NORTHSIDE INDEPENDENT SCHOOL DISTRICT...NISD Project Manager – Richard De La Cruz, P.E. Contractor...
Transcript of NORTHSIDE INDEPENDENT SCHOOL DISTRICT...NISD Project Manager – Richard De La Cruz, P.E. Contractor...
NNOORRTTHHSSIIDDEE IINNDDEEPPEENNDDEENNTT SSCCHHOOOOLL DDIISSTTRRIICCTT
Engineering Services
Leroy San Miguel ASSIST. SUPERINTENDENT FOR FACILITIES & OPERATIONS
Ceasar Ponce, A.I.A. EXECUTIVE DIRECTOR CONSTRUCTION & ENGINEERING
Richard De La Cruz, P.E. ASSISTANT DIRECTOR OF ENGINEERING
July 2013
FIRE ALARM SYSTEMS REPLACEMENT JERRY D. ALLEN ELEMENTARY SCHOOL AND SUL ROSS MIDDLE SCHOOL
Engineer – CNG Engineering NISD Project Manager – A.J. Halbardier Contractor – Consolidated Electric Service, Inc. Construction Cost - $258,000.00 Construction Period – May 31, 2013 – August 16, 2013 Project Scope – Replace existing fire alarm system. 10% Complete
JERRY D. ALLEN ELEMENTARY SCHOOL AND SUL ROSS MIDDLE SCHOOL
EXISTING PANELS
GLENOAKS ELEMENTARY SCHOOL & JACK C. JORDAN MIDDLE SCHOOL
Engineer – Alderson & Associates, Inc. NISD Project Manager – A.J. Halbardier Contractor – Consolidated Electric Service, Inc. Construction Cost - $239,000.00 Construction Period – May 31, 2013 – August 16, 2013 Project Scope – Replace existing fire alarm system. 10% Complete
GLENOAKS ELEMENTARY SCHOOL
EXISTING PANEL
ROBERT F. McDERMOTT ELEMENTARY SCHOOL AND HOLMGREEN CENTER
Engineer – CNG Engineering NISD Project Manager – A.J. Halbardier Contractor – TBD Construction Cost - $150,000.00 Construction Period – August 19, 2013 – November 22, 2013 Project Scope – Replace existing fire alarm system. 100% Design- Not yet in construction- July Board Approval.
F.R. SCOBEE ELEMENTARY SCHOOL AND STINSON MIDDLE SCHOOL
Construction Period – August 19, 2013 – November 22, 2013
100% Design- Not yet in construction. July board approval.
Project Scope – Replace existing fire alarm system.
NISD Project Manager – A.J. Halbardier Engineer – Alderson & Associates
Construction Cost - $250,000.00 Contractor – TBD
HVAC UPGRADES KNOWLTON ELEMENTARY SCHOOL
Engineer – Wallis Engineering Group NISD Project Manager – Alfred Vitela III, P.E. Contractor – International Mechanical Services, Inc. Construction Cost - $1,145,000.00 Construction Period – June 12, 2013 – August 9, 2013 Project Scope – Chiller replacement and HVAC upgrade. 15% Complete
KNOWLTON ELEMENTARY SCHOOL
CHILLER YARD
ZACHRY MIDDLE SCHOOL
Engineer – Cleary Zimmermann Engineers NISD Project Manager – Alfred Vitella III, P.E. Contractor – Gillette Air Conditioning Co., Inc. Construction Cost - $1,070,000.00 Construction Period – June 10, 2013 – August 9, 2013 Project Scope – Chiller replacement and HVAC upgrade. 15% Complete
ZACHRY MIDDLE SCHOOL
BOILER REPLACEMENTS DISTRICT WIDE-CLARK HS, HOLMES HS, JONES MS, SUL ROSS MS, COKE STEVENSON MS, BRAUCHLE ES AND GALM ES
Engineer – MS2 Consulting Engineers NISD Project Manager – Alfred Vitela III, P.E. Contractor – International Mechanical Services, Inc. Construction Cost - $758,425.00 Construction Period – June 2012 – August 2013 Project Scope – Replace end-of-life domestic Boilers. 75% Complete – Schools completed: Brauchle Elementary, Galm Elementary, Holmes High School, and Clark High School.
Schools Remaining: Stevenson Middle School, Sul Ross Middle School and Jones Middle School
LIGHTING UPGRADES RAYBURN MIDDLE SCHOOL AND NORTHSIDE LEARNING CENTER
Engineer – Alderson & Associates, Inc. NISD Project Manager – Ramiro Guerrero Contractor – Consolidated Electric Service, Inc. Construction Cost - $45,000.00 Construction Period – June 10, 2013 – August 20, 2013 Project Scope – Lighting Retro-fit 75% Complete
RAYBURN MIDDLE SCHOOL AND NORTHSIDE LEARNING CENTER
MAIN GYM
JERRY ALLEN ELEMENTARY, SUL ROSS AND PAT NEFF MIDDLE SCHOOL
Engineer – CNG Engineering NISD Project Manager – Ramiro Guerrero Contractor – Excel Energy Group, Inc. Construction Cost - $122,433.97 Construction Period – June 10, 2013 – August 20, 2013 Project Scope – Lighting Retro-fit 10% Complete
JERRY ALLEN ELEMENTARY
F.R. SCOBEE ELEMENTARY SCHOOL AND JOHN MARSHALL HIGH SCHOOL
Engineer – Alderson & Associates, Inc. NISD Project Manager – Ramiro Guerrero Contractor – Consolidated Electric Service, Inc. Construction Cost - $78,000.00 Construction Period – May 20, 2013 – August 9, 2013 Project Scope – Lighting Retro-fit 50% Complete
JOHN MARSHALL HIGH SCHOOL
GIRLS PRACTICE GYM – 90% COMPLETE
OAK HILLS TERRACE ELEMENTARY SCHOOL
Engineer – Alderson & Associates, Inc. NISD Project Manager – Ramiro Guerrero Contractor – Quinney Electric, Inc. Construction Cost - $51,300.00 Construction Period – June 3, 2013 – August 20, 2013 Project Scope – Lighting Retro-fit 10% Complete
COKE R. STEVENSON MIDDLE SCHOOL & HENRY T. BRAUCHLE ELEMENTARY
Engineer – CNG Engineering NISD Project Manager – Ramiro Guerrero Contractor – Consolidated Electric Service, Inc. Construction Cost - $108,000.00 Construction Period – June 10, 2013 – August 20, 2013 Project Scope – Lighting Retro-fit 10% Complete
HELOTES ELEMENTARY SCHOOL AND LEON VALLEY ELEMENTARY SCHOOL
Engineer – Alderson & Associates, Inc. NISD Project Manager – Ramiro Guerrero Contractor – Excel Energy Group, Inc. Construction Cost - $105,541.34 Construction Period – May 20, 2013 – August 9, 2013 Project Scope – Lighting Retro-fit 10% Complete
EDUARDO VILLARREAL ELEMENTARY SCHOOL
Construction Period – June 3, 2013 – August 20, 2013
Contractor – Consolidated Electric Service, Inc. NISD Project Manager – Ramiro Guerrero Engineer – Alderson & Associates, Inc.
Project Scope – Lighting Retro-fit
Construction Cost - $140,000.00
10% Complete
PAVING/ PARKING / DRAINAGE HENRY T. BRAUCHLE ELEMENTARY SCHOOL
Engineer – Bury & Partners-SA, Inc. NISD Project Manager – Richard De La Cruz, P.E. Contractor – R.L. Rohde General Contracting, Inc. Construction Cost - $57,500.00 Construction Period – June 8, 2013 – August 9, 2013 Project Scope – Drainage project 25% Complete
HENRY T. BRAUCHLE ELEMENTARY SCHOOL
MURRAY E. BOONE ELEMENTARY SCHOOL
Engineer – Moy Tarin Ramirez Engineers, LLC NISD Project Manager – Mike Boehmer Contractor – D&D Contractors, Inc. Construction Cost - $289,064.48 Construction Period – June 10, 2013 – August 9, 2013 Project Scope – Paving Improvements 20% Complete
MURRAY E. BOONE ELEMENTARY SCHOOL
ED CODY ELEMENTARY SCHOOL
Engineer – Moy Tarin Ramirez Engineers, LLC NISD Project Manager – Mike Boehmer Contractor – R.L. Rhode General Contracting, Inc. Construction Cost - $156,000.00 Construction Period – June 10, 2013 – August 9, 2013 Project Scope – Paving project 95% Complete
ED CODY ELEMENTARY SCHOOL
BEFORE AFTER
HEALTH CAREERS HIGH SCHOOL
Engineer – Cude Engineers NISD Project Manager – Richard De La Cruz, P.E. Contractor – Alamo City Constructors, Inc. Construction Cost - $162,000.00 Construction Period – June 8, 2013 – August 9, 2013 Project Scope – Paving front parking lot. 40% Complete
HEALTH CAREERS HIGH SCHOOL
SIDE PARKING LOT @ EWING HALSELL FRONT PARKING LOT @ HAMILTON WOLFE
DR. MARTHA MEAD ELEMENTARY SCHOOL
Engineer – Bury + Partners-SA, Inc. NISD Project Manager – Richard De La Cruz, P.E. Contractor – Industrial Construction Co. Construction Cost - $33,428.00 Construction Period – June 8, 2013 – August 9, 2013 Project Scope –Drainage project 60% Complete
DR. MARTHA MEAD ELEMENTARY SCHOOL
RETAINING WALL @ BUS LOOP
WILLIAM H. TAFT HIGH SCHOOL
Engineer – Cude Engineers NISD Project Manager – Richard De La Cruz, P.E. Contractor – D. Plata Construction Co., LLC Construction Cost - $87,844.72 Construction Period – June 8, 2013 – August 9, 2013 Project Scope –Paving front parking lot. 35% Complete
WILLIAM H. TAFT HIGH SCHOOL
FRONT PARKING LOT
SANDRA DAY O’CONNOR HIGH SCHOOL
Engineer – Cude Engineers NISD Project Manager – Ramiro Guerrero Contractor – Yantis Construction Co. Construction Cost - $59,700.00 Construction Period – July 2013- August 2013 Project Scope – Paving project. 0% Construction
SANDRA DAY O’CONNOR HIGH SCHOOL
PLAYGROUND UPGRADES BRAUN STATION ELEMENTARY SCHOOL
Engineer – Moy Tarin Ramirez Engineers, LLC NISD Project Manager – Mike Boehmer Contractor – R.L. Rohde General Contracting, Inc. Construction Cost - $203,000.00 Construction Period – July 1, 2013 – August 16, 2013 Project Scope –Upgrade playground equipment, install new wood fiber surfacing and ADA accessibility upgrades in upper level playgrounds.
40% Complete
DISTRICT-WIDE UPPER-LEVEL PLAYGROUNDS GROUP 4: (GALM, LEWIS, PASSMORE AND COON ELEMENTARY SCHOOLS)
Engineer – Moy Tarin Ramirez Engineers, LLC NISD Project Manager – Mike Boehmer Contractor – R.L. Rohde General Contracting, Inc. Construction Cost - $623,000.00 Construction Period – May 1, 2013 – August 16, 2013 Project Scope –Upgrade playground equipment, install new wood fiber surfacing and ADA accessibility upgrades in upper level playgrounds.
65% Complete
DISTRICT-WIDE UPPER-LEVEL PLAYGROUNDS GROUP 5: (CARSON, GLASS, NORTHWEST CROSSING AND VILLARREAL ELEMENTARY SCHOOLS)
Engineer – Moy Tarin Ramirez Engineers, LLC NISD Project Manager – Mike Boehmer Contractor – R.L. Rohde General Contracting, Inc. Construction Cost - $639,200.00 Construction Period – May 1, 2013 – August 16, 2013 Project Scope –Upgrade playground equipment, install new wood fiber surfacing and ADA accessibility upgrades in upper level playgrounds.
50% Complete
DISTRICT-WIDE UPPER-LEVEL PLAYGROUNDS GROUP 6: (COLONIES NORTH, GLEN OAKS, LEON SPRINGS AND McDERMOT ELEMENTARY SCHOOLS)
Engineer – Moy Tarin Ramirez Engineers, LLC NISD Project Manager – Mike Boehmer Contractor – R.L. Rohde General Contracting, Inc. Construction Cost - $499,979.16 Construction Period – May 1, 2013 – August 16, 2013 Project Scope –Upgrade playground equipment, install new wood fiber surfacing and ADA accessibility upgrades in upper level playgrounds.
40% Complete
PLAYGROUND UPGRADES
VILLARREAL ELEMENTARY
PLAYGROUND UPGRADES
FLASHERS 2013 DR. SARA B. McANDREW ELEMENTARY SCHOOL
Engineer – Civil Engineering Consultants NISD Project Manager – Richard De La Cruz, P.E. Contractor – Saeco Electric & Utility Construction Cost - $24,999.00 Construction Period – May 7, 2013 – August 9, 2013 Project Scope – Install school flashers 5% Complete
DR. FOLKS MIDDLE SCHOOL AND KAY FRANKLIN ELEMENTARY SCHOOL
Construction Period – May 7, 2013 – August 9, 2013
NISD Project Manager – Richard De La Cruz, P.E. Engineer – Cude Engineering Consultants
Project Scope – Install school flashers
Contractor – The Levy Company, LP Construction Cost - $55,650.00
5% Complete
TENNIS COURTS O’CONNOR HIGH SCHOOL AND PAT NEFF MIDDLE SCHOOL
Engineer – Moy Tarin Ramirez Engineers, LLC NISD Project Manager – Mike Boehmer Contractor – Hellas Construction Construction Cost - $77,600.00 Construction Period – June 11, 2013 – August 9, 2013 Project Scope – Resurface Tennis Courts 50% Complete
PAT NEFF MIDDLE SCHOOL
BEFORE AFTER