Overview and status of international systems Reminder of the principal deliverables Status reports on: Spectrometer solenoids Radio Frequency Coupling Coils (RFCC) Electron-Muon Ranger (EMR) Absorbers, liquid and solid Conclusion Acknowledgements to Steve Gourlay, Ruslan Asfandiayarov, Alan Bross, Ruben Carcagno, Steve Virostek, Alan DeMello 1 Andy Nichols, STFC, MICE OsC, 30-4-13

Transcript of Overview and status of international systems Reminder of the principal deliverables Status reports...

Page 1: Overview and status of international systems Reminder of the principal deliverables Status reports on: Spectrometer solenoids Radio Frequency Coupling.

1

Overview and statusof international systems

• Reminder of the principal deliverables• Status reports on:

• Spectrometer solenoids• Radio Frequency Coupling Coils (RFCC)• Electron-Muon Ranger (EMR)• Absorbers, liquid and solid

• Conclusion

• Acknowledgements to Steve Gourlay, Ruslan Asfandiayarov, Alan Bross, Ruben Carcagno, Steve Virostek, Alan DeMello

Andy Nichols, STFC, MICE OsC, 30-4-13

Page 2: Overview and status of international systems Reminder of the principal deliverables Status reports on: Spectrometer solenoids Radio Frequency Coupling.

Principal deliverables

• EMR (Electron Muon Ranger)• UNIGE responsibility, in manufacture, recent injection of manpower

Q3 2013

• SS (Spectrometer solenoids)• First magnet ready for mapping, second in advanced state of

construction Q3, 2013

• RFCC (Radio Frequency Coupling module)• Cryostat/cold mass parts now in manufacture at LBNL, very good

news – assembly plan for all three magnets in US is advanced but not complete. Cavities are being electro-polished, tuning mechanisms well advanced

• LHe cooling pipe leak now by-passed, first coil test underway• RFCCs are the main driver for MICE Steps V & VI

• Other international equipment is now covered by M&O• But owners are still engaged, eg INFN for TOF/KL & UMISS for

cKOV

2

Page 3: Overview and status of international systems Reminder of the principal deliverables Status reports on: Spectrometer solenoids Radio Frequency Coupling.

Principal deliverables

• Liquid hydrogen absorber #1• Required for Step IV• Delivered for some time, but…• Much work required to understand integration

• Liquid hydrogen absorber vessel #2• Required for MICE Step V• In manufacture at KEK, update required

• LiH absorber• US responsibility – has been complete for sometime• MOU between US and UK under construction• When this is done, risk assessment for acceptance can begin

3

Page 4: Overview and status of international systems Reminder of the principal deliverables Status reports on: Spectrometer solenoids Radio Frequency Coupling.

Spectrometer solenoids

• Main points to note:• Magnet #1 has passed its

acceptance criteria• Decision taken by MICE to do

mapping at US rather than UK- had hoped to save time

• CERN mapping gear being shipped now, CERN magnet Group will arrive when we know exact arrival date

• Virostek shielding needs fitting, will be shipped soon, Tim & Roy will assist

• Then it’s ready for mapping• Second magnet going well, cold

mass is wrapped and inserted in vessel services turret is being assembled on bench and may well be fitted by now

4

Page 5: Overview and status of international systems Reminder of the principal deliverables Status reports on: Spectrometer solenoids Radio Frequency Coupling.

5

• Much activity at Wang NMR• Training and assembly in parallel• No shortage of effort!• Significant support from DL Controls• Group

Page 6: Overview and status of international systems Reminder of the principal deliverables Status reports on: Spectrometer solenoids Radio Frequency Coupling.

RFCC/Coupling magnets

• Progressing on four fronts:• Cold mass test at FNAL – plan is to train coil before final assembly into

magnet • Vessel fabrication at LBNL• Coil winding at Qi-Huan – successful review held in December last, main

driver is obviously successful training of first coil• Cavity production at LBNL – electro-polishing, completion of electro-

mechanical tuners

Page 7: Overview and status of international systems Reminder of the principal deliverables Status reports on: Spectrometer solenoids Radio Frequency Coupling.

Cooling Pipe Leak

7

Problem with leaky cooling tubeSolved with by-pass pipeHas passed FNAL PED

Page 8: Overview and status of international systems Reminder of the principal deliverables Status reports on: Spectrometer solenoids Radio Frequency Coupling.

8

Wrapped and unwrapped cold massOn lid supports ready for insertion]Into cryostatThis is a significant piece of work

Page 9: Overview and status of international systems Reminder of the principal deliverables Status reports on: Spectrometer solenoids Radio Frequency Coupling.

9

Warm test stand commissioning starting this week

• Cold test stand commissioning and coil cooldown will start as soon as CHL has enough Liquid Helium to support cold operations – CHL startup activities underway – LHe at CHL expected by April 24, 2013

• Powered operations expected to start ~ 2 weeks after the start of cold commissioning – Controlled cooldown may take a long time (LBNL model estimate: 2.5 days. First time cooldown may take a week or so) – Week of May 6th?

• Estimate two months of testing for coil training, including a thermal cycle

• Commissioning of a new test stand and test of first of a kind coil adds substantial uncertainty to the schedule

Page 10: Overview and status of international systems Reminder of the principal deliverables Status reports on: Spectrometer solenoids Radio Frequency Coupling.

10

• Vessel fabrication, for three magnets; material delivered to LBNL, 12th February• Fabrication and machining complete in six months – very ambitious indeed

Page 11: Overview and status of international systems Reminder of the principal deliverables Status reports on: Spectrometer solenoids Radio Frequency Coupling.

Progress with EMR

11

• Increased technician effort at UNIGE• Work concentrating on fibre bundles, 20/96 complete as of March• All scintillator bars are ready for assembly• Delivery to RAL scheduled for mid-June• Will aim to run with EMR before Summer ISIS shutdown• But we have not yet planned detail work in R.2 for that period yet

Page 12: Overview and status of international systems Reminder of the principal deliverables Status reports on: Spectrometer solenoids Radio Frequency Coupling.

Solid absorbers

12

Procured through Y12:– 1 – 20 cm diameter by 4 cm thick disk

• For thermal studies– 1 - 45 cm diameter by 6.5 cm thick disk– 2 half-wedges• Disks complete– Thermal measurements complete• Meet spec.• Wedges still in fab at Y12– Negotiating a cost to complete

CRADA is being negotiated between FNALAnd STFC for deliveryProcess for acceptance and risk assessment cannot begin till we know How it arrives

Page 13: Overview and status of international systems Reminder of the principal deliverables Status reports on: Spectrometer solenoids Radio Frequency Coupling.

Liquid and solid absorbers

• Liquid absorber #1 has been unpacked• Very rudimentary check with FC done• One pipe might need to ‘persuaded’• Handling/insertion tool required• No major worries…..• Liquid absorber integration needs to be

defined as an engineering package, many interface-type issues:

• Services, cables, pipes• Sealing• Pressure testing and PED acceptance• Handling and alignment

• AND, we need to work out how to import the thin windows from LBNL/Mississippi

• Lithium hydride absorber holder is complete and ready for use

13

Page 14: Overview and status of international systems Reminder of the principal deliverables Status reports on: Spectrometer solenoids Radio Frequency Coupling.

Conclusion

• Very encouraging news with the spectrometer solenoids; injection of engineering effort and realistic planning has paid off

• Not sure if field mapping in US will save any time or effort, but we’re doing it as the SS is ready and the FC is not

• The RFCCs are also on a much better engineering footing:• Coil #1 test is impressive and training outside the vessel very sensible• CC magnet schedule for series production though is very aggressive

• ‘Administrative’ processes may yet hold us up though:• Avoidance of VAT in UK – historic agreement has been rescinded by

HMRC• Import of LiH and safety framework• Import of thin windows