Overcoming Oregon Design-Build Challenges Rapid Bridge Replacement at Hancock Mountain Scott M....
-
Upload
justice-shield -
Category
Documents
-
view
212 -
download
0
Transcript of Overcoming Oregon Design-Build Challenges Rapid Bridge Replacement at Hancock Mountain Scott M....
![Page 1: Overcoming Oregon Design-Build Challenges Rapid Bridge Replacement at Hancock Mountain Scott M. Nettleton P.E. Justin Doornink Ph.D April, 2009 Presentation.](https://reader035.fdocuments.us/reader035/viewer/2022070306/5519c8e9550346047c8b4918/html5/thumbnails/1.jpg)
Overcoming Oregon Design-Build ChallengesOvercoming Oregon Design-Build ChallengesRapid Bridge Replacement at Hancock MountainRapid Bridge Replacement at Hancock Mountain
Scott M. Nettleton P.E.Justin Doornink Ph.D
April, 2009
Presentation to the
2009 ACEC/ODOT Conference
![Page 2: Overcoming Oregon Design-Build Challenges Rapid Bridge Replacement at Hancock Mountain Scott M. Nettleton P.E. Justin Doornink Ph.D April, 2009 Presentation.](https://reader035.fdocuments.us/reader035/viewer/2022070306/5519c8e9550346047c8b4918/html5/thumbnails/2.jpg)
History of Rapid Reconstruction in Oregon
I-5 Columbia River (Interstate) Bridge Trunnion Replacement (1997)Portland, Oregon
TYLI offered services in analysis of construction options and assistance during construction.
![Page 3: Overcoming Oregon Design-Build Challenges Rapid Bridge Replacement at Hancock Mountain Scott M. Nettleton P.E. Justin Doornink Ph.D April, 2009 Presentation.](https://reader035.fdocuments.us/reader035/viewer/2022070306/5519c8e9550346047c8b4918/html5/thumbnails/3.jpg)
Project Outcome
“The traffic nightmare that state transportation officials had predicted when the freeway traffic was narrowed from six lanes to three never materialized as commuters used buses or trains, detoured to Interstate 205 or simply stayed home. “ - The Oregonian
“I expected gridlock. I was never so glad to be wrong. I am so proud of our citizens -- all of our citizens.”
- Royce Pollard, Mayor, City of Vancouver
Christie Constructors realized $1.5 million in bonus payments ($100,000 per day) on top of $2.87 million for the project.
![Page 4: Overcoming Oregon Design-Build Challenges Rapid Bridge Replacement at Hancock Mountain Scott M. Nettleton P.E. Justin Doornink Ph.D April, 2009 Presentation.](https://reader035.fdocuments.us/reader035/viewer/2022070306/5519c8e9550346047c8b4918/html5/thumbnails/4.jpg)
Design–Build Procurement
Oregon Design-Build
• OTIA III – Oregon Transportation Investment Act
– Examined Repair and Replacement of over 300 Bridges Statewide
– Bond Funding
– Differing Delivery Methods Traditional Design-Bid-Build
Design-Build
CMGC – “Contractor at Risk” – One project, the I-5 Willamette River (Eugene)
• Utilizes a Program Manager – Oregon Bridge Delivery Partners (OBDP)
• Project is “Elk Creek to Hardscrabble Creek, Bundle 401”
• Partners Construction Contractor, Slayden Construction Group, with the Engineer, T.Y. Lin International
![Page 5: Overcoming Oregon Design-Build Challenges Rapid Bridge Replacement at Hancock Mountain Scott M. Nettleton P.E. Justin Doornink Ph.D April, 2009 Presentation.](https://reader035.fdocuments.us/reader035/viewer/2022070306/5519c8e9550346047c8b4918/html5/thumbnails/5.jpg)
Elk Creek to Hardscrabble Creek
Oregon State Highway 38
• Elkton to Drain, Oregon
• 5 Bridge Replacements
– Elk Creek Crossings 1, 2, 3 and 4
– Hardscrabble Creek
• Cost - $52 Million, Design, Construction and Program Management
• Unique Features
– Schools Program – Student designed Bridge Pylons
– Rapid Replacement
– Aesthetic components (Bridge rail and Features at Bridge #1)
• http://www.obdp.org/files/dashboard/projects/bundles/401.pdf
![Page 6: Overcoming Oregon Design-Build Challenges Rapid Bridge Replacement at Hancock Mountain Scott M. Nettleton P.E. Justin Doornink Ph.D April, 2009 Presentation.](https://reader035.fdocuments.us/reader035/viewer/2022070306/5519c8e9550346047c8b4918/html5/thumbnails/6.jpg)
Elk Creek Crossing #1, Before and After
![Page 7: Overcoming Oregon Design-Build Challenges Rapid Bridge Replacement at Hancock Mountain Scott M. Nettleton P.E. Justin Doornink Ph.D April, 2009 Presentation.](https://reader035.fdocuments.us/reader035/viewer/2022070306/5519c8e9550346047c8b4918/html5/thumbnails/7.jpg)
Elk Creek Crossing #2, Before and After
![Page 8: Overcoming Oregon Design-Build Challenges Rapid Bridge Replacement at Hancock Mountain Scott M. Nettleton P.E. Justin Doornink Ph.D April, 2009 Presentation.](https://reader035.fdocuments.us/reader035/viewer/2022070306/5519c8e9550346047c8b4918/html5/thumbnails/8.jpg)
Hardscrabble Creek, Before and After
![Page 9: Overcoming Oregon Design-Build Challenges Rapid Bridge Replacement at Hancock Mountain Scott M. Nettleton P.E. Justin Doornink Ph.D April, 2009 Presentation.](https://reader035.fdocuments.us/reader035/viewer/2022070306/5519c8e9550346047c8b4918/html5/thumbnails/9.jpg)
Elk Creek Crossing #3 and #4
Location of Bridges in Proximity to the Elk Creek TunnelLocation of Bridges in Proximity to the Elk Creek Tunnel
Bridge #3 approximately 100 ft from tunnel portal Bridge #4 approximately 50 ft from tunnel portal
Rapid Replacement in 2 - Weekend closure periods
![Page 10: Overcoming Oregon Design-Build Challenges Rapid Bridge Replacement at Hancock Mountain Scott M. Nettleton P.E. Justin Doornink Ph.D April, 2009 Presentation.](https://reader035.fdocuments.us/reader035/viewer/2022070306/5519c8e9550346047c8b4918/html5/thumbnails/10.jpg)
Schematic
![Page 11: Overcoming Oregon Design-Build Challenges Rapid Bridge Replacement at Hancock Mountain Scott M. Nettleton P.E. Justin Doornink Ph.D April, 2009 Presentation.](https://reader035.fdocuments.us/reader035/viewer/2022070306/5519c8e9550346047c8b4918/html5/thumbnails/11.jpg)
Crossing #4
• Relatively Simple
– Straight Alignment (Superelevation transition)Straight Alignment (Superelevation transition)
– 2 Span w/ 90 degree bents2 Span w/ 90 degree bents
– Prestressed concrete simple spansPrestressed concrete simple spans
• Environmental ChallengesEnvironmental Challenges
– Fluvial Criteria – Oregon interpretation of requirements forFluvial Criteria – Oregon interpretation of requirements for
re-establishing lost habitatre-establishing lost habitat
• Geotechnical ChallengesGeotechnical Challenges
– Tailings from the tunnel construction in the areaTailings from the tunnel construction in the area
– Pre-bored piling required at West abutmentPre-bored piling required at West abutment
![Page 12: Overcoming Oregon Design-Build Challenges Rapid Bridge Replacement at Hancock Mountain Scott M. Nettleton P.E. Justin Doornink Ph.D April, 2009 Presentation.](https://reader035.fdocuments.us/reader035/viewer/2022070306/5519c8e9550346047c8b4918/html5/thumbnails/12.jpg)
Crossing #4
![Page 13: Overcoming Oregon Design-Build Challenges Rapid Bridge Replacement at Hancock Mountain Scott M. Nettleton P.E. Justin Doornink Ph.D April, 2009 Presentation.](https://reader035.fdocuments.us/reader035/viewer/2022070306/5519c8e9550346047c8b4918/html5/thumbnails/13.jpg)
Existing Structure, Before
![Page 14: Overcoming Oregon Design-Build Challenges Rapid Bridge Replacement at Hancock Mountain Scott M. Nettleton P.E. Justin Doornink Ph.D April, 2009 Presentation.](https://reader035.fdocuments.us/reader035/viewer/2022070306/5519c8e9550346047c8b4918/html5/thumbnails/14.jpg)
Perpendicular Temporary Supports
![Page 15: Overcoming Oregon Design-Build Challenges Rapid Bridge Replacement at Hancock Mountain Scott M. Nettleton P.E. Justin Doornink Ph.D April, 2009 Presentation.](https://reader035.fdocuments.us/reader035/viewer/2022070306/5519c8e9550346047c8b4918/html5/thumbnails/15.jpg)
Just Prior to Move, April 29th
![Page 16: Overcoming Oregon Design-Build Challenges Rapid Bridge Replacement at Hancock Mountain Scott M. Nettleton P.E. Justin Doornink Ph.D April, 2009 Presentation.](https://reader035.fdocuments.us/reader035/viewer/2022070306/5519c8e9550346047c8b4918/html5/thumbnails/16.jpg)
Crossing #4, Current
![Page 17: Overcoming Oregon Design-Build Challenges Rapid Bridge Replacement at Hancock Mountain Scott M. Nettleton P.E. Justin Doornink Ph.D April, 2009 Presentation.](https://reader035.fdocuments.us/reader035/viewer/2022070306/5519c8e9550346047c8b4918/html5/thumbnails/17.jpg)
Crossing #4, Precast Wingwall
![Page 18: Overcoming Oregon Design-Build Challenges Rapid Bridge Replacement at Hancock Mountain Scott M. Nettleton P.E. Justin Doornink Ph.D April, 2009 Presentation.](https://reader035.fdocuments.us/reader035/viewer/2022070306/5519c8e9550346047c8b4918/html5/thumbnails/18.jpg)
Crossing #3
• ___ ________ ______ ________ ___
– _____ _________ ____
– _____ ______________ _________
– ____ ____________ ________
– ___ ____ ________ ____ _____
– ____ _____ ______ ______ ____ _____ ___ _________ _____ ______ ______ ____ _____ ___ _____
– ______ ________________ __________
• More Difficult SiteMore Difficult Site
– Longer spanLonger span
– Curved alignmentCurved alignment
– Super - elevatedSuper - elevated
– High skew angleHigh skew angle
– Steel plate girder bridge with short end spansSteel plate girder bridge with short end spans
– Extreme topographyExtreme topography
![Page 19: Overcoming Oregon Design-Build Challenges Rapid Bridge Replacement at Hancock Mountain Scott M. Nettleton P.E. Justin Doornink Ph.D April, 2009 Presentation.](https://reader035.fdocuments.us/reader035/viewer/2022070306/5519c8e9550346047c8b4918/html5/thumbnails/19.jpg)
Design Challenges
• Short End Span ConfigurationShort End Span Configuration
– Produces upliftProduces uplift
– Code requires restraintCode requires restraint
Difficult to install complex restraint system in short time periodDifficult to install complex restraint system in short time period
– SolutionSolution
Construct bridge with “low” ends to Construct bridge with “low” ends to elasticallyelastically deform upon placement deform upon placement
and “pre-stress” a downward force onto the abutmentsand “pre-stress” a downward force onto the abutments
Not sufficient to offset all code required loads, but it will cover the Not sufficient to offset all code required loads, but it will cover the
Service loading.Service loading.
Originally based no the concept of Alternate Load Factor Design. Originally based no the concept of Alternate Load Factor Design.
Plastic deformation to establish an “Auto-moment”. Abandoned Plastic deformation to establish an “Auto-moment”. Abandoned
because criteria do not support bottom flange plastic deformation, because criteria do not support bottom flange plastic deformation,
contract also disallows untried techniques.contract also disallows untried techniques.
![Page 20: Overcoming Oregon Design-Build Challenges Rapid Bridge Replacement at Hancock Mountain Scott M. Nettleton P.E. Justin Doornink Ph.D April, 2009 Presentation.](https://reader035.fdocuments.us/reader035/viewer/2022070306/5519c8e9550346047c8b4918/html5/thumbnails/20.jpg)
Crossing #3 Plans
![Page 21: Overcoming Oregon Design-Build Challenges Rapid Bridge Replacement at Hancock Mountain Scott M. Nettleton P.E. Justin Doornink Ph.D April, 2009 Presentation.](https://reader035.fdocuments.us/reader035/viewer/2022070306/5519c8e9550346047c8b4918/html5/thumbnails/21.jpg)
Differing Skew Angles
![Page 22: Overcoming Oregon Design-Build Challenges Rapid Bridge Replacement at Hancock Mountain Scott M. Nettleton P.E. Justin Doornink Ph.D April, 2009 Presentation.](https://reader035.fdocuments.us/reader035/viewer/2022070306/5519c8e9550346047c8b4918/html5/thumbnails/22.jpg)
Existing Structure, Before
![Page 23: Overcoming Oregon Design-Build Challenges Rapid Bridge Replacement at Hancock Mountain Scott M. Nettleton P.E. Justin Doornink Ph.D April, 2009 Presentation.](https://reader035.fdocuments.us/reader035/viewer/2022070306/5519c8e9550346047c8b4918/html5/thumbnails/23.jpg)
Shoring at Bent 3
![Page 24: Overcoming Oregon Design-Build Challenges Rapid Bridge Replacement at Hancock Mountain Scott M. Nettleton P.E. Justin Doornink Ph.D April, 2009 Presentation.](https://reader035.fdocuments.us/reader035/viewer/2022070306/5519c8e9550346047c8b4918/html5/thumbnails/24.jpg)
Shoring at Bent 3
![Page 25: Overcoming Oregon Design-Build Challenges Rapid Bridge Replacement at Hancock Mountain Scott M. Nettleton P.E. Justin Doornink Ph.D April, 2009 Presentation.](https://reader035.fdocuments.us/reader035/viewer/2022070306/5519c8e9550346047c8b4918/html5/thumbnails/25.jpg)
Precasting End Panels
![Page 26: Overcoming Oregon Design-Build Challenges Rapid Bridge Replacement at Hancock Mountain Scott M. Nettleton P.E. Justin Doornink Ph.D April, 2009 Presentation.](https://reader035.fdocuments.us/reader035/viewer/2022070306/5519c8e9550346047c8b4918/html5/thumbnails/26.jpg)
Crossing #3, Three Dimensional Modeling
![Page 27: Overcoming Oregon Design-Build Challenges Rapid Bridge Replacement at Hancock Mountain Scott M. Nettleton P.E. Justin Doornink Ph.D April, 2009 Presentation.](https://reader035.fdocuments.us/reader035/viewer/2022070306/5519c8e9550346047c8b4918/html5/thumbnails/27.jpg)
Summary and Conclusions
• _____ ________ __ ______ ________________ ________ __ ______ ___________
– ____ ____ ________ ___________ ____ ____ ________ ___________
– ____ ____ ____ _____ ____ ____ ____ _____
– ____ ____ ____ ______ __ ____ __ ____ ____ ____ ______ __ ____ __
___________ ___________
• _________ __ ____ ___ ______ ______________ __ ____ ___ ______ _____
– ______ _______ ____ ___ ____ _________ ______ _______ ____ ___ ____ _________
________ __ _____ ________ ____ ____ ___ ________ __ _____ ________ ____ ____ ___
____ _______ _______ __ __ _______ ____ ___ ____ _______ _______ __ __ _______ ____ ___
______ ____ __ ___ _____________ ____ __ ___ _______
– _____ ____ __ ___ ___________ ______ ____ _____ ____ __ ___ ___________ ______ ____
____ ____ __________ ____ ______
• Useful Technique in Various EnvironmentsUseful Technique in Various Environments
– Dense Urban (I-5 trunnion replacement)Dense Urban (I-5 trunnion replacement)
– Small Urban (Depot Street)Small Urban (Depot Street)
– Rural with long detour (Elk Creek to Hardscrabble)Rural with long detour (Elk Creek to Hardscrabble)
• Perception is Often the Biggest HurdlePerception is Often the Biggest Hurdle
– Several Projects have had this technique proposed in Several Projects have had this technique proposed in
Oregon, Generally they have not gone forward because it is Oregon, Generally they have not gone forward because it is
felt that the impact will be too extreme.felt that the impact will be too extreme.
• Note: Proposed on McKay Cr to Silvies Slough project, Note: Proposed on McKay Cr to Silvies Slough project,
Proposal evaluators indicated that the technique was Proposal evaluators indicated that the technique was
inappropriate at that site, despite relatively simple detour.inappropriate at that site, despite relatively simple detour.
– Design Build is the contracting format that make this Design Build is the contracting format that make this
happen. happen.
![Page 28: Overcoming Oregon Design-Build Challenges Rapid Bridge Replacement at Hancock Mountain Scott M. Nettleton P.E. Justin Doornink Ph.D April, 2009 Presentation.](https://reader035.fdocuments.us/reader035/viewer/2022070306/5519c8e9550346047c8b4918/html5/thumbnails/28.jpg)
Summary and Conclusions - continued
• Technical ChallengesTechnical Challenges
– Connecting the super structure appropriately to the Connecting the super structure appropriately to the
substructure after the movesubstructure after the move
Satisfactory performance under ServiceSatisfactory performance under Service
Seismic Loads – connections to transfer loads Seismic Loads – connections to transfer loads
appropriately are difficult, isolation should be appropriately are difficult, isolation should be
investigated (no anticipated cost advantage)investigated (no anticipated cost advantage)
– Understanding of grades and movementsUnderstanding of grades and movements
Encourage 3-D modeling and sophisticated Encourage 3-D modeling and sophisticated
visualizationvisualization
![Page 29: Overcoming Oregon Design-Build Challenges Rapid Bridge Replacement at Hancock Mountain Scott M. Nettleton P.E. Justin Doornink Ph.D April, 2009 Presentation.](https://reader035.fdocuments.us/reader035/viewer/2022070306/5519c8e9550346047c8b4918/html5/thumbnails/29.jpg)
Crossing #4, Time Lapse