mpc blockdiagram
-
Upload
kalpesh-barde -
Category
Documents
-
view
237 -
download
3
Transcript of mpc blockdiagram
-
8/2/2019 mpc blockdiagram
1/15
Presentation on:-
Manufacturing
Planning &
Control systems and its linkages
prepared by- Kalpesh Barde
B.E Mechanical
Roll no:-104
-
8/2/2019 mpc blockdiagram
2/15
Manufacturing planning & control (MPC)
systems are the systems that deals with all
the activities from acquisition of raw
material to the delivery of completed
product.
-
8/2/2019 mpc blockdiagram
3/15
Master productionschedule (MPS)
Purchasing system
Demand planningProductionPlanning
Materialrequirement
planning
Shop floor controlsystem
Detailed capacityplanning
Material andcapacity plans
FRONT
END
ENGINE
BACK
END
-
8/2/2019 mpc blockdiagram
4/15
-
8/2/2019 mpc blockdiagram
5/15
FRONT END
The front end, is the set of activities and systems for overall
direction setting. This phase establishes the overall company
direction for manufacturing planning and control.
ENGINE
The middle third, or engine, encompasses the set of MPC
systems for detailed material and capacity planning.
BACK END
The bottom third, or back end, depicts MPC execution systems.
-
8/2/2019 mpc blockdiagram
6/15
Demand planning encompasses forecastingcustomer/end-product demand, order entry,
order promising, accommodating interplant andintercompany demand, and spare partsrequirements.
Production planning is the activity whichprovides the production input to the companygame plan and determines the manufacturingrole in strategic plan.
-
8/2/2019 mpc blockdiagram
7/15
The Master Production Schedule (MPS) is the
disaggregated version of the sales and operations
plan. That is, it states which end items or product
options manufacturing will build in the future.
The master production schedule feeds directly
into the detailed material planning module.
-
8/2/2019 mpc blockdiagram
8/15
Material Requirement and Planning (MRP) determines
the period-by-period plans for all component parts and rawmaterials required to produce all the products in the MPS.
This technique determines what component are needed
and when they should be ordered so that they are likely tobe available as needed.
This material plan can thereafter be utilized in the
detailed capacity planning systems to compute labor ormachine center capacity required to manufacture all thecomponent parts.
-
8/2/2019 mpc blockdiagram
9/15
In the back end the system configuration
depends on the products manufactured andproduction processes employed.
Their shop floor system establishes prioritiesfor all shop orders at each work center so the
orders can be properly scheduled.
Purchasing system provide detailed planning
information for vendor scheduling.
-
8/2/2019 mpc blockdiagram
10/15
Productionplanning
Resourceplanning
Demandmanagement
Rough cutcapacityplanning
Masterproductionscheduling
input/output analysis
Vendorfollow up
systemShop floor
control
Capacityrequirement
planning
Materialrequirement
planning(MRP)
Finiteloading
-
8/2/2019 mpc blockdiagram
11/15
These 5 levels of capacity planning activitiesrange from large aggregation of capacities forlong term period to very detailed machinescheduling for shorter time interval.
There must be a correspondence between thecapacity required to execute a given materialplan and that made available to execute a plan.If the correspondence does not exist the planeither be impossible to execute.
-
8/2/2019 mpc blockdiagram
12/15
Resource planning activity is directly linked to
production planning module. Resource
planning involves converting monthly quarterlyor even annual data from production plan into
aggregate resources such as goods labor hours ,
floor space , machine hours and links.
-
8/2/2019 mpc blockdiagram
13/15
The master production schedule is the primary
source for rough cut planning.
The capacity requirements of particular masterschedule can be estimated by techniques like
I. Capacity planning using overall planning factor
(CPOF)
II. Capacity bills
III. Resources profile
-
8/2/2019 mpc blockdiagram
14/15
The material plans produced by MRP systems
serve as the basis for calculating time-phasedcapacity requirements.
The finite loading is a method for schedulingwork orders.
The input and output analysis helps inmonitoring the actual consumption of capacity
during the execution of material plans.
-
8/2/2019 mpc blockdiagram
15/15
Thank you . . . . ! ! !