Ohlone Elementary School Phase 1 Campus Replacement
9
OHLONE ELEMENTARY SCHOOL PHASE 1 CAMPUS REPLACEMENT
description
Ohlone Elementary School Phase 1 Campus Replacement. Ohlone Elementary School. Ohlone Elementary School. Ohlone Elementary School. Ohlone Elementary School Project Status Report. - PowerPoint PPT Presentation
Transcript of Ohlone Elementary School Phase 1 Campus Replacement
![Page 1: Ohlone Elementary School Phase 1 Campus Replacement](https://reader035.fdocuments.us/reader035/viewer/2022062517/56813cbb550346895da66731/html5/thumbnails/1.jpg)
OHLONE ELEMENTARY SCHOOLPHASE 1 CAMPUS
REPLACEMENT
![Page 2: Ohlone Elementary School Phase 1 Campus Replacement](https://reader035.fdocuments.us/reader035/viewer/2022062517/56813cbb550346895da66731/html5/thumbnails/2.jpg)
![Page 3: Ohlone Elementary School Phase 1 Campus Replacement](https://reader035.fdocuments.us/reader035/viewer/2022062517/56813cbb550346895da66731/html5/thumbnails/3.jpg)
![Page 4: Ohlone Elementary School Phase 1 Campus Replacement](https://reader035.fdocuments.us/reader035/viewer/2022062517/56813cbb550346895da66731/html5/thumbnails/4.jpg)
![Page 5: Ohlone Elementary School Phase 1 Campus Replacement](https://reader035.fdocuments.us/reader035/viewer/2022062517/56813cbb550346895da66731/html5/thumbnails/5.jpg)
Ohlone Elementary School
![Page 6: Ohlone Elementary School Phase 1 Campus Replacement](https://reader035.fdocuments.us/reader035/viewer/2022062517/56813cbb550346895da66731/html5/thumbnails/6.jpg)
Ohlone Elementary School
![Page 7: Ohlone Elementary School Phase 1 Campus Replacement](https://reader035.fdocuments.us/reader035/viewer/2022062517/56813cbb550346895da66731/html5/thumbnails/7.jpg)
Ohlone Elementary School
![Page 8: Ohlone Elementary School Phase 1 Campus Replacement](https://reader035.fdocuments.us/reader035/viewer/2022062517/56813cbb550346895da66731/html5/thumbnails/8.jpg)
![Page 9: Ohlone Elementary School Phase 1 Campus Replacement](https://reader035.fdocuments.us/reader035/viewer/2022062517/56813cbb550346895da66731/html5/thumbnails/9.jpg)
• Construction Days Elapsed: 233• Construction Days Remaining: 487• Percent of Contract Days Elapsed:
32%
Construction Schedule: 720 days
• Notice to Proceed: 8/1/11• Original Completion Date: 7/20/13• Percent of Construction Completed:
30%
Projected Completion
Date: 7/20/2013
Ohlone Elementary School Project Status Report