Transcript of Overview Presentation Fall 2015 Gainesville-Haymarket Extension Study.
![Page 1: Overview Presentation Fall 2015 Gainesville-Haymarket Extension Study.](https://reader035.fdocuments.us/reader035/viewer/2022062409/5697c0191a28abf838cce788/html5/thumbnails/1.jpg)
Overview PresentationFall 2015
Gainesville-Haymarket Extension Study
![Page 2: Overview Presentation Fall 2015 Gainesville-Haymarket Extension Study.](https://reader035.fdocuments.us/reader035/viewer/2022062409/5697c0191a28abf838cce788/html5/thumbnails/2.jpg)
2
WHAT IS THE GAINESVILLE-HAYMARKET EXTENSION PROJECT?
![Page 3: Overview Presentation Fall 2015 Gainesville-Haymarket Extension Study.](https://reader035.fdocuments.us/reader035/viewer/2022062409/5697c0191a28abf838cce788/html5/thumbnails/3.jpg)
3
VRE Overview
• Commuter rail system serving Washington, DC and Northern Virginia
• Two lines, 90 miles
• 4.5 million annual passengers
• A partnership of NVTC and PRTC
• Vital capital and operating support from the Commonwealth of Virginia
![Page 4: Overview Presentation Fall 2015 Gainesville-Haymarket Extension Study.](https://reader035.fdocuments.us/reader035/viewer/2022062409/5697c0191a28abf838cce788/html5/thumbnails/4.jpg)
4
Our Importance to Northern Virginia
• Part of a balanced transportation system
• Reduces peak congestion
• An efficient and effective means of adding peak travel capacity
• Investment pays long-term dividends for generations
![Page 5: Overview Presentation Fall 2015 Gainesville-Haymarket Extension Study.](https://reader035.fdocuments.us/reader035/viewer/2022062409/5697c0191a28abf838cce788/html5/thumbnails/5.jpg)
6
WHY EXTEND VRE?
![Page 6: Overview Presentation Fall 2015 Gainesville-Haymarket Extension Study.](https://reader035.fdocuments.us/reader035/viewer/2022062409/5697c0191a28abf838cce788/html5/thumbnails/6.jpg)
7
Why Extend VRE?
• I-66 corridor is the focus of Virginia strategic investment
• VRE provides additional choice and capacity• Growing congestion driven by continued rapid land
development
![Page 7: Overview Presentation Fall 2015 Gainesville-Haymarket Extension Study.](https://reader035.fdocuments.us/reader035/viewer/2022062409/5697c0191a28abf838cce788/html5/thumbnails/7.jpg)
8
Project Corridor
Potential Haymarket Station Area
Potential Gainesville Station Area
Potential Innovation/Sudley Station Area
![Page 8: Overview Presentation Fall 2015 Gainesville-Haymarket Extension Study.](https://reader035.fdocuments.us/reader035/viewer/2022062409/5697c0191a28abf838cce788/html5/thumbnails/8.jpg)
9
VRE Manassas Line Riders
![Page 9: Overview Presentation Fall 2015 Gainesville-Haymarket Extension Study.](https://reader035.fdocuments.us/reader035/viewer/2022062409/5697c0191a28abf838cce788/html5/thumbnails/9.jpg)
10
Project Overview
JUL AUG SEP OCT NOV
Contingent upon Norfolk Southern approval and funding availability.
2015
2016
2017
2018
2019
2020
2021
2022
Planning
Environmental
Preliminary Engineerin
gFinal Design
Construction
StartUp
Current Study
Pro
ject
Acti
vit
ies
We are here 2023
2024
START OF REVENUE SERVICEPROJECT IMPLEMENTATION
PROJECT DEVELOPMENT
Pro
ject
Ph
ase
Schedule as of September 2015
![Page 10: Overview Presentation Fall 2015 Gainesville-Haymarket Extension Study.](https://reader035.fdocuments.us/reader035/viewer/2022062409/5697c0191a28abf838cce788/html5/thumbnails/10.jpg)
11WHAT ARE THE KEY ISSUES?
![Page 11: Overview Presentation Fall 2015 Gainesville-Haymarket Extension Study.](https://reader035.fdocuments.us/reader035/viewer/2022062409/5697c0191a28abf838cce788/html5/thumbnails/11.jpg)
12
What are the Key Issues?
• Railroad Ownership: Norfolk Southern owns the Railroad and approves VRE service
• Community Growth and Economic Development: The corridor is home to many existing communities and potential new residential, commercial, and mixed-use developments
• Funding: The project will rely on a mix of federal, state, regional, and private funding sources
• Environmental: Corridor is home to many natural and cultural resources, such as wetlands, historic sites, and parks
![Page 12: Overview Presentation Fall 2015 Gainesville-Haymarket Extension Study.](https://reader035.fdocuments.us/reader035/viewer/2022062409/5697c0191a28abf838cce788/html5/thumbnails/12.jpg)
13
How Are We Going to Decide?
• Select the best route, service plan, and station locations
• Decision based on:– Freight and VRE
interoperability – Ridership– Costs and funding – Project benefits– Community and
environmental impacts
![Page 13: Overview Presentation Fall 2015 Gainesville-Haymarket Extension Study.](https://reader035.fdocuments.us/reader035/viewer/2022062409/5697c0191a28abf838cce788/html5/thumbnails/13.jpg)
14
Next Steps
• Identify the route and station location alternatives that best serve the community and VRE riders
• Estimate the cost and identify possible funding sources
• Identify preliminary impacts and benefits of the project
• Come back to the public and stakeholders in Spring 2016 with specific alternatives for your input
![Page 14: Overview Presentation Fall 2015 Gainesville-Haymarket Extension Study.](https://reader035.fdocuments.us/reader035/viewer/2022062409/5697c0191a28abf838cce788/html5/thumbnails/14.jpg)
15
Thank You. Your Input is Appreciated.
Doug AllenVRE Chief Executive Officer
Christine HoeffnerVRE Manager of Project Development
VRE GHXwww.vre.org/ghx @vre_ghx [email protected]