Monthly Safety Meeting - Avvery

24

Transcript of Monthly Safety Meeting - Avvery

Page 1: Monthly Safety Meeting - Avvery
Page 2: Monthly Safety Meeting - Avvery

Perspective View

Page 3: Monthly Safety Meeting - Avvery

Contract Details

PROPOSED INTERNAL PARTITION WORKS AT EXISTING 2ND & 3RD STOREY PRODUCTION AREA AT EXISTING 6-STOREY SINGLE USER FACTORY BUILDING ON LOT 2125W MK 19 -UPGRADE CLEANROOM TO CLASS 100 AT 1A2F & 1A3F FOR EWLB 8K FOR STATS CHIPPAC 5 YISHUN STEET 23, SINGAPORE 768442

Page 4: Monthly Safety Meeting - Avvery

Project Organisation Chart

Page 5: Monthly Safety Meeting - Avvery

Safety Committee Chart

Michael TanChairman

Faizal(Secretary)

Ken Toh(Member)

Kelvin Oon(Vice Chairman)

William Ng(Member)

Chaw Kok Wei(Member)

Lai Koy Soon(Member)

Steven Tan(Member)

Johnson Chin(Member)

Eugene Tan(Secretary)

Page 6: Monthly Safety Meeting - Avvery

RM/RA Organisation Chart

Page 7: Monthly Safety Meeting - Avvery

Signed Policy

Page 8: Monthly Safety Meeting - Avvery

Safety Plan

Annual Safety Plan: 2016

Project No: To Design & Build New Cleanroom of Class 10K, 1K & 100 at 1A3F for eWLB

Date Start:

S/N Month/ Week

Element Wk 1 Wk 2 Wk 3 Wk 4 Wk 1 Wk 2 Wk 3 Wk 4 Wk 1 Wk 2 Wk 3 Wk 4 Wk 1 Wk 2 Wk 3 Wk 4 Wk 1 Wk 2 Wk 3 Wk 4 Wk 1 Wk 2 Wk 3 Wk 4 Wk 1 Wk 2 Wk 3 Wk 4 Wk 1 Wk 2 Wk 3 Wk 4 Wk 1 Wk 2 Wk 3 Wk 4 Wk 1 Wk 2 Wk 3 Wk 4 Wk 1 Wk 2 Wk 3 Wk 4 Wk 1 Wk 2 Wk 3 Wk 4

1 Safety Policy (Review)

2 Safe Work Procedures (Review)

3 Safety Training

4 Safety Meeting

5 Incident Investigation Analysis

6 In-House Rules (Review)

7 Safety Promotion

8 ESC of Contractors

9 Safety Inspection

10 Maintenance Regime(LEW)

11 Risk Assessment Committee

12 Hazardous Substance (Review)

13 Occupational Health Programme

14 Emergency Prepardness

15 Audit

PreparedBy: _____________________ Approved By: ___________________

Name: __________________________ Name: _________________________

Designation:_____________________ Designation: ____________________

Month 12Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10 Month 11

Page 9: Monthly Safety Meeting - Avvery

Statistics on Authority Visits

0

1

2

3

4

5

6

7

8

9

10

Nov-16 Dec-16 Jan-17 Feb-17

Authority Visit

HDB MOM NEA SCDF

Page 10: Monthly Safety Meeting - Avvery

Legal/Community Updates

Page 11: Monthly Safety Meeting - Avvery

Statistics on PTW on Site(JAN 17)

0 5 10 15 20 25 30 35 40

Hot Works

WAH

Lifting

General Permit

Permit to Work

Approved Rejected

Page 12: Monthly Safety Meeting - Avvery

Statistics on SWP onsite(JAN 17)

0 0.2 0.4 0.6 0.8 1 1.2

EST

KEESE

SYC

JOHNSON CHIN

PIPE WORLD

Safe Work Procedure

Approved Rejected

Page 13: Monthly Safety Meeting - Avvery

Statistics on FPP onsite(JAN 17)

0 0.5 1 1.5 2 2.5 3 3.5 4 4.5 5

EST

SYC

JOHNSON CHIN

Fall Protection Plan

Approved Rejected

Page 14: Monthly Safety Meeting - Avvery

Statistics of AFR & ASR

Total

Manpower

Total

Manhours

No. Of

Incident

No. Of

Occupationa

l Disease

AFRTotal

Mandays

Lost

ASR

Nov-16 1042 10420 0 0 0 0 0

Dec-16 1266 12660 0 0 0 0 0

Jan-17 831 8310 0 0 0 0 0

Feb-17

Page 15: Monthly Safety Meeting - Avvery

Statistics of Good Safety Practices

0

0.5

1

1.5

2

2.5

3

3.5

4

4.5

Housekeeping Barricade WAH Maintenance PPE noise pollution signage access Electrical hazard Trip & Fall

Good Practices

Nov-16 Dec-16 Jan-17

Page 16: Monthly Safety Meeting - Avvery

Schedule of Safety Campaign

There is no schedule for upcoming promotion campaign as yet

Page 17: Monthly Safety Meeting - Avvery

Statistics of EsC of Contractors

0

1

EST Hydal Tan & Eng KIV

EsC of Contractors

Nov-16 Dec-16

Page 18: Monthly Safety Meeting - Avvery

Inspections(SAFETY LAPSE)

0

1

2

3

4

5

6

7

8

9

Inspections

Nov-16 Dec-16 Jan-17

Page 19: Monthly Safety Meeting - Avvery

Maintenance Regime(JAN 17)S/N TYPE MODEL DATE DUE COMPANY

1 Power Drill *00131 1/2/2017 Keess2 Metal Bend Saw *084836 1/2/2017 Keess3 RCCB RCCB_01 1/2/2017 Keess4 Extension wire EW_01 1/2/2017 Keess5 Vaccum Cleaner *052600096 1/2/2017 Keess6 Battery Charger BC-1204A 1/2/2017 Keess7 Battery Charger BC-1204B 1/2/2017 Keess8 Circular Saw *013577 1/2/2017 Keess9 Repro Saw *00168082 1/2/2017 Keess

10 Jig Saw *003727 1/2/2017 Keess11 Hand Grinder HG_01 1/2/2017 Keess12 Vinyl Heating Tools WG_01 1/2/2017 Keess13 ELCB V026A 1/2/2017 Keess14 Vaccum Cleaner GM80 / 17049071 1/2/2017 Pipe World15 Vaccum Cleaner NILFISK / 1114253450 1/2/2017 SYC16 Chopsaw BOSCH / 303000087 1/2/2017 SYC17 Circular Saw MAKITA / 4131 1/2/2017 SYC18 Band Saw SYC BS-01 1/2/2017 SYC19 ELCB SCY SOA-01 1/2/2017 SYC

Page 20: Monthly Safety Meeting - Avvery

Risk Assessment(JAN 17)

0 1 2 3 4 5

EST

JOHNSON CHIN

PIPEWORLD

KEESS

SYC

Risk Assessment

Approved Rejected

Page 21: Monthly Safety Meeting - Avvery

Hazardous Substances(JAN 17)

S/N TYPE NAME CLASSIFICATION COMPANY

1 PAINT AS-299H FLAMMABLE & TOXIC SYC

2 PAINT KL - 5 WATER BASED FLAMMABLE & TOXIC KEESS

Page 22: Monthly Safety Meeting - Avvery

Occupational Health

No statistics and upcoming programs scheduled.

Page 23: Monthly Safety Meeting - Avvery

Emergency

No Emergency Drill has been scheduled to date.

Page 24: Monthly Safety Meeting - Avvery

Audit

The Internal audit was conducted on 9th Jan 2017.