NPH Evaluation Specific Methodology & Lessons Learned Natural Phenomena Hazards (NPH) Evaluation at...
-
Upload
howard-jordan -
Category
Documents
-
view
214 -
download
0
Transcript of NPH Evaluation Specific Methodology & Lessons Learned Natural Phenomena Hazards (NPH) Evaluation at...
NPH Evaluation Specific Methodology & Lessons Learned
Natural Phenomena Hazards (NPH) Evaluation at Argonne National Laboratory
Establishing a Specific Methodology and Lessons Learned
Betsy Grom, Argonne National Laboratory
Alex Smith, Nexus Technical Services Corp.
NPH Evaluation Specific Methodology & Lessons Learned
I. Introduction
II. Background
III. Establishing a Specific Methodology
IV. Lessons Learned
V. Questions
NPH Evaluation Specific Methodology & Lessons Learned
Introduction
• Why is this important?– Seismically Induced Fires
I. Introduction
II. Background
III. Specific Methodology
IV. Lessons Learned
V. Questions
NPH Evaluation Specific Methodology & Lessons Learned
Introduction
• Why is this important?– Rescue Operations
I. Introduction
II. Background
III. Specific Methodology
IV. Lessons Learned
V. Questions
Photo Courtesy of USGS
NPH Evaluation Specific Methodology & Lessons Learned
Introduction
• Why is this important?– Mitigation of Hazardous Material
Release– Required by DOE Order 420.1B,
Facility Safety
I. Introduction
II. Background
III. Specific Methodology
IV. Lessons Learned
V. Questions
NPH Evaluation Specific Methodology & Lessons Learned
Introduction
• Why is this important?– Ensure confinement of hazardous
materials– Protection of facility workers and public– Continued operation of essential
facilities– Protection of government property
I. Introduction
II. Background
III. Specific Methodology
IV. Lessons Learned
V. Questions
NPH Evaluation Specific Methodology & Lessons Learned
Introduction
• Why is this important?– Argonne is susceptible to NPH Events
I. Introduction
II. Background
III. Specific Methodology
IV. Lessons Learned
V. Questions
NPH Evaluation Specific Methodology & Lessons Learned
IntroductionI. Introduction
II. Background
III. Specific Methodology
IV. Lessons Learned
V. Questions
Photo Courtesy of Argonne
NPH Evaluation Specific Methodology & Lessons Learned
IntroductionI. Introduction
II. Background
III. Specific Methodology
IV. Lessons Learned
V. Questions
Photo Courtesy of Argonne
NPH Evaluation Specific Methodology & Lessons Learned
IntroductionI. Introduction
II. Background
III. Specific Methodology
IV. Lessons Learned
V. Questions
Photo Courtesy of Argonne
NPH Evaluation Specific Methodology & Lessons Learned
Introduction
• NPH Evaluations are required for all Structures, Systems, and Components (SSCs)– Evaluation uses a graded approach. – Vital SSCs require a more rigorous
evaluation.
I. Introduction
II. Background
III. Specific Methodology
IV. Lessons Learned
V. Questions
NPH Evaluation Specific Methodology & Lessons Learned
Project Description
• NPH Gap Analysis
• Development or update of Site Specific Design Basis Events
• Development of a Design Criteria Document
• NPH evaluation of Argonne’s hazard-category nuclear facilities
I. Introduction
II. Background
III. Specific Methodology
IV. Lessons Learned
V. Questions
NPH Evaluation Specific Methodology & Lessons Learned
Performance Categories
• Structures, Systems, and Components (SSCs)
• Hazard Category (HC)– HC-1 (Reactor), HC-2 (Lots of
Material), HC-3 (Moderate Material)
• Performance Category (PC)– PC-0, PC-1, PC-2, PC-3, PC-4 (Most
Important)
I. Introduction
II. Background
III. Specific Methodology
IV. Lessons Learned
V. Questions
NPH Evaluation Specific Methodology & Lessons Learned
Performance Categories, DOE-STD-1021-93 Change Notice 1I. Introduction
II. Background
III. Specific Methodology
IV. Lessons Learned
V. Questions
NPH Evaluation Specific Methodology & Lessons Learned
Performance Categories
• Argonne Methodology– Survey Safety Basis Documents– Review System Drawings– Verify Field Conditions– Assign Preliminary Performance
Categories– Evaluate SSCs– Prepare Final PC List
I. Introduction
II. Background
III. Specific Methodology
IV. Lessons Learned
V. Questions
NPH Evaluation Specific Methodology & Lessons Learned
Performance CategoriesI. Introduction
II. Background
III. Specific Methodology
IV. Lessons Learned
V. Questions
Structures, Systems
Systems, Components
Structures, Systems,
Components
Chemical Hazards
Programmatic Equipment
Identify and Field Verify
Assign Performance Category According to
DOE-STD-1021
DSA
SDDs
1995 NPH SSC Questionaire
FIMS
Chemical Management System
Support Systems
NPH Evaluation Specific Methodology & Lessons Learned
Summary of Wind/Tornado Design and Evaluation CriteriaI. Introduction
II. Background
III. Specific Methodology
IV. Lessons Learned
V. Questions
Performance Category 1 2 3 4
Wind
Hazard Annual Probability of Exceedance
2 x 10-2 1 x 10-2 1 x 10-3 1 x 10-4
Importance Factor 1.0 1.0 1.0 1.0
Wind Speed (mph) 90 96 Tornado Governing Tornado Governing
Missile Criteria NA NA Tornado Governing Tornado Governing
Tornado
Hazard Annual Probability of Exceedance
NA NA 2 x 10-5
(4 x 10-5) (3)
2 x 10-6
(4 x 10-6) (3)
Importance Factor NA NA 1.0 1.0
Tornado Speed (mph) NA NA 248(224) (3)
310(292) (3)
Missile Criteria NA NA 2x4 timber plank 15 lb @150 mph (horiz.), max. height 200 ft.; 100 mph (vert.) 3 in. dia. std. steel pipe, 75 lb @ 75 mph (horiz.); max. height 100 ft, 50 mph (vert.)
3,000 lb automobile @25 mph, rolls and tumbles
2x4 timber plank 15 lb @150 mph (horiz.), max. height 200 ft.; 100 mph (vert.) 3 in. dia. std. steel pipe, 75 lb @ 75 mph (horiz.); max. height 100 ft, 50 mph (vert.)3,000 lb automobile @25 mph, rolls and tumbles
APC NA NA 125 psf @ 50 psf/sec 125 psf @ 50 psf/sec
NPH Evaluation Specific Methodology & Lessons Learned
PC-3 and PC-4 Wind Driven Missiles
• 2x4 timber plank, 15 lb weight, traveling at 150 mph
I. Introduction
II. Background
III. Specific Methodology
IV. Lessons Learned
V. Questions
Photo Courtesy of KSHB, Kansas City, MO
NPH Evaluation Specific Methodology & Lessons Learned
PC-3 and PC-4 Wind Driven Missiles
• 3 in diameter standard steel pipe, 75 lb weight, traveling at 75 mph
I. Introduction
II. Background
III. Specific Methodology
IV. Lessons Learned
V. Questions
NPH Evaluation Specific Methodology & Lessons Learned
PC-3 and PC-4 Wind Driven Missiles
• 3,000 lb automobile traveling at 25 mph, rolling and tumbling
I. Introduction
II. Background
III. Specific Methodology
IV. Lessons Learned
V. Questions
Photo Courtesy of WDBR-FM, Springfield, IL
NPH Evaluation Specific Methodology & Lessons Learned
PC-3 and PC-4 Wind Driven MissilesI. Introduction
II. Background
III. Specific Methodology
IV. Lessons Learned
V. Questions
Missile Criteria Acceptable Missile Barrier
Horizontal Component: 2x4 timber plank, 15 lb @ 150 mph, max. height 200 ft above ground
• 6 in. concrete slab with #4 rebar @ 6 in. on center, each way in middle of slab
• 8 in. concrete masonry unit (CMU) wall with one #4 rebar grouted in each vertical cell and horizontal trussed joint reinforced @ 16 in. on center
Vertical Component: 2x4 timber plank 15 lb @100 mph
• 4 in. concrete slab with #3 rebar @ 6 in . on center each way in middle of slab
Horizontal Component: 3 in. diameter steel pipe 75 lb @ 75 mph max. height 100 ft above ground
• 10 in. concrete slab with #4 rebar @ 12 in . on center each way place 1.5 in. from each face
Vertical Component: 3 in. diameter steel pipe 75 lb @ 50 mph
8 in. concrete slab with #4 rebar @ 8 in . on center each way placed 1.5 in. from inside face
NPH Evaluation Specific Methodology & Lessons Learned
PC-3 and PC-4 Wind Driven Missiles
• Many walls at Argonne are unreinforced CMU walls
I. Introduction
II. Background
III. Specific Methodology
IV. Lessons Learned
V. Questions
Photo Courtesy of WDBR-FM, Springfield, IL
NPH Evaluation Specific Methodology & Lessons Learned
Seismic LoadsI. Introduction
II. Background
III. Specific Methodology
IV. Lessons Learned
V. Questions
Performance Category (PC)
1 2 3 4
Hazard Exceedance Probability, PH
4x10-4
(8x10-4)4x10-4
(8x10-4)4x10-4
(8x10-4)1x10-4
(2x10-4)
Response Spectra 2/3 MCE ground motion (1,3) Site-specific Response Spectra
Damping for Structural Evaluation
5% Damping Values TableJNPH-101-Q-T003
Acceptable Analysis Approaches for
Structures
Static or dynamic force method as described in IBC 2000
Dynamic analysis
Analysis approaches for systems and components
IBC Force equation for equipment and non-structural elements (or
more rigorous approach)
Dynamic analysis using in-structure response spectra (Damping Values
Table JNPH-101-Q-T003)
Seismic Use group I III NA
Importance Factor 1 1.5 NA
Load Factors Code specified load factors 1.0
Scale Factors (SF) NA 0.9 1.25
Inelastic Energy Absorption Ratios For Structures
R in IBC 2000 Inelastic Energy Absorption Factors, Fμ Table, JNPH-101-Q-T003
Material Strength Minimum specified or 95% non-exceedance in-situ values
NPH Evaluation Specific Methodology & Lessons Learned
Seismic Loads
• Seismic Interaction– URM Interaction
I. Introduction
II. Background
III. Specific Methodology
IV. Lessons Learned
V. Questions
Photos Courtesy of USGS
NPH Evaluation Specific Methodology & Lessons Learned
Seismic Loads
• Seismic Interaction– System interaction– Sprinkler pipe falling and breaking a
hot cell containment window– System was not designed to be
operable following event.
I. Introduction
II. Background
III. Specific Methodology
IV. Lessons Learned
V. Questions
NPH Evaluation Specific Methodology & Lessons Learned
Seismic LoadsI. Introduction
II. Background
III. Specific Methodology
IV. Lessons Learned
V. Questions
Lateral Brace Longitudinal Brace
NPH Evaluation Specific Methodology & Lessons Learned
SSC Evaluations
• System Evaluation Work Sheet (SEWS)
• Walk-down assessment follows the methodology established by the Seismic Qualification Users Group (SQUG), which is the basis of the DOE-GIP (EH-0545)
I. Introduction
II. Background
III. Specific Methodology
IV. Lessons Learned
V. Questions
NPH Evaluation Specific Methodology & Lessons Learned
SSC EvaluationsI. Introduction
II. Background
III. Specific Methodology
IV. Lessons Learned
V. Questions
NPH Evaluation Specific Methodology & Lessons Learned
SSC EvaluationsI. Introduction
II. Background
III. Specific Methodology
IV. Lessons Learned
V. Questions
NPH Evaluation Specific Methodology & Lessons Learned
SSC EvaluationsI. Introduction
II. Background
III. Specific Methodology
IV. Lessons Learned
V. Questions
NPH Evaluation Specific Methodology & Lessons Learned
SSC EvaluationsI. Introduction
II. Background
III. Specific Methodology
IV. Lessons Learned
V. Questions
NPH Evaluation Specific Methodology & Lessons Learned
Results
• Provides quantitative input for future safety basis development.
• NPH mitigation deficiencies identified. Planning for upgrades can be prioritized:– Safety significance of upgrades– Time or funding constraints– Mission requirements
• Forms basis for future development of post-event procedures in facilities.
I. Introduction
II. Background
III. Specific Methodology
IV. Lessons Learned
V. Questions
NPH Evaluation Specific Methodology & Lessons Learned
Lessons Learned
• Employing the use of a specific methodology minimizes interpretations of requirements.
• Ensures consistency of individual analyses.
I. Introduction
II. Background
III. Specific Methodology
IV. Lessons Learned
V. Questions
NPH Evaluation Specific Methodology & Lessons Learned
I. Introduction
II. Background
III. Specific Methodology
IV. Lessons Learned
V. Questions
Questions