New Bridges with new Technology

64
NVF Annual Bridge Conference 2014 New Bridges with new Technology 3-4th of September 2014 Reykjavik Iceland Tuning the cable-stayed bridges harp Pedestrian bridges over Elliðaár Sigurður Ingi Ólafsson Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson 1 31.8.2014

Transcript of New Bridges with new Technology

Page 1: New Bridges with new Technology

NVF Annual Bridge Conference 2014 New Bridges with new Technology 3-4th of September 2014 Reykjavik Iceland

Tuning the cable-stayed bridges harp

Pedestrian bridges over Elliðaár

Sigurður Ingi Ólafsson

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson 1 31.8.2014

Page 2: New Bridges with new Technology

The geography

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

2

Geirsnef

31.8.2014

Page 3: New Bridges with new Technology

Elliðaárvogur 1963 Landfill has just started

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

3 31.8.2014

Page 4: New Bridges with new Technology

A picture which shows the seabed and outlines the landfill.

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

4 31.8.2014

Page 5: New Bridges with new Technology

Elliðaárvogur 2012

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

5 31.8.2014

Page 6: New Bridges with new Technology

Elliðaárvogur 2014

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

6 31.8.2014

Page 7: New Bridges with new Technology

Assumptions of the bridges

• When the City Council of Reykjavik approved a new cycling plan in 2010 a network of biking in the city was laid.

• Part of the plan was a connection with a new pedestrian and cycle route across the north end of Elliðaárvogur on Geirsnef.

• Two new bridges were to be built.

• Location of the bridges would be the northern Geirsnef where the river Elliðaár expire in two branches.

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

7 31.8.2014

Page 8: New Bridges with new Technology

On a bike to work 2012 A map with pedestrian and cycle routes

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

8 31.8.2014

Page 9: New Bridges with new Technology

On a bike to work 2012

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

9

A new pedestrian and cycle route

31.8.2014

Page 10: New Bridges with new Technology

The client and owners:

The City of Reykjavik & The Icelandic Road and Coastal Administration

The design team: Role Firm In responce

Arcitects: Teiknistofan TRÖÐ Hans Olav Andersen

Structural Design: Teiknistofan NÝBÝLI ehf. Sigurður Ingi Ólafsson

Electric lighting: Vst. Jóhanns Indriðasonar Arnþór Þórðarson

Land design Snøhetta (Oslo) Jenny B. Osuldsen

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

10 31.8.2014

Page 11: New Bridges with new Technology

The crossing It was required that no foundations would be between existing river banks and that the river banks were unchanged after bridge construction

The east river Elliðaá West river (in low tide)

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

11 31.8.2014

Page 12: New Bridges with new Technology

• Choosing a structural system for the bridges is the start. The structural building block of the Tetrahedon is the orginal idea of our proposal. This idea we never left.

Tetrahedron A block of tetrahedrons

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

12 31.8.2014

Page 13: New Bridges with new Technology

Example of an early stage study. In all design work we used 3D BIM software.

A study which was not presented No foundations allowed between existing river banks

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

13 31.8.2014

Page 14: New Bridges with new Technology

The idea behind the structural solution

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

14 31.8.2014

Page 15: New Bridges with new Technology

Some changes made to make traffic easier

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

15

Tension bars

31.8.2014

Page 16: New Bridges with new Technology

The bridge deck connects the horizontal tension rods.

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

16 31.8.2014

Page 17: New Bridges with new Technology

Stactions in floor plan extended (red lines)

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

17 31.8.2014

Page 18: New Bridges with new Technology

The final proposal – east bridge 3D model in an actual picture

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

18 31.8.2014

Page 19: New Bridges with new Technology

Load on bridge deck: Eurocode 1: Actions on structures –

Part 2: Traffic loads on bridges

5.3.2 Load Models

5.3.2.1 Uniformly distributed load.

• Load Model 4 (crowd loading) Defined in 4.3.5, qfk = 5 kN/m2

5.6.3 Accidental presence of vehicles on the bridge

31.8.2014 Tuning the Cable-stayed bridges harp

Sigurður Ingi Ólafsson 19

JCB4CX 81 kN

Page 20: New Bridges with new Technology

Solutions on bridge deck valuated.

Hollow core with in situ topping Steel Deck

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

20 31.8.2014

Page 21: New Bridges with new Technology

Top view. The bridges wear a long axes mirror of each other

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

21 1.9.2014

Page 22: New Bridges with new Technology

Structural calculations: FEM test for all loadcases checked for entire plate construction.

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

22 31.8.2014

Page 23: New Bridges with new Technology

Axial forces Profile stress

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

23 31.8.2014

Page 24: New Bridges with new Technology

Structural steel design –Structural detailing

It is all too common to separate thease two design parts.

• Design documents for a steel constructions:

1. Material and assemly lists

2. General arrangement drawings 39 drawings (each bridge)

3. Assembly drawings 24 drawings (each bridge)

4. Single part drawings 175 drawings (mostly A4) for steel production

Parts : 960

Bolts : 175

Components : 92

Assemblies : 324

Drawings : 243

Welds : 747

Fittings : 31

Cuts : 467

Reinforcing bars : 714

Guardrail is not included:

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

24 31.8.2014

Page 25: New Bridges with new Technology

Modelling

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

25 31.8.2014

Page 26: New Bridges with new Technology

Detailing

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

26 31.8.2014

Page 27: New Bridges with new Technology

Top of tetrahedron (transparent)

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

27 31.8.2014

Page 28: New Bridges with new Technology

Top of one of shorter legs.

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

28 31.8.2014

Page 29: New Bridges with new Technology

The only on site welding

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

29 31.8.2014

Page 30: New Bridges with new Technology

Reinforcement 3D observation

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

30 1.9.2014

Page 31: New Bridges with new Technology

Overview drawing of the steel frame of the bridgedeck

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

31 31.8.2014

Page 32: New Bridges with new Technology

The tender and the contract

• The lowest bidder was one of the largest contractor in Iceland.

• They had a variation offer, which included that steelwork was produced in China.

• A contract was signed .

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

32 31.8.2014

Page 33: New Bridges with new Technology

Comparision of standards

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

33 31.8.2014

Page 34: New Bridges with new Technology

Steelwork Assembly list

31.8.2014 34

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

Page 35: New Bridges with new Technology

Even the smallest part gets its drawing. This drawing shows single part no. 5 It its placed in a assembly number B45. Single part drawings are 175 (mostly A4).

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

35 31.8.2014

Page 36: New Bridges with new Technology

The highligted part is assembly B45

31.8.2014 36

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

Page 37: New Bridges with new Technology

Assembly-drawing number B45 shows assembly no. B45

31.8.2014 37

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

Page 38: New Bridges with new Technology

Foundation geometry details with defined coordinated points

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

38 31.8.2014

Page 39: New Bridges with new Technology

Work started on site

East river work started West river work started

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

39 31.8.2014

Page 40: New Bridges with new Technology

Piles were driven

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

40 31.8.2014

Page 41: New Bridges with new Technology

Foundations

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

41 31.8.2014

Page 42: New Bridges with new Technology

Steel arrives from China

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

42 31.8.2014

Page 43: New Bridges with new Technology

The erection. Three crane operation.

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

43 31.8.2014

Page 44: New Bridges with new Technology

Start of erection. Careful planning is necessary to earn the advantage of speed offered by steel construction.

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

44 31.8.2014

Page 45: New Bridges with new Technology

There are three main planning factors that affect the results. · Practical erection sequence. · Simplicity of assembly connections. · Logical trade sequences.

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

45 31.8.2014

First the two shorter legs.

Page 46: New Bridges with new Technology

Temporary stactions adjusted

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

46 31.8.2014

Page 47: New Bridges with new Technology

Tetrahedron on west bridge in place

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

47 31.8.2014

Page 48: New Bridges with new Technology

First cable placed

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

48 31.8.2014

Page 49: New Bridges with new Technology

Stactions on place

Stactions adjusted by length

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

49 31.8.2014

Page 50: New Bridges with new Technology

Hollowcore on place Elements are made with acquired cover thickness on bottom.

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

50 31.8.2014

Page 51: New Bridges with new Technology

The bridge deck topping.

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

51 31.8.2014

Page 52: New Bridges with new Technology

A cut in bridge deck

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

52 31.8.2014

Page 53: New Bridges with new Technology

Second adjustment of stactions Starting of tuning the harp

3d view deflection (x50) from concrete topping.

Side view

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

53 31.8.2014

Page 54: New Bridges with new Technology

Camber

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

54 31.8.2014

Page 55: New Bridges with new Technology

Cambering is much easier in a cable supported structure than other types of structures. The final shape is a political question. The aim was to make a straight deck under the structuses own weight .

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

55 31.8.2014

• Load is only from the concrete of the deck overlay

Page 56: New Bridges with new Technology

Hollowcore topping laid

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

56 31.8.2014

Page 57: New Bridges with new Technology

The results –The east bridge - straight line

South side North side

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

57 31.8.2014

Page 58: New Bridges with new Technology

Tuning the harp A stringed Harp – the musical instrument – cable-stayed bridge

same method

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

58 31.8.2014

Page 59: New Bridges with new Technology

The forces and frequencies calculated

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

59 1.9.2014

Page 60: New Bridges with new Technology

Measured Observed and documented

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

60 31.8.2014

Page 61: New Bridges with new Technology

Calculated and measured forces compared. The whole bridge without any live loads. If necessary, adjustments are made, (tuning) and measure repeated to get required results. Uncertainty on end support has to be taken into account.

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

61 1.9.2014

Page 62: New Bridges with new Technology

Next time I will download an app for my smartphone. And tune cables just like I do with my musical instrument.

Occilators apps for Android

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

62 31.8.2014

Page 64: New Bridges with new Technology

31.8.2014 64

Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson

A new pedestrian and cycle route.