Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
NORTH POWER CORPORATION
Electric Network Project Management Board
-------------------------------
ENVIRONMENTAL MANAGEMENT PLAN
(EMP)
SUBPROJECT:
DISTRIBUTION EFFICIENCY PROJECT
YEN THANH 110KV SUBSTATION
PREPARED BY
DPT CONSULTANT JOINT STOCK COMPANY
Hanoi, 20 April 2012
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
ABBREVIATIONS
CPC Commune People’s Committee
DEP Distribution Efficient Project
ECOP Environmental Code of Practice
EIA Environmental Impact Assessment
EMF Electromagnetic Field
EMP Environmental Management Plan
EVN Electricity of Vietnam
GOV Government of Vietnam
HH Household
HV High voltage
LV Low Voltage
MOIT Ministry of Industry and Trade
MONRE Ministry of Natural Resources and Environment
MV Medium Voltage
NGO Northern Grid Company
NPC Northern Power Corporation
OHL Overhead Line
PAH Project Affected Household
PCBs Polychlorinated Biphenyls
PMU Network Project Management Unit (under the NPC)
PPC Provincial People’s Committee
ROW Right of Way
DPT DPT consultant Joint-Stock Company
WB World Bank
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
2
CONTENT
1. INTRODUCTION..............................................................................................................3
2. Policy, Regulations, and Institutional Frameworks........................................................4
2.1. Government Regulations: ................................................................................................4
2.2. World Bank Safeguard Policies .......................................................................................4
3. SUBPROJECT DESCRIPTION ......................................................................................4
3.1. Objectives of the Subproject ...........................................................................................4
3.2. Subproject Location .........................................................................................................5
3.3. Subproject Management Organization ..........................................................................5
3.4. Subproject Components ...................................................................................................5
3.4.1. Electric cable 110kV ......................................................................................................5
3.4.2 110kV substation:............................................................................................................5
3.4.3 Sub expansion 110kV at 220kV Pho Noi substation ....................................................6
3.4.3. Subproject Technical Specifications ..........................................................................11
3.4.5. Khối lượng công việc chính của dự án .......................................................................11
4. ENVIRONMETNAL BACKGROUND .........................................................................15
4.1 Geography .........................................................................................................................15
4.2 Climate, topography, pedology .......................................................................................15
4.2.1. Climate ..........................................................................................................................15
4.2.2 Topography ...................................................................................................................16
4.2.3 Pedology .........................................................................................................................16
4.3 Natural resources .............................................................................................................16
4.3.1 Land ...............................................................................................................................16
4.3.2. Forest .............................................................................................................................16
4.4 Population, culture, society .............................................................................................16
4.5. Transportation ................................................................................................................17
5. SUBPROJECT POTENTIAL IMPACTS .....................................................................18
6. ENVIRONMETNAL MANAGEMENT PLAN ............................................................24
6.1. Mitigation Measures. ......................................................................................................24
Table 6.1. Mitigation measures .............................................................................................24
6.2. Environmental Monitoring Plan ...................................................................................34
Table 6.2: Environmental monitoring plan is shown in the below table ..........................34
7. EMP IMPLEMENTATION ARRANGEMENT AND CAPACITY
BUILDING .......................................................................................................................36
7.1 Responsibilities for Implementing the Environmental Management Plan ...............36
7.1.1 During Detailed Design and Preparation of Bidding Contract Documents ............36
7.1.2 During Construction Phase ..........................................................................................36
Table 7.1. Responsibility for EMP Implementation ..........................................................37
7.2 Capacity Building for EMP Implementation ...............................................................38
Table 7.2 Estimates of capacity building for implementing EMP .....................................38
7.3 Reporting procedure ......................................................................................................39
7.4 Estimated cost for implementing the EMP ..................................................................39
8. PUBLIC CONSULTATION AND DISCLOSURE OF INFORMATION .................41
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
3
1. INTRODUCTION
The subproject: “Yen Thanh 110KV Substation” is one of the subprojects that will be
implemented in Phase I of the Distribution Efficiency Project (DEP) funded by the World
Bank. The subproject will be implemented in 13 communes of 2 districts in Nghe An
Province.
Activities of Subproject consist of: (i) new construction of 27.382 km of 02-loop
110kV(in current 01-loop will be stretched from Do Luong 220kV substation to Yen Thanh
110kV substation) on the compass of 13 communes within 02 districts of Nghe An province,
including: Xuan Son, Minh Son, Tan Son, Lac Son, Thinh Son, Hoa Son, Thai Son commune
belonging to Do Luong district and My Thanh, Cong Thanh, Khanh Thanh, Lien Thanh, Nam
Thanh, Bac Thanh commune belonging toYen Thanh district (ii) Building new one 110kV
bay at Do Luong 220kV substation and (iii) Building new Yen Thanh 110kV substation, Yen
Thanh district, Nghe An province with capacity of 25MVA. These activities may cause
negative impacts on the local environment and communities during pre-construction,
construction, and operation phases.
To ensure the potential negative impacts are identified and mitigated during the
subproject implementation and in compliance with the policy on environmental assessment of
the World Bank (OP/BP 4.01), an Environmental Management Plan (EMP) of the subproject
has been prepared in accordance with the guidelines provided in the Environmental
Management Framework (EMF) of the DEP project. The EMP includes the following
contents: an introduction, the main legal framework, the subproject description, the
environmental background, potential positive and negative impacts, proposed mitigation
measures to be carried out during the subproject implementation, and implementation
arrangements. It also includes an Environmental Codes of Practice (ECOP) prepared for the
subproject, and it will be incorporated into the bidding documents and construction contracts,
as well as a scope for environment quality monitoring. A Resettlement Plan (RP) has been
prepared and presented separately.
To comply with the government environmental management regulation, an
Environmental Impact Assessment (EIA) of the subproject has been completed and approved
by the Nghe An PPC as a premise of the EMP.
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
4
2. POLICY, REGULATIONS, AND INSTITUTIONAL FRAMEWORKS
2.1. Government Regulations:
The following laws and regulations are applied for subproject:
- Law on Protection of the Environment No. 52/2005/QH11 passed by the National
Assembly on November, 29th
, 2005 regulates the obligations of individuals,
organizations in protecting environment.
- Law on Water Resource No. 08/1998/QH10 dated 20 May, 1998
- Decree of Government No. 80/2006/ND-CP dated 9 August, 2006 on guidance for
implementation of Law on Protection of the Environment.
- Decree of Government No. 29/2011/ND-CP dated 18 April, 2006 regulating strategic
environmental assessment, environmental impact assessment and environment
protection commitment.
- Circular No.26/2011/TT-BTNMT dated 18 July, 2011 on guidance for Decree
No.29/2011/ND-CP dated 18 April, 2011.
- Decree of Government No.106/2005/ND-CP dated 17 August, 2005 on guidance for
Law on electricity relating to the protection of high-voltage networks.
- Decree of Government No.81/2009/ND-CP dated 12 October, 2009 amending some
Article of Decree No.106/2005/ND-CP dated 17 August, 2005.
- Circular No.12/2011/TT-BTNMT dated 14 April, 2011 relating to toxic waste
management.
- Vietnam National Standard: QCVN01: 2009/BYT- national technical regulation on
drinking water quality; QCVN02: 2009/BYT- national technical regulation on
domestic water quality; QCVN08: 2008/BTNMT - national technical regulation on
surface water quality; QCVN09: 2008/BTNMT - national technical regulation on
ground water quality; QCVN05: 2009/BTNMT – air quality – Standard for ambient
air quality; QCVN06: 2009/BTNMT – air quality –specified maximum allowable
concentrations of certain hazardous substances in ambient air.
- Guidance of EVN No. 2623/CV-EVN - KHCN & MT dated 28 May, 2007 on
management and pollution prevention and exposure to PCBs.
2.2. World Bank Safeguard Policies
An environmental screening was undertaken in line with the guidelines provided in the
Environmental Management Framework (EMF) of the DEP project and it showed that the
World Bank’s policies on Environmental Assessment (OP 4.01) and Involuntary
Resettlement (OP 4.12) will be triggered for the subproject. In addition, the Bank’s
requirements on public consultation and information disclosure will need to be followed. The
implementation of policy on involuntary resettlement (OP 4.12) will be addressed in a
separate report.
3. SUBPROJECT DESCRIPTION
3.1. Objectives of the Subproject
The objectives of the proposed subproject are to: i) To supply power for Dien Chau, Do
Luong substations, prevent overload of the local power grid for the subproject communes and
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
5
meet the power supply demand of Nghe An Province; ii) reduce power losses, improve
electricity quality, and provide stable power supply for living, production, and business
activities in the rural areas; iii) meet the power supply demand of the subproject local
communes for socio-economic development in present and future of Do Luong, Yen Thanh
districts; iv) contribute to Government poverty reduction programs in rural areas by providing
basic infrastructures, particularly electricity; and v) contribute to improving material and
spiritual life of people in remote areas of the central provinces.
3.2. Subproject Location
1. Do Luong district
(07 communes)
Xuan Son, Minh Son, Tan Son, Lac Son, Thinh
Son, Hoa Son, Thai Son communes
2. Yen Thanh district
(06 communes)
My Thanh, Cong Thanh, Khanh Thanh, Lien
Thanh, Nam Thanh, Bac Thanh communes
3.3. Subproject Management Organization
- Subproject Owner: North Power Corporation
- Technical Design Consulting Unit: DPT consantant Joint Stock Company.
- Subproject Management Unit: North Grid PMU-North Power Corporation
3.4. Subproject Components
3.4.1. Electric cable 110kV
Yen Thanh 110kV line has the length of 27.382m, its starting point connects to
pooctic of bay of 110kV from Do Luong 220 kV bay, Nghe An province, the ending point is
110KV pooctic of Yen Thanh 110kV substation, Yen Thanh district,Nghe An province. The
line goes through area consisting of thirteen communes belonging to two districts: Do Luong
and Yen Thanh, in which Do Luong districtconsists of communes:Xuan Son, Minh Son, Tan
Son, Lac Son, Thinh Son, Hoa Son, Thai Son, and Yen Thanh districtconsists of communes:
My Thanh, Cong Thanh, Khanh Thanh, Lien Thanh, Nam Thanh, Bac Thanh. The line
mainly runs on flat rice-fields with low different levels, there is one line section of 3.7km
crosses the hill with rather slope terrain (Section from G7 to G13).
Some sections cross through the forested hills of public land of Hoa Son commune, pine-hills
beloging to Thai Son Commune. The Line also many time crosses fields, several times over
the small pond (within area of Son Thinh, Son Hoa, Thai Son and My Thanh communes).
The Line several times crosses field paths, over electrified line with lower voltage such as 35
kV and 0.4kV. It also passes many communication wires.
The line does not affect the residential Works, defense economy, and planning of
local, historical, cultural places or natural conservation zones.
3.4.2 110kV substation:
Yen Thanh 110kV substation is located on rice-field of Bac Thanh commune, Yen
Thanh district, Nghe An province, the transformer station is far from the edge of Provincial
Road 538 about 34m, beyond the road-boundary markers. This area has a relatively flat
terrain.
Yen Thanh 110kV transformer station is built on rice-field of Bac Thanhcommune, Yen
Thanh district, Nghe An province, far from provicial Road 22, far about 25m from the South.
- In order able to build this transformer station the total required land acquisition is
4,262.2m2. In which:
+ Area of station: 3,100m2
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
6
+ Area of access to station: 346.66m2
+ Area around station (Slopes, grassing ...): 815.54m2
3.4.3 Sub expansion 110kV at 220kV Pho Noi substation
- At Do Luong 220kV transformer, the Subproject will expansion an outgoing feeder. The
bay is in precinct of Do Luong 220kV substation, land acquision is not necessary as well as
there is no effect to soil and crops.
Bảng 3.4: Description of transmission lines
No. Project
commune
Item Length
(m)
Environmental and social highlights
1 Xuan Son
commune Do
Luong district
Do Luong
220kv
Substation to
beginning
point
40 - Do Luong 220 kV transformer
station is located in rice fields of
Xuan Son commune, Do Luong Son
district, Nghe An province. The
transformer is far from edge of
highway 15 about 250m, out of the
Right-of-way.
2 Xuan Son
commune,
Minh Son
commune Do
Luong district
Beginning
point – G1
515.6 - Line section from ND -G1has
3newly built steel posts. The line
crosses QL15Aone time, and 35 kV
line one time. G1is located on rice
fields of Minh Son commune. The
whole line passes over the rice fields
belonging to Xuan Son and Minh
Son communes.
3 Minh Son
commune, Tan
Son commune
Do Luong
district.
G1 – G2 1,480.4 - Section G1- G2 has 6 newly built
steel posts. The Line passes over the
rice field and irrigation systems in
the area of Minh Son, Tan Son
communes. G2is located on rice
fields of Lac Son, near hamlet 1 of
Tan Son Commune (far about 200
m), the Line crosses the field-paths
six times.
4 Lac Son
commune and
Thinh Son
commune Do
Luong district.
G2 – G3 1,932.7 - Section G2 – G3 has 6 newly built
steel posts. The Line passes over the
rice field and irrigation systems in
the area of Lac Son, Thinh Son
communes, G3 is located on rice
fields near hamlet 3 of Thinh Son
commune. The Line crosses the
field-paths seventeen times.
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
7
No. Project
commune
Item Length
(m)
Environmental and social highlights
5 Thinh Son
commune, Do
Luong district.
G3 – G4 662.2 - Section G3-G4 has 6 newly built
steel posts. The Line passes over the
rice field and irrigation systems in
the area of Son Thinh commune, the
Line passes through UB hamlet and
hamlet 3 of Thinh Son commune.
The Line crosses soil path five
times, inter-provicial road one time,
and 35V line one time. G4is located
on the rice field of Thinh Son
commune.
6 Thinh Son
commune, Hoa
Son commune
Do Luong
district.
G4 – G5 2,067.2 - Section G4-G5 has 8 new built steel
posts, the Line crosses the field-
paths twelve times, inter-commune
road one time, 35 kV line one time,
and small pond on field Thinh Son
commune three times. The Line is
totally passes over rice fields and
crosses irrigation systems for
agriculture. G5is located on rice
fields of Hoa Son commune
(between hamlet 3 andHighway7)
7 Hoa Son
commune, Do
Luong district
G5 – G5A 1,457.3 - Section G5-G5A has 6 new built
steel posts, the Line crosses rice
fields of Hoa Son commune, it
crosses soil-paths eight times, inter-
hamlet roads one time,
telecomunication line one time,
power line 0.4kv one time, and
small ponds on rice fields of Hoa
Son commune two times.
8 Hoa Son
commune, Do
Luong district
G5A – G6 274.4 - Section G5A-G 6 has 2 new built
steel posts. The Line crosses the
miscellaneous garden belong to
public land of Hoa Son commune,
and the line cross soil-path onetime.
9 Hoa Son
commune,
Thai Son
commune Do
Luong district
G6 – G7 734.3 - Section G6-G7 has 3 newly built
steel posts. The Line passes over the
rice field and irrigation systems of
Hoa Son commune upward to hill
slope belonging to Thai Son
commune. The Line crosses soil-
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
8
No. Project
commune
Item Length
(m)
Environmental and social highlights
path two times, across the pond two
times. G7 is located at eucalyptus
hill in Thai Son commune.
1
0
Thai Son
commune, Do
Luong district
G7 – G8 124 - Section G7-G8 has 1 newly built
steel post. The Line by passes the
residential area of Thai Son
Commune, line crosses eucalyptus
hill which is handed to local people
of Thai Son commune. G7 is located
at eucalyptus hill side of Thai Son
commune.
1
1
Thai Son
commune, Do
Luong district
G8 – G9 876.6 - Section G8-G 9 has 2 newly built
steel posts. The Line runs over a
eucalypts and pine plantation on hill
side which was handed to local
people of Thai Son commune.
1
2
Thai Son
commune, Do
Luong district
G9 – G10 1,738 - Section G9-G10 has 3 newly built
steel posts. The Line runs over pine
plantation on hill side which was
handed to local people of Thai Son
commune. The line crosses soil-path
one time, pond one time, in here
there are two places crossing the
valleys.
1
3
Thai Son
commune, Do
Luong district
and My Thanh
commune Yen
Thanh district.
G10 – G11 503.7 - Section G10-G11 has 2 newly built
steel posts. The Line runs over pine
plantation from the hillside to the
top of hill under public land of My
Thanh commune.
1
4
My Thanh
commune Yen
Thanh district.
G11 – G12 502.4 - G11 – G12 has 2 newly built steel
posts. The Line runs over pine
plantation on hill side of My Thanh.
G12 will be placed on a rice field of
My Thanh commune which is
6,100m from the residential area.
- Section G11-G12 has 2 newly built
steel posts. The Line runs over pine
plantation on hill side of My Thanh
commune, and crosses pond one
time. G12 is located on rice fields of
My Thanh commune far from
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
9
No. Project
commune
Item Length
(m)
Environmental and social highlights
residential area of hamlet 6 about
100m.
1
5
My Thanh
commune Yen
Thanh district.
G12 – G13 827.9 - Section G12-G13 has 1 newly built
steel posts. The Line passes over
rice fields of My Thanh commune,
crosses soil-path one time, power
line 0.4kV two times, and 35kV line
one time. G13 is located on rice
fields of My Thanh commune, far
from residential area of hamlet2
about 90m.
1
6
My Thanh
commune ,
Cong Thanh
commune Yen
Thanh district.
G13 – G14 1,915.8 - Section G13 – G14 has 8 newly
built steel posts, the line passes over
the rice field near hamlet 2 of My
Thanh commune to the rice field of
Cong Thanh commune. The line
also crosses irrigational system for
rice fields of My Thanh and Cong
Thanh communes. The line crosses
inter commune road one time, soil
roads 9 times, power line 35 kV two
times, and ponds three times.
1
7
Cong Thanh
commune Yen
Thanh district.
G14 – G14A 780.8 - Section G14 – G14A has 4 newly
built steel posts, the line crosses
plain rice field, power line 35 kV
one time, power line 0.4 kV one
time. G14A is located on rice fields
of Cong Thanh commune.
1
8
Khanh Thanh
commune Yen
Thanh district.
G14A – G15 1,626.6 - Section G14A – G15 has 7 newly
built steel posts, the line crosses
plain rice field, line crosses soil
roads two time, power line 35 kV
one time, power line 0.4 kV one
time.
1
9
Khanh Thanh
commune Yen
Thanh district.
G15 – G15A 2,121.3 - Section G15 – G15A has 9 newly
built steel posts, the line mainly
passes over rice fields, it is on the
left side of the electrical line 500
KV, it also avoid the planned town
areas, the line crosses irrigational
ditch one time, power line 0.4 kV
two times, Hac stream one time.
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
10
No. Project
commune
Item Length
(m)
Environmental and social highlights
G15A is located in Dong My area.
2
0
Lien Thanh
commune Yen
Thanh district.
G15A – G16 1,036.8 - Section G15A – G16 5 has newly
built steel posts, the line crosses
plain rice field, and the line crosses
National Road QL7 one time,
telecommunication cable one time.
2
1
Nam Thanh
commune Yen
Thanh district.
G16 – G17 815.8 - Section G16 – G17 has 4 newly
built steel posts, the line crosses
plain rice field, telecommunication
cable one time, power line 35 kV
three times, roads five times,
irrigational ditch one time on the
ricefield of Nam Thanh commune.
2
2
Nam Thanh
commune Yen
Thanh district.
G17 – G18 2.028,2 - Section G17 – G18 has 8 newly
built steel posts, the line crosses
plain rice field, inner-field soil paths
6 times.
2
3
Bac Thanh
commune Yen
Thanh district.
– G19 1,297.8 - Section G18 – G19 has 6 newly
built steel posts, the line crosses
plain rice field, inner-field soil paths
3 times, power line 0.4 kV one time,
telecommunication cable one time.
2
4
Bac Thanh
commune Yen
Thanh district.
G19 – G20 1,448.3 - Section G19 – G20 has 6 newly
built steel posts, the line crosses
plain rice field, soil roads 5 times,
power line 35 kV one time.
2
5
Bac Thanh
commune Yen
Thanh district.
G20 – NC 613.9 - Section G20 – NC has 4 newly built
steel posts, the line crosses plain
rice field, provincial road 538 one
time, power line 0.4 kV one time.
2
6
Bac Thanh
commune
NC-TBA
Yên Thành
22 - Yen Thanh 110kV transformer is
located on rice field of Bac Thanh
commune – Yen Thanh district –
Nghe An province, the transformer
is about 34m far from the edge of
provincial road 538, out of the
Right-of-way.
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
11
3.4.3. Subproject Technical Specifications
a. The 110 kV Transmission Line:
Construct new 27.382 km of 02-loop 110kV(in current 01-loop will be stretched from Do
Luong 220kV substation to Yen Thanh 110kV substation)
Main technical specifications:
- Rated voltage 110 kV
- Number of circuits 02 line
- Beginning Point: Gantryof the 110kV at Do Luong 220kV
Substation.
- Endding Point: Yen Thanh 110kV Substation
- Length: 27,382m.
- Cable AC 50/8
- Earth wire : OPGW – 57/ 12(lightning)
- Insulation use glass or pottery insulator
- Pole: Erect dip-galvanized steel column
- Foundation area: From 42.25m2 to 207.36m
2
b) Subexpansion 110kV at 220kV Pho Noi substation
Main technical specifications:
- Install a switchgear for one expanded cell including main equipment such as switch,
disconnector, current transformer. Equip with additional earthing equipment and lightning
protection for the expandable and transportable equipment.
c) Yen Thanh 110kV Sustation: Construct new 110kv substation with capacity of 25kVA in
Bac Thanh commune, Yen Thanh district, Nghe An Provine.
Main technical specifications:
-Rated voltage:
+ HV: 110kV.
+ MV: 35kV.
+ LV: 22kV.
- Capacity: expected two transformers of 25MVA, one of them should be installed initially, the
other will be installed in future;
3.4.5. Work volume to be implemented in subproject.
No. Construction and installation Unit Quantity Method
1 Pulling the electrical wire
ACSR240/32
m 86,452 Manual + machine
2 Installation of 2-circuit steel
supporting pole 27m
pole 79 Manual + machine
3 Installation of 2-circuit steel
supporting pole 31m
pole 6 Manual + machine
4 Installation of steel 2-circuit
anchored pole 24m
pole 17 Manual + machine
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
12
No. Construction and installation Unit Quantity Method
5 Installation of steel 2-circuit
anchored pole 29m
pole 9 Manual + machine
6 Installation of steel 2-circuit
anchored pole 38m
pole 1 Manual + machine
7 Foundation of steel supporting
pole
foundation 85 Manual + machine
8 Foundation of steel 2-circuit
anchored pole 24m
foundation 17 Manual + machine
9 Foundation of steel 2-circuit
anchored pole 29m
foundation 9 Manual + machine
10 Foundation of steel 2-circuit
anchored pole 36m
foundation 1 Manual + machine
11 Construction of control and
distribution station 28,8x15,2m
house 1 Manual + machine
12 Construction of Operation and
shift-break house 9,5x18m
house 1 Manual + machine
13 Installation of power
transformer 25000kVA/110kV.
machine 1 Manual + machine
14 Installation of bar-type
transformer 100kVA/35kV.
machine 1 Manual + machine
15 Installation of bar-type
transformer 100kVA/22kV.
machine 1 Manual + machine
16 Installation of spin-cast concrete
pole 20m
pole 2 Manual + machine
17 Installation of spin-cast concrete
pole 16m
pole 1 Manual + machine
18 Installation of steel beam 9m set 1 Manual + machine
19 Installation of support for
breaker 110kV
pier 2 manual
20 Installation of support for
disconnector 110kV - 1 earthing
pier 3 manual
21 Installation of support for
disconnector 110kV 2 earthing
pier 6 manual
22 Installation of support for
earthing conductor - neutral
anti-lightning 72 kV
pier 1 manual
23 Installation of support for
current transformer 110kV
pier 3 manual
24 Installation of support for
lightning arrester 110kV
pier 3 manual
25 Installation of support for
transformer 110kV
pier 3 manual
26 Installation of support for bar-
type transformer 35/0,4kV
pier 1 manual
27 Installation of support for bar-
type transformer 22/0,4kV
pier 1 manual
28 Installation of support for piece 1 manual
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
13
No. Construction and installation Unit Quantity Method
outdoor connection cabinet
29 Construction of working bend
for cutter
piece 1 manual
30 Foundation of spin-cast pole
MC-7
foundation 3 manual
31 Foundation of pier foundation 23 manual
32 Foundation of transformer foundation 1 manual
33 Installation of earthing system system 1 manual
34 Construction of outdoor cable
trough system
system 1 manual
35 Construction of concrete slab
system for outdoor cable trough
system 1 manual
36 Construction of breakdown oil
reservoir V=27m3
piece 1 manual
37 Construction of fire fighting
sand reservoir
piece 1 manual
38 Construction of internal path
system
system 1 manual
39 Construction of external path
system
system 1 manual
40 Construction of water and oil
supply, drainage
system 1 manual
41 Construction of fire fighting
system
system 1 manual
42 Construction of external lighting
system
system 1 manual
43 Backfill for grading m3 6,606.41 Manual + machine
44 Rip-rap 4x6 for station
foundation with thickness of
100mm
m2 1,077.92 manual
45 Construction of concrete ground
M150 with thickness of 150
m2 485.98 manual
3.5. Main Activities Before and During Construction
3.5.1. Main Activities Before and During Construction
Activities before construction:
- Compensation and site clearance.
- Set-up of temporary construction camps.
- Mobilization of workers.
- Temporary land acquisition partly along roadside for storing material and
equipment..
- Construction of temporary worker camps workers.
- Set-up of domestic water supply for the domestic and construction needs
Activities during construction:
- Construction of substation:
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
14
+ Foundation excavation.
+ Transportation of material and equipment to the site.
+ Set-up of pillars and substation equipment.
- Construction of transmission line:
+ Foundation excavation.
+ Transportation of material to the site.
+ Set-up of poles – installation of line components.
- Main materials and equipment to be used:
+ Cement, sand, stone, iron, pole, porcelain, mixing station, cranes, etc.
3.5.2. Transportation
Material and equipment supply
Material and equipment supply will be determined in detail in later phase, depending on
the state budget disbursement and the subproject bidding method. Two sources are expected:
- Material and equipment supply by the subproject owner.
- Material and equipment supply by the contractor.
Long distance transportation
For material and equipment supplied by the project owner:
+ Long distance transportation of such material and equipment will be undertaken
using specialized trucks. Such trucks will be selected in accordance with the requirements
provided in the contract.
+ Long distance transportation from the subproject owner warehouse to the site
will be undertaken using 5-7.5 ton trucks and loading and unloading will be done using 5-
ton cranes.
For materials and equipment supplied by the contractor:
+ Electric poles will be transported using Kawaz trucks, using 5-ton cranes for
loading and unloading.
+ Supporting frames and accessories will be transported using 5-ton trucks with
manual loading and unloading.
+ Cement and steel will be transported using 5-ton trucks with manual loading and
unloading.
+ Stone and sand will be transported using 5-ton dump trucks.
Intermediate transportation
- Materials and equipment stored at the site such as cables, insulators, accessories,
breakers, capacitors, power meters, meter boxes and cement will be transported to the
construction sites using non-motorized vehicles and manual handling.
Manual handling
All materials and equipment will be transported to the construction site manually. The
distance will be determined case by case.
3.6 SubprojectImplementation Schedule and Total Investment
3.6.1 Subproject Implementation Schedule
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
15
Based on the requirements of power supply and capacity of the subproject owner, the
subproject timeline is scheduled as follows:
Preparing the investment 12/2011-6/2012
Preparing as-built drawing design 07/2012-08/2012
Tendering equipment 08/2012-09/2012
Tendering construction and
installation 09/2012-10/2012
Implementation 12/2012-08/2013
Completion 9/2013
3.6.2. Total Investment Total investment breakdown:
Civil construction 93,339,720,000
Procurement 30,729,061,000
Project management 3,106,811,000
Compensation 1,728,288,000
Construction consultancy 7,078,223,000
Others 6,684,860,000
Contingency 14,266,696,000
Total investment: 156,933,658,000
4. ENVIRONMETNALBACKGROUND
4.1 Geography
Nghe An has its area of 16,487km2. Nghe An is the biggest province of Vietnam
belonging to Mid-northern area.
+ Bordering Thanh Hoa province in the North
+ Bordering Ha Tinh province in the South
+ Bordering Laos in the West
+ Bordering Eastern Ocean in the East.
The project is located in Dong Luong district and Yen Thanh district, in the East of Nghe An
province.
4.1. Climate, topography, pedology
4.2.1. Climate
The communes in the project area are located in tropical monsoon climatic region,
with 4 seasons: spring, summer, autumn, winter. Annually, from April to August, the climate
of the province is affected by dry and hot south-west wind. In winter, it is affected by cold
and wet northeast monsoon. In the project area, annual average rainfall is: 1,670 mmwith
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
16
average temperature of 25.2 °C, average relative humidityof 86-87%and number of annual
sunny hour of 1,420 hours.
4.2.2 Topography
Communes in the project area are belonging to delta region. The topography is
relatively convenient. Nghe An has a dense river system, Ca River (Lam River) is the biggest
river with the total length of 532 km. However, the wire line does not pass over Rivers but
also crosses some small lakes and ponds, irrigational channels in Thinh Son, Hoa Son, Thai
Son, My Thanh, Khanh Thanh communes. Foundations of poles are not built on public
ground and ricefields. The construction of foundation on rice fields does not impact on
irrigational channels and drainage ditches.
4.2.3 Pedology
Survey result shows that the foundation geology of the project area is mainly formations with
erosive accumulated origin (alQ4), including 3 soil layers: cultivating soil, clay, clay mixed
with grit and gravel fragments.
4.2. Natural resources
4.3.1 Land
Nghe An province has its natural soil area of 1,648,728 ha. In which, agricultural land is
195,944 ha, accounting for 11.88%; forestrial area with forest is 685,504 ha, accounting for
41.57%; specialized area is 59,221 ha, accounting for 3.59%; residential land is 14,893 ha,
accounting for 0.90%; land area not yet used and river/stream is 693,166 ha, accounting for
42.04%.
In agricultural land, the area for tree plantation annually is 142,333 ha, accounting for
72.63%, particularly for rice plantation accounting for 22.4% with 2 harvest seasons; the land
area for long-planting tree is 12,401 ha, accounting for 6.32%.
4.3.2. Forest
Total forest area is 745,557 ha, coverage of 45.2% (according to data in 2004).
Wood deposit is more than 52 million m3
including many valuable types of wood such
ashinoki wood, samu wood, iron wood, dracontomelum wood, clove wood, bassia...
Bamboo, neohouzeaua, met: more than 1 billion trees; estimated about 226 valuable
medical and forestrial species.
The project line does not pass by forest areas.
4.3. Population, culture, society
Nghe An population (according to the survey on 01/04/2009) has 3,113,055 peoples.
Over the province, there are many minorities living together such as Thai people, Muong
people besides the main ethnic – Kinh people. In the project area, only Kinh people lives.
In the project area: cultural and social matters are under the attention of local
authorities, all people living the area have pure water and electricity. The project will directly
and indirectly contribute to the life improvement for local residents by supplying power for
manufacture, local economic development and lighting public works.
The project is not located in the areas having historical heritages, cultural-social
works as well as state security works.
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
17
4.4. Traffic:
Nghe An is an important traffic node of the nation. It has a developed and diverse transport
network, with roadway, railway, waterway, airport and harbour, which are established and
distributed suitably along residential areas and admin-economic centers.
Roadway: national road 7, national road 48, national road 46, national road 15;
moreover, 132km Ho Chi Minh Highway passing by mountainous and midland
districts of the province.
Railway: 124 km, including 94 km North-South line, with 7 stations, Vinh station is
the main one.
Airway: Vinh airport, with flights from Vinh to Da Nang and from Vinh to Tan Son
Nhat (and backward)
Harbour: Cua Lo harbour presently can adapt 1.8 ton seaboat, to be an international
exchange terminal
International entry gates: Nam Can, Thanh Thuy; in the coming time Thong Thu (Que
Phong) gate will be openned.
Because traffic conditions of project is rather convenient, further construction access
is not necessary.
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
18
5. SUBPROJECT POTENTIAL IMPACTS
The project will play an important role in the electrification program and poverty
reduction policy in 13 communes of 02 districts. It will also speed up the national
modernization and industrialization which is a step towards promoting rural development and
poverty reduction.
When the transmission lines are constructed, the local residents will tend to move to
live close to electricity access. The local authorities will need to plan for this by opening new
roads, new residential areas and industrial and agriculture development. All the subproject
districts and the city will have to work in this direction.
The project will bring about significant socioeconomic benefit. This has been
documented in detail in the description of feasibility report. Apart from such benefits, the
subproject may also result in environmental and socioeconomic impacts which are adverse to
the local conditions.
The environmental screening of the subproject indincates that it is eligible for financing
considering that the subproject will not involve possible high UXO risk and will not create
possible adverse impacts on (a) critical natural habitats and/or protected area including
proposed protected areas; (b) loss or damage to cultural property, including sites having
archeological (prehistoric), paleontological, historical, religious, cultural and unique natural
values, graves and graveyards; (c) water regime, particularly water flow and water quality;
and (d) local traffic.
The potential negative impacts of the subproject are identified in table 5.1 and could
be minimized by applying the proposed mitigation measures developed for the subproject
which is described in Sections 6.
Question Yes No Description of impact
I. Is project located
near or in sensitive
area with regards to?
Cultural
heritage X X
- The transmission line and substation will not
pass through areas with cultural and historic
value.
Reservation
zone X
Flooded land X
Forestry X
Estuary X
Reservation
buffer zone X
Naturereserve X
River and
reservoir X
In the area of Nghe An province has Lam River.
However, the nearest distance from Lam River to
Project location is so far (about 20km), so the
project does not affect the river.
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
19
Question Yes No Description of impact
Canaland
irrigation
network X
- The area of project has also Nong Giang canal
but the line does not pass through the area, but
only crosses over some small ponds and
irrigation systems for agriculture at Thinh Son,
Hoa Son and Thai Son, My Thanh, Khanh
Thanh communes. These impacts are
considered very small and can minimize.
II.Potential
environmental
impact, by project?
- Intrusion to cultural
and historical sites X
- Intrusion to
ecosystem (ex:
nature reserve,
national park)
X
- Affecting landscape
and resulting in
waste
X
- The entire project is mainly located on rice-
field so it should not cause any major impact on
landscape. Clearance of alignment corridor at
pine hill may have small change on landscape
and increase of wastes, however it is considered
as at low levels and to have appropriate
measures
- Undermining
vegetation cover or
cutting down trees
for site during site
clearance for
substations and
along the
transmission line?
X
- The tree higher than 4m will be cut off whereas
the low vegetations such as brushes and
savanna are remained unchanged.
- Location of transformer is on field land, mainly
growing rice and crops. There are some small
effects during clearance process serving for
ground leveling of station floor.
- During site clearance, there are 28 households
to be affected because number of trees is cut.
When implementation of wiring work,
excavation of post foundation through rice
fields where are in harvest season. This affects
368 households
- Change surface
water quality or
river course
X
- Increase water
turbidity due to
change in surface
water quality or
erosion X
- The transmission line would overpass some of
ponds, lakes, lagoons, irrigation channels and
rice fields. These surface water bodies may be
affected by increased turbidity due to soil
residue from excavation of the tower
foundations.
- The subproject would be implemented in
relatively flat areas with some short line
sections along low hill range. Therefore, the
impacts of erosion and run off are expected to
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
20
Question Yes No Description of impact
be small.
- Positions of post foundation are located far
away from the surface water sources.
Earthwork is planned to implement in dry
season. Excess soils will be reused to backfill
foundation, embankment. Therefore, there is no
waste land, rock after completion of
construction
- The impact on surface water is assessed as
small and could be mitigated.
- Domestic waste
water by workers is
discharged directly
into outside water
bodies?
X
- The contractor will rent local houses for
workers, and thus wastewater will be collected
into household waste treatment facilities such
as septic tanks. In case of building temporary
tents for workers, drainage and garbage
collection must be complied with the
regulations.
- Construction waste
water is discharged
directly into outside
water bodies?
X
- Result in more
dust?
X
- Dust will be generated from soil excavation,
ground leveling activities, particularly in dry
season. The affected are people living and
working around the subproject site.
- Dust would also be generated by transportation
means that carry materials and equipment
during the construction. The affected are people
involved in the traffic during the transportation
of construction materials or equipment, either
on local roads or on provincial or national
roads.
- Result in higher
noise or vibration
level?
X
- - Noise and vibration are generated by
operation of equipment, transportation of
materials, transportation means, ground
leveling, pole erection, and operation of power
generator (if any).
- -The substations will be located on field land,
far from residential areas, and hence noise and
vibration during construction would not affect
local communities.
- - Construction materials will be provided and
transported to the construction sites by local
suppliers.
- Base on above-mentioned reasons, impacts on
increasing the noise and/or vibration at the
subproject area are assessed as not significant
and can be mitigated.
- Relevant measures listed in section VI will be
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
21
Question Yes No Description of impact
implemented to minimise these impacts.
- Permanently
acquired land
X
- Permanently acquired land area is: 12,156 m2.
In which:
+ Field land: 10,326m2
+ Hill land: 1,830m2
- Temporarily
acquired land
X
- Temporarily acquired land area is: 59,044m2.
in which:
+ Field land: 52,607m2
+ Hill land: 6,437m2
- Resettlement
required? If yes,
how many
households?
X
- Is there any risk in
spreading disease
from workers to
local residents (and
vice versa)?
X
- The project will hire two groups of workers:
The first group: Permanent workers of the
contractor, with specialized skill arriving from
other areas. The second group: seasonal labour
who are mobilized from communes where
project goes through. The disease spread from
worker to population and vice versa can occur
during project construction
- Interactions with local community may pose
the risks of STD/HIV/AIDs diseases
transmission between workers and local
community. Relevant measures described in
section VI of this EMP will be implemented to
minimise these risks.
- Is there any
potential conflict
between workers
and local residents?
X
- The subproject will make effort to recruit local
workers, and the number of workers is very
small compared with total local population.
- Numbers of construction workers are about 90
people at construction site. They may create a
risk of conflict with local people due to
different level of education, and behavior.
However, these conflicts are evaluated as minor
because in project area there is no ethnic people
so that different level about cultural
acknowledge is not very much.
- Is there explosive or
toxic substance
used by the project?
X
- Is there any
accident due to
mine or explosives
remained from
X
- Because of the war, up to now there may be
mine and bombs still remain. Consequently,
disarming bombs and mines at construction
area must be carried out prior to implement, the
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
22
Question Yes No Description of impact
wartime? Employer shall sign contracts with companies
who conducts mine and bombs disarming.
- Project construction
interrupts local
traffic?
X
- The transportation routes for equipment will
follow the national roads 7, 15, provincial roads
538, 22, and the existing intercommune and
inter village roads. Due to light traffic in the
area, and short time for unloadding (usually
abour 01 hour), and automatic unloading of
construction materials, the impact on the traffic
is assessed as minor.
- Project construction
badly affects local
power network? X
- Because transport with high frequency and
load, the project will affect the quality of the
existing road system.
- The mitigation measures described in Section
VI will also be implemented
- Excavation causes
erosion?
X
- Although terrain of the subproject areas is
mainly mountainous with high landslide risk,
foundation excavation would be carried out on
a relatively flat area, and some short sections
run along the low hills, so the erosion risk is
not high.
- The construction time of pole foundation is
short (about 1/2 day) and the construction
would not be implemented in the rainy season.
Each item will completely be done before the
construction of another item, and thus erosion
is expected to be small.
- Is there a need for
opening new
service road?
X
- Since the transmission lines and substation
would be located along roads. Existing roads
will be used.
- Project interrupts
the habitat of local
fauna and flora?
X
- Project badly
affects local air
quality?
X
- The level of impact on the environment by
emission and dust from transportation vehicles
would be small because they will be covered
during the transportation of construction
materials. Transportation means need to
comply with emission regulations.
- The mitigation measures described in Section
VI will also be implemented
- Project results in
risks in labor
accidents for
workers and local
community during
construction phase?
X
- Minor impact
- Project creates toxic X - The transmission lines shall be designed and
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
23
Question Yes No Description of impact
waste, including
PCB due to
replacement of
transformers?
constructed in accordance with applicable
standards of power industry (in accordance
with Vietnam applicable technical regulations,
electromagnetic field (EMF) < 5 kV/m),
wherein impacts from EMF and safety
standards and operation safety have to be taken
into due account.
- Prior to operation, all safety indicators shall be
tested and accepted by the project owner,
contractor and operation entity therefore
workers shall not be suffering from such EMF
impacts.
- In the phase of commissioning, the safety in
power use of households of ethinic minorities
who use electricity for the first time also needs
to be paid attention to minimize the risk of
electric shock. However, this impact is very
little and avoidable if the people are trained
well in safe power use.
- The mitigation measures in Section VI will also
be implemented to minimise safety risks
Since implementation of the subproject would mainly cause land acquisition, increased
dust generation, air pollution, and domestic wastes. However, these impacts are not
significant, temporary, and localized, and can be mitigated available mitigation measures.
Therefore, the subproject is assessed as B environmental category and eligible for funding by
the World Bank.
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
24
6. ENVIRONMETNAL MANAGEMENT PLAN
6.1. Mitigation Measures.
The above impacts can be mitigated by: (a) ensuring that the application and supervision of
ECOP (Table 6.1) below; and (b) implementing site specific mitigation measures.
Table 6.1. Mitigation measures
Mitigation Measures Implementati
on
responsibility
A. Preparation phase
Permanent and
temporary land
acquisition will
impact affected
households and
agriculture
production
- To plan for construction activities after
harvesting season and try to shorten the progress.
- Inform the affected HHs about permanent and
temporary land acquisition.
- Properly compensate for land acquisition and
tree compensation in accordance with the
Resettlement Policy Framework of the DEP
project and Resettlement Plan of the subproject.
- PMU
Contractor
Impacts on
vegetation cover as
a result of site
clearance (ROW)
- Minimize land clearing by planning for
installation of transmission/distribution lines
above existing vegetation.
- Utilize hand clearing of vegetation if possible.
Save as much vegetation as possible. Careful
manage cutting trees. Cut only tree above 4m
within the ROW.
- Do not burn cleared trees and branches;
- Carry out the safety procedures to prevent hazard
of downing trees.
- Dispose at established dump site.
- During clearing, contact with the affected HHs in
order to mitigate impacts and carry out
compensation.
- PMU
- Contracto
r
Explosive materials
left from war
- Contract with related army unit to clear the site
from unexploded ordnances left from war.
- Return the ground after the clearance.
- PMU
- Army
- Local
authorities
B. Construction phase
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
25
Mitigation Measures Implementati
on
responsibility
1. Dust pollution - The contractor is responsible for implementing
the state applicable regulations related to air
quality.
- The contractor will ensure minimum dust
generation and no impact on local residents and
take proper measures to control dust generation
(for example, praying water, covering the trucks
when carrying material).
- Material will be covered up during.
transportation to prevent scattering of material
along the way.
- Material dump site and storage yards will be
covered up and isolated from winds and located
away from schools and residential areas.
- Workers will be provided with masks when
working in high risk areas.
- Contractor
- CSC
2. Air pollution - All transportation vehicles must comply with
applicable regulations of Vietnam with regards to
exhaust gases.
- Transportation vehicles in must be tested
frequently on the waste gases and have to show
certificate of quality, technical safety and
environmental friendliness according to Decision
No.35/2005/QD-BGTVT.
- Do not burn waste or construction materials at
the site.
- Contractor
- CSC
3. Noise and
vibration level
- The contractor will be responsible for complying
with applicable regulations related to permitted
noise and vibration levels.
- All transportation vehicles need to show
certificate of quality, technical safety and
environmental friendliness according to the
Decision No.35/2005/QD-BGTVT; to prevent
excessive noise level from machinery that is not
properly maintained, proper noise reduction
measures are taken, including noise reducers or
arrangement of noisy machinery in a specific
noise proof area.
- To prevent or reduce traffic in residential area as
well as processing of material in residential areas
(concrete mixing)
- Contractor
- CSC
4. Waste water
pollution
- The contractor will be responsible for complying
with applicable regulations related to waste water
treatment and discharge.
- To provide mobile toilets or construct proper
toilets for workers at the site. Toilet waste water
and restaurants will be treated before discharging
- Contractor
- CSC
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
26
Mitigation Measures Implementati
on
responsibility
into the outside environment.
- When construction is completed, toilets have to
be properly destroyed and/or removed.
5. Water drainage
and sedimentation
control
- The contractor will comply with the water
drainage system design to prevent rain drop from
causing local inundation, soil erosion in high risk
areas.
- To ensure proper operation of the drainage
system.
- To sustain those areas not impacted by
construction activities.
- The excavation work needs to be done in
compliance with applicable technical
construction regulations.
- To prevent the spreading of mud into
surrounding environment, take proper measures
to control sedimentation in high risk areas.
- When there is a need to dry construction site
(foundation concrete pouring), the pumped water
containing sand will be controlled with regards to
sedimentation before discharging it into outside
water bodies.
- Use diversion techniques at construction to
prevent deposit from being stirred up in water
bodies.
- Contractor
- CSC
6. Material
warehouse and
material quarry
management
- Material storage yards will be predetermined in
the approved engineering design.
- Material supplied by local suppliers need to have
operation licenses for particular material type.
- To rehabilitate material storage yard after
construction is completed.
- Contractor
- CSC
7. Waste and
hazardous waste
- Prior to construction, the contractor needs to
prepare a procedure for controlling waste
(storage, use of recycle bins, site
decommissioning, etc.) and strictly complying
during construction phase.
- Prior to construction, all necessary licenses have
to be obtained related to waste management.
- Proper measures are taken to ensure good
practices in waste management and treatment.
The contractor will provide recycle bins,
containers and other means to collect waste from
necessary areas.
- Waste can be stored temporarily at the site when
it is approved by the Construction Monitoring
Consultant, local authorities before collection
and treatment. If in the absence of such
- Contractor
- CSC
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
27
Mitigation Measures Implementati
on
responsibility
authorities, normal domestic waste can be land
filled.
- Recycle bins or containers storing waste have to
be covered up from weather impacts and
intrusion by scavengers. Do not burn waste.
- Recyclable waste such as wood form, waste steel
and packing material will be collected and
separated at the site from other waste sources for
reuse, refilling or sale to an external company.
- If it is impossible to carry away from the site,
solid waste can be land filled at a certain place
approved by the construction supervising
consultant provide in the waste management
plan. Under any circumstance, the contractor has
to treat all construction waste within the site.
- Waste lubricants will be taken out from the site
by an authorized recycling company.
- Waste lubricants and cleaning solutions will be
collected into covered containers and carried
away by a contracted external company that is
permitted to treat hazardous waste
8. Site clearance - The contractor will prepare a plan on site
clearance and vegetation recovery according to
applicable regulations for the construction
supervising consultant to approve. The contractor
will strictly comply with this plan.
- Do not use chemicals in clearing vegetation.
- Do not cut down any trees when it is not
provided in the vegetation clearance plan.
- If necessary, set up temporary fence to protect
valuable trees prior to starting any construction
activities.
- Contractor
- CSC
9. Traffic
management
- Prior to construction, conduct consultation with
local authorities and traffic police.
- Impacts on traffic flow needs to be considered in
the construction plan before approval. Traffic
routes, particularly those with heavy duty
vehicles need to consider high risk area such as
schools, hospitals or markets.
- It is necessary to provide sufficient lighting
system for night time to ensure proper traffic
conditions.
- Arrange indication signs at the construction site
to inform public people, provide instructions to
different components and instructions and safety
directions.
- Take proper traffic safety measures including
- Contractor
- CSC
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
28
Mitigation Measures Implementati
on
responsibility
sign posts and flags to indicate danger
- Do not transport material during peak house.
- Space spared for walkers and vehicles at the site
need to be separate from the site and can be
easily accessible. Provide proper sing posts
where necessary.
10. Interruption of
utility and
businessservices
- Planned or unplanned interruptions to services
such as water, gas power supply and internet
access: The contractor will be prepared for
emergency scenarios and any potential failures.
- Cooperate with services suppliers (water,
telecommunications, etc.) to work out a proper
construction schedule.
- During the laying out of cables crossing over
telecommunications cable, mitigation measures
have to be taken (What are the measures?)
- Notify affected households of construction
schedule as well as expected interruptions (at
least 5 days in advance)
- Interruptions to water supply for agriculture
production need to be avoided.
- The contractor will ensure alternative water
supply for affected residents in case it is more
than one day.
- Any damage to the existing service cables will be
notified to the local authorities for timely repair.
- Contractor
- CSC
- PMU
11. Rehabilitation of
affected areas
- Clearance areas such as soil or rock quarries,
waste treatment areas, worker houses, warehouse
and wood forms and any other temporary areas
during construction phase will be rehabilitated
with regards to the landscape and vegetation
cover.
- Compensate the vegetation cover at the soonest.
Use proper vegetation for such rehabilitation.
- Do not use exotic or banned vegetation for such
rehabilitation
- Excavated hillsides and waste yard need to be
planted with grass to prevent soil erosion and
landslide;
- All the affected areas will be compensated with
proper landscape and there should be no delay in
doing so, including any necessary repair or
construction of green space and other affected
areas.
- Soil contaminated with chemicals or hazardous
waste will be carried away and land filled in a
proper hazardous dump site
- Contractor
- CSC
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
29
Mitigation Measures Implementati
on
responsibility
- Rehabilitate all affected roads and bridges due to
the project construction
12. Labor and public
safety
- The contractor will comply with all applicable
regulations related to labor safety.
- Prepare and implement action plan in response to
risk and emergency cases.
- Prepare emergency services right at the site.
- Provide training for workers on labor safety
requirements.
- Ensure to provide protective devices for workers,
including noise protection at high risk places
- In destroying existing structures, workers and
community need to be protected from falling
objects by taking proper protection measures
- Provide protective fences and warnings of danger
at the construction site to indicate danger to local
resident.
- The contractor will provide safety measures such
as installation of fences, provision of warning
signs at high risk areas, including pole
foundation under construction to prevent traffic
accidents as well as other risk to local residents.
- Only allow trained workers to install, maintain or
repair electrical equipment.
- Cut off and do correct earthling for the existing
power line prior to construction work.
- Comply with labor safety procedures when
working at height and with electrical equipment
- Contractor
- CSC
13. Communications
to local community
- Sustain communications to local authorities and
community; the contractor will work with local
authorities to agree on construction schedule for
sites near sensitive areas or at sensitive time
(regional festivals).
- Enhance relationship with local community in
order to obtain necessary information about the
project activities in the region, progress and
performance;
- Keep track of the community concerns and
information required such as project progress;
- Respond to community concerns via telephones
and documents in a timely manner;
- Notify local residents of construction schedule,
work schedule, potential interruptions to services
and detour roads and temporary buses, any
destruction or mine explosion schedule;
- Provide technical data and drawings for
community, particularly a scheme on
- Contractor
- CSC
- PMU
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
30
Mitigation Measures Implementati
on
responsibility
construction sites and EMP;
- Provide notice boards at all sites to provide
information about the site manager,
environmental officer, medical and safety officer,
with concrete contact details and other
information so that affected people will be able
to raise their voice and concerns.
14. Chance find
procedures
- During construction phase if the contractor finds
any cultural and historical sites, including
commentary or tombs, the contractor will:
- Stop construction activities in the particular area;
- Protect the area from any damage or loss to the
sites. In case the historical objects can be
removed or sensitive objects assign a person to
protect it until local authorities come to confirm
and take over the issue;
- Notify the construction supervising consultant,
who will be responsible for informing local
authorities or the state agencies of such cultural
or historical sites (within 24 hours or less);
- Local authorities or state agencies will be
responsible for protecting and isolating such area
before any further processing.
- Decide how to process such issues is the
responsibility of the local authorities, including
change, (in case a cultural or historical site is
found and cannot be removed), reservation,
isolation, rehabilitation and rescue;
- If the cultural or historical site are of high value
and the reservation is recommended by relevant
agencies the project owner will have to change
project design accordingly for the component in
that particular area;
- Decisions related to the management of found
sites will be notified in writing to relevant
authorities;
- Construction work will continue only after
relevant authorities come and take responsibility
of potential sites.
- Contractor
- CSC
- PMU
C.Operation phase
1. Health and safety
for workers and local
residents
- Disseminate the information on electricity safety
regulations to the users.
- Comply Decree No. 106/2005/ND-CP dated 17
August 2005 of Goverment on protecting grid;
Decree No. 81/2009/ND-CP dated 12 October
2009 of Government on protecting high voltage
grid
- NPC
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
31
Mitigation Measures Implementati
on
responsibility
- Regular training for local technicians and people
on safety issues.
- Use warning signs, barriers (locks, gates, iron
barriers...) around substation or tower to prevent
people reach danger equipment;
- Putting warning signs, barriers on the ground
close to electricity wire to prevent electric shock
2. Fire and explosion - Periodically inspect fire prevention and fighting
facilities.
- Organize training on fire prevention and fighting
for operation workers.
- NPC
3.Transmisison line -
Mitigation measures
related to transmission
lines
- Only allow workers who have been trained and
obtained certificates on installation, maintenance
and repair of electrical equipment
- Cut off power and provide safe earthling before
construction on the power line or where it is near
power line
- Ensure operations related to power line will be
undertaken by trained workers with strict
compliance with safety regulations. Qualified or
trained workers to operate power lines need to
able to:
Distinguish between online and offline power
lines from other parts of the distribution system
Determine voltage of online power lines
Understand safety distance for each cable types
Ensure correct and sufficient use of safety
devices and other safety procedures or other
online parts of the distribution system
Even when being trained, workers will not contact
any online parts unless:
Workers have been safely isolated from online
parts via gloves or other insulation devices
Online parts have been safely isolated from
workers and other parts or
Workers have been isolated and safely insulated
from online objects
When operations and maintenance request minimum
distance, provide trainings on safety measures and
safety devices for individuals and other preventive
measures identified in the health and safety
compliance plan. (Below is the recommended safety
distance for workers:
o 2-15 kV: 0.6 m
o 15.1-35kV: 0.71 m
o 72.6-121 kV: 1.01 m
- NPC
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
32
Mitigation Measures Implementati
on
responsibility
4.Safety measures
when working at
height
- Preventive and control measures include:
- Check the firmness of structures before starting
work
- Take anti-fall measures including climbing skills,
use of supporting devices and first aid toolkit
- Install supporting and anti-fall devices
- Safety bands will not be smaller than 16 mm,
two layers, and durable strength. Safety bands
will be replaced before any defect or crack is
detected or if is too old
- When working with tools at height, workers will
need an additional safely band (backup).
- Sign posts and other obstacles need to be
removed before starting work
- Use standard tool bag to carry tools and materials
to the height when working on pillars
- NPC
5. EMF impacts - Prevent or minimize exposure to EMF in the
working environment by developing and
implementing a EMF safety program with the
following components:
- Determination of potential exposure level
- Trainings for workers on how to identify their
exposure to EMF and its impacts
- Determination of safe areas in order to
differentiate those areas with higher EMF
impacts than the others where EMF impacts are
small enough not to be provided with mitigations
and minimize exposure to high EMF impact
areas
- The exposure detector for individuals will be
installed to give warning when exposure is below
the safety limit (for example, 50%). Action plans
for mitigating impacts includes taking turn to
work in high risk areas, and if necessary being
provided with protective devices.
- NPC
B. Site specific mitigation measures
Period Impacts/
influences
Mitigation Measures Implementati
on
responsibility
Construction Electricity cutting
off on the crossing
over line will
influence
production and
To avoid electricity cutting-off for a long
time when the 100kV line crossing over
the information line; line 35; 22; 0,4 kV;
scaffoldings must be used.
Before the setting up of the scaffoldings,
- NPC
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
33
Period Impacts/
influences
Mitigation Measures Implementati
on
responsibility
living activities in
the electricity
cutting- off area
the contractors should work directly with
the electricity control team of the
commune and the hamlet for permission
to cut off electricity during the setting up
of scaffoldings and avoid electricity
cutting-off during peak time. The
electricity control team of the commune
and the hamlet shall inform in advance the
electricity cutting-off time to the local
people to arrange their production plan
and living.
After the setting-up of scaffoldings,
electricity should be supplied again to the
line. Only after that, line extending could
be conducted.
Influence on the
information line
where the line is
crossing over
With the setting up of scaffoldings, the
line extending shall not be disconnected
or cause interferences to the transmission
line.
- NPC
Influence on
production,
agricultural crops
and forest tress
while the line is
extending, the
foundation is built
and the ports are
planted
Construction is made after the harvests
and construction progress should be
reduced.
Felling trees on the area to be taken back.
Appropriate compensation is made for
losses as specified in the Plan for
Resettlement of the project.
- NPC
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
34
6.2. Environmental Monitoring Plan
Table 6.2: Environmental monitoring plan is shown in the below table
Impact Monitored
parameter
Monitored
point
Monitoring
equipment
/method
Timing/
frequency of
monitoring
Responsibilit
y
Construction phase
I.
Vegetation
cover
clearance or
cutting
down trees
-Clearance
technique
- Disposal of
cut-down trees.
- Along the
transmission
line
- In a
centralized
place for
processing.
Observation -From
beginning to
the last
moment.
-Contractor
-Construction
supervising
consultant
I I. Rural
roads in the
project
region
- All heavy
tonnage
vehicles on the
local roads
- Along the
roads
Observation
and
consultation
with local
residents.
-Weekly basis
when material
is transported
to the region.
- Four months.
- Contractor,
-Construction
supervising
consultant
III. Surface
water
quality,
sedimentati
on and
erosion
- Not excavate
while it is
raining
- Not clear
plants
completely
- Surface
water near
the site.
Observation -During and
after heavy
rain
-Contractor,
-Construction
supervising
consultant
IV. Dust
and air
pollution
- Dust
concentration
in material
storage area
- Cover for
material during
transportation
process
- Areas with
excavation
foils and
material
storage
Observation -In presence of
strong winds
-Contractor,
-Construction
supervising
consultant
V. Noise
level
- Noise by
machinery
- Local
resident
response to
noise from the
construction
process
- The line
section
running over
residental
area
Consultatio
n with local
residents
-During
activities that
may result in
high noise
level;
Complaints by
local residents
-Contractor,
-Construction
supervising
consultant
VI. The
culture and
history
monuments
- The effects of
noise
-At the
construction
places close
to culture and
history
monuments
Observing
the local
residents
-During
construction,
the activities
emanate noise
-Contractors
-Construction
monitoring
consultant
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
35
Impact Monitored
parameter
Monitored
point
Monitoring
equipment
/method
Timing/
frequency of
monitoring
Responsibilit
y
VII.
Sanitation
situation at
the
construction
site,
including
the hygiene
of workers’
camps
-Garbage,
waste water at
the
construction
site and
workers’ tents
- If he tents
have been
supplied clean
water and had
sanitary
latrines
-At the tents Observing -Every week,
when official
acceptance of
work
-Contractors
-Construction
monitoring
consultant
VII. Safety
of workers
and local
presidents
- Accidents
happen
- At the sites,
local areas
- Consult,
Record the
constructio
n log of the
contractor
-Contractors
-Construction
monitoring
consultant
Operation phase
I. Maintain
and protect
the ROW
The height of
plants along
the ROW
Along the
ROW, houses
and trees
Prune trees
and ensure a
safe
distance for
the ROW
One month/
time
North High
Voltage grid
Company
II. Danger
due to
danger
-The intact
situation of
poles,
insulators,
protecting
devices of the
station
- At the pole
of the line
route, the
position of
the station
- Observing
and
assessing
3months/
time
-North high
voltage grid
Company
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
36
7. EMP IMPLEMENTATION ARRANGEMENT AND CAPACITY BUILDING
7.1 Responsibilities for Implementing the Environmental Management Plan
Non-compliance by the contractor could result in suspension of works, financial
penalties, or other penalties, as must be clearly spelled out in the EMP and in the contract.
Contractors are responsible for implementation of EMP. The responsibilities for
monitoring EMP implementation are typically shared between the contractor, the PMU, and
the Construction Supervision Consultant (CSC). The Contractor’s Work Plan should
incorporate the guidelines provided in the EMP created for the subproject. The designated
Technical Officer(s) and Safeguards Officer(s) of the PMU are responsible for supervising
the adherence to the agreed EMP by the selected contractor(s). The World Bank may
periodically supervise implementation activities of the subproject.
At a minimum, the contractor should prepare a monthly report on adherence to EMP
which should be submitted to the CSC and to the PMU. Subproject-specific or contract-
specific reporting requirements are described in the EMP. CSC is responsible for monitoring
overall environmental performance of the project and submit to PMUs quarterly monitoring
reports.
To ensure effective implementation of the EMP, the following actions will be carried out
during the implementation of the subproject:
7.1.1 During Detailed Design and Preparation of Bidding Contract Documents
During the detailed design and bidding invitation preparation, the project management
unit will be responsible for incorporate the EMP (mitigation measures, responsibilities of the
contractor) into the attached annexes in the bidding invitation and contract signed with the
contractor. Engineers taking charge of the detailed design will also refer to findings in the
EIA and EMP to ensure environmental issues will be looked at in the final design.
During the bidding invitation preparation and the contract, it is necessary to ensure the
contractor is fully informed of its responsibilities in implementing environmental mitigation
measures and its commitment to compliance.
7.1.2 During Construction Phase
PPMU will assign the Construction Supervising Consultant (CSC) and/or field engineer
to be responsible for supervision of safeguard performance of contractor on a daily basis. A
generic Terms of Reference (TOR) is provided in Annex 1. CSC and/or field engineers will
carry out, but not limited to, the following tasks:
- Before the commencement of the construction, confirm that all compensation for land
and facilities are provided and relocation and/or land acquisition/donation has been
completed.
- Closely supervise the implementation of safeguard measures throughout the
construction period.
- Confirm the compliance with the EMP and inspect for any damages caused by the
contractor. If necessary, prepare a minutes to ask the contractor to compensate or
rehabilitate as provisions of the contract. Contractor safeguard performance will be
included in the subproject progress report.
Role and responsibilities of parties in implementing EMP are summarized in the below table:
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
37
Table 7.1. Responsibility for EMP Implementation
Role Responsibility Organizatio
n
- Project
owner
- Take final responsibility with regards to the
management and implementation of project including
environmental compliance environmental
performance.
-North
Electricity
Corporation
- Environme
ntal officer
- Indicate specific responsibility and provide contact
details.
Environment
al officer of
project
- Project
manageme
nt and
implement
ation entity
Responsible for cooperating and managing the
implementation of project including providing guidance
and implementing the EMP:
- Develop plan and implement EMP activities during
construction.
- Cooperate with relevant stakeholders with regards to
environmental performance.
- Conduct internal supervision and independent audit.
- Supervise and provide budget for monitoring
activities.
- Report environmental information to relevant
stakeholders.
PMU
- Project
operation
entity
- Operating the project including environmental
management and supervision during operation phase.
North High
Voltage Grid
Company
- Contractor
supervisor
- Support the PMU in supervising project operations
with regards to environmental impacts mitigation
according to measures described in the EMP and keep
in touch with local residents.
Construction
supervising
consultant
hired by the
PMU
- Contractor Constructing and complying with technical requirements of
the EMP, including:
- Taking mitigation measures to minimize negative
impacts as described in the EMP.
- Communicating with local residents and taking action
to prevent environmental and social interruptions in
the project region during construction.
- Ensuring at least one officer supervises compliance to
EMP during construction.
- Ensuring all construction activities are given necessary
approvals from relevant authorities.
- Ensuring workers and officers understand their
responsibilities and procedures in environmental
management.
- Reporting to the construction supervising consultant
on difficulties and solutions.
- Reporting to local authorities and PMU and
cooperating with relevant agencies to address any
issues.
Construction
supervising
consultant
hired by the
PMU
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
38
7.2 Capacity Building for EMP Implementation
Training plan in the coming time includes:
EVN’s training program: Internal training courses on the implementation of
environmental management work at site, the preparation of reports on the Project
environmental issues as a part of half-yearly and annual reports. The program will
also provide training on environmental impact mitigation measures which
unexpectedly occur and differ with forecasts stated in the EMP report.
Northern Power Corporation’s training program: NPC’s training program
provided to the local power company’s staff and some local people is about:
Training on safety work: Periodically training on the safety work and power
network maintenance;
Supervision method and report EMP implementation to stakeholders in the
province and the districts where the Project is located. The training work will also
provide guidance’s on the coordination with the people in the environmental
management work;
Training on environmental management and waste management:
Table 7.2 Estimates of capacity building for implementing EMP
No
.
Training
contents
Training
subjects
Educato
r
Implementatio
n period Cost estimate
1 Annual
training of
EVN for all
of its
subsidiaries
Officials
of CPC,
PMU-CPC
EVN 2 days
2 persons x 2 days x
2.500,000
VND/person/day
=10,000,000 VND
(integrated into operating
cost of EVN)
2 Training and
exchanging
experience in
implementin
g
environment
management
plan and the
Environment
al
Management
Plan
Officials
of CPC,
PMU-CPC
EVN,
WB
2 days
2 persons x 2 days x
3,000,000
VND/person/day =
12,000,000 VND
(Incorporated in
operating costs of EVN)
3 Training on
implementin
g the
Environment
al
Management
Plan
Officials
of PMB-
CPC,
communes/
towns
where
project is
launched
and
EVN,
CPC
2 days
05 persons x 2 days x
2,000,000
VND/person/day =
20,000,000VND(Includin
g: 02 PMUofficials, 01
official of construction
unit, 02 officials of
communes to be
participated)
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
39
No
.
Training
contents
Training
subjects
Educato
r
Implementatio
n period Cost estimate
constructio
n agency
4 NPC’s
training on
safety
(regularly
conducted by
the PC)
Officials of
PMU-CPC
and
operation
manageme
nt units
CPC 2 days
04 persons x 2 days x
300,000 VND/person/day
= 2,400,000 VND
(Included in operating
costs of provincial PC:
02 project officials and
02 officials of operation
management unit to be
participated)
TOTAL 44,400,000 VND
7.3 Reporting procedure
Responsibility and frequency of reporting on EMP implementation are shown
in the below table.
N
o.
Report by Submitted to Frequency of reporting
1 By contractor to project owner PMU Once prior to starting
construction afterwards
every one month.
2 Construction supervisor (cum
environmental monitor)
PMU Monthly
3 Community supervisor (if any) MPU If any complaint
4 PMU EVN Quarterly
5 EVN WB Biannually
7.4 Estimated cost for implementing the EMP
Estimated cost for (i) implementing main mitigation measures (ii) and trainings:
No. Description Construction phase Operation phase
01 Mitigation measures. Under the contract
with the contractor
Under the
production cost of
province electricity
02 Environmental monitoring
during construction phase
(incorporated into the cost
of construction
supervising consultant).
Under the cost for
PMU operation
(Supervising
consultant will
exercise
independent
monitoring)
Under the cost of
the project owner
operation
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
40
03 Training on
environmental
management by project
investor for local officers,
contractor and supervising
consultant.
44,400,000 VND Capacity building
need assessment
(trainings,
workshops and
study tours)
TOTAL COST:
44,400,000 VND
*
The cost for mitigation measures during the construction phase and
environmental monitoring by the supervising consultant will be included in the
construction supervising contract.
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
41
8. PUBLIC CONSULTATION AND DISCLOSURE OF INFORMATION In the subproject preparation phase (the year of 2011), the following five activities
were carried out:
Activity 1: Surveying the site, working with the local authorities to discuss the route
and the substation locations.
Activity 2: Surveying the site and preparing the EPC and the EMP reports.
Activity 3: Conducting public consultation on the subproject.
From Octorber 1st 2011 to Octorber 17, 2011, a meeting with local residents in 13
communes was organized in order to consult with the public on the EMP, the representatives
of the Subproject Owner were also involved the following contents:
- Describing the subproject, the route, thesubstation locations, and the necessity for
the subproject;
- The potential impacts on the environment and communities;
-The measures to mitigate environmental impacts.
Participants: Participants of the Commune People Committee, Farmer Association, Women
Association , and other public organizations, hamlet chiefs, representatives of project’s
affected households, and consulting agency.
Summary of comments from the participants
In general, most of opinions of the local authorities and people were supportive of the
subproject. Similarly, most participants agreed that the impact that caused by the project
to the environment will not be severe due to the nature of the impact is slight and even
the reasonable scope of project. Furthermore, they also emphasized that the benefits will
clearly be able to compensate for the negative effects.
Most of opinions of the local authorities and people were supportive of the subproject.
The subproject would soon be done for people enjoying its benefits.
People care about the impact of electrical field intensity on their life.
Impact of dust and noise on their life
Measures for rehabilitating fields after using them as temporary roads for construction
Construction safety and electrical safety of works in rain, storm.
When the project construction is finished?
The public consultation minutes is included in Appendix 6.
All the involved issues as well as suggestion of the local people that recognized by
the consultant and the investor, will be considered in the sub-project design and in the EMP
implementation phase.
Activity 4: Review and correct the EMP in accordance with the
comments. Continuing to receive feedback from the affected households. To collect opinions
of the people to complete the environmental impact mitigation measures in the EPC and
EMP.
Activity 5:Disclosure of the EMP
The EMP in Vietnamese will be disclosed at the offices of 13 People Committees of
the 13 subproject comunes, and People Committee offices of Do Luong and Yen Thanh
districts, Nghe An Province.
The EMP copies in Vietnamese and English will be sent to the Vietnam Development
Information Center at 63 Ly Thai To street, Hanoi City for disclosure of information.
The EMP copies in English will also be disclosed in the InfoShop of the World Bank
in Washington DC.
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
42
REFERENCES
1 The project’s compensation plan
2 Source book of the World Bank on environmental impact assessment
3 Statistical Yearbook 2010
4 The project investment report
5 Draft of Safety Policy Framework on environmental and distribution
efficiency project
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
43
APPENDIX:
Appendix 1: Consultation terms on monitoring the environmental management plans
for the construction supervision consultancy
Appendix 2: Example of the EMP performance monitoring reports (applied to
monthly construction monitoring consultancy which be sent to PMU);
Appendix 3: Example of the EMP performance monitoring reports (applied to the
contractor's report);
Appendix 4: The project environment license (The certificate of project
environmental protection commitment)
Appendix 5: The local map and current images of the project (attached)
Appendix 6: The information of the public consultation (attached)
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
44
ANNEX 1
---------------
TERMS OF REFERENCES FOR MONITORING OF EMP IMPLEMENTATION FOR
CONSTRUCTION SUPERVISING CONSULTANT
Background
The construction supervising consultant will deliver technical services (“Services”) to ensure
efficient implementation of the EMP for the project.
Scope of services:
Services provided by the supervising consultant will include reviewing and monitoring of
construction activities to ensure mitigation measures described in the EMP for the project are
correctly complied with and negative environmental impacts are minimized.
On behalf of the PMU, supervising consultant undertakes the following duties:
- Conduct frequent field inspection;
- Review the implementation of environmental protection measures described in the EMP
and contract documentation;
- Review the effectiveness of the mitigation measures and environmental performance of
the project;
- If necessary, validate the acceptability of construction methods with regards to
environmental compliance (for temporary and permanent items), relevant design plans
and other submitted documents. If necessary, the supervising consultant will seek for and
recommend methods with less environmental impacts with consultation with the design
consultant and the PMU;
- Validate inspection results with regards to any non-conformance to environmental
performance and effectiveness of any countermeasures;
- Provide audit results for the leading engineer of the contractor in accordance with non-
conformance handling procedure described in the EMP;
- Direct the contractor to take corrective actions within a specific time period and exercise
additional monitoring if necessary, as per the requirements of the contract in case of non-
conformance and complaints;
- Direct the contractor to take actions to mitigate impacts and comply with the EMP in case
non-conformance is found;
- Direct the contractor to stop any activity resulting negative impacts and/or in case the
contractor does not fulfill requirements of the EMP, to take corrective actions.
- For contracts that need Site Environmental Management Plan (SEMP), the
supervising consultant will conduct a final review and approve all environmental plans at
the site that may affect environment. This work includes but not limited to: dredging
areas, material quarries and dumping areas and worker houses. The supervising consultant
will review and approve such SEMP submitted by the contractor. If such plans are found
non-compliant to the EMP, EPC or RAP, the supervising consultant will work with the
PMU and contractor for a proper solution.
- Complaint handling: Complaints from local residents will be collected by site officer of
the contractor, which may include violations to noise level, dust concentration and traffic
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
45
safety requirements. The lead consultant of the contractor and the supervising consultant
will address and work out a final solution organizes all such complaints. The supervising
consultant will provide a list of these complaints and confirm they have been properly
handled by the contractor in the same way with issued identified during site inspection.
- Confirmation of monthly payment: The supervising consultant will confirm monthly
payment for environment related activities undertaken by the contractor.
- Report: The supervising consultant will make the following reports in English:
o Report twice a week on non-conformances
o Monthly summary report will include issues and findings from the reviewing
and monitoring of construction activities
o At the end of project, the supervising consultant will make a final summary
report on findings from their work, number of violations, and solutions, etc. as
well as provide consultancy and guidance on how to implement such duties in
future.
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
46
ANNEX 2
--------------------
Report template for monitoring of EMP implementation
(Used for report by supervising consultant to PMU)
Project name:
Project location: Province: District:
Commune/Town:
Supervising consultant:......Full name Date of report:……………………
No. Parameter
Assessment of
comments by
supervising
consultant and
community
Comment/
Recommenda
tion
Construction phase
1 Water turbidity and soil erosion
2 Noise level at the site and nearby
residential area
3 Dust concentration
4 Solid waste and site cleaning after
construction
5 Conflict between workers and local
residents
6 Disease spreading
7 Hygiene condition and safety for workers
8 Local traffic interruption
9 Road damage
10 Safety measure application
11 Material management
12 Remained soil and rock management
13 Evidences about loss to biodiversity (if
any)
14 Evidences about loss to cultural and
historical sites
15 Other environmental issues (if any)
….
Operation phase
16 Transmission line lobby maintenance
17 1. Health and safety for operation
workers and local residents
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
47
ANNEX 3
--------------------
Report template for monitoring of EMP implementation
(Used for reports by contractor)
Project name:
Project location:
Contractor name:
Initial or monthly report:
Date of report:
No. Impact Mitigation
measure taken Comment
Construction phase
1 Surface water pollution
2 Noise and vibration level
3 Soil erosion
4 Air pollution
5 Impacts on agriculture land due to
temporary land acquisition
6 Local traffic interruptions
7 Existing road damage
8 Solid waste from excavation
9 Remained soil management
10 Environmental impacts by workers
11 Conflict between workers and local
residents
12 Disease spreading between workers
and local residents
13 Health and safety
14 …..
Reported by :
Title :
Address :
Telephone :
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
48
ANNEX 4: Project Environmental License
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
49
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
50
ANNEX 5: Project map and some photos about the transmission line routes
a. Project map
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
51
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
52
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
53
This position will build Yen Thanh 110kV substation .
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
54
The line in Tan Son communes
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
55
ANNEX 6:
a. Summary of comments from stakeholder meetings
N
o.
Location Date Wom
en/pa
rticip
ant
Comment Response by project
owner
Venue of
Xuan Son
commune
people’s
committee
Do luong
district
6/10/2011 2/17 - People care about the
impact of electrical field
intensity on their life.
- Impact of dust and noise
on their life
- Measures for rehabilitating
fields after using them as
temporary roads for
construction
- Construction safety and
electrical safety of works in
rain, storm.
- When the project
construction is finished?
-Present briefly the
project information,
resettlement plan and
environment
management plan
- The construction
contractor will
implement resettlement
plan and environment
management plan to
guarantee the stability
and safety of people
during the project
construction
- Construction time up
to: 1/2013
Venue of
Minh Son
commune
people’s
committee
Do luong
district
8:30 am
11/10/ 2011
3/20 - People care about the
impact of electrical field
intensity on their life.
- Impact of dust and noise
on their life
- Measures for rehabilitating
fields after using them as
temporary roads for
construction
- Construction safety and
electrical safety of works in
rain, storm.
- When the project
construction is finished?
-Present briefly the
project information,
resettlement plan and
environment
management plan
- The construction
contractor will
implement resettlement
plan and environment
management plan to
guarantee the stability
and safety of people
during the project
construction
- Construction time up
to: 1/2013
Venue of
Tan Son
commune
people’s
committee
Do luong
district
2:30 pm
14/10/ 2011
3/20 - People care about the
impact of electrical field
intensity on their life.
- Impact of dust and noise
on their life
- Measures for rehabilitating
fields after using them as
-Present briefly the
project information,
resettlement plan and
environment
management plan
- The construction
contractor will
implement resettlement
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
56
N
o.
Location Date Wom
en/pa
rticip
ant
Comment Response by project
owner
temporary roads for
construction
- Construction safety and
electrical safety of works in
rain, storm.
- When the project
construction is finished?
plan and environment
management plan to
guarantee the stability
and safety of people
during the project
construction
- Construction time up
to: 1/2013
Venue of
Lac Son
commune
people’s
committee
Do luong
district
8:30 am
13/10/ 2011
4/22 - People care about the
impact of electrical field
intensity on their life.
- Impact of dust and noise
on their life
- Measures for rehabilitating
fields after using them as
temporary roads for
construction
- Construction safety and
electrical safety of works in
rain, storm.
- When the project
construction is finished?
-Present briefly the
project information,
resettlement plan and
environment
management plan
- The construction
contractor will
implement resettlement
plan and environment
management plan to
guarantee the stability
and safety of people
during the project
construction
- Construction time up
to: 1/2013
Venue of
Thinh Son
commune
people’s
committee
Do luong
district
8:30 am
04/10/ 2011
2/20 - People care about the
impact of electrical field
intensity on their life.
- Impact of dust and noise
on their life
- Measures for rehabilitating
fields after using them as
temporary roads for
construction
- Construction safety and
electrical safety of works in
rain, storm.
- When the project
construction is finished?
-Present briefly the
project information,
resettlement plan and
environment
management plan
- The construction
contractor will
implement resettlement
plan and environment
management plan to
guarantee the stability
and safety of people
during the project
construction
- Construction time up
to: 1/2013
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
57
N
o.
Location Date Wom
en/pa
rticip
ant
Comment Response by project
owner
Venue of
Hoa Son
commune
people’s
committee
Do luong
district
2:30 pm
17/10/ 2011
3/30 - People care about the
impact of electrical field
intensity on their life.
- Impact of dust and noise
on their life
- Measures for rehabilitating
fields after using them as
temporary roads for
construction
- Construction safety and
electrical safety of works in
rain, storm.
- When the project
construction is finished?
-Present briefly the
project information,
resettlement plan and
environment
management plan
- The construction
contractor will
implement resettlement
plan and environment
management plan to
guarantee the stability
and safety of people
during the project
construction
- Construction time up
to: 1/2013
Venue of
Thai Son
commune
people’s
committee
Do luong
district
8:30 am
12/10/ 2011
3/23 - People care about the
impact of electrical field
intensity on their life.
- Impact of dust and noise
on their life
- Measures for rehabilitating
fields after using them as
temporary roads for
construction
- Construction safety and
electrical safety of works in
rain, storm.
- When the project
construction is finished?
-Present briefly the
project information,
resettlement plan and
environment
management plan
- The construction
contractor will
implement resettlement
plan and environment
management plan to
guarantee the stability
and safety of people
during the project
construction
- Construction time up
to: 1/2013
Venue of
My Thanh
commune
people’s
committee
Yen Thanh
district
2:30 pm
06/10/ 2011
3/23 - People care about the
impact of electrical field
intensity on their life.
- Impact of dust and noise
on their life
- Measures for rehabilitating
fields after using them as
temporary roads for
construction
- Construction safety and
-Present briefly the
project information,
resettlement plan and
environment
management plan
- The construction
contractor will
implement resettlement
plan and environment
management plan to
guarantee the stability
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
58
N
o.
Location Date Wom
en/pa
rticip
ant
Comment Response by project
owner
electrical safety of works in
rain, storm.
- When the project
construction is finished?
and safety of people
during the project
construction
- Construction time up
to: 1/2013
Venue of
Cong
Thanh
commune
people’s
committee
Yen Thanh
district
8:30 am
10/10/ 2011
2/26 - People care about the
impact of electrical field
intensity on their life.
- Impact of dust and noise
on their life
- Measures for rehabilitating
fields after using them as
temporary roads for
construction
- Construction safety and
electrical safety of works in
rain, storm.
- When the project
construction is finished?
-Present briefly the
project information,
resettlement plan and
environment
management plan
- The construction
contractor will
implement resettlement
plan and environment
management plan to
guarantee the stability
and safety of people
during the project
construction
- Construction time up
to: 1/2013
Venue of
Khanh
Thanh
commune
people’s
committee
Yen Thanh
district
2:30 pm
02/10/ 2011
2/21 - People care about the
impact of electrical field
intensity on their life.
- Impact of dust and noise
on their life
- Measures for rehabilitating
fields after using them as
temporary roads for
construction
- Construction safety and
electrical safety of works in
rain, storm.
- When the project
construction is finished?
-Present briefly the
project information,
resettlement plan and
environment
management plan
- The construction
contractor will
implement resettlement
plan and environment
management plan to
guarantee the stability
and safety of people
during the project
construction
- Construction time up
to: 1/2013
Venue of
Lien
Thanh
commune
people’s
2:30 pm
11/10/ 2011
2/24 - People care about the
impact of electrical field
intensity on their life.
- Impact of dust and noise
-Present briefly the
project information,
resettlement plan and
environment
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
59
N
o.
Location Date Wom
en/pa
rticip
ant
Comment Response by project
owner
committee
Yen Thanh
district
on their life
- Measures for rehabilitating
fields after using them as
temporary roads for
construction
- Construction safety and
electrical safety of works in
rain, storm.
- When the project
construction is finished?
management plan
- The construction
contractor will
implement resettlement
plan and environment
management plan to
guarantee the stability
and safety of people
during the project
construction
- Construction time up
to: 1/2013
Venue of
Nam
Thanh
commune
people’s
committee
Yen Thanh
district
2:30 pm
10/10/ 2011
2/23 - People care about the
impact of electrical field
intensity on their life.
- Impact of dust and noise
on their life
- Measures for rehabilitating
fields after using them as
temporary roads for
construction
- Construction safety and
electrical safety of works in
rain, storm.
- When the project
construction is finished?
-Present briefly the
project information,
resettlement plan and
environment
management plan
- The construction
contractor will
implement resettlement
plan and environment
management plan to
guarantee the stability
and safety of people
during the project
construction
- Construction time up
to: 1/2013
Venue of
Bac
Thanh
commune
people’s
committee
Yen Thanh
district
2:30 pm
3/10/ 2011
1/36 - People care about the
impact of electrical field
intensity on their life.
- Impact of dust and noise
on their life
- Measures for rehabilitating
fields after using them as
temporary roads for
construction
- Construction safety and
electrical safety of works in
rain, storm.
- When the project
-Present briefly the
project information,
resettlement plan and
environment
management plan
- The construction
contractor will
implement resettlement
plan and environment
management plan to
guarantee the stability
and safety of people
during the project
construction
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
60
N
o.
Location Date Wom
en/pa
rticip
ant
Comment Response by project
owner
construction is finished?
- Construction time up
to: 1/2013
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
61
.
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
62
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
63
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
64
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
65
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
66
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
67
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
68
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
69
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
70
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
71
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
72
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
73
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
74
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
75
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
76
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
77
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
78
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
79
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
80
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
81
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
82
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
83
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”
DPT CONSULTANT JOINT STOCK COMPANY
84
Distribution Efficiency Project, Subproject: “Yen Thanh 110KV Substation”