Organization and Capabilities Introduction Offshore ... · Organization and Capabilities...
Transcript of Organization and Capabilities Introduction Offshore ... · Organization and Capabilities...
Organization and Capabilities Introduction
Offshore Engineering and Technical Services
January, 2014
• A registered Chinese company, headquartered at Shekou-Shenzhen, wholly owned by a Hong Kong registered entity.
• Company founded by technical, and operations specialists from Oil & Gas industry with a great depth of international experience:
China Brazil Africa Russia GOM
• Organization’s objectives:
i. Complete challenging oil and gas engineering projects
ii. Facilitate technology exchange between China and overseas technology companies
iii. Maintain a focus on HS&E and legal or regulatory compliance
• Partnered with industry leading firms exclusively representing their business activities within China.
Summary Introduction
• Areas of Expertise
– Project Management and Technical Staffing
– Drilling Operations and Well Planning
– Fracturing operations – design, analysis and on-site supervision
– Completions and Artificial Lift design
– Flow assurance and Process Modeling (Hysim and Olga)
– Asset Integrity Management and Materials Selection
– Operational Readiness Documentation and Commissioning Services
– Production Chemistry and Materials Selection
• Field Operations and Development Projects
– Application of Lessons Learned
• 24 years per consultant average experience based in China
– Feasibility, Based on Life of Field
• What makes sense based on the actual well and reservoir history
– Design and Integration Requirements
• From the reservoir, to well, to the production facility to export
What can we do?
Offshore Gas Project - Case History No. 1
• Petrobras - Peroa Cangoa Gas Field
– Sub-sea well completions in water depths to 100 to 500+ meters
– Initial 4 well design in varying water depths
– First wet gas sub-sea umbilical pipeline within Brazil.
– Design envelope of 0.5 to 2.3 million scm per day
• 8 to 350 m3 per day of condensate
– Completed flow assurance study and recommended line sizing
– Supported materials of construction selection process
– Developed production treatment strategy
– Oversaw offshore and onshore
facility commissioning
Angola Deepwater Project Management
Case History No. 2 ‐ TLPs and FPSOs
• Exxon Mobil – Kizomba Projects (Block 15) – 1,300 meters water depth
• Production of 488,000 bopd from two deepwater production systems
• Predictive modeling of the flow characteristics in the flow lines (1300 meters water depth)
• Support of the selection of materials used in the construction of deepwater structures
• Developed process operational procedures
• On-site comissioning support and process troubleshooting services
• Development of corrosion monitoring – ER and weight loss corrosion coupons, Fe+ levels etc.
• Failure analyses – ship deck on new build vessel, and also heat exchanger tubes
Case History 3
FEED Study
• FEED and Project Study for Perdido, Shell Gulf of Mexico
– Mudline boosting system for water depth of 2,600 meters
– Design based on US patent authored by Profundo staff
– Production rates up to 25,000 BFPD
• Initial Design and Functional Validation
– Identification and validation of the system to the component level
– Key requirements for command and control structure
– Scope of Supply
– Qualification Plan
– Integration Requirements
– Factory Acceptance Testing (FAT) Requirements
– Systems Integration Testing (SAT) Requirements
Deepwater Feed Study - Case History No. 3
FEED Study and Project Management
Case History No. 4
• FEED and Project Management Jubarte Field – Petrobras, Brazil
– Water Depth 1400 m - Deepest subsea Electric Submersible Pump completion (2006)
• 6000m Pipeline and Tie Back
• Design Production Rate 22,000 BFPD (3500 M3FPD)
• Sea Bed temperature 40F (4C)
– 17 API Crude, Flow Assurance Challenges - Modeling
• Well sizing and design prior to drilling operations
– Largest Horsepower system ever installed (2006) – 1200 Hp
– Designed to be produced initially with Gas Lift (GL) then transition to ESP production
– Interface and Project Management
• Tree Interface Design and Qualification
• Oversight of drilling operations
• Onsite rig supervision during completion
Construction and Commissioning
Case History No. 5
• Olowi Project, CNR Int. – Gabon Africa
– $1.6+ billion USD Project
– 35 meters of water - oil rim/gas reservoir
– Managed construction and pipe laying
– Used ENI HLV and Bokalis pipe laying vessels
– Well tubing heat traced and also flow lines – (paraffinic crude oil)
– Contract management of FPSO and MPVs
– Managed successful commissioning of system
Case History 2 Artificial Lift Design
Exeter - Mutineer Project Design, Santos Australia,
– Water depth of 140 meters
– Step-outs up to 7 km
– Production rates 12,000 to 20,000 BFPD
• Design of dual (redundant) ESP systems
– Surface and down hole string design – component level
– Scope of supply
• Tree Interface Design and Qualification
• Command and Control Structure
• Qualification Plan
• Integration Requirements
• Factory Acceptance Testing (FAT)
• Systems Integration Testing (SIT)
Artificial Lift Design - Case History No. 6
Offering complete staffing solutions for offshore oil and gas facilities:
• Staff have worked on the deepest and most challenging oil and gas
production wells in the world.
• Experts in deepwater facility design and development
• Management possesses extensive oil and gas deepwater operations
experience in the field.
• Projects co-ordinated or managed by professional staff based within
PRC employed by a registered Chinese entity.
• Flexibility with respect to contracting services structure
Summary Value ProposiDon