Minnesota Business Venture Minnesota Business Venture “Beyond Business”
No.75 Design and Evaluation of the Joint Venture...
Transcript of No.75 Design and Evaluation of the Joint Venture...
1
No.75
Design and Evaluation
of the Joint Venture Formation
in EPC Projects
Nobuaki Ishii, Kanagawa University, Japan
Yuichi Takano, University of Tsukuba, Japan
Masaaki Muraki, Tokyo Institute of Technology, Japan
December 8, 2018
APIEMS2018
Proceedings of the Asia Pacific Industrial Engineering & Management Systems Conference 2018
2
① Background & Objectives
② Related work
③ Design Method for Competitive Joint
Venture Formation
④ Mathematical Model in Design Method
⑤ Evaluation
⑥ Conclusions
Overview of the Presentation
3
EPC (Engineering-Procurement-Construction) Project
• Contractors design and build unique
products based on the client requirements.
• Contractor has a solo responsibility for the
project as a lump-sum contract.
Background About EPC Project
Typical Examples of EPC Project: Construction, Civil engineering,
Plant Engineering, Information System Development, etc.
4
Background About EPC Project
EPC contractors have been suffered
unstable business results, so far.
Contractors’ unstable business results
would also have
harmful effects on client’s business.
・Additional cost ・Delay of project delivery
(800,000)
(600,000)
(400,000)
(200,000)
0
200,000
400,000
600,000
800,000
1,000,000
1972 1977 1982 1987 1992 1997 2002 2007 2012 2017
年度
受注 売上 税引き前利益(百万円×10)
5
Background
Year
Example <Financial results of a world class contractor>
Accepted
orderSales
Profit (×10-1)
[MM¥]
About EPC Project
In EPC, contractor’s business performance is highly affected by the
market &competitors‘ conditions.
Stable profit is critical for any contractor to improve sustainability.
Unstable Sales & Profits
6
Background
Why so unstable?
Risks of cost & time affect profitability,
especially, in complex & large-scale EPC
projects.
“Reduce risks of project ” is critical for
the contractor to gain stable profit.
Risks & Profits
One solution:
The joint venture contract It has become more common among EPC contractors.
More than one contractor works on a project in the joint venture.
7
Background
Why Joint venture can reduce risks:
Each partner in joint venture needs not carry
out all the works in the project by sharing
works within partners.
Each partner only need to carry out the
works having specialty.
Risks & Profits
Risks of cost & time could be reduced by the
complementary effects within joint venture
partners.
8
Background
However,
Partners in the joint venture encounter many
challenges to gain advantages by forming a
joint venture.
<Examples>
Increased managerial costs,
Hard negotiations of profit & risk sharing
among partners, and so on,
Challenges of Joint Venture
A method to design a competitive joint venture
formation is necessary.
9
Research Objectives
Based on the background;
Develop a method to design a
competitive joint venture formation;
Reduce project cost and deficit risks,
by maximizing the complementary effects
within joint venture partners.
Related work
11
Most studies on joint ventures have focused on
complementarity in repetitive businesses,
Literature focusing on project-based business
has been limited so far.
Especially, issues for organizing competitive joint venture
formation in EPC projects have not been studied well by
either industry and academia, although expectations for
joint venture contracts have increased among EPC
contractors.
This paper focuses on the design of joint venture
formation in EPC projects
as a new area of joint venture studies.
Overview of design method
13
The design method consists of four steps.
Estimated costs of WP by each partner
WP set conditions in each partner
Client requirement
s Create 2D-
WBS
Estimate cost
of WP (average
& variance) in
2D-WBS
Search
optimal
formation
Mathematical model for
optimization
Constraint of maximum projectcost
Cost data of each partner
2D-WBSsCreate 2D-WBS of
each partner
2D-WBS
Cost estimation
models
Joint venture formation
1st step
2nd step
3rd step
4th step
Overview of design method
14
1st Step:
Creates a 2D-WBS (Work Breakdown structure)
based on the project scope determined by the
client requirements,
The 2D-WBS:
Consists of a process WBS and functional
WBS,
Shows the association between the WPs of the
project and the potential partners carrying out
the WPs.
Indicates the work process in the
EPC project, such as design,
procurement, and construction
processes.
Shows the work breakdown to
deliver the results of the project.
C5
C4
C3
C2
D2
D1
C1
B1
B2
A
D1 D2 P1 P2 S1 S2 S3
Design Constriction
Process WBS
Procurement
Functional WBS
Each cell shows Work Package (WP) to
be done by partner
Work
Process
WPC3,P1
WPC2,S1
Two-Dimensional Work Breakdown Structure
(2D-WBS).
15
Final deliverable is A,
and the works to deliver A is broken down as C2 via C5,
and D1 and D2.
WP of work C3 in
process P1
Each joint venture partner has the same 2D-WBS,
although costs and those variances to carry out the WPs
would be different for each partner.
Tasks
Resources
Cost
Schedule
PartnerWPC3,S2
The 2D-WBS is used as a platform of joint
venture design in Steps 2 to 4.
Overview of design method
16
2nd Step:
Cost and MH data of each WP in the 2D-WBS is
estimated by each partner.
Cost estimation model & cost data would be
different for each partner,
Estimated costs & cost estimation accuracy can
be different for each partner. AACE cost model
Uses the data of the cost estimation accuracy to
evaluate the project deficit risk.
Cost estimation accuracy is defined as the percentage of
deviation from the actual cost.
Overview of design method
17
3rd Step:
2D-WBS of each partner is created by putting the
cost and MH data of WPs into the 2D-WBS.
Total N 2D-WBSs are created if the number of
partners is N.
4th Step:
Joint venture formation is searched based on the
project data in the 2D-WBSs by using the
mathematical model. The model finds the combinations of WPs and partners
who carry out the WPs so that the sum of cost variances
of WPs is minimized under the constraint of the maximum
project cost like a portfolio optimization problem.
18
Mathematical Model in Detail
Minimize
𝑛=1
𝑁
𝑤=1
𝑊
𝑝=1
𝑃
𝑎𝑤,𝑝𝑛 𝑑𝑐𝑣𝑤,𝑝
𝑛 (1)
Subject to𝑎𝑤,𝑝𝑛 ={0, 1} (2)
𝑛=1
𝑁
𝑎𝑤,𝑝𝑛 = 1 (𝑤 = 1~𝑊, 𝑝 = 1~𝑃) (3)
𝑛=1
𝑁
𝑤=1
𝑊
𝑝=1
𝑃
𝑎𝑤,𝑝𝑛 𝑑𝑐𝑤,𝑝
𝑛 +
𝑛=1
𝑁
(
𝑤=1
𝑊
𝑝=1
𝑃
𝑎𝑤,𝑝𝑛 𝑖𝑑𝑐𝑤,𝑝
𝑛 )𝑠𝑐 < 𝑡𝑐𝑜 (4)
𝑤=1
𝑊
𝑝=1
𝑃
𝑎𝑤,𝑝𝑛 𝑚ℎ𝑤,𝑝
𝑛 ≤ 𝐻𝑀𝑛 (𝑛 = 1~𝑁) (5)
If WPw,p and WPw’,p’ must be carried out by the single
partner n for all wand p.
𝑎𝑤,𝑝𝑛 = 𝑎𝑤′,𝑝′
𝑛 (𝑛 = 1~𝑁)
(6)
Minimizes the sum of
the variance of WPs’
costs.
Decision variable of the
formation of JV.
Constraints of project costs.
Constraints of MH of each
partner.
A set of WPs each partner
intends to carry out.
20
<Objectives>
Evaluate the effectiveness of the design
method of joint venture formation by
examining the expected profits of EPC
projects,
with the result of improved cost estimation
accuracy and/or the reduced project cost .
<Evaluation method>
Simulation model of the competitive bidding
is used for evaluation.
Numerical Examples
22
Simulation Model --- Two modules
① Competitivebiddingmodule
Estimate costs
and bid prices
Expected orders & profits
Estimated costs & markups
(Bidding price)
Bidding price=Estimated cost +Markup.
② Bid evaluation
module
Evaluate bidding &
expected profits
Search the bidding price maximizes the expected
profits.
Consists of two modules.
Repeated
24
Simulation scenarios
Scenario OrganizationCost
estimationaccuracy
Cost reduction
S0 One’s own companyCompetitors +/-5% none
S1Joint venture
+/-5%0~5% of S0 cost
Competitors none
S2Joint venture +/-3% 0~5% of S0 cost
Competitors +/-5% none
S0 (Base scenario): No joint ventures.
S1: Reduced project cost by JV.
S2: Improved cost estimation accuracy & the reduced
project cost by JV.
Cost estimation accuracy = the percentage representation of the coefficient of variance, such as 5% of the actual cost.
It is obtained by dividing the standard deviation of the estimated cost by the actual cost. Namely, a lower deviation means higher
estimation accuracy.
25
Simulation data
Number of simulation runs SR 5
Number of simulation years N 5
Number of competitors
S0 5
S1 and S2 4
Number of orders in each simulation year 10
Probability function of project costNormal
distribution
Markup in competitor j: 𝑟𝑚𝑘𝑖𝑗 Random variable
between 9~11%
Actual project cost 100 [MM$/project]
Target volume of accepted orders in
each simulation year
Joint venture 500 [MM$/year]
one’s own company
250 [MM$/year]
(MM: Million)
0
5
10
15
20
25
30
35
40
0 1 2 3 4 5
S0 S1 S2
[MM$/year]
Project cost reduction in joint venture [%]27
The expected profits in the joint venture increasesaccording to the reduction of the project cost
The improved cost estimation accuracy by the effectof joint venture formation increases the expectedprofit.
Cost estimation accuracy: +/-3%
Cost estimation accuracy: +/-5%
Results of Simulation Experiments
Expected profits of accepted orders
Improved profits by the reduced No.of competitors
Improved
profits by
accurate cost
estimation
102
103
104
105
106
107
108
0 1 2 3 4 5
S0 S1 S2
[MM$/order]
Project cost reduction in joint venture [%]28
The average bid prices in the joint venture slightly
decreased according to the project cost reduction.
The joint venture can improve contractors’ profits as
well as reduce the investment costs of clients.
Results of Simulation Experiments
Average bid price of accepted orders
Reduction of client's
investment cost
30
Conclusions
①Develop a design method & a mathematical
model to identify a joint venture formation.
Minimizes the cost estimation errors associated with the
deficit risk of projects under the constraints on the
maximum expected project costs and MH.
Consider the complementary effects of the joint venture
and the managerial cost among contractors within the
formation.
②Propose the 2D-WBS as a platform to indicate
project data of each partner organizing the
joint venture formation.
31
Conclusions
③Findings via simulation experiments.
Joint venture can reduce deficit risks and
improve the expected profits
Joint venture can also reduce client's
investment cost
32
Conclusions
Further research
① The design method should consider more facets of
the joint venture,
Such as, knowledge creation, the presence of competition between joint
venture partners, and so on, to evaluate the diverse aspects of joint
ventures.
② The mathematical model should be expanded so
that it can consider the bid conditions and bid
strategy of each competitor,
③ In the simulation model of the competitive bidding,
the bid performance of each competitors should be
evaluated not as a set of competitors.