Transcript of Harding Elementary School Exterior Repairs & Select Roofing Replacement 08/12/2014.
WCCUSD Bond Program
Construction UpdateHarding Elementary School
Exterior Repairs & Select Roofing Replacement08/12/2014
General Contractor Best Contracting Services,
Inc.
Architect of Record Grossman Design Group
Construction Manager Willie Robinson
Harding Elementary SchoolExterior Repairs & Select Roofing
Replacement
Project Team
Contract Amount $918,600
Notice of Award 06/17/14
Notice to Proceed 07/21/14
Duration 56 days
Completion Date 09/15/14
Harding Elementary SchoolExterior Repairs & Select Roofing
Replacement
Project Team
Contractor has mobilized & installed site
surveillance
Set up stairs & scaffolding to access roof
and walls for demolition
Demolition of exterior walls
Removal of windows on west side of
building A
Harding Elementary SchoolExterior Repairs & Select Roofing
Replacement
Project Status