nAm I BI A UnIVERSITY OF SCIEnCE AnD TECHnOLOGY Faculty of Management Sciences Department of Management QUAliFICATION: Bachelor of Logistics and Supply Chain Management QUAliFICATION CODE: 07BLSM LEVEL: 7 13 Slorc h Street Private Bag 13388 Wi nd hoek NAMIBIA T: +264 61 207 2220 F: +264 61 207 9220 E: dml@n ust.na W: www. nu st. na COURSE: Project Management/ SME Projects COURSE CODE: PRM422S/ BEP712S DATE: July 2017 SESSION: July 2017 DURATION: 3 Hours MARKS: 100 2nd OPPORTUNITY EXAMINATION- July 2017 1. 2. 3. 4. EXAMINERS : Mr M. L. Nelenge Mr J. V. Olu Ojo MODERATOR : Mr R. Ritter THIS PAPER CONSISTS OF 6 PAGES (INCLUDING THIS FRONT PAGE) INSTRUCTIONS Answer all questions. Read all the questions carefully before answering. Marks for each question are indicated at the end of each question. Please ensure that your writing is legible, neat and presentable. 1

Transcript of nAm I B I A UnIVERSITY 13 Slorch Street T: F: +264 61 207...

Page 1: nAm I B I A UnIVERSITY 13 Slorch Street T: F: +264 61 207 ...exampapers.nust.na/greenstone3/sites/localsite/collect/exampape/in… · SECTION A-Multiple Choice Questions (20 marks)

nAm I B I A UnIVERSITY OF SCIEnCE AnD TECHnOLOGY

Faculty of Management Sciences

Department of Management

QUAliFICATION: Bachelor of Logistics and Supply Chain Management

QUAliFICATION CODE: 07BLSM LEVEL: 7

13 Slorch Street Private Bag 13388 Wi ndhoek NAMIBIA

T: +264 61 207 2220 F: +264 61 207 9220 E: [email protected] W: www. nust.na

COURSE: Project Management/ SME Projects COURSE CODE: PRM422S/ BEP712S

DATE: July 2017 SESSION: July 2017

DURATION: 3 Hours MARKS: 100

2nd OPPORTUNITY EXAMINATION- July 2017

1.

2.

3.

4.

EXAMINERS : Mr M. L. Nelenge

Mr J. V. Olu Ojo

MODERATOR: Mr R. Ritter

THIS PAPER CONSISTS OF 6 PAGES

(INCLUDING THIS FRONT PAGE)

INSTRUCTIONS

Answer all questions.

Read all the questions carefully before answering.

Marks for each question are indicated at the end of each question.

Please ensure that your writing is legible, neat and presentable.

1

Page 2: nAm I B I A UnIVERSITY 13 Slorch Street T: F: +264 61 207 ...exampapers.nust.na/greenstone3/sites/localsite/collect/exampape/in… · SECTION A-Multiple Choice Questions (20 marks)

SECTION A- Multiple Choice Questions (20 marks)

1. Which ofthese is a project?

a. Eradication of Malaria Fever Disease in Namibia

b. Organization of a Baptismal and Confirmation party

c. Visiting a patient in the hospital

d. Writing an Essay on Tourism in Namibia

e. None of the above

2. A project manager has been asked to support an internal project request by developing a business case. What kind of information is the person expected to provide in the document?

a. The detailed information from a business standpoint to determine whether bidding for the customer project will be successful.

b. The detailed information from a project management standpoint to determine whether the project will be successful.

c. The detailed information from a technical standpoint to determine whether the project will be successful.

d. The necessary information from a business standpoint to determine whether the project is worth the investment.

e. None ofthe above

3. In which project management phase is the Critical Path Method (CPM) usually applied.

a. In the initiation phase b. In the execution and control (implementation) phase c. A+B d. None of these e. All of the above

4. What is true for modern project management? Project managers need ...

a. . .. to have a strict standing in negotiating b. to show experience in tricking business partners c. ... to be team players and facilitators instead of "bosses" d. . .. to be strongly linked to local traditions e. . .. All of the above.

5. What is an easy way to document schedules in a project?

a. WBS b. Gantt chart c. PERT d. A+B+C e. None of the above

2

Page 3: nAm I B I A UnIVERSITY 13 Slorch Street T: F: +264 61 207 ...exampapers.nust.na/greenstone3/sites/localsite/collect/exampape/in… · SECTION A-Multiple Choice Questions (20 marks)

6. What does the acronym RACI commonly stand for in project management?

a. Responsible, Accountable, to be Consulted, to be Informed b. Remote, Attached, Connected, Integrated c. Risk Analysis and Caution Initiative d. Randomly Accessible Cash flow Information e. None of the above.

7. Which of the following statements is true about Project Management?

a. Project must not be aligned with the organizational strategic goals

b. Stakeholders may or may not be affected by the outcome of the project.

c. In order to manage a project effectively and efficiently, there is need for application of knowledge, skills, tools and techniques

d. Project Management cannot be carried out outside business environment

e. All of the above are true.

8. The relationship between the organization and its environment is defined by

a. Using tools such as SWOT analysis. b. Review of relevant external economic data

c. The political climate of the environment

d. The attitude of the organization's employees towards the environment

e. The effect of globalization on the business of the organization.

9. Which of the following is not a project initiation

a. Scope identification b. Planning c. Team Set-up

d. Scope verification e. All of the above

10. Which ofthe following statements is true about risks?

a. When evaluating risks, their impact should be considered, however the probability of

occurrence is not important b. Risks ifthey happen always have negative impact and not positive c. Risk register documents all risks in detail d. Risk response plan is another name for Risk Management Plan

e. All of the above

3

Page 4: nAm I B I A UnIVERSITY 13 Slorch Street T: F: +264 61 207 ...exampapers.nust.na/greenstone3/sites/localsite/collect/exampape/in… · SECTION A-Multiple Choice Questions (20 marks)

11. The work of a project must be integrated with the ongoing operations of an organization

a. True b. False

c. Irrelevant d. Teamwork e. All of the above

12. In the project planning phase, the following tools ensure scheduling

a. WBS b. Gantt Chart c. A+B d. None ofthese e. All of the above

13. PERT is useful for determining how much time a project needs before completion

a. True b. False c. Irrelevant d. Crashing e. None ofthe above

14. The second stage in the team development process is ...

a. Storming b. Performing

c. Adjourning d. Forming e. None ofthe above

15. Project Management is about ...

a. Application ofPower

b. Achievement of Top Management Objectives c. Reduction of employee workload

d. Application of knowledge, skills, tools and techniques in order to meet or exceed stakeholder's expectations

e. Application of knowledge, skills tools and techniques in order to save the costs

4

Page 5: nAm I B I A UnIVERSITY 13 Slorch Street T: F: +264 61 207 ...exampapers.nust.na/greenstone3/sites/localsite/collect/exampape/in… · SECTION A-Multiple Choice Questions (20 marks)

16. The project life cycle is ...

a. All activities that took place during the life of the project

b. Cycle of all the meetings that took place during a project

c. A+B

d. End of Phase reviews

e. All of the above

17. Which ofthe following true about a projects

a. A defined beginning and an end

b. Projects have definable goals, deadlines or targets

c. Most projects are carried out only once

d. Projects are usually temporary- and last only until the purpose or goal has been

achieved

e. All ofthe above

18. Phase exits or Stage gates are .. .. ...... .. ..

a. Exit of project team members

b. Briefing of Top Management Team about a project

c. a+ b

d. End of phase reviews e. None ofthe above

19. Which ofthe following statement is true about Project Life Cycle

a. Takes into account more than cost and time

b. To help with the timing of decisions

c. Focused on minimizing cost and time

d. The performing organization

e. Managing Stakeholders expectations

20. Which of the following is not part of defining the project

a. Determining the time,

b. Determining the cost,

c. Determining the qual ity

d. Determining the context

e. Determining the resource requirements

5

Page 6: nAm I B I A UnIVERSITY 13 Slorch Street T: F: +264 61 207 ...exampapers.nust.na/greenstone3/sites/localsite/collect/exampape/in… · SECTION A-Multiple Choice Questions (20 marks)

,--.

SECTION B- Essay Type Questions (80marks)

1. Carry out a comprehensive comparison of traditional and modern approaches to project

management. Provide examples in each case discussion (20 Marks)

2. Discuss the concept of Integration and its effect on project management (10 Marks)

3. The communication plan is an important part of a project planning. As a newly appointed project manager, you are facing the following situation: The project needs to begin on 3 March 2015. Before the project can commence, the team needs to be built. The first project team development meeting is scheduled for 6 February 2015. The project assistant is requested to send an agenda via email for the meeting on 15 January 2015 to all team members. Later, on 22 January 2015, he needs to call all team members to invite them personally to participate in a project team development programme. On 15 February 2015, the project manager will send the project team development document via email to all team members in order to inform them about the procedure. You are requested to create the communication plan with appropriate headings by using data from the Case Study 5. Plan carefully and allocate correct information in a table. (20 Marks)

4. Sometime Project managers experience the dilemma in managing stakeholder' s expectations.

This can be explained as difficult because of the sometimes widely different objectives of the

various groups of stakeholders. Illustrate with examples how the Project management team can

manage the Stakeholders cycle (20 marks)

5. a. Create a new Work-Breakdown Structure (WBS) for a project with the following elements:

developing a new technology product, design phase, programming phase, testing phase, first

design phase and second design phase. (15 marks)

b. What other breakdown structure can be used in Project Management? (5 marks)

TOTAL MARKS = 100