is increasing rapidly. Thus the company’s access to
high quality manganese reserve.
Imports vs. Indigenous production.
Good grade of Manganese deposit is available in and around the Nagpur district
of Maharashtra. The proposed area is located in the jurisdiction of village - Pali.
The proposed site is 56 km away from Nagpur, District headquarter and is at a
distance of 10km from Parseoni, tehsil headquarter. Parseoni is also an important
commercial town. The nearest railhead is at Ramtek at distance of 25km from the
proposed site. Due to proximity to the road and Parseoni is well connected to the
various places and Manganese marketing will not be a problem.
iv) Export Possibility
Not envisaged.
v) Domestic / export Markets.
Nagpur district is bestowed with abundance of manganese deposits as such there
is no requirement of import. The proposed site is 56 km away from District
headquarter Nagpur and due to proximity to the road up to Parseoni is well
connected to the various places and Manganese marketing will not be a problem.
vi) Employment Generation (Direct and Indirect) due to the project
The mine will have a potential of direct employment comprising of managerial,
skilled, semiskilled and unskilled staff decides the opening of this manganese mine.
Due to proximity of villages near the proposed area there is not much problem
Pre Feasibility Report of Pali Manganese Ore Deposit
6
about the labor forces for mining operation such as loading and other associated
jobs.
PROJECT DESCRIPTION
i) Type of project including Interlinked and Interdependent project, if any.
The project is manganese mining (4,500 TPA) by opencast method in the lease
hold area of 4.80 Ha. The project will be for meeting the manganese requirement
for Steel plants, Ferro-Manganese plants and Manganese based chemicals and
compounds for various applications at village – Pali, Tehsil- Parseoni, District -
Nagpur of State Maharashtra.
ii) Location (map showing general location, specific location, and project
boundary & project site layout) with coordinates.
The mining lease area is covered in parts of Survey of India Toposheet No. 55 O/3
and having a height of 305 MSL within latitude as given below :
Latitude: 21°25'33.64"N
Longitude: 79°11'44.31"E
The land is mostly a private owned agricultural Land .There is no forest land
involved.
The location of site is shown in the given below -
Pre Feasibility Report of Pali Manganese Ore Deposit
7
Location map of Pali Manganese Ore Deposit
iii) Details of alternate sites considered and the basis of selecting the
proposed site, particularly the environmental consideration gone into
should be highlighted.
The occurrence of mineral is site specific and the mining/exploitation is to be
taken up to that particular location only therefore no alternative sites were
required to be explored.
Pre Feasibility Report of Pali Manganese Ore Deposit
8
iv) Size or magnitude of operation.
The open cast manual mining of Manganese (4,500 TPA) will be carried out from
the leasehold area of 4.80 Ha. It has been observed from the Geological Plan that
the topography of the area is flat and there five trial pits located in the proposed
area where manganese has exposed around 3.0 m deep it is also continuing
below the pit floor. The manganese mining will be carried out by semi
mechanized opencast method as per approved mining plan.
v) Project description with process details (a schematic diagram/ flow chart
showing the project layout, components of the project etc. should be
given).
The area has exposures of Manganese. The manganese mining will be carried out
by opencast method as per approved mining plan. Method of minerals resource
estimation will be Surface Area Method, Cross Section Area Method or Software
Method. The proposed area is prospected by five trial pits which are sunk in the
area and also the Manganese ore is well exposed at places. It is considered
existence of Manganese ore from 2m to 6m in the area for the purpose of
estimation reserves from the exposure of manganese ore from surface.
The ore reserves are estimated by drawing cross sections perpendicular to strike
of the ore body at 50 mtrs interval. Cross sections are drawn with 1:500 for better
clearity .Pitting in the area reveals presence of probable synclinal structure .To
estimate ore reserves under 111categoryof UNFC, Ore zone has been extended 5
mt below the present pit bottom . Area is calculated graphically and reserve
quantity is estimated by applying the length factor in between two consecutive
cross sections. The ore zone up to 8mts below the surface has been
considered under 111 category of UNFC. The depth factor that is 8mt is
applicable for the both the lims of syncline. The area defined by trough of
syncline is estimated under G3 category of UNFC.
Pre Feasibility Report of Pali Manganese Ore Deposit
9
vi) Raw material along with estimated quantity, likely source marketing area of
final products, mode of transport of raw material and Finished product.
There is no requirement of any Raw Material for the production of Manganese
from this project except the explosives required for blasting, diesel for movement
of machinery and electricity.
vii) Resource optimization / recycling and reuse envisaged in the project, if
any, should be briefly outlined.
The top soil and the overburden will be temporarily stacked on surface at the
designated places before top soil is used for plantation and overburden in
backfilling.
The mine pumped out water will be treated and used plantation to the maximum
extent. The liquid waste generated from the office toilets will be treated in the
pre-fabricated package sewage treatment plant.
viii) Availability of water its source, Energy / power requirement and source
should be given.
The quantity of water that would be available within the mine void and
will be pumped out is estimated to be 5 m3/day. Drinking water is
available from well & tube well near the proposed site which is potable
and will fulfill the requirement of drinking water at site.
Electricity is available near the lease area and after due sanction from the
Maharashtra State Electricity Board, the power supply will be available.
ix) Quantity of waste to be generated (liquid and solid) and scheme for their
Management /disposal.
Solid Waste: There is no solid waste generation during mine development.
Liquid Effluent: There is no effluent generation. There will not be any change in
the runoff pattern due to the proposed project site. However peripheral drainage
channel and storm water drain will be provided for peak rainfall.
Pre Feasibility Report of Pali Manganese Ore Deposit
10
x) Schematic representation of the feasibility drawing which give information
of EIA purpose
4 SITE ANALYSIS
i) Connectivity.
The area is approachable by well developed road network.
ii) Land use and Land ownership.
Pali Manganese Ore Deposit admeasuring an area of 4.80 Ha of Privately
owned agricultural Land.
iii) Topography (along with map).
The topography of the lease area is flat terrain. The general slope of the
terrain is from east to west. The 4.80 Ha of mining lease lies towards
western side as shown on the surface plan.
iv) Existing land use pattern (agriculture, non-agriculture, forest, water
bodies (including area under CRZ), shortest distances from the
periphery of the project to periphery of the forest, national park, wild
life sanctuary, eco sensitive areas, water bodies (distance from the
HFL of the river), CRZ. In case of notified industrial area, a copy of the
Gazette notification should be given.
The mining lease 0f 4.82 Ha is categorized as Agricultural land has been
used for extraction of the manganese.
Significant features in 10 Km radius (aerial distance) of the project are tabular below
.
Sr. No. FEATURES DETAILS DISTANCE
1. Village (Nearest) Umari, Pali, Neur
Wada, Salai, Mahuli, Ghukashi, Parseoni,
Within 10.0 Km
Pre Feasibility Report of Pali Manganese Ore Deposit
11
Mansar
No. of villages 8 -
2. River Pench River 1.0 km : W
Pond Parsivni pond 7 km: S
Reservoir Navegaon reservoir 5.0 Km N
3. Reserved Forest Ghuksi R. F
Junawani R.F 2.5 km : E
3.5 Km: NE
4. National Highway State Highway
NH - 7 SH - 267
8.5 Km East 7.0 Km South
5. Major Industries No -
6. Thermal Power Plant
No -
7. Mines Manganese mines Within 7-8 km
8. Railway Line Ramtek Railway
Station 12Km : SE
9. Archeological Monument
No -
10. National Park No -
11. Wildlife Sanctuary
No -
v) Existing Infrastructure.
Land Development, Service / Welfare / Office Buildings, Workshops, Store,
Substation, Roads, Culverts, other infrastructure etc.
vi) Soil classification.
The lease area is land with manganese exposures. The proposed area is
having flat topography and is covered with lateritic soil and overburden
having thickness of l.2m to 2.0m in the area. It is formed due to
decomposition of schist & is brown in color.
Pre Feasibility Report of Pali Manganese Ore Deposit
12
vii) Climatic data from secondary sources.
The climate of the area is of moderate to extreme nature with maximum
temperature of 460C and mean minimum temperature of 120C. This is dry
area and excepting in rainy season humidity is low and the atmosphere is
dry. However average rainfall pattern in the area is 800mm to 1000mm
which is spread over from June to October.
Viii) Social Infrastructure
Social infrastructure like primary school at Pali and secondary school and
post office are located at Parseoni. The tehsil township Parseoni has all the
essential facilities like school, hospitals, P.W.D rest house and good private
medical facilities etc and well connected with Nagpur.
5 PLANNING BRIEF
i) Planning Concept (type of Industries, facilities, transportation etc) Town
and country planning/ Development authority Classification.
ii) Population Projection.
iii) Land use planning (breakup along with green belt etc.).
The proposed area is having flat topography surrounded by agricultural
land and forest land. The area is covered with alluvial soil and murrum. There
is no other activity in the area as the area is mostly barren. The deposit is in
flat ground and the surroundings area is agricultural land of single crop
pattern depending on proper and sufficient rainfall. In the surrounding area it
is mostly private land owned by individual.
iv). Assessment of Infrastructure Demand (physical & social).
The project requires roads for the transport of the produced material which
is adequate, besides it requires manpower to operate the mine and is
available locally.
Pre Feasibility Report of Pali Manganese Ore Deposit
13
V) Amenities/Facilities.
Associated buildings like mine office, store, rest shelter, magazine, hospital,
school, community hall, staff quarter etc. will be constructed.
6 PROPOSED INFRASTRUCTURE
i) Industrial area (processing area). There is no processing in mine
premises
ii) Residential Area (Non processing Area). No processing proposed
iii) Green Belt. Plantation will be developed in 33% of the lease area on non
mineralized zone
.
iv) Social Infrastructure.
Social infrastructure like primary school at Pali and secondary school and
post office are located at Parseoni. The telsil township Parseoni has all the
essential facilities like school, hospitals, P.W.D rest house and good private
medical facilities etc and well connected with Nagpur.
v) Connectivity (Traffic and Transportation Road/Rail/Metro/Water ways
etc.) Adequate road facility is existing in the area
vi) Drinking Water management (Source & Supply of water)
Drinking water is available from well & tube well near the
proposed site which is potable and will fulfill the requirement of
drinking water at site.
Source - Borewell
vii) Sewerage System.: Septic tank & soak pit will be provided
viii) Industrial Waste Management.
Pre Feasibility Report of Pali Manganese Ore Deposit
14
Non mineralized area will be used for dumping of soil which will be used for
green belt development.
ix) Solid Waste Management.
The overburden including associated waste will be accommodated in
non mineralized and the worked out pit by reclaiming and plantation
purpose.
x) Power Requirement & Supply / Source.
Maharashtra State Electricity Board
7 REHABILITATION AND RESETTLEMENT (R & R ) PLAN
i) Policy to be adopted (central/state) in respect of the project affected
person including home oustees, land oustees and landless laborers
(a brief outline to be given.)
No Re-habitation.
8 PROJECT SCHEDULE & COST ESTIMATES
i) Likely date of start of construction and likely date of completion
(Time schedule for the project to be given.)
The operations are carried as per the statutory guidelines. Adequate
reserves are available. Reclamation and Rehabilitation plan will be
prepared for sustainable development and minimized environmental
damage.
ii) Estimated project cost along with analysis in terms of economic viability of the project.
Expected cost of the project- Rs.45 lakh