Overview of Methodology

download Overview of Methodology

of 12

Transcript of Overview of Methodology

  • 8/2/2019 Overview of Methodology

    1/12

    I. Overview of methodologyTo realise this project, an interconnection of the Southern Interconnected Grid (SIG) and

    Northern Interconnected Grid (NIG) of Cameroon is realised with a HVDC connection with the

    aim of minimising the active power transmission losses in the AC networks, while studying the

    voltage stability of the HVDC link in terms of voltage values between nodes.

    I.1 Active Power minimizationIn this section, the basic concept applied for the minimization of active power transmission

    losses is explained. The following steps are then followed in order to attain the objective of (see

    flow chart below);

  • 8/2/2019 Overview of Methodology

    2/12

    Apply the particle swarm Optimization method to the OPFControl variables

    Reactive power generated bycapacitor banks

    Position of OLTC trans formers

    Voltages at the generator buses

    Output variables

    Optimal position of control variables forminimum trans mission loss es

    Formulation of the Optimal Power Flow Problem (OPF)

    Objective function Network constraints

    Solution of the Power Flow Problem by the Newton Raphson methodInput variables

    Bus admittance matrix

    Active and reactive power generatedand consumed at the different nodes

    Output variables

    Voltage and phas e at the differentnodes

    Active and reactive power generated

    Formulate the Power Flow Problem

    Formulate the bus admittance matrix Power Flow Equation

    Impedance model of the different network elements

    Impedance model of transmissionlines

    Impedance model of transformers

    Adaptation of the SIG and NIG mode

    Hypothesis for themodeling of the SIG

    Determine the numberof nodes

    One line diagram of theSIG model

  • 8/2/2019 Overview of Methodology

    3/12

    I.2 Model of the SIGGeneral Hypothesis for SIG and NIG

    The following assumptions were made in modelling the SIG:

    The base apparent power is

    and the base

    corresponds to the nominal

    voltage at a particular node;

    For two transmission lines in parallel, the equivalent resistance and reactance are

    calculated. This implies for two nodes connected by two lines in parallel, only one

    equivalent transmission line is considered;

    In all power plants (except Song Loulou and Lagdo) with two or more generators, the

    latter are considered as one and the power generated is the sum of the power

    generated by these different generators. This signifies the power generated by

    individual generators is not specified;

    The power consumed at a node varies as a function of the voltage across the node. In

    this model, the loads were considered constant irrespective of the voltage across them

    Generally, the reactive power injected by a capacitor bank varies as a function of its

    capacitance and the voltage across it. This was not taken into account in this model. The

    reactive power injected by a capacitor bank was considered constant regardless of the

    voltage across it.

    All the HV substations with capacitor banks have two capacitor banks each. Only one

    capacitor bank is indicated with a capacity equal to the sum of the reactive power

    injected by the two capacitor banks.

    Diagram of the SIG model

    The figure below is a diagram showing the different bus bars, generators and transformers of

    the SIG model considered. A total of 46 buses and 50 branches (branches are transmission lines

    or transformers). Table below indicates the generator nodes together with their corresponding

    node indices and Table shows the different transformers as well as their departure and arrival

    nodes;

  • 8/2/2019 Overview of Methodology

    4/12

    Ta b le 1: Generators in the m odel and their corresponding node indicesLocation of Power

    plant

    Number of generators

    considered

    Name used in model Node index as

    represented in the model

    Song Loulou 4 SLL1 1

    SLL2 2SLL3 3

    SLL4 4

    Oyomabang 2 Oyo HFO 11

    Oyo LFO 12

    Edea 1 Edea PP 23

    Dibamba 1 Dibamba PP 27

    Logbaba 2 Logbaba HFO 29

    Logbaba LFO 30

    Bassa 2 Bassa2 34

    Bassa3 35Limbe 1 Limbe HFO 41

    Bafoussam 1 Bafoussam PP 44

    Ta b le 2: Transformers and the ir corresponding arrival and departure node indices

    Location of transformerDeparture node Arrival node

    Song Loulou 1 5

    2 5

    3 5

    4 5

    Oyomabang Substation 9 10

    9 18

    Oyomabang HFO 10 11

    Oyomabang LFO 10 12

    Mangombe Substation 8 25

    Logbaba Substation 7 28

    Logbaba HFO 28 29

    Logbaba LFO 28 30

    Bekoko Substation 6 39

    Bassa2 33 34

    Bassa3 33 35

    Edea Power plant 22 23

    Dibamba 26 27

    Limbe 41 42

    Bafoussam 44 45

  • 8/2/2019 Overview of Methodology

    5/12

    Some of the transmission lines are of particular interest because the amount of power that

    flows through them is very high, and others by virtue of the fact that they are very long and

    thus have very high resistances. These two factor affect considerably the active power

    transmission losses in these lines. The length of the 225kV and some 90kV transmission lines

    are indicated in the figure below.

    10

    LOGBABABEKOKO MANGOMBE

    OYOMABANG

    B

    NSI

    AHALANGOUSSO

    KONDENGUI

    NJOCK-

    KONG

    EDEA PP

    ALUCAM

    NGODI BAKOKO

    KOUMASSI

    DIBAMBA

    MAKEPE

    BASSA

    DEIDO

    BONABERI

    LIMBE

    NKONGSAMBA

    BAFOUSSAM

    BAMENDA

    LIMBE HFO

    1

    SONGLOULOU

    7

    1

    96 8

    18

    19

    14

    30

    27

    21

    22

    20

    35

    32

    3334

    38

    40

    37

    41

    46

    45

    2 3

    5

    11 12

    24

    23

    26

    25

    28

    31

    29

    36

    39

    43

    42

    44

    4

    15

    DR NSIMALEN

    Key

    Hydo electric power gen

    HFO thermal generato

    LFO thermal generato

    225kV____________

    90kV_____________

    HV capacitor banks

    EDEA

    (41.5km) (58km)

    (65km)

    (58km)(168.38km)

    (94km)

    (94k

    m)

    (70km)

    Formulating the power flow problem

    Formulation of the bus admittance matrix ()The first step in developing the mathematical model describing the power flow in the network is the

    formulation of the bus admittance matrix. The bus admittance matrix is an matrix (where is thenumber of buses in the system) constructed from the admittances of the equivalent circuit elements of

    the segments making up the power system. Most system segments are represented by a combination of

    shunt elements (connected between a bus and the reference node) and series elements (connected

  • 8/2/2019 Overview of Methodology

    6/12

    between two system buses). Formulation of the bus admittance matrix follows two simple rules Error!

    Reference source not found.:

    Consider 2 nodes and , and be the corresponding admittance between and .If and k are linked by a transmission line or transformer

    Else

    For a node

    Whereis the set of nodes connected to bus by a line or transformer and the reactance connectedto the node (shunt of reactance).In polar form, is expressed in the form || || Where are the real and imaginary parts of the admittance respectively.

    Formulation of the power flow problem

    The power flow problem is used to determine the values for all state variables (voltage magnitude and

    angle) by solving an equal number of power flow equations based on the input data specifications. In

    this section, the different input data known at each of the nodes are specified.The voltage at a bus of the system in polar coordinates is as follows: The voltage at another bus is simi larly written by changing the subscript from to .The net current injected into the network at bus in terms of the elements of the admittance matrixis given by

    Let

    and

    denote the net real and reactive power injected at the bus

    . The complex conjugate of

    the power injected at bus is By substituting equations and in equation we obtain:

    Expanding this equation into real and imaginary parts:

  • 8/2/2019 Overview of Methodology

    7/12

    Equations and constitute the polar form of the power-flow equations; they provide calculatedvalues for the net real power and the net reactive power injected at bus .Let denote the scheduled power generated at bus and denote the scheduled power demand.Then, is the net scheduled power being injected at bus . If the calculated value of isdenoted by , we can define the mismatch, as the scheduled value minus the calculatedvalue .i.e. Likewise, the reactive power mismatch at bus is:

    Mismatches occur in the process of solving power flow problems when calculated values ofand do not coincide with the scheduled values and . If the calculated values and match the scheduled values and perfectly, then the mismatches and are zeroat the bus , i.e. If there is no scheduled value for bus , then the active power mismatch cannot be defined andthere is no requirement to satisfy equation in the course of solving the power flow problem.Similarly, if

    is not specified at bus

    , then equation

    does not have to be satisfied.

    Four unknown quantities associated with each bus are , voltage angle and the voltagemagnitude. For a system with N nodes, there are:N voltage amplitudes N voltage angles N active power at the node N reactive power at the node

    4N unknowns can be identified. There are at most two equations available for each node, and so the

    number of unknown quantities must be reduced to agree with the number of available equations before

    beginning to solve the power flow problem. The general practice in power flow is to identify three types

    of buses in the network. At each bus, two of the variables , andare specified and theremaining two are calculated.

  • 8/2/2019 Overview of Methodology

    8/12

    Ta b le 3: Summary of power-flow problemBus type Number of

    buses

    Quantities

    specified

    Number of available

    equations

    Number of state

    variables( ,)Slack (1)

    Voltage controlled (2) Load (3) 2( ) 2( )Totals

    The power flow formulation was applied to the SIG. As seen in Error! Reference source not

    found., buses. The node types were defined as follows:All thermal generators, interconnection nodes and load nodes are PQ buses giving a

    total of

    buses. Nodes with thermal generators are PQ nodes because the amount of

    power generated by these plants are considered fixed, in order to respect the cost

    effective schedule made by QSOM ;

    The generators in Edea and six generators of Song Loulou are PV buses giving a total of 4

    PV buses;

    Two generators in Song Loulou are connected to the slack bus.

    Table gives a summary of the number of buses of each type and the number of corresponding

    equations.

    Ta b le 4: Node Configuration for the SIGBus type Number of buses Number of available

    equations

    Slack (1) Voltage controlled (2) Load (3) Totals

    There are different computational techniques used by different programs to determine the state

    variablesError! Reference source not found.. These are: the Gauss-Seidel Method, the Newton Raphson

    Method and the Fast Decoupled method. In this work the Newton Raphson method will be applied

    because the number of i terations required by the Newton Raphson method is independent of the

    number of buses whi le the computation time using Gauss-Seidel increases almost directly with the

    number of buses.

  • 8/2/2019 Overview of Methodology

    9/12

    Solution of Load flow using Newton Raphsons method

    Taylor's series expansion for a function of two or more variables is the basis for the Newton-Raphson

    method of solving the power flow problem Error! Reference source not found. . To apply the Newton-

    Raphson method to the solution of the power-flow equations, we express bus voltages and line

    admittances in polar form i.e.

    These equations are differentiated with respect to the voltage angles and the magnitudes (state

    variables). For active power we have

    A similar mismatch equation can be written can written for the reactive power ,

    Each non slack bus has two equations for . Collecting all the mismatch equations intovector-matrix form yields

    (

    [

    ] [

    ]

    [

    ] [ ])

    The partitioned form of the equation above emphasizes the four different types of partial

    derivatives which enter into the Jacobian . The solution to this equation is found by iteration as follows:1. Estimate values for the state variables

    and

    (generally,

    =0 and

    ;

    2. Use the estimate to calculate from equations and and the mismatchesfrom equations and and the partial derivatives elements of the Jacobian;3. Solve equation below for initial corrections ;4. Add the solved corrections to the initial estimates to obtain

  • 8/2/2019 Overview of Methodology

    10/12

    5. Use the new values

    as starting values for iteration 2.

    Formulas for the update of state variables are as follows:

    This process is repeated until the mismatch is less than a tolerance or when the number of iterations is greater than the maximum number of iterations (generally, the

    tolerance is 0.005 and the maximum number of iterations is 12).

    The NIG model

  • 8/2/2019 Overview of Methodology

    11/12

    Ta b le 5: Generators in the m odel and their corresponding node indicesLocation of Power

    plant

    Number of generators

    considered

    Name used in model Node index as

    represented in the model

    Lagdo 2 G1 1

    G2 2Garoua 1 Gen 3 11

    Ta b le 6: Transformers and the ir corresponding arrival and departure node indices

    Location of transformerDeparture node Arrival node

    Lagdo 1 Lagdo

    2 Lagdo

    Ngaoundere Substation Ngaoundere 6

    6 7

    Garoua substation Garoua1 8

    Garoua substation 9 8

    Garoua substation 8 10

    Garoua substation 8 11

    Guider 12 Guider

    Maroua substation 12 Maroua

    Maroua substation Maroua 15

    Maroua substation 15 16

    DC link modification on the N-R algorithm

    The work to be realise is a study on the interconnected link using the HVDC, hence the AC-DC newton

    Raphson load flow algorithm is given below

    Where

    Yac: the admittance matrix for the AC network

    Ydc: the admittance matrix for the DC line

    Jac: Jacobian matrix for AC network

    Jac: Jacobian matrix for DC line

    X: values obtained from iterations

    : tolerance

  • 8/2/2019 Overview of Methodology

    12/12