National Grid. Outage Management System Overview June 9, 2009. PowerOn Outage Management Applications. PowerOn suite of Outage Management programs developed by General Electric; used in NE since June of 2007 Full PowerOn used by Control Centers for Dispatching trouble orders - PowerPoint PPT Presentation

Transcript of National Grid

Page 1: National Grid

National Grid

Outage Management System Overview

June 9, 2009

Page 2: National Grid

2

PowerOn Outage Management Applications

PowerOn suite of Outage Management programs developed by General Electric; used in NE since June of 2007

Full PowerOn used by Control Centers for Dispatching trouble orders Dispatching In-Service field conditions Tracking of scheduled field work that involves customer

outagesPowerOn Remote Dispatch (PORD) used by Field Operations

during decentralization for high-volume storms, working of wires down and tree type conditions

PowerOn Real Time Information System (PORTIS) used by management as a tool to analyze storm impacts such as

Number and locations of customers without power By town, feeder, device

Working crews assigned to outages Emergency / 911 calls

Page 3: National Grid

3

Basic Features of PowerOn

GIS-driven electrical network model CSS integration - accepts trouble calls and provides restoration status Automated analysis and intelligent prediction of trouble calls Crew management functions Dispatching and management of in-service & no-service trouble orders Provides graphical display of electrical network and crew locations Emergency and planned distribution switching functions Dynamic real-time reporting capability – PPowerOOn RReal TTime IInformation SSystem (PORTIS) Historical archiving of trouble order data

Page 4: National Grid

4

National Grid Outage Management Process

Customer calls CSS or VRU takes call& sends informationto PowerOn

PowerOn

PowerOn predictsthe most likely device that operated

Crew fixes the problem; tells DCC what the problem is and when it has been repaired

PowerOn

DCC enters analysisdata into PowerOn

IDS

DCC dispatches a crew

Data is automaticallysent to IDS via snapshots

IDS stores archival data

Page 5: National Grid

5

PowerOn Power Control Window

Page 6: National Grid

6

PowerOn Map Window

Page 7: National Grid

7

PowerOn Trouble Order Worksheet – Assign Tab

Page 8: National Grid

8

PowerOn Trouble Order Worksheet – Complete Tab

Page 9: National Grid

9

IDS Analysis Data Screen

Page 10: National Grid

10

PORTIS