New Bridges with new Technology
Transcript of New Bridges with new Technology
NVF Annual Bridge Conference 2014 New Bridges with new Technology 3-4th of September 2014 Reykjavik Iceland
Tuning the cable-stayed bridges harp
Pedestrian bridges over Elliðaár
Sigurður Ingi Ólafsson
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson 1 31.8.2014
The geography
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
2
Geirsnef
31.8.2014
Elliðaárvogur 1963 Landfill has just started
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
3 31.8.2014
A picture which shows the seabed and outlines the landfill.
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
4 31.8.2014
Elliðaárvogur 2012
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
5 31.8.2014
Elliðaárvogur 2014
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
6 31.8.2014
Assumptions of the bridges
• When the City Council of Reykjavik approved a new cycling plan in 2010 a network of biking in the city was laid.
• Part of the plan was a connection with a new pedestrian and cycle route across the north end of Elliðaárvogur on Geirsnef.
• Two new bridges were to be built.
• Location of the bridges would be the northern Geirsnef where the river Elliðaár expire in two branches.
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
7 31.8.2014
On a bike to work 2012 A map with pedestrian and cycle routes
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
8 31.8.2014
On a bike to work 2012
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
9
A new pedestrian and cycle route
31.8.2014
The client and owners:
The City of Reykjavik & The Icelandic Road and Coastal Administration
The design team: Role Firm In responce
Arcitects: Teiknistofan TRÖÐ Hans Olav Andersen
Structural Design: Teiknistofan NÝBÝLI ehf. Sigurður Ingi Ólafsson
Electric lighting: Vst. Jóhanns Indriðasonar Arnþór Þórðarson
Land design Snøhetta (Oslo) Jenny B. Osuldsen
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
10 31.8.2014
The crossing It was required that no foundations would be between existing river banks and that the river banks were unchanged after bridge construction
The east river Elliðaá West river (in low tide)
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
11 31.8.2014
• Choosing a structural system for the bridges is the start. The structural building block of the Tetrahedon is the orginal idea of our proposal. This idea we never left.
Tetrahedron A block of tetrahedrons
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
12 31.8.2014
Example of an early stage study. In all design work we used 3D BIM software.
A study which was not presented No foundations allowed between existing river banks
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
13 31.8.2014
The idea behind the structural solution
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
14 31.8.2014
Some changes made to make traffic easier
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
15
Tension bars
31.8.2014
The bridge deck connects the horizontal tension rods.
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
16 31.8.2014
Stactions in floor plan extended (red lines)
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
17 31.8.2014
The final proposal – east bridge 3D model in an actual picture
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
18 31.8.2014
Load on bridge deck: Eurocode 1: Actions on structures –
Part 2: Traffic loads on bridges
5.3.2 Load Models
5.3.2.1 Uniformly distributed load.
• Load Model 4 (crowd loading) Defined in 4.3.5, qfk = 5 kN/m2
5.6.3 Accidental presence of vehicles on the bridge
31.8.2014 Tuning the Cable-stayed bridges harp
Sigurður Ingi Ólafsson 19
JCB4CX 81 kN
Solutions on bridge deck valuated.
Hollow core with in situ topping Steel Deck
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
20 31.8.2014
Top view. The bridges wear a long axes mirror of each other
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
21 1.9.2014
Structural calculations: FEM test for all loadcases checked for entire plate construction.
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
22 31.8.2014
Axial forces Profile stress
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
23 31.8.2014
Structural steel design –Structural detailing
It is all too common to separate thease two design parts.
• Design documents for a steel constructions:
1. Material and assemly lists
2. General arrangement drawings 39 drawings (each bridge)
3. Assembly drawings 24 drawings (each bridge)
4. Single part drawings 175 drawings (mostly A4) for steel production
Parts : 960
Bolts : 175
Components : 92
Assemblies : 324
Drawings : 243
Welds : 747
Fittings : 31
Cuts : 467
Reinforcing bars : 714
Guardrail is not included:
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
24 31.8.2014
Modelling
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
25 31.8.2014
Detailing
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
26 31.8.2014
Top of tetrahedron (transparent)
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
27 31.8.2014
Top of one of shorter legs.
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
28 31.8.2014
The only on site welding
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
29 31.8.2014
Reinforcement 3D observation
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
30 1.9.2014
Overview drawing of the steel frame of the bridgedeck
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
31 31.8.2014
The tender and the contract
• The lowest bidder was one of the largest contractor in Iceland.
• They had a variation offer, which included that steelwork was produced in China.
• A contract was signed .
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
32 31.8.2014
Comparision of standards
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
33 31.8.2014
Steelwork Assembly list
31.8.2014 34
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
Even the smallest part gets its drawing. This drawing shows single part no. 5 It its placed in a assembly number B45. Single part drawings are 175 (mostly A4).
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
35 31.8.2014
The highligted part is assembly B45
31.8.2014 36
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
Assembly-drawing number B45 shows assembly no. B45
31.8.2014 37
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
Foundation geometry details with defined coordinated points
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
38 31.8.2014
Work started on site
East river work started West river work started
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
39 31.8.2014
Piles were driven
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
40 31.8.2014
Foundations
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
41 31.8.2014
Steel arrives from China
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
42 31.8.2014
The erection. Three crane operation.
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
43 31.8.2014
Start of erection. Careful planning is necessary to earn the advantage of speed offered by steel construction.
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
44 31.8.2014
There are three main planning factors that affect the results. · Practical erection sequence. · Simplicity of assembly connections. · Logical trade sequences.
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
45 31.8.2014
First the two shorter legs.
Temporary stactions adjusted
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
46 31.8.2014
Tetrahedron on west bridge in place
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
47 31.8.2014
First cable placed
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
48 31.8.2014
Stactions on place
Stactions adjusted by length
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
49 31.8.2014
Hollowcore on place Elements are made with acquired cover thickness on bottom.
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
50 31.8.2014
The bridge deck topping.
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
51 31.8.2014
A cut in bridge deck
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
52 31.8.2014
Second adjustment of stactions Starting of tuning the harp
3d view deflection (x50) from concrete topping.
Side view
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
53 31.8.2014
Camber
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
54 31.8.2014
Cambering is much easier in a cable supported structure than other types of structures. The final shape is a political question. The aim was to make a straight deck under the structuses own weight .
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
55 31.8.2014
• Load is only from the concrete of the deck overlay
Hollowcore topping laid
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
56 31.8.2014
The results –The east bridge - straight line
South side North side
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
57 31.8.2014
Tuning the harp A stringed Harp – the musical instrument – cable-stayed bridge
same method
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
58 31.8.2014
The forces and frequencies calculated
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
59 1.9.2014
Measured Observed and documented
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
60 31.8.2014
Calculated and measured forces compared. The whole bridge without any live loads. If necessary, adjustments are made, (tuning) and measure repeated to get required results. Uncertainty on end support has to be taken into account.
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
61 1.9.2014
Next time I will download an app for my smartphone. And tune cables just like I do with my musical instrument.
Occilators apps for Android
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
62 31.8.2014
Opening ceremony
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
63 31.8.2014
31.8.2014 64
Tuning the Cable-stayed bridges harp Sigurður Ingi Ólafsson
A new pedestrian and cycle route.