Community MeetingBoone High School Capital Projects
OCTOBER 30, 2017
Welcome! Please sign in on your mobile device:
http://communitymeeting.ocps.net/
Orange County Public Schools
Boone High School 2
Boone High School Community MeetingMeeting AgendaOctober 30, 2017 6:00 PM
•Welcome – School Board Member: Linda Kobert
•Introductions – Lauren Roth/ Facilities Communications
•Project Update – Architect:Contractor: Williams Construction Co.
•Questions and Answers
•Adjournment
Orange County Public Schools
Boone High School 3Campus Overview
100
200300
500
1300 800
40010001100
700
600Football Field & Track
Practice
Softball
Baseball
Retention
BusParent
BlanknerElementary
WadeviewPark
M I C H I G A N S T R E E T
K A L E Y S T R E E T
MI
LL
S A
VE
.LAKE
WADE
Delaney Street Baptist Church
north
Boone High School Master Plan
4
JAN. 2018
FEB. MAR. APR. MAY JUNE JULY AUG. SEPT. OCT. NOV. DEC. JAN. 2020
FEB. MAR. APR. MAY JUNE JULY AUG. SEPT. OCT. NOV. DEC. JAN. 2019
FEB. MAR. APR. MAY JUNE JULY
Phase 1
100
0’ 100’
north
200
1000
500
1300
600
700
300
800
Capital Renewal Work Begins in Building 100 Begins
Capital Renewal Project to Construct New StormwaterExfiltration System Begins
1100
400
Existing Baseball
Existing Softball
Existing Track, Field,
and Stadium
Practice Field
SUMMER SUMMERBASEBALL SEASON BASEBALL SEASON
Existing Bus Drop
Existing Parent Drop
400
Boone High School Master Plan
5
JAN. 2018
FEB. MAR. APR. MAY JUNE JULY AUG. SEPT. OCT. NOV. DEC. JAN. 2020
FEB. MAR. APR. MAY JUNE JULY AUG. SEPT. OCT. NOV. DEC. JAN. 2019
FEB. MAR. APR. MAY JUNE JULY
Phase 2
0’ 100’
north
Demolition of Existing Auditorium & Construction of New Auditorium Begins
100
200
1000
500
1300
600
700
300
800
Aud.
BaseballConstruction of New Baseball Field Begins
1100
Capital Renewal Work Begins in Building 100, 200, 600, 700, 1000, & 1100.
Capital Renewal Work Begins in Buildings 700.
Capital Renewal Work Continues in Building 100
Existing Baseball
Existing Softball
Track, Field, and
Stadium
Practice Field
SUMMER SUMMERBASEBALL SEASON BASEBALL SEASON
Existing Bus Drop
Existing Parent Drop
400
Netting
Track Renovation/ Re-surfacing Begins
Boone High School Master Plan
6
JAN. 2018
FEB. MAR. APR. MAY JUNE JULY AUG. SEPT. OCT. NOV. DEC. JAN. 2020
FEB. MAR. APR. MAY JUNE JULY AUG. SEPT. OCT. NOV. DEC. JAN. 2019
FEB. MAR. APR. MAY JUNE JULY
Phase 3
0’ 100’
north
Capital Renewal Work Continues in Building 200
Construction of New Gymnasium & Business/Law Magnet Begins
Construction of New Baseball Field COMPLETE
Demolition of Existing Auditorium & Construction of New Auditorium Continues
Baseball
100
200
1000
500
1300
600
300
800
Aud.
1100
700Existing P.E.
Locker Rooms
Existing Music
Gym
Bus./Law
Existing Softball
Practice Field
SUMMER SUMMERBASEBALL SEASON BASEBALL SEASON
Existing Bus Drop
Existing Parent Drop
400
Netting
Track Renovation/ Re-surfacing COMPLETE
Track, Field, and
Stadium
Boone High School Master Plan
7
JAN. 2018
FEB. MAR. APR. MAY JUNE JULY AUG. SEPT. OCT. NOV. DEC. JAN. 2020
FEB. MAR. APR. MAY JUNE JULY AUG. SEPT. OCT. NOV. DEC. JAN. 2019
FEB. MAR. APR. MAY JUNE JULY
Phase 4
0’ 100’
north
100
200
1000
500
1300
600
700
300
800
Aud.
Gym
1100
Baseball
Construction of New Auditorium Continues
Construction of New Gymnasium & Business/Law Program Continues
Capital Renewal Work Begins in Buildings 300 & 500
Bus./Law
Existing Music
Existing P.E. Locker Rooms
SUMMER SUMMERBASEBALL SEASON BASEBALL SEASON
Existing Softball
Practice Field
Existing Bus Drop
Existing Parent Drop
400
Netting
Track, Field, and
Stadium
Boone High School Master Plan
8
JAN. 2018
FEB. MAR. APR. MAY JUNE JULY AUG. SEPT. OCT. NOV. DEC. JAN. 2020
FEB. MAR. APR. MAY JUNE JULY AUG. SEPT. OCT. NOV. DEC. JAN. 2019
FEB. MAR. APR. MAY JUNE JULY
Phase 5
0’ 100’
north
100
200
1000
500
1300
600
700
300
800
Aud.
Gym
Cafe.
1100
Baseball
Construction of New Auditorium COMPLETE
Construction of New Gymnasium & Business/Law Program COMPLETE
Capital Renewal Work Continues in Buildings 300 & 500
Demolition of Existing Gym and Construction of New Cafeteria Begins
Existing Cafeteria
Bus./Law
Existing Music
Existing P.E. Locker Rooms
SUMMER SUMMERBASEBALL SEASON BASEBALL SEASON
Existing Softball
Practice Field
Existing Bus Drop
Existing Parent Drop
400
Netting
Track, Field, and
Stadium
Boone High School Master Plan
9
JAN. 2018
FEB. MAR. APR. MAY JUNE JULY AUG. SEPT. OCT. NOV. DEC. JAN. 2020
FEB. MAR. APR. MAY JUNE JULY AUG. SEPT. OCT. NOV. DEC. JAN. 2019
FEB. MAR. APR. MAY JUNE JULY
Phase 5
0’ 100’
north
100
200
1000
500
1300
600
700
300
800
Aud.
Gym
Cafe.
1100
Baseball
Construction of New Cafeteria Continues
Existing Cafeteria
Bus./Law
Existing Music
Existing P.E. Locker Rooms
SUMMER SUMMERBASEBALL SEASON BASEBALL SEASON
Capital Renewal Project COMPLETE
Existing Softball
Practice Field
Existing Bus Drop
Existing Parent Drop
400
Netting
Track, Field, and
Stadium
Boone High School Master Plan
10
JAN. 2018
FEB. MAR. APR. MAY JUNE JULY AUG. SEPT. OCT. NOV. DEC. JAN. 2020
FEB. MAR. APR. MAY JUNE JULY AUG. SEPT. OCT. NOV. DEC. JAN. 2019
FEB. MAR. APR. MAY JUNE JULY
Phase 6
0’ 100’
north
1000
1300
600
Aud.
Gym
Cafe.
Practice Fields &/or Future Use
1100
Construction of Cafeteria and Demolition of Existing Building 800 and COMPLETEPractice Fields / Future Use
New Buildings GSF
New Prototype Cafeteria (w/out Central Plant) 29,975 New Prototype Gymnasium (with classrooms in
lieu of Locker Rooms) 39,217 New Prototype Auditorium Only 25,372
TOTAL NEW 94,564
Bus./Law700
Existing P.E. Locker Rooms
Existing Music
Future Portables
Baseball
Existing Softball
Practice Field
SUMMER SUMMERBASEBALL SEASON BASEBALL SEASON
Existing Bus Drop
Existing Parent Drop
400
Netting
100
200
500
300
Track, Field, and
Stadium
Addtl. 28 Pkg. Spaces
Orange County Public Schools
Boone High School 11Auditorium
Orange County Public Schools
Boone High School 12Gymnasium
Orange County Public Schools
Boone High School 13Cafeteria
Orange County Public Schools
Boone High School 14
• Windermere High School
• Oak Ridge High School replacement
• Lake Nona High School
• Evans High School replacement
• East River High School
• West Orange High School replacement
• Ocoee High School
• Apopka High School replacement
• Freedom High School
• Timber Creek High School
• Olympia High School
PREVIOUS OCPS SCHOOLS USING THE SAME/SIMILAR PROTOTYPE BUILDING COMPONENTS
Orange County Public Schools
Boone High School 15
Questions and Answers