Project Progress–7 th Oct,2014

description

My home vihanga status report as on 07.10.2014

Transcript of My home vihanga status report as on 07.10.2014

Page 1: My home vihanga status report as on 07.10.2014

Project Progress–7th

Oct,2014

Page 2: My home vihanga status report as on 07.10.2014

MY HOME VIHANGA BLOCK-“01” AS ON 7th Oct, 2014

Basement –II, Basement-I, Ground, 1st to 15th Floor Slabs Completed

Page 3: My home vihanga status report as on 07.10.2014

MY HOME VIHANGA BLOCK - “02” AS ON 7th Oct, 2014

Basement –II, Basement-I, Ground, 1st to 13th Floor Slabs Completed

Page 4: My home vihanga status report as on 07.10.2014

MY HOME VIHANGA BLOCK- “03” AS ON 7th Oct, 2014Basement –II, Basement-I, Ground, Slabs Completed

Page 5: My home vihanga status report as on 07.10.2014

MY HOME VIHANGA BLOCK- “04” AS ON 7th Oct, 2014

Basement II & I Slabs Completed

Page 6: My home vihanga status report as on 07.10.2014

MY HOME VIHANGA BLOCK- “05” AS ON 7th Oct, 2014

Basement-II Slab Completed, Basement-I Slab Shuttering work In Progress

Page 7: My home vihanga status report as on 07.10.2014

MY HOME VIHANGA BLOCK- “06” AS ON 7th Oct, 2014

Basement II & I Slabs Completed

Page 8: My home vihanga status report as on 07.10.2014

MY HOME VIHANGA BLOCK-“07” AS ON 7th Oct, 2014

PCC & Footing work In Progress

Page 9: My home vihanga status report as on 07.10.2014

MY HOME VIHANGA BLOCK-“08” AS ON 7th Oct, 2014

PCC & Footing work In Progress

Page 10: My home vihanga status report as on 07.10.2014

MY HOME VIHANGA BLOCK- “09” AS ON 7th Oct, 2014

PCC & Footings Work Completed

Page 11: My home vihanga status report as on 07.10.2014

MY HOME VIHANGA BLOCK- “10” AS ON 7th Oct, 2014

PCC & Footings Work Completed

Page 12: My home vihanga status report as on 07.10.2014

MY HOME VIHANGA BLOCK-“11” AS ON 7th Oct,2014

PCC & Footing work In Progress

Page 13: My home vihanga status report as on 07.10.2014

MY HOME VIHANGA BLOCK-“12” AS ON 7th Oct,2014

PCC & Footing work In Progress

Page 14: My home vihanga status report as on 07.10.2014

MY HOME VIHANGA BLOCK-“13” AS ON 7th Oct, 2014

Grade Slab Sand Filling work In Progress

Page 15: My home vihanga status report as on 07.10.2014

MY HOME VIHANGA BLOCK-“14” AS ON 7th Oct, 2014

PCC Completed, Footings Work In Progress

Page 16: My home vihanga status report as on 07.10.2014

MY HOME VIHANGA BLOCK-“15” AS ON 7th Oct, 2014

Basement-II & I Slabs Completed, Ground Floor Slab Progress

Page 17: My home vihanga status report as on 07.10.2014

MY HOME VIHANGA BLOCK-“16” AS ON 7th Oct, 2014

Basement II, Basement-I Slab Completed

Page 18: My home vihanga status report as on 07.10.2014

MY HOME VIHANGA BLOCK-“17” AS ON 7th Oct, 2014

Grade Slab Completed, Basement-II Slab Work In Progress

Page 19: My home vihanga status report as on 07.10.2014

MY HOME VIHANGA BLOCK-“18” AS ON 7th Oct, 2014

Grade Slab Completed

Page 20: My home vihanga status report as on 07.10.2014

MY HOME VIHANGA BLOCK-“19”AS ON 7th Oct, 2014

Basement –II Slab Completed, Basement-I Slab Work In Progress

Page 21: My home vihanga status report as on 07.10.2014

MY HOME VIHANGA BLOCK-“20” AS ON 7th Oct, 2014

Basement II Slab Completed, Basement-I Slab Columns Work Progress