Overview of Regulations and Guides in Japan...Technical Meeting on Novel Design and Safety...

23
Tsuyoshi Nakajima Regulatory Standards and Research Division Nuclear Regulation Authority (NRA-Japan) Overview of Regulations and Guides in Japan IAEA, Vienna, Austria 3-6 October 2016 Technical Meeting on Novel Design and Safety Principles of NPPs Technical Meeting on Novel Design and Safety Principles of NPPs, Vienna, Austria, 3-6, October, 2016

Transcript of Overview of Regulations and Guides in Japan...Technical Meeting on Novel Design and Safety...

  • Tsuyoshi Nakajima Regulatory Standards and Research Division Nuclear Regulation Authority (NRA-Japan)

    Overview of Regulations and Guides in Japan

    IAEA, Vienna, Austria 3-6 October 2016

    Technical Meeting on Novel Design and Safety Principles of NPPs

    Technical Meeting on Novel Design and Safety Principles of NPPs, Vienna, Austria, 3-6, October, 2016

  • Contents

    i. Japan Update

    ii. Overview of the New Regulation

    iii. Practical Elimination and Safety Goal

    iv. Review Guide for Severe Accident Measures

    v. Continuous Improvement for Safety

    vi. Conclusions

    1 Technical Meeting on Novel Design and Safety Principles of NPPs, Vienna, Austria, 3-6, October, 2016

  • i. Japan Update

    2 Technical Meeting on Novel Design and Safety Principles of NPPs, Vienna, Austria, 3-6, October, 2016

  • Timeline and Current Status

    The NRA was established in Sep. 2012 and urgently started developing the new regulatory requirements for NPPs which came into force in July 2013.

    After the 1F accidents, all the 48 units had suspended their operation one by one by May 2012.

    • 26 units (16 PWRs, 10 BWRs) have applied for conformance review to the new requirements

    • NRA has granted the permissions for 7 units: Sendai-1, -2, Takahama-1~-4 and Ikata-3

    • Sendai-1, 2 and Ikata-3 in operation

    IPPAS mission’s review was done in Feb. 2015

    IRRS mission’s review was done in Jan. 2016

    3 Technical Meeting on Novel Design and Safety Principles of NPPs, Vienna, Austria, 3-6, October, 2016

  • Nuclear Power Reactors in Japan

    <Tomari>

    <Higashidori>

    <Onagawa>

    <Fukushima Dai-ichi>

    <Fukushima Dai-ni>

    <Tokai Plant, Tokai Dai-ni>

    <Hamaoka>

    <Ikata>

    <Sendai > <Genkai >

    <Shimane >

    <Takahama>

    <Ohi >

    <Kashiwazaki-Kariwa>

    <Shika>

    <Mihama>

    <Tsuruga>

    Reactors undergoing decommissioning (3)

    Already Service Terminated (6)

    Specified nuclear facility

    BWR (24)

    PWR (24)

    Restarted (3)

    Applied (26)

    <Ohma> BWR, under Construction (2)

    As of Oct, 2016

    Application

    PWR 16

    BWR 10

    Total 26

    Application of Conformity Review for NPPs

    4 Technical Meeting on Novel Design and Safety Principles of NPPs, Vienna, Austria, 3-6, October, 2016

  • Licensee Facility

    JNFL Reprocessing /Uranium Enrichment /MOX Fuel Fab。/High-Level Radioactive Waste Storage Center

    RFS Spent Fuel Storage Facility (Interim Storage)

    JAEA Oarai R&D Center (Waste Management Facility)

    MNF Uranium Fuel Fab. Facility (PWR)

    NFI Uranium Fuel Fab. Facility (Tokai(BWR)/Kumatori(PWR))

    GNF-Japan Uranium Fuel Fab. Facility (BWR)

    Kyoto Univ. RRs (KUR/KUCA)

    Kinki Univ. RR

    JAEA RRs(JRR-3/NSRR), STACY , R&D facility

    JAEA Oarai R&D Center, RRs (HTTR/JMTR)

    Application of Conformity Review for FCFs and RRs

    5 Technical Meeting on Novel Design and Safety Principles of NPPs, Vienna, Austria, 3-6, October, 2016

  • ii. Overview of the New Regulations

    6 Technical Meeting on Novel Design and Safety Principles of NPPs, Vienna, Austria, 3-6, October, 2016

  • Revision of the Reactor Regulation Act Overview

    1. NRA can issue rules and permissions as the RB

    2. Back-fit system: No difference from new and existing NPPs Moratorium may be decided when the additional

    requirement established Specialized Safety Facility …… 5 years moratorium

    3. Clarification of the Primary Responsibilities for operators

    4. Evaluations to improve the safety of NPPs: Periodically Update as FSAR’

    5. Limits on the operation period: 40 years only one extension up to 20 years if approved by the NRA

    7 Technical Meeting on Novel Design and Safety Principles of NPPs, Vienna, Austria, 3-6, October, 2016

  • Re

    info

    rced

    &

    Ne

    w

    (SA M

    easu

    res)

    NEW

    R

    ein

    force

    d

    Req. for AOOs and DBAs were strengthened.

    Req. for “SAs” that are equivalent to “DECs” in SSR 2/1 were newly added.

    DiD4

    Structure of New Regulatory Requirements

    8 Technical Meeting on Novel Design and Safety Principles of NPPs, Vienna, Austria, 3-6, October, 2016

    Seismic / Tsunami resistance

    Natural phenomena

    Reliability of power supply

    Function of other SSCs*

    Fire protection

    Seismic / Tsunami resistance

    Natural phenomena (Volcano, Tornadoes, Forest fire: New)

    Prevention of core damage (Postulate multiple failures)

    Suppression of radioactive materials dispersal

    Response to intentional aircraft crash

    Prevention of CV failure & large release

    Function of other SSCs

    Internal flooding (New)

    Fire protection

    Reliability of power supply DiD3

  • iii. Practical Elimination and Safety Goal

    9 Technical Meeting on Novel Design and Safety Principles of NPPs, Vienna, Austria, 3-6, October, 2016

  • The New Requirements in Plant States

    New Design Requirements

    Previous Design Requirements

    Operational States Accident Conditions Practically

    Elimin

    ated

    o

    f Early/Large

    Re

    lease

    NO AOO DBA DEC

    w/o Sig. Fuel Deg. (DEC-a)

    w/Core Melt (DEC-b)

    1 2 3 4a 4b

    Non-P.E.: SFP, Catastrophic Disaster, Intentional Aircraft Crash B-DEC: Mobile equipment, e.g. Cannon Spray Pump DEC Mitigation Equip.: Classified in Higher Class SSR-2/1 (Rev. 1): No Significant Gaps

    Operating Safety Program (~EOP~SAMG~)

    Technical Meeting on Novel Design and Safety Principles of NPPs, Vienna, Austria, 3-6, October, 2016 10

  • Safety Goal (Conceptual Scheme)

    CDF CFF-1 CFF-2

    Status

    Freq. 10-4 10-5 10-6

    Release 100 TBq (CS137)

    Measures Prevent Core

    Damage Prevent CV Failure Prevent CV Damage

    & Large Release Mitigate

    Expansion

    Core Damage Controlled Release Uncontrolled Release

    Applied to all NPPs equally

    Safety Goal is the goal that NRA should achieve through implementing its regulation over nuclear facilities

    Technical Meeting on Novel Design and Safety Principles of NPPs, Vienna, Austria, 3-6, October, 2016 11

  • iv. Review Guide for Severe Accident Measures

    12 Technical Meeting on Novel Design and Safety Principles of NPPs, Vienna, Austria, 3-6, October, 2016

  • 1. Outline of SA Measures Requirements

    General Requirements on the SA measures Equip.

    Preparation of procedures, implementation of drills, and development of organizational system

    Prepare equipment and procedures for the following 19

    Outline of SA Measures Requirements

    13 Technical Meeting on Novel Design and Safety Principles of NPPs, Vienna, Austria, 3-6, October, 2016

  • Prepare equipment and procedures

    14 Technical Meeting on Novel Design and Safety Principles of NPPs, Vienna, Austria, 3-6, October, 2016

    Reactor shutdown Cooling reactor at high / √ low pressure Depressurizing RCPB Securing UHS Cooling, depressurization and RM reduction in the atm. CV Preventing the CV failure due to overpressurization Cooling molten core fallen to the bottom of the CV Hydrogen explosions inside the CV and R/B etc. Cooling, shielding and maintaining the sub-criticality of SFP Securing make-up water and water sources √power sources Control room √Emergency response center Instrumentation devices Radiation monitoring facilities Communications devices Suppression of off-site radioactive

  • 2. AM for External Events beyond Design Basis

    AM with mobile equipment, etc.

    3. Evaluation of the Effectiveness of SA Measures

    Preventive measures against core damage and CV failure

    Prevent measures against fuel damage in SFPs

    Prevent measures against fuel damage in a reactor during shutdown

    AM for EE beyond DB & Evaluation

    15 Technical Meeting on Novel Design and Safety Principles of NPPs, Vienna, Austria, 3-6, October, 2016

  • v. Continuous Improvement for Safety

    16 Technical Meeting on Novel Design and Safety Principles of NPPs, Vienna, Austria, 3-6, October, 2016

  • 1. “As-Built” or “As-Is” plant description and compliance with requirements (Clarification of “license basis”)

    2. Voluntary Efforts for Safety Improvement: Policy and plan on continuous improvement of safety

    Feedback of operating experience and state-of-the-art knowledge/information, and plant walk-down

    Additional actions taken

    Peer Review (e.g. IAEA OSART)

    3. Effectiveness of voluntary efforts demonstrated by: Level 1 and 2 PRAs for both internal / external events

    Safety margin analysis (e.g. stress test)

    4. Comprehensive Assessment for Plant Safety

    Continuous Improvement of Regulatory Requirements and Systems

    17 Technical Meeting on Novel Design and Safety Principles of NPPs, Vienna, Austria, 3-6, October, 2016

  • Continuous Improvement of Regulatory Requirements and Systems

    1. Strengthen the OEF Process through “Technical Information Committee” • “Single-Phase Open Circuit” (Byron-2, US, 1/2012), ⇒Amended a relevant regulatory guide.

    2. Always be vigilant to the state-of-the-art knowledge / information and therefore, is enhancing its learning process through bilateral / multilateral international cooperative activities.

    18 Technical Meeting on Novel Design and Safety Principles of NPPs, Vienna, Austria, 3-6, October, 2016

  • Secretariat of NRA: • Collection and Analysis of OE and

    Regulatory Activities • Screening” and Tracking” • Communication with Licensees

    • Actions: “Information notice” to Licensees New Regulations and Guides Amendments to Existing Rs & Gs

    NRA’s System for Global OEF

    Advisory Committees

    Technical Information Committee

    Information Sources: • OECD/NEA, IAEA IRS,

    FINAS, INES,… • OECD/NEA/CNRA WGOE,

    WGIP, IAEA IRS,..

    • IAEA CSS, INSAG, IEMs,.. • OECD/NEA CSNI • Public information:

    • U.S.NRC’s Bulletins, Generic Letters, Info. Notices

    • Bilateral info. exchange

    The NRA

    Licensees

    19 Technical Meeting on Novel Design and Safety Principles of NPPs, Vienna, Austria, 3-6, October, 2016

  • vi. Conclusions

    20 Technical Meeting on Novel Design and Safety Principles of NPPs, Vienna, Austria, 3-6, October, 2016

  • Conclusions

    • The New Safety Requirements have been enforced since July, 2013 taking into account L.L. from 1F Accidents and IAEA SSs, such as …

    Introduced DiD with Independency among levels …… Practically

    Use of non-permanent equipment Back-fit rule Safety Margins by stress test

    • Main Points are ………

    SAM for Conditions exceeding DiD level 4 Higher value of the DBE for DEC equipment Improve safety continuously

    21 Technical Meeting on Novel Design and Safety Principles of NPPs, Vienna, Austria, 3-6, October, 2016

  • 22 Technical Meeting on Novel Design and Safety Principles of NPPs, Vienna, Austria, 3-6, October, 2016