Transcript of Operate Chilled Water System

  • 7/28/2019 Operate Chilled Water System

    1/35

    NationalSkills

    Standard

    Copyright WDA 2003Updated on December

    Industry Chemical Process

    Reference CPS-028-2-0403

    Job Function Operate utilities for chemical

    Level NSC-2

    Unit of Competence Operate chilled water system

    manufacturing plant

  • 7/28/2019 Operate Chilled Water System

    2/35

    1

    UNIT OF COMPETENCE

    Operate chilled water system

    LEVEL

    NSC-2

    SN ELEMENTS OF COMPETENCE

    1 Prepare to operate chilled water system

    2 Start-up chilled water system

    3 Monitor and maintain chilled water system

    4 Shut down chilled water system

  • 7/28/2019 Operate Chilled Water System

    3/35

  • 7/28/2019 Operate Chilled Water System

    4/35

    3

    ELEMENT OF COMPETENCE

    1 Prepare to operate chilled water system

    UNIT OF COMPETENCE

    NSC-2 Operate chille

    PERFORMANCE CRITERIA UNDERPINNING KNOWLEDGE RANGE EVI

    Field preparation

    Personal protectiveequipment

    Safety helmet

    Safety shoes

    Safety goggles

    Ear plugs

    Gloves

    Overalls

    Plant and equipment

    Pumps

    Valves

    Piping system

    Compressor

    Lubrication system

    Evaporator

    Condenser

    Heat exchanger(absorber)

    Refrigeration system

    Electricity supply

    Tanks and vessels

    Cooling tower

    Cooling water system Chemical treatment

    systems

    Control instruments

  • 7/28/2019 Operate Chilled Water System

    5/35

    4

    ELEMENT OF COMPETENCE

    1 Prepare to operate chilled water system

    UNIT OF COMPETENCE

    NSC-2 Operate chille

    PERFORMANCE CRITERIA UNDERPINNING KNOWLEDGE RANGE EVI

    Valves, actuators anddampers

    - Electric

    - Hydraulic

    - Pneumatic

    - Manual

    Compressed air systems

    Filters

    Strainers

    Pressure control devices

    Water analysers

    Drum screens andcleaning systems

    Documentation

    Safety checklist

    Shift log

    Health, safety andenvironmental hazards

    Pressure build up

    Compressor and pumpfailure

    Hose rupture or leakage

    Faulty instruments

    Toxic and hazardous

    materials

    Appropriate person

    Supervisor

  • 7/28/2019 Operate Chilled Water System

    6/35

    5

    ELEMENT OF COMPETENCE

    1 Prepare to operate chilled water system

    UNIT OF COMPETENCE

    NSC-2 Operate chille

    PERFORMANCE CRITERIA UNDERPINNING KNOWLEDGE RANGE EVI

    Relevant process units

    - Utility plants

    - Process plants

    Environment

    Operating plant

  • 7/28/2019 Operate Chilled Water System

    7/35

  • 7/28/2019 Operate Chilled Water System

    8/35

    7

    ELEMENT OF COMPETENCE

    2 Start-up chilled water system

    UNIT OF COMPETENCE

    NSC-2 Operate chille

    PERFORMANCE CRITERIA UNDERPINNING KNOWLEDGE RANGE EVI

    - Condenser

    - Refrigerant

    Water analysers

    Auxiliary safety andcontrol equipment

    Non-conformances andabnormalities

    Failure and malfunction

    - Pump

    - Actuator

    - Valve

    - Dampers

    - Control equipment

    Electricity supply failure

    Instrument air supplyfailure

    Water supply failure

    Water quality

    Excessive vibration

    - Pumps

    - Motors

    High filter and strainerdifferential pressure

    Pressure build up

    System leakage

    Water temperature

    Toxic and hazardousmaterials

  • 7/28/2019 Operate Chilled Water System

    9/35

    8

    ELEMENT OF COMPETENCE

    2 Start-up chilled water system

    UNIT OF COMPETENCE

    NSC-2 Operate chille

    PERFORMANCE CRITERIA UNDERPINNING KNOWLEDGE RANGE EVI

    Communication mode

    Walkie-talkie

    Appropriate person

    Supervisor

    Relevant process units

    - Utility plants

    - Process plants

    Environment

    Operating plant

  • 7/28/2019 Operate Chilled Water System

    10/35

    9

    ELEMENT OF COMPETENCE

    3 Monitor and maintain chilled water system

    UNIT OF COMPETENCE

    NSC-2 Operate chille

    PERFORMANCE CRITERIA UNDERPINNING KNOWLEDGE RANGE EVI

    1 Chilled water system operation is monitored and maintained inaccordance with given work instructions and established organisationalprocedures

    2 Plant and equipment are routinely inspected to ensure good workingcondition in accordance with established organisational procedures

    Chilled water tank is monitored

    Refrigeration system, compressor and lubrication is monitored

    Water level and quality, pumps and heat exchanger are monitored

    3 Operating parameters for temperature, flow, pressure and level aremonitored and maintained in accordance with establishedorganisational procedures

    4 Water samples are tested to ensure water quality falls within prescribedspecifications in accordance with established organisational procedures

    5 Abnormalities encountered during monitoring and maintaining ofcondensate system are rectified, documented and reported toappropriate person in accordance with established organisationalprocedures

    6 Relevant industrial health and safety precautions are adhered to duringmonitoring and maintaining of chilled water system in accordance withestablished organisational procedures

    7 Where monitoring and maintaining of chilled water system cannot becarried out or completed, appropriate person is informed

    1 Organisational procedures relatedto monitoring and maintainingoperation of chilled water system

    2 Organisational procedures relatedto inspection of plant and equipment

    3 Operating parameters fortemperature, flow, pressure andlevel

    4 Organisational procedures relatedto water quality

    5 Abnormalities and faults in plantand equipment

    6 Organisational procedures relatedto industrial health and safety

    Organisational procedures

    Monitoring andmaintaining operation ofchilled water system

    Inspection of plant andequipment

    Water quality

    Industrial health andsafety

    Monitoring chilled watersystem and equipment

    Chilled water tank

    Pumps, valves andactuators

    Heat exchanger

    Filter

    Strainer

    Refrigeration system

    Operating parameters

    - Pressure

    - Flow

    - Temperature

    - Level

    Water quality

    - Nitrate

    - pH

    - Water conductivity

    - Total dissolvedsolids

  • 7/28/2019 Operate Chilled Water System

    11/35

    10

    ELEMENT OF COMPETENCE

    3 Monitor and maintain chilled water system

    UNIT OF COMPETENCE

    NSC-2 Operate chille

    PERFORMANCE CRITERIA UNDERPINNING KNOWLEDGE RANGE EVI

    Abnormalities and faults inplant and equipment

    Failure and malfunction

    - Pump

    - Actuator

    - Valve

    - Dampers

    - Control equipment

    Electricity supply failure

    Instrument air supplyfailure

    Water supply failure

    Water quality Excessive vibration

    - Pumps

    - Motors

    High filter and strainerdifferential pressure

    Pressure build up

    System leakage

    Water temperature

    Toxic and hazardousmaterials

    Industrial health and safetyprecautions

    Use of personalprotective equipment

    Use of safety checklistand inspections

  • 7/28/2019 Operate Chilled Water System

    12/35

    11

    ELEMENT OF COMPETENCE

    3 Monitor and maintain chilled water system

    UNIT OF COMPETENCE

    NSC-2 Operate chille

    PERFORMANCE CRITERIA UNDERPINNING KNOWLEDGE RANGE EVI

    Personal protectiveequipment

    Safety helmet

    Safety shoes

    Safety goggles

    Ear plugs

    Gloves

    Overalls

    Appropriate person

    Supervisor

    Relevant process units

    - Utility plants- Process plants

    Environment

    Operating plant

  • 7/28/2019 Operate Chilled Water System

    13/35

  • 7/28/2019 Operate Chilled Water System

    14/35

    13

    ELEMENT OF COMPETENCE

    4 Shut down chilled water system

    UNIT OF COMPETENCE

    NSC-2 Operate chille

    PERFORMANCE CRITERIA UNDERPINNING KNOWLEDGE RANGE EVI

    Use of blind tracking list

    Relevant permit to work

    Abnormalities in shut down

    Plant and equipment

    - Failure

    - Faults

    - Damage

    - Malfunction

    Documentation

    Safety checklist

    Job report Shift log

    Communication mode

    Walkie-talkie

    Appropriate person

    Supervisor

    Relevant process units

    - Utility plants

    - Process plants

    Environment

    Operating plant

  • 7/28/2019 Operate Chilled Water System

    15/35

    14

    II ASSESSMENT PLAN

    A Performance

    CANDIDATE NAME NRICJOB TITLE TELEPHONE

    COMPANY

    UNIT OF COMPETENCE

    NSC-2 Operate chilled wa

    COMPETENT*ASSESSMENT PERFORMANCE CRITERIA

    YES NOREM

    A Prepare to operate chilled water system

    1 Reference is made to process and instrumentation diagrams,commissioning procedures and technical manuals related to plantand equipment prior to commencement of work activities

    2 Chilled water system operational pre-requisites and any givenwork instructions are clarified with appropriate person

    3 Appropriate personal protective equipment is worn in accordancewith established organisational procedures

    1 Practical test

    Given the following:

    Chilled water system ormock-up

    Process and

    instrumentation diagrams

    Equipment lists

    Technical specifications

    Safety checklists

    System operation manuals

    Materials Safety DataSheets

    Commissioning procedures

    Personal protectiveequipment

    Walkie talkie

    Perform the following taskswithin 1 hour 20 minutes:

    Prepare to operate chilledwater system within 20minutes

    4 Inspection and field walk-down is carried out to verify plant andequipment status in accordance with established organisationalprocedures

    Plant and related equipment are checked

    Valve status is checked

    Line-up status is checked

    Service and utility supply are checked

    * Please tick

  • 7/28/2019 Operate Chilled Water System

    16/35

    15

    CANDIDATE NAME NRIC

    JOB TITLE TELEPHONE

    COMPANY

    UNIT OF COMPETENCE

    NSC-2 Operate chilled wa

    COMPETENT*ASSESSMENT PERFORMANCE CRITERIA

    YES NOREM

    5 Potential health, safety and environmental hazards are rectifiedand documented in accordance with established organisationalprocedures

    6 Where potential health, safety and environmental hazards cannotbe rectified, appropriate person is informed

    7 Preparation to operate chilled water system is carried out andcompleted in accordance with industrial health and safetyprocedures

    8 Where preparation to chilled water system cannot be carried outor completed, appropriate person is informed

    B Start-up chilled water system

    9 Start-up of chilled water system is carried out in accordance withgiven work instructions and established organisationalprocedures

    Start-up chilled watersystem within 20 minutes

    Monitor and maintainchilled water system within20 minutes

    Shut down chilled watersystem within 20 minutes

    10 Communication with appropriate persons from relevant processunits is carried out in accordance with established organisationalprocedures

    * Please tick

  • 7/28/2019 Operate Chilled Water System

    17/35

    16

    CANDIDATE NAME NRIC

    JOB TITLE TELEPHONE

    COMPANY

    UNIT OF COMPETENCE

    NSC-2 Operate chilled wa

    COMPETENT*ASSESSMENT PERFORMANCE CRITERIA

    YES NOREM

    11 Chilled water system is lined up in accordance with systemrequirements and established organisational procedures

    Tank

    Pump

    Heat exchanger

    Safety and drain valves

    12 Refrigeration, chilled and cooling water systems are checked toensure proper line up and integration in accordance with systemrequirements and established organisational procedures

    13 Chemical injection dosage to chilled water system is adjusted andmaintained in accordance with established organisationalprocedures

    14 Water quality analysers are commissioned in accordance withestablished organisational procedures

    2 Oral test

    Oral questions to coverperformance criteria 5, 6, 8, 17,18, 23, 25, 33 and 36

    Candidates are required toanswer 9 oral questions in 15minutes

    Sample Questions forPerformance Criteria

    5 What should be done if apotential safety hazard isdiscovered duringpreparation to operatechilled water system?

    6 What should be done if anabnormality in plantequipment cannot beimmediately rectified?

    8 What should be done ifpreparation to operatechilled water systemcannot be carried out or

    completed?15 Instrument controls are commissioned and checked for

    functionality in accordance with established organisationalprocedures

    * Please tick

  • 7/28/2019 Operate Chilled Water System

    18/35

    17

    CANDIDATE NAME NRIC

    JOB TITLE TELEPHONE

    COMPANY

    UNIT OF COMPETENCE

    NSC-2 Operate chilled wa

    COMPETENT*ASSESSMENT PERFORMANCE CRITERIA

    YES NOREM

    16 Control system is set to appropriate pressure, temperature, leveland flow settings in accordance with established organisationalprocedures

    17 Non-conformances and abnormalities are identified, rectified anddocumented in accordance with established organisationalprocedures

    18 Where start-up of chilled water system cannot be carried out orcompleted, appropriate person is informed

    C Monitor and maintain chilled water system

    19 Chilled water system operation is monitored and maintained inaccordance with given work instructions and establishedorganisational procedures

    17 What should be done if anabnormality in refrigerationsystem is identified duringstart-up of chilled watersystem?

    18 What should be done ifstart-up of chilled watersystem cannot becompleted?

    23 What should be done if anabnormality in temperatureis identified duringmonitoring of chilled watersystem operation?

    25 What should be done ifchilled water quality cannotbe maintained?

    33 What should be done if anabnormality in chilled watersystem equipment isdiscovered during shutdown?

    36 What should be done ifshut down of chilled water

    system cannot becompleted?

    20 Plant and equipment are routinely inspected to ensure goodworking condition in accordance with established organisationalprocedures

    Chilled water tank is monitored

    Refrigeration system, compressor and lubrication ismonitored

    Water level and quality, pumps and heat exchanger aremonitored

    * Please tick

  • 7/28/2019 Operate Chilled Water System

    19/35

    18

    CANDIDATE NAME NRIC

    JOB TITLE TELEPHONE

    COMPANY

    UNIT OF COMPETENCE

    NSC-2 Operate chilled wa

    COMPETENT*ASSESSMENT PERFORMANCE CRITERIA

    YES NOREM

    21 Operating parameters for temperature, flow, pressure and levelare monitored and maintained in accordance with establishedorganisational procedures

    22 Water samples are tested to ensure water quality falls withinprescribed specifications in accordance with establishedorganisational procedures

    23 Abnormalities encountered during monitoring and maintaining ofcondensate system are rectified, documented and reported toappropriate person in accordance with established organisationalprocedures

    24 Relevant industrial health and safety precautions are adhered toduring monitoring and maintaining of chilled water system inaccordance with established organisational procedures

    25 Where monitoring and maintaining of chilled water system cannotbe carried out or completed, appropriate person is informed

    D Shut down chilled water system

    26 Shut down of chilled water system is carried out in accordancewith given work instructions and established organisationalprocedures

    * Please tick

  • 7/28/2019 Operate Chilled Water System

    20/35

    19

    CANDIDATE NAME NRIC

    JOB TITLE TELEPHONE

    COMPANY

    UNIT OF COMPETENCE

    NSC-2 Operate chilled wa

    COMPETENT*ASSESSMENT PERFORMANCE CRITERIA

    YES NOREM

    27 Shut down sequence and system status are clarified withappropriate person in accordance with established organisationalprocedures

    28 Safety precautions are adhered to and personal protectiveequipment is worn in accordance with established organisationalprocedures

    29 Communication with appropriate persons from relevant processunits is carried out in accordance with established organisationalprocedures

    30 Chilled water equipment operation is stopped and chilled watersystem is isolated in accordance with established organisationalprocedures

    Refrigeration system

    Pumps

    Heat exchanger

    31 Chilled water system is depressured and chilled water is drained,where required, in accordance with established organisationalprocedures

    * Please tick

  • 7/28/2019 Operate Chilled Water System

    21/35

    20

    CANDIDATE NAME NRIC

    JOB TITLE TELEPHONE

    COMPANY

    UNIT OF COMPETENCE

    NSC-2 Operate chilled wa

    COMPETENT*ASSESSMENT PERFORMANCE CRITERIA

    YES NOREM

    32 Inspection of plant and equipment is carried out to confirm status,and to ensure proper shut down, depressurisation and drainagein accordance with established organisational procedures

    33 Abnormalities encountered during shut down of chilled watersystem are rectified, documented and reported to appropriateperson in accordance with established organisational procedures

    34 Shut down of chilled water system is accurately documented inaccordance with established organisational procedures

    35 Shut down of chilled water system is carried out and completed inaccordance with industrial health and safety procedures

    36 Where shut down of chilled water system cannot be carried out orcompleted, appropriate person is informed

    E Complete work activities within time scale

    37 Work activities are completed within agreed time scale for the unitof competence

    * Please tick

  • 7/28/2019 Operate Chilled Water System

    22/35

    21

    B Knowledge

    CANDIDATE NAME NRIC

    JOB TITLE TELEPHONE

    COMPANY

    UNIT OF COMPETENCE

    NSC-2 Operate chilled w

    COMPETENT*ASSESSMENT UNDERPINNING KNOWLEDGE

    YES NORE

    A Prepare to operate chilled water system

    1 Process and instrumentation diagrams and technical manuals

    2 Organisational procedures related to commissioning of chilledwater system

    3 Chilled water system operational pre-requisites

    4 Personal protective equipment

    3 Oral / Written test

    Candidates are required toanswer 31 questions in 45minutes.

    At least one question will be setfor each knowledge item.

    Sample questions are given at

    Annex A.

    5 Organisational procedures related to industrial health and safety

    * Please tick

  • 7/28/2019 Operate Chilled Water System

    23/35

    22

    CANDIDATE NAME NRIC

    JOB TITLE TELEPHONE

    COMPANY

    UNIT OF COMPETENCE

    NSC-2 Operate chilled w

    COMPETENT*ASSESSMENT UNDERPINNING KNOWLEDGE

    YES NORE

    6 Organisational procedures related to safety checks, pre-operational inspection and field-walk down

    7 Chemical process plants, chilled water systems and equipment

    8 Health, safety and environmental hazards

    9 Organisational procedures related to documentation

    10 Organisational procedures related to preparation to operate chilledwater system

    B Start-up chilled water system

    11 Organisational procedures related to start-up of chilled watersystem

    * Please tick

  • 7/28/2019 Operate Chilled Water System

    24/35

    23

    CANDIDATE NAME NRIC

    JOB TITLE TELEPHONE

    COMPANY

    UNIT OF COMPETENCE

    NSC-2 Operate chilled w

    COMPETENT*ASSESSMENT UNDERPINNING KNOWLEDGE

    YES NORE

    12 Parts, functions and operation of chilled water system andequipment

    13 Organisational procedures related to communications

    14 Organisational procedures related to line up of chilled watersystem

    15 Organisational procedures related to chemical injection dosage

    16 Organisational procedures related to commissioning of wateranalysers

    17 Organisational procedures related to start-up of control system

    * Please tick

  • 7/28/2019 Operate Chilled Water System

    25/35

    24

    CANDIDATE NAME NRIC

    JOB TITLE TELEPHONE

    COMPANY

    UNIT OF COMPETENCE

    NSC-2 Operate chilled w

    COMPETENT*ASSESSMENT UNDERPINNING KNOWLEDGE

    YES NORE

    18 Non-conformances and abnormalities

    C Monitor and maintain chilled water system

    19 Organisational procedures related to monitoring and maintainingoperation of chilled water system

    20 Organisational procedures related to inspection of plant andequipment

    21 Operating parameters for temperature, flow, pressure and level

    22 Organisational procedures related to water quality

    23 Abnormalities and faults in plant and equipment

    * Please tick

  • 7/28/2019 Operate Chilled Water System

    26/35

    25

    CANDIDATE NAME NRIC

    JOB TITLE TELEPHONE

    COMPANY

    UNIT OF COMPETENCE

    NSC-2 Operate chilled w

    COMPETENT*ASSESSMENT UNDERPINNING KNOWLEDGE

    YES NORE

    24 Organisational procedures related to industrial health and safety

    D Shut down chilled water system

    25 Organisational procedures related to shut down of chilled watersystem

    26 Organisational procedures related to industrial health and safety

    27 Organisational procedures related to communications

    28 Organisational procedures related to isolation, depressurisationand drainage of chilled water system

    29 Organisational procedures related to inspection of plant andequipment

    * Please tick

  • 7/28/2019 Operate Chilled Water System

    27/35

    26

    CANDIDATE NAME NRIC

    JOB TITLE TELEPHONE

    COMPANY

    UNIT OF COMPETENCE

    NSC-2 Operate chilled w

    COMPETENT*ASSESSMENT UNDERPINNING KNOWLEDGE

    YES NORE

    30 Abnormalities in shut down

    31 Organisational procedures related to documentation

    * Please tick

  • 7/28/2019 Operate Chilled Water System

    28/35

    27

    I certify that the candidate has/has not achieved all thecompetencies required in this unit of competence.

    I have audited the assessment and certified tconducted as stipulated by the skills standar

    Remarks Remarks

    Assessor Signature Supervising Assessor Signature

    Assessor Name Supervising Assessor Name

    Telephone Telephone

    Date Date

  • 7/28/2019 Operate Chilled Water System

    29/35

    28

    ANNEX A - SAMPLE QUESTIONS

    SN UNDERPINNING KNOWLEDGE QUESTIONS

    1

    A Prepare to operate chilled water system

    Process and instrumentation diagrams and technical manuals 1 Why is it necessary to refer to process and instrumentation diagrams chilled water system?

    2 Organisational procedures related to commissioning of chilledwater system

    2 What are commissioning procedures?

    3 Chilled water system operational pre-requisites 3 What operational pre-requisites should be in place prior to operation o

    4 Personal protective equipment 4 List the personal protective equipment required to be worn prior to fiesystem.

    5 Organisational procedures related to industrial health and safety 5 What industrial health and safety procedures related to personal proteobserved prior to commencement of work activities?

  • 7/28/2019 Operate Chilled Water System

    30/35

    29

    SN UNDERPINNING KNOWLEDGE QUESTIONS

    6 Organisational procedures related to safety checks, pre-operational inspection and field-walk down

    6 Explain how a field-walk down is conducted.

    7 Chemical process plants, chilled water systems and equipment 7 Explain the operation of a chilled water system in a chemical plant.

    8 Health, safety and environmental hazards 8 List three safety hazards related to chilled water system.

    9 Organisational procedures related to documentation 9 Explain what must be documented during preparation to operate chille

    10 Organisational procedures related to preparation to operate chilledwater system

    10 Explain the main tasks required to be performed when preparing to op

    11

    B Start-up chilled water system

    Organisational procedures related to start-up of chilled watersystem

    11 What must be checked when starting-up chilled water system?

  • 7/28/2019 Operate Chilled Water System

    31/35

    30

    SN UNDERPINNING KNOWLEDGE QUESTIONS

    12 Parts, functions and operation of chilled water system andequipment

    12 Why is the purpose of a heat exchanger in a chilled water system?

    13 Organisational procedures related to communications 13 How is communication between field and console technicians usually

    14 Organisational procedures related to line up of chilled watersystem

    14 Explain how a chilled water system is lined up.

    15 Organisational procedures related to chemical injection dosage 15 Explain how chemical injection dosage is set and monitored.

    16 Organisational procedures related to commissioning of wateranalysers

    16 Explain the function of a water analyser.

    17 Organisational procedures related to start-up of control system 17 Explain how control system is commissioned.

  • 7/28/2019 Operate Chilled Water System

    32/35

    31

    SN UNDERPINNING KNOWLEDGE QUESTIONS

    18 Non-conformances and abnormalities 18 List three common faults or abnormalities found in chilled water syste

    19

    C Monitor and maintain chilled water system

    Organisational procedures related to monitoring and maintainingoperation of chilled water system

    19 Explain the routine tasks performed during monitoring and maintainin

    20 Organisational procedures related to inspection of plant andequipment

    20 Explain how chilled water system is inspected or checked.

    21 Operating parameters for temperature, flow, pressure and level 21 Where can information relating to required operating parameters for televel be found?

    22 Organisational procedures related to water quality 22 Explain why water quality is important in a chilled water system.

    23 Abnormalities and faults in plant and equipment 23 List one common fault during monitoring and maintaining chilled waterectified.

  • 7/28/2019 Operate Chilled Water System

    33/35

    32

    SN UNDERPINNING KNOWLEDGE QUESTIONS

    24 Organisational procedures related to industrial health and safety 24 List two safety precautions which should be observed during monitoriwater system.

    25

    D Shut down chilled water system

    Organisational procedures related to shut down of chilled watersystem

    25 How often is shut down of chilled water system carried out, and what down?

    26 Organisational procedures related to industrial health and safety 26 List two important safety procedures which must be observed during ssystem.

    27 Organisational procedures related to communications 27 Who are the parties involved in shut down of chilled water system, anout?

    28 Organisational procedures related to isolation, depressurisationand drainage of chilled water system

    28 How is chilled water system isolated?

    29 Organisational procedures related to inspection of plant andequipment

    29 What should be checked after shut down of chilled water system?

  • 7/28/2019 Operate Chilled Water System

    34/35

    33

    SN UNDERPINNING KNOWLEDGE QUESTIONS

    30 Abnormalities in shut down 30 List three abnormalities in plant and equipment which can occur after system.

    31 Organisational procedures related to documentation 31 What must be documented after shut down of chilled water system?

  • 7/28/2019 Operate Chilled Water System

    35/35

    Skills and Curriculum Development Division

    Singapore Workforce Development Agency, c/o SPRING Singapore

    2 Bukit Merah Central #14-00, Singapore 159835

    Telephone: (65) 6223 0012 Facsimile: (65) 6276 5062

    Website: http://www wda gov sg/nsrs Email:wda nsrs@wda gov sg

    singaporeworkforcedevelopmentagency