Project Progress – 4 th Aug,2014

description

My home vihanga status report as on 04.08.2014

Transcript of My home vihanga status report as on 04.08.2014

Page 1: My home vihanga status report as on 04.08.2014

Project Progress – 4thAug,2014

Page 2: My home vihanga status report as on 04.08.2014

MY HOME VIHANGA BLOCK-“01” AS ON 4th Aug, 2014

Basement –II, Basement-I, Ground, First, Second , Third, Forth, Fifth , Sixth, Seventh Floor Slabs Completed

Page 3: My home vihanga status report as on 04.08.2014

MY HOME VIHANGA BLOCK - “02” AS ON 4th Aug, 2014

Basement –II, Basement-I, Ground, First, Second , Third, Forth, Fifth Floor Slabs Completed

Page 4: My home vihanga status report as on 04.08.2014

MY HOME VIHANGA BLOCK- “03” AS ON 4th Aug, 2014

Basement II Slab Completed

Page 5: My home vihanga status report as on 04.08.2014

MY HOME VIHANGA BLOCK- “04” AS ON 4th Aug, 2014

Basement II Slab Completed, Basement-I Columns work completed

Page 6: My home vihanga status report as on 04.08.2014

MY HOME VIHANGA BLOCK- “05” AS ON 4th Aug, 2014

PCC Work Completed, Footing Work Completed, Preparing for Grade Slab

Page 7: My home vihanga status report as on 04.08.2014

MY HOME VIHANGA BLOCK- “06” AS ON 4th Aug, 2014

Basement II Slab Completed

Page 8: My home vihanga status report as on 04.08.2014

MY HOME VIHANGA BLOCK-“07” AS ON 4th Aug, 2014

PCC Work In Progress

Page 9: My home vihanga status report as on 04.08.2014

MY HOME VIHANGA BLOCK-“08” AS ON 4th Aug, 2014

Earth Work Completed

Page 10: My home vihanga status report as on 04.08.2014

MY HOME VIHANGA BLOCK- “09 & 10” AS ON 4th Aug, 2014

Earth Work In Progress

Page 11: My home vihanga status report as on 04.08.2014

MY HOME VIHANGA Block- “11 & 12” AS ON 4th Aug, 2014

Earth Work In Progress

Page 12: My home vihanga status report as on 04.08.2014

MY HOME VIHANGA BLOCK-“13 & 14” AS ON 4th Aug, 2014

Footings-Work In Progress

Page 13: My home vihanga status report as on 04.08.2014

MY HOME VIHANGA BLOCK-“15” AS ON 4th Aug, 2014

Basement-II Slab Completed, Basement-I Slab shuttering work in Progress

Page 14: My home vihanga status report as on 04.08.2014

MY HOME VIHANGA BLOCK-“16” AS ON 4th Aug, 2014

Basement II Slab Completed

Page 15: My home vihanga status report as on 04.08.2014

MY HOME VIHANGA BLOCK-“17” AS ON 4th Aug, 2014

Grade Slab Completed

Page 16: My home vihanga status report as on 04.08.2014

MY HOME VIHANGA BLOCK-“18” AS ON 4th Aug, 2014

Grade Slab Bar bending work in progress

Page 17: My home vihanga status report as on 04.08.2014

MY HOME VIHANGA BLOCK-“19”AS ON 4th Aug, 2014

Basement –II Slab Completed

Page 18: My home vihanga status report as on 04.08.2014

MY HOME VIHANGA BLOCK-“20” AS ON 4th Aug, 2014

Basement II Slab Completed