1 © Nokia Solutions and Networks 2014
NPO Services – Planning Process
• IMS Portfolio products
22/04/20232 © Nokia 2014 - File Name - Version - Creator - DocIDConfidential
IMS Products NPO Services Deliverables Tools Mapping of Services/Deliverables to IMS Products Planning flow Additional references
CONTENT
22/04/20233 © Nokia 2014 - File Name - Version - Creator - DocIDConfidential
NPO offers planning & design services for following IMS products :
- CFX-5000- CMS-8200 (HSS)- CMS-8200 (DRA)- iNUM- TAS- BGW- Oracle Acme SD /BG- Radisys MRF
IMS Products
22/04/20234 © Nokia 2014 - File Name - Version - Creator - DocIDConfidential
IMS Products
CMS-8200 (DRA)
Diameter Routing Agent
Multiple hardware options (HP, ATCA)
CFX-5000
Call Session Control Function (CSCF)
Breakout Gateway / Transit Routing control
Integrated Session Border Control Functionality
Multiple hardware options (HP, ATCA)
CMS-8200 (HSS)
HSS subscriber management integrated with central subscriber repository
Multiple hardware options (HP, ATCA)
iNUM
tElephone NUmber Mapping
Domain Name System (DNS)
Multiple hardware options (ATCA, HP-on request)
Open TAS
Telephony Applicaton Server
Multiple hardware options (HP, ATCA)
Open BGW
Border Gateway Function
ATCA hardware supported
Oracle Acme SD/BG
Session Director (SD) Border Gateway (BG) Rack mount servers
from Oracle
Radisys MRF
Media Resource Server
Rack mount servers from Radisys
22/04/20235 © Nokia 2014 - File Name - Version - Creator - DocIDConfidential
NPO ServicesNPO offers following planning & design services for all IMS products :
Note : These services as a whole are applicable to all IMS Products.Certain service component parts however can be product specific, as described in the “Mapping of Services/Deliverables to IMS Products” section
NOMINAL DESIGN Assessment of business strategy Assessment of technical parameters Creation of high level design documentation Solution design workshop
DETAILED DESIGN Low level network topology Detailed planning parameters Integration required application settings Equipment specific databuild for installation and pre-configuration
22/04/20236 © Nokia 2014 - File Name - Version - Creator - DocIDConfidential
NPO Services
NOMINAL DESIGN
DETAILED DESIGN
Assessment of business strategy and technical parameters Creation of high level design documentation
High level physical network topology High level logical network topology Protocol design
Solution design workshop
Low level network topology Low level physical network topology Low level logical network topology
Detailed planning parameters IP addressing scheme Equipment specific parameters
Integration required application settings Equipment specific databuild for installation and pre-configuration
Services Outputs
CIQCustomer Information Questionnaire
DNPDocumentation IT-Net Planning
TPDTechnical Project Data
22/04/20237 © Nokia 2014 - File Name - Version - Creator - DocIDConfidential
CIQCustomer Information QuestionnaireIs a living document intended to constitute an organized platform for collecting required integration inputs from customer side. It also plays a “project log” role by documenting the agreed integration approach. It is not a “deliverable” as of such, but supports the planning & design activity.
DNPDocumentation IT-Net PlanningConstitutes the actual customer specific planning documentation detailing high level and/or low level physical and IP network connectivity design and logical planning aspects. It is the official NPO deliverable within the project’s scope, a customer documentation that serves as reference and basis for later troubleshooting or expansions.
TPDTechnical Project DataRepresents the “Databuild” phase which is equipment & product specific, and based on which equipment installation & configuration scripts are created.
Following deliverables are within NPO Services scope for IMS Portfolio products :
NPO Service Deliverables
22/04/20238 © Nokia 2014 - File Name - Version - Creator - DocIDConfidential
NPO Service DeliverablesCIQ Details CONTENT :
Project and customer specific content related to all issues that require mutual agreement and customer inputs, like (but not limited to) :
Deployment overview aspects Network Design aspects Network Parameters
SCOPE and PURPOSE : It is a living document throughout the project/planning cycle, shared amongst the project team and customer side, documenting all agreed integration aspects and provided customer inputs. It is not intended as an actual delivery, but as a supporting document through out the planning phase to ensure best quality outcome and meeting customer requirements & expectations
SoR : Guidance/template development
responsibility : GS NPO Project development method : manual /
template based Project deployment responsibility : project
planner Guidance hosted in the GS NPO
Communities Support : GS NPO
CIQ Template for IMS
22/04/20239 © Nokia 2014 - File Name - Version - Creator - DocIDConfidential
DNP DetailsNPO Service Deliverables
CONTENT : Common Document
Document History Color codes Abbreviation list Red corrections
Requirements for IT Net Planning Internal/External Interface definitions
Network Topology Traffic categorization Deployment Overview Network segmentation
Network Parameters Host/VLAN Naming Scheme IP Network Details Physical Configuration IP Addressing Routing Rules IP Ranges Usage
ASI-PAE Handover Handover Points Overview Communication Relations
SOR : Guidance development responsibility : GS
NPO Project development method : SECANT Tool Project deployment responsibility : project
planner Guidance hosted in the GS NPO CEUS
Communities Support : GS NPO
DNP Master Template
22/04/202310 © Nokia 2014 - File Name - Version - Creator - DocIDConfidential
NPO Service DeliverablesEPF Details CONTENT :
•Common Document• Document History• Color codes• Abbreviation list• Red corrections
• Material List• Core Components• Additional Components
• System Engineering Requirements• Engineering requirements overview• Engineering requirements in detail
• Hardware Setup• Rack layout• Equipment interface configuration
• Annex 1 – Room Planning• Site Specifics• Room Details• Room Layout Diagram• Deployment Specifics
• Annex 2 – Cable Laying List• List of cables
• Annex 3 – Power Concept• Power Circuit Diagram• Power Circuit Configuration
SOR : Templates development responsibility :
NI ?? Project development method : manual /
template based Project deployment responsibility : NI ?? Support : NI
EPF is NOT a NPO Deliverable !
EPF is complementary to DNP, addressing power engineering and hardware setup
aspects
EPF = Engineering Planning FolderEPF
MasterTemplate
22/04/202311 © Nokia 2014 - File Name - Version - Creator - DocIDConfidential
NPO Service DeliverablesDNP & EPF Mapping
Common Document
Requirements for IT Net Planning
Network Topology
Network Parameters
ASI-PAE Handover
Common Document
Material List
System Engineering Requirements
Hardware Setup
Annex 1 – Room Planning
Annex 2 – Cable Laying List
Annex 3 – Power Concept
Documentation IT Net PlanningEngineering Planning Folder
HLD = Nominal Design
LLD = Detailed Design
Note : On customer demand, DNP & EPF can be presented also under a High Level Design (HLD) / Low Level Design (LLD) format, by mapping the information as shown above
22/04/202312 © Nokia 2014 - File Name - Version - Creator - DocIDConfidential
NPO Service DeliverablesTPD Contributors Overview for IMS Products
Department
Contributor
Contribution
TPD block
Customer Team (CT)
SSM SolutionArchitect
-Feature Parity (sales features)
- Feature Mapping- Parameter Matching
Product Line
R&D Expert
- Additional inputs
Technical Project Descriptor (TPD)
GS SI
SecurityExpert
- Security Data
NI
HW Engineer
- Hardware cross-check
GS NPO
Project Planner
- Network parameters- Routing rules- Node settings
22/04/202313 © Nokia 2014 - File Name - Version - Creator - DocIDConfidential
NPO Service DeliverablesTPD Details CONTENT :
Product specific content related to all required parameters for equipment installation and configuration, like (but not limited to) :
IP addressing & VLAN information Port settings Equipment specific application
settings
SCOPE and PURPOSE :
TPD is required mainly by NI / Staging Center for equipment pre-installationTPD defines various configuration parameters and IP addresses, required to bring up the IMS nodes.
SOR : Template development responsibility :
Product Line Project development method : manual /
SECANT Project deployment responsibility :
project planner Guidance hosted in the GS NPO Technical
Expertise Support : Product Line / GS NPO
TPD Homepage
22/04/202314 © Nokia 2014 - File Name - Version - Creator - DocIDConfidential
ToolsSECANT
SECANT is the official NSN tool for IP Planning and Design, maintained and developed by Network Engineering.
SECANT is an online tool that employs Product Line blueprints for various products
SECANT DNP generation is based on the DNP Master Template framework and the product blueprint, which combined with customized design possibilities and tool’s flexibility allow for product specific DNP generation within the project’s scope.
SECANT Homepage
22/04/202315 © Nokia 2014 - File Name - Version - Creator - DocIDConfidential
ToolsIMS Load Tool
IMS Load Tool is maintained and developed by Network Engineering.
IMS Load Tool is used to generate the BoQ/BoM for particular customer case as well as specifying some particular requirements (like inter-site required bandwidth).
Although the dimensioning is done by SSM (local CT) with Network Engineering support, the planner should be able to support re-dimensioning activities if such are required during planning phase by previously undocumented network aspects or customer specific requests.
IMS Load Tool Homepage
22/04/202316 © Nokia 2014 - File Name - Version - Creator - DocIDConfidential
Mapping of Services/Deliverables to IMS Products
Services :Nominal Design YES YES YES YES YES YES YES YES
Detailed Design YES YES YES YES YES YES YES YES
Deliverables :CIQ YES YES YES YES YES YES YES YES
DNP YES YES YES NO NO NO NO NO
TPD / Databuild YES YES YES YES YES YES* YES* NO
CFX-5000
CMS-8200 (HSS)
iNUMTAS BGW
CMS-8200 (DRA)
Oracle A
cme S
D /BG
* - not yet in use, but under development
Radisys M
RF
22/04/202317 © Nokia 2014 - File Name - Version - Creator - DocIDConfidential
Planning FlowProject phases overview
Presales Planning Staging
On-site Installatio
nAcceptanc
e
*Product dependant phase
NPO ServicesProject assigned planner
Support
Planning &
Design
Support Supp
ort
Supp
ort
22/04/202318 © Nokia 2014 - File Name - Version - Creator - DocIDConfidential
Planning FlowPresales phase
Presales
NPO Services
Project assigned planner /
GSD / GS NPO Global
Support
Support can be offered to local Customer Teams (CT) during Presales phase to ensure a correct product dimensioning and quotation of NPO Services related efforts, as well as awareness of integration requirements. Please note :
Respective SSM and PM are must to join all customer workshops to have a clear picture of project and requirements. Before conducting a customer workshop, an internal workshop is a must.
NPO Services DO NOT typically include Network Dimensioning, which is under the responsibility of CSSC. Planners, however, should be enabled on IMS Dimensioning Tool to be able to support with re-dimensioning, if needed, during the planning phase.
NPO Services DO NOT include Feature Parity (assessment of features compared to swapped products), which falls under the responsibility of SSM (local CT)
NPO Services DO NOT include Feature Planning, including parameter matching (translating feature parameters from swapped products), which reflects in the Common Configuration section of TPD, and which is in the responsibility of the Solution Architect (local CT)
22/04/202319 © Nokia 2014 - File Name - Version - Creator - DocIDConfidential
Planning FlowPlanning phase
Planning
NPO Services
Project assigned planner
Planning & Design
INPUTS: Bill of Quantity/Materials (BoQ/BoM) Network overview (if available) Product related Planning & Design Guidance materials (from GS NPO) Product’s Standard Configuration Guide (from Product Line) Customer WS outputs
OUTPUTS : Finalized Customer Information Questionnaire – CIQ Documentation IT Net Planning – DNP Technical Project Data –TPD /Databuild
TOOLS : SECANT, the official IP Planning tool of NSN will be used in the Planning phase to produce the DNP document and fill the TPD databuildIMS Load Tool, if required, for re-dimensioning purposes
CIQ
AssessmentLow
Level Design
Solution Design
Workshop
High Level
DesignDataBuild
NOMINAL DESIGN DETAILED DESIGN
22/04/202320 © Nokia 2014 - File Name - Version - Creator - DocIDConfidential
Planning FlowPlanning phase details
NPO Services
Project assigned planner
Planning & Design
Customer WS is recommended as a sign-off agreement point on the High Level Design, which will constitute the base for Low Level Design proceedings
At High Level Design stage, outputs will be the corresponding parts of DNP (and CIQ for justification)
At the end of the planning phase, the complete DNP and TPD (or databuild) should be ready and available for staging and/or on-site installation that follows. DNP and node TPD (Databuild) will be produced by the project planner based on the inputs and by means of the SECANT Tool * and appropriate TPD templates
CIQ is a living document, produced at the start of the planning phase based on available inputs and solution blueprints, which will remain in place after planning phase has ended as a reference and justification for the design decisions made.
* SECANT currently supports generation of DNP network parameter chapters and is planned to fully support DNP generation by end of 2013
Planning
CIQ
AssessmentLow
Level Design
Solution Design
Workshop
High Level
DesignDataBuild
NOMINAL DESIGN DETAILED DESIGN
22/04/202321 © Nokia 2014 - File Name - Version - Creator - DocIDConfidential
Planning FlowStaging phase
Staging
NPO Services
Project assigned planner
Support
Staging phase represents the factory verification and pre-installation of project equipments in the Staging Center, for having the product shipped to site as ready pre-configured Staging phase is product dependant – not all IMS products require staging Staging requires network setup configuration information - the DNP, EPF and TPD. Staging requires a time slot to be reserved for the project in the Staging Center. This is done right after presales phase and constitutes the deadline for planning & design activities Throughout the time that staging takes place, the planner should be able to support staging colleagues for any queries regarding network setup and parameters. Planner should update his planning documents (DNP) with any feedback received from staging colleagues, to ensure planning document’s accuracy.Staging is an optional step in the delivery process for IMS networks. There is also option available for getting the hardware raw, directly at customer location.
feedback
22/04/202322 © Nokia 2014 - File Name - Version - Creator - DocIDConfidential
Planning FlowOn-site Installation and Acceptance phases
On-siteInstallatio
n
NPO Services
Project assigned planner
Support
feedback
Planner should be available locally/remotely throughout the on-site installation and acceptance phases to support on-site colleagues on queries regarding the network design and parameters.
Acceptance
feed
back
Planner should incorporate all feedback received from on-site colleagues into the project’s planning documentation, to ensure a perfect match between the actual configuration and the planning reference documentation.
22/04/202323 © Nokia 2014 - File Name - Version - Creator - DocIDConfidential
Planning FlowPlanning process overview
Presales Planning & Design Staging On-siteInstallation Acceptance
*Productdependant
phase
Proj
ect
Flow
Inpu
ts /
Out
puts
Plan
ning
Act
iviti
esPl
anni
ngTo
ols
BoQ NetworkOverview
SolutionStandard DNP [EPF] Node TPD Updated
DNP / [EPF]
Updated DNP / [EPF]
FINALDNP / [EPF]
Support Assess. HLD CWS LLD
Data
Build
Support
Support
Support
NOMINAL DESIGN DETAILED DESIGN
BoQ – Bill of QuantityAssess. – Network AssessmentHLD – High Level DesignLLD – Low Level DesignIMS Load
ToolCIQ*
* CIQ is described in the diagram as a “tool” that supports planning activities, although it can also be viewed as a input/output document throughout the planning phase.[xxx]: EPF belongs to GS NI. - Non NPO activities
CWS – Customer WorkshopDNP – Documentation IT Net PlanningEPF – Engineering Planning FolderTPD – Technical Project Data
22/04/202324 © Nokia 2014 - File Name - Version - Creator - DocIDConfidential
High Level Design
Customer Information Questionnaire(customer provided network information and
parameters)
Planning FlowPlanning process – Nominal Design workflow
Planning & Design – Nominal Design
IMS Load Tool
INPUTS OUTPUTS
Bill of Quantity(Bill of Materials)
Existing Network Overview
from CT :
from CT / Customer :
Customer
Standard Configuration
Guide
from Product Line:
Product related Planning Guidance
from GS NPO :
DNP HLD Part( Requirements for
IT network planning
& Network Topology) EPF HLD Part
( Materials List & System
Engineering Requirements ) NOMINAL DESIGN
Deployment related Business & Network KPIs
Assessment
HLDAgreement ?
(sign-off)
CustomerWorkshop
Yes Re-dimensioningrequired ?
No
1 2
3
Major planning steps
NI ?
YesN
o
Detailed Design phase
4 5
Star
t c
reat
ion
22/04/202325 © Nokia 2014 - File Name - Version - Creator - DocIDConfidential
Customer Information Questionnaire(customer provided network information and
parameters)
Planning FlowPlanning process – Detailed Design workflow
Planning & Design – Detailed DesignINPUTS OUTPUTS
from Nominal Design :
Customer
Standard Configuration
Guide
from Product Line:
TPD Template or Framework
Product related Planning Guidance
from GS NPO :
DETAILED DESIGN
Complete DNP( all chapters and
annexes)
Complete EPF( all chapters and
annexes)
Node TPD ( NPO
contribution)
Major planning steps
HLDAgreement ?
(sign-off)CustomerWorkshop
3Yes Low Level Design
NI ?
Staging
On-siteInstallation
Databuild Creation
4
5
CustomerAgreement ?
Yes
No
High Level Design
part
22/04/202326 © Nokia 2014 - File Name - Version - Creator - DocIDConfidential
Is advisable to manually check the SECANT generated DNP output for any format and content errors.
SECANT projects are saved on SECANT server, allowing re-using and sharing for knowledge improvement purposes.
Please help in improving our support and feedback any issues or inconsistencies to SECANT Team and/or GS NPO.
DNP is the official customer documentation for network planning & design and the only planning document to be delivered to our end customer. DNP should be delivered in a PDF format which is protected against editing.
Source Word/Excel files generated by SECANT can be delivered to local CT upon request, after ensuring those won’t be shared with the customer in order to preserve our accuracy of the network view as well as offering the possibility of additional business in the planning and design area in case of later expansions/migrations.
If project specific aspects render the SECANT output to unsatisfactory coverage of your planning needs, is advisable to use the SECANT generated DNP output as base and enlist Product Line and GS NPO support to guide you for manual DNP adjustment and completion.
Additional pointsPlanning Flow
22/04/202327 © Nokia 2014 - File Name - Version - Creator - DocIDConfidential
SECANT Tool Homepage (where you can sign-up for a SECANT account and access SECANT enabling materials)
IMS Load Tool (where you can request for tool access and find enabling materials and tool related support)
CIQ Template for IMS
TPD Homepage
GS NPO CEUS Core Community – IMS Area (where you can find a searchable list of all GS NPO Guidance and Enabling materials related to IMS Portfolio products)
GS NPO CEUS Core Community – IMS Forum (dedicated forum for all queries related to NPO Services for IMS Products)
GS NPO CEUS IMS area - IMS Design (storage area for all our materials : Service Description, Marketing materials, Working cards, References, Guidance and Enabling materials)
VIPT Open Core Community - IMS area (latest features and roadmap information related to IMS portfolio products)
Additional references