Northern Sacramento Valley Conjunctive Water Management Investigation Public Workshop December 8,...
-
Upload
ashton-beans -
Category
Documents
-
view
220 -
download
0
Transcript of Northern Sacramento Valley Conjunctive Water Management Investigation Public Workshop December 8,...
Northern Sacramento Valley Conjunctive Water Management
Investigation
Public Workshop
December 8, 2010
The Glenn-Colusa Irrigation District and
The Natural Heritage Institute
12/8/2010 1
Workshop Objective & Process
• Objective– Respond to questions from October 21, 2010
workshop 1
• Process– Organized questions into topics– Describe each topic– Provide response– Engage in discussion
12/8/2010 2
How Does The Proposed Project Work?
4
Re-operate Surface Reservoirs with Groundwater “Backstop”
• Reservoir re-operation – Additional releases to meet program objectives
(North of Delta water supply and environmental enhancement)– Expect reservoir refill from surplus surface flows– Honor existing CVP and SWP delivery obligations and
operations constraints
• Groundwater operation– Pump groundwater to “repay” reservoirs if storage conditions put
contract deliveries or temperature control at risk– Groundwater used in lieu of surface entitlements that then
remain in storage– Minimize or avoid GW impacts
12/8/2010
10
Spring(no inflow)
Summer(no inflow)
Fall-Winter(inflow)
Spring(no inflow)
8
Project ReservoirOperation
BaselineReservoirOperation
Re-Operation Case 1- Reservoir Refills
Reservoir Full
100
Deliveries = 50
Target Carryover = 50
50
Reservoir Full
100
Reservoir Full
100
FloodRelease = 20
Inflow = 70
100
Inflow = 70
FloodRelease = 10
100 100
Reservoir Full
Target Carryover = 40
Deliveries = 60
40
10Project ReservoirOperation
BaselineReservoirOperation
Re-operation Case 2- Reservoir Does Not Refill
Reservoir Full
100
Reservoir Full
100
Deliveries = 50
Target Carryover = 50
50
Reservoir Partially Full
80
Target Carryover = 40
Deliveries = 40
40
Target Carryover = 40
Deliveries = 60
40
Target Carryover = 40
Deliveries = 30
40
Reservoir Partially Full
70
Spring(no inflow)
Summer(no inflow)
Fall-Winter(inflow)
Spring(no inflow)
Summer(no inflow)
Inflow = 30
Flood Release = 0
70
Inflow = 30
Flood Release = 0
80
GW
Groundwater = 1040
Project Performance SummaryProject Scenario 2 Evaluated with Revised Model Including Biological
Opinions, Forecast-based Operation and Minimum Reservoir Release Criteria
12/8/2010 7
Performance MetricSac R
(Shasta)Feather R (Oroville)
Total number of years in simulation (1922-2003) 82 82
Number of years no project releases made 62 45
Number of years project releases made 20 37
Average annual (82 years) project release, (TAF)(Roughly 2/3 environmental and 1/3 ag benefits)
Cumulative benefit over 82 years (TAF) =
25
2,050
30
2,460
Maximum year project release (TAF)(Includes environmental and ag)
180 102
Number of years “payback” pumping is needed 4 11
Average annual (82 years) project pumping (TAF)Cumulative pumping over 82 years (TAF) =
2164
9738
Maximum year project pumping (TAF)(Maximums do not occur in same year)
100 100
Average annual (82 years) reservoir refill from surplus flows (TAF) 23 23
Spillage of payback water 0 -2
Questions How Does The Proposed Project Work?
• Can you do just reservoir re-operation without doing the pumping for repayment?
• Where does the water for environmental enhancements and other project benefits come from?
• How does the payback water get used?
• How do the project benefits compare to the frequency and magnitude of payback?
12/8/2010 8
• How would the reservoir releases be measured?
• How would it be determined that water needs to be repaid…what triggers reservoir payback?
• Which aquifer are we talking about, the deep or shallow?
• Does the study address the total groundwater picture?
Questions, continued
How Does The Proposed Project Work?
12/8/2010 9
• What are the existing contractual obligations?
• Public wants assurance that there is adequate thought going into monitoring and mitigation.
Questions, continued
How Does The Proposed Project Work?
12/8/2010 10
Investigation Tools and Data
Overview of Analysis Tools
12/8/2010 12
Ground WaterModel
Other User Input
EnvironmentalObjectives
System OperationWith
Conjunctive Management
Surface WaterModel
CalSim Results
Surface WaterModel
CalSim Results
SW-GW InteractionTarget River Flows
GW PumpingReservoir Ops
Other Assumptions
13
Groundwater Model Area and Grid Density
Sacramento
Orland Unit
GCID
Butte Basin
Willows
12/8/2010
Chico
14
Groundwater Flow Model• Regional scale with high spatial detail
– 5,950 square miles (3.8 million acres)– 88,922 surface nodes– 7 vertical layers
• Aquifer properties based on analysis of more than 1,000 production wells
• Calibration– Static calibration for year 2000– Water levels from 257 monitoring wells
• Monthly time step, 1982 through 2003
12/8/2010
15
Surface Water Operations Model • Spreadsheet-based for ease and speed of
operation• Re-operates Shasta and Oroville Reservoirs
relative to a baseline condition depicted by CalSim II outputs (1922 through 2003)
• Driven by additional target deliveries for:– Environmental restoration in Sac and Feather Rivers– Unmet Sac Valley agricultural demands
• Various operational constraints• Uses generalized SW-GW interaction functions
derived from GW model12/8/2010
QuestionsInvestigation Tools and Data
• Why are critical dry years not used in the analysis?
• What is the time-step used to develop the groundwater model? Is the time-step appropriate for capturing localized effects of day to day well operation and aquifer response?
• Were economic impacts beyond just project costs and benefits considered, such as impacts to specific segments of the agricultural community?
12/8/2010 16
Project Benefits
QuestionsProject Benefits
• What are the project benefits?
• Are there benefits to the groundwater systems and were they considered in the economic analysis?
12/8/2010 18
Project Benefits• Increased Sac Valley surface water supply
– More local benefit (water supply) from CVP and SWP
– Reduced overall reliance on Sac Valley groundwater, though increased local pumping in certain years
• Improved habitat in Sac and Feather Rivers through – Recovery of salmon populations– Ecosystem sustainability
12/8/2010 19
Project Impacts
QuestionsProject Impacts
• What are the impacts of groundwater pumping in the valley on foothill aquifers?
• What are the critical recharge months in the upper reaches? In the area in general?
• Project pumping may be a small share of Valley wide pumping but what proportion is it of pumping within the project area?
12/8/2010 21
22
Typical Sacramento Valley GW Hydrograph (Butte Co.)
12/8/2010
Sacramento Valley Water Uses and Sources by County
Peak Year Project Pumping (100 TAF1) in Relation to Estimated Annual Baseline Pumping
Area
Estimated Baseline
Pumping (TAF)
Project Pumping as % of Area
Baseline
Butte County 411 24%
Glenn and Colusa Counties 635 16%
Butte, Glenn and Colusa Counties
1,046 10%
Northern Sacramento Valley (Butte, Glenn, Colusa, Tehama and Shasta Counties)
1,323 8%
Entire Sacramento Valley(Source: GW model water budgets)
2,500 +/- 4%
12/8/2010 24
1 Peak year project pumping is 100 TAF in the Butte Basin and in GCID but the two not occur in the same year based on the 1922 through 2003 modeling
QuestionsProject Impacts
• Is the interconnection between streams and underlying aquifers sufficiently defined to predict the effects of even modest changes in groundwater levels (e.g., Butte and Big Chico Creeks)?
12/8/2010 25
• What is the extent of the impact on domestic (and other wells)? You show 0 to 6 feet, but you also say that near the wells that are pumping payback water it could be 50 or 60 feet? Even a few feet can have a large impact. This needs to be clarified.
Questions, continued
Project Impacts
12/8/2010 26
Comparison of Drawdown from Modeling and Averaged for Impact Analysis
12/8/2010 27
Potential Impact Zones:Worst Case, New Wells
Regional Aquifer Drawdown in Aug 1990 , Scenario 1, New Well Field
Figure 11-15, p.11-16 from Modeling Report, Feb 2010
Next Steps
• Draft and Final Investigation Report
• Additional public meetings
• Phase 2
12/8/2010 28