Monthly Progress Report No. 68 -...

184
Monthly Progress Report No. 68 Covering Project Activities During August 2018

Transcript of Monthly Progress Report No. 68 -...

Page 1: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report No. 68Covering Project Activities During

August 2018

Page 2: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

PT. PERENTJANA DJAJA in subconsultancy with 4'l' Yongma Engineering Co. Ltd and :i'PT. Epadascon Permata Engineering Consultant CTC Office: JI. Ciniru VII No. 25, Kebayoran Baru, Jakarta Selatan, 12180

Phone /Fax: (021) 7229823

Ve ~o¥(i1bi1rs ,o~em 11•s• . ~'nt .. p \1>1,0 '%

~t.,\~ "8!. C'., :;:,"'-' ~ .,, <r('J'• I,,,.. *

* Jc~l --~)~ ..,..~ . . CTC _ WINRIP /;;/

~16 _,.--"", ; .. ' . Yon "·''/ [ ~n~i:1->· '

Team Leader Cc:

1. Direktur Jenderal Bina Marga 2. lnspektorat Jenderal.Kementerten PU-PERA- 3. Direktur Transportasi - Bappenas 4. Direktur Penge.lolaan Kas Negara (PKN), Kementerian Keuangan 5. Direktur Penqernbanqan Jarinqan Jalan, Dit.Jen Bina Marga 6. Direktur Jalan Bebas Hambatan, Perkotaan dan Fasilitasi Jalan Daerah, Dit.Jen Bina Marga 7. Direktur Pernbanqunan Jalan, Dit.Jen Bina Marga 8. Direktur Preservasi Jalan, Dit.Jen Bina Marga 9. Biro Perencanaan & KLN, Kementrian PU-PERA 10. Kepala Balai Besar Pelaksanaan Jalan Nasional II Medan 11. Kepala Balai Besar Pelaksanaan Jalan Nasional Ill Padang 12. Kepala Balai Besar Pelaksanaan Jalan Nasional V Palembang 13. Kasubdit Keterpaduan Perencanaan & Sistem Jaringan, DPJJ - DJBM 14. Ketua Pelaksana Harian PIU WINRIP 15. Kepala Satker Pembinaan Administrasi dan Pelaksanaan Pengendalian PHLN 16. PT. Perentjana Djaja 17. Yongma Engineering Co, Ltd 18. PT. Epadascon Permata Engineering Consultant 19. File .

Should you have any comment or additional information that need to be incorporated in the Report, please feel free to get in touch with us.

This Report is reproduced in twenty (20) copies for distribution to all concerned authorities.

In compliance with the Terms of Reference of our Consultancy Contract, we submit herewith the Monthly Progress Report No.68 covering the month of August 2018.

Dear Sir,

Attention: Andria Muharami Fitra, ST. M.Eng Officer In Charge PMU WINRIP

Subject : Submission of August 2018 Monthly Progress Report No.68; WINRIP Loan IBRD No.8043-ID

Directorate General of Highways, MPWH JI. Patimura 20 Kebayoran Baru Jakarta Selatan Indonesia

Jakarta, September D9, 2018 : 03_02/LHW/0/~-08)618 Our Ref.No. I Perentjana Djaja

MINISTRY OF PUBLIC WORKS & HOUSING DIRECTORATE GENERAL OF HIGHWAYS

DIRECTORATE OF ROAD NETWORK DEVELOPMENT Core Team Consultant for

Western Indonesia National Roads Improvement Project (WINRIP) IBRD Loan No. SQ.43-10

Page 3: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan
Page 4: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

Table of Contents

1 EXECUTIVE SUMMARY............................................................................................................ 1-11.1 Current Implementation Situation.......................................................................................................1-1

1.2 Disbursement..........................................................................................................................................1-41.3 World Bank Implementation Review Mission and Site Visit...............................................................1-5

1.4 Procurement of Civil Works Contract Under Category 1 of the Loan Agreement...........................1-52 PROJECT DESCRIPTION ........................................................................................................... 2-1

2.1 Background.............................................................................................................................................2-1

2.2 Project Development.............................................................................................................................2-12.3 Project Objective ......................................................................................................................................2-6

3 CONSULTANCY SERVICES ........................................................................................................... 3-13.1 CTC Consultants ......................................................................................................................................3-1

3.1.1 Scope of Services ........................................................................................................... 3-13.1.2 CTC Manning ................................................................................................................. 3-23.1.3 CTC Contract.................................................................................................................. 3-4

3.2 DSC Consultants.....................................................................................................................................3-6

3.3 Technical Assistance for Development of Slope Stabilization, Design and Management............3-74 CIVIL WORKS............................................................................................................................ 4-1

4.1 Detailed Design Preparation...................................................................................................................4-14.2 Procurements ............................................................................................................................................4-1

4.3 Civil Works Implementation ...................................................................................................................4-14.4 Civil Works Progress.................................................................................................................................4-3

4.5 Quality Assurance.....................................................................................................................................4-7

4.6 Environmental and Social Considerations...........................................................................................4-12

4.6.1 Current Overall Situation............................................................................................ 4-124.6.2 Environmental and Social Issues................................................................................ 4-13

4.7 Anti Corruption Issues..........................................................................................................................4-39

4.7.1 Anti‐Corruption Action Plan (ACAP) ............................................................................ 4-394.7.2 Community Representative Observers (CRO)............................................................ 4-394.7.3 Publication / Disclosure ............................................................................................... 4-404.7.4 Complaints Handling Mechanism (CHS) ..................................................................... 4-414.7.5 Third Party Monitoring (TPM)...................................................................................... 4-41

4.8 Road Safety Audit ...............................................................................................................................4-425 FINANCIAL & MANAGEMENT INFORMATION SYSTEMS.......................................................... 5-1

5.1 Draw‐Downs and Future Costs..............................................................................................................5-15.2 Disbursement..........................................................................................................................................5-1

Page 5: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

5.3. Management Information System ......................................................................................................5-1

6 PROJECT PERFORMANCE ........................................................................................................ 6-16.1 World Bank and GOI Compliance........................................................................................................6-1

6.1.1 World Bank Missions .................................................................................................... 6-16.1.2 Agreed Key Actions and during the Coordination Meeting ...................................... 6-1

6.2 Implementation Support Components...............................................................................................6-4

6.2.1 Core Team Consultant (CTC)........................................................................................ 6-46.2.2 Design and Supervision Consultant (DSC)................................................................... 6-56.2.3 Study on Development of Slope Stabilization Design and Management................ 6-5

6.3 Anti‐Corruption Issues .............................................................................................................................6-5

6.3.1 Anti-Corruption Action Plan (ACAP) ............................................................................ 6-56.3.2 Community Representative Observers (CRO)............................................................ 6-66.3.3 Third Party Monitoring (TPM)...................................................................................... 6-66.3.4 Complaint Handling System (CHS)............................................................................... 6-66.3.5. Public Disclosures / Publication.................................................................................... 6-7

6.4 Road Safety Audit ..................................................................................................................................6-8

6.4.1 Activities during This Month (August 2018) ............................................................... 6-86.5 Management Information System ......................................................................................................6-8

6.6 Quality Assurance................................................................................................................................6-15

6.7 Project Risks and Mitigation Measures............................................................................................6-15

6.7.1 Risks Related to Delays ............................................................................................... 6-156.7.2 Financial Risks.............................................................................................................. 6-156.7.3 Risks Related to Quality .............................................................................................. 6-15

6.8 Training to Support Project Implementation......................................................................................6-16

7 CURRENT ISSUES AND FOLLOW-UP ACTIONS ......................................................................... 7-18 CORRESPONDENCES ............................................................................................................... 8-1

Page 6: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

ABBREVIATIONS AND ACRONYMS

ACAP : Anti Corruption Action PlanAER : Application Evaluation ReportAIP : Australian Indonesia PartnershipAMDAL : Environmental Management (Analisis Mengenai Dampak

Lingkungan)ANDAS : Analisis Dampak SosialAWPs : Annual Work ProgramsBalai : Regional Office for National Roads ImplementationBAPPENAS : Badan Perencanaan Pembangunan Nasional (National

Development Planning Agency of GOI)Bappedalda : Regional Environmental Impact AgenciesBBPJN : Balai Besar Pelaksanaan Jalan Nasional (Regional Office for

National Roads Implementation)BER : Bid Evaluation Report

BLH : Badan Lingkungan Hidup

BPK : Badan Pemeriksaan Keuangan (Audit Board of the Government

of Indonesia)

CAD : Computer Aided Design

CHS : Complaint Handling System

CTC : Core Team Consultant

CHU : Complaint Handling Unit

CRO : Community Representative Observer ( = WPM)

DIA : Directorate of Implementing Affairs

DRND : Directorate of Road Network Development

DGH : Directorate General of Highways

DMS : Document Management System

DRP : Directorate Road of Preservation

DMS : Document Management System

DSC : Design and Supervision Consultants

EA : Executing Agency

EINRIP : Eastern Indonesian National Roads Improvement Project

EIRTP-1 : Eastern Indonesia Regional Transport Project First Project

ESAMP : Environmental and Social Assessment Plan

ESS : Environmental and Social Safeguards

FMIS : Financial Management Information System

FIDIC : Federation Internationale des Ingenieur Conseils

Page 7: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

FMIS : Financial Management Information System

GIS : Geographic Information System

GOI : Government of Indonesia

IA : Implementation Agency

IBRD : International Bank for Reconstruction and Development

IFR : Interim Financial Report

IRMS : Integrated Road Management System

Kabupaten : Regency

KPIs : Key Performance Indicators

KPPN : Kantor Pelayanan Perbendaharaan Negara (Indonesian: State

Treasury Service Office)

LAN : Local Area Network

LARAP : Land Acquisition and Resettlement Plan (Rencana Tindak

Pengadaan Tanah dan Pemukiman Kembali)

MIS : Management Information System

MOF : Ministry of Finance

MPW H : Ministry of Public Work & Housing

MPRs : Monthly Progress Reports

P2JN : Perencanaan Pengawasan Jalan dan Jembatan Nasional

PDF : Portable Document Format

PMU : Project Management Unit

PAPs : Project Affected Peoples

PMM : Project Management Manual

PMU : Project Management Unit (WINRIP)

POKJA : Bina Marga Project Managers and Procurement Committes

PPC : Project Preparation Consultants

PP3 : Pemantau Pihak ke 3

PPK : Sub Project Manager

PPR : Project Progress Report

QPRs : Quarterly Progress Reports

RKL/RPL : Rencana Pengelolaan/Pemantauan Lingkungan

RS : Road Safety

Satker : Satuan Kerja (Work Unit for Road Project Implementation)

SPPL : Surat Pernyataan Pengelolaan Lingkungan

SRIP : Strategic Road Infrastructure Project

TA : Technical Assistance

Page 8: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

TOR : Terms of Reference

UKL/UPL : Upaya Pengelolaan Lingkungan / Upaya Pemantauan Lingkungan

(Site Specific Environmental and Monitoring Plan)

WINRIP : Western Indonesia Roads Improvement Project

WB : World Bank

WP : Work Program

WPs : Works Programs

WPM : Wakil Pengamat dari Masyarakat (or Community Representative

Observer / CRO)

Page 9: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

APPENDICES

Appendix A : Overall Loan ProgressAppendix B : Road Safety Audit ProgressAppendix C : Financial ProgressAppendix D : Quality Assurance ProgressAppendix E : Environmental and Social ProgressAppendix F : Procurement Plan and ProgressAppendix G : WINRIP Website ProgressAppendix H : ACAP Training/Dissemination ProgressAppendix I : Performance IndicatorAppendix J : Correspondences

ANNEXESAnnex P-1 : Package No. 1Annex P-2 : Package No. 2Annex P-3 : Package No. 3Annex P-4 : Package No. 4Annex P-5 : Package No. 5Annex P-6 : Package No. 6Annex P-7 : Package No. 7Annex P-8 : Package No. 8Annex P-11 : Package No. 11Annex P-12 : Package No. 12Annex P-13 : Package No. 13Annex P-14 : Package No. 14Annex P-15 : Package No. 15Annex P-16 : Package No. 16Annex P-17 : Package No. 17Annex P-19 : Package No. 19Annex P-20 : Package No. 20Annex P-21 : Package No. 21

ATTACHMENTAttachment 1 : Summary of Studies and Reports on Environmental Activity

Page 10: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

1 - 1

1 EXECUTIVE SUMMARY

1.1 Current Implementation SituationCivil Works

Implementation of the WINRIP Project is scheduled to be implemented into three (3) Annual WorkPrograms (AWP’s). The implementation starts with the preparation of tender documents (detaileddesign drawings including associated bidding documents), tendering stage (procurement of works)and the actual civil works construction implementation.

The original implementation schedules of the three (3) Annual Work Programs (AWPs) arescheduled in three (3) phases namely; AWP-1 to start in mid-2011 and to be completed on the lastquarter of 2014, AWP-2 is expected to begin in mid 2012 with target date of completion by mid-2016 and AWP-3 is expected to start during the early part of 2013 and to be completed during themiddle part of 2017.

However, due to some unavoidable circumstances the original implementation schedules did notmaterialize.

Based on the present status of the program implementation progress, a revised implementationschedule, the “Project Implementation Timeline” (as shown on Page 1-2) is to be implemented inorder to accommodate the originally delayed schedule into the remaining time frame of theWINRIP Program until the expiry date of the loan agreement by the end of December 2018. Shownon Page 1-3 is the current actual status of the implementation relative to the “ProjectImplementation Timeline”.

Implementation Status as of August 31, 2018

PackPackage Name

Contract Under Under Defect LiabilityPeriodNo. Sign Construct

1 Krui - Biha √ Completed Completed FHO2 Padang Sawah - Sp.Empat √ Completed √3 Manggopoh - Padang Sawah √ Completed √4 Ipuh - Bantal √ Completed √5 Sp. Rampa - Poriaha √ Completed √

6 Ps. Pedati - Kerkap √ Completed √7 Indrapura - Tapan √ Completed √8 Bts.Pariaman - Manggopoh √ Completed √

11 Bantal - Mukomuko √ Completed √12 Kambang - Indrapura √ √13 Sp. Rukis - Tj.Kemuning √ Completed √14 Painan - Kambang √ √15 Sibolga - Bts.Tap Sel √ √16 Seblat - Ipuh √ √17 Sp.Gn.Kemala - Pg.Tampak √ Completed √19 Lais - Bintunan √ Completed √20 Lubuk Alung - Sicincin √ Completed √

21 Lubuk Alung - Kuraijati √ TerminatedT O T A L : 18 4 12

Note: Package No.9 (Rantau Tijang – Kota Agung), Package No.10 Sp.Empat-Sp.Air Balam and Package No.18 (Mukomuko – Bts.Sumbar) are cancelled from the program.

Page 11: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

1 - 2

Length C'tionKm Period J N D J F M A MJ J A S ON D J F M A M J J A S ON D J F M A MJ J A S ON D J F M A MJ J A S ON D J F M A MJ J A S ON D J F M A MJ J A S ON D

1 Krui - Biha 25,00 21 mth

2 Padang Sawah - Sp.Empat 40,90 24 mth

3 Manggopoh - Padang Sawah 32,00 24 mth

4 Ipuh - Bantal 42,40 24 mth

5 SIMPANG RAMPA - PORIAHA 11,10 18 mth

11 BANTAL - MUKOMUKO 50,10 24 mth

13 SP RUKIS - TJ KEMUNING 56,30 24 mth

17 Sp.Gn.KEMALA - Pg. TAMPAK 36,80 24 mth

6 PS. PEDATI - KERKAP 25,00 15 mth

19 LAIS - BINTUNAN 11,60 10 mth

15 SIBOLGA - BATAS TAPSEL 36,00 27 mth

7 INDRAPURA - TAPAN 19,50 21 mth

8 BTS.Kt PARIAMAN-MANGGOPOH 46,80 24 mth

10 SIMPANG EMPAT - SP.AIR BALAM 61,70 24 mth

12 KAMBANG - INDRAPURA 55,20 24 mth

14 PAINAN – KAMBANG 31,50 21 mth

16 SEBLAT – IPUH 34,50 21 mth

20 LUBUK ALUNG – SICINCIN 14,60 18 mth

21 LUBUK ALUNG – KURAITAJI 16,80 18 mth

9 RANTAU TIJANG-KOTA AGUNG 42,00 The Road has been constructed by MPW within 2011-2013. Road condition is good. Proposed to be deleted from the list of WINRIP's work program

18 MUKOMUKO-BTS SUMBAR 25,80 The Road has been constructed by MPW within 2011-2013. Road condition is good. Proposed to be deleted from the list of WINRIP's work program

Original target : 715,60 km ENVIRONMENT & SOCIAL SAFEGUARDPrequalification Detail Eng Design LARAP Study

Road Safety Owner's Estimate Appraisal & Public Consultation

Procurement & Sign Contr Bid Document LARAP Implementation

Preparation for Commencement of Work

Standard Biding Document

Rev-DED RS

DED

COWPROC

COW CONSTRUCTION

OE & BD

DED Rev-DED RSOE & BD

OE & BD

DED OE & BD

COW

CONSTRUCTION

SBD & OE + BD

SBD & OE + BD

PQ PROC

PROC

CONSTRUCTION

CONSTRUCTION

DED RSA & REVISED DED

CONSTRUCTION

PQRS

ProcCOWSBD

CONSTRUCTION

CONSTRUCTION

CONSTRUCTION

DED RSA & REVISED DEDOE & BD

DED RSA & REVISED DEDOE & BD

OEBD

DED

SBD & OE + BD

Rev-DED RS

DED Rev-DED RS

OE & BD

DED RSA & REVISED DEDOE & BD

CONSTRUCTION

PROC COW

Review DED & RS

Review DED & RS

Review DED & RS

Review DED & RS

Review DED & RS PQ

CONSTRUCTION

Review DED & RS PQ PROC COW

Review DED & RS PQ

CONSTRUCTION

COW CONSTRUCTION

PROC

Pack#

PACKAGE NAME 2012 2013 2014 2015 2016 2017 2018

PROC COW

PROC COW

PROC COW

CONSTRUCTION

CONSTRUCTION

CONSTRUCTION

CONSTRUCTION

CONSTRUCTION

COW

PROC COW

PROC COW

PROC

CONSTRUCTION

CONSTRUCTION

PROC COW

Project Timeline Schedule

December 31, 2018

Page 12: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

1 - 3

Length C'tionKm Period J N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D

Core Team Consultant (CTC) 40 mth IMPLEMENTATION Time extension for sevices

Design & Supervision Cslt (DSC) 42 mth IMPLEMENTATION Time extension for sevices #

TA for Dev.of Slope Stabilization, Design & M anagement 7 Jun'18

1 Krui - Biha 25,06 21 mth 8 Jan'14

2 Padang Sawah - Sp.Empat 40,70 24 mth 6 Jan'14

3 Manggopoh - Padang Sawah 32,00 24 mth 6 Jan'14

4 Ipuh - Bantal 42,45 24 mth 10 Jan'14

5 SIMPANG RAMPA - PORIAHA 9,70 18 mth 18 Jun'15 10 Apr'18

11 BANTAL - MUKOMUKO 50,65 24 mth 23 Feb'15 26 May'17

13 SP RUKIS - TJ KEMUNING 56,27 24 mth 15 May' 18

17 Sp.Gn.KEMALA - Pg. TAMPAK 35,91 24 mth 04 Sep'15 27 Dec'17

6 PS. PEDATI - KERKAP 20,89 15 mth 11 Mar'15

19 LAIS - BINTUNAN 10,81 10 mth 11 Mar'15 CONSTRUCTION 300+125+53 days 30 Jun '16

15 SIBOLGA - BATAS TAPSEL 36,00 27 mth 20 Nov'15 30 Jun' 18

7 INDRAPURA - TAPAN 19,50 21 mth 10 Dec'15 28 Jan' 18

8 BTS.Kt PARIAMAN-MANGGOPOH 46,80 24 mth PROC 23 Mar'16 31 Dec'17

12 KAMBANG - INDRAPURA 55,20 24 mth 28 Jul' 18

14 PAINAN – KAMBANG 31,50 21 mth PROC 13 Aug'16 17 Jun' 18

16 SEBLAT – IPUH 34,50 21 mth 08 Nov'16 30 Jul'18

20 LUBUK ALUNG – SICINCIN 14,60 18 mth 1 Sep'16 2 Mar'18

21 LUBUK ALUNG – KURAITAJI 16,23 18 mth 1 Sep'16 28 Jun'18

5A 0,69 5 mth 30 Nov'18

9 RANTAU TIJANG-KOTA AGUNG 42,00 To be cenceled

18 MUKOMUKO-BTS SUMBAR 25,80 To be Cenceled

Original target : 715,60 km ENVIRONMENT & SOCIAL SAFEGUARD

1st Revised target : 640,00 km Prequalification Detail Eng Design LARAP Study

2nd Revised target : 579,46 km Road Safety Owner's Estimate Appraisal & Public Consultation

Procurement & Sign Contr Bid Document LARAP Implementation

Preparation for Commencement of Work

Standard Biding Document

PQ

Review DED & RS

Review DED & RS

PROC

CONSTRUCTION 720 days

CONSTRUCTION 720 days22-Jul-15

PQ PROC

14-Apr-16

PROC

17-Mar-16

CONSTRUCTION 540 + 224 days

CONSTRUCTION 730 + 105 days

CONSTRUCTION 730 + 75 days

CONSTRUCTION 730 + 90 days 31-Mei-16

20-Jan-16

PQ

Pack# PACKAGE NAME

2012 2013 2014 2015 2016 2017 2018

PQRS

ProcCOWSBD

DED

OEBD

DED

NCB

NCB

DED

NCB

OE & BD

DED

19-Jun-13

PROC

DED

Rev-DED RS

ICB RSA & REVISED DED OE & BD

Review DED & RS

SBD & OE + BDReview DED & RS

Review DED & RS SBD & OE + BD

RSA & REVISED DED

ICB

ICB

ICB

ICB

ICB

CONSTRUCTION 640 + 93 days

Review DED & RS PQ

Review DED & RS

ICB

NCB

NCB

DED

PROC

CONSTRUCTION 720 daysICB

ICB

ICB

ICB

PROC

CONSTRUCTION 810 - 37 days

DED

CONSTRUCTION 630 days

23-Mei-16 CONSTRUCTION 720 - 132 days

NCB

NCB

NCB

OE & BD

SBD & OE + BD

DED RSA & REVISED DED

Penangan Lereng Ruas Sp. Rampa -Poriaha

30 Nov' 18

31 oct' 18

IMPLEMENTATION

31-Des-17

PROC

PROC

CONSTRUCTION 720 - 71 days

Rev-DED RS

Rev-DED RS

Rev-DED RS

CONSTRUCTION 450+90 days

CONSTRUCTION 540 - 53 days

CONSTRUCTION 540 - 53 days

CONSTRUCTION 630 - 114 days

PROCUREMENT

CONSTRUCTION 640 days

28 Jan'17

ConstructionDED EE,BD PROC

6-Nov-12

Actual Implementation Timeline of WINRIP

Page 13: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

1 - 4

1.2 Disbursement

Loan Allocation and Percent (%) Disbursement To Date

#REF! 1,25

0,00

10,00

20,00

30,00

40,00

50,00

60,00

70,00

80,00

90,00

100,00

Month

% C

ompl

ete Actual Expenditure USD 175,70 mil

(70,28%)

WINRIP ACTUAL PROGRESS UP TO AUGUST 2018 AND FORECAST UP TO DECEMBER 2018

ACTUAL August 2018

Original Forecast

Forecast Expenditure Rev USD 208,38 mil(83,35%)

Forecast August 2018

Deviation = - 13,07%

The total disbursement summary from the loan by The World Bank to the end of August 2018was USD 175,701,077.12 equivalent to approximately 70.28% of the loan funds. The followingtable summarizes the individual disbursements as calculated by CTC but retaining the totaldisbursement from Client Connection at the end of August 2018. Appendix A shows theOverall Loan Progress Status.

Category DescriptionLoan

RestructuringAmount US$

DisbursementThis Period

PreviousDisbursement

Totals Disbursedto End August2018 in US$

%Disbursed

1Part 1 Betterment andCapacity Expansion of

National Roads.225,400,000.00 1,417,193.08 164.076.757,21 165.493.950,29 73.42

2Part 2

Implementation Support17,000,000.00 0 10.207.126,83 10.207.126,83 60.04

3Part 3

Road Sector InstitutionalDevelopment

0 0 0 0 0

4Part 4

Contingency for DisasterRisk Response

0 0 0 0 0

Unallocated 7,600,000.00 0 0 0 0Original Loan

Amount 250,000,000.00 1,417,193.08 174.283.884,04 175,701,077.12 70.28

Breakdown of amount disbursed during the period (August 2018) are for “Statement of WorkAccomplished” for the following civil works contract package :

Package No.12 : MS Nos. 25-26 USD 1,417,193.08

The Ending balance for Special Account end of August 2018 USD 682,720.58

Page 14: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

1 - 5

1.3 World Bank Implementation Review Mission and Site VisitNot performed for this month.

1.4 Procurement of Civil Works Contract Under Category 1 of the Loan AgreementAs of end this reporting month, nineteen (19) contract packages are already procured and areeither completed, ten (13) packages had been took over to the employer, eight (4) packagesunder construction, one (1) package terminated and the remaining one (1) package iscancelled

Package No. 10 (Sp. Empat – Sp. Air Balam) is cancelled, because the road is still relatively inthe good condition and widening is not needed immediately.

The new civil work sub-project named Package No. 5A: Penanganan Lereng Ruas SimpangRampa – Poriaha has been approved by the World Bank to be funded within the WINRIPProject. This package is needed to handle extreme slope conditions in packet 05 at somespots, requiring treatment for slope stability and protection against road users. Procurementof this package has started on April 24, 2018 under e-procurement system at LPSE of Ministryof Public Works and Housing. This e-procurement used SPSE 3.6 application which wasbuilded by LKPP. Bid opening on May 16, 2018, from 61 registered bidders only 2 (two)bidders upload the bids for this package. POKJA has evaluated all the bids and the results is nobidder passed the qualification criteria. The Bank has issued No-Objection Letter for re-bidding this package with incorporation some suggestions from Bank and improvements tobidding document. Rebidding of this package has announced at LPSE of Ministry Public Worksand Housing on August 30, 2018.

Package 21: Lubuk Alung – Kuraitaji was terminated and to complete the remaining works, itis needed to carry out a new bidding called Package 21A : Lubuk Alung – Kuraitaji (CompletionStage). The World Bank has issued No-Objection Letter (NOL) on July 9, 2018 for carrying out anew bidding process for Package 21A. The bidding is scheduled for 2(two) months start inearly September and commencement of works will mid of November 2018.

1.5 Procurement of Consultancy Package under Category 2 of the Revised LoanAgreement Reallocation.

As of end this reporting month, three (3) consulting services are completely selected and arestill running. Consulting services under this category are following:

a. Technical Assistance for Core Team Consultant (CTC) to Support the ProjectManagement Unit of Western Indonesia National Roads Improvement Project(WINRIP);

b. Design and Supervision Consultant (DSC) of Western Indonesia National RoadsImprovement Project (WINRIP);

c. Technical Assistance for Development of Slope Stabilization, Design and Managementof Western Indonesia Roads.

Page 15: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

2 - 1

2 PROJECT DESCRIPTION

2.1 Background

The Government of Indonesia wishes to continue strengthening of the National Road system inIndonesia while the Eastern Indonesia National Roads Improvement Project (EINRIP which isassisted by AusAID through the Australian Indonesia Partnership or AIP), is providing supportprogram of National road and bridge improvement works in Eastern Indonesia. The WesternIndonesia National Road Improvement Project (WINRIP) will provide similar support for Nationalroad and bridge in the Sumatera region of Indonesia. The focus of WINRIP will be roadsadministered directly by the National Government, including those currently classified asProvincial, Kabupaten (District) or non-status roads which are in process of being reclassified asNational roads. In addition, provision will be made for major bridge repair works, rehabilitation,duplication and replacement as necessary to complement road betterment works.

2.2 Project Development

The loan effectiveness date for the WINRIP is 12 March 2012 and key project data is shown in thefollowing detail.

Key Project Data WINRIP Loan No. 8043-ID

Project Cost US$350 million

Original Loan Amount US$250 million

Revised Loan Amount N/A

Board Approval Date 26 May 2011

Loan Signing Date 14 December 2011

Effectiveness Date 12 March 2012

Disbursement (as of August 31, 2018) US$ 175,701,077.12 million (70.28%)Original Closing Date 31 December 2018

Environmental Category B-Partial Assessment

The IBRD loan amount is US$250 million. The Project is intended to finance a part of the DGHinvestment program for national roads with a particular focus on the Western corridor ofSumatera. The corridor is one of the three main corridors in Sumatera and connects the city ofPadang (with a population of around one million) to major towns along the west coast (Bukittinggi, Sibolga and Bengkulu). It also connects through connector roads on the West coast toMedan in the northeast and to Pekanbaru in the center of the island. The project has fourcomponents:

Project Component 1: Betterment and Capacity Expansion of National Roads

According to the Amendment No.4 Loan Agreement, this component will cover three workprograms of betterment and capacity expansion of approximately 579 km including replacement of160 meters of bridges. This civil works program will be executed in three Annual WorkPrograms(AWP), as summarized in Table 2.1. The table shows the IBRD assisted scope and costs ofcivil works at estimated current (year of implementation) prices, excluding taxes.

Page 16: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

2 - 2

Table 2.1 Proposed Physical Works by DGH Program

Type of WorksAWP-1 AWP-2 AWP-3

Km USDMillion Km USD

Million Km USDMillion

Road Betterment - - 53.10 22.77 - -

Capacity Expansion 137.10 79.70 314.60 127.67 207.60 74.58

Bridge works 0.100 1.94 - - 0.08 2.06

TOTAL(excluding tax @ current prices)

137.20 81.64 367.70 150.45 207.68 76.65

The batches of projects are termed Annual Work Programs (AWPs) in line with terminology used inother Bina Marga projects. They are not in fact “annual” programs as such but rather a series ofmulti-year programs, each commencing in consecutive years. Hence, hereinafter it will call as justWork Programs (WPs). It is expected that implementation of the first Works Program (WP-1) willcommence in the third quarter of 2013 and be completed by third quarter or late 2015. Thesecond Work Program (WP-2) is expected to commence in early 2014 and be completed by late2015 or middle 2016. The third Work Program (WP-3) is expected to commence in early 2015 andbe completed by mid-2017. The loan will be closed on December 2018.

Table 2.2 presents details of the First Works Program (WP-1). The four packages in this groupshould have been free from any land acquisition issues, but in fact two packages (Krui – Biha andManggopoh – Padang Sawah) had land issues which were solved by the DGH properly. Thus, thereare no foreseeable impediments to implementation.

Table2.2 IBRD Assisted WINRIP Civil Work WP-1

No Province LinkNo.

LinkName

Clas

s

Road

Typ

e

Road Works Bridge Works Total Cost

From

To Leng

th

Trea

tmen

t

Cost

(201

0)

No

Leng

th

Cost

(201

0)

2010

Pric

es

Equi

vale

nt

Km Km Km Rp mill m Rp mill Rp mill US$ mill

1 Lampung 053.0 Krui –Biha K1 IU 225.91 246.97 25.06 Bett’nt

to 7 m. 148,668 148,668 16.52

2 WestSumatera 047.2

PadangSawa –SimpangEmpat

K1 IU 0.0 40.70 40.70 Bett’ntto 7 m. 189,810 189,810 21.09

2a WestSumatera 34.1 AirGadan

gBridge K1 IU NewBridge 1 100 17.580 17,580 1.95

3 WestSumatera 047.1

Manggopoh –PadangSawah

K1 IU 102.2 134.2 32.0 Bett’ntto 7 m. 152,435 152,435 16.94

4 Bengkulu 015.3 Ipuh -Bantal K1 IU 0.0 42.45 42.45 Bett’nt

to 7 m. 226,275 226,275 25.14

Page 17: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

2 - 3

It should be noted that all road sub-projects have been subject to economic appraisal and haveestimated Economic Internal Rates of Return (EIRR) in excess of 15%. These were selected forinclusion and are subject to completion of environmental and social screening, to confirm thatthere is no land acquisition or resettlement requirements remain outstanding.

Final Engineering Designs, Engineer’s Estimates and bidding documents have been completed forall projects proposed for WP-1.

Sub-projects to be included in WP-2 and WP-3 have also been determined as listed in Table 2.3.Final Engineering Designs and Engineer’s Estimates for all WP-2 and WP-3 proposed works requirepreparation or finalization. In the cases of some projects, preliminary Engineering Designs wereprepared during Project preparation which will require review and possible amendment by theDesign and Supervision Consultant prior to procurement.

The revised costs presented in Table 2.3 are planning estimates only, and the revisedimplementation plan is based on the “Revised Implementation Timeline Schedule” of the civilworks.

Table2.3: IBRD Loan WINRIP Civil Work WP-2 and WP-3

NO. SUBPROJECT LINK NO. AND NAME LENGTH(KM)

ENGINEER’SESTIMATE(RP. MILL)

WIDTH(M)

REVISED IMPLEMENTATION PLAN

START DURATION(MONTHS)

WP-2

5. Sumut : Link No. 015.xx,Sp. Rampa – Poriaha 9.70 152,870 6.0 Mar 2015 18

6. Bengkulu : Link No. 010.0,Ps. Pedati – Kerkap 20.89 92,127 7.0 Mar 2015 15

7. Sumbar : Link No. 019.0,Indrapura – Tapan 19.50 178,600 7.0 Jan 2016 21

8. Sumbar : Link No. 024.0,Bts. Pariaman – Manggopoh 46.80 379,034 7.0 Jan 2016 24

9. Lampung : Link No. 026.1,Rantau Tijang - Kota Agung - - - - Cancelled

10. Sumbar : Link No. 034.1,Sp. Empat - Sp. Air Balam 61.70 515,842 7.0 - Cancelled

11. Bengkulu : Link No. 015.2,Bantal – Mukomuko 50.65 246,500 6.0 Feb 2015 24

12. Sumbar : Link No. 017.2,Kambang – Indrapura 55.20 451,810 7.0 Jan 2016 24

13. Bengkulu : Link No. 006.1,Simpang Rukis - Tanjung Kemuning 56.27 316,305 7.0 Jun 2015 24

WP-3

14.Sumbar : Link No. 017.1,Painan – Kambang 31.50 252,000 7.0 May 2016 21

Page 18: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

2 - 4

NO. SUBPROJECT LINK NO. AND NAME LENGTH(KM)

ENGINEER’SESTIMATE(RP. MILL)

WIDTH(M)

REVISED IMPLEMENTATION PLAN

START DURATION(MONTHS)

15. Sumut : Link No. 016.0,Sibolga - Bts. TapSel 36.00 376,479 7.0 Oct 2015 27

16.Bengkulu : Link No. 009.4,Seblat – Ipuh, including Air Galang andAir Guntung Bridges

34.500.052 241,500 6.0 May 2016 21

17. Lampung : Link No. 061.1,Sp. Gunung Kemala - Pugung Tampak

35.91 255,269 6.0 May 2015 24

18. Bengkulu : Link No. 015.3,Mukomuko - Bts. Sumbar - - - - Cancelled

19. Bengkulu : Link No. 009.1,Lais – Bintuan 10.81 35,886 7.0 Feb 2015 10

20. Sumbar : Link No. 002.0,Lubuk Alung – Sicincin 14.60 116.800 7.0 May 2016 18

21. Sumbar : Link No. 027.0Lubuk Alung – Kuraitaji 16.23 65,788 7.0 May 2016 18

5ASumut : Link No. 015.xx,Penanganan Lereng Ruas Sp. Rampa –Poriaha

0.69 65,726 - July 2018 5

Project Component 2: Implementation Support

This component provides consulting services to support project management and implementationso as to ensure implementation efficiency and overall quality of the works. It also includes fundsfor a small amount of training of DGH staff and for incremental operating costs for the project. Thiswill provide support to the MPWH for the implementation of the civil works, including: (a)provision of Core Team Consultants (CTC), Design and Supervision Consultants (DSC) and roadsafety audits; (b) Project management support and technical audits. This is directly related to theimplementation of the civil works and covers consulting services for design and supervision of thecivil works in Component 1; management support and technical audits to help improve the qualityof construction and support to governance improvements during procurement andimplementation; and a series of systematic road safety audits of road designs for all project roadsin Component 1. This is to ensure compliance with road safety standards and regulations, identifyroad hazards and undertake remedial treatments for safety improvements, (c) slope protectiondesign and management. This is related to Technical Assistance and Support to StrengthenDisaster Risk Mitigation in the Road Sector mainly to deal with stabilizing and strengthening, inparticular roadway side cut and high embankment slopes by providing appropriate slopeprotection structures. These activities initially is part of Component-3: Road Sector InstitutionalDevelopment, however, due to reallocation or realignment of funds, the propose work, “TechnicalAssistance for Development of Slope Stabilization, Design and Management” implementation hasbeen realigned to Component-2 : Implementation Support. This activity covers consulting servicefor design and management of slope protection. The revised Loan Category restructuring ispresented in Table 2.4 and revised implementation is based on the approval of GOI and WorldBank.

Page 19: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

2 - 5

Tabel 2.4

Project Management Core Team Consultants (CTC)

The CTC will provide support to the PMU and DGH in the management of the Project, based inJakarta. Their tasks include financial and progress monitoring and reporting, informationmanagement and dissemination, quality assurance and performance review for the Design andSupervision Consultants, implementation and monitoring of the anti-corruption action plan,support for project monitoring and evaluation, and support for implementation of a trainingprogram to support project management and implementation. The CTC contract No. 06-20/CTC/TA/LN/8043/1112 was signed on 5 November 2012 by both DGH and a Joint Venture ofPT. Perentjana Djaja, Yongma Engineering Co, Ltd, and PT. Epadascon Permata EngineeringConsultant.

Design and Supervision Consultants (DSC)

A Design and Supervision Consultant (DSC) will be responsible for design of WP-2 and WP-3 civilworks and supervision of all civil works. They will have the role of ‘Engineer’ under a FIDIC-typecontract. The tasks include the preparation and maintenance of a quality assurance plan,validation and updating of designs, supervision of all civil works, environmental and socialmonitoring and management, and support for financial and progress monitoring and reporting.The DSC will also be responsible for quality assurance of materials and workmanship, certifyingwhether or not contractors have achieved the required results, as well as documentation andreporting based on the financial management plan. They will prepare a Quality Assurance systemcovering all subprojects, and continuously monitor the effectiveness of their supervisionprocedures. The team will be contracted and managed by DGH through the Bina Marga RegionalOffice (Balai II), and will be based in Padang, West Sumatera.

CategoryOriginal Amount ofthe Loan Allocated

(expressed in USD)

Revised Amountof the Loan

Allocated(expressed in

USD)

Percentage ofExpenditures to be

financed (inclusive ofTaxes)

(1) Civil Works under Part 1 of theProject WP-l 220,400,000 225,400,000 70%

(2) Goods, Non-consulting Services,Consultants Services andIncremental Operating Costs* underPart 2 of the Project

16,000,000 17,000,000 100%

(3) Goods, Non-consulting services andConsultants' Services under Part 3of the Project

1,000,000 Cancelled Cancelled

(4) Works, Goods, Non-ConsultingServices, Consultants' Services andIncremental Operating Costs* underPart 4 of the Project

0 0 0%

(5) Unallocated 12,600,000 7,600,000 100%T O T A L : 250,000,000 250,000,000

Page 20: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

2 - 6

Technical Assistance for Development of Slope Stabilization, Design and Management WesternIndonesia Road

The Technical Assistance’s objective is to provide technical support to DGH in improving theircapacity for road slope/embankment protection and management. It will include identification andinventory of the existing slope and embankment conditions, assessment of future potential landslide/road erosion problems, development of risk maps, prioritization of high problem/high riskareas, and development of the Detail Engineering Designs for a limited amount of areas in theWestern Corridor of Sumatra6. It will also include the review (and revision) and preparing the newNational Standard and Manual (NSPM) related to the slope protection and capacity building. TheTA’s contract was signed on July 7, 2017 between DGH trough the Sub-Directorate of Geotechnicaland Slope Management of Directorate of Road Construction and PT. Egis International Indonesia inJV with PT. Disiplan Consult and PT. Widya Graha Asana.

Project Component 3: Road Sector Institutional Development

This component which is originally intended to provide technical assistance and support tostrengthen disaster risk mitigation in the road sector, including capacity building support for thenew environment/risk mitigation and road safety unit of DGH has been cancelled due to revisionof the loan allocation. In the meeting, DGH and World Bank agreed upon that DGH will conductanalytical work of an alternative design for road segment that pass through critical environmentalassets and vulnerable areas especially on slope protection design and management. Due todeletion of the allocated funds for Category 3 of the loan agreement and reallocated to Category 2to accommodate the implementation of Technical Assistance for Development of SlopeStabilization, Design and Management, into Component-2. The Loan Category restructuring can beseen in Table 2.4 page 2-5.

Project Component 4: Contingency for Disaster Risk Response

This special component will provide preparedness and rapid response to disaster, emergencyand/or catastrophic events as needed. This provisional zero dollar component will be added underthis project to allow for rapid reallocation of loan proceeds from other components understreamlined procurement and disbursement procedures.

2.3 Project Objective

The main objective of the program will be to increase the effective use of selected sections ofNational roads along the Western Sumatera Corridor by reducing road user costs, throughimproving the National road network especially in 4 (four) Provinces of Sumatera (North Sumatera,West Sumatera, Bengkulu and Lampung) and, where desirable, raise the road standard to that setby the Directorate General of Highways. This will contribute significantly to ensuring that thenational road network in the region provides acceptable standards of service and accessibility, andis capable of supporting local and regional economic development.

Page 21: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

3 - 1

3 CONSULTANCY SERVICES

3.1 CTC Consultants

3.1.1 Scope of Services

The CTC contract services originally were structured in its different project management elements.

* Inception Phase

A key activity during the inception phase will be to establish lines of communication with PMU-WINRIP and DSC’s Team Leader as well as with all Provincial Project Managers (Satker) wherethe first works are to be constructed under WP-1.

* Project Management and Support to PMU, including acting DSC until the DSC is established

The Terms of Reference (TOR) identify a number of sub-items to be performed by CTC. The keyfactor that will ensure success is that the CTC must work pro-actively and alongside PMUcounterparts and with DSC team in a professional manner based on mutual respect and trust.

* Preparation of Work Programs

The tendering process for WP 1 sub-projects began as soon as procurement committees havebeen formed and received appropriate training in the procurement procedures required. Theindicative work programs and cost estimates identified for WP-2 and WP-3 are subject toverification, and are likely to change following more detailed investigations. Furtherpreparation for WP-2 and WP-3 will be managed by the PMU supported by the CTC.

* Financial Monitoring

It will be the role of the CTC to first assess the level of understanding of the financialmanagement, monitoring and reporting procedures by the finance staff at the provincial andcentral level and subsequently devise an appropriate training program and assist the PMU intraining delivery.

* Project Progress and Performance Monitoring

CTC will monitor the loan project progress and prepare the report in monthly basis. In themeantime, GOI and the World Bank have agreed on a set of Key Performance Indicators (KPIs)to measure the project’s performance in achieving its stated development objectives. CTC willtherefore first concentrate on the establishment of precise definitions, calculation methodsand data collection procedures to monitor the KPIs.

* Support for the Implementation of the ACAP

The CTC will assist PMU and be responsible for ensuring the ACAP is properly implemented.And for revising the Project Management Manual on an annual basis is to incorporatenecessary improvements of process and procedure.

Page 22: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

3 - 2

* ESAMP and LARAP Implementation Monitoring

CTC will closely work with BLH and DSC and will monitor and report the action of theEnvironmental Management Plan on a periodical basis and/or as required.

* Training to Support Project Implementation

CTC is responsible for preparation and management of all training program required underWINRIP.

* Reporting

CTC is responsible for all reports required under the contract agreement with standardizeforms, charts and tables.

3.1.2 CTC Manning

CTC professional staffs involved in the project as of end of August 2018 are listed in Table 3.1.

The International Staff (Senior Highway Engineer, Senior Road Safety Audit Engineer and SeniorProcurement Specialist) have completed their respective engagements and man-months havedemobilized on March 31, 2014 and May 31, 2015, respectively.

The task of conducting final Road Safety Audit during post-construction phase which is supposedto be conducted by the Senior Road Safety Audit Engineer will be performed by the local RoadSafety Audit Engineer with man-months for the task to be covered by Amendment No.4 of theConsultancy Contract.

The Training Specialist has been demobilized since the end of August 2016 due to completion ofhis allocated man-month under Amendment No.4 of the Consultancy Contract.

Page 23: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

3 - 3

Table 3.1

40.00 - - - - - - Mahbub ur Rahman - - - - A

- 35.25 12.25 12.25 12.25 12,20 9.90 Per Weiss Pedersen Apr-2013 Mar-2014 12,25 0,00 B

- - 23.00 23.00 30,13 30,13 24,17 C.T. Arenas Apr-2014 Oct-2016 30,13 0,00 B

- - - - - 13,00 23,60 Lee Hee Won Dec-2016 - 19,00 3,00 -

Senior HighwayEngineer

8.00 12.50 14.00 14.00 14,00 14,00 14.30 Moon, Sung Hyung Mar-2013 Mar-2014 14,00 0.00 C

Senior Road SafetyAudit

6.00 11.00 13.00 13.00 11,00 11,00 8.97 Cho, Woo Sung Jun-2013 Mar-2014 11,00 0,00 C

18.00 - - - - - - Wasim ur Rahman - - - - A

- 16.00 16.00 16.00 16,00 16,00 14.03 Sanjeev Kumar Agarwal Jan-2014 May-2015 16,00 0,00 C

40.00 9,67 9,67 9.67 9,67 9,70 9.67 Besar Awiat Bowo Nov-2012 Sep-2013 9.67 0,00 B

- 30,33 6,66 6.66 6,66 6,70 6.63 Agus Setiawan Sep-2013 Mar-2014 6,66 0,00 B

- - 23.67 23.67 45,50 45,00 55.43 Julius J. Sohilait Apr-2014 - 52,00 3,00

36.00 7,37 7,37 7.37 7,37 7,40 7.37 Whiliyanto Nov-2012 Jun-2013 7.37 0,00 B

- 28.40 28,63 32.13 38,96 54,00 61.60 Lebiyartono Jul-2013 - 62,00 3,00

Quality AssuranceSpecialist-1

30.00 30.00 30.00 32.00 53,83 54,00 63.87 Uray Abdul Manaf Jul-2013 - 62,00 3,00 -

Quality AssuranceSpecialist-2

- - - - - - 11.00 Hafifuddin - - 17,00 3,00 -

36.00 10.37 10.37 10.37 10,37 10,40 10.37 Uus Martawijaya Nov-2012 Oct-2013 10,37 0,00 B

- 25,63 25,63 29.13 50,96 51,00 60.73 YD Tarwanto Oct-2013 - 58,00 3,00

EnvironmentalSpecialist

30.00 30.00 30.00 38.50 60,33 60,47 67.57 Leti Hermawati Dec-2012 - 68,47 3,00

36.00 9,37 9.37 9.37 9,37 9,40 9.37 M. Sutopo Nov-2012 Oct-2013 9,37 0,00 B

- 26,63 26,63 30.13 39,96 51,97 60.33 Witono Sep-2013 - 59,97 3,00

12.00 - - Darmansiri - - - - A

- 12.00 12.00 Muhdi - - - - A

- - 12.00 7.00 7,00 7,00 7.00 Mardiansyah Jul-2014 Mar-2015 7,00 0,00 B

12.00 - 4.10 4.10 4,10 4,13 4.10 Rudi Rungkat Nov-2012 Mar-2015 4.10 0,00 B

- 24.00 24.00 35.40 40,23 43,20 42.70 M. Edhi Fachri Mar-2013 - 43,20 0,00 C

30 - - - - - - Agung Lukito - - - - A

- 25.00 25.00 34.00 55,83 56,00 66.47 Sony Thamrin May-2013 - 64,00 3,00 -

CommunityDevelopment Officer

36.00 36.00 36.00 38.00 59,83 95.93 67.33 Yakobus Jan-2013 - 66,93 3,00 -

Road Safety AuditEngineer

25.00 25.00 19.00 21.00 42,83 42,97 50.80 Aditya Moraza Alwi Jun-2014 - 50,97 3,00 -

Bridge Engineer 5.00 5.00 5.00 5.00 5,00 5,00 4.93 Harimurti Suprihantoro Apr-2013 Aug-2013 5.00 0.00 C

Training Specialist - 12.00 12.00 25.00 30,83 31,23 31.07 Roedjitarjo Jan-2014 Aug-2016 31,23 0,00 C

Traffic Engineer - - - 1,00 7,00 7,00 7.00 Harianto Parman Mar-2015 - 1,00 6,00 D

Contract Doc.Specialist

- - - - - 14,00 25.00 M Edhi Fachri Nov-2016 - 22,00 3,00 -

RemarksA - Not able to mobilizied due to poor health or personal reasonsB - Resigned due to personal reasons or poor healthC - Task assigment completedD - Intermittent assignment to update AADTE - Man-months untilNovember 30, 2018 to be covered Amendment No.6

RemarksAmendNo.5

Team Leader

Senior ProcurementSpecialist

Assistant TeamLeader

OriginalContract

AmendNo.1

AmendNo.2

POSITION

FinancialManagement

Specialist

Social ImpactSpecialist

ProcurementSpecialist-1

ProcurementSpecialist-2

ManagementInformationSpecialist

Highway Engineer

Man -Month

RemainingAmend

No.3

Name MobilizedDemob-

ilized

Man - MonthUsed as of end of

August 2018Amend

No.4

Man - Months Duration

AmendNo.6

Page 24: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

3 - 4

3.1.3 CTC Contract

The CTC contract for “Western Indonesia National Roads Improvement Project” (Contract No.06-20/CTC/TA/LN/8043/1112) was signed on 05 November 2012. The contract is between theGovernment of Indonesia represented by Directorate General of Highways in the Ministry of PublicWorks and PT. Perentjana Djaja in joint venture with Yongma Engineering Co.Ltd. and PT.Epadascon Permata Engineering Consultant.

The Notice To Proceed was issued by letter dated 6 November 2012 from the PPK, and the officialstarting date of the contract was set at 6 November 2012.

Likewise, Amendment No. 1 to the original contract was signed on 25 October 2013 to coverall requirements of the CTC are summarized below.

* Replacement of the Senior Procurement Specialist* Extending the assignment of the Senior Highway Engineer.* Extending the assignment of the Senior Road Safety Audit Engineer.* Extending the assignment of the Procurement Specialist 2 and replacement of the

Procurement Specialist 1.* Adding the new position of Bridge Engineer.* Adding the new position of Training Specialist, and* Adding the new position of Road Safety Engineer.

Amendment No. 2 to the Original Contract and Amendment No. 1 was signed on September 3,2014 to cover requirements of CTC are enumerated as follows :

* Additional / Modification to Terms of Reference (TOR)* Amendment to the Team Composition and Staffing Schedule* Replacement of Foreign and Local Consultants* Adjustments of Remuneration paid in foreign currency and local currency* Adjustment inputs of personnel* Modification to various reimbursable and provisional sum to match the actual requirement

Amendment No.3 to the current CTC Contract (Original Contract and Amendments 1 and 2 wassigned on November 30, 2015 which is in line with the Updated Timeline Bar Schedule takinginto consideration the current and look ahead situations of the WINRIP program.

Based on the current progress of the Project, the services of several local professional and sub-professional staff have been extended beyond the end of the respective dates of completionassignments under Amendment No. 2.

In addition, new position of Traffic Engineer for local professional staff have been added toconduct traffic surveys on six (6) selected road links within the WINRIP Program in order toupdate the AADTs and to prepare a “Technical Analysis of the Annual Average Daily Traffic”.

Page 25: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

3 - 5

Amendment No.3 covers the requirements of CTC are as follows:

* Amendment to the team composition and staffing schedule* Adjustment of inputs of personnel* Adjustment of remuneration paid in local currency* Adding the new position of Traffic Engineer* Modification to various reimbursable to match the actual requirements.

Amendment No. 4 to the current CTC Contract (Original Contract and Amendments 1, 2 and 3)was signed on March 4, 2016 and to expire or completed on December 31, 2017, the same dateas the expiry/closing date of the loan agreement.

Based on the current progress of the Project, services of professional international and local staffas well as local sub-professional staff have been extended beyond their respective dates ofassignment engagement covered by Amendment No. 3.

Amendment No.4 covers the requirements of CTC are as follows:

* Consultancy services time extension* Additional/Modification to TOR/Terms of Reference* Adjustment of input schedule for Professional Staff, Sub Professional and Supporting Staff* Amendment to the Team Composition* Amendment of the Staffing Schedule* Modification to the Provisional Sums* Adjustment of Remuneration paid in foreign currency and local currency* Adjustment to the reimbursable expenses* Amendment to Clause 6.1(b) of the Special Condition of Contract

Proposed Amendment No.5 to the current CTC Contract will cover the following requirementsof CTC :

* Adjustment of input schedule for professional staff, sub-professional and supporting staff.* Amendment of Staffing schedule.* Adjustment of remuneration covered by Special Conditions of the Contract, Clause 6.2 (a).* Adjustment of cost estimates for foreign and local currencies.

Amendment No.6 to the current CTC Contract cover the following requirements of CTC :* Additional/Modification to Terms of Reference (TOR);* Additional Professional Staff (Key Personnel);* Adjustment of input schedule for Professional Staff* Adjustment to the Reimbursable Expenses* Adjustment of Cost Estimate in Foreign and Local Currency

Amendment No.7 to the current CTC Contract cover the following requirements of CTC :* Adjustment of Price

Page 26: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

3 - 6

Presented in Table 3.2 is the current status of CTC contract.Table 3.2

Description USD IDR

Original Contract including 10% VAT 1,404,370 23,556,940,000

Amendment No.1 including 10% VAT 1,447,517 24,668,792,500

Variance Against Original Contract +3,07% +4,72%

Combine Variance Against Original Contract +4.12%

Amendment No. 2 including 10% VAT 1,509,117 24,704,544,150Variance Against Original Contract +7,46% +4,87%Combine Variance Against Original Contract +5.81%Amendment No.3 including 10% VAT 1,473,917 26,328,054,500Variance Against Original Contract +4.95% +11.76%Combine Variance Against Original Contract +9.29%Amendment No. 4 including 10% VAT 1,918,158 40,878,169,529Variance Against Original Contract +36.58% +73.53%Combine Variance Against Original Contract +60.12%Amendment No. 5 including 10% VAT 1,595,403.33 41,545,386,446Variance Against Original Contract 13.69% 76.36%Combine Variance Against Original Contract 53.58%Amendment No. 6 including 10% VAT 1,819,253.33 48,653,875,746Variance Against Original Contract 29.54% 106.54%Combine Variance Against Original Contract 68.04%Amendment No. 7 including 10% VAT 1,847,388.04 50,707,302,309Variance Against Original Contract 31.55% 115.25%Combine Variance Against Original Contract 73.40%

Note : Combine variance (USD+IDR) is based on 1 USD = Rp. 9,558 exchange rate used during thetime of signing the original Contract Agreement.

3.2 DSC ConsultantsThe Design and Supervision Consultant (DSC) is responsible to design of WP-2 and WP-3 civil worksand supervision of all civil works. They will assume the role of ‘Engineer’ under a FIDIC-typecontract. The tasks include the preparation and maintenance of a quality assurance plan,validation and updating of designs, supervision of all civil works, environmental and socialmonitoring and management, and support for financial and progress monitoring and reporting.The DSC is also be responsible for quality assurance of materials and workmanship, certifyingwhether or not contractors have achieved the required results, as well as documentation andreporting based on the financial management plan. They will prepare a Quality Assurance systemcovering all subprojects, and continuously monitor the effectiveness of their supervisionprocedures. The team is being contracted and managed by DGH through the Bina Marga RegionalOffice (Balai III), and is being based in Padang, West Sumatera.

DSC has been established in Balai II Padang following the contract signing on 11 June 2013between Balai II and Renardet SA in joint venture with PT. Cipta Strada, PT. Daya Creasi Mitrayasa,

Page 27: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

3 - 7

PT. Seecons and PT. Yodya Karya. The Notice To Proceed was issued by the Balai II on 19 June2013.

Shown in Table 3.3 is the present status of the Design Supervision Consultant (DSC) contract.

Table 3.3

Description USD IDR

Original Contract plus 10% VAT 902.660 57,000,575,500

Addendum No.3 plus 10% VAT 1,062,534 70,781,353,406

Variance Against Original Contract +17.71% +24.18%

Addendum No.2 plus 10% VAT 848,034 59,973,161,962

Variance Against Original Contract -6.05% +5.22%

Addendum No.3 plus 10% VAT 1,062,534 70,781,353,406

Variance Against Original Contract +17.71% +24.18%Note:

1) Addendum No.3 was approved by DGH on 22 December 2017 with World Bank concurrence andissuance of No Objection Letter (NOL)

3.3 Technical Assistance for Development of Slope Stabilization, Design andManagement

The TA’s objective is to provide technical support to DGH in improving their capacity for roadslope/embankment protection and management. It will include identification and inventory ofthe existing slope and embankment conditions, assessment of future potential land slide/road erosion problems, development of risk maps, prioritization of high problem/high riskareas, and development of the Detail Engineering Design for a limited amount of areas in theWestern corridor of Sumatra. It will also include the review (and revision) of the NationalStandard and Manual (NSPM) related to the slope protection, and capacity building.

Following the problem that arise in Civil Works of WINRIP especially in related to slopestability, the Consultant is assigned to design the slope stability in Package No. 5 : Sp. Rampa –Poriaha as one of the 5 (five) priority locations. The expected final outputs are designstructure of slope stability and structure of road user safety against landslide include designdrawing, bill of quantities and material specification to be additional contract for Package No.05 above. Until this month the consultant had been completed the evaluation for priotitylocation with highest risk based on Pusjatan Guideline. There are 5 location with highest risk asfollows: 1 location in North Sumatera (Ruas Rampa – Poriaha), 1 location in Lampung (Ruas Sp.Gunung Kemala – Pg Tampak), 1 Location in West Sumatera (Ruas Bukit Putus – Teluk Bayur) and 2location in Aceh (both on Ruas Batas Kota Banda Aceh – Batas Aceh Barat). DED for slopetreatment at Sp. Rampa – Poriaha has been complete. For others, remaining 4 DEDs hadpresented in a workshop on May 30, 2018 and inputs from workshop audiences will beaccommodate in final DED, meanwhile for 4 (four) others design works still ongoing andplanned to be completed in next month.For other assignment of TA, the consultant had been conducted desk study to identify, reviewand conduct a preliminary inventory of the road sections/areas that have already slope andembankment problems and those that are prone to the erosions/landslides. Furthermore,field surveys have been conducted along west coast of Sumatera Island on 526 spots identifiedby desk study, resulting from this survey and desk study would be presented as the Risk Mapof slope stability along West Coast of Sumatera Island. Review of some NSPMs related to slope

Page 28: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

3 - 8

treatment on road project also still ongoing then three capacity building workshops plan to bearrange on early June.The NSPM Product for Guidelines and Specifications have been presented in the workshop onJkt date, 28-May-2018 input from participants will be accommodated in the final product.Capacity building - the final workshop that is planned to be held early June is postponed dueto enter the period before Idul Fitri, The workshop participants will be invited are busy withRamadan event. Now the service is still in process to amend contract related to person’schanges and schedule of workshop.

Page 29: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

4 - 1

4 CIVIL WORKS

4.1 Detailed Design PreparationFinal Engineering Designs, Engineer’s Estimates and bidding documents have been completed for allprojects proposed for WP-1, WP-2, and WP-3.

A brief status of the eighteen (18) sub-projects relative to the procurement of Civil works contractsand implementation can be found in “Implementation Status” table on Page 1-1 of this Report.The progresses of road safety audit are shown in Appendix B.

4.2 Procurements

Procurement shall be conducted under the Bank’s Procurement Procedures as mentioned in the LoanAgreement. The International Competitive Bidding (ICB) based on the Bank letter Ref. WINRIP/136 willapply to the packages with the construction estimated cost of more than US$ 25 Million to comply withthe new Bank’s threshold for ICB. According to the GOI regulation, a prequalification shall be applied forthe packages with the construction estimated cost more than IDR 10 Billion. Review from previousprocurement process, the World Bank in the Aide Memoire requested to GOI, for next 4 ICB subprojectsqualification still used Pre-Qualification and for remaining sub-project must be process with PostQualification. As well as for all NCB the World Bank also requested to follow Post Qualification inprocurement process.

As of this reporting month, a more detailed current updates are fully indicated in Sub-Chapter 1.4Procurement of Civil Works Contract Under Category 1 on Page 1-5 of this Report.

Under Category 3 of Loan Agreement the three (3) consultancy packages (capacity building for disasterrisk reduction, environmental management and road safety) has been cancelled. As a result of thecancellation of the three (3) Technical Assistances, the “Technical Assistance for Development of SlopeStabilization, Design and Management” has been included as replacement, but to be part of the LoanCategory-2;

Procurement update of the new consultancy package can be found in Sub-Chapter 1.5 Procurement ofConsultancy Package under Category 2 on Page 1-5 of this Report.

The WINRIP updated Procurement Plan and Progress is shown in Appendix F.

4.3 Civil Works Implementation

As of end of this reporting month, seven (7) of contract packages were previously completed andcurrently under defects liability period for twenty four (24) months effective on the day the TOCswere issued and ten (10) packages are currently under construction.

Details of each contract package are shown in Table 4.1.

Page 30: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

4 - 2

Table 4.1

ProgramContractPackage

#Contractor Name of Road Province Contract

Signed

Commencement of

Work

OriginalTime

Extension/Contraction

Revised

ContractAmount

ContractTime

CompletionDate Contract Amount Contract

TimeCompletion

Date

AWP-1

1 PT. Jaya KonstruksiManggala Pratama Tbk Biha - Krui Lampung Nov 25,

2013 Jan 8, 2014 134,909,211,000 640 CD Oct 9, 2015 93 CD 149,193,782,000 733 CD Jan 20, 2016

2PT.Jaya Konstruksi ManggalaPratama Tbk

Padang Sawah –Sp. Empat includingAir Gadang

WestSumatera Dec 6, 2013 Jan 6, 2014 197,936,699,000 730 CD Jan 5, 2016 105 CD 247,572,130,000 835 CD Apr 14,

2016

3 PT. Jaya KonstruksiManggala Pratama Tbk

Manggopoh –Padang Sawah

WestSumatera Dec 6, 2013 Jan 6, 2014 143,688,963,000 730 CD Jan 5, 2016 75 CD 183,452,130,000 805 CD Mar 17,

2016

4 PT. Waskita Karya and PT.Mulya Turangga (JO) Ipuh - Bantal Bengkulu Nov 14,

2013 Jan 13, 2014 186,936,750,000 730 CD Jan 12, 2016 90 CD 212,290,705,872 820 CD May 31,2016

AWP-2

5 PT. Nusa KonstruksiEnjiniring Tbk.

Sp. Rampa -Poriaha

NorthSumatera

March 17,2015

June 18,2015 107,321,260,310 540 CD Dec 8, 2016 455 CD 130,143,384,830 995 CD April 10,

2018

6 PT. Waskita Karya (Persero)Tbk. Ps. Pedati - Kerkap Bengkulu Feb 27,

2015Mar 11,

2015 86,517,470,000 450 CD Jun 2, 2016 240 CD 118,444,156,000 690 CD Jan 28, 2017

7 PT. Adhi Karya Indrapura – Tapan WestSumatera

Nov 26,2015

Dec 10,2015 129,699,900,000 630 CD Aug 30,

2017 151CD 129,699,900,000 781 CD Jan 28, 2018

8 PT. PP/PT. Statika MitraSarana J.O

Bts. Kota Pariaman- Manggopoh

WestSumatera Jan 28, 2016 Mar 23,

2016 355,500,000,000 720 CD Mar 12,2018 -71 CD 378.042.000.000 649 CD Dec 31,

2017

11 PT. Hutama Karya/PT. DayaMulya J.O.

Bantal –Mukomuko Bengkulu Dec 18,

2014Feb 23,

2015 228,899,717,000 720 CD Feb 11,2017 104 CD 263,656,603,000 824 CD May 26,

2017

12 PT. Lancar Jaya/PT. CahayaT.A. J.O

Kambang –Indrapura

WestSumatera Jan 28, 2016 May 23,

2016 358,650,400,000 720 CD May 12,2018 77 CD 358,650,400,000 797 CD Jul 28, 2018

13 PT. Waskita Karya (Persero)Tbk.

Sp. Rukis – TJ.Kemuning Bengkulu Dec 18,

2014July 22,

2015 292,700,000,000 720 CD July 10,2017 309 CD 305,889,100,000 1029 CD May15,

2018

AWP-3

14 PT. Yasa PatriaPerkasa/Conbloc, JO Painan – Kambang West

Sumatera Jun 1, 2016 Aug 3, 2016 214,327,429,680 630 CD Apr 12,2018 94 CD 214,327,429,000 724 CD Jul 27, 2018

15 PT. PembangunanPerumahan (Persero)

Sibolga – Bts.Tapsel

NorthSumatera

July 13,2015

Nov 20,2015 260,100,000,000 810 CD Feb 6, 2018 144 CD 260,100,000,000 954 CD Jun 30, 2018

16 KSO PT Yasa PP-MultiStructure Ipuh - seblat Bengkulu Oct 28, 2016 Nov 8, 2016 211,374,500,000 630 CD July 30,

2018 - 211,374,500,000 630 CD Jul 30, 2018

17 PT. Jaya KonstruksiManggala Pratama Tbk

Sp. Gunung Kemala– Pugung Tampak Lampung Nov 17,

2014 Sept 4, 2015 199,551,000,000 720 CD Aug 23,2017 126 CD 211,712,283,000 846 CD Dec 27,

2017

19 PT. Roda Tekindo Purajaya Bintunan - Lais Bengkulu Feb 27,2015

Mar 11,2015 33,689,452,000 300 CD Jan 4, 2016 178 CD 44,419,760.000 478 CD Jun 30, 2016

20 PT. Nindya Karya Lubuk Alung –Sicincin

WestSumatera Jun 1, 2016 Sept 1, 2016 113,818,300,000 540 CD Feb 22,

2018 6 CD 113,818,300,000 546 CD Feb 28,2018

21 PT. Multi Structure Lubuk Alung –Kuraitaji

WestSumatera Jun 1, 2016 Sept 1, 2016 126,301,900,000 540 CD Feb 22,

2018 126 CD 126,301,900,000 666 CD Jun 28, 2018

Page 31: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

4 - 3

4.4 Civil Works ProgressActivities done during this month on the on-going construction packages were repair and restoration ofdeteriorated existing pavements, roadway excavation, embankment formation, spreading of granularpavement for roadway widening, asphalt paving, structural works, construction of stone masonry sideditches, stockpiling of raw material, production of crush aggregates, other minor works, bridge construction,finalization of “Field Engineering” surveys.

The four (4) contract packages under implementation program AWP-1 were already completed. The one (1)package was finally handed over after the defects liability period for two (2) years to the employer and thethree (3) packages are still undertaken for the final hand-over inspection.

Under the implementation program AWP-2 and AWP-3, the nine (9) packages were already completed andnow under defects liability period for two (2) years. There are currently four (4) contract packages that areon-going construction implementation. Physical progress of four (4) of the packages are lagging far behindschedule with negative slippages from -10.50% to -19.72% and the one (1) package is to be terminate by theemployer.

Progress status of the on-going civil works contracts as of this reporting period are shown in Table 4.2.

Following are brief status of the on-going construction contract packages:

Package No. 1 : Biha – KruiThe contract package is completed on January 20, 2016 and provisionally handed over to the Employer and“Defects Notification Period” of two (2) is completed on January 20, 2018 and finally handed over to theEmployer.

A more detailed previous status during the whole duration of the contract implementation of this Package ispresented in ANNEX P-I Executive Summary Report.

Package No. 2 : Padang Sawah – Sp. Empat (Including Air Gadang Bridge)The contract package is completed on April 14, 2016 and provisionally handed over to the Employer andcurrently Final Hand Over (FHO) inspection is still going on.

ANNEX P-2 Executive Summary Report present a more detailed status during the whole duration of thecontract implementation of the Contract Package.

Package No. 3 : Manggopoh – Padang SawahThe contract package is completed on March 17, 2016 and provisionally handed over to the Employer onMarch 17, 2016 and currently Final Hand Over (FHO) inspection is still going on.

A more detailed status of the project progress during the whole duration of the contract implementationare shown in ANNEX P-3 “Executive Summary Report”.

Package No. 4 : Ipuh – BantalThe contract package is completed on May 31, 2016 and provisionally handed over to the Employer on May31, 2016 and currently Final Hand Over (FHO) inspection is still going on.

ANNEX P-4 “Executive Summary Report” shows the details and status of the project.

Page 32: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

4 - 4

Table 4.2

ProgramContractPackage

#Contractor Name of Road

Target ProgressSchedule Ending

August 2018

Actual ProgressAccomplished Slippage Time Elapsed Remaining

Time Remarks

AWP-1

1 PT. Jaya Konstruksi ManggalaPratama Tbk Biha - Krui * - - - - Completed

PHO : January 20, 2016

2PT. Jaya Konstruksi ManggalaPratama Tbk Padang Sawah –

Sp.Empat incl.Air Gadang * - -- - -Completed

PHO : April 14, 2016

3 PT. Jaya Konstruksi ManggalaPratama Tbk

Manggopoh – PadangSawah * - - - - Completed

PHO : March 17, 2016

4 PT. Waskita Karya and PT.Mulya Turangga (JO) Ipuh - Bantal * - - - - Completed

PHO : May 31, 2016

AWP-2

5 PT. Nusa Konstruksi Enjiniring Sp. Rampa - Poriaha 100% 95.28% -4.72% Contract amount reduced4.72% (Revised BOQ)

CompletedPHO : April 10, 2018

6 PT. Waskita Karya Tbk Ps. Pedati – Kerkap * - - - - CompletedPHO : January 28, 2017

7 PT. Adhi Karya Indrapura - Tapan * - - - - CompletedPHO : January 28, 2018

8 PT. PP/PT. Statika Mitra J.O Bts. Kota Pariaman –Manggopoh * - - - - Completed

PHO : December 31, 2017

11 PT. Hutama Karya/ PT. DMT Mukomuko - Bantal * - - - - CompletedPHO : January 28, 2017

12 PT. Lancarjaya/PT. CahayaT.A. JO Kambang – Indrapura 100% 80.28% -19.72% 103.52% -28 CD Based on revised contract time

and schedule

13 PT. Waskita Karya (Persero)Tbk Sp. Rukis – Tj. Kemuning * - - - - Completed

PHO : May 15, 2018

AWP-3

14 PT. Yasa – PT. Conbloc (JO) Painan – Kambang 100% 81.02% -18.98% 104.01% -29 CD Based on revised contract timeand schedule

15 PT. PembangunanPerumahan (Persero) Sibolga – Bts. Tapsel 100% 80.50% -19.50% Contract amount reduced

19.5% (Revised BOQ)Based on revised contract timeand schedule

16 PT Yasa-Multi Structure, Jo Seblat –Ipuh 100% 89.50% -10.50% 104.13% -26 CD

17 PT. Jaya Konstruksi ManggalaPratama Tbk

Sp. Gn Kemala – Pg.Tampak * - - - - Completed

PHO : December 27, 2017

19 PT. Rodatekindo Purajaya Lais – Bintunan * - - - - CompletedPHO : June 30, 2016

20 PT. Nindya Karya Lubuk Alung – Sicincin * - - - - CompletedPHO : March 2, 2018

21 PT. Multi Structure Lubuk Alung – Kuraitaji 100% 55.79% -44.21% - - Contract To Be Terminated* Under defects liability period for 720 calendar days.

Page 33: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

4 - 5

Package No. 5 : Sp. Rampa – Poriaha

The contract package is completed on April 10, 2018 and provisionally handed over to the Employer andcurrently under “Defects Notification Period” until after two (2) years reckoned from the issuance of TOC.

ANNEX P-5 “Executive Summary Report” shows the Contractor’s Progress Schedule.

Package No. 6 : Kerkap – Ps. Pedati

The contract package is completed on January 28, 2017 and provisionally handed over to the Employer andcurrently under “Defects Notification Period” until after two (2) years reckoned from the issuance of TOC.

ANNEX P-6 “Executive Summary Report” shows the complete details of the contract package.

Package No. 7: Indrapura – TapanThe contract package is completed on January 28, 2018 and provisionally handed over to the Employer andcurrently under “Defects Notification Period” until after two (2) years reckoned from the issuance of theTOC.

A more detailed status of the project progress during the whole duration of the contract implementationare shown in ANNEX P-7 “Executive Summary Report”.

Package No. 8 : Bts. Kota Pariaman - ManggopohThe contract package is completed on December 29, 2017 and provisionally handed over to the Employerand currently under “Defects Notification Period” until after two (2) years reckoned from the issuance of theTOC.

A more detailed status of the project progress during the whole duration of the contract implementationare shown in ANNEX P-8 “Executive Summary Report”.

Package No. 11 : Bantal - MukomukoThe completion date is on 26, May 2017 and the inspection for the provisional hand-over is already doneand the process verbal has been issued on 19, May 2017.

For more detailed of the Contract Package, refer to ANNEX P-11 “Executive Summary Report”.

Package No. 12 : Kambang - IndrapuraThe work progress of this reporting month, August 2018 is achieved of only 3.33% and the Accumulatedprogress as of this month is reached at only 80.28% in spite that the completion date is on 28, July 2018.

The main reasons of delay of progress are the lack of operation fund of the contractor and sudden increaseof prices for Asphalt Bitumen due to rapid devaluation of rupiah and cement which are much affected tothe operation fund of the contractor.

The contractor had proposed the extension of time for the completion and is waiting for the approved.

Details of the Contract Package are shown in ANNEX P-12 “Executive Summary Report”.

Package No. 13 : Sp. Rukis – Tj. KemuningThe packages is under the inspection of provisional hand over.Details of the work progress are shown in ANNEX P-13 “Executive Summary Reports.

Page 34: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

4 - 6

Package No. 14: Painan - KambangThe work progress of this reporting month, August 2018 is achieved of only 1.10% and the accumulatedprogress is reached at only 81.02% in spite that the completion date is on 27, July 2018.

The main reason of delayed progress is the lack of operation fund of the contractor.

In this regard, the Balai Office III is looking for the resolutions and counteneasures.

ANNEX P-14 “Executive Summary Report” shows the complete details of the project.

Package No. 15: Sibolga – Bts. TapselThe work porgress as of this month is achieved of 74.42% even though the completion date is on 30, June2018.

The main reasons of delayed progress are the unsettled Land Acquisition area mostly situated in pinangsoriarea, around 3 km long and reduction of contract amount due to decrease of quantities, especiallymortared, stonework, selectedembankment, etc.

In this regard, the Balai Office and PPK are looking for resolutions though site investigation.

Detailed and work progresses of the contract package are shown in ANNEX P-15 “Executive SummaryReport”.

Package No. 16: Seblat – IpuhDuring this reporting month, August 2018, the work progress is only 0.01% and the accumulated workprogress is still 89.50% even though the completion date is on 30 July 2018.

The main reason of delayed progress is also the serious lack of operation fund of the contractor. Butrecently the contractor have resumed to work in normal, the A/P paving work, drainage works which arethe major remaining works.

The contractor proposed the extension of time and the Balai Office under reviewing.

ANNEX P-16 “Executive Summary Report” shows the complete details and work progress of the project.Package No. 17 : Sp. Gunung Kemala – Pg. TampakThe contract package is completed on December 26, 2017 and provisionally handed over to the Employerand currently under “Defects Notification Period” until after two (2) years reckoned from the issuance of theTOC.

ANNEX P-17 Executive Summary Report present a more detailed status during the whole duration of thecontract implementation of the Contract Package.

Package No. 19 : Lais – BintunanThe contract package is completed on June 30, 2016 and provisionally handed over to the employer andcurrently under “Defects Notification Period” until after two (2) years reckoned from the issuance of theTOC.

Complete details of the contract package are shown in ANNEX P-19 “Executive Summary Report”.

Package No. 20 : Lubuk Alung - SicincinThe contract package is completed on March 2, 2018 and provisionally handed over to the Employer and

Page 35: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

4 - 7

currently under “Defects Notification Period” until after two (2) years reckoned from the issuance of theTOC.

A more detailed status of the project progress during the whole duration of the contract implementationare shown in ANNEX P-20 “Executive Summary Report”.Package No. 21 : Lubuk Alung - KuraitajiThis package will be terminated by the employer and remaining works will be performed by the newcontractor who is a successful bidder through the procurement process.ANNEX P-21 “Executive Summary Report” shows the Contractor’s schedule and work progress.

4.5 Quality AssuranceThe DSC will be responsible for quality assurance of materials and workmanship, certifying whether or notcontractors have achieved the required results, as well as documentation and reporting based on thefinancial management plan. They will prepare a Quality Assurance system covering all subprojects, andcontinuously monitor the effectiveness of their supervision procedures.

Following are current problems which were the same problems during the preceding month and issues

relative to the execution of the works and quality assurance:

Package No.1 : Krui - Bihaa) Completed.b) Currently under defects notification period for two (2) years until January 17, 2018.c) Both TFAC findings follow-up formal report has been approved by World Bank on 14th September,

2016d) CTC site visit 3rd with TFAC WB on 23 November 2017, deadline submit formal to WB on January 09,

2018. CTC have been receipted informal report from PPK but not yet approval by CTC on 22February 2018.

Package No.2 : Padang Sawah – Sp. Empata) Completed.b) Presently under defects notification period for twenty four (24) months until April 18, 2018.c) Since the design and construction of side cut slope protection works were not included in the

original contract design/construction have to be implemented under a new contract.d) CTC site visit 3rd with TFAC WB on 18 January 2017, quality inspection report of the WB has been

received by the PPK, Contractor on 7 February 2017.In accordance with the PMM WINRIP deadline follow up report should be completed and approvedless than two months from the time the team TFAC visit and according to records World Bankdeadline TFAC follow-up report was approve on 22 March 2017.

e) Based on the letter Ka.Balai III dated April 17, 2017, to the Satker PJN 1 Prov. West Sumatra that nolater than April 25,2017, the follow-up report on the findings of TFAC package 02 (third visit afterPHO) must have been submitted to Balai III Padang.

f) The informally approved of TFAC finding package 02 after PHO on September 04, 2017 by WorldBank.

g) Formaly from Director PJJ to World Bank on October 16, 2017.

Package No.3 : Manggopoh – Padang Sawaha) Completed.b) Currently under defects notification period for two (2) years until March 16, 2018.

Page 36: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

4 - 8

c) Since the Design and construction of side cut slope protection works were not included the originalcontract design/construction have to be implemented under a new contract.

d) CTC site visit 3rd with TFAC WB on 18th January 2017 , quality inspection report of the WB has beenreceived by the PPK, Contractor on 23rd February 2017.In accordance with the PMM WINRIP deadline follow up report should be completed and approvedless than two months from the time the team TFAC visit and follow-up report findings TFACimmediately resolved.

e) Based on the letter Ka.Balai III dated April 17, 2017, to the Satker PJN 1 Prov. West Sumatra that nolater than April 25, the follow-up report on the findings of TFAC package 03 (first visit, second visitand third visit after PHO) must be submitted to Balai III Padang. The report has been approved byWB on August 21, 2017.

f) The informally approved of TFAC finding package 03 after PHO on August 21, 2017 by World Bank.g) Formally from Director PJJ to World Bank on October 16, 2017.

Package No.4 : Ipuh - Bantala) Even through the contract time have been extended, contractor still failed to complete and turned

over the Project to the Employer on the revised target date of completion on April 11st , 2016.b) Contractor under liquidated damages.c) Substantially completed, Taking Over Certificate issued by DSC on May 31st , 2016.d) Currently under defects notification period for two (2) years until May 17th , 2018.e) CTC site visit 3rd with TFAC WB on 07 November 2017. deadline submit formal to WB on February

05, 2018. Not yet submit from Balai.f) CTC site visit before FHO from 26 February to 02 March 2018.

Package No.5 : Sp. Rampa - Poriahaa) Field Engineering still to be finalized and approve by DGH.

Following a geotechnical test to obtain rock excavation safest slope /angle. Additionally, the unitprice for rock excavation shall be renegotiated between the “Panitia Peneliti Kontrak” andContractor.

b) Contractor to prepare and implement catch-up schedule to reduce the huge progress negativeslippage.

c) CTC site visit with 1st TFAC WB on 22 Augustus 2016, quality inspection report of the WB has beenreceived by the PPK, Contractor on 29 September 2016.In accordance with the PMM WINRIP deadline follow up report should be completed and approvedless than two months from the time the team TFAC visit and follow-up report findings TFACimmediately resolved.

d) The on-going design revision involving massive quantities of rock excavation shall be thoroughlyevaluated.

e) A follow-up formal report of the TFAC (first visit) package result 05 was approved by WB on 5 April2017.

f) The informally approved of TFAC finding package 05 second visit on October 12, 2017 by WorldBank.

g) Tfac's second visit has been held on May 11, 2017, The deadline for a follow-up report is the dateon August 09, 2017

h) The informally approved of TFAC finding package 05 second visit on October 12, 2017 by WorldBank.

i) CTC site visit 3rd with TFAC WB on 20 November 2017, deadline submit formal to WB on January22, 2018. Not yet submit from Balai.

j) Formaly from Director PJJ to World Bank on January 09, 2018.

Page 37: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

4 - 9

k) Not yet submit report from field team.

Package No.6 : Ps. Pedati - Kerkapa) CTC site visit with 2nd TFAC WB on 25 August 2016, quality inspection report of the WB has been

received by the PPK, Contractor.b) A follow-up formal report of the TFAC (second visit) package result 06 was approved by WB on 29

March 2017.c) CTC site visit 3rd with TFAC WB on 09 November 2017.d) CTC site visit to assess pavement work quality of package 06 on December 27 to 29, 2017

Package No.11 : Bantal - Mukomukoa) CTC site visit with 2nd TFAC WB on 25 August 2016, quality inspection report of the WB has been

received by the PPK, Contractor.b) A follow-up formal report of the TFAC (second visit) package result 11 was approved by WB on 5

April 2017.c) The Taking Over Certificate has been done on 19 may 2017d) The maintenance period are two years as to 09 may 2019.

Package No.13 : Sp. Rukis – Tj. Kemuninga) Contractor to finalize technical justifications relative to results of Field Engineering.b) Field Engineering and Technical Justifications just approved by DGH with balance budget.c) CTC site visit with 1st TFAC WB on 28 August 2016, quality inspection report of the WB has been

received by the PPK, Contractor.d) TFAC findings (first visit) follow-up formal report has been approved by World Bank on 29th March,

2016e) The informally approved of TFAC finding package 13 second visit on September 28, 2017 by World

Bank.f) Formally from Director PJJ to World Bank on October 16, 2017

Package No.15 : Sibolga – Bts. Tapsela) Field Engineering and Technical Justifications are still to be finalized.b) Field Engineering and Technical Justifications just approved by DGH with balance budget.c) CTC site visit with 1st TFAC WB on 22 Augustus 2016, quality inspection report of the WB has been

received by the PPK, Contractor on 12 October 2016.In accordance with the PMM WINRIP deadline follow up report should be completed and approvedless than two months from the time the team TFAC visit and follow-up report findings TFACimmediately resolved.

d) A follow-up formal report of the TFAC (first visit) package result 15 was approved by WB on 5 April2017.

e) Tfac's second visit has been held on May 11, 2017, The deadline for a follow-up report is the dateon August 09, 2017.

f) Formaly from Director PJJ to World Bank on January 09, 2017

Package No.17 : Sp. Gn. Kemala – Pugung Tampaka) Field Engineering and Technical Justification are still to be finalizedb) Field Engineering and Technical Justifications just approved by DGH with balance budget.c) CTC site visit with 1st TFAC WB on 04 October 2016, quality inspection report of the WB has been

received by the PPK, Contractor on 08 December 2016.d) TFAC findings follow-up formal report has been approved by World Bank on 31th March, 2016

Tfac's second visit has been held on May 23, 2017, The deadline for a follow-up report is the dateon August 14, 2017

Page 38: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

4 - 10

e) Formally from Director PJJ to World Bank on November 08, 2017f) Tfac's 3rd visit has been held on November 23, 2017.g) Formaly from Director PJJ to World Bank on July 30, 2018

Package No.20 : Lb. Alung - Sicincina) Sign Contract on June 01, 2016b) SPMK on September 01, 2016c) Field Engineering and Technical Justifications are still to be being worked on.d) Tfac's first visit has been held on Marth 20, 2017 deadline on 25 May, 2017 and has been informaly

approval by WB on 05 June 2017.e) Formally from Director PJJ to World Bank on October 16, 2017f) Tfac's 2nd visit has been held on November 01, 2017 deadline on January 30, 2017.g) Formaly from Director PJJ to World Bank on March 12, 2018.h) CTC has been site visit monitoring maintenance period package 20 (Lb. Alung – Sicincin), Padang

west Sumatera on may 21 to 23, 2018.

Package No. 21: Kuraitaji – Lb. Alunga) Sign Contract on June 01, 2016b) SPMK on September 01, 2016c) Amendment (01) on September 01, 2016d) TOC/PHO on December 31, 2017 (base on Add.01)e) Field Engineering and Technical Justifications are still to be being worked on.f) Tfac's first visit has been held on Marth 21, 2017 deadline on 15 June, 2017 and has been informaly

approval by WB on 15 June 2017g) Formally from Director PJJ to World Bank on October 16, 2017h) Tfac's 2nd visit has been held on November 02, 2017 deadline on January 30, 2017.i) Formaly from Director PJJ to World Bank on March 19, 2017

Package No. 07: Inderapura – Tapana) Sign Contract on December 03, 2015b) SPMK on December 10, 2015c) Amendment (01) on February 01, 2016d) Amendment (02) on Marth 07, 2016e) Amendment (03) on November 04, 2016f) TOC/PHO on August 30, 2017 (base on Add.01)g) Field Engineering and Technical Justifications are still to be being worked on.h) Tfac's first visit has been held on October 21, 2016 and just approved by WA on April 05, 2017i) Tfac's second visit has been held on May 18, 2017 and deadline on 11 August, 2017 .j) The Informally approved of TFAC finding package 07 second visit on September 28, 2017 by World

Bank.k) Formaly from Director PJJ to World Bank on April 03, 2018.l) CTC has been visit after PHO to package 07 (Indrapura – Tapan ) at July 25 to July 29, 2018.

Package No. 08: Bts. Pariaman – Manggopoha) Sign Contract on January 28, 2016b) SPMK on March 23, 2016c) Amendment (01) on March 23, 2016d) Amendment (02) on October 13, 2016e) Amendment (03) on January 16, 2017f) TOC/PHO on December 31, 2017 (base on Add.01)g) Field Engineering and Technical Justifications has been approval on October 13, 2016 (base on Add.

Page 39: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

4 - 11

02).h) Tfac's first visit has been held on January 17, 2017 and just approved by WA on April 05, 2017i) Tfac's second visit has been held on May 15, 2017 and deadline on 17 May, 2017 .j) CTC has been visit before TOC/PHO package #08(Bts. Kota Pariaman –Manggopoh) on December

05, 2017.k) The Taking Over Certivicat has been done on 29 December 2017l) The maintenance period are two years as to 29 December 2019.m) First time for maintenance period (January 2018 to March 2018) has been done.

Package No. 14: Painan – Kambanga) Sign Contract on June, 2016b) SPMK on August 03, 2016c) Ammendemen (01) on August 12, 2016d) Ammendemen (02) on August 25, 2016e) Ammendemen (03) on September 15, 2016f) TOC/PHO on December 31, 2017 (base on Add.01)g) Field Engineering and Technical Justifications are still to be being worked on.h) Tfac's first visit has been held on March 22, 2017 and deadline on June 15, 2017i) The has been approved by WB on July 26, 2017j) Formally from Director PJJ to World Bank on August 10, 2017k) Tfac’s 2nd visit has been held on October 31, 2017 and deadline on January 22, 2018.l) Formaly from Director PJJ to World Bank on March 12, 2018.

Package No. 19: Bintunan – Laisa) Sign Contract on Febuary 27, 2015b) SPMK on March 11, 2015c) TOC/PHO on June 30, 2016 (base on Add.01)d) Tfac's first visit has been held on November 02, 2015 and just approved by WA on December 06,

2016e) Tfac's second visit has been held on March 03, 2016 and just approved by WA on September 29,

2016.f) CTC site visit 3rd with TFAC WB on 08 November 2017 and deadline on February 05, 2018

Package No. 12: Kambang – Indraouraa) Sign Contract on January 28, 2016b) SPMK on May 23, 2016c) Ammendemen (01) on May 23, 2016d) TOC/PHO on December 31, 2017 (base on Add.01)e) Field Engineering and Technical Justifications are still to be being worked on.f) Tfac's first visit has been held on May 18, 2017, and deadline on August 11, 2017g) The Informaly approved of TFAC finding package 12 on September 28, 2017 by World Bank.h) Formaly from Director PJJ to World Bank on April 03, 2018.

Package No. 16: Seblat – Ipuha) This is last WINRIP package contractedb) Work site hand over to Contractor on 7 November, 2016c) COW/SPMK letter issued by PPK on 8 November, 2016d) Pre - Construction Meeting (PCM) held on 14 November, 2016e) Field Engineering and Technical Justifications are still to be being worked on.f) Training or briefing TPM already implemented CTC in package 16 from dated 26 April until 28 April

Page 40: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

4 - 12

2017 in Bengkulu Province. QA /CTC participated in this event.g) Tfac's first visit has been held on May 11, 2017, The deadline for a follow-up report is the date on

September 08, 2017h) The Informaly approved of TFAC finding package 16 on January 25, 2018 by World Bank.i) Formaly from Balai III Padang to Director Preservasi at April 04, 2018.j) Not yet formaly from Director Preservasi to Director.

4.6 Environmental and Social Considerations

4.6.1 Current Overall Situation

A project category is assigned to each package as either Category A, B or C depending on the likely degreeof influence on environmental issues with a brief explanation as follows:

Category A project is one which will have a significant negative impact on the environment and may havean influence on areas outside the actual project area. A project classified as such requires an Amdal (Andal,RKL&RPL) study.

Category B project is one which affects the people or the environment to some extent but with a smallerimpact than a Category A. The required environmental analysis is a UKL/UPL study only.

Category C project has minimal effect on the people or environment and an environmental analysis is notrequired. SPPL are used to handle any minor problem which may arise.

Details of packages that require environmental and social safeguard are given in Appendix E and thefollowing Table 4.3 provides a summary of the work involved in the 18 WINRIP packages.

All the eighteen (18) packages require environmental impact investigations and studies which need theapproval by Forestry and Environmental Agency (DLHK) and has been issued of IPPKH for package No.05(Sp.Rampa – Poriaha) at 9 November 2017.

Nine (9) of the eighteen (18) packages are categorized under “Category A” projects wherein Amdal/EIAstudies are required and have to be approved by World Bank. The nine (9) packages are covered only byfive (5) Amdal/EIA studies as some single study covers a combination of two (2) or three (3) sub-projects asindicated in Table 4.3. While 21 social studies (SLARAP and LARAP) require the approval of the World Bank.Up to 31 May 2017, all the 22 environmental studies for the eighteen (18) sub-projects including a separatestudy (UKL-UPL) for Air Gadang Bridge on Package No.2 were approved by BLH with 5 of these studies(Amdal/EIA) were granted No Objection Letter (NOL) from the World Bank while all the 18 social studies(LARAP) were already issued No Objection Letter (NOL) from the World Bank.

Table 4.3Works

ProgramNo of

PackagesNo of Investigations Approval by Remarks

BLH World Bank

AWP-1 4 9

1 - Amdal2 – UKL-UPL2 - SPPL4 - Full LARAP

1 - Amdal2 – UKL-UPL2 - SPPL

1 - EIANo NeedNo Need4 - Full LARAP

Coverage of SingleAmdal/EIA study arethe following Packages :

a) Packages 1 and 17b) Package 7,12 and

14c) Package 11 and 16d) Package 8

AWP-2 7 15

3 - Amdal4 – UKL-UPL1 - Simple LARAP7 - Full LARAP

3 - Amdal4 – UKL-UPL

3 - EIANo Need1 - SLARAP7 - Full LARAP

Page 41: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

4 - 13

AWP-3 7 111 - Amdal5 – UKL-UPL6 - Full LARAP

1 – Amdal;5 – UKL-UPL

1 - EIANo Need6 - Full LARAP

Total 18 35 Env=18, Soc=18 18 Env= 4, Soc=18Note: 1) UKL & UPL do not need a NOL from WB, and SPPL not necessary to submit to the WB.

2) Packages 9 and 18 to be deleted.3) Air Gadang Bridge have separate investigation, hence, total equals 22.

Appendix E shows the Progress of Environmental Safeguard Studies.

4.6.2 Environmental and Social Issues

This section outlines the activities of the Social Impact Specialist and the Environmental Specialist duringAugust 2018.

4.6.2.1 Environmental Issues

Generally for safeguard all packages on WINRIP complete and on going submit to BLH for implementing,nevertheless the main environmental issues, specifically on the packages under construction are the spilledoil & diesel fuel contamination, air, noise, waste hazardous pollution, also poor housekeeping beingoccurred at base camp, Protected forest on pack No.05 (IPPKH has been issued from PMPPTSP Agency ofNorth Sumatera Province on 9 November 2018), Air and dust pollution along stretches of thickly populatedareas are not properly addressed by the Contractors. Water spraying is not continuously implemented.Dump trucks transporting construction material are not fully covered and traffic management plan is notfully implemented, generally workers on all packages partially not use PPT, only contractor staff has beenused the PPT. Follow-up to the implementation of the Bank's supervision mission related to the finding ofbase camp pollution on the all packages under construction, The Director of Road Network Developmentrequested that all base camp packages under construction be completed with temporary storage permitsfor Hazardous waste and only 1 (one) package is link of Sp.Gn.Kemala-Pg.Tampak (No.17) is alreadyequipped with permission.

Status as 31 May 2018 the conditions on going packages WINRIP there has been an increase in progress asin packages No.05,12,13,14,16 & 21 while other packages are being repair process. The packages availableof hazardous waste storage (TPS) are No.05, No.15, 08,21,14,12,16 & 13 while package No.20 the TPSbuilding not available.

Environmental issues on each of the individual sub-projects (Packages) are shown in Appendix E of thisReport.

Monitoring of Environmental Aspects During Construction

CTC provided revised monitoring forms to DSC and Contractor for use in monitoring of environmental andsocial impacts. These forms are to be used every month by the DSC Environmental Specialist.

CTC’s environmental staffs actively advises DSC on environmental monitoring, DSC have directly carried outmonitoring or to implement the Environmental and Social Safeguard and Road Safety (ESSR) for WINRIP.

CTC’s Environment Specialist monitored the implementation of environmental mitigations during themonth of 30 April 2018 and the following were observed :

Package No.05 : Sp.Rampa – Poriaha

a) The contractor does not use the existing quarry, the current buys material from the supplier (PT.

Page 42: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

4 - 14

Rogada/same owners quarry with package No.15 )b) The IPPKH license for the link of Sp.Rampa-Poriaha at Sta. 12+525 – Sta.13+950 and Sta.15+025 – Sta.

15 + 150 has been issued on 9 November 2017 from Dinas PPTSP of North Sumatera Province.c) Concrete & drainage floor already exists & has been wide, no found a spill of diesel to the ground.d) Concrete floor storage of solar & asphalt tank is quite adequate, there is already sloof there is a direct

channel to the ground & roof on a container was completed.e) There is not a spill of diesel and asphalt on the ground.f) The storages explosive was built, Health & Safety was implemented.g) The civil work under asphalt pavement , drainage work & the blasting activities. Explosive/detonator

has been finishh) The base camp management improvement such infrastructure, housekeeping & B3 storage has been

done.i) The hazardous waste storage (TPS) available.

Package No.13 : Sp. Rukis – Tj. Kemuning

a) The civil work under Asphalt pavement & under roadway excavation especially from Sta.26+000 to43+000 part of segment.

b) The lands under payment. The land acquisition budget from the PPK/Satker (APBN)c) There is a spill of diesel to the ground although the contractor has made the storage of jerry cans for

solar charging, the storage area of the jerry was enough large.d) Contractors has been made a zinc roof for a spill container of diesel fuel continue to the building of the

tank fuel to the reservoir.e) Storage of a reserve solar tank is smaller than the tank with open conditions (exposed to rainfall fall

from the roof beside it, the tarpaulin has been install at the storage.f) There is a spill of diesel on genset house on AMP&Stone crusher, the existing concrete floor (bulk

asphalt storage tank & diesel) is too small, not roofed, no channels to the oil trap.g) AMP pool with hydrocarbon, no mud dredging and no yellow line signs around the pool for the safety of

the project workers, etch) The base camp management improvement such infrastructure, housekeeping & B3 storage partially

done.i) The hazardous waste storage (TPS) available.

Package No.15 : Sibolga - Bts Tapsel

a) Water pipes belonging was cross the road pavement, shoulder widening and mortal, the current hasbeen cover by asphalt pavement & no complaint from the resident.

b) There are puddles in basecamp, the contractor should improve the layout stockpile storage onbasecamp,

c) Ex-diesel spill was noticeable in front of diesel storage room to follow up: clean up the contaminatedsoil, store temporarily in separate drum/container with label. Establish SOP for diesel loading &unloading and train related personnel.

d) Empty container without label was located in front of storage room to follow up: improvehousekeeping by giving the label and keeping the container at the designated place

e) Pond of AMP 2 has been improved with mud dredging & repair for AMP pond and completed by yellowline signs around the pool for the safety of the project workers

f) Ex drum asphalt drums have been mostly placed on the concrete floor with sloof but there is no B3waste container & not roofed

Page 43: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

4 - 15

g) The AMP 1 under demobilization but demobilization schedule still not clearance.h) The base camp management improvement such infrastructure, housekeeping & B3 storage partially

done

Package No.17 : Sp. Gn.Kemala - Pugung Tampak

a) Base camp was built on a hill it has the potential landslides, b) The Quarry/AMP/Stone Crusher permitswas complete,

b) The Contractor has been implement the Health & road sapety aspect on project on some segmen, Eartwork & shoulder excavation & drainage construction is underway, the contractor has been managethe construction areas with traffic management (road sign, flaghmen etc). The proposed blastingmethods on STA 11, will be canceled & the new proposed widening to seaword. : partially electric poleshave been removed by PLN.

c) Oil & diesel fuel contamination has occurred in the base camp, based on General Specification : 1.17.2.1(a) The Contractor shall ensure that polluting effluent from all of the Contractor’s activities shall notexceed the values stated in the prescribed applicable Laws (Refer specifically to Regulation No.82/2001regarding Water Quality Management & Water Pollution Control).

d) The contractor partially done for base camp improvemente) The project PHO on 27 Dec 2017

Package No.7 : Indrapura - Tapan (The project has been PHO)

The base camp activity has been operate, the power for AMP & stone crusher activities used genset. thecivil work was done for the excavation shoulder and widening, the quarry & base camp permission underprocess to ESDM/Governor, the contractor use 2 (two) quarries are in Aer pura and Tapan, all quarriespermits has been complete from Governor. Inadequate traffic sign on construction site,c) Flooding on 3(three poin arround Sta.08+500), drainage issues and The contractor has been provide the box culvert atSta.8 + 500 & u ditch at Km PDG 197 BLS 46 to handle flooding at site and surrounding, d) cow sign isneeded Sta.15 - Sta.20, d) is needed embankment for some houses was affected by project end project(pasar Tapan) and Drums containing chemicals with no labels were stored in an open area, on the groundand no secondary containment to follow up: provide designated area to store the chemicals, ensure theavailability of drainage and secondary containment and give label/sign for the drums. Provide roof or coverdrums with tarpaulin. The contractor partially done for base camp improvement, Not inform aboutprogress the base camp management from DSC status December 2017. Based on CTC visited on 6 Dec 2017,was found that the box culvert for 3 (three) point in Desa Gemuruh has been built, the embankmen on twohouses at end project (Tapan) has built but the electric pole at the end of the project not all have beenmoved, the AMP pool has been dredged, storage of solar tank not roof & minimum cement concrete & oiltrap. ex chemical, asphalt & solar drum stored on the ground & housekeeping not more improve. Theproject PHO on 28 January 2018, based on CTC monitoring on January 2018 (after PHO) was found thatAMP, stone crusher & some heavy vehicle not yet demobilization

Package No.12 : Kambang - Indrapura

a) Roads existing damage, air pollution at dens resident etc, no traffic sign at construction site.b) The quarry license was complete from Governor, environmental permit of AMP & Crusher from Bupati

was complete,

Page 44: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

4 - 16

c) Hydrocarbon layers were observed in the dust collector effluent pit and contaminated soil was clearlyobserved nearby the pit, likely due to the overflow and no proper drainage. Water from the pit went tothe soil ditch and ultimately to the soil pit prior to discharge to the environment. Water contaminatedwith hydrocarbon was also seen in the soil pit to follow up: build concrete pit and ditch and ensure nohydrocarbon contaminated water is in contact directly with soil. Monitor the discharge to theenvironment and check the UKL/UPL requirements.

d) The contractor partially done for base camp improvement.e) Not inform about progress the base camp management from DSC as per Dec 2017

Based on CTC visited on 6 Dec 2017 was found that the holes of culvert box at the bridge turns have notbeen closed, the base camp enough clean, housekeeping more improve, the B3 drainage & pond wasbuilt but without roof. there is a bit of diesel fuel at the AMP location.

Based on CTC visited on 20 Feb 2018 the environment issues was found the AMP water pond wascontaminated with hydrocarbon & asphalt spill under asphalt tank still not yet manage, also solar spillat AMP surrounding and little housekeeping need improve.

j) Based on CTC visited on 17 July 2018 finding the base camp management improvement suchinfrastructure, housekeeping & B3 storage has been done.

Package No.14 : Painan - Kambang

The base camp activity has been operate, the contractor not yet manage the soil pollution caused oil &solar spill, the civil work was done for the excavation shoulder and widening, the quarry license completefrom Governor, AMP & Crusher permission complete from Bupati, Inadequate traffic sign on constructionsite,c) Flooding on part of segmen because no drainage system, Air pollution but the contractor has beenmanage with sprayer. Oil & diesel fuel contamination has occurred in the base camp. The contractor notyet done for base camp improvement, Not inform about progress the base camp management from DSC asper Dec 2017. Based on CTC visited on 5 Dec 2017, was found Asphalt spill at AMP, road access &workshop areas, the AMP pool has not been dredged with hydrocarbon mixed with mud, storage of solartank not roof & minimum cement concrete & oil trap. ex chemical, asphalt & solar drum stored on theground & housekeeping not more improve but the Hazardous waste traetment available.Based on CTC visited on 19 April 2018 the base camp relatively environment issues was found such AMPwater pond was contaminated with hydrocarbon & asphalt spill under asphalt tank, solar spill at AMP stillunder repair process and little housekeeping generally has been improve all of the impact has beenrepair/complete as target then CTC visited on 17 July 2018 finding the base camp managementimprovement such infrastructure, housekeeping & B3 storage has been done.

Package No.8 : Manggopoh – Bts. Pariaman

The project has been PHO,. a) The project under construction, b) the base camp enough clean becausepower from PLN for operate AMP & base camp, c) The quarry & base camp permits (Governor) available,the utilities isues PLN can’t move the electrical pole because no budget in this year, d) 1 (one) PAP requesthigh compensation for his land caused the contractor can’t work on his lands. e) 2 houses at Kota Pariamanhas been moved. f) Fuel drainage on soil without concrete cement & mixed with rain drainage. g) the basecamp clean enough because the contractor used PLN for power, e) Road damage at sungai limau & ±Sta.15(Pak oyon lands), Not inform about progress the base camp management from DSC as per Oct 2017.Based on CTC site visit on 11 to 14 October 2017, the environment issues was found are:1) The base camp at Sta.23+600 condition clean enough but need improve the housekeeping & oil trap

given a roof then not mixed for rain drainage & solid contaminate drainage.

Page 45: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

4 - 17

2) Road damage at S.Limau (Sta.15+800 & Sta.26+350) front of Bapak Oyon shop already done asphaltpavement (Row efficient)

3) There has been a flood potential at Sta.22+900, Sta.23+900, Sta.18+100, Sta.24+000 & Sta.19+500 atSta.19+500 & Sta.21+300. The contractor should concern for mitigate.

4) Raising work at Sta.27+900 to protect the sea tidal5) Embankment work to protect soil erosion at Sta.21+500, Sta.42+700 & Sta.44+0006) The base camp condition after PHO suitable with SOP/clean the base camp area/good condition.7) The Project PHO on 31 Dec 2017k) Based on CTC visited on 30 January 2018, was found the base camp clean, no found solar& asphalt spill

at AMP & solar tank area. The base camp management improvement such infrastructure, housekeeping& B3 storage has been done as target.

Package.No. 16: Seblat - IpuhCivil works activities such as clearing and grubbing, roadway excavation along shoulders, stone crusher andquarry operations already done until 10 Km. the quarry & AMP permission complete. Oil & diesel fuelcontamination has occurred in the base camp, based on General Specification : 1.17.2.1 (a) TheContractor shall ensure that polluting effluent from all of the Contractor’s activities shall not exceed thevalues stated in the prescribed applicable Laws (Refer specifically to Regulation No.82/2001 regardingWater Quality Management & Water Pollution Control). The contractor on going done for base campimprovement.a. AMP & Crusher environment license issues (should upgrade the SPPL to UKL-UPL)b. Housekeeping still needs improvement: to collect/store used tire, tarpaulin, and other

tools/equipment in the proper place; increase housekeeping, waste segregation and spill preventionawareness to all workers.

c. A drum containing hydrocarbon/diesel was put directly on the ground, without label and secondarycontainment

d. Ambient water quality monitoring and water discharge quality monitoring were being prepared and tobe conducted when AMP in operation

e. The base camp management improvement such infrastructure, housekeeping & B3 storage partiallydone

f. Based on CTC monitoring at 25 April 2018, has been finding that solar & asphalt, taek coat spill stillfound at workshop & AMP areas then housekeeping very poor at workshop, the contractor was agreedwill repair all impact within 1 (one) weeks or be finished at 2 May 2018.

g. Based on CTC visited on 31 July 2018 finding the base camp management improvement suchinfrastructure, housekeeping & B3 storage has been done.

Package No.20 : Lubuk Alung-Sicincin

a) The project has been PHO. b) The permits for Quarry complete from Governor & AMP/Stonecrusher under process in BLH Kab.Pariaman. c) Utilities issues on commercial & residents areas, d)occur puddle on pasar Lubuk Alung because inadequate side ditch system, e)Oil & diesel fuelcontamination has occurred in the base camp, based on General Specification : 1.17.2.1 (a) TheContractor shall ensure that polluting effluent from all of the Contractor’s activities shall not exceedthe values stated in the prescribed applicable Laws (Refer specifically to Regulation No.82/2001regarding Water Quality Management & Water Pollution Control). The contractor not yet done forbase camp improvement. Not inform about progress the base camp management from DSC as per

Page 46: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

4 - 18

Sep 2017.b) there is a diesel fuel in the AMP solar tank the cements concrete is less wide there is no roof & oil

trap, there is a puddle in AMP areas & drainage charging from the AMP pool not continue into themain drainage

c) The base camp management improvement such infrastructure, housekeeping & B3 storage partiallydone, the contractor not yet done to improve of base camp still remaining the residual impact.

Package No.21 : Lubuk Alung – Kurataji

a) The project under construction. b) The permits for Quarry complete from Governor & AMP/Stonecrusher license complete, the owner AMP & Crusher is supplier LMKP. c) Railway & irrigationchannel issues on Started project, d) Utilities issues on commercial & residents areas, e) occurpuddle on resident area because inadequate drainage system, f) only some workers who usehelmets, vests and boots, flooding on part of roads because no side ditch system. Side ditch issueson some segmen.

b) The condition of new base camp, there little spilled fuel from kran solar to AMPc) The genset house there is a diesel fuel, no cements concrete no roof & oil trap.d) The signage boards can be re-used / collected in a special storage ex-material con- struction.e) No trash bin at office base campf) The generally base camp of package No.21 condition clean

1. Review Design Integration, Road Safety Aspects and Monitoring of Environmental Studies

Task 5.8.0 of CTC-2 TOR (Implement the Environmental and Social Analysis Management Plan/ESAMP) andparagraph 10.9 of the PMM requires ensuring that environmental management aspects of contracts havebeen implemented in accordance with AMDAL, UKL&UPL, SPPL studies and Environmental issues will beintegrated in the design and to prepare environmental mitigation on construction stage for contractor(Contractor Program for Executing Environmental Management Plan CPEMP/RKPPL). CTC has submitted toPMU all of reports of Review Integration Amdal,UKL-UPL and SPPL.

2. External Monitoring Report (Satker/PPK to BLH) for Implementation of Amdal/UKL-UPL/SPPL on PreConstruction Phase, Construction Phase and Post Construction Phase.

The 3st external monitoring reports of Amdal, UKL-UPL implementation for BLH are preparation by CTC hasbeen submit to PMU & the WB see Appendix

3. The Contractor Action Plan on Environmental Management and Monitoring (RKPPL)

The RKPPL provided by the Contractors for the packages (Packages 1,2,3,4,5,6,11,13,15 and 19) werecompleted and No Objection Letter (NOL) have been already issued by the World Bank.

The current activity on 6 (Six) packages under construction such as packages No.7: Indrapura-Tapan,No.12:Kambang-Indrapura, No.14: Painan-Kambang, No.20: Lubuk Alung-Sicincin & No.21:Lubuk Alung-Kurataji has been submit to the WB on 28 Feb 2017 and package is No.16: Seblat-Ipuh submit to PMU & WBon May 2017. WB comments for RKPPL of Seblat – Ipuh on 18 July 2017, the Director PJJ letter to responds

Page 47: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

4 - 19

WB comments has been submit (informally) to WB end of Sep 2017.

4. Environmental Quarterly Report

The CTC has finalized the environmental quarterly report for the period April to June 2015 for PackagesNo.1: Krui-Biha, No.2: Padang Sawah-Sp.Empat, incl.Air Gadang bridge, No.3: Manggopoh-Padang sawahand No.4: Ipuh-Bantal. The report has been submitted to PMU and the WB on 3 July 2015.

Environmental Quarterly Reports for the period January to March 2016 for Packages No.2,4,5,6,11,13,15,17and 19 complete and has been submit to PMU/WB on 28 June 2016

Environmental Quarterly Reports for the period April to September 2016 for Packages No.5,6,13,15 &17 hasbeen submit to PMU/WB on 28 November 2016.

RKPPL Training for package No.16 (Seblat-Ipuh) Done on 18 to 19 January 2017

Environmental Quarterly Reports for the period October to December 2016 for PackagesNo.5,6,7,8,11,12,13,14,15,17,20 & 21 has been submit informal to WB on 15 March 2017

Environmental Quarterly Reports for the period January to March 2017 for PackagesNo.5,7,8,11,12,13,14,15,16,17,20 & 21 has been submit informal to WB on 9 May 2017

The WB comments for Environmental Quarterly Reports on 18 July 2017 and noted to disclosed on websiteWINRIP.

Environmental Quarterly Reports for the period April to June 2017 for PackagesNo.5,7,8,11,12,13,14,15,16,17,20 & 21 has been submit informal to PMU/WB on August 2017

Environmental Quarterly Reports for the period July to Sep 2017 for PackagesNo.5,7,8,11,12,13,14,15,16,17,20 & 21 has been submit informal to PMU/WB on October 2017

Environmental Quarterly Reports for the period Oct to Dec 2017 for PackagesNo.5,7,8,12,13,14,15,16,17,20 & 21 has been submit informal to PMU/WB on 19 March 2018

Period Jan to March 2018 for packages No.05,15, 21,20,14,12,16 & 13 has been submit to PMU & WB(informally) at 21 May 2018.

WB Comments to Environmental Quarterly Reports for the period Jan to March 2018 for packagesNo.05,15, 21,20,14,12,16 & 13 at July 4, 2018, the WB suggest that environment specialist DSC & CTCbetter coordinate between them, continue intensive monitoring for base camp housekeeping and check thestatus of spill clean-ups in base camp more frequently (such as package 15 and 20)

Please ensure that the required environmental management implementation reports (UKL-UPL or RKL-RPL)are received by the respective local environmental agencies (Dinas Lingkungan Hidup).

Socialization of HIV-AIDs Campaign

The socialization of HIV-AIDs activities on 18 (eight ten) packages has been Complete, are packages No.1(Krui-Biha = 10 Nov 2015) , No.2 : Padang sawah-Sp.Empat, incl.Air Gadang bridge and No.3 manggopoh-

Page 48: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

4 - 20

Padang Sawah = 17 Nov 2015 and No.4 : Ipuh-Bantal = 4 Dec 2015. Package No.11 : Bantal – Muko Muko =5 Dec 2015. Package No.6 : Psr Pedati-Kerkap= 12 Jan 2016. Package No.19: Lais-Bintunan: 13 Jan 2016 thenpackage No.13 :Sp.Rukis-Tj.Kemning = 19 January 2016. Package No.5: Sp.Rampa-Poriaha = 27 Jan 2016.Package No.15: Sibolga-Bts Tapsel = 28 Jan 2016, Package No.7 (Indrapura-Tapan) & No.12 (Kambang –Indrapura) = 6 September 2016, Package No.8 (Bts.Pariaman – Manggopoh) = 4 October 2016 & PackageNo.14: Painan-Kambang was complete and all of reports has been submit to PMU/Balai and the WB, Theschedule to carried out the workshop on HIV/AIDS for new packages ongoing construction No.8 :Manggopoh-Bts.Pariaman Done 7 March 2017, No.20: Lubuk Alung-Sicincin, No.21 Lubuk Alung-KuratajiDone 8 March 2017, while for package No.16: Seblat-Ipuh Done 15 May 2017.

Quarries Management.

In most packages under construction, the project contractor purchase material from suppiers that havevalid licenses, but the supplier not implement the environmental management and monitoring plans onquarry site refer to license.

As the World Bank Safeguard Policy considers a quarry as project area of influence, we therefore urgentCTC environmental specialist to discuss this issues with the respective BLHs and check the owner of thequarry complies with the provisions in its environmental license.

The generally permission of quarry, AMP & Stone Crusher on packages WINRIP under construction thepermits from Bupati or Governor have been complete.

Package No.5The quarry, AMP & Stone Crusher permits from Bupati, (the quarry owner has been extentd licensing/thequarry permits was available before new law issued), the contractor has been manage the quarry area suchas reclamation & air quality & noise measurement, etc as UKL-UPL recommendation and the contractor wasprepare the UKL-UPL implementation of quarry and submit to the BLH.

Package No.7'The quarry, AMP & stone crusher permit complete from Governor, the quarry owner not yet submit theUKL&UPL implementation to BLH but periodic report to Mining Agency has been done.

Package No.8'The quarry permit from Head of Mining Agency of West Sumatera Province,complete. & Base camp permitcomplete. the contractor will submit the base camp UKL-UPL implementation to BLH of Kab.Pariaman.

Package No.12The quarry license complete from Governor & the AMP & Stone Crusher permits complete from Bupatirefer to Law 23 year 2014. the owner has been submit periodic report to Mining Agency has been done

Package No.13The AMP&StoneCrusher permits was decided by Govenor on 16 January 2016 (refer to Law 23,year 2014),The quarry permits in Kab.Kaur, complete from ESDM Bengkulu province, periodic report to Mining Agencyhas been done. the contractor will submit the base camp UKL-UPL implementation to BLH Kab. SouthBengkulu.

Package No.14

Page 49: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

4 - 21

The UKL-UPL of AMP & Stone Crusher permits complete by Bupati & under process to Governor permitsthen Quarry permits complete by Governor. The owner has been managed the quarry site based onEnvironment permit.

Package No.15The quarry permits complete by Governor/ Head of Mining Agency of North Sumatera province but theUKL-UPL of AMP & stone crusher permits complete by Bupati under process to Governor permits, and thecontractor has been manage the environmental impact such as water river quality caused quarry activity.

Package No.17The quarry & base camp permits complete by Governor (ESDM/ of Lampung Province), the contractorunder prepare implementation of UKL&UPL quarry and base camp & will submit to BLH Kab. Pesisir Barat &periodic reporting every 6 9six) months to Mining Agency.

Package No.16The quarry permits complete The Yasa Contractor has been used the quarry from H Medi only 1 (quarries &the capacity enough (Contractor information). The BLH suggest for AMP & Crusher license should upgradefrom SPPL to UKL-UPL.

Package No.20The permits for Quarry complete from Governor & AMP/Stone crusher complete.

Package No.21The permits for Quarry complete from Governor & AMP/Stone crusher complete.

WB Mission 15 – 17 February 2017 on Packages No.7,12 & 14

a) Environmental Safeguards. The environmental licenses for all work packages were obtained. Similarly,the quarry permits for the ongoing works are up to date. The licenses for the stone crushers andasphalt mixing plans for the three last packages (12, 21 and 15) are expected to be issued imminently.For the three last packages (07, 12, and 16) there have also been some delays in the preparation of theenvironmental management implementation plans (RKPPLs). This has not been a significant issue asCTC’s environmental specialist also carried out monitoring for the packages that have not yetcompleted their RKPPLs. Submission of environmental management and monitoring (EMP) reports tothe local environmental agency (BLH) has so far been largely satisfactory. All environmental relateddocuments are published on the project website. The findings of the field visit that took place onFebruary 16 and 17, 2107 is reported below.

b) General Heath Safety and Environment. Overall, the application of good practice as per the SOP DGHighway requirement varied among the packages and contractor. Though from time to time, the trendtoward compliance is positive, still some packages require persistent push (or perhaps penalty),especially for issue related to good house-keeping in AMP areas and minimum safety requirement ofusing PPE during work. Oil/fuel spillage as well as fuel storage without proper containment are stillcommon issues, found on AMP area as well as worker without proper PPE.

c) Labor influx and HIV/AIDS/STD public consultation. Recruitments of unskilled labor for all packageshave given priority for local community. Within a section being rehabilitated, depending on the length

Page 50: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

4 - 22

of the section, there can be few groups local communities involved in the civil work. The local laborcommutes daily from their own house to the site. The proportion of local labor to the total populationliving along most of section is small, likewise the migrant workers who stay in the contractor basecampis insignificant compare with the total local community. Thus, the risk of negative impact due to laboris low. Furthermore, the HIV/AIDS/STD prevention workshops attended by both local and migrantworkers have been conducted for most of the packages, The local experts from the local HIV/AIDSprevention agency (i.e. Dinas Kesehatan) ware asked as resource person for the workshop. For thethree recently contracted packages No.8,20 & 21 these workshops are scheduled for 7 & 8 March andthe remaining 1 (one) package No.16 done on 15 May 2017.

d) Complaint handling. The most recent complaint was received via email (February 7,2017) fromcommunity living along the section of Package 14 (Painan – Kambang). Complaint was about anincrease of dust due to project activities. Upon the tripartite discussion (i.e. PPK (and CTC), contractorand community), it was agreed that the contractor shall provide a dedicated water-tank truck on thatparticulars sections. Site visit on February 16,2017 confirms the contractor’s commitment for dustsuppressing along the road being rehabilitated. In contrast to Package 14, driving along the Package 12(Kambang – Indrapura), the team found local community tried by themselves to control the dust byputting speed bump and watering the road by themselves. Further follow-up with contractor will berequired.

Fact Finding for Package No.05, site visit on 13 – 15 March 2017

1. Meeting coordination with Environmental Agency & Secretary of Kabupaten Tapanuli Tengah – NorthSumatera Province on 13 March 2017

2. Meeting coordination with Chief of BPKH Medan North Sumatera Province on 15 March 20173. Meeting Coordination with KLHK Jakarta on 20 March 2017

The Result Meeting, as follows:1. The Environment Agency of Central Tapanuli stated UKL-UPL-Poriaha Sp.Rampa can used as the

technical requirements for IPPKH, because the location of the alignment shift is still in the corridorwhich has been accommodated in the Minister of Forestry to the Governor of North Sumatra No.S.390/ Menhut-VII / 2004 dated July 29, 2004, concerning principle permits of IPPKH to road constructionRampa - Poriaha - Labuan Angin in Central Tapanuli.

2. The KLHK is needed Amdal study for activity on protected forest (refer to Decree of EnvironmentalMinister No.05 year 2012 art 3

3. Nevertheless the initial link of Sp.Rampa-Poriaha has been complete the environmental safeguard withUKL-UPL document allows for preparation DELH.

World Bank Training on 11, 18 & 22 May 2017 for Base Camp Management Improvement

Basecamp Environmental Management training was delivered in Package 15 PP Office in Pandan, attendedby 12 persons from Package 5 and Package 15, including representatives from CTC and DSC.

Basecamp Environmental Management training was delivered in Package 12 PT LMA Office in Indera Pura,attended by 13 persons from Package 12, Package 7 and Package 14, including representatives from PMU,CTC and DSC.

Page 51: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

4 - 23

Basecamp Environmental Management training was delivered in Package 13 PT Waskita Karya Office inManna, attended by 7 persons from Package 13 including representatives from CTC and DSC

Summary of Observations The findings generally can be divided into 3 key areas: SOP not implemented/unavailability of SOP, poor

infrastructure design and lack of housekeeping awareness/enforcement. None of the contractors have permitted temporary toxic and hazardous (B3) waste storage and

contract with licensed B3 waste treatment/collector/disposal companies even though the requirementswere stated in some of the UKL/UPL documents.

Suggestions and Next Steps Organize housekeeping campaign for all working areas involving all workers to improve site

environmental performance. Behavior change is the key. An opportunity to apply reward andpunishment.

Include environmental topic in regular safety morning/safety talk which should cover: SOP/working instruction socialization Pollution prevention Spill reporting Housekeeping improvement Increase field supervision and share the observations to all stakeholders as lessons learned/continual

improvement Make the plan for disposal/treatment of contaminated soil and other B3 wastes, such as used drums ex

chemical, used drums ex asphalt, used battery, used lamps, contaminated rags, etc. (Licensed thirdparty, treatment/bioremediation, utilization?).

Check the contract for potentially no detail clause for pollution prevention, pollution handling andenvironmental monitoring (not stated in the Bill of Quantity no Unit Price) for future improvement.

WB Meeting in DGH

WB Meeting with PMU, Subdit LKJ & CTC has been conducted on 2 August 2017 to follow up base campmanagement improvement all packages on going construction, the result meeting as follow:

PMU is preparing tools / tools as an effective way to improve environmental performance and safety in thefield.

Rules and guidelines are available but on-the-ground implementation is still weak because pollutionprevention and environmental management have not been covered in the BoQ

For the future (upcoming contract / new contract), DGH is revising the technical specifications to includesuch matters in the tender documents, namely in the RKPPL (contract draft included in the tenderdocument).

In considering the Project will closing date until December 2017, so related to environmental management,especially environmental management in basecamp, plans and prioritization should be made:

Page 52: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

4 - 24

Prioritize environmental management SOP housekeeping and SOP fuel loading (if not there), socializationof SOP and increase awareness through safety talk / morning talk on a regular basis, campaign, The aim isto increase the tidiness and prevention of pollution in the site construction & base camp and the change ofbehavior of all workers.Immediate execution of infrastructure improvements, especially for fuel storage areas, storage of materialsand B3 waste, and pit for effluent water AMP.

Establish a waste management / disposal plan from basecamp activities.Monitor progress actively according to their respective roles (DSC, CTC, PMU).

Create an informative progress status report (eg, with traffic light) starting August 2017 for ease ofmonitoring and use of this report in a field visit to communicate with each Contractor. In addition to PMUpurposes, this progress status report also needs to be submitted to the World Bank every month.

WB Mission to supervise safeguard & review the implementation progress of base camp management on16 to 18 September 2017

Summary of Observations

• The findings generally can be divided into 3 key areas: SOP not implemented/unavailability of SOP,poor infrastructure design and lack of housekeeping awareness/enforcement.

• None of the contractors have permitted temporary toxic and hazardous (B3) waste storage andcontract with licensed B3 waste treatment/collector/disposal companies; Contractors have to followthe requirements in their respective environmental documents (RKL-RPL/UKL- UPL/SPPL).

• Few improvements have been made since the last visit for Package 13, however, the basecampenvironmental aspects still require more attention especially during the operation and productionacceleration

Suggestions and Next Steps

• Organize housekeeping campaign for all working areas involving all workers to improve siteenvironmental performance. Behavior change is the key. An opportunity to apply reward andpunishment.

• Include environmental topic in regular safety morning/safety talk which should cover:• SOP/working instruction socialization• Pollution prevention• Spill reporting• Waste segregation - organic, inorganic, toxic and hazardous wastes• Housekeeping improvement

• Follow the requirements in environmental documents (RKL-RPL/UKL-UPL/SPPL) for toxic andhazardous waste management (temporary storage permit and disposal).

• Continue the activities of monitoring and reporting by CTC Environmental Specialist to PMU and Balaias a mechanism to raise the environmental concerns.

• Increase field supervision of Contractors by DSC and share the observations to allstakeholders as lessons learned/continual improvement. Desirable sanctions to Contractors may beconsidered as necessary.

Page 53: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

4 - 25

Western Indonesia National Roads Improvement Project (WINRIP) (Ln.8043-IND) September 2017Supervision Mission

Base on the Supervision Mission by World Bank's Environmental Safeguard Specialist (Ms. AgustinaParwitosari) & Environmental Sp. CTC to Package No. 13 and 16 in Bengkulu on September 16-18,2017, was found as follows:

Outlining the observations of base camp environmental management from May 2017 site visit, theBank still identified shortcomings in September 2017 mission despite the few improvements.Oil/fuel spills and hydrocarbon storage/drums directly placed on the ground are still commonissues in base camps. There are still inadequacies on the infrastructures (for spill prevention andwaste management) and behavior for housekeeping improvement has not significantly changed.More attention and supervision is required especially during production and operation accelerationphase. Contractors are expected to provide dedicated place for temporary storage of materials andtoxic and hazardous wastes separately in compliance with Indonesia regulatory requirements andthe relevant environmental document of each package.

Since these have been recurring concerns, the Bank team urged the DOH to follow-up more strictlyand ensure that the local requirements, which are in line with Bank requirements, are observed.The DOR should send warning letters to all contractors with unsatisfactory basecamp management.If the problems persist, the local Environmental Agencies will be alerted and administrativesanctions applied.

The letters of Director of Network Development to Director of Preservation forwarded to Head of BBPJN II,BPJN III & BBPJN V for respond WB request related base camp management improvement all packagesWINRIP. The principle refer to Law No.2 year 2017 concerning Jasa Konstruksi & Law No.18 year 2009concerning procedure of temporary hazardous waste storage so request all contractors on packages underconstruction to build the temporary hazardous waste storage (B3) at their base camp.

Verification by CTC & DSC to improve base camp management all packages under construction on WINRIP

Following the Director of Road Network Development letter, No. 1136 / ND / BP / 2017 dated 19 October2017 concerning Follow-up Implementation of World Bank Supervision Mission related to Pollution Findingsin Base Campup and Refer to Official in charge PMU WINRIP, No. 04, dated 10 January 2018 concerningSchedule of Site Visits Plan to Follow Up Base Camp Management Improvement at Base Camp on PackagesWINRIP.

CTC has been site visit to verified the base camp of packages No.05, 15, 07,12,14,13,17, 08,20 &21. & allreport has been submit to PMU on 29 January 2017.

Progress of base camp improvement report for packages No. 05,15,14,12&07 status until 15 February 2018has been submit to PMU on 5 March 2018.

Base camp improvement report status until 31 March 2018 for packages No.05, 15,21,20,14,12,16 & 13 hasbeen submit to WB on 20 April 2018

Page 54: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

4 - 26

CTC Monitoring for Base Camp Management Improvement.

Based on CTC monitoring for base camp improvement progress, status until March 15, 2018 was found asfollows:SOP documents and morning talk / induction implementation routinely (Daily & Weekly) to project workersin field was available for all contractor (No.05,15,21,20,12,14,16&13).

Package No.05,15,14 & 12 is equipped with TPS building, while packages No.13, 21,16 and 20 on processbuilt of TPS B3.

Packages that have completed the findings of joint verification (CTC / PMU / CTC / DSC / Contractor & CTCmonitoring results include B3 waste infrastructure improvements, TPS B3 provision and housekeepingimprovements are package No.05 (Sp.Rampa-Poriaha), No. 12 (Kambang - Indrapura) and No.14 (Painan-Kambang) while other packages are still in process of completion of infrastructure & housekeepingimprovement.

CTC monitoring results on March 13, 2018 to package PHO No.20 (Lubuk Alung - Sicincin) in general basecamp conditions are still the same as at the time of joint verification (PPK / CTC / DSC / Contractor), onlyslight improvement of diesel fuel spills at diesel tanks are in other work units such as AMP generator, AMPsolar tank still occur diesel and asphal / taek coat spilled.

Findings of non-conformity repeats always occur at AMP sites, diesel tanks and workshops, such as:

Infrastructure of concrete floor, zinc roof and inadequate container so as to cause diesel/solar, oil andasphalt spills, on the ground. Ex asphalt drums, ex-diesel, ex-chemical placed directly above the ground arenot placed on concrete floors with edge borders and waste and tarps storage containers. Disturbance at thebase camp location due to poor housekeeping & There is no temporary storage place (TPS) of B3 waste tocollect B3 waste materials such as batteries, plastic, AKI, ex electronic appliances etc.) which furthermoreB3 waste must be submitted to licensed third party.

Packages with the completion of fixes according to agreed Targets, is package No.05 (Sp.Rampa-Poriaha),No.12 (Kambang-Indrapura) & No.14 (Painan-Kambang) while other partial packages on process are No.13(Sp.Rukis-Tj.Kemuning) has not submitted the base camp repair documentation until March 15, 2018,resulting in no record of progress.

Require good cooperation and regular and strict supervision of the DSC to motivate contractors inimplementing the base camp management in accordance with environmental clearance and spec contracts.

CTC monitoring result on 19 to 20 April 2018 to packages No.12 and No.14 finding as follows:Package No.14: The remaining carbon on the ground from Ketel asphalt & ponds of AMP not yet dredge buthousekeeping under repair such solar spilled at AMP & genset building.Package No.12: generally housekeeping & infrastructur has been done but still remaining/little solar spilledat burner AMP.

CTC monitoring result on 25 April 2018 to package No.16 (Seblat-Ipuh) was found as follows.

Page 55: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

4 - 27

The workshop & AMP areas poor housekeeping & need more improved. Solar, oil spilled at workshop &solar, teak coat, asphalt spilled at AMP areas then shrubs grow on the road shoulders, erosion end ofproject & some art of road segment the side ditch is not continuous due to blockage by soil etc.

WB Mission to supervise safeguard & review the implementation progress of base camp management toPackages No.12& 14 at 7 to 9 May 2018 and No.13 & 16 at 29 to 31 May 2018

Notes for Package 14 Painan-Kambang Basecamp

1. Best Practices:• PPE for visitors and workers were available and safety induction was provided to the visitors

prior to site visit.• Secondary Containments were available for diesel fuel and other oil-based products.• Temporary storage for hazardous wastes was accessible and in the process of obtaining the

permit from Local Government.• Water was sprayed regularly to prevent dust.• Wastewater from AMP passed the analysis according to standards in Ministry of

Environment Regulation 5/2014 Attachment XLVII and the deposition was utilized as backfillmaterials by the community; the transfer was well documented.

2. Need Improvement:• Minor spills were still observed in the area of electricity generator house, fuel tanks.• Minor sheen was observed in drainage.• Hazardous Waste Temporary Storage: the absence of fire extinguisher, first aid kit, eye wash

facility, no B3 waste symbol/label on the containers, no B3 waste records/log bookand no access restriction. There were only 2 drums containing contaminated soil/sand. Thetemporary storage was visited by the Environmental Agency of Pesisir Selatan District in March2018 and the recommendations are being followed up. The update shall be submitted again tothe District Environmental Agency after improvement.

• An empty container contaminated with diesel fuel, which belongs to a vendor/sub-contractor, was located next to the temporary storage; potential for generating sheen in thedrainage when raining.

• Plastic bottles and garbage were observed in the area near the office, not properlydisposed in the available bins.

Notes for Package 12 Kambang-Indrapura Basecamp #1 and Basecamp #2

1. There are 2 basecamps for Package 12, Basecamp #1 is the basecamp utilized by Package 12 since thebeginning of the project; Basecamp #2 is the newer one, located about 3 km from Basecamp #1. Thetemporary hazardous waste storage in Basecamp #1 is used for wastes generated from Basecamp #1and Basecamp #2. As expected, the newer basecamp is more organized, tidier, and better designedfor secondary containment compared to Basecamp #1.

2. Best Practices:• PPE for visitors and workers were available and safety induction was provided to the visitors

prior to site visit.• Secondary Containments were available for diesel fuel and other oil-based products,

Page 56: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

4 - 28

however SOP for fuel loading and pollution prevention shall be routinely communicated toworkers and sub-contractors.

• Temporary storage for hazardous wastes was accessible in Basecamp #1 and in the processof obtaining the permit from Local Government.

• Water was sprayed regularly to prevent dust.• The deposition was utilized as backfill materials by the community; the transfer was well

documented.• There was a PIC under HSE team for waste and environmental matters, responsible for both

basecamps.

3. Need Improvement:• Hazardous Waste Temporary Storage:

▪ The presence of a gap at the back wall of temporary storage that potentially drains thecontaminated wastewater from the temporary storage directly to environment.

▪ The absence of fire extinguisher, first aid kit, eye wash facility, no B3 wastesymbol/label on the containers and access restriction.

▪ Log book and waste record are available, but the records need to be improved with thetemplate from the GOI regulation.

▪ The temporary storage should be utilized as much as possible for warehousing used lube oiland used drums.

▪ Proposal for the temporary waste storage permit was submitted to Environmental Agencyof Pesisir Selatan District in November 2016, and the recommendations are being followedup. The update shall be submitted again to the District Environmental Agency afterimprovement.

• No updated data for the wastewater analysis from the AMP and the surface water quality outsidethe facility as control. Stack emission has not been monitored; dark smoke was seen from thestack.

• The secondary containment for solar drum in AMP Basecamp #1 was not adequate,potential for spill if the drum is roll-over or if it rains.

• Lack of awareness from the workers on waste management; minor spill and plastic bottleimproper disposal were still observed.

Notes for Package 16: Seblat-Ipuh Basecamp

1. Best Practices:• PPE for visitors and workers were available and safety induction was provided to the visitors

prior to site visit.• Secondary Containments were available for diesel fuel and other oil-based products.• Temporary storage for hazardous wastes was accessible and in the process of obtaining the

permit from Local Government.• The hazardous Waste Temporary Storage (TPS) has been complete by APAR, first aid, eyes wash &

log book. The workshop clean enough

2. Need Improvement:• Minor spills were still observed in the area of electricity generator house, fuel tanks.

Page 57: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

4 - 29

• Minor sheen was observed in drainage.• An empty container contaminated with diesel fuel, which belongs to a vendor/sub-

contractor, was located next to the temporary storage; potential for generating sheen in thedrainage when raining.

Notes for Package 13: Sp.Rukis-Tj.Kemuning Basecamp

1. Best Practices:• PPE for visitors and workers were available and safety induction was provided to the visitors

prior to site visit.• Secondary Containments were available for diesel fuel and other oil-based products.• Temporary storage for hazardous wastes was accessible and in the process of obtaining the

permit from Local Government.• The hazardous Waste Temporary Storage (TPS) has been complete by APAR,first aid, eyes wash & log

book &Label safety. The oil trap at solar tank has been cover by zeng & sloof around no spill on the ground

2. Need Improvement:• Minor spills were still observed in the area of electricity generator house at AMP & stone crusher

& ex fuel generator scattered at generator kanibal area.• Minor sheen was observed in drainage.• An empty container contaminated with diesel fuel, which belongs to a vendor/sub-

contractor, was located next to the temporary storage; potential for generating sheen in thedrainage when raining.

WB TFAC Severe Shortcomings in Environmental Management to base camp of package No.16 (Seblat-Ipuh)and No.11 (Bantal – Muko Muko) as follows:

For Package No.16, among others, the concrete patching plant is being cleaned next to the lagoon on thebeach, pouring the concrete waste into the water In addition the pond with the asphalt mixing plant wastedoes not have a concrete bottom, causing contaminated water to sink into the ground. Based on CTC visiton 31 July 2018 for this case, the contractor partially has been done to improve the impact, partially beingon process the zenk embankment side left of AMP pond.

For package 11 the base camp has not been properly decommissioned, leavingoil and asphalt spills andcontaminatedsoil and water in many areas.

Based on CTC visit on 31 July 2018 that the contractor of pack No.11 has been done improve oil & asphaltspills, the camp areas now was clean, while for the pack No.16 the base camp management improvementsuch housekeeping & B3 storage has been done and the remaining for side embankment of AMP ponds stillon process.

Page 58: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

4 - 30

4.6.2.2 Social Issues

1. Monitoring Report of the LARAPPackage No. 1 : Krui – BihaProvince : Lampung

A. Previous Status:

LARAP implementation documents approved by World Bank on January 4, 2013

Monitoring Report No.1 (revised) approved by World Bank on June 26, 2013

Monitoring Report No.2 approved by World Bank on October 20, 2015.

Construction completed in January 20, 2016.

B. Pending Issues, Concern and Actions

No more issue, LARAP fully completed.

C. Update during this reporting month of August 2018

a) Total PAP = 2,815; Compensated = 2,815; Percent complete = 100%.

b) No update for reporting of the certification of PAP lands.

2. Monitoring Report of the LARAPPackage No. 2 : Padang Sawah – Sp. EmpatProvince : Sumatera Barat

A. Previous Status:

LARAP documents approved by World Bank on January 13, 2013

Monitoring Report No.1 (revised) approved by World Bank on July 19, 2013

Additional LARAP Implementation documents approved by World Bank on July 21, 2014

Monitoring Report No.2 approved by World Bank on Feb. 12, 2015

Satker PJN I West Sumatera has issued a statement on the status of 1 PAP along Air GadangBridge, and land acquisition plan belonging of 24 peoples as in Additional LARAP Document ofthis package on August 16, 2016.

Construction completed in April 19, 2016.

B. Pending Issues, Concern and Actions

a) No more issue, LARAP fully completed

C. Update during this reporting month of August 2018

a) Total PAP = 466; Compensated = 466; Percent complete = 100.00%.

3. Monitoring Report of the LARAPPackage No. 3 : Manggopoh – Padang SawahProvince : Sumatera Barat

A. Previous Status:

LARAP documents approved by World Bank on January 4, 2013

Monitoring Reports No.1, 2, 3, 4 and 5 already approved and World Bank issued No ObjectionLetter (NOL).

Monitoring Report for the remaining 1 PAP already submitted to WB

Page 59: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

4 - 31

Construction completed on March 17, 2016.

B. Pending Issues, Concerns and Actions

No more issue, LARAP fully completed.

C. Update during this reporting month of August 2018

a) Total PAP = 1,338; Compensated = 1,338; Percent complete = 100%.

4. Monitoring Report of the LARAPPackage No. 4 : Ipuh – BantalProvince : Bengkulu

A. Previous Status:

LARAP documents approved by World Bank on December 10, 2012

Monitoring Report No.1, 2 and 3 already approved and No Objection Letter (NOL) were issued byWorld Bank

Construction completed in April 11, 2016.

B. Pending Issues, Concern and Actions

No more issue, LARAP fully completed.

C. Update during this reporting month of August 2018

a) Total PAP = 261; Compensated = 261; Percent complete = 100%.

5. Monitoring Report of the LARAPPackage No. 5 : Sp. Rampa – PoriahaProvince : Sumatera Utara

A. Previous Status:

Revision of the Additional LARAP documents signed by Satker II North Sumatera Province

6 APs already be relocated to the permanent houses

Compensation for 85 from total 92 APs (updated 98 Aps) has been paid by Satker.

B. Pending Issues, Concern and Actions

Complete.

C. Update during this reporting month of August 2018

a) For the remaining of 7 already paid by Satker

6. Monitoring Report of the LARAPPackage No. 6 : Pasar Pedati - KerkapProvince : Bengkulu

A. Previous Status:

World Bank issued on May 30, 2015 a No Objection Letter on the revised LARAP documents forimplementation.

Monitoring Report concerning the compensation payment for 546 out of 637 PAPs was given NoObjection Letter (NOL) on March 23, 2015.

Monitoring Report regarding compensation payment for the remaining 91 PAPs out of 637 PAPshas been given No Objection Letter (NOL) on January 5, 2016.

B. Pending Issues, Concern and Actions

Page 60: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

4 - 32

No more issue, LARAP fully completed.

C. Update during this reporting month of August 2018

a) On-going construction.

b) Total PAP = 637; Compensated = 637; Percent complete = 100%.

c) For certification process of 72 Aps is under budgeting allocation on Revision-4 DIPA 2018

7. Monitoring Report of the LARAPPackage No. 7 : Indrapura - TapanProvince : Sumatera Barat

A. Previous Status:

LARAP documents approved by World Bank on October 14, 2014.

Implementation action plan of the LARAP was issued No Objection Letter (NOL) on March 17,2015 by the World Bank.

A report of the compensation payment for 276 from total 861 PAPs already submitted to WorldBank on February 9, 2016 and no objection letter (NOL) was issued on March 16, 2016.

Monitoring Report No. 2 for the compensation payments of 207 PAPs submitted to WB on July 21,2016 and no objection letter (NOL) was issued on August 18, 2016.

A monitoring report of the payment progress for 89 PAPs has submitted to WB and no objectionletter (NOL) was issued on November 12, 2016

A monitoring report of the payment progress for 61 PAPs has submitted to WB and no objectionletter (NOL) was issued on January 16, 2017.

A monitoring report of the payment progress for 20 PAPs has submitted to WB and no objectionletter (NOL) was issued on June, 2017.

PHO of the package is 28 January 2018

Satker conducts design change on the land that be occupied 4 affected persons which is not paidby Satker PJN II West Sumatera

B. Pending Issues, Concern and Actions

No more issue.

C. Update during this reporting month of August 2018

a) Total PAP = 878; Compensated = 878; Percent Complete = 100%.

8. Monitoring Report of the LARAPPackage No. 8 : Bts. Pariaman - ManggopohProvince : Sumatera Barat

A. Previous Status :

LARAP documents submitted to World Bank on August 7, 2014.

LARAP documents approved by World Bank on August 12, 2014.

Monitoring Report for the payment of 840 PAPs has been submitted to World Bank on January 14,2016 and issued on March 8, 2016.

Monitoring Report for compensation payment of 926 PAPs submitted to WB on May 9, 2016 andno objection letter (NOL) was issued on May 12, 2016

A monitoring report of the payment progress for 440 PAPs has submitted to WB and no objectionletter (NOL) was issued on January 6, 2017

Page 61: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

4 - 33

B. Pending Issues, Concern and Actions

Complete

C. Update during this reporting month August 2018

a) Total PAP = 2,339 (updated); Compensated = 2,339; Percent complete = 100%.

9. Monitoring Report of the LARAPPackage No. 9 : Rantau Tijang – Kota AgungProvince : Lampung

Cancelled from the WINRIP Program.

10. Monitoring Report of the LARAPPackage No. 10 : Sp. Empat – Sp. Air BalamProvince : Sumatera Barat

A. Previous Status :

LARAP documents submitted to World Bank on August 7, 2014.

LARAP documents approved by World Bank on August 12, 2014.

Monitoring Report for payment of 1,421 PAPs has been submitted to World Bank on January 14,2016 and Bank issued No Objection Letter (NOL) on March 8, 2016.

B. Pending Issues, Concern and Actions

Payments for the remaining 1,190 PAPs not yet paid by Satker PJN I West Sumatera and LocalGovernment.

C. Update during this reporting month of August 2018

a) Monitoring Report for payment of 138 PAPs on-going preparation by Satker PJN I SumateraBarat.

b) PPK/Satker PJN I West Sumatera and Local Government continue the appraisal andpayment processing of the remaining PAP.

c) Total PAP = 2,915; Compensated = 1,725; Percent complete = 59.18%.

Cancelled from the WINRIP Program

11. Monitoring Report of the LARAPPackage No. 11 : Bantal - MukomukoProvince : Bengkulu

A. Previous Status :

World Bank issued on May 30, 2014 a No Objection Letter (NOL) on the revised LARAP documentsfor implementation.

Monitoring Report No.1 and No.2 were issued No Objection Letters (NOL) from the World Bank.

Monitoring Report No. 3 regarding the payment for 15 of the remaining 123 PAPs was given NoObjection Letter (NOL) on November 26, 2015

A monitoring report of the payment progress for the remaining 89 PAPs already submitted to WBand no objection letter (NOL) was issued on October 28, 2016

B. Pending Issues, Concern and Actions

No more issue.

Page 62: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

4 - 34

C. Update during this reporting month of August 2018

a) Complete.

b) Total PAP = 243 (updated); Compensated = 243; Percent complete =100%.

12. Monitoring Report of the LARAPPackage No. 12 : Kambang - IndrapuraProvince : Sumatera Barat

A. Previous Status :

LARAP documents approved by World Bank on October 14, 2014.

Signed Action Plan of LARAP was given No Objection Letter (NOL) by the World Bank.

Monitoring Report for compensation payment of 216 PAPs submitted to WB on May 26, 2016.

A Monitoring Report of the compensation payment progress for 60 PAPs has submitted to WBand no objection letter (NOL) was issued on November 14, 2016

A Monitoring Report of the compensation payment progress for 88 PAPs has submitted to WBand no objection letter (NOL) was issued on Feb 13, 2017

A Monitoring Report of the compensation payment progress for 265 PAPs has submitted to WBand no objection letter (NOL) was issued on June, 2017

A Monitoring Report of the compensation payment progress for 286 PAPs has submitted to WB

B. Pending Issues, Concern and Actions

No more issue.

D. Update during this reporting month of August 2018

a) Satker will conducts design change on the land that be occupied 2 affected persons which isnot paid by Satker.

b) Total PAP = 2,873 (updated); Compensated = 2.873; Percent complete = 100%.

13. Monitoring Report of the LARAPPackage No. 13 : Sp. Rukis – Tj. KemuningProvince : Bengkulu

A. Previous Status :

World Bank issued on May 30, 2014 a No Objection Letter (NOL) on the revised LARAP documentsfor implementation.

Signed Action Plan of LARAP was given No Objection Letter (NOL) by the World Bank.

World Bank issued on August 18, 2015 No Objection Letter (NOL) on the monitoring Report No.1.

World Bank issued on October 13, 2015 No Objection Letter (NOL) on the monitoring Report No.2.

Monitoring Report No.3 for compensation payments of 193 PAPs in Kab. Kaur submitted to WBwhich was submitted on February 23, 2016 has been issued by the Bank the NOL on March 8,2016.

Monitoring Report No.4 for compensation payments of 188 PAPs in Kab. Kaur submitted to WBwhich was submitted on October 6, 2016 has been issued by the Bank the NOL on October 12,2016.

Monitoring Report of the payments progress for 333 PAPs has submitted to WB has been issuedby the Bank the NOL on November 18, 2016.

Monitoring Report of the payments progress for 1.090 PAPs has submitted to WB has been issued

Page 63: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

4 - 35

by the Bank the NOL on March 20, 2017.

Monitoring Report of the payments progress for 186 PAPs has submitted to WB has been issuedby the Bank the NOL on May 23, 2017

B. Pending Issues, Concern and Actions

Complete

C. Update during this reporting month of August 2018

a) Satker will conducts design change on the land that be occupied 53 affected persons which isnot paid by Satker.

b) The remainning of 50 Aps already paid by Satker

c) For certification process of 382 Aps is under budgeting allocation on Revision-2 DIPA 2018.

d) Total PAP = 3.040; Compensated = 3.040, Percent complete = 100%

14. Monitoring Report of the LARAPPackage No. 14 : Painan - KambangProvince : Sumatera Barat

A. Previous Status :

World Bank issued on December 19, 2014 the No Objection Letter to the LARAP documents.

LARAP’s signed action plan was given No Objection Letter (NOL) by World Bank.

Monitoring Report No.1 for compensation payments of 126 PAPs submitted to WB which wassubmitted on July 20, 2016 has been issued by the Bank the NOL on August 1, 2016.

Monitoring Report of the payments progress for 62 PAPs has submitted to WB on Nov 11, 2016

Monitoring Report of the payments for 220 PAPs has been issued by the Bank the NOL on March20, 2017

Monitoring Report of the payments for 59 PAPs has been issued by the Bank the NOL on May,2017

Monitoring Report of the payments for 402 PAPs has been issued by the Bank the NOL on July 14,2017

A Monitoring Report of the compensation payment progress for 386 PAPs has submitted to WB

B. Pending Issues, Concern and Actions

No more issue.

C. Update during this reporting month of August 2018

a) Satker conducted design change on the land that be occupied 57 affected persons which isnot paid by Satker

b) Total PAP = 2,242 (update); Compensated = 2,242; Percent complete = 100%.

Page 64: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

4 - 36

15. Monitoring Report of the LARAPPackage No. 15 : Sibolga – Bts. TapselProvince : Sumatera Utara

A. Previous Status :

World Bank approved the LARAP documents on February 6, 2014 for implementation in acquiringRoad Right of Ways and removal of obstruction.

Monitoring report No.1 for 40 of the remaining 1.554 PAPs was given No Objection Letter (NOL)on November 16, 2015.

Monitoring Report No.2 for payment of remaining 72 PAPs already submitted to World Bank.

Monitoring Report-3 for the compensation payment for 237 from the remaining 1.439 PAPsalready be submitted to WB on February 19, 2016 and Bank issued no objection letter (NOL) onMarch 16, 2016.

Monitoring Report No.4 for compensation payment of 55 PAPs submitted to WB on April 13,2016 and Bank issued no objection letter (NOL) on May 19, 2016.

Monitoring Report No.5 for compensation payment of 34 PAPs submitted to WB on August 8,2016 and Bank issued no objection letter (NOL) on August 18, 2016.

Monitoring Report No.6 for compensation payment of 127 PAPs is under submission to WB andBank issued no objection letter (NOL) on January 26, 2017.

Monitoring Report No.7 for compensation payment of 134 PAPs is under submission to WB andBank issued no objection letter (NOL) on July 14, 2017.

A Monitoring Report of the compensation payment progress for 815 PAPs has submitted to WB

B. Pending Issues, Concern and Actions

No more issue

C. Update during this reporting month of August 2018

a) The remainig of 18 Aps already paid by Satker.

b) Satker will conducts design change on the land that be occupied 17 affected persons whichis not paid by Satker

c) For certification process of 321 Aps is under budgeting allocation on Revision-2 DIPA 2018

d) Total PAP = 1.820 (update); Compensated = 1.820; Percent complete = 100%.

16. Monitoring Report of the LARAPPackage No.16 : Seblat - IpuhProvince : Bengkulu

A. Previous Status :

World Bank issued on May 30, 2014 a No Objection Letter (NOL) on the revised LARAP documentsfor implementation.

World Bank issued No Objection Letter (NOL) on Monitoring Report No.1 and 2 for LARAPimplementation.

Monitoring report for 102 of the remaining 120 PAPs was given No Objection Letter (NOL) onNovember 26, 2015.

Updated LARAP documents submitted on February 22, 2016 to World Bank with NOL issued byBank on March 8, 2016.

Page 65: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

4 - 37

Monitoring Report No.3 for compensation payment of 33 PAPs submitted to WB on October 24,2016 and NOL issued by Bank on November 11, 2016

B. Pending Issues, Concern and Actions

No more issue

C. Update during this reporting month of August 2018

a) Total PAP = 259; Compensated = 259; Percent complete = 100.00%.

17. Monitoring Report of the LARAPPackage No.17 : Sp. Gunung Kemala – Pg. TampakProvince : Lampung

A. Previous Status :

World Bank approved the corrected LARAP documents on November 12, 2013

Monitoring Report for 154 of the total 2,014 PAPs was given No Objection Letter (NOL) onOctober 13, 2015.

Monitoring Report for 735 of the remaining 1.860 PAPs was given No Objection Letter (NOL) onNovember 26, 2015.

A Monitoring Report for the compensation payments progress for 1,156 APs was given NoObjection Letter (NOL) on November 18, 2016.

Monitoring Report No.4 for compensation payment of 462 PAPs was given No Objection Letter(NOL) on April 17, 2017.

This package was PHO during Dec 2017

Satker conducted the design change on the land that be occupied 56 affected persons which isnot paid by Satker

B. Pending Issues, Concern and Actions

Certification (2.247 plots) not yet resolved

A. Update during this reporting month of August 2018

a) Satker conducted design change on the land that be occupied 56 affected persons which isnot paid by Satker

b) For certification process of 2.247 Aps is under budgeting allocation on Revision-2 DIPA 2018

c) Total PAP = 2,285 (update); Compensated = 2,585; Percent complete = 100%.

18. Monitoring Report of the LARAPPackage No.18 : Mukomuko – Bts. SumbarProvince : Bengkulu

Cancelled from the WINRIP Program.

19. Monitoring Report of the LARAPPackage No.19 : Lais - BintunanProvince : Bengkulu

B. Previous Status :

World Bank issued on May 30, 2014 No Objection Letter (NOL) on the revised LARAP documentsfor implementation

World Bank issued No Objection Letter (NOL) on Monitoring Report No.1 for the LARAPimplementation.

Page 66: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

4 - 38

Monitoring Report for 208 of the remaining 272 PAPs was given No Objection Letter (NOL) onNovember 26, 2015.

A Monitoring Report for the compensation payments progress for the remaining of 64 APs hassubmitted to WB and NOL issued by Bank on November 11, 2016.

C. Pending Issues, Concern and Actions

No more issue LARAP fully completed.

Certification (290 plots) not yet resolved

D. Update during this reporting month of August 2018

a) For certification process of 193 Aps is under budgeting allocation on Revision-2 DIPA 2018

b) Total PAP = 538 (updated); Compensated = 538; Percent complete = 100%.

20. Monitoring Report of the LARAPPackage No. 20 : Lubuk Alung - SicincinProvince : Sumatera Barat

A. Previous Status :

World Bank issued NOL to LARAP documents on December 19, 2014.

NOL WB of the Monitoring Report of the payments progress for 670 PAP on Sep 26, 2016.

A monitoring report of the payment progress for 280 Aps already submitted to WB and approvedby WB on April 17, 2017.

B. Pending Issues, Concern and Actions

No more issue LARAP fully completed.

C. Update during this reporting month of August 2018

a) Satker conducted the design change on the land that be occupied 72 affected personswhich is not paid by Satker

b) Total PAP =950 (updated); Compensated =950; Percent complete =100%.

21. Monitoring Report of the LARAPPackage No. 21 : Lubuk Alung - KuraitajiProvince : Sumatera Barat

A. Previous Status :

World Bank issued NOL to LARAP documents on December 19, 2014.

NOL WB of the Monitoring Report-1 for compensation payment of 515 out of the total 869 PAPson August 23, 2016

A Monitoring Report of the compensation payments progress for 236 Aps has submitted to WBand NOL issued by Bank on January 24, 2017

B. Pending Issues, Concern and Actions

No more issue LARAP fully completed

C. Update during this reporting month of August 2018

a) Satker will conducts the design change on the land that be occupied 6 affected personswhich is not paid by Satker

b) Total PAP = 908 (updated); Compensated = 908; Percent complete = 100%.

Page 67: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

4 - 39

4.7 Anti Corruption Issues4.7.1 Anti‐Corruption Action Plan (ACAP)

ACAP for WINRIP was developed from the previous SRIP experiences. Basically, it has the same maincomponents of involving the Community Representative Observers (CRO) in the bid opening and ThirdParty Monitoring (TPM) during the construction supervision although modification was made on theselection process of the CROs for SRIP. Within this plan there are four main pillars as indicated separatelybelow

a) Community Representative Observers (CRO)b) Publication / Disclosurec) Complaints Handling System (CHS)d) Third Party Monitoring (TPM)

4.7.2 Community Representative Observers (CRO)

The Community Representative Observers, who are required to observe the actual bidding activities, wereappointed for WP-1 group. All of the CROs were university staff, selected in accordance with the WorldBank suggestion to request assistance from local universities.

CRO is the independent observer who is not related directly or indirectly to the Contractors, Consultants,and Suppliers or not be part of the WINRIP’s management, and not a member of any political party.

CROs selection procedures:

a. Review the criteria and qualifications of candidates for the CRO.b. Director of Planning, DGH/ as Chairman of the Project Management Unit, delegated the authority to

the selection of the CRO to the Head of National Roads Implementation Agency(BBPJN) / Head of Procurement Services Unit (Unit Layanan Pengadaan - ULP), hereinafter referred to asHead of Balai.

c. Head of Balai to invite CRO candidates from the local universities or colleges.d. Selection of CRO to be facilitated by Balai (BBPJN) / Procurement Services Unit (Unit Layanan

Pengadaan - ULP).e. Elected CRO and substitute CRO must attend one day training to be conducted by the PMU / CTC

WINRIP.f. Head of Balai to report the result of CRO selection by attaching the Minutes of Election Meeting and

send an approval application letter of the CRO to Director of Planning DGH as the Chairman of PMU.g. Based on the report and a written request from the Head of Balai, the Director of Planning DGH as the

Chairman of PMU must sign a Letter of Agreement and the Decree of the Establishment of CROs.

The duties and obligations of CRO are:

a. CRO must be present in any procurement activity (Pre-Bid Meeting, Site Visit, Bids Submission andOpening of Bids, and Announcement of Bids Winner) by invitation of the Procurement Committee, andare required to sign the attendance list

b. If the elected CRO is unable to attend on procurement activities, a Substitute CRO shall be appointed toattend these activities.

c. In discharging of duties the Substitute CRO have the same responsibilities as elected CRO.

Page 68: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

4 - 40

d. The CRO / Substitute CRO, after attending the Procurement activities, required to make a report ofhis/her activities and submit them to the PMU and copy furnished to the related Head of Balai.

CRO as the representative of the community is to be independent observers and in performing their dutiesvoluntarily and not demanding benefits of their works.

In the performance of its duties, the CROs receive transportation cost from their home / office to thelocation of procurement meeting, and also he / she also receives per diem or Out Station Allowance (OSA)and hotel accommodation if necessary to stay. CROs also get additional charged for their reporting costs.The financing standards adjusted to the General Cost Standard (Standar Biaya Umum) issued by theMinistry of Finance.

The CRO’s financing charged to the Contract for Consulting Services for Technical Assistance for Core TeamConsultants (CTC) No: 06-20/CTC/TA/LN/8043/1112, dated 5 November 2012.

4.7.3 Publication / Disclosure

The second task under ACAP is publication of related ACAP documents for public disclosure with easyaccess to the general public and this is mainly manifested in the ACAP segment of the WINRIP website. ThisACAP section has been being designed to attain the best possible transparency of the project.

Ministry of Public Work (MPW) will provide necessary information in the Project Implementation Plan (PIP),Project Management Manual (PMM) on its website, and in the bidding documents, such as contact pointfor complaint (mail and e-mail address, phone, fax, text message). The contact will also include the Bank’sFraud and Corruption Hotline. MPW will hold Annual Accountability Meetings to enhance accountabilityand project information sharing with civil society. The PMM will provide guidelines on disclosure ofinformation related to the project. MPW official website will display critical information on WINRIP toenhance both internal and external monitoring of the project:

Work Plan and Procurement Plan.

Quarterly newsletter containing information on the list of contracts, implementation progress, projectsrelated activities, number, types and status of complaints in each location. The newsletter will also bemade available to civil society in hard copy and through electronic mailing system.

Mid-Term Review Report, promptly after completion of the mid-term review implementation support iscarried out in accordance with the loan agreement;

All final audit reports (financial or otherwise, including qualified audit reports) prepared in accordancewith the loan agreement and all formal responses of the government in relation to such reports. Thepublication should be done within one month after the report is accepted as final.

Contracts awarded with information on general scope of work (with location), value, and summaryinformation of the awarded firms/ contractors. The practice in other projects demonstrates thatdisclosure of contracts awarded will help in reducing fraudulent practices

Ministry of Public Works (MPW) maintains a website: http://www.pu.go.id/, with a link to 'eproc.pu.go.id'for information on semi e-procurement or e-procurement. PMU WINRIP supported by CTC will developtheir own website: http://www.winrip-ibrd.com, and with it all the information and data about WINRIP beinputted or uploaded on this site.

Page 69: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

4 - 41

In the application of one of the components of ACAP, the public disclosure and transparency, it is necessaryto spread information and increase the capacity of all stakeholders involved in the implementation of thisWINRIP project, through a variety of relevant training. The trainings have been expressed in the TOR of CTCWINRIP and described in the Project Implementation Plan (PIP).

One of the major risks to effective project implementation and management derives from the likelihoodthat project management staff does not have adequate training in or experience of the management oflarge-scale projects.

4.7.4 Complaints Handling Mechanism (CHS)

The ACAP as adopted by the Ministry of Public Works for WINRIP states on the subject of “ComplaintsHandling System”. The Community Development Specialist and the Management Information Specialist willplay a crucial role in the set-up of the Complaints Handling System (CHS) within PMU, in cooperation withthe PMU officer(s) in charge of the Complaints Handling Unit (CHU).

CHS essentially has four main components as follows:

Data Entry.

All complaints are expected to be submitted through the WINRIP website but in fact, to date, mostcomplaints have been received by letter, either directly or indirectly, although a few were sent by faxor email. However, to attain the best possible transparency of the project, complaints submittedmanually through letter, facsimile, telephone, e‐ mail or visit to the Public Works regional offices willbe entered in the WINRIP website by the CHS team of CTC. The possibility of using the ‘short messageservice’ (SMS) from a cell phone for complaints was considered and it was decided that all SMSmessages, although not treated as formal complaints, will be recorded as additional information.

Complaint Registration.

Every submitted complaint is registered and stored into the CHS database, categorized, and sent tothe correlated expert for future consultation in order to formulate a response.

Complaint Assessment.

The CHS Team assesses the urgency and complexity of all complaints. Simple complaints are followedby the formulation of a response for PMU’s approval before uploading the formal response into theWINRIP website. Complex complaints are followed by a thorough investigation.

Field Investigation and Analysis.

In the case of an investigation being required, the CHS team will make field visits and take necessaryaction such as discussion with related institutions (Satker, Dinas, Supervision Consultant, etc); invitethe complainer; interview the contractor; etc. Findings will be used for analysis to formulate aconclusion, solution, next action and any further decision.

4.7.5 Third Party Monitoring (TPM)

All WINRIP packages are designed to have external parties involved in conducting an independent

Page 70: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

4 - 42

assessment of the project throughout construction. Project information is accessible through the WINRIPwebsite (under construction), project information booth which is normally maintained in thePPK/Satker/Dinas office or, project announcement (billboard) at each site. ACAP requires a third party, fromoutside the project, to independently monitor the progress of construction work of each link and thesepersonnel are provided by universities nearby each package.

It was decided that the best method of recruitment for TPM was through the universities closest to eachpackage and PMU mailed invitations asking them to express their interest in forming independentmonitoring teams of Third Party Monitors. This concept is based on the fact that Universities/TechnicalFaculties have the engineers available for recruitment and Universities could use this opportunity to beinvolved in public service. It is hoped that this concept will be more effective and more efficient in gettinglegitimate, competent, independent Third Party Monitoring (TPM).

The duties of a TPM included:a) Report to the PPK for his intended package and obtain copies of all drawings and contract

documentation.b) Make at least three (3) separate visits to site, with each visit up to four (4) days long, and ascertain that

the works are being carried out in compliance with the drawings and documentation.c) Prepare and submit a report for the PMU following each visit with their last report post PHO.

4.8 Road Safety Audit

Since the Senior Road Safety Audit Engineer has been mobilized on 1st May 2013 until hisdemobilization on April 1st 2014, technical design and road safety engineering review and road safetyaudit for several packages in AWP-2 and AWP-3 sub-projects has been implemented.

However, there were still some task which were not covered by the Senior Road Safety Engineer duringthe duration of the road safety audit stage. Upon mobilization of the National Road Safety Engineer andthe Assistant Road Safety Engineer who were mobilized on June 2, 2014 and November 3, 2014respectively, the remaining road safety audit works were continued.

The remaining works are as follows:

1. Road Safety Audit at DED stage, for :a. AWP-3 sub-project (Packages 14, 16, 20 and 21)

2. Road Safety Audit at Construction Stage, for :a. AWP-1 sub-projects (Packages 1, 2, 3 and 4)b. AWP-2 sub-projects (Packages 5, 6, 8, 10, 11, 12 and 13)c. AWP-3 sub-projects (Packages 14, 15, 16, 17, 19, 20 and 21)

3. Road Safety Audit at Pre-opening Stage, for :a. AWP-1 sub-projects (Packages 1, 2, 3 and 4)b. AWP-2 sub-projects (Packages 5, 6, 7, 8, 10, 11, 12 and 13)c. AWP-3 sub-projects (Packages 14, 15, 16, 17, 19, 20 and 21)

Road Safety Audit at detailed design stage is to identify the road safety weaknesses in design drawingsthrough site visiting, review of design drawings and official meeting with stake holder. Road Safety

Page 71: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

4 - 43

Audit report is the recommendation for improvement of road safety.

Road Safety Audit at Construction stage or Traffic Management and Safety Monitoring is to check theperformance of contractors related to the implementation of application management and trafficsafety in the field.

Road Safety Audit at pre-opening stage is to ensure that the road has been built as designed and toidentity any safety issues that may have been missed through the design process.

The overall progress of the different stages of Road Safety Audit are shown in Appendix B.

Page 72: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

5 - 1

5 FINANCIAL & MANAGEMENT INFORMATION SYSTEMS

5.1 Draw‐Downs and Future CostsDetails of the disbursements already made from the loan are listed in the followingsub‐section.

5.2 DisbursementThe total disbursement by World Bank from the loan to the end of August 2018 was USD175,701,077.12 equivalent to approximately 69.71% of the loan funds. A total disbursementof USD 1,417,193.08 was made during the month of August 2018 for the payment InterimPayment Certificates for the Statement of Work Accomplished under Category 1 Part 1 of theloan agreement.

The total expenditure to date measured in the term of the World Bank commitment, notincluding the Special Account advance, is shown in Appendix C. The following tablesummarizes the individual disbursements as calculated by CTC but retaining the totaldisbursement from Client Connection at the end of August 2018.

Category DescriptionLoan Restructuring

Amount USDTotals Disbursed toEnd August 2018 in

USD% Disbursed

1Part 1 Betterment andCapacity Expansion of

National Roads.225,400,000.00 165.493.950,29 73.42

2Part 2

Implementation Support17,000,000.00 10.207.126,83 60.04

3Part 3

Road Sector InstitutionalDevelopment

0 0 0

4Part 4

Contingency for DisasterRisk Response

0 0 0

Unallocated 7,600,000.00 0 0

OriginalLoan

Amount250,000,000.00 175,701,077.12 70.28

5.3. Management Information System

5.3.1. General OverviewThe Management Information System tasks are as follows below:

1) Information Systema. Develop and manage the File Storage as database system to store soft copy

documents into the server.b. Establish the Document Management System (DMS) to provide:

Letter Database System, used to record all information of incoming andoutgoing letter.

Page 73: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

5 - 2

Document Library System, used to record all information of hard copydocuments then store it into library shelves.

c. Create and updated content of the WINRIP official website.d. Develop and updated content of the Website Geographic Information System

(WebGIS) of spatial and roads information that overlay into Google Maps.e. Develop, manage and updated content of the Financial Management

Information System (FMIS), the web based application to monitoring thefinancial report and the physical progress report.

f. Provide and manage of the Complaint Handling System (CHS), used andsupport the ACAP activities to accommodate complaints from the public.

2) Data Collection and Document Uploada. Collecting data and updating list of data catalog every month.b. Uploading documents into a file storage server.

3) Technical and Computer Troubleshootinga. Setting up and manage cable network of local area network and internet

connection.b. Setting up and manage hardware problem of the computer, printer, copier

and phone.c. Software installation and cleaning up of computer virus.

5.3.2. Database

A typical workflow in management of incoming and outgoing data is divided into 3types of data handling, below:

1. Hardcopy, the document is stored in a rack.2. Soft files, saved in the File Storage Server.3. Data information, inputted in database applications.

For further handling that needs to be made an integrated database managementsystem so that all data can be stored properly. The database system has been

Incoming andOutgoing Data Administrator Saved

Stored

Inputted

File StorageServer

Shelves

DatabaseApplication

Soft File

Hard Copy

DataInformation

Typical Workflow ofDatabase Management

Page 74: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

5 - 3

prepared to store all of WINRIP project information in a systematic, easilytraceable, maintainable, and manageable format as outlined below with the followingsystems:

a. File Storage Server, used to stored all files of report and other document. Pleasecheck the URL address http://storage.winrip-ibrd.com.

b. Document Management System (DMS), used to record all information of letter anddocument files. The URL address of the DMS application will be athttp://dms.winrip-ibrd.com. The DMS have 2 main modules below:

1. Letter Database System, used to record all information of incoming andoutgoing letter.

2. Document Library System, used to record all information of document andreport files.

Page 75: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project1

6 - 1

6 PROJECT PERFORMANCE

6.1 World Bank and GOI Compliance

6.1.1 World Bank Missions

A World Bank supervision mission for implementation review took place on July 3, 2018 withcoordination meeting.

6.1.2 Agreed Key Actions and during the Coordination Meeting

Lists of the key actions monitored during the period are listed below.No. Action By Whom Update Status

July 3, 2018New Deadline

1 Package 5 – Send to the PMU a letter insistingon not operating the road until the slopeprotection works is completed.

WB New action. July 6, 2018

2 Package 5 – Clarify the situation of theremaining 38 affected people who did notreceive the compensation payment.

PMU/CTC New action. July 6, 2018

3 Package 5A – Carry out the re-bidding processincluding the World Bank’ssuggestions/improvements in the biddingdocuments.

PMU/CTC As soon as possible.

4 Package 12 – Pay particular attention to thequality of the civil works and reject them if thetechnical specification is not fully met.

PMU/CTC/DSC Continuously.

5 Package 13 – Send to the WB informally therevised design modifications on the sectionswhere the land acquisition activities could benot completed.

PMU/CTC/DSC July 13, 2018.

6 Package 14 – Pay particular attention to thequality of the civil works and reject them if thetechnical specification is not fully met.

PMU/CTC/DSC Continuously.

7 Package 14 – Send to the WB informally therevised design modifications on the sectionswhere the land acquisition activities could benot completed.

PMU/CTC/DSC July 24, 2018.

8 Packages 12 and 14 – Inform to the WB on thequarry permit status.

PMU/CTC/DSC New action. Mid-July 2018.

9 Packages 12 and 14 – Send to the WB thecontract time extension requests.

PMU/CTC/DSC New action. Mid-July 2018.

10 Package 15 – Send to the WB informally the RoadSafety department’s comments on the designmodifications on the sections where the landacquisition activities could be not completed.

PMU/CTC/DSC July 6, 2018.

11 Package 15 – Send to the WB the civil works costreduction justification.

PMU/CTC/DSC New action. July 30, 2018.

12 Package 16 – Pay particular attention to thequality of the civil works and reject them if thetechnical specification is not fully met.

PMU/CTC/DSC Continuously.

13 Package 16 – Sent to the WB the investigationreport on the asphalt mixing plant (AMP).

PMU/CTC/DSC July 13, 2018.

14 Package 16 – Carry out a field inspection toevaluate potential uses of the remaining fundsunder this package.

WB New action. July 9-13, 2018.

15 Package 21 – Send to the PMU the response tothe no objection request for the contracttermination.

WB July 6, 2018.

16 Package 21A– Send to the WB informally the PMU/CTC/DSC New action. July 6, 2018.

Page 76: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project2

6 - 2

No. Action By Whom Update StatusJuly 3, 2018

New Deadline

revised design and bill of quantities. A field visitcould be considered.

(i) 17(ii) Package 21A – Send to the PMU the commentson the revised procurement plan.

WB July 6, 2018.

(iii) 18(iv) Send to the WB the action plan to fix the qualityshortcomings observed during the DLP inspectionfor packages 2, 3, 4, 6, and 19.

PMU/CTC/DSC October 2018.

(v) 19(vi) Ensure that there is a valid contract in place toimplement the design changes in packages 13, 14and 15.

PMU

(vii) 20(viii) Carry out an environmental safeguard site visitfor packages 13 and 16.

WB Done – May 30, 2018.

(ix) 21(x) Closely monitor the contractors’ efforts inmaintaining good housekeeping, improving thehazardous waste storages, upgrading thesecondary containment, and regularly raisingenvironmental awareness in all workers andsubcontractors.

PMU Regularly.

(xi) 22(xii) Send to the Bank the FY2017 traffic data. Informthe WB about any methodological change incalculating the previous years’ traffic data.

PMU/CTC July 31, 2018.

(xiii) 23(xiv) Send to the WB the latest signed amendmentsfor time extension for the remaining civil workspackages and the DSC and CTC contracts.

PMU/CTC/DSC Partially done – CTCamendment no.7 sent

on May 28, 2018.

DSC amendment no. 3:July 13, 2018.

(xv) 24(xvi) Submit to the WB the pending LARAPsimplementation monitoring reports.

PMU and CTC Package 17: mid-July2018;Packages 5, 14, and 21:beginning of August2018;Packages 7, 12: end ofAugust 2018;Package 13 and 15: endof July 2018.

(xvii) 25(xviii) Submit to the WB the confirmation letterreflecting that sufficient budget will be allocatedto conduct the splitzing process.

PMU and CTC End of August 2018.

(xix) 26(xx) Send to the WB all the outstanding TFACresponses for packages 1, 4, 6, 19, and 21.

PMU/DSC/CTC Mid-July 2018.

(xxi) 27(xxii) Send to the WB the basecamp demobilizationstatus for the 18 packages (ongoing andcompleted). Field visits could be considered.

PMU/DSC/CTC Mid-July 2018.

(xxiii) 28(xxiv) Submit to the WB the NOL request for the DSCcontract amendment no. 4.

DSC New action. July 15, 2018.

(xxv) 29(xxvi) Send to the WB the slope protection technicalassistance time extension request to hold thetechnical workshop.

PMU/CTC Mid-July 2018.

(xxvii) 30(xxviii) Publish the revised Procurement Plan, includingpackages 5A and 21A, in the MPWH’s website.

PMU/CTC July 13, 2018.

(xxix) 31(xxx) Submit to the WB the quarterly IFR for the periodApril to June 2018.

PMU August 15, 2018.

(xxxi) 32(xxxii) Update the WINRIP website with all the receivedcomplaints through the Complaint Handling Unit(CHU).

PMU and CTC July 6, 2018.

(xxxiii) 33(xxxiv) Send to the WB the environmental managementand monitoring plan of RKPPLs and UKL-UPLimplementation quarterly and every semesterrespectively for all packages.

PMU and CTC Quarterly and eachsemester.

(xxxv) 34(xxxvi) Submit regularly to the WB the quarterlyprogress reports.

PMU This activity must becarried out every

Page 77: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project3

6 - 3

No. Action By Whom Update StatusJuly 3, 2018

New Deadline

calendar quarter.(xxxvii) 35(xxxviii) Update the newsletter quarterly, including the

list of contracts, implementation progress,project related workshops, and number, typologyand status of complaints.

PMU This activity must becarried out everycalendar quarter.

(xxxix) 36(xl) Send the quarterly newsletter to the civil societyforum in each project province in hard copy orthrough an electronic mailing system.

PMU This activity must becarried out everycalendar quarter.

(xli) 37(xlii) Update the WINRIP website with allenvironmental documents including RKPPLs,RKPPL and other monitoring reports, etc.

PMU and CTC Mid-July 2018.

(xliii) 38(xliv) Send to the WB informally the revised draftrestructuring/closing date extension request.

PMU and CTC Mid-July 2018.

6.1.3 The Next Supervision MissionThe next supervision mission will take place in October/November 2018. The next formalproject progress review will be carried out in early July 2018.

6.1.4 Performance IndicatorsKey Performance Indicators are developed and agreed between the World Bank and GOI,and will be monitored over the whole project period the changes in variables will becalculated annually. The set indicators are describing in the project Appraisal Document(PAD) and the Loan Agreement between the GOI and the World Bank.

The overall progress towards achieving the PDO of increasing the effective use of selectedsections of national roads along the Western Sumatra Corridor by reducing road user costsis considered moderately satisfactory. Progress in implementation has picked up, andthere has been an advance with respect to several project indicators. In addition, a projectrestructuring is being processed which should bring the project largely back on track.

The PMU provided an update on the achievement of the indicator targets. There has beenrelatively good progress on three of the five intermediate indicators. For one of theremaining intermediate indicators on bridge improvement, progress is expected within thenext semester. The last intermediate indicator related to institutional strengthening will becancelled in the framework of project restructuring. For the PDO indicator on AADT, CTCcarried out static traffic counts in March 2015 and confirmed that the original indicatortargets are adequate. The mission refined a few indicators definitions/baselines andupdated some indicator targets to take into account the project implementation delays.These changes will be reflected in the upcoming project restructuring.

From the “baseline 2010 AADT and estimated AADT for the year 2014/2015, theextrapolated AADT for the year 2013 resulted to 11,254 vehicles per day or 8.8% above thetargeted 10,347 vehicles per day in 2013. Shown in Table 6.1 is the comparison betweentarget and actual estimated AADT.

Page 78: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project4

6 - 4

Table 6.1Year Targeted AADT EstimatedBaseline (2010) 7,837

FY1 (2013) target 10,347FY1 (2013) actual 11,254FY2 (2014) target 11,351FY2 (2014) actual 12,696FY3 (2015) target 12,453FY4 (2016) target 13,304

FY5 (2017) end target 14,214

Appendix I shows the updated WINRIP Performance Indicators.

6.2 Implementation Support Components

6.2.1 Core Team Consultant (CTC)

The CTC is responsible to provide support to the PMU and DGH in the management of the Project,based in Jakarta. The CTC tasks include financial and progress monitoring and reporting, informationmanagement and dissemination, quality assurance and performance review for the Design andSupervision Consultants (DSC), implementation and monitoring of the anti-corruption action plan,support for project monitoring and evaluation, and support for implementation of a trainingprogram to support project management and implementation.

The CTC contract No. 06-20/CTC/TA/LN/8043/1112 was signed on 5 November 2012 by both DGHand a Joint Venture of PT. Perentjana Djaja, Yongma Engineering Co.Ltd., and PT. EpadasconPermata Engineering Consultant.

The main CTC activities during August 2018 are as follows:

Preparation of Monthly Progress Reports.

Monitoring the implementations of the ESAMP, anti-corruption action plans, complains from project

site, progress of LARAP and financial progress.

Prepared and issued various letters to PMU and DSC.

Preparing the draft of outgoing letter for PMU and PIU.

Submitted various Reports to PMU concerning environmental, the status of LARAP implementations

and Site Visit Reports of each Specialist who conducted site inspection.

Monitored the actual construction progresses of the on-going contract packages and advised PMU

of the current situations of the sub-projects.

Monitored Base Camp Management Improvement & RKKPL for Package No. 11 and No.16.

survey and evaluation of premateur pavement cracks of Package No.11 Bantal-Mukomuko on

August 27 – 31, 2018.

Conducted Road Safety Audit for Package No.12 and 14 for PHO stage.

Page 79: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project5

6 - 5

Site Inspection by Co Team Leader and Quality Assurance Specialist for Packages No. 12 and No. 14

on August 23 – 25, 2018.

TFAC inspector Package No.05 and No.15 on August 6 – 8, 2018.

Site Inspection by Team Leader and Highway Engineer for Packages No. 16 on August 27 – 28,

2018.

6.2.2 Design and Supervision Consultant (DSC)

The Design and Supervision Consultant (DSC) will be responsible for design of WP 2 and WP 3 civilworks and supervision of all civil works. They will have the role of ‘Engineer’ under a FIDIC-typecontract. The tasks include the preparation and maintenance of a quality assurance plan, validationand updating of designs, supervision of all civil works, environmental and social monitoring andmanagement, and support for financial and progress monitoring and reporting.

The DSC will also be responsible for quality assurance of materials and workmanship, certifyingwhether or not contractors have achieved the required results, as well as documentation andreporting based on the financial management plan. They will prepare a Quality Assurance systemcovering all subprojects, and continuously monitor the effectiveness of their supervision procedures.The team will be contracted and managed by DGH through the Bina Marga Regional Office (Balai II),and will be based in Padang, West Sumatera.

DSC contract was negotiated in Balai Besar Pelaksanaan Jalan Nasional II (Balai-II) of DGH. Thenegotiation result and draft contract have been sent to WB on 25 March 2013 for review andapproval. The Bank issued no objection letter on the negotiation results and draft contract withletter dated 19 April 2013.

6.2.3 Study on Development of Slope Stabilization Design and Management

This component consists of technical assistance for analytical work of an alternative design for roadsegment that pass through critical environmental assets and vulnerable areas especially on slopeprotection design and management.

6.3 Anti‐Corruption Issues

6.3.1 Anti-Corruption Action Plan (ACAP)

The main duties of the Community Development Officer are implemented of Anti-CorruptionMeasures, and Monitoring their Effectiveness. Provide assistance as required with the establishmentof anti-corruption measures necessary to support the project, and monitor and report theireffectiveness based on the Anti-Corruption Action Plan (ACAP) agreed between the World Bank andthe DGH.

The following tasks particularly need to establish procedures to be undertaken:

Selection of Community Representative Observers (CROs) of civil society groups to attend the

Page 80: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project6

6 - 6

Procurements process on key procurement steps including Pre-Bid meeting and site visit, bidssubmission and bids opening, and the announcement of the bid winner. These CROs will beinvited from local universities or other selected independent institutions, and will sign theattendance list for the procurement/selection process.

Establishment of a Third Party Monitoring (TPM) mechanism, whereby the media and civilsociety groups can become involved in monitoring the progress of the project. This Mechanismwill include regular sharing of information with the media.

Establishment and Management of a Complaints Handling Mechanism System (CHS), whichincludes maintaining project complaint log and filing to monitor status of follow-up of eachcomplaint. This mechanism will include provision for follow up investigations of substantialcomplaints by the Inspectorate General of Ministry of Public Works or third party audit to ensureindependence and reliability of the system. The CTC assignment concerns the monitoring of theaspects of Anti-Corruption Action Plan (ACAP) implementation and where required act pro-active in resolving issues when such a matter arises. The Community Development Officer has amajor role in monitoring performance and assists PMU in the set-up and follow-through of theComplaints Handling Unit (CHU) for the ACAP related incidents

Enhanced Disclosure Provisions and Transparency, Ministry of Public Work (MPW) have beenprovided necessary information in the Project Implementation Plan (PIP), Project ManagementManual (PMM) on their website, and in the bidding documents, such as contract point forcomplaint (mail and e-mail address, phone, fax, text message). The contact will also include theBank’s Fraud and Corruption Hotlines. MPW will hold Annual Accountability Meetings toenhance accountability and project information sharing with civil society. The PMM will provideguidelines on disclosure of information related to the project. MPW official website will displaycritical information on WINRIP to enhance both internal and external monitoring of the project

6.3.2 Community Representative Observers (CRO)

The Anti-Corruption Action Plan (ACAP) on Community Representative Observers (CROs) aspectduring August, 2018 is relatively minor activity.

The activities progress of Community Representative Observers (CROs) from January 2013 untilAugust 2018, as shown in Appendix H1.

6.3.3 Third Party Monitoring (TPM)

The Third Party Monitoring (TPM) activity during August 2018 is relatively minor activity

The activities progress of the Third Party Monitoring (TPM) from January 2013 until August 2018, asshown in Appendix H2.

6.3.4 Complaint Handling System (CHS)

The Community Development Officer with collaboration with MIS Specialist has developed a

Page 81: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project7

6 - 7

software application of Complaint Handling System (CHS) in integrated to website of WINRIPhttp://www.winrip-ibrd.com.

In the implementation of Complaint Handling System (CHS) essentially there are four maincomponents as follows:

Data Entry. Complaint Registration. Complaint Assessment. Field Clarification and Analysis. Problem Solving and taking the Decision

The final draft of Complaint Handling System (the framework of the complaint procedures on theweb site of WINRIP and provided ACAP inputting data in the web site) has ready to be operated.

However these applications still continuously to be refined by considering input from various parties.The CHS team has been monitored and noted the public complaints via website of Sytem InformasiPemantauan Proyek “SiPP” / Project Monitoring Information System and WINRIP website.

On August 2018 the Complaint Handling Unit had not received any complaint from any parties.

The Complaints Handling Mechanism System (CHS) Activities is shown in Appendix H3.

6.3.5. Public Disclosures / Publication

Publication and disclosure is an attempt to increase transparency of information to the public, sothe public can easily to access information about the project WINRIP. Some components ofpublication and disclosures are as follows: a) announcing the information about the project throughdissemination activities and provision the leaflets, b) installation of the project information boards,c) the provision of space / project information booth, d) providing important information that canonly be accessed by public with submitted an officially applications to the authorities, and e) theprovision of information in the website which can be accessed via the internet.

The Community Development Team has sent the CRO’s activities and Third Party Monitoring (TPM)activities and has been up load to the website of WINRIP.

Data and report documents of the Community Development activities on CommunityRepresentative Observers (CROs) for 20 packages (# 01, 02, 03, 04, 05, 06, 07, 08, 10, 11, 12, 13,14, 15, 16, 17, 19, 20, 21 and 05A#) has been uploaded on the website of WINRIP.

The Third Party Monitoring (TPM) for all of 19 packages was completed selected / appointed andall of the TPM’s data has been entry /uploaded to the website of WINRIP (# 01, 02, 03, 04, 05,06, 07, 08, 10, 11, 12, 13, 14, 15, 16, 17, 19, 20 and 21).

Review and being updating of the Project Management Manual (PMM).

During August 2018, the Community Development team relatively minor activity on public disclosure/ publication.

The Works Activities for Publication / Disclosure is shown in Appendix H4.

Page 82: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project8

6 - 8

6.3.6. Action Plan for Next Month (September 2018)

The Activities plan for future months, in order of priority are as follows:

Prepare of CRO selection for re-bid of package 05A in North Sumatera Province.

Accompanying of the CRO in following the Pre-Bid Meeting of package 05A in Balai BBPJN 2Medan, and site visit to the project field in North Sumatera Province

Selection of CRO for re-bid of package 21A (Lb. Alung – Kuraitaji) in West Sumatera Province.

Accompanying of the CRO in following the Pre-Bid Meeting of package 21A in Balai BPJN 3Padang, and site visit to the project field in Lubuk Alung – Kuraitaji) in West SumateraProvince

The third stage monitoring of TPM activity on observation the project field for packages thatwill be final taken over (FHO).

Preparing the CRO certificate, that they have carried out their duties as CRO is successfully

6.4 Road Safety Audit

6.4.1 Activities during This Month (August 2018)The Road Safety activities of this month are:

1. Road Safety Audit at PHO stage of Package #12 Kambang - Indrapura; 28 – 29 August 2018;2. Road Safety Audit at PHO Stage of Package #14 Painan - Kambang, 30 – 31 August 2018.

6.4.2 Current status of the project for technical field as of August 2018.

The Details of Program of Road Safety Audit as of the end of August 2018 are shown in the table onAppendix B.

6.5 Management Information System

In addition to collecting documents and reports of the WINRIP project in hard copy, we alsoarchive that documents and reports in the soft files. And we have created a file managerapplication to archive the files. We called it the WINRIP File Storage application.

Furthermore, in addition with the collection of the PHO documents and reports, thefollowing is status of the PHO document list of completed WINRIP packages that already becollected.

Page 83: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project9

6 - 9

NO. DOCUMENT TYPECOMPLETED OF WINRIP PACKAGE

01 02 03 04 06 07 08 11 17 19 201 Contract Document

2

ContractAmendment(including ChangeContract Original -CCO)

3 Contract Addendum

4Record of Pre-ConstructionMeeting (PCM)

5Commencement ofWork (COW) andSPMK

6Record ofProvisional HandOver (PHO)

7Taking OverCertificate

8Record of FinalQuantity

9 Job Mix Design

10 Job Mix Formula

11 MC and IPC

12Contract Drawing,As Build Drawing

13DocumentationPhoto

14ContractorMaintenance

15 Backup Quality

16 Strip Map

17 Request Work

18 RencanaKeselamatan danKesehatan KerjaKontrak (RK3K)

19 Price Adjustment(Eskalasi)

20 TechnicalJustification

21Other SupportingDocuments

All documents we have received are hard copy. Then we need to scan the document in order

Page 84: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project10

6 - 10

to save the soft copy file in PDF. And we will use the Canopile scanner tool to make thescanning process faster.

Our hard copy documents are stored in File Box Storage. While our soft copy files are savedin database of Document Management System (DMS) application.

Regarding to document update, the DMS application is still online well. And upload activitiesinto the DMS database continues as usual. Then number of files that have been uploaded toincrease rapidly. The data that has been uploaded to the DMS database until the end ofAugust 2018 are: 802 records of letters and 554 records of documents.

6.5.1 WINRIP File Storage

1) Folder Categorization

The file folder structure using the same system with the DMS applications. The root folders

are sorted based on the WINRIP components, namely:

ROOT 1ST FOLDER 2ND FOLDER 3RD FOLDER

C1_Civil_Works

C1.01_Krui-BihaC1.01.01_Pre-construction

C1.01.01.01_ACAPC1.01.01.02_EnvironmentC1.01.01.03_Social

C1.01.02_ProcurementC1.01.03_ConstructionC1.01.04_PHO

C1.01.05_FHOC1.02_Pd.Sawah-Sp.Empat

C1.02.01_Pre-construction

C1.02.01.01_ACAPC1.02.01.02_EnvironmentC1.02.01.03_Social

C1.02.02_ProcurementC1.02.03_ConstructionC1.02.04_PHO

C1.02.05_FHO

C1.03_Manggopoh-

Page 85: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project11

6 - 11

ROOT 1ST FOLDER 2ND FOLDER 3RD FOLDERPd.Sawah

C1.03.01_Pre-construction

C1.03.01.01_ACAPC1.03.01.02_EnvironmentC1.03.01.03_Social

C1.03.02_ProcurementC1.03.03_ConstructionC1.03.04_PHO

C1.03.05_FHO

Etc…C2_Consulting_Services

C2.01_PMU

C2.01.01_Letter

C2.01.02_Contract

C2.01.03_Report

C2.02_CTC

C2.02.01_Letter

C2.02.02_Contract

C2.02.03_Report

C2.03_DSC

C2.03.01_Letter

C2.03.02_Contract

C2.03.03_ReportC3_Technical_Assistant

C3.01_Slope_Protection

C3.01.01_Letter

C3.01.02_Contract

C3.01.03_Report

2) File Manager

We use the Explorer platform as a file manager to display data files. Explorer interface is

very similar to Windows Explorer on the Windows operating system, then users are familiar

and easy to use this application.

Page 86: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project12

6 - 12

6.5.2 File Box Storage

1) Document Categorization

The folder structure using the same system with the DMS applications. The root folders are

sorted based on the WINRIP components, namely:

COMPONENT NO. PACKAGE CODE

Component 1: Civil Works C1

1 Package 01 Krui – Biha C1.01

2 Package 02 Padang Sawah – Sp.Empat C1.02

3 Package 03 Manggopoh – PadangSawah C1.03

4 Package 04 Ipuh – Bantal C1.04

5 Package 05 Simpang Rampa – Poriaha C1.05

6 Package 06 Pasar Pedati – Kerkap C1.06

7 Package 07 Indrapura – Tapan C1.07

8 Package 08 Bts.Kota Pariaman –Manggopoh C1.08

9 Package 11 Bantal – Mukomuko C1.11

10 Package 12 Kambang – Indrapura C1.12

11 Package 13 Sp Rukis – Tj Kemuning C1.13

12 Package 14 Painan – Kambang C1.14

13 Package 15 Sibolga – Batas Tapsel C1.15

14 Package 16 Seblat – Ipuh C1.16

15 Package 17 Sp.Gng Kemala – PugungTampak C1.17

16 Package 19 Lais – Bintunan C1.19

17 Package 20 Lubuk Alung – Sicincin C1.20

18 Package 21 Lubuk Alung – Kuraitaji C1.21Component 2: ConsultingServices C2

1 PMU C2.01

Page 87: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project13

6 - 13

COMPONENT NO. PACKAGE CODE

2 CTC C2.02

3 DSC C2.03Componet 3: TechnicalAssistant

1 Slope Protection C3.01

2) Box File Cabinet

All report documents are stored in boxes, then placed on an iron shelf for easy use later.

Each box is given a note of contents for makes it easier to find documents.

6.5.3 DMS Statistic

Today the DMS application already stored many file of Letters and Documents. And the next

days will be more files are stored in the DMS database. At the end, it is expected to store all

of files that related with WINRIP project.

Below is the number of Letter files that have been stored in DMS database, updates until the

end of August 2018. This Letter statistics have sorted by "Package".

Page 88: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project14

6 - 14

0

10

20

30

40

50

60

70

P1 K

rui -

Bih

a

P2 P

adan

g Sa

wah

- Sp

Em

pat

P3 M

angg

opoh

- Pa

dang

Saw

ah

P4 Ip

uh -

Bant

al

P5 S

p Ra

mpa

- Po

riaha

P6 P

asar

Ped

ati -

Ker

kap

P7 In

drap

ura

- Tap

an

P8 B

ts K

ota

Paria

man

- M

angg

opoh

P9 R

anta

u Ti

jang

- Ko

ta A

gung

P10

Sp E

mpa

t - S

p Ai

r Bal

am

P11

Bant

al -

Muk

omuk

o

P12

Kam

bang

- In

drap

ura

P13

Sp R

ukis

- Tj K

emun

ing

P14

Pain

an -

Kam

bang

P15

Sibo

lga

- Bat

as T

apse

l

P16

Sebl

at -

Ipuh

P17

Sp G

n Ke

mal

a - P

g Ta

mpa

k

P18

Muk

omuk

o - B

ts S

umba

r

P19

Lais

- Bin

tuna

n

P20

Lubu

k Al

ung

- Sici

ncin

P21

Lubu

k Al

ung

- Kur

aita

ji

WIN

RIP

3628

61

25

15 1711

70

6

1612 12

6 8 5 40

14

2 2

66

Package

Letter StatisticSorted by Package

And here are the number of Document files that have been stored in DMS database, updates

until the end of August 2018. This Document statistics have sorted by "Document Type".

0

10

20

30

40

50

60

70

7

38

0

66

33

15 13

6 8

18

10

28

0

8

Document StatisticSorted by Document Type

Document Type

Page 89: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project15

6 - 15

6.6 Quality AssuranceIn the month August, 2018 the Quality Assurance Engineer/ IQA.1 has been visited twice topackages WINRIP, as:

-. Site visit to package 14 (Painan – Kambang) and package 12 (Kambang – Indrapura),Padang West Sumatera Province from August 23 to August 25, 2018 and

-. Site visit to package 11 (Bantal – Mukomuko), Padang West Sumatera Province, fromAugust 27 to September 01, 2018.

The activity of Quality Assurance Engineer/ IQA .1 on July 2018 place see in appendix D.

Appendix D shows the activities of the Quality Assurance Engineer during this period.

6.7 Project Risks and Mitigation Measures

6.7.1 Risks Related to Delays

Since the detailed engineering design (DED) is under responsibility of the Design andSupervision Consultant (DSC), delay on DSC establishment affected the procurement ofAWP-2 and AWP-3 sub-projects. The DED of several subprojects of WP-2 and WP-3 wereprepared and completed by respective P2JN. The CTC has then been instructed by DGH toreview the DEDs of seven packages completed by the P2JNs (package 5, 6, 11, 13, 15, 17 and19).

6.7.2 Financial Risks

The following factors will be monitored during implementation of the loan project. Loan Amount Actual Tender Prices Price Adjustments Contract Amendments (Additive or Deductive Variations) Currency Fluctuation Current Estimated Situation

No risk was detected until preparation of this report, however CTC prepared revised costestimates in anticipation of future cost claims to cover contract price escalations andvariation orders. A revised factor from 10% has been reduced to 5% for both additional costcomponents is applied on the original cost.

6.7.3 Risks Related to Quality

The quality of work is inherently tied to the competence of the Contractors and the diligenceof the Supervision Teams. The competence of contractors shall be considered at the time ofbid evaluation and prior to the award of any contract.

The quality of supervision however is influenced by the following factors:

Ensuring that supervision staff levels are fully manned with competent, honest,qualified and experienced personnel.

The provision of properly equipped laboratories with properly trained operators foreach package.

Package supervision comes under the responsibilities of the immediate supervision teams

Page 90: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project16

6 - 16

and the relevant DSC and the Quality Assurance Engineer from CTC.

6.8 Training to Support Project ImplementationNot performed for this month.

Page 91: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project7 - 17 - 1

7 CURRENT ISSUES AND FOLLOW-UP ACTIONS

PACKAGE CURRENT ISSUES FOLLOW-UP Actions

# 05 Simpang Rampa -Poriaha

The design of cut slope based on geotechnical investigation.

In order to finalize the design, site visit with WB geotechnicalexpert and concerned parties was made on 14 – 15, February2018.

The open tender for Package 5A, was conducted on 30. May2018.

WB, NOL regarding Biding Evaluation Report and Re-tender wasissued on 29, June 2018

Bidding annocement for the re-tender was made on 30, August2018

# 06 Ps. Pedati - KerkapSplitzing program for land acquisition in province of Bengkuluis still not budgeted.

The PPK is trying to allocate the fund for splitzing program (FY 2018)

# 12 Kambang - IndrapuraCatch up the delayed progress The contractor proposed the Extension of Time for the completion

and The Engineer is reviewing the proposal.

# 13 Sp Rukis - Tj Kemuning

Design for traffic safety of the unsettled land acquisition The Design for traffic safety is under review by the World Bank (53locs)

Splitzing program for land acquisition in province of Bengkuluis still not budgeted.

The PPK is trying to allocate the fund for splitzing program (FY 2018)

# 15 Sibolga - Batas TapselSplitzing program for land acquisition in the province ofNorth Sumatra is still not budgeted.

The PPK is trying to allocate the fund for splitzing programs(FY 2018).

Design for traffic safety of the unsettled land acquisition The Design for traffic safety is under review by the Engineer (17 locs)

# 17 Sp.Gn. Kemala - Pg.Tampak

Splitzing program for land acquisition in the province ofLampung is still not budgeted.

The PPK is trying to allocate the fund for splitzing programs(FY 2018).

Page 92: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project7 - 27 - 2

PACKAGE CURRENT ISSUES FOLLOW-UP Actions

# 19 Bintunan - LaisSplitzing program for land acquisition in province of Bengkuluis still not budgeted.

The PPK is trying to allocate the fund for splitzing program (FY 2018)

# 21 Lubuk Alung –Kuraitaji

Catch-up the delayed progress. The Contractor has been failed for the Test Case I, II and TestCase III. Accordingly, PPK proposed the termination due to thecontractor’s default and the WB NOL was issued on 9, July 2018.

Tender documents, specification, design drawing, bill ofquantities is under review by the World bank.

Page 93: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project1

8 - 1

8 CORRESPONDENCESDuring the period the CTC received and issued letters. Lists of letters received and issued areshown in Appendix J.

Page 94: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

ANNEXES

Annex P-1 : Package No. 1

Annex P-2 : Package No. 2

Annex P-3 : Package No. 3

Annex P-4 : Package No. 4

Annex P-5 : Package No. 5

Annex P-6 : Package No. 6

Annex P-7 : Package No. 7

Annex P-8 : Package No. 8

Annex P-11: Package No.11

Annex P-12: Package No.12

Annex P-13: Package No.13

Annex P-14: Package No.14

Annex P-15: Package No.15

Annex P-16: Package No.16

Annex P-17: Package No.17

Annex P-19: Package No.19

Annex P-20: Package No.20

Annex P-21: Package No.21

Page 95: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

05-Jul-15 Status : 25-Agu-18Contract

BALAI Amount Time ellaps Remaining

Plan (incl VAT) days days Target Highest Avg The latest

Actual IDR million % % % % % % SIMPANG RAMPA - PORIAHA II 17-Mar-15 540 8-Mar-18 130.143 100,00 95,28 (4,72) Contract amount reduced 4.72 %PT. NUSA KONSTRUKSI ENJ Tbk. Medan 18-Jun-15 455 10-Apr-18 124.000 100,00 100,00 - Revised BOQSIBOLGA - Batas TAPSEL II 13-Jul-15 810 30-Jun-18 260.100 100,00 80,50 (19,50) Contract amount reduced 19.5 %

PT. PEMBANGUNAN PERUMAHAN Medan 20-Nov-15 144 209.394 100,00 100,00 - Revised BOQ

PADANG SAWAH-SIMPANG EMPAT III 6-Dec-13 730 19-Apr-16 247.572 100 100 -PT Jaya Konstruksi MP, Tbk Padang 6-Jan-14 105 14-Apr-16MANGGOPOH - PADANG SAWAH III 6-Dec-13 730 20-Mar-16 183.940 100 100 -PT Jaya Konstruksi MP, Tbk Padang 6-Jan-14 75 17-Mar-16BATAS KOTA PARIAMAN-MANGGOPOH III 28-Jan-16 720 31-Dec-17 378.042 100 100 -PT PP - STATIKA JO Padang 23-Mar-16 -71LUBUK ALUNG - SICINCIN III 1-Jun-16 540 28-Feb-18 113.818 100 100 -PT NINDYA KARYA Padang 1-Sep-16 6KURAI TAJI - LUBUK ALUNG III 1-Jun-16 540 28-Jun-18 126.301 100,00 55,79 (44,21) Contract is terminatedPT MULTI STRUCTURE Padang 1-Sep-16 126INDRAPURA-TAPAN III 26-Nov-15 630 28-Jan-18 129.700 100 100 -PT. ADHI KARYA Padang 10-Dec-15 151KAMBANG-INDERAPURA III 28-Jan-16 720 28-Jul-18 358.650 100,00 80,28 (19,72) 825 -28 19,72 13,59 3,21 3,33PT LANCARJAYA MA-CAHAYA TA,JO Padang 23-May-16 77 103,52% -3,52%PAINAN - KAMBANG III 1-Jun-16 630 27-Jul-18 214.327 100,00 81,02 (18,98) 753 -29 18,98 9,72 3,52 1,10KSO YASA - CONBLOC Padang 3-Aug-16 94 104,01% -4,01%

IPUH - BANTAL III 14-Nov-13 730 11-Apr-16 212.290 100 100 -PT WASKITA KARYA - PT DMT, JO Padang 13-Jan-14 90 31-May-16KERKAP - PASAR PEDATI III 27-Feb-15 450 28-Jan-17 118.444 100 100 -PT. WASKITA KARYA Tbk Padang 11-Mar-15 240 28-Jan-17BANTAL - MUKOMUKO III 18-Dec-14 720 26-May-17 263.656 100 100 -PT. HUTAMA KARYA - PT. DMT, JO Padang 23-Feb-15 104 BINTUNAN-LAIS III 27-Feb-15 300 30-Jun-16 44.419 100 100 -PT RODATEKNINDO PURAJAYA Padang 11-Mar-15 178 30-Jun-16SEBLAT - IPUH III 28-Oct-16 630 30-Jul-18 211.375 100,00 89,50 (10,50) 656 -26 10,50 13,74 4,47 0,01PT YASA - MULTI STRUCTURE, JO Padang 8-Nov-16 - 104,13% -4,13%SIMPANG RUKIS-TANJUNG KEMUNING III 18-Dec-14 720 15-May-18 305.886 100 100 -PT. WASKITA KARYA Padang 22-Jul-15 309

BIHA - KRUI V 25-Nov-13 640 10-Jan-16 154.073 100 100 -PT Jaya Konstruksi MP, Tbk Palembang 8-Jan-14 93 20-Jan-16Sp.Gn KEMALA-PUGUNG TAMPAK V 17-Nov-14 720 27-Dec-17 211.712 100 100 -PT Jaya Konstruksi MP, Tbk Palembang 4-Sep-15 126

CONTRACTSIGN DATE

COW

CIVIL WORKS PROGRESSWESTERN INDONESIA ROAD IMPROVEMENT PROJECT (WINRIP)

Package No. & Name PROGRESS ACHIEVEMENTTime forCompletion TOC/ PHO

Time for Completion

Actual Dev

Physical Progress (%)

SchTime

extension /contraction

17

11

07

16

14

01

13

04

06

19

12

20

21

02

03

Contractor

08

05

15

ESR CTC 25 Aug 2018_1AF1E91C.xlsx

Page 96: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

PlanActual Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Mei Jun Jul Aug

LUBUK ALUNG - KURAI TAJI III 1-Jun-16 540 28-Jun-18 10,13 2,28 5,59 1,16 12,50 4,42 1,20 1,71 0,86 2,36 2,17 1,54 1,19 2,06 1,31 1,51 Terminate

PT MULTI STRUCTURE Padang 1-Sep-16 126

KAMBANG-INDERAPURA III 28-Jan-16 720 28-Jul-18 0,01 0,96 0,94 1,42 2,37 2,21 1,46 2,29 1,85 3,35 2,25 2,85 4,04 11,19 8,43 13,59 9,04 1,19 3,48 3,33PT LMA - CTA, JO Padang 23-May-16 77 Decline

PAINAN - KAMBANG III 1-Jun-16 630 27-Jul-18 2,02 3,31 6,37 3,54 9,72 3,99 3,99 9,16 6,14 3,57 3,57 3,32 3,15 3,11 6,44 2,55 0,86 0,12 0,00 1,10KSO YASA - CONBLOC Padang 3-Aug-16 94 Decline

SEBLAT - IPUH III 28-Oct-16 630 30-Jul-18 0,15 0,63 1,13 2,73 3,78 3,43 5,46 6,19 0,18 13,74 8,87 5,53 1,52 8,88 7,99 6,00 6,17 2,25 4,88 0,01PT YASA - MULTI STR, JO Padang 8-Nov-16 - Decline

CIVIL WORKS PROGRESS per MONTH(Ongoing Construction only)

WESTERN INDONESIA ROAD IMPROVEMENT PROJECT (WINRIP)

TOC/PHOPackage No. & Name

2017 2018Contractor

21

16

14

12

COW ExtensionBALAI

CONTRACTSIGN DATE

Time forCompletion PROGRESS per MONTH (%)

C:\Users\Tediero Pratama\AppData\Local\Temp\ESR CTC 25 Aug 2018_1AF1E91C.xlsx % Per MONTH

Page 97: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

05-Jul-15 Status tanggal : 25-Agu-18Re Target Time for 25-Agu-18

BALAI Time ellaps Remaining maining Progress completion Est

Plan days days Target Highest Avg Thelatest progress per required Completion

Actual % % % % % % month month date

KURAI TAJI - LUBUK ALUNG III 1-Jun-16 540 28-Jun-18 100,00 55,79 (44,21) 44% Contract is terminatedPT MULTI STRUCTURE Padang 1-Sep-16 126

KAMBANG-INDERAPURA III 28-Jan-16 720 28-Jul-18 100,00 80,28 (19,72) 825 -28 19,72 13,59 3,21 3,33 20% 12%PT LMA - CTA,JO Padang 23-May-16 77 103,52% -3,52%

PAINAN - KAMBANG III 1-Jun-16 630 27-Jul-18 100,00 81,02 (18,98) 753 -29 18,98 9,72 3,52 1,10 19% 7%KSO YASA - CONBLOC Padang 3-Aug-16 94 104,01% -4,01%

SEBLAT - IPUH III 28-Oct-16 630 30-Jul-18 100,00 89,50 (10,50) 656 -26 10,50 13,74 4,47 0,01 11% 7%PT YASA - MULTI STR, JO Padang 8-Nov-16 - 104,13% -4,13%

to be estimated from remainingquanity of major works

to be estimated from remainingquanity of major works

to be estimated from remainingquanity of major works16

Actual Dev

12

Contractor COW

21

14

Timeextension /contraction

Sch

ESTIMATED COMPLETION DATES OF ONGOING PAKAGESWESTERN INDONESIA ROAD IMPROVEMENT PROJECT (WINRIP)

Package No. & Name CONTRACTSIGN DATE

Time forCompletion TOC/ PHO Physical Progress (%) Time for Complation PROGRESS ACHIEVEMENT

Page 98: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

ANNEX P-1

MONTH :

Package No. Time Elapsed (Days)

Name Time Elapsed (%)

Project Manager Scheduled Progress (%) 100,00 Contractor Actual Overall Progress (%) 100,00 Supervision Consultant Balance (%)Contract Sign Progress This Month (%) Commencement Date Time for Complation (Days) 733 Take Over Date Status date Contract Amount Rp. Accumulative Rp. 100% Contract Amount Add-1 (+ VAT) Rp. Contract Amount Add-5 (+ VAT) Rp.Price Adjustment Rp.

Comp Add.2 Accum Actual Accum AccumTotal Total Last this to this Sch to

% % Month Month Month thisMonth

I G e n e r a l 8,25 7,22 7,54 7,54 7,54II D r a i n a g e 34,19 23,78 25,35 25,35 25,35III Earthworks 3,95 6,56 4,65 4,65 4,65

IV Pavement Widening &Shoulders 1,47 0,94 1,02 1,02 1,02

V Granular Pavement 9,22 7,04 7,49 7,49 7,49VI Asphalt Pavement 40,14 46,76 41,07 41,07 41,07VII S t r u c t u r e s 1,09 5,36 6,41 6,41 6,41

VIII Reinstatement & MinorWorks 1,20 1,91 6,05 6,05 6,05

IX Day Work 0,14 0,12 0,09 0,09 0,09

X Routine MaintenanceWorks 0,36 0,32 0,33 0,33 0,33

TOTAL 100,00 100,00 100,0 - 100,0 100,0Note :

1. 100% completed on January 20162. Taking-Over Certificate issued on January 20, 20163. Defects Liability Periode until January 19, 2018

2016Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 250,22 0,87 1,69 5,62 11,11 18,06 24,50 31,58 38,99 46,36 52,53 60,68 67,46

31,90 35,31 40,53 47,72 56,69 65,59 75,18 84,21 94,42 100,0088,43 91,76 96,08 100,00

0,10 0,58 0,79 1,59 2,93 3,71 4,79 5,98 8,60 11,28 12,62 16,08 18,71 21,04 25,88 32,67 37,50 42,27 45,05 55,51 65,00 70,08 76,56 91,02 100,00(0,12) (0,29) (0,90) (4,03) (8,18) (14,35) (19,71) (25,60) (30,39) (35,08) (39,91) (44,60) (48,75) (14,27) (14,65) (15,06) (19,18) (23,31) (30,13) (28,70) (29,43) (18,34) (15,19) (5,06) -

0,48 0,21 0,80 1,34 0,78 1,08 1,19 2,62 2,68 1,34 3,46 2,63 2,33

140.255.020.000

Actual Progress (%) Balance (%)

Div Description

The month of time for complation

Rivised Progress Schedul Add.1 (%) Original Progress Schedul (%)

Month

Rivised Progress Schedul Add.2 (%)

25-Agu-18

PHYSICAL PROGRESS MONITORING TABLE2014 Year

20-Jan-16

PHYSICAL WORK PROGRESS BY CATEGORY

134.909.211.000154.073.015.000

2015

The cracked pavement surface has been fixed. WB request that pavement investigation to be done.The result of the investigation as a reference BBPJN-VPalembang to conduct road maintenance.

PT JAYA KONSTRUKSI MP, Tbk

EXECUTIVE SUMMARY REPORTAgu-18

PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS

MAJOR PROBLEMS ACTION TO BE TAKEN01

TIM

E August 25, 2018

BIHA - KRUI

RENARDET S.A JV

Joko Wisargo, ST, MT

AMOU

NT

08-Jan-1425-Nov-13

DISBURSEMENT (Incl VAT)

140.255.020.000

0

10

20

30

40

50

60

70

80

90

100

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

PHYS

ICAL

PRO

GRES

(%)

THE MONTH OF TIME FOR COMPLATION

PROGRESS SCHEDULEPACKAGE # 01

Original

1st Revised Shc

2nd Revised Sch

ACTUAL

ESR CTC 25 Aug 2018_1AF1E91C.xlsx P-1

Page 99: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

ANNEX P-2

MONTH :

Package No. Time Elapsed (Days) Name Time Elapsed (%) Project Manager Scheduled Progress (%) 100,00 Contractor PT JAYA KONSTRUKSI MP, Tbk Actual Overall Progress (%) 100,00 Supervision Consultant Balance (%)Contract Sign Progress This Month (%) Commencement Date Time for Complation (Days) 730 Time for Complation (Days) 835 Status date Take Over Date Accumulative Rp. 100% Original Contract Amount Rp. *) Include advance payment Contract Amount + VO + Price Adj Rp.

Comp Accum Actual Accum AccumTotal Last this to this Sch to

% % Month Month Month thisMonth

I G e n e r a l 10,46 3,378 3,38 3,38 3,38II D r a i n a g e 3,53 3,244 3,24 3,24 3,24III Earthworks 4,44 4,691 4,69 4,69 4,69

IV Pavement Widening &Shoulders 2,26 1,948 1,95 1,95 1,95

V Granular Pavement 10,49 10,944 10,94 10,94 10,94VI Asphalt Pavement 52,09 57,028 57,03 57,03 57,03VII S t r u c t u r e s 14,35 16,115 16,12 16,12 16,12

VIII Reinstatement & MinorWorks 1,65 2,002 2,00 2,00 2,00

IX Day Work 0,12 0,108 0,11 0,11 0,11

X Routine MaintenanceWorks 0,62 0,541 0,54 0,54 0,54

TOTAL 100,00 100,00 100,00 - 100,00 100,00Note :

Year Month Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr

2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 Original Progress Schedul (%) 0,45 0,90 2,20 3,45 7,17 13,58 17,48 20,63 27,88 33,56 38,81 44,72 50,52 56,13 62,58 67,95 73,65 79,35 1st Revised Progress Schedul (%) 66,92 71,10 81,03 87,07 91,35 95,62 100,00 2nd Revised Progress Schedul (%) 92,53 95,62 96,75 97,25 98,21 100,00Actual - 0,13 1,02 2,19 4,11 5,96 9,69 13,85 22,55 25,61 31,45 33,73 40,41 44,25 49,98 55,715 58,61 58,35 63,76 71,36 77,80 83,27 92,53 93,20 92,85 95,73 96,83 100,00Balance (0,45) (0,77) (1,17) (1,26) (3,07) (7,62) (7,80) (6,78) (5,33) (7,95) (7,36) (10,99) (10,11) (11,88) (12,59) (12,23) (15,04) (8,57) (7,35) (9,67) (9,27) (8,08) (3,09) (2,41) (3,90) (1,52) (1,37)

0,89 1,17 1,91 1,86 3,72 4,17 8,69 3,07 5,84 2,28 6,68 3,84 38,29

1. 100% completed April 14, 20162. Taking-Over Certificate issued on April 14, 20163. Defects Liability Periode until April 13, 2018

197.936.699.000

Amandm04

(i) Found some cracks on the surface of the pavement.(ii) FHO is temporarily suspended until crack is know cause and repair isdone.

DSC is conducting pavement investigation planned for completionin Oct 2018.

ISMAN, ST

AMOU

NT

RENARDET S.A JV06-Dec-1306-Jan-14

August 25, 2018PADANG SAWAH-SIMPANG EMPAT02

TIM

E

MAJOR PROBLEMS ACTION TO BE TAKEN

EXECUTIVE SUMMARY REPORT

PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS

Agu-18

The month of time for complation

DISBURSEMENT (Incl VAT)25-Agu-18

247.572.130.000

PHYSICAL WORK PROGRESS BY CATEGORY

Div Description

PHYSICAL PROGRESS MONITORING TABLE2014 2015 2016

247.572.130.000

14-Apr-16

0

10

20

30

40

50

60

70

80

90

100

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28

PHYS

ICAL

PRO

GRES

(%)

THE MONTH OF TIME FOR COMPLATION

PROGRESS SCHEDULEPACKAGE # 02

ORIGINAL

1st Revised Sch

2nd Revised Sch

ACTUAL

ESR CTC 25 Aug 2018_1AF1E91C.xlsx P-2

Page 100: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

ANNEX-P3

MONTH :

Package No. Time Elapsed (Days)

Name Time Elapsed (%) Project Manager Scheduled Progress (%) 100,00 Contractor Actual Overall Progress (%) 100,00 Supervision Consultant Balance (%)Contract Sign Progress This Month (%) Commencement Date Time for Complation (Days) 730 Time for Complation (Days) 805 Status date Take Over Date Accumulative Rp. 100,0% Original Contract Amount Rp. *) Include advance payment Contract Amount + VO + Price Adj Rp.

Comp Revised Accum Actual Accum AccumTotal Total Last this to this Sch to

% % Month Month Month thisMonth

I G e n e r a l 10,21 10,21 2,39 2,39 2,39II D r a i n a g e 13,17 13,17 10,09 10,09 10,09III Earthworks 3,04 3,04 6,99 6,99 6,99

IV Pavement Widening &Shoulders

2,45 2,45 1,92 1,92 1,92

V Granular Pavement 11,27 11,27 11,25 11,25 11,25VI Asphalt Pavement 55,81 55,81 59,72 59,72 59,72VII S t r u c t u r e s 0,80 0,80 5,28 5,28 5,28

VIII Reinstatement &Minor Works

2,27 2,27 1,02 1,02 1,02

IX Day Work 0,22 0,22 0,69 0,69 0,69

X Routine MaintenanceWorks

0,76 0,76 0,65 0,65 0,65

TOTAL 100 100 100,0 - 100 100Note :

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 270,26 1,00 1,67 2,45 4,78 7,45 10,70 14,27 21,53 30,10 36,95 44,01 51,62 58,67 65,63 73,03 79,97 87,04

70,14 74,54 82,69 89,96 95,17 97,89 100,0093,78 98,11 99,31 100,00

0,24 0,48 2,07 2,43 2,87 5,45 5,70 7,01 12,43 14,45 19,30 24,38 29,11 30,11 32,97 39,72 43,28 43,98 48,56 54,37 65,63 85,01 91,15 96,30 98,38 99,13 100,00(0,02) (0,52) 0,40 (0,02) (1,91) (2,00) (5,00) (7,26) (9,10) (15,65) (17,65) (19,63) (22,51) (28,56) (32,66) (33,31) (36,69) (26,16) (25,98) (28,32) (24,33) (10,16) (6,74) 2,52 0,27 (0,18) -

0,24 1,59 0,36 0,44 2,58 0,25 1,31 5,42 2,02 4,85 5,08 4,73 1,00 Balance (%)

2016

Rivised Progress Schedul (%)

183.452.685.000

Rivised Progress Schedul (%)

Actual Progress (%)

PHYSICAL PROGRESS MONITORING TABLE Year 2014 Month The month of time for complation

2015

PHYSICAL WORK PROGRESS BY CATEGORY

Original Progress Schedul (%)

Div Description

183.452.685.000143.688.963.000

1. 100% completed on March 17, 20162. Taking-Over Certificate issued on March 17, 2016 3.Defects Liability Periode until March 16, 2018

DISBURSEMENT (Incl VAT)

17-Mar-1625-Agu-18

17-Mar-18

(i) Found some cracks on the surface of the pavement.(ii) FHO is temporarily suspended until crack is know cause and repair isdone.

DSC is conducting pavement investigation planned forcompletion in Oct 2018.

Opukenigara, ST

AMOU

NT

RENARDET S.A JV06-Dec-13

PT JAYA KONSTRUKSI MP, Tbk

06-Jan-14

EXECUTIVE SUMMARY REPORT

PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS

Agu-18

03

TIM

E August 25, 2018MANGGOPOH - PADANG SAWAH MAJOR PROBLEMS ACTION TO BE TAKEN

0

10

20

30

40

50

60

70

80

90

100

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27

PHYS

ICAL

PRO

GRES

(%)

THE MONTH OF TIME FOR COMPLATION

PROGRESS SCHEDULEPACKAGE # 03

ORIGINAL

1st Revised Sch

2nd Revised Sch

ACTUAL

ESR CTC 25 Aug 2018_1AF1E91C.xlsx P-3

Page 101: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

ANNEX P-4

MONTH :

Package No. Time Elapsed (Days)

Name Time Elapsed (%) Project Manager Scheduled Progress (%) 100,00 Contractor PT WASKITA KARYA - PT DAYA JO Actual Overall Progress (%) 100,00 Supervision Consultant Balance (%)Contract Sign Progress This Month (%) Commencement Date Time for Complation (Days) 730 Time for Complation (Days) 820 Status date Take Over Date Accumulative Rp. 100,0% Contract Amount Rp. *) Include advance payment

Contract Amount Add-1 Rp.Price Adjustment Rp.

Comp Accum Actual Accum AccumTotal Last this to this Sch to

% Month Month Month thisMonth

I G e n e r a l 7,59 5,99 5,99 5,99II D r a i n a g e 12,26 8,18 8,18 8,18III Earthworks 3,58 3,06 3,06 3,06

IV Pavement Widening &Shoulders 3,39 3,05 3,05 3,05

V Granular Pavement 18,07 16,82 16,82 16,82VI Asphalt Pavement 49,27 47,02 47,02 47,02VII S t r u c t u r e s 2,55 4,82 4,82 4,82

VIII Reinstatement & MinorWorks 2,95 10,88 10,88 10,88

IX Day Work 0,14 0,00 0,00 0,00

X Routine MaintenanceWorks 0,20 0,18 0,18 0,18

TOTAL 100 100,0 - 100,00 100,00Note :

1. 100% completed on March 31, 20162. Taking-Over Certificate issued on March 31, 20163. Defects Liability Periode until March 30, 2018

Year Month Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr The month of time for complation 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 Schedl Progress Original (%) 0,11 0,32 0,75 1,14 6,57 10,29 12,85 15,81 20,08 24,22 32,76 40,88 47,93 55,61 63,451st Revised Schedule (%) 28,57 37,28 48,18 56,89 64,18 73,78 84,47 91,89 98,53 2nd Revised Schedule (%) 61,23 62,14 76,26 86,77 96,29 100,0 Actual Progress (%) - 0,18 0,40 0,53 0,56 0,78 0,87 1,45 3,73 5,35 8,10 9,35 13,79 21,76 27,67 35,43 39,36 42,14 44,24 46,28 50,09 53,17 61,23 70,32 78,69 84,64 91,62 94,53 Balance (%) (0,11) (0,14) (0,35) (0,61) (6,01) (9,51) (11,98) (14,36) (16,35) (18,88) (24,66) (31,53) (34,14) (33,85) (0,91) (1,86) (8,81) (14,75) (19,95) (27,51) (34,38) (38,72) (37,30) 8,18 2,43 (2,13) (4,67) (5,47)

0,22 0,13 0,03 0,22 0,09 0,58 2,27 1,62 2,76 1,25 4,44 7,97

Fathoni Ikhsan, ST

04MAJOR PROBLEMS ACTION TO BE TAKENTI

ME August 25, 2018

IPUH - BANTAL

EXECUTIVE SUMMARY REPORTAgu-18

PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS

13-Jan-1414-Nov-13

2015

RENARDET S.A JV

AMOU

NT

(i) Found some cracks on the surface of the pavement.(ii) FHO is temporarily suspended until crack is know cause and repair isdone.

DSC is conducting pavement investigation planned for completion in Oct2018.

20162014PHYSICAL PROGRESS MONITORING TABLE

31-Mei-16

Div Description

194.902.179.000212.290.705.872

DISBURSEMENT (Incl VAT)

186.936.750.000212.290.705.872

PHYSICAL WORK PROGRESS BY CATEGORY

25-Agu-1831-Mei-18

0

10

20

30

40

50

60

70

80

90

100

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28

PHYS

ICAL

PRO

GRES

(%)

THE MONTH OF TIME FOR COMPLATION

PROGRESS SCHEDULEPACKAGE # 04

ORIGINAL

1st Revised Sch

2nd Revised Sch

ACTUAL

ESR CTC 25 Aug 2018_1AF1E91C.xlsx P-4

Page 102: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

ANNEX P-06

MONTH :

Package No. Time Elapsed (Days) Name Time Elapsed (%) Project Manager Yahya, ST Scheduled Progress (%) 100,00 Contractor PT. WASKITA KARYA Tbk Actual Overall Progress (%) 100,00 Supervision Consultant RENARDET S.A JV PT. CIPTA STRADA Balance (%) Contract Sign Progress This Month (%) Commencement Date Time for Complation (Days) 450 240 Take Over Date Status date Contract Amount (Incl VAT) Rp. Accumulative Rp. 100,00%Price Adjustment Rp.

Add Accum Actual Accum AccumLast this to this Sch to this

% Month Month Month MonthI G e n e r a l 1,69 1,69 1,69 1,69II D r a i n a g e 1,61 1,61 1,61 1,61III Earthworks 8,58 8,58 8,58 8,58

IV Pavement Widening &Shoulders 2,93 2,93 2,93 2,93

V Granular Pavement 16,48 16,48 16,48 16,48VI Asphalt Pavement 60,39 60,39 60,39 60,39VII S t r u c t u r e s 5,63 5,63 5,63 5,63

VIII Reinstatement & MinorWorks 2,15 2,15 2,15 2,15

IX Day Work - - - -

X Routine MaintenanceWorks 0,54 0,54 0,54 0,54

TOTAL 100 100,0 - 100,00 100,00Note :

1. 100% completed on January 28, 20172. Taking-Over Certificate issued on January 28, 2073. Defects Liability Periode until January 28, 2019

Year 2017 Month March Apr May June July August Sep Oct Nop Dec Jan Feb March Apr May June July August Sep Oct Nop Dec Jan The month of time for complation 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 Schedl Progress Original (%) 0,17 0,59 1,28 3,09 4,38 8,17 14,27 25,82 38,49 49,93 62,08 75,00 85,36 95,41 100,001st Revised schedul 56,000 60,47 74,94 100,002nd Revised schedul 58,86 70,27 79,80 88,09 96,07 100,0 Actual Progress (%) 0,07 0,33 0,76 1,04 1,18 2,27 10,03 15,13 18,75 20,54 23,04 25,89 27,55 32,701 36,020 39,34 45,15 56,31 64,44 74,87 87,78 91,23 100,0 Balance (%) -0,15 -0,26 -0,53 -2,04 -3,20 -5,90 -4,24 -10,69 -19,74 -29,38 -39,04 -49,11 -57,81 -62,71 -63,98 -21,12 -29,79 -2,56 -5,83 -4,93 -0,31 -4,84 0,00

0,42 0,29 0,13 1,10 7,76 5,09 3,62 1,79 2,49 2,85 1,67 5,15

PHYSICAL PROGRESS MONITORING TABLE2015

118.444.155.000

PHYSICAL WORK PROGRESS BY CATEGORY

Div Description

2016

118.444.156.000

EXECUTIVE SUMMARY REPORTAgu-18

PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS6

TIM

E August 25, 2018KERKAP - PASAR PEDATI MAJOR PROBLEMS

25-Agu-1828-Jan-17DISBURSEMENT (Incl VAT)

ACTION TO BE TAKEN

AMOU

NT

27-Feb-1511-Mar-15

Calendar Days +

(i) Found some cracks on the surface of the pavement.(ii) FHO is temporarily suspended until crack is knowcause and repair is done.

DSC is conducting pavement investigation planned for completion in Oct 2018.

28-Jan-19

0

10

20

30

40

50

60

70

80

90

100

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

PHYS

ICAL

PRO

GRES

(%)

THE MONTH OF TIME FOR COMPLATION

PROGRESS SCHEDULEPACKAGE # 06

Original Sch

1st Revised Sch

2nd Revised Sch

Actual

ESR CTC 25 Aug 2018_1AF1E91C.xlsx P-06

Page 103: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

ANNEX P-07

MONTH :

Package No. Time Elapsed (Days) Name Time Elapsed (%) Sub Project Manager / PPK Scheduled Progress (%) 100,00 Contractor PT ADHI KARYA Actual Overall Progress (%) 100,00 Supervision Consultant Balance (%)Contract Sign Progress This Month (%) Commencement Date Time for Complation (Days) 780 Take Over Date Status date Contract Amount (Incl VAT) Rp. Accumulative Rp. 100,0%Price Adjustment Rp.

Comp Accum Actual AccumTotal Last this to this

% % Month Month MonthI G e n e r a l 2,45 2,59 1,89 0,70 2,59 2,29II D r a i n a g e 21,84 19,36 12,26 7,10 19,36 12,80III Earthworks 5,38 7,49 7,29 0,20 7,49 7,29IV

Pavement Widening &Shoulders 1,09 0,72 0,37 0,35 0,72 0,42

V Granular Pavement 9,22 7,51 7,48 0,04 7,51 7,07VI Asphalt Pavement 51,16 51,55 52,20 (0,66) 51,55 52,20VII S t r u c t u r e s 6,08 7,87 14,69 (6,81) 7,87 14,69VIII

Reinstatement & MinorWorks 2,48 2,53 1,59 0,94 2,53 2,86

IX Day Work 0,09 0,18 0,18 - 0,18 0,18X

Routine MaintenanceWorks 0,20 0,20 0,19 0,01 0,20 0,20 TOTAL 100,0 100,00 98,14 1,86 100,00 100,00

Note :

Year 2015 Month Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Des Jan The month for complation 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 Original Progress Schedul (%) 0,16 0,31 0,59 0,67 1,24 1,92 3,90 5,63 8,72 16,79 24,44 32,37 43,74 50,84 62,90 72,65 80,61 87,11 94,03 98,20 100,0 100,0 100,0 100,0 1st Revised Progress Sch (%) 24,44 32,37 43,74 50,84 62,90 72,65 80,61 87,11 94,03 98,20 100,0 100,0 100,0 100,0 2nd Revised Progress Sch (%) 24,437 32,366 43,743 53,151 62,904 72,649 80,609 87,106 94,032 98,202 100,00 3rd Revised Progress Sch (%) 79,145 81,90 88,87 99,04 100,00 4th Revised Progress Sch (%) 90,36 100,00 5th Revised Progress Sch (%) 94,21 100,00 Actual Progress (%) 0,15 0,31 0,59 0,82 1,18 3,62 4,75 5,63 12,87 16,70 23,49 31,35 39,03 41,27 45,61 48,054 48,87 50,46 55,86 59,00 63,63 67,58 76,48 84,62 93,85 100,00 Balance (%) (0,01) - 0,00 0,15 (0,06) 1,70 0,85 0,00 4,15 (0,09) (0,95) (1,02) (4,71) (9,57) (17,29) (24,60) (31,74) (36,65) (38,17) (39,20) (18,26) (21,28) (22,56) (5,74) (6,15) 0,00Progress per month 0,31 0,28 0,23 0,36 2,44 1,14 0,88 7,24 3,83 6,79 7,86 7,68 2,24 4,34 2,44 0,82 1,59 5,41 3,14 4,63 3,95 8,90 8,14 9,23 6,15

0,59 0,23 0,36 2,44 1,14 0,88 7,24 3,83 6,79 7,86 7,68 2,24 37,65

EXECUTIVE SUMMARY REPORTAgu-18

PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS

Amandment

Accum Schto thisMonth

28-Jan-18 25-Agu-18

10-Des-15

Filino Kalani, ST

AMOU

NT

RENARDET S.A JV PT. SEECONS03-Dec-15

DISBURSEMENT (Incl VAT)

129.699.900.000

2017

August 25, 2018MAJOR PROBLEMS ACTION TO BE TAKEN

2016

7

TIM

E

INDRAPURA - TAPAN

129.699.900.000

PHYSICAL PROGRESS MONITORING TABLE

PHYSICAL WORK PROGRESS BY CATEGORY

Div Description

0

10

20

30

40

50

60

70

80

90

100

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

PHYS

ICAL

PRO

GRES

(%)

THE MONTH OF TIME FOR COMPLATION

PROGRESS SCHEDULEPACKAGE # 07

ORIGINAL SCH

1st REVISED SCH

2nd REVISED SCH

3rd REVISED SCH

4th REVISED SCH

5th REVISED SCH

ACTUAL PROGRESS

ESR CTC 25 Aug 2018_1AF1E91C.xlsx P-07

Page 104: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

ANNEX P-08

MONTH :

Package No. Time Elapsed (Days) Name Time Elapsed (%) Sub Project Manager / PPK Scheduled Progress (%) 100,00 Contractor PT. PP - STATIKA CONSORTIUM Actual Overall Progress (%) 100,00 Supervision Consultant Balance (%)

Contract Sign Progress This Month (%)

Commencement Date Time for Complation (Days) 649 Take Over Date Status date Contract Amount (Incl VAT) Rp. Accumulative Rp. 100,0%Price Adjustment Rp.

Comp Actual Accumto to

Total this this% Month Month Month

I G e n e r a l 1,50 0,25 0,00 0,25 0,25II D r a i n a g e 9,75 10,00 0,03 10,04 10,01III Earthworks 5,32 4,91 0,01 4,92 4,92IV Pavement Widening &

Shoulders 1,63 2,05 0,28 2,33 1,93V Granular Pavement 10,77 9,93 0,00 9,93 9,93VI Asphalt Pavement 59,20 56,42 1,02 57,44 57,44VII S t r u c t u r e s 7,62 9,88 0,489 10,37 10,37VIII Reinstatement & Minor

Works 3,43 2,52 1,206 3,73 3,82IX Day Work 0,05 0,00 0,000 0,00 0,00X Routine Maintenance

Works 0,19 0,19 0,002 0,19 0,20I.X.I Painting Bridge 0,54 0,59 0,025 0,61 0,61

TOTAL 100,0 96,75 3,07 100 100Note :

Year Month Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Jan Feb The month for complation 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Original Progress Schedul (%) 0,02 0,09 0,17 0,31 0,44 2,77 7,58 13,22 22,21 30,85 35,38 48,22 55,71 66,39 74,64 78,72 83,79 90,13 94,80 97,82 99,27 100,0 1st Revised Progress Schedul (%) 27,55 35,38 44,13 51,83 59,73 68,69 70,25 73,59 75,43 94,40 97,52 99,37 100,0 2nd Revised Progress Schedul (%) 79,0 82,61 87,54 94,64 100,0 Actual Progress (%) 0,27 1,12 2,37 3,59 6,21 9,69 18,79 28,40 32,15 37,93 47,48 57,22 65,01 68,99 74,73 79,93 84,86 82,62 88,05 96,75 100,0 Balance (%) 0,18 0,96 2,06 3,15 3,44 2,12 5,57 6,19 1,30 2,55 3,35 5,39 5,28 0,31 4,48 6,35 9,43 0,01 0,52 2,12 -Progress per month 0,00 0,27 0,85 1,25 1,22 2,62 3,48 9,10 9,61 3,75 5,78 9,55 9,75 7,79 3,98 5,74 5,20 4,93 (2,24) 5,43 8,70 3,25

0,94 1,25 1,22 2,62 3,48 9,10 9,61 3,75 5,78 9,55 9,75 7,79 58,80

378.042.000.000

EXECUTIVE SUMMARY REPORTAgu-18

PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS08

TIM

E August 25, 2018Bts Kota Pariaman - Manggopoh MAJOR PROBLEMS ACTION TO BE TAKEN

378.042.000.000

RENARDET S.A JV PT. SEECONS

28-Jan-16

23-Mar-16

Opukenigara, ST

AMOU

NT

DISBURSEMENT (Incl VAT)01-Jan-18 25-Agu-18

2018Dec

Div DescriptionAccum

LastAccumSch to

thisMonth

PHYSICAL PROGRESS MONITORING TABLE2016 2017

PHYSICAL WORK PROGRESS BY CATEGORY

355.500.000.000

0

10

20

30

40

50

60

70

80

90

100

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22

PHYS

ICAL

PRO

GRES

(%)

THE MONTH OF TIME FOR COMPLATION

PROGRESS SCHEDULEPACKAGE # 08

ORIGINAL SCH

1st REVISED SCH

2nd REVISED SCH

ACTUAL PROGRESS

Page 105: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

ANNEX P-11

MONTH :

Package No. Time Elapsed (Days) Name Time Elapsed (%) Project Manager Scheduled Progress (%) 100,00 Contractor PT. HUTAMA KARYA, Tbk JO PT. DMT Actual Overall Progress (%) 100,00 Supervision Consultant RENARDET S.A JV PT. CIPTA STRADA Balance (%) Contract Sign Progress This Month (%) Commencement Date Take Over Date Time for Complation (Days) 824 Calendar Days Status date Contract Amount (Incl VAT) Rp. Accumulative Rp. 100,0% Contract Amount Add-1 (+ VAT) Rp.Price Adjustment Rp.

Accum Actual Accum AccumLast this to this Sch to this

% Month Month Month MonthI G e n e r a l 0,85 0,87 - 0,87 0,87II D r a i n a g e 2,49 2,88 2,88 2,88III Earthworks 11,27 10,58 - 10,58 10,58

IV Pavement Widening &Shoulders

3,60 3,22 0,17 3,40 3,40

V Granular Pavement 14,41 14,21 - 14,21 14,21VI Asphalt Pavement 52,35 53,27 0,00 53,27 53,65VII S t r u c t u r e s 9,88 11,02 0,03 11,06 10,59

VIII Reinstatement & MinorWorks

4,87 2,90 0,56 3,46 3,55

IX Day Work - - - - -

X Routine MaintenanceWorks

0,28 0,28 0,28 0,28

TOTAL 100,00 99,23 0,77 100,0 100,0Note :

Year Month March Apr May June July August Sep Oct Nop Dec Jan Feb March Apr May June July August Sep Oct Nop Dec Jan Feb Mar Apr May The month of time for complation 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 Schedl Progress Original (%) 0,39 2,18 4,68 7,70 9,91 14,17 18,72 22,96

20,01 22,98 25,39 29,15 36,74 43,85 51,45 58,80 66,39 70,16 77,18 84,00 89,39 93,63 96,19 99,45 100,0075,54 92,39 95,86 98,98 100

Actual Progress (%) 1,477 5,59 6,59 9,13 10,00 11,28 15,09 17,23 23,22 24,82 26,84 33,04 38,87 44,59 51,81 56,74 58,88 65,03 71,00 74,78 84,85 86,28 87,49 89,78 96,37 99,23 100 Balance (%) 1,08 3,42 1,92 1,43 0,09 (2,89) (3,64) (2,78) 0,23 (0,56) (2,31) (3,70) (4,98) (6,86) (6,99) (9,65) (11,28) (12,15) (13,01) (14,61) (8,78) (9,91) (11,96) (2,61) 0,52 0,25 0,00Progress per month 4,12 1,00 2,54 0,87 1,28 3,80 2,15 5,99 1,61 2,02 6,20 5,83 5,71 7,22 4,93 2,14 6,15 5,97 3,79 10,07 1,43 1,21 2,28 6,60 2,86 0,77

1,00 2,54 0,87 1,28 3,80 2,15 5,99 1,61 2,02 6,20 5,83 5,71

Fathoni Ikhsan, ST

EXECUTIVE SUMMARY REPORTAgu-18

PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS11

TIM

E August 25, 2018BANTAL - MUKOMUKO MAJOR PROBLEMS ACTION TO BE TAKEN

Div Description

263.656.603.000

263.656.603.000

Amend-02

(i) Found some cracks on the surface of thepavement.(ii) FHO is temporarily suspended until crack isknow cause and repair is done.(iii) Road Maintenance within the DNP is notimplemented

25-Agu-18

23-Feb-15DISBURSEMENT (Incl VAT)26-May-17

18-Dec-14 AMOU

NT

DSC is conducting pavement investigation plannedfor completion in Oct 2018.

2 nd Rivised Progress Schedul (%)

2017

1 st Rivised Progress Schedul (%)

PHYSICAL PROGRESS MONITORING TABLE2015 2016

228.899.717.000262.611.303.000

PHYSICAL WORK PROGRESS BY CATEGORY

0

10

20

30

40

50

60

70

80

90

100

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27

PHYS

ICAL

PRO

GRES

(%)

THE MONTH OF TIME FOR COMPLATION

PROGRESS SCHEDULEPACKAGE # 11

Original Sch

1st Revised Sch

2nd Revised Sch

Actual

ESR CTC 25 Aug 2018_1AF1E91C.xlsx P-11

Page 106: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

ANNEX P-17

MONTH :

Package No. Time Elapsed (Days) Name PUGUNG TAMPAK-Sp.Gn KEMALA Time Elapsed (%) Project Manager Scheduled Progress (%) 100,00 Contractor PT. JAYA KONSTRUKSI MP, Tbk Actual Overall Progress (%) 100,00 Supervision Consultant Balance (%)Contract Sign Progress This Month (%) Commencement Date Time for Complation (Days) 846 Take Over Date Status date Contract Amount (Incl VAT) Rp. Accumulative Rp. 100% Revised Contract Amount (Incl VAT) Rp.

Comp Accum Actual Accum AccumTotal Last this to this Sch to this

% Month Month Month MonthI G e n e r a l 8,05 1,514 0,296 1,810 1,810II D r a i n a g e 12,92 9,04 0,300 9,34 9,34III Earthworks 16,93 16,55 1,169 17,72 17,72

IV Pavement Widening &Shoulders 7,36 7,04 0,953 7,99 7,99

V Granular Pavement 4,09 2,69 0,100 2,79 2,79VI Asphalt Pavement 42,82 46,43 (0,005) 46,42 46,42VII S t r u c t u r e s 1,98 5,04 2,038 7,08 7,08

VIII Reinstatement & MinorWorks 5,30 3,338 2,922 6,260 6,26

IX Day Work 0,23 0,08 0,172 0,25 0,25

X Routine MaintenanceWorks 0,34 0,30 0,037 0,34 0,34

TOTAL 100,0 92,02 7,98 100,00 100,00Note :

211.712.283.000,00 106,09

Year Month Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May June July August Sep Oct Nop Dec The month of time for complation 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 Schedl Progress Original (%) 0,18 0,70 1,18 1,51 2,39 3,80 6,10 10,09 14,15 18,21 21,04 26,32 33,01 39,79 46,73 54,12 61,80 69,15 75,00 80,05 85,25 90,26 95,19 100,0 1st Revised Progress Schedul (%) 50,59 55,87 62,09 68,69 75,33 79,35 85,57 91,8 100,0 2nd Revised Progress Sch Add-4 (%) 69,39 75,07 81,7 88,6 94,3 100,0 3rd Revised Progress Sch Add- (%) 69,39 75,07 81,7 88,6 94,3 94,3 100 Actual Progress (%) 0,921 1,13 1,42 3,05 3,45 4,11 6,16 9,54 13,81 16,99 17,41 20,33 28,34 33,32 38,86 41,34 49,01 53,30 61,37 66,06 72,73 77,53 73,41 78,69 84,78 87,52 92,02 100 Balance (%) 0,74 0,43 0,23 1,54 1,06 0,30 0,06 (0,55) (0,34) (1,23) (3,63) (5,99) (4,68) (6,47) (7,87) (12,78) (12,80) (2,57) (0,72) (2,63) (2,60) (1,82) (1,7) (3,05) (3,83) (6,81) (2,32)Progress per month 0,92 0,21 0,29 1,63 0,40 0,66 2,05 3,38 4,28 3,18 0,42 2,92 8,00 4,99 5,54 2,48 7,66 4,29 8,08 4,69 6,67 4,80 (4,12) 5,28 6,09 2,74 4,50 7,98

0,21 0,29 1,63 0,40 0,66 2,05 3,38 4,28 3,18 0,42 2,92 8,00 4,99

EXECUTIVE SUMMARY REPORTAgu-18

PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS17

TIM

E August 25, 2018MAJOR PROBLEMS ACTION TO BE TAKEN

Need to be observed and if excessive bleeding pavementsurface treatment should be done.

RENARDET S.A JV17-Nov-1404-Sep-15

DISBURSEMENT (Incl VAT)

AMOU

NT

Joko Wisargo, ST, MT

27-Des-17 25-Agu-18199.551.233.000 211.712.283.000,00

(i) There are many bleeding on pavement surface(ii) Road Maintenance within the DNP is notimplemented.

PHYSICAL PROGRESS MONITORING TABLE2015 2016 2017

PHYSICAL WORK PROGRESS BY CATEGORY

Div Description

211.712.283.000

0

10

20

30

40

50

60

70

80

90

100

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28

PHYS

ICAL

PRO

GRES

(%)

THE MONTH OF TIME FOR COMPLATION

PROGRESS SCHEDULEPACKAGE # 17

ORIGINAL SCH

1st REVISED SCH

2nd REVISED SCH

3rd REVISED SCH

ACTUAL PROGRESS

ESR CTC 25 Aug 2018_1AF1E91C.xlsx P-17

Page 107: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

ANNEX P-19

MONTH :

Package No. Time Elapsed (Days) Name Time Elapsed (%) Project Manager Yahya, ST Scheduled Progress (%) 100,0 Contractor Actual Overall Progress (%) 100,0 Supervision Consultant Balance (%) Contract Sign Progress This Month (%) Commencement Date Time for Complation (Days) 300 Calendar Days Final Time for Complation (Days) 477 Calendar Days Status date Take Over Date Accumulative Rp. 100% Contract Amount (Incl VAT) Rp. Contract Amount Add-1 (+ VAT) Rp.

Comp Accum Actual Accum AccumTotal Last this to this Sch to this

% Month Month Month MonthI G e n e r a l 0,43 0,32 0,32 0,32II D r a i n a g e 3,15 2,73 2,73 2,73III Earthworks 11,96 11,31 11,31 11,31

IV Pavement Widening &Shoulders 5,30 4,02 4,02 4,02

V Granular Pavement 10,69 8,82 8,82 8,82VI Asphalt Pavement 59,66 64,4 64,4 64,41VII S t r u c t u r e s 2,00 4,02 4,02 4,02

VIII Reinstatement & MinorWorks 6,79 4,35 4,35 4,35

IX Day Work

X Routine MaintenanceWorks 0,03 0,02 0,02 0,02

TOTAL 100,00 100,00 - 100 100,00Note :

1. 100% completed on 30 Jun 20162. Taking-Over Certificate issued on 30 Jun 20163. Defects Liability Periode until 29 Jun 2018

Year Month March April May June July Aug Sept Oct Nov Des Jan Feb March April May The month of time for complation 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Schedl Progress Original (%) 0,12 1,40 8,96 18,40 21,37 23,62 37,37 58,19 87,25 100,00

43,60 52,20 67,79 79,68 98,93 100,00 Actual Progress (%) 0,15 1,30 6,28 14,54 16,21 22,41 28,90 49,74 57,15 57,48 52,77 77,34 80,78 97,14 100,00 Balance (%) 0,03 -0,10 -2,68 -3,86 -5,16 -1,21 -8,47 -8,45 -30,10 13,88 0,57 9,55 1,10 -1,79 0,00

4,98 8,26 1,67 6,20 6,49 20,84 7,42 0,32 (4,71) 24,57 3,44 16,36

19

TIM

E August 25, 2018 BINTUNAN-LAIS MAJOR PROBLEMS ACTION TO BE TAKEN

EXECUTIVE SUMMARY REPORTAgu-18

PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS

44.419.760.000

Rivised Progress Schedul Add.1 (%)

2016PHYSICAL PROGRESS MONITORING TABLE

Div

2015

Description

PHYSICAL WORK PROGRESS BY CATEGORY

DSC is conducting pavement investigation planned forcompletion in Oct 2018.

25-Agu-1844.419.760.829

27-Feb-1511-Mar-15

RENARDET S.A JV

30-Jun-16

DISBURSEMENT (Incl VAT)

AMOU

NT PT RODATEKNINDO PURAJAYA

33.689.452.000

(i) Found some cracks on the surface of the pavement.(ii) FHO is temporarily suspended until crack is know causeand repair is done.

0

10

20

30

40

50

60

70

80

90

100

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

PHYS

ICAL

PRO

GRES

(%)

THE MONTH OF TIME FOR COMPLATION

PROGRESS SCHEDULEPACKAGE # 19

ORIGINAL

REVISED SCH

ACTUAL

ESR CTC 25 Aug 2018_1AF1E91C.xlsx P-19

Page 108: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

ANNEX P-20

MONTH :

Package No. Time Elapsed (Days) 723 Name Time Elapsed (%) 100,00% Project Manager Andi Mulya Rusli, ST, MT Scheduled Progress (%) 100,00 Contractor 'PT Nindya Karya (Persero) Actual Overall Progress (%) 100,00 Supervision Consultant RENARDET S.A JV PT.Yodya (Persero) Balance (%) Contract Sign Progress This Month (%) Commencement Date Time for Complation (Days) 547 Calendar Days Take Over Date Status date Contract Amount (Incl VAT) Rp. Accumulative Rp. 85,45%Price Adjustment Rp.

Comp Accum Actual Accum AccumTotal Last this to this Sch to this

% Month Month Month MonthI G e n e r a l 0,90 0,60 - 0,60 0,69II D r a i n a g e 32,44 27,92 - 27,92 27,92III Earthworks 6,64 4,75 - 4,75 3,74

IV Pavement Widening &Shoulders 3,78 1,56 - 1,56 1,51

V Granular Pavement 9,52 6,66 - 6,66 6,66VI Asphalt Pavement 42,49 42,28 2,74 45,02 45,02VII S t r u c t u r e s 1,83 5,63 2,28 7,91 9,28

VIII Reinstatement & MinorWorks 1,93 0,24 2,60 2,84 3,78

IX Day Work 0,04 - 0,10 0,10 0,09

X Routine MaintenanceWorks 0,43 0,24 0,18 0,42 0,41

TOTAL 100,00 89,88 7,89 97,77 99,12Note :

Year Month Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb March The month of time for complation 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 Schedl Progress Original (%) 0,30 0,57 4,81 12,51 19,71 30,61 45,72 57,80 68,70 71,89 77,79 84,28 89,32 95,60 98,79 100,00 1st Revised Progress Schedul (%) 0,23 0,52 4,41 10,83 18,56 30,61 42,24 55,64 67,61 71,88 76,86 82,61 88,27 94,64 97,91 100,00 2nd Revised Progress Schedul (%) Add 3 0,23 0,51 4,33 10,47 16,67 25,51 34,93 45,42 52,47 56,70 61,73 68,56 76,09 85,65 95,41 100,00 3rd Revised Progress Schedul (%) 81,63 87,66 100,00 4th Revised Progress Schedul (%) 86,36 92,12 99,12 100,00 Actual Progress (%) 0,39 0,63 3,77 13,60 16,95 23,14 33,37 46,78 54,23 57,73 58,83 59,02 64,70 73,69 79,99 83,00 89,88 97,77 100,00 Balance (%) 0,09 0,06 (1,04) 1,09 (2,76) (7,47) (12,35) (8,86) (13,39) (14,15) (2,89) (9,54) (11,39) (11,97) (15,43) (17,00) (2,24) (1,35) -Progress per month 0,39 0,24 3,14 9,83 3,35 6,19 10,23 13,41 7,45 3,50 1,10 0,18 5,68 8,99 6,30 3,01 6,88 7,89 2,23

3,14 9,83 3,35 6,19 10,23 13,41 7,45 3,50 1,10 0,18 5,68 8,99

20

TIM

E August 25, 2018LubuK Alung - Sicincin (14,60 km) MAJOR PROBLEMS ACTION TO BE TAKEN

EXECUTIVE SUMMARY REPORTAgu-18

PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS

2016 2017

113.818.300.0002-Mar-18

AMOU

NT

1-Jun-161-Sep-16

DISBURSEMENT (Incl VAT)

2018

25-Agu-1897.259.310.000

Div Description

PHYSICAL PROGRESS MONITORING TABLE

PHYSICAL WORK PROGRESS BY CATEGORY

0

10

20

30

40

50

60

70

80

90

100

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

PHYS

ICAL

PRO

GRES

(%)

THE MONTH OF TIME FOR COMPLATION

PROGRESS SCHEDULEPACKAGE # 20

ORIGINAL SCH

1st REVISED SCH

2nd REVISED SCH

3rd REVISED SCH

4th REVISED SCH

ACTUAL PROGRESS

ESR CTC 25 Aug 2018_1AF1E91C.xlsx P-20

Page 109: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

ANNEX P-5

MONTH :

Package No. Time Elapsed (Days) Name SIMPANG RAMPA - PORIAHA Time Elapsed (%) Project Manager Scheduled Progress (%) 100,00 Contractor PT. NUSA KONSTRUKSI ENJ Tbk. Actual Overall Progress (%) 100,00 Supervision Consultant Balance (%)Contract Sign Progress This Month (%) Commencement Date Time for Complation (Days) 994 Take Over Date Status date Contract Amount (Incl VAT) Rp. Accumulative Rp. 81,27% 1st Revised Contr Amount (Incl VAT) Rp. Proposed Rev Contr Amount (Incl VAT) Rp.

Comp Accum Actual Accum AccumTotal Last this to this Sch to this

% Month Month Month MonthI G e n e r a l 2,09 1,87 0,22 2,09 2,09II D r a i n a g e 2,02 2,03 (0,02) 2,02 2,02III Earthworks 41,93 41,83 0,11 41,93 41,93

IV Pavement Widening &Shoulders 1,15 1,14 0,00 1,15 1,15

V Granular Pavement 6,17 6,16 0,01 6,17 6,17VI Asphalt Pavement 25,93 25,91 0,02 25,93 25,93VII S t r u c t u r e s 18,07 18,06 0,02 18,07 18,07

VIII Reinstatement & MinorWorks 2,33 2,42 (0,09) 2,33 2,33

IX Day Work 0,31 0,23 0,07 0,31 0,31

X Routine MaintenanceWorks - - -

TOTAL 100,0 99,65 0,35 100,00 100,00Note :

Year Month Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Des Jan Feb Mar Apr May Jun Jul The month of time for complation 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 Schedl Progress Original (%) 0,22 0,99 3,89 8,90 16,87 23,69 36,44 40,23 46,08 50,69 56,28 60,45 66,93 69,02 78,66 88,79 96,82 1001st Revised schedul 41,88 41,99 53,49 63,38 76,53 82,27 97,61 99,43 1002nd Revised schedul 99,7 1003rd Revised schedul 99,11 1004th Revised schedul 87,93 93,54 98,00 1005th Revised schedul 87,93 93,54 98,00 99,94 1006th Revised schedul 76,53 87,93 96,21 99,88 100 100 100 100 100 Actual Progress (%) - 0,57 1,09 1,69 2,72 3,08 3,53 5,77 7,37 10,11 16,66 18,44 26,83 28,19 30,00 31,28 35,23 35,25 42,73 43,50 45,99 48,20 51,22 56,42 62,37 67,2 71,58 75,05 71,94 74,31 84,73 86,30 88,09 91,20 96,85 100 Balance (%) (0,22) (0,42) (2,80) (7,20) (14,16) (20,61) (32,91) (34,45) (38,70) (40,58) (39,63) (42,02) (40,10) (40,83) (48,66) (57,51) (61,59) (6,63) 0,74 (9,99) (17,39) (28,32) (31,06) (41,19) (37,05) (32,8) (27,5) (24,9) (26,1) (25,6) (3,2) (9,9) (11,8) (8,8) (3,2) -Progress per month - 0,57 0,52 0,60 1,03 0,37 0,44 2,25 1,60 2,74 6,55 1,78 8,40 1,36 1,81 1,28 3,95 0,02 7,5 0,8 2,49 2,22 3,01 5,20 5,95 4,79 4,41 3,48 (3,12) 2,38 10,41 1,57 1,78 3,12 5,64 3,15

0,57 0,52 0,60 1,03 0,37 0,44 2,25 1,60 2,74 6,55 1,78 8,40 1,36

PHYSICAL PROGRESS MONITORING TABLE2016

17-Mar-15

25-Agu-18

RENARDET S.A JV

AMOU

NT

Saleh Samsuri, ST

DISBURSEMENT (Incl VAT)18-Jun-15

Div Description

2018

100.315.083.94408-Mar-18

130.143.385.310

20172015

107.321.260.310

PHYSICAL WORK PROGRESS BY CATEGORY

EXECUTIVE SUMMARY REPORT

05

TIM

E August 25, 2018MAJOR PROBLEMS ACTION TO BE TAKEN

Agu-18

PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS

123.428.115.302

0

10

20

30

40

50

60

70

80

90

100

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38

PHYS

ICAL

PRO

GRES

(%)

THE MONTH OF TIME FOR COMPLATION

PROGRESS SCHEDULEPACKAGE # 05

Series1 Series2

Series3 Series4

Series5 Series6

Series7 Series8

ESR CTC 25 Aug 2018_1AF1E91C.xlsx P-05

Page 110: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

ANNEX P-13

MONTH :

Package No. Time Elapsed (Days) Name SIMPANG RUKIS-TANJUNG KEMUNING Time Elapsed (%) Project Manager Paides Tabril, ST,MT Scheduled Progress (%) 100,00 Contractor PT. WASKITA KARYA Actual Overall Progress (%) 100,00 Supervision Consultant Balance (%)Contract Sign Progress This Month (%) Commencement Date Time for Complation (Days) 1028 Take Over Date Status date Contract Amount (Incl VAT) Rp. Accumulative Rp. 72,22%Price Adjustment Rp.

Comp Accum Actual Accum AccumTotal Last this to this Sch to this

% Month Month Month MonthI G e n e r a l 0,41 0,309 - 0,409 0,41II D r a i n a g e 1,76 1,633 0,27 2,590 2,59III Earthworks 9,35 7,586 1,13 9,477 9,48

IV Pavement Widening &Shoulders 4,41 2,635 - 3,253 3,25

V Granular Pavement 17,19 14,052 0,06 14,115 14,12VI Asphalt Pavement 62,34 57,181 4,29 62,263 62,26VII S t r u c t u r e s 2,23 3,375 0,93 5,166 5,17

VIII Reinstatement & MinorWorks 2,14 1,529 0,51 2,553 2,55

IX Day Work - -

X Routine MaintenanceWorks 0,18 0,072 0,01 0,174 0,17

TOTAL 100,0 88,37 7,20 100,00 100,00Note :

Year Month Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May June July Aug Sep Oct Nov Dec Jan Feb Mar Apr May The month of time for complation 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 Schedl Progress Original (%) 0,02 0,21 1,65 4,18 6,69 9,61 14,62 20,36 26,94 33,58 41,24 47,87 50,63 58,32 63,60 68,28 72,97 77,66 82,62 86,79 91,19 95,75 99,36 99,74 1001st Revised Schedule (%) 0,20 0,90 2,20 4,00 5,80 7,50 9,50 11,50 13,30 15,40 16,13 20,18 24,00 27,82 32,00 36,44 41,47 46,63 54,87 63,48 72,34 81,13 90,08 97,87 1002nd Revised Schedule (%) 54,29 75,28 82,33 91,9 1003rd Revised Schedule (%) 68,39 76,55 1004th Revised Schedule (%) 84,86 97,34 1005th Revised Schedule (%) 79,34 86,47 94,76 100 Actual Progress (%) - 0,36 0,88 2,19 3,39 13,71 13,84 14,37 14,62 16,02 17,34 18,25 18,55 19,06 19,25 20,53 22,77 32,63 41,11 42,71 44,34 47,26 48,87 50,29 52,54 55,99 57,94 60,69 64,77 68,64 70,94 74,85 85,64 92,98 100 Balance (%) (0,02) 0,14 (0,77) (1,98) (3,30) 4,10 (0,78) (5,99) (12,32) (17,56) (23,90) (29,63) (32,08) (39,26) (44,34) (47,75) (50,20) (45,03) (41,51) (20,77) (28,01) (33,87) (41,21) (47,58) (22,74) (26,3) (34,0) (39,3) (11,8) (31,4) (26,4) (25,2) (0,8) (1,8) -Progress per month - 0,36 0,52 1,32 1,20 10,3 0,14 0,53 0,24 1,40 1,32 0,91 0,30 0,51 0,19 1,27 2,24 9,86 8,48 1,60 1,63 2,92 1,61 1,42 2,25 3,45 1,95 2,75 4,07 3,88 2,30 3,91 10,79 7,34 7,02

0,36 0,52 1,32 1,20 10,31 0,14 0,53 0,24 1,40 1,32 0,91 0,30 0,51

22-Jul-15

EXECUTIVE SUMMARY REPORTAgu-18

PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS13

TIM

E August 25, 2018MAJOR PROBLEMS ACTION TO BE TAKEN

2018

DISBURSEMENT (Incl VAT)15-Mei-18 25-Agu-18

305.886.100.000 220.915.325.000

There are several road narrowings due to thelimitations of ROW.

A revised design is needed to secure road users.

AMOU

NT

RENARDET S.A JV18-Dec-14

PHYSICAL PROGRESS MONITORING TABLE2015 2016 2017

PHYSICAL WORK PROGRESS BY CATEGORY

Div Description

0

10

20

30

40

50

60

70

80

90

100

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35

PHYS

ICAL

PRO

GRES

(%)

THE MONTH OF TIME FOR COMPLATION

PROGRESS SCHEDULEPACKAGE # 13

Series1

Series2

Series3

Series4

Series5

Series6

Series7

ESR CTC 25 Aug 2018_1AF1E91C.xlsx P-13

Page 111: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

ANNEX P-15

MONTH :

Package No. Time Elapsed (Days) Name Time Elapsed (%) Project Manager Scheduled Progress (%) 100,00 Contractor PT. PEMBANGUNAN PERUMAHAN Actual Overall Progress (%) 100,00 Supervision Consultant Balance (%)Contract Sign Progress This Month (%) Commencement Date Time for Complation (Days) 953 Take Over Date Status date Contract Amount (Incl VAT) Rp. Accumulative Rp. 66,83% Proposed Rev Cont Amount (Incl VAT) Rp. 100,00%Cancellation (incl VAT) Rp. 0,00%

Comp Accum Actual Accum AccumTotal Last this to this Sch to this

% Month Month Month MonthI G e n e r a l 1,72 1,43 0,29 1,72 2,30II D r a i n a g e 0,41 0,38 0,03 0,41 5,13III Earthworks 7,76 7,28 0,27 7,55 6,34

IV Pavement Widening &Shoulders

2,71 1,91 0,80 2,71 2,16

V Granular Pavement 18,39 18,61 - 18,61 24,41VI Asphalt Pavement 57,17 55,13 2,04 57,17 40,48VII S t r u c t u r e s 7,58 7,35 0,24 7,58 16,75

VIII Reinstatement & MinorWorks

3,92 1,33 2,60 3,92 2,39

IX Day Work 0,34 0,01 0,33 0,34 0,04

X Routine MaintenanceWorks

- - - - -

TOTAL 100,0 93,40 6,60 100,00 100,00Note :

Year Month Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun The month of time for complation 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 Schedl Progress Original (%) 0,11 0,45 1,04 3,18 5,57 8,98 13,46 19,96 23,3 29,8 36,3 42,3 48,17 53,91 58,4 64,3 69,6 75,51 81,15 87,1 90,01 93,9 97,3 98,7 99,7 100,01st Revised Sch 7,4 11,8 14,1 18,5 23,8 30,1 37,5 44,4 49,9 57,0 63,5 70,2 77,5 84,7 88,2 93,1 97,6 99,4 100,02nd Revised Sch 80,66 82,67 83,68 86,39 88,64 92,16 98,37 1003rd Revised Sch 68,89 76,50 83,18 88,64 94,35 99,54 100 Actual Progress (%) 0,15 0,46 0,92 1,42 1,69 2,34 4,72 5,59 5,96 8,94 8,99 12,04 13,25 20,5 27,0 27,9 29,4 34,7 40,6 43,7 46,4 50,0 54,3 56,8 59,6 61,0 65,83 70,77 72,50 74,14 96,78 97,26 Balance (%) 0,03 0,02 (0,12) (1,76) (3,88) (6,64) (2,7) (6,2) (8,2) (9,5) (14,8) (18,0) (24,2) (23,9) (23,0) (29,2) (34,1) (35,5) (36,9) (40,9) (41,9) (43,1) (43,4) (35,3) (38,8) (39,0) (10,7) (12,4) (16,1) (20,2) (2,8) (2,4)Progress per month 0,3 0,5 0,5 0,5 0,3 0,6 2,4 0,9 0,4 3,0 0,0 3,1 1,2 7,3 6,5 0,9 1,6 5,2 5,9 3,2 2,6 3,6 4,3 2,6 2,8 1,4 4,8 4,9 1,7 1,6 22,6 0,5

0,32 0,46 0,50 0,27 0,65 2,38 0,87 0,37 2,99 0,04 3,05 1,21 7,27

EXECUTIVE SUMMARY REPORT

PROGRESS STATUS15

TIM

E

Agu-18

PROJECT DATA SUMMARY OF WORK PROGRESSAugust 25, 2018

MAJOR PROBLEMS ACTION TO BE TAKENSIBOLGA - BTS. TAPSEL• Activities slow down and progress late

0260.100.000.000

• A penalty is applied• There are locations with limited ROW width • Required re-design for road safety• Proposed reduction in work volume and contract value of25.58% equivalent to IDR 67 billion

• Require Technical Justification, approval of re-designfrom BBPJN-II Medan and field review

DISBURSEMENT (Incl VAT)

AMOU

NT

Saleh Samsuri, ST

PHYSICAL WORK PROGRESS BY CATEGORY

30-Jun-18 25-Agu-18173.815.637.972

A Joint Venture of Renardet, S.A.13-Jul-1520-Nov-15

260.100.000.000

2018PHYSICAL PROGRESS MONITORING TABLE

Div Description

2015 2016 2017

0

10

20

30

40

50

60

70

80

90

100

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32

PHYS

ICAL

PRO

GRES

(%)

THE MONTH OF TIME FOR COMPLATION

PROGRESS SCHEDULEPACKAGE # 15

ORIGINAL SCH

1st REVISED SCH

2nd REVISED SCH

3rd REVISED SCH

ACTUAL PROGRESS

ESR CTC 25 Aug 2018_1AF1E91C.xlsx P-15

Page 112: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

ANNEX P-12

MONTH :

Package No. Time Elapsed (Days) 824 Name Time Elapsed (%) 103,52 Sub Project Manager / PPK Filino Kalani, ST Scheduled Progress (%) 100,00 Contractor Actual Overall Progress (%) 80,28

Balance (%) (19,72) Supervision Consultant RENARDET S.A JV PT. Daya Creasi Mitrayasa Progress This Month (%) 3,33 Contract Sign Commencement Date Take Over Date Status date Time for Complation (Days) 796 Calendar Days Accumulative Rp. 58,08% Contract Amount (Incl VAT) Rp.Price Adjustment Rp.

Add. Accum Actual Accum AccumTotal Last this to this Sch to

% Month Month Month thisMonth

I G e n e r a l 2,45 0,74 - 0,74 2,45II D r a i n a g e 4,93 2,85 - 2,85 4,93III Earthworks 5,42 4,92 - 4,92 5,42

IV Pavement Widening &Shoulders

1,51 0,96 - 0,96 1,51

V Granular Pavement 13,88 13,31 - 13,31 13,88VI Asphalt Pavement 58,61 49,37 3,33 52,70 58,61VII S t r u c t u r e s 9,00 4,27 - 4,27 9,00

VIII Reinstatement & MinorWorks

4,03 0,43 - 0,43 4,03

IX Day Work 0,04 0,01 - 0,01 0,04

X Routine MaintenanceWorks

0,13 0,08 - 0,08 0,13

TOTAL 100,00 76,95 3,33 80,28 100Note :

May June July August Sept October Nov Des January Feb March April May June July August Sept October Nov Des January Feb March April May June July August1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 280,09 0,58 0,84 1,26 1,61 4,10 8,31 14,09 21,50 31,99 44,07 56,50 71,44 77,99 77,99 80,17 82,88 85,50 89,12 91,76 94,29 97,31 99,45 99,78 100,00

1,50 2,34 4,93 9,39 15,87 27,24 40,55 54,23 70,99 77,90 80,34 83,37 86,33 90,58 95,17 100,01,50 2,27 4,92 9,51 17,87 23,46 28,68 35,12 47,91 55,53 63,68 77,09 88,00 96,16 99,21 100,0

50,76 54,74 61,52 67,07 75,33 87,88 96,04 100,00 100,000,192 0,44 0,87 0,98 1,05 1,97 2,13 4,02 4,03 4,99 5,928 7,35 9,72 11,93 13,39 15,68 17,53 20,88 23,13 25,98 30,02 41,22 49,65 63,24 72,28 73,47 76,95 80,28

0,10 (0,14) 0,03 (0,28) (0,45) (0,37) (2,80) (5,37) (11,84) (22,25) (34,62) (46,88) (61,27) (65,97) (50,28) (61,41) (70,47) (75,28) (76,08) (74,02) (24,72) (20,31) (17,42) (12,09) (15,60) (22,57) (23,05) (19,72)Progress per month 0,43 0,11 0,07 0,91 0,17 1,89 0,01 0,96 0,94 1,42 2,37 2,21 1,46 2,29 1,85 3,35 2,25 2,85 4,04 11,19 8,43 13,59 9,04 1,19 3,48 3,33

0,25 0,43 0,11 0,07 0,91 0,17 1,89 0,01 0,96 0,94 1,42 2,37 2,21

208.316.205.647

28-Jan-1623-May-16 DISBURSEMENT (Incl VAT)28-Jul-18 25-Agu-18

12

TIM

E August 25, 2018Kambang - Indrapura MAJOR PROBLEMS ACTION TO BE TAKEN

EXECUTIVE SUMMARY REPORTAgu-18

PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS

Actual Progress (%) Balance (%)

2nd Rivised Progress Sch Add.2 (%)

358.650.400.000

Original Progress Schedul (%)

Month

PHYSICAL WORK PROGRESS BY CATEGORY

Div Description

PHYSICAL PROGRESS MONITORING TABLE Year 2016 2017 2018

• Late payment of IPC in Jan - Apr 2018• Activities slow down and progress late

• Required extension of time for completion

The month of time for complation

3rd Rivised Progress Sch (%)

1st Rivised Progress Sch Add.1 (%)

AMOU

NTPT. LANCARJAYA MANDIRI ABADI - PT.CAHAYA TUNGGAL ABADI , JO.

0

10

20

30

40

50

60

70

80

90

100

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27

PHYS

ICAL

PRO

GRES

(%)

THE MONTH OF TIME FOR COMPLATION

PROGRESS SCHEDULEPACKAGE # 12

ORIGINAL SCH

1st REVISED SCH

2nd REVISED SCH

3rd REVISED SCH

ACTUAL PROGRESS

C:\Users\Tediero Pratama\AppData\Local\Temp\ESR CTC 25 Aug 2018_1AF1E91C.xlsx P-12

Page 113: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

ANNEX P-14

MONTH :

Package No. Time Elapsed (Days) 752 Name Time Elapsed (%) 103,87 Sub Project Manager / PPK Rahmat Donal, ST, MT Scheduled Progress (%) 100,00 Contractor 'PT YASA - CONBLOC, JV Actual Overall Progress (%) 81,02 Supervision Consultant RENARDET S.A JV Balance (%) (18,98) Contract Sign Progress This Month (%) 1,10 Commencement Date Time for Complation (Days) 724 Calendar Days Take Over Date Status date Contract Amount (Incl VAT) Rp. Accumulative Rp. 67,80%Price Adjustment Rp.

Comp Accum Actual Accum AccumTotal Last this to this Sch to

% Month Month Month thisMonth

I G e n e r a l 1,17 0,73 - 0,73 1,17II D r a i n a g e 14,61 3,54 - 3,54 14,61III Earthworks 7,28 8,24 - 8,24 7,28

IV Pavement Widening &Shoulders

2,68 0,16 0,08 0,24 2,68

V Granular Pavement 12,61 13,38 0,08 13,46 12,61VI Asphalt Pavement 54,22 51,02 0,92 51,94 54,22VII S t r u c t u r e s 2,73 2,23 0,02 2,25 2,73

VIII Reinstatement &Minor Works

4,39 0,34 - 0,34 4,39

IX Day Work 0,04 0,01 - 0,01 0,04

X Routine MaintenanceWorks

0,28 0,28 - 0,28 0,28

TOTAL 100,00 79,92 1,10 81,02 100,0Note :

August Sept October Nov Des January Feb March April May June July August Sept October Nov Des January Feb March April May June JuL Aug1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 250,17 0,34 0,51 0,94 2,02 4,47 7,12 10,30 14,85 21,63 29,98 38,68 47,74 54,09 63,68 71,43 79,18 86,11 92,51 97,49 100,00,17 0,56 0,72 1,78 5,87 10,05 15,36 20,60 28,07 32,72 37,80 45,12 53,79 66,71 80,65 92,59 100,00,17 0,56 0,72 1,78 5,87 10,05 15,36 20,60 28,07 32,72 37,80 43,57 53,79 66,71 80,65 92,59 100,0

64,64 77,91 83,08 87,87 97,79 100,0 100,0 100,0 100,00,18 0,47 2,65 3,83 3,94 5,96 9,27 15,63 19,18 28,90 32,89 36,88 46,05 52,18 55,75 59,32 62,64 65,79 68,90 75,34 77,89 78,75 79,92 79,92 81,020,00 (0,09) 1,92 2,05 (1,92) (4,09) (6,09) (4,96) (8,89) (3,82) (4,91) (6,69) (7,74) (14,53) (24,90) (33,27) (37,36) (12,13) (14,18) (12,52) (19,90) (21,25) (20,08) (20,1) (19,0)

Progress per month 0,18 0,29 2,18 1,19 0,11 2,02 3,31 6,37 3,54 9,72 3,99 3,99 9,16 6,14 3,57 3,57 3,32 3,15 3,11 6,44 2,55 0,86 1,17 - 1,100,29 2,18 1,19 0,11 2,02 3,31 6,37 3,54 9,72 3,99 3,99 9,16 6,14

1-Jun-163-Aug-16

PHYSICAL PROGRESS MONITORING TABLE

PHYSICAL WORK PROGRESS BY CATEGORY

Div Description

DISBURSEMENT (Incl VAT)25-Agu-18

• A penalty is applied

27-Jul-18214.322.429.680 145.313.747.806

• The contractor lacks operational costs • PPK / Satker / PJN-III clarification to thecontractor

• Activities slow down and progress late

EXECUTIVE SUMMARY REPORTAgu-18

PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS

ACTION TO BE TAKEN

AMOU

NT

14

TIM

E August 25, 2018 Painan - Kambang MAJOR PROBLEMS

2018

Actual Progress (%) Balance (%)

20172016 Year Month

1st Revise Progress Schedul (%)

The month of time for complation Original Progress Schedul (%)

2nd Revise Progress Schedul (%) 3rd Revise Progress Schedul (%)

0

10

20

30

40

50

60

70

80

90

100

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

PHYS

ICAL

PRO

GRES

(%)

THE MONTH OF TIME FOR COMPLATION

PROGRESS SCHEDULEPACKAGE # 14

ORIGINAL SCH

1st REVISED SCH

2nd REVISED SCH

3rd REVISED SCH

ACTUAL

C:\Users\Tediero Pratama\AppData\Local\Temp\ESR CTC 25 Aug 2018_1AF1E91C.xlsx P-14

Page 114: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

ANNEX P-16

MONTH :

Package No. 16 Time Elapsed (Days) 655

Name Seblat - Ipuh Time Elapsed (%) 103,97

Project Manager Fathoni Ikhsan, ST Scheduled Progress (%) 100,00 Contractor KSO PT Yasa - Multi Structure Actual Overall Progress (%) 89,48 Supervision Consultant A Joint Venture of Renardet, S.A. Balance (%) -10,52Contract Sign Progress This Month (%) 4,59 Commencement Date Time for Complation (Days) 630 Take Over Date Status date Contract Amount (Incl VAT) Rp. Accumulative Rp. 79,87%Price Adjustment Rp.

Comp Add.2 Accum Actual Accum AccumTotal Total Last this to this Sch to

% % Month Month Month thisMonth

I G e n e r a l 1,40 1,51 1,19 - 1,19 1,51II D r a i n a g e 13,85 13,71 10,90 - 10,90 13,71III Earthworks 6,57 5,95 4,78 - 4,78 5,95

IV Pavement Widening &Shoulders

2,32 2,30 4,44 - 4,44 2,30

V Granular Pavement 10,85 10,97 11,51 - 11,51 10,97VI Asphalt Pavement 51,52 53,55 46,09 - 46,09 53,55VII S t r u c t u r e s 8,41 8,46 8,75 - 8,75 8,46

VIII Reinstatement & MinorWorks

4,79 3,25 1,53 - 1,53 3,25

IX Day Work 0,05 0,05 0,05 0,00 0,05 0,05

X Routine MaintenanceWorks

0,24 0,24 0,24 0,01 0,26 0,24

TOTAL 100,00 100,00 89,5 0,01 89,50 100Note :

Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 220,07 0,26 0,57 4,03 8,73 12,40 17,12 21,87 25,29 30,86 36,98 43,59 52,25 58,94 63,06 69,89 75,30 80,70 86,70 92,22 100,0

1st REVISED Schedul (%) 0,16 0,34 0,62 1,05 2,47 4,31 7,08 10,63 14,96 20,69 24,96 29,89 37,24 46,45 53,45 62,17 70,31 80,83 90,54 100,0 100,0 100,00,18 0,260 0,407 1,04 2,17 4,90 8,68 12,11 17,57 23,76 23,95 37,68 46,55 52,08 53,60 62,48 70,47 76,47 82,64 84,89 89,48 89,500,11 - (0,16) (2,99) (0,31) 0,59 1,61 1,48 2,61 3,07 (1,01) 7,79 9,32 5,63 0,15 0,31 0,16 (4,36) (7,90) (15,11) (10,52) (10,50)

Progress per month 0,18 0,08 0,15 0,63 1,13 2,73 3,78 3,43 5,46 6,19 0,18 13,74 8,87 5,53 1,52 8,88 7,99 6,00 6,17 2,25 4,59 0,010,08 0,15 0,63 1,13 2,73 3,78 3,43 5,46 6,19 0,18 13,74 8,87 5,53

168.828.736.529

Year

EXECUTIVE SUMMARY REPORTAgu-18

PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS

DISBURSEMENT (Incl VAT)31-Jul-18 25-Agu-18

211.374.500.000

ACTION TO BE TAKEN

AMOU

NTTI

ME August 25, 2018

2018

MAJOR PROBLEMS

• The contractor lacks operational costs • PPK / Satker / PJN-III clarification to thecontractor

• Activities slow down and progress late • Required extension of time

PHYSICAL WORK PROGRESS BY CATEGORY

Balance (%)

28-Oct-1608-Nov-16

2016 2017 Month The month of time for complation Original Progress Schedul (%)

Actual Progress (%)

Div Description

PHYSICAL PROGRESS MONITORING TABLE

0

10

20

30

40

50

60

70

80

90

100

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

PHYS

ICAL

PRO

GRES

(%)

THE MONTH OF TIME FOR COMPLATION

PROGRESS SCHEDULEPACKAGE # 16

ORIGINAL Sch

1st REVISED Sch

ACTUAL

C:\Users\Tediero Pratama\AppData\Local\Temp\ESR CTC 25 Aug 2018_1AF1E91C.xlsx P-16

Page 115: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

ANNEX P-21

MONTH :

Package No. Time Elapsed (Days) 723 Name Time Elapsed (%) 108,72 Project Manager Opukenigara, ST Scheduled Progress (%) 100,00 Contractor 'PT Multi Structur Actual Overall Progress (%) 55,79 Supervision Consultant RENARDET S.A JV PT. CIPTA STRADA Balance (%) (44,21) Contract Sign Progress This Month (%) Terminate Commencement Date Time for Complation (Days) 665 Calendar Days Take Over Date Status date Contract Amount (Incl VAT) Rp. Accumulative Rp. 91,49%Est FINAL Contract Amount (Incl VAT) Rp.

Comp Accum Actual Accum AccumTotal Last this to this Sch to this

% Month Month Month MonthI G e n e r a l 3,34 3,33 (0,00) 3,33 3,34II D r a i n a g e 28,82 13,54 1,68 15,22 28,82III Earthworks 5,39 5,26 - 5,26 5,39

IV Pavement Widening &Shoulders

2,35 - - - 2,35

V Granular Pavement 7,92 7,50 - 7,50 7,92VI Asphalt Pavement 41,26 21,7 (0,42) 21,3 41,26VII S t r u c t u r e s 8,01 5,81 - 5,81 8,01

VIII Reinstatement & MinorWorks

2,57 0,56 (0,31) 0,25 2,57

IX Day Work 0,04 - - - 0,04

X Routine MaintenanceWorks

0,30 0,16 (0,06) 0,10 0,30

TOTAL 100,00 57,90 0,89 55,79 100,00Note :

Year Month Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun The month of time for complation 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 Schedl Progress Original (%) 0,56 2,40 4,37 12,27 21,33 28,48 37,16 43,98 50,80 55,91 62,73 71,26 76,82 82,58 94,28 100,0 1st Revised Progress Schedul (%) 2,05 3,03 9,86 20,07 28,23 35,21 42,76 50,07 55,91 61,52 69,07 75,59 81,76 91,81 100,0 2nd Revised Progress Sch Add-3 (%) 48,35 53,35 60,57 70,25 77,68 84,95 93,34 100,0 3rd Revised Progress Sch (%) 51,09 57,14 64,67 72,11 82,28 91,94 100,00 Actual Progress (%) 0,78 1,94 2,20 3,25 13,38 15,66 21,25 22,41 34,91 39,33 40,53 42,24 43,10 45,46 47,63 49,17 50,36 52,42 53,73 55,24 57,90 55,79 Balance (%) 0,22 (0,11) (0,83) (6,61) (6,69) (12,57) (13,96) (20,35) (15,16) (16,58) (20,04) (28,01) (34,58) (39,49) (45,71) (50,83) (6,78) (12,25) (18,38) (27,04) (34,04) (44,21)Progress per month 0,78 1,16 0,26 1,05 10,13 2,28 5,59 1,16 12,50 4,42 1,20 1,71 0,86 2,36 2,17 1,54 1,19 2,06 1,31 1,51 2,66

0,26 1,05 10,13 2,28 5,59 1,16 12,50 4,42 1,20 1,71 0,86 2,36

21

TIM

E August 25, 2018LubuK Alun - Kuraitaji (16,80 km) MAJOR PROBLEMS ACTION TO BE TAKEN

EXECUTIVE SUMMARY REPORTAgu-18

PROJECT DATA SUMMARY OF WORK PROGRESS PROGRESS STATUS

2016 2017

28-Jun-18126.301.900.000

Contract is terminated

AMOU

NT

1-Jun-161-Sep-16

DISBURSEMENT (Incl VAT)

2018

Require new procurement for remaining quantity

25-Agu-1864.470.415.000

70.463.830.010

Div Description

PHYSICAL PROGRESS MONITORING TABLE

PHYSICAL WORK PROGRESS BY CATEGORY

0

10

20

30

40

50

60

70

80

90

100

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22

PHYS

ICAL

PRO

GRES

(%)

THE MONTH OF TIME FOR COMPLATION

PROGRESS SCHEDULEPACKAGE # 21

ORIGINAL SCH

1st REVISED SCH

2nd REVISED SCH

3rd REVISED SCH

ACTUAL PROGRESS

ESR CTC 25 Aug 2018_1AF1E91C.xlsx P-21

Page 116: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

ATTACHMENT No. 1

Summary of Submitted Environmental Reports

Page 117: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

As of Agustus 2018

1 2 3 5 6 7 8 9

1 Krui - Bha Lampung 1 SPPL November 2010 1X 24 Sep 2013 30 Sep 2013 20 Nov 2013 /NOL

2 AMDAL Environmental Feasibility : 12 Oct 2012Environmental permits: 21 Nov 2012 1X 24 Sep 2013 30 Sep 2013 20 Nov 2013/NOL

3 Monitoring of IntegrationAMDAL into Design - 1X 15 August 2014 NN NN

4 AMDAL Implementation Report(PIU to BLH) - each 6

month 17 April 2015 ; 6 Oct

2015 ; 29 April 2015 ; 19 Oct

2015 11 Mei 2015 ; 14 Des

2015

5 RKPPL - 1X 28 Jan 2015 06 Feb 2015 23 Feb 2015/NOL

6 RKPPL Implementation Report - Quarter 3 July 2015 ; 13 Nov

2015 ; 4 Feb 2016 ; 17Feb 2016

31 July 2015 ; 24 Nov2015 ; Informal to WB 4

& 17 Feb 2016

13 August 2015:14 Dec 15 ; 19 Feb

2016

7 HIV - AIDS Campaign Report - 1X 8 January 2016 15 March 2016 NN

2 Padang Sawah - Sp Empat Sumatera Barat 1 SPPL Nov. 2013 1X - 20 Jan 2014 14 April 2014/NOL

Jembatan Air Gadang Sumatera Barat 2 UKL & UPL Recommendation: Nov 2013 1X - 09 June 2014 08 Auguts 2014/NOL

3 UKL&UPL ImplementationReport (PIU to BLH) - each 6

month 17 April 2015 ; 6 Oct2015 ; 28 Jun 2016

29 April 2015 ; 19 Oct2015 : 21 Juli 2016

11 Mei 2015 ; 14 Des2015 ; 22 Juli 2016

4 RKPPL - 1X 11 Dec 2014 19 Dec 2014 30 Jan 2015/NOL

5 RKPPL Implementation Report - Quarter 3 July 2015 ; 13 Nov

2015 ; 4 Feb 2016 ; 17Feb 2016 ; 28 Jun 2016

31 July 2015 ; 24 Nov2015 ; Informal to WB 4& 17 Feb 2016 ; 21 Juli

2016

13 August 2015:14 Dec 15 ; 19 Feb2016 ; 22 Juli 2016

6 HIV - AIDS Campaign Report - 1X 8 January 2016 15 March 2016 NN

3 Manggopoh - Padang Sawah Sumatera Barat 1 SPPL 30 Dec 2013 1X - 20 Jan 2014 14 April 2014

2 SPPL Implementation Report(PIU to BLH) - each 6

month 17 April 2015 29 April 2015 11 Mei 2015

3 RKPPL - 1X 11 Dec 2014 19 Dec 2014 30 Jan 2015/NOL

4 RKPPL Implementation Report - Quarter 3 July 2015 ; 13 Nov

2015 ; 4 Feb 2016 ; 17Feb 2016

31 July 2015 ; 24 Nov2015 ; Informal to WB 4

& 17 Feb 2016

13 August 2015:14 Dec 15 ; 19 Feb

2016

5 HIV - AIDS Campaign Report - 1X 8 January 2016 15 March 2016 NN

4 Ipuh - Bantal Bengkulu 1 SPPL (Initial study) 20 Dec 2013 1X April 2013 - -

2 UKL & UPL Environmental permits : 6 Des 2014 1X - 06 Feb 2015(Environment permits) 23 Feb 2015

3 UKL&UPL ImplementationReport (PIU to BLH) - each 6

month 17 April 2015 ; 6 Oct2015 ; 28 Juni 2016

29 April 2015 ; 19 Oct2015 : 21 Juli 2016

11 Mei 2015 ; 14 Des2015 ; 22 Juli 2016

4 RKPPL - 1X 28 Jan 2015 06 Feb 2015 23 Feb 2015/NOL

Environmental Safeguard

Correspondence of Environmental Safeguard and Reporting on CTC WINRIP

Date of Recomendation/Environmental Permits

No ofPackage Name of Link Province Sent to WBCTC Letters to PMUDurations

Environmental Activity, CTC WINRIP

WB NOL/Letters4

Page 118: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

1 2 3 5 6 7 8 9

Environmental Safeguard Date of Recomendation/Environmental Permits

No ofPackage Name of Link Province Sent to WBCTC Letters to PMUDurations WB NOL/Letters

4

5 RKPPL Implementation Report - Quarter 3 July 2015 ; 13 Nov

2015 ; 4 Feb 2016 ; 17Feb 2016 ; 28 Jun 2016

31 July 2015 ; 24 Nov2015 ; Informal to WB 4& 17 Feb 2016 ; 21 Juli

2016

13 August 2015:14 Dec 15 ; 19 Feb2016 ; 22 Juli 2016

6 HIV - AIDS Campaign Report - 1X 8 January 2016 15 March 2016 NN

5 Sp. Rampa - Poriaha Sumut 1 UKL & UPL Recommendation : 8 Dec 2011 1X 24 Sep 2013 30 Sep 2013 20 Nov 2013

2 Monitoring of IntegrationUKL&UPL into Design - 1X 11 Nov 2014 NN NN

3 UKL&UPL ImplementationReport (PIU to BLH) - each 6

month 28 Jun 2016; 31 Auguts

2017 21 Juli 2016; 28 Sept

2017 22 Juli 2016; WB file

4 RKPPL - 1X 26 April 2016 13 May 2016 30 Juni 2016

6 RKPPL Implementation Report - Quarter

4 Feb 2016 ; 17 Feb2016 ; 28 Jun 2016;11Nov 2016; 2 Jun 2017;31 August 2017 ; 8 Nov2017; 21 Mei 2018; 14

Agustus 2018

Informal to WB 4 & 17Feb 2016 : 21 Juli 2016;28 Nov 2016 ; 15 Mar2017 (informal) ; 9 Jun2017; 28 Sept 2017 ; 04

Des 2017; 19 Maret 2018-informal; 31 Agustus

2018

19 Feb 2016 ; 22 Juli2016; 19 Des 2016; 18Juli 2017; WB file ; 12

Jan 2018 (ask torevised report); 4 Juli

2018

6 HIV - AIDS Campaign Report - 1X 29 February 2016 15 March 2016 NN

7 Improvement Base CampManagement

30 Januari 2018; 15 Feb2018 (infomal 13 Feb) ;6March 2018; 23 March2018; 9 April 2018; 15

Mei 2018

7 Februari 2018;informal 13 Feb 2018;

informal 6 March 2018;informal 22 March 2018 ;10 April 2018 -informal;16 Mei 2018-informal

12 Februari 2018

6 Ps. Pedati - Kerkap Bengkulu 1 UKL & UPL Recommendation : 9 Nov 2011 1X 24 Sep 2013 30 Sep 2013 20 Nov 2013

2 Monitoring of IntegrationUKL&UPL into Design - 1X 29 Oct 2015 NN NN

3 UKL&UPL ImplementationReport (PIU to BLH) - Quarter 28 Jun 2016 21 Juli 2016 ; 20 Nov

2016 (informal) 22 Juli 2016

4 RKPPL - one time 4 Nov 2015 24-Nov-15 14 Des 2016 (NOL)

5 RKPPL Implementation Report Quarter 13 Nov 2015 ; 4 Feb

2016 ; 17 Feb 2016 ; 28Jun 2016 ; 11 Nov 2016

24 Nov 2015; Informal toWB 4 & 17 Feb 2016; 21Juli 2016; 28 Nov 2016 ;15 Mar 2017 (informal)

14 Des 2016 (NOL) ; 19Feb 2016 ; 22 Juli 2016;

19 Des 2016

6 HIV - AIDS Campaign Report - 1X 12 February 2016 15 March 2016 NN

7 Indrapura - Tapan Sumatera Barat 1 AMDAL Environmental feasibility : 05 Feb 2014 ;environmental permits : 5 Feb 2014 1X - 09 June 2014 08 August 2014

2 Monitoring of IntegrationAMDAL into Design - 1X 2 Dec 2015 NN NN

3 AMDAL Implementation Report(PIU to BLH) - each 6

month 1 March 2017 13 April 2017 17 April 2017

4 RKPPL - 1X 27 Feb 2017 20 March 2017 5 April 2017

Page 119: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

1 2 3 5 6 7 8 9

Environmental Safeguard Date of Recomendation/Environmental Permits

No ofPackage Name of Link Province Sent to WBCTC Letters to PMUDurations WB NOL/Letters

4

5 RKPPL Implementation Report Quarter 15 Mar 2017 (informal); 2 Jun 2017; 31 August

2017; 8 Nov 2017

15 Mar 2017 (informal) ;9 Jun 2017; 28 Sept 2017;

4 Des 2017; 19 Maret2018-Informal

5 April 2017 ; 18 Juli2017; WB file ;12 Jan2018 (ask to revised

report)

6 HIV - AIDS Campaign Report - 1X 29 Sept 2016 13 October 2016 NN

7 Improvement Base CampManagement

30 Januari 2018; 15 Feb2018 (infomal 13 Feb); 6

March 2018

7 Februari 2018;informal 13 Feb 2018;informal 6 March 2018

12 Feb 2018

8 Bts. Kota Pariaman - Manggopoh Sumatera Barat 1 AMDAL Environmental permits : 23 July 2013 1X - 20 Jan 2014 14 April 2014

2 Monitoring of IntegrationAMDAL into Design - 1X 6 Oct 2015 NN NN

3 AMDAL Implementation Report(PIU to BLH) - each 6

month 29 Sept 2016 ; 08November 2017

13 October 2016; 4 Des2017 12 Jan 2018

4 RKPPL - 1X 02 November 2016 14 November 2016 23 November 2016

5 RKPPL Implementation Report Quarter 15 Mar 2017 (informal); 2 Jun 2017; 31 August

2017; 8 Nov 2017

15 Mar 2017 (informal) ;9 Jun 2017: 28 Sept 2017

; 4 Des 2017; 19 Maret2018-informal

18 Juli 2017; WB file;12 Jan 2018 (ask to

revised report)

6 HIV - AIDS Campaign Report - 1X 11 November 2016 ; 6April 2017

28 November 2016; 13April 2017 NN

9 Bentungan- Tais (N.013.018 ; 43,42km) Bengkulu

10 Sp. Empat - Air Balam Sumatera Barat 1 AMDAL Environmental permits : 23 July 2013 1X - 20 Jan 2014 14 April 2014

11 Bantal - Mukomuko Bengkulu 1 AMDAL Environmental permits : 3 April 2014 1X - 09 June 2014 08 August 2014

2 Monitoring of IntegrationAMDAL into Design - 1X 10 Dec 2014 NN NN

3 AMDAL Implementation Report(PIU to BLH) - each 6

month 28 Jun 2016 ; 31

August 2017

29 April 2016 (informal)& 21 Juli 2016 (formal) ; 5

Des 2016 informal ; 28Sept 2017

22 Juli 2016; WB file

4 RKPPL - 1X 10 Des 2015 23-Des-15 8 Jan 2016/NOL

5 RKPPL Implementation Report Quarter

13 Nov 2015 ; 4 Feb2016 ; 17 Feb 2016 ; 28Jun 2016 ; 11 Nov 2016;15 Mar 2017 (informal) ;

2 Jun 2017; 31 August2017

24 Nov 2015; Informal toWB 4 & 17 Feb 2016; 21Juli 2016; 28 Nov 2016 ;15 Mar 2017 (informal) ;9 Jun 2017: 28 Sept 2017

14 Des 2016 (NOL) ; 19Feb 2016 ; 12 Juli 2016;

19 Des 2016 ; 18 Juli2017; WB file

6 HIV - AIDS Campaign Report - 1X 8 January 2016 15 March 2016 NN

12 Kambang - Indrapura Sumatera Barat 1 AMDAL Environmental Feasibility : 05 Feb 2014 ;Environmental permits : 5 Feb 2014 1X - 09 June 2014 08 August 2014

2 Monitoring of IntegrationAMDAL into Design - 1X 2 Dec 2015 NN NN

3 AMDAL Implementation Report(PIU to BLH) - each 6

month 1 March 2017 13 April 2017 17 April 2017

Page 120: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

1 2 3 5 6 7 8 9

Environmental Safeguard Date of Recomendation/Environmental Permits

No ofPackage Name of Link Province Sent to WBCTC Letters to PMUDurations WB NOL/Letters

4

4 RKPPL - 1X 27 Feb 2017 ; 8 May2017 (Rev RKPPL)

20 March 2017 ; 29 May2017 (Rev RKPPL)

5 April 2017 ; 18 Juli2017

5 RKPPL Implementation Report Quarter

15 Mar 2017 (informal); 2 Jun 2017; 31 August2017; 8 Nov 2017; 21Mei 2018; 14 Agustus

2018

15 Mar 2017 (informal) ;9 Jun 2017: 28 Sept 2017;

4 Des 2017; 19 Maret2018-informal; 29 Juni2018; 31 Agustus 2018

5 April 2017 ; 18 Juli2017; WB file ; 12 Jan2018 (ask to revisedreport); 4 Juli 2018

6 HIV - AIDS Campaign Report - 1X 29 Sept 2016 13 October 2016 NN

7 Improvement Base CampManagement

30 Januari 2018; 15 Feb2018 (infomal 13 Feb) ;26 Feb 2018 (informal21 feb); 6 March 2018;23 March 2018; 9 April2018; 15 Mei 2018; 7

Juni 2018

7 Februari 2018;informal 13 Feb 2018;infomal 21 Feb 2018;

informal 6 March 2018;informal 22 March 2018 ;10 April 2018-informal;16 Mei 2018-informal; 7

Juni 2018-informal

12 Feb 2018

13 Sp. Rukis - Tj. Kemuning Bengkulu 1 UKL & UPL Recommendation : 31 Jan 2012 (Link of Sp Rukis

Mana-Bts Kab Kaur & 4 Feb 2012 (Bts Kaur - TjKemuning)

1X - 09 June 2014 08 August 2014

2 Monitoring of IntegrationUKL&UPL into Design - 1X 6 Oct 2015 NN NN

3 UKL&UPL ImplementationReport (PIU to BLH) - each 6

month 28 Jun 2016; 31 August

2017 21 Juli 2016; '28 Sept

2017 22 Juli 2016; WB file

4 RKPPL - 1X 4 Nov 2015 24-Nov-15 14 Dec 2015/NOL

5 RKPPL Implementation Report Quarter

4 Feb 2016 ; 17 Feb2016 ; 28 Jun 2016 : 11

Nov 2016; 15 Maret2017 ; 2 Jun 2017: 31August 2017; 8 Nov

2017; 21 Mei 2018; 14Agustus 2018

Informal to WB 4 & 17Feb 2016 : 21 Juli 2016;

28 Nov 201615; Mar2017 (informal) ; 9 Jun2017: 28 Sept 2017; 4Des 2017; 19 Maret

2018; 29 Juni 2018;31Agustus 2018

19 Feb 2016 ; 22 Juli2016; 19 Des 2016 ; 18Juli 2017; WB file; 12

Jan 2018 (ask torevised report); 4 Juli

2018

6 HIV - AIDS Campaign Report - 1X 12 February 2016 15 March 2016 NN

7 Improvement Base CampManagement

30 Januari 2018; 6March 2018 ; 9 April2018; 15 Mei 2018; 7

Juni 2018

7 Februari 2018; 6 March2018; 10 April 2018-

informal; 16 Mei 2018-informal; 7 Juni 2018

12 Feb 2018

14 Painan - Kambang Sumatera Barat 1 AMDAL Environmental Feasibility : 05 Feb 2014 ;Environmental permits : 5 Feb 2014 1X - 09 June 2014 08 August 2014

2 Monitoring of IntegrationAMDAL into Design - 1X 2 Dec 2015 NN NN

3 AMDAL Implementation Report(PIU to BLH) - each 6

month 1 March 2017 13 April 2017 17 April 2017

4 RKPPL - 1X 10 Feb 2017 28 Feb 2017 17 March 2017

Page 121: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

1 2 3 5 6 7 8 9

Environmental Safeguard Date of Recomendation/Environmental Permits

No ofPackage Name of Link Province Sent to WBCTC Letters to PMUDurations WB NOL/Letters

4

5 RKPPL Implementation Report Quarter

15 Mar 2017 (informal); 2 Jun 2017; 31 August2017; 8 Nov 2017; 21Mei 2018; 14 Agustus

2018

15 Mar 2017 (informal) ;9 Jun 2017; 28 Sept 2017;

4 Des 2017; 19 Maret2018-informal; 29 Juni2018; 31 Agustus 2018

17 March 2017 ; 18Juli 2017; WB file ; 12

Jan 2018 (ask torevised report); 4 Juli

2018

6 HIV - AIDS Campaign Report - 1X 21 Des 2016 28 Des 2016 NN

7 Improvement Base CampManagement

30 Januari 2018; 15 Feb2018 (infomal 13 Feb) ;26 Feb 2018 (informal21 feb); 6 Macrh 2018;23 March 2018; 9 April2018; 15 Mei 2018; 7

Juni 2018

7 Februari 2018;informal 13 Feb 2018;infomal 21 Feb 2018;

informal 6 March 2018;22 March 2018; 10 April2018-informal; 16 Mei2018-informal; 7 Juni

2018-informal

12 Feb 2018

15 Sibolga - Bts. Tapsel Sumut 1 UKL & UPL Recommendation : 8 Dec 2011 1X 24 Sep 2013 30 Sep 2013 20 Nov 2013

2 Monitoring of IntegrationUKL&UPL into Design - 1X 11 Nov 2014 NN NN

3 UKL&UPL ImplementationReport (PIU to BLH) - each 6

month 28 Jun 2016; 31 August

2017 21 Juli 2016; '28 Sept

2017 22 Juli 2016; WB file

4 RKPPL - 1X 02 November 2016 14 November 2016 23 November 2016

5 RKPPL Implementation Report Quarter

28 Juni 2016 : 11 Nov2016; 15 Mar 2016

(informal) ; 2 Jun 2017;31 August 2017; 8 Nov2017; 21 Mei 2018; 14

Agustus 2018

21 Juli 2016; 28 Nov2016; 15 Mar 2017

(informal) ; 9 Jun 2017;28 Sept 2017; 4 Des

2017; 19 Maret 2018-informal; 29 Juni 2018;

31 Agustus 2018

22 Juli 2016; 19 Des2016 ; 18 Juli 2017; WBfile; 12 Jan 2018 (ask to

revised report); 4 Juli2018

6 HIV - AIDS Campaign Report - 1X 29 February 2016 15 March 2016 NN

7 Improvement Base CampManagement

30 Januari 2018; 15 Feb2018 (infomal 13 Feb) ;26 Feb 2018 (informal21 feb); 6 Macrh 2018;

9 April 2018; 15 Mei2018; 7 Juni 2018

7 Februari 2018;informal 13 Feb 2018;infomal 21 Feb 2018;

informal 6 March 2018;10 April 2018-informal;16 Mei 2018-informal; 7

Juni 2018-informal

12 Feb 2018

16 Sebelat-Ipuh Inc.Air Lalang & AirGunung Bridges Bengkulu 1 AMDAL Environmental permits : 3 April 2014 1X - 09 June 2014 08 August 2014

2 Monitoring of IntegrationAMDAL into Design - 1X 10 Dec 2014 NN NN

3 AMDAL Implementation Report(PIU to BLH) - each 6

month 31 August 2017 ; 08

November 2017 28 September 2017 WB file

4 RKPPL - 1X 2 June 2017 ; 15

September 2017 (RevRKPPL)

9 June 2017; 28 Sept2017

18 Juli 2017; 25 Okt2017 NOL RKPPL RV

Page 122: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

1 2 3 5 6 7 8 9

Environmental Safeguard Date of Recomendation/Environmental Permits

No ofPackage Name of Link Province Sent to WBCTC Letters to PMUDurations WB NOL/Letters

4

5 RKPPL Implementation Report Quarter

2 Jun 2017; 31 Agustus2017; 8 Nov 2017; 21Mei 2018; 14 Agustus

2018

9 Jun 2017; 28 Sept2017; 4 Des 2017; 19

Maret 2018-informal; 29Juni 2018; 31 Agustus

2018

18 Juli 2017; WB file;12 Jan 2018 (ask to

revised report); 4 Juli2018

6 HIV - AIDS Campaign Report - 1X 13 June 2017 10 Juli 2017 NN

7 Improvement Base CampManagement

26 Feb 2018 (informal22 Feb 2018); 6 March2018; 9 April 2018; 15Mei 2018; 7 Juni 2018

Informal 22 Feb 2018;Informal 6 March 2018;10 April 2018-informal;16 Mei 2018-informal; 7

Juni 2018-informal

17 Sp. Gunung Kemala-Pg. Tampak, IncWay Tauu Bridge Lampung 1 AMDAL Environmental Feasibility : 12 Oct 2012

Environmental permits: 21 Nov 2012 1X 24 Sep 2013 30 Sep 2013 20 Nov 2013

2 Monitoring of IntegrationAMDAL into Design - 1X 11 Nov 2014 NN NN

3 AMDAL Implementation Report(PIU to BLH) - each 6

month 28 Jun 2016; 31 August

2017

21 Juli 2016 ; 28 Sept2016 ; 20 Nov 2016; 28

Sept 2017 22 Juli 2016; WB file

4 RKPPL - 1X 26 April 2016 13 May 2016 30 Juni 2016

5 RKPPL Implementation Report Quarter

28 Juni 2016 : 11 Nov2016;15 Mar 2017

(informal) ; 2 Jun 2017;31 August 2017; 8 Nov

2017

21 Juli 2016; 28 Nov2016 ;15 Mar 2017

(informal) ; 9 Jun 2017;28 Sept 2017; 4 Des

2017; 19 Maret 2018-informal

22 Juli 2016; 19 Des2016 ; 18 Juli 2017; WBfile; 12 Jan 2018 (ask to

revised report)

6 HIV - AIDS Campaign Report - 1X 8 January 2016 15 March 2016 NN

18 Seblat - Ketahun (N.013.005 :Panjang 42,07km) Bengkulu

19 Lais- Bintunan Bengkulu 1 UKL & UPL Recommendation : 9 Nov 2011 1X 24 Sep 2013 30 Sep 2013 20 Nov 2013

2 Monitoring of IntegrationUKL&UPL into Design - 1X 6 Oct 2015 NN NN

3 UKL&UPL ImplementationReport (PIU to BLH) - each 3

month 28 Jun 2016 21 Juli 2016 ; 20 Nov2016 (informal) 22 Juli 2016

4 RKPPL - 1X 4 Nov 2015 24-Nov-15 14 Dec 2015/NOL

5 RKPPL Implementation Report Quarter 13 Nov 2015 ; 4 Feb

2016 ; 17 Feb 2016 ; 28Jun 2016 ; 11 Nov 2016

24 Nov 2015; Informal toWB 4 & 17 Feb 2016: 21Juli 2016; 28 Nov 2016

14 Des 2016 (NOL) ; 19Feb 2016 ; 22 Juli 2016;

19 Des 2016

6 HIV - AIDS Campaign Report - 1X 12 February 2016 15 March 2016 NN

20 Lubuk Alung - Sincin Sumatera Barat 1 UKL & UPL Recommendation : 27 Dec 2011 1X 24 Sep 2013 30 Sep 2013 20 Nov 2013

2 Monitoring of IntegrationUKL&UPL into Design - 1X 29 Oct 2015 NN NN

3 UKL&UPL ImplementationReport (PIU to BLH) - each 6

month 2 June 2017 ; 8November 2017 9 June 2017; 4 Des 2017 18 Juli 2017; 12 Jan

2018

4 RKPPL - 1X 10 Feb 2017 28 Feb 2017 17 March 2017

Page 123: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

1 2 3 5 6 7 8 9

Environmental Safeguard Date of Recomendation/Environmental Permits

No ofPackage Name of Link Province Sent to WBCTC Letters to PMUDurations WB NOL/Letters

4

5 RKPPL Implementation Report Quarter

15 Mar 2017 (informal);2 Juni 2017; 31 August2017; 8 Nov 2017; 21

Mei 2018

15 Mar 2017 (informal);9 Juni 2017; 28 Sept2017; 4 Des 2017; 19

Maret 2018-Informal; 29Juni 2018

17 March 2017 ; 18Juli 2017; WB file; 12

Jan 2018 (ask torevised report); 4 Juli

2018 6 HIV - AIDS Campaign Report - 1X 6 April 2017 13 April 2017 NN

7 Improvement Base CampManagement

15 Feb 2018 (informal13 Feb 2018); 6 March

2018; 23 March 2018; 9April 2018;15 Mei 2018;

7 Juni 2018

informal 13 Feb 2018;informal 6 March 2018;22 Mar 2018 ; 10 April-informal ; 16 Mei 2018-Informal; 7 Juni 2018-

informal;

21 Lubuk Alung - Kuraitaji Sumatera Barat 1 UKL & UPL Recommendation : 27 Dec 2011 1X 24 Sep 2013 30 Sep 2013 20 Nov 2013

2 Monitoring of IntegrationUKL&UPL into Design - 1X 29 Oct 2015 NN NN

3 UKL&UPL ImplementationReport (PIU to BLH) - each 6

month 2 June 2017 ; 8November 2017 9 June 2017; 4 Des 2017 18 Juli 2017; 12 Jan

2018

4 RKPPL - 1X 27 Feb 2017 ; 8 May2017 (Rev RKPPL)

20 March 2017 ; 29 May2017 (Rev RKPPL)

5 April 2017 ; 18 Juli2017

5 RKPPL Implementation Report Quarter

15 Mar 2017 (informal); 2 Juni 2017; 31 August

2017; 8 Nov 2017; 21Mei 2018

15 Mar 2017 (informal) ;9 Juni 2017; 28 Sept2017; 4 Des 2017; 19

Maret 2018-informal; 29Juni 2018

5 April 2017 ; 18 Juli2017; WB file; 12 Jan2018 (ask to revisedreport); 4 Juli 2018

6 HIV - AIDS Campaign Report - 1X 6 April 2017 13 April 2017 NN

7 Improvement Base CampManagement

15 Feb 2018 (informal13 Feb 2018); 6 march

2018; 23 March 2018; 9April 2018; 15 Mei2018; 7 Juni 2018

informal 13 Feb 2018;informal 6 March 2018;

informal 22 March 2018 ;10 Mar 2018-informal; 16Mei 2018-informal; 7 Juni

2018-infomal

Keterangan :

NY : Not Yet

NN : Not Need

UP : Under Process

incl. 1 Document Studi Amdal

incl. 1 Document Studi Amdal

NYS: Not Yet Started incl. 1 Document Studi Amdal

Page 124: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

Appendix A

Overall Loan Progress

Page 125: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Estimated Contractor(s) or Total Est. Budget

Starting Completion Consultant(s) Man-Month WB + GOI Remarks

Date Date Name (Excl. the (PIP) Original Physical Man-Month Physical Man-Month Physical Man-Month

Supp. Staff) (USD, Excl.VAT) In IDR In USD Amendment No. 1 InIDR

Amendment No. 2 InIDR

Amendment No. 3 InIDR

Amendment No. 4 InIDR

Amendment No. 5 InIDR

Amendment No. 6 InIDR

Amendment No. 7 InIDR

Amendment No. 8 InIDR ( % ) ( MM ) ( % ) ( MM ) ( % ) ( MM )

1 Betterment and Capacity 308.730.000,00 $222.678.368,65Expansion of NationalRoads

1.A AWP-1 ICB DGH 81.630.000,00 $57.821.551,951. Krui-Biha 08-Jan-14 10-Jan-16 PT. Jaya Konstruksi 134.909.211.000,00Rp $11.757.337,74 154.073.015.000Rp 154.073.015.000Rp 140.255.020.000Rp 149.193.782.000Rp 100% 100% 0,00% FHO2. Pd. Sawah-Sp. Empat 06-Jan-14 19-Apr-16 PT.Jaya Konstruksi 197.936.699.896,00Rp $17.250.183,32 226.713.217.000Rp 249.348.931.000Rp 247.572.130.000Rp 100% 100% 0,00% Completed3. Manggopoh-Pd. Sawah 06-Jan-14 20-Mar-16 PT. Jaya Konstruksi 143.688.963.435,00Rp $12.522.493,13 165.157.772.000Rp 183.940.872.000Rp 183.452.685.000Rp 100% 100% 0,00% Completed4. Ipuh-Bantal 10-Jan-14 11-Apr-16 PT. Waskita Karya 186.936.750.000,00Rp $16.291.537,76 196.438.084.000Rp 194.902.179.000Rp 212.290.705.872Rp 100% 100% 0,00% Completed

1.B AWP-2 and AWP-3 ICB &NCB DGH 227.100.000,00 $164.856.816,70

5. Sp. Rampa - Poriaha 18-Jun-15 30-Sep-17 PT. Nusa KonstruksiEnjiniring Tbk 107.321.260.000,00Rp $8.084.464,03 130.143.384.830Rp 100% 95% -4,72% Revised BOQ

6. Ps Pedati - Kerkap 11-Mar-15 28-Jan-17 PT. Waskita Karya Tbk 86.517.470.000,00Rp $6.641.396,33 118.444.156.000Rp 100% 100% 0,00% Completed7. Indrapura - Tapan 10-Des-15 10-Nov-17 PT. Adhi Karya 129.699.900.000,00Rp $9.350.065,79 100% 100% 0,00% Completed8. Bts. Kt Pariaman - Manggopoh 23-Mar-16 31-Des-17 PT. PP/PT. Statika 355.500.000.000,00Rp $25.627.995,00 378.042.000.000Rp 100% 100% 0,00% Completed9. R. Tijang - Kt. Agung Cancelled10. Sp Empat - Sp Air Balam Cancelled

11. Bantal - Mukomuko 23-Feb-15 26-Mei-17 PT. Hutama Karya - PT.DMT, JO 228.899.717.000,00Rp $18.765.198,80 262.611.303.000Rp 263.656.603.000Rp 100% 100% 0,00% Completed

12. Kambang - Indrapura 23-Mei-16 31-Des-17 PT. Lancarjaya/PT. CahayaT.A 358.650.400.000,00Rp $25.855.107,34 100% 80,28% -19,72% Ongoing Construstion

13. Sp. Rukis - Tj. Kemuning 22-Jul-15 25-Okt-17 PT. Waskita Karya 292.700.000.000,00Rp $23.454.051,00 305.886.100.000Rp 100% 100% 0,00% Completed14. Painan -Kambang 03-Agu-16 31-Des-17 KSO Yasa - Conbloc 214.327.429.680,00Rp $16.286.741,38 100% 81,02% -18,98% Ongoing Construction15. Sibolga - Bts Tap Sel 20-Nov-15 31-Des-17 PT. PP 260.100.000.000,00Rp $19.954.872,00 100% 80,50% -19,50% Revised BOQ16. Seblat - Ipuh 08-Nov-16 30-Jul-18 KSO Yasa - Conbloc 211.374.500.000,00Rp 100% 89,50% -10,50% Ongoing Construction17. Sp. Gunung Kemala - Pg.Tampak 04-Sep-15 12-Nov-17 PT. Jaya Konstruksi 199.551.233.000,00Rp $16.335.263,93 223.922.283.000Rp 211.712.283.000Rp 100% 100% 0,00% Completed

18. Mukomuko - Bts. Sumbar Cancelled19. Lais- Bintunan 11-Mar-15 30-Jun-16 PT. Rodatekindo Purajaya Rp 33.689.452.000,00 $2.586.125,12 Rp 44.419.760.000 100% 100% 0,00% Completed20. Lubuk Alung - Sicincin 01-Sep-16 31-Des-17 PT. Nindya Karya Rp 113.818.300.000,00 $8.578.485,27 100% 100% 0,00% Completed21. Lubuk Alung -Kuraitaji 01-Sep-16 31-Des-17 PT. Multi Structure Rp 126.301.900.000,00 $9.519.374,20 100% 55,79% -44,21% Contract to be Terminated

1.C Contingency - DGH 6.170.000,00

2 Implementation Support 16.000.000,00

2.A Core Team Consultants (CTC) QCBS DGH 06-Nov-12 31-Des-17 PT. Perentjana Djaja 556 5.000.000,00 $1.276.700,00 $1.315.925,00 $1.371.925,00 $1.339.925,00 $1.339.925,00 $1.450.367,33 $1.653.866,67 $1.679.443,67 212.95 187.95 25.00 Supporting PMU. Joint Venture with Rp21.415.400.000,00 Rp22.426.175.000 Rp22.458.676.500 Rp23.934.595.000 Rp37.161.972.299 Rp37.768.533.132 Rp44.230.796.132 Rp46.097.547.554 Yongma Engineering Co.Ltd. Or US$ equivalent total : 25-Okt-13 03-Sep-14 30-Nov-15 04-Mar-16 10-Apr-17 08-Des-17 30-Apr-18 PT. Epadascon Permata $3.512.681,91 $3.641.077,48

2.B Design & Superv. Consultants QCBS DGH 19-Jun-13 31-Des-17 Renardet S.A. 1.068 10.000.000,00 $820.600,00 $1.042.900,00 $770.940,00 $965.940,00 42.33 36.33 -6.00 construction supervision.

Joint Venture with Rp51.818.705.000,00 Rp55.037.399 Rp54.521.056 Rp64.346.684.915 PT Cipta Strada Or US$ equivalent total : PT. Daya Creasi Mitrayasa $6.465.729,72 PT. Seecons PT. Yodya Karya

2.C

2.D Incremental Operating Cost Varies PMU 1.000.000,00Including Technical Audits

4 Contingency for Disaster DGH -Risk Response

5 Unallocated DGH 18.100.000,00

Total 342.830.000,00 232.656.780,28

Development of SlopeStabilization, Design andManagement

31 August 2018

PROGRESS

Respon-sibility

Total ( WB + GOI )

Contract Value

Revised (in 000)

Appendix - AOVERALL PROGRESS STATUS

Description

WESTERN INDONESIA NATIONAL ROADS IMPROVEMENT PROJECT (WINRIP)IBRD LOAN No. 8043-ID

Proc.Metho

dCategory

Planned Actual Balance

Page 126: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

Appendix B

Road Safety Audit Progress

Page 127: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Appendix B. Road Safety Audit Progresss (August 2018)

Old (2004) New (2009) Site VisitSubmission of

ReportSite Visit

Submission ofReport

Site VisitSubmission of

Report1. No Road Safety Audit at Design Stage.

2. RSA at Construction Stage/Monitoring of Traffic Mgmt & Safety by CTC, Dec, 2014

3. RSA at PHO stage by CTC, February, 2016

Date 13-Nov-14 29-Des-14 13-Nov-14 29-Des-14 11-Feb-16 22-Feb-161. No Road Safety Audit at Design Stage.

2. RSA at Construction Stage/Monitoring of Traffic Mgmt & Safety by CTC, Dec, 2014

3. RSA at PHO stage by CTC, April, 2016

Date 09-Okt-14 05-Nov-14 09-Okt-14 05-Nov-14 06-Apr-16 12-Apr-161. No Road Safety Audit at Design Stage.

2. RSA at Construction Stage/Monitoring of Traffic Mgmt & Safety by CTC, Dec, 2014

3. RSA at PHO stage by CTC, March, 2016

Date 09-Okt-14 05-Nov-14 09-Okt-14 05-Nov-14 17-Mar-16 23-Mar-161. No Road Safety Audit at Design Stage.

2. RSA at Construction Stage/Monitoring of Traffic Mgmt & Safety by CTC, Dec, 2014

3. RSA at PHO stage by CTC, April, 2016

Date 13-Nov-14 29-Des-14 13-Nov-14 29-Des-14 14-Apr-16 26-Apr-161. Technical Advisory Report by International RSA CTC, Sept 2013

2. RSA at PHO stage by CTC, March, 2018

Date 08-May-13 17-Sep-13 28-Feb-18 26-Mar-181. Technical Review & RSA at Design Stage done by International RSA CTC

2. RSA at Construction Stage/Monitoring of Traffic Mgmt & Safety by CTC, Sep, 2015

3. RSA at PHO stage by CTC, November, 2016

Date 18-Jul-13 17-Sep-13 25-Agu-15 08-Sep-15 18-Nov-16 19-Des-161. Technical Advisory Report by International RSA CTC, Sept 2013

27-Sep-13 2. Road Safety Audit by Dit. EA & RS, May 2014

3. RSA at Construction stage by CTC, December, 2016

Date Apr-14 Mei-14 08-Des-16 22-Des-16 27-Des-17 05-Jan-18 4. RSA at PHO stage by CTC, January, 2018

1. Technical Advisory Report by CTC, Sept 2013

27-Sep-13 2. Road Safety Audit by Dit. EA & RS, May 2014

3. RSA at Construction stage by CTC, August 2017

Date Apr-14 Mei-14 26-Jul-17 25-Agu-17 07-Des-17 11-Des-17 4. RSA at PHO stage by CTC, December 2017

1. Technical Review & RSA at Design Stage by International RSA CTC , Jul, 2013

2. RSA at Construction Stage/Monitoring of Traffic Mgmt & Safety by CTC, Dec, 2015

3. RSA at PHO stage by CTC, April 2017

Date 18-Jul-13 18-Jul-13 17-Des-15 29-Des-15 11-Apr-171. Technical Advisory Report by International RSA CTC, Sept 2013

27-Sep-13 2. Road Safety Audit by Dit. EA & RS, May 2014

3. RSA at Construction stage by CTC, January 2018

Date Apr-14 Mei-14 17-Jan-18 06-Feb-18 28-Agu-181. Technical Advisory Report by International RSA CTC, Sept 2013

2. RSA at Construction Stage/Monitoring of Traffic Mgmt & Safety by CTC, Mar, 2017

3. RSA at PHO stage by CTC, April, 2018

Date 18-Jul-13 18-Jul-13 23-Mar-17 03-Apr-17 05-Apr-18 20-Apr-181. RSA DED Report by CTC, June, 2015

2. RSA at Construction stage by CTC, January 2018

Date 15-Apr-15 15-Jun-15 16-Jan-18 30-Jan-18 30-Agu-181. Technical Advisory Report by International RSA CTC, Sept 2013

2. RSA at Construction Stage/Monitoring of Traffic Mgmt & Safety by CTC, Aug, 2017

Date08-May-1321-Aug-13

23-Sep-13 28-Agu-17 25-Sep-17 24-Jul-18

1. RSA DED Report by CTC, Sept, 2014

2. RSA at Construction stage by CTC, January 2018

Date 14-Agu-14 01-Sep-14 29-Jan-18 15-Feb-18 26-Jul-181. No Road Safety Audit at Design Stage.

2. RSA at Construction Stage/Monitoring of Traffic Mgmt & Safety by CTC, May, 2017

3. RSA at PHO stage by CTC, October, 2017

EstimatedCost /

Excl.VAT(mil. RP)

Road Safety AuditTotal Process

(%)Remarks

StatusDesign Stage Construction Stage PHO StageNo

PkgNo.

Name of Sub-projectLink No

2 #2 Padangsawah - Simpangempat 06.047.2 06.021.0

1 #1 Biha - Krui 17.053.0 17.027.0

228.772Process

100%

163.535Process

100%

4 #4 Ipuh - Bantal 13.051.1 13.003

3 #3 Manggopoh -Padangsawah 06.047.1 06.022.0

247.105Process

100%

167.678Process

100%

6 #6 PS.Pedati - Kerkap 13.010.0 13.009.0

5 #5 Sp.Rampa – Poriaha xx.xxx.x 03.075.0

92.127Process

100%

152.870Process

100%

No RSA at Const. Stage

175.812Process

100%

8 #8 Bts.Pariaman – Manggopoh 06.24.0 06.23.0

7 #7 Indrapura – Tapan 06.019.0 06.34.0

374.647Process

100%

10 #12 Kambang – Indrapura 06.17.2 06.033.0

9 #11 Bantal - Mukomuko 13.015.2 13.002.0

438.675Process

83%

262.611Process

100%

13 #15 Sibolga – Bts TapSel 03.016.1 03.044.0

316.304,8Process

100%

12 #14 Painan – Kambang 06.017.1 06.032.0

11 #13 SP.Rukis - TJ.Kemuning 13.006.0 13.021.0

376.479Process

83%

118.993Process

83%

15 #17 Sp.Gng Kemala–Pg.Tampak 17.061.1 17.025.0

14 #16 Seblat – Ipuh 13.010.0 13.004.0

255.269Process

100%

110.237Process

83%

Page 128: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Old (2004) New (2009) Site VisitSubmission of

ReportSite Visit

Submission ofReport

Site VisitSubmission of

Report

EstimatedCost /

Excl.VAT(mil. RP)

Road Safety AuditTotal Process

(%)Remarks

StatusDesign Stage Construction Stage PHO StageNo

PkgNo.

Name of Sub-projectLink No

Date 17-18 May 2017 18-Jul-17 03-Okt-17 30-Nov-17

1. Technical Advisory Report by International RSA CTC, Sept 2013

2. RSA at Construction Stage/Monitoring of Traffic Mgmt & Safety by CTC, Sep, 2015

3. RSA at PHO stage by CTC, May, 2016

Date 18-Jul-13 17-Sep-13 25-Agu-15 08-Sep-15 19-Mei-16 24-Mei-161. RSA DED Report by CTC, June, 2015

2. RSA at Construction Stage/Monitoring of Traffic Mgmt & Safety by CTC, Jul, 2017

3. RSA at PHO stage by CTC, January, 2018

Date 15-Apr-15 15-Jun-15 27-Jul-15 25-Agu-15 15-Jan-18 24-Jan-181. RSA DED Report by CTC, June, 2015

2. RSA at Construction Stage/Monitoring of Traffic Mgmt & Safety by CTC, Jul, 2017

Date 15-Apr-15 15-Jun-15 25-Jul-15 25-Agu-15

Notes :Road Safety Engineering Review by CTC

Road Safety Audit by International RSA CTC

Road Safety Audit by Dit. EA & RS DGH

Road Safety Audit by CTC

No Road Safety Audit

15 #17 Sp.Gng Kemala–Pg.Tampak 17.061.1 17.025.0 255.269 100%

No RSA at DED. Stage

18 #21 Lubuk Alung - Kuraitaji 06.027.0 06.025.0

35.886Process

100%

17 #20 Lubuk Alung – Sicincin 06.009.1 06.041.0

16 #19 Lais - Bintuan 13.009.1 13.007.0

65.788Process

66%

54.557Process

100%

TERMINATION

Page 129: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

Appendix C

Financial Progress

Page 130: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

Appendix C Financial ProgressThe table below shows total expenditure to date measured in the terms of World BankCommitment.

DatePercentage

Completion oftime

WBExpenditureCommitment

Percentage ofAvailable

ExpenditureSource

31/03/2012 1.45% - - -30/04/2012 2.90% - - -31/05/2012 4.35% - - -30/06/2012 5.80% - - -31/07/2012 7.25% - - -30/08/2012 8.70% - - -30/09/2012 10.15% - - -31/10/2012 11.60% - - -30/11/2012 13.05% - - -31/12/2012 14.50% 800,000 0.32% Actual31/01/2013 15.95% 800,000 0.32% Actual28/02/2013 17.40% 800,000 0.32% Actual31/03/2013 18.85% 2,207,915 0.88% Actual30/04/2013 20.30% 2,207,915 0.88% Actual31/05/2013 21.75% 2,207,915 0.88% Actual30/06/2013 23.20% 2,207,915 0.88% Actual31/07/2013 24.65% 2,207,915 0.88% Actual31/08/2013 26.10% 2,207,915 0.88% Actual30/09/2013 27.55% 2,207,915 0.88% Actual31/10/2013 29.00% 2,207,915 0.88% Actual30/11/2013 30.45% 2,207,915 0.88% Actual31/12/2013 31.90% 2,207,915 0.88% Actual31/01/2014 33.35% 4,940,115 1.98% Actual28/02/2014 34.80% 4,940,115 1.98% Actual31/03/2014 36.25% 4,966,535 1.99% Actual30/04/2014 37.70% 4,966,535 1.99% Actual31/05/2013 39.15% 6,109,480 2.44% Actual30/06/2014 40.60% 6,263,610 2.51% Actual31/07/2014 42.05% 6,470,288 2.59% Actual31/08/2014 43.50% 6,470,288 2.59% Actual30/09/2014 44.95% 6,681,304 2.67% Actual31/10/2012 46.40% 6,991,757 2.80% Actual30/11/2014 47.85% 7,323,303 2.93% Actual31/12/2014 49.30% 11,533,045 4.61% Actual31/01/2015 50.75% 11,533,045 4.61% Actual28/02/2015 52.20% 12,794,201

4.61%Actual4.61%Actual

5.12% Actual31/03/2015 53.65% 14,918,776 5.97% Actual30/04/2015 55.10% 18,424,843 7.37% Actual

Page 131: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

DatePercentage

Completion oftime

WBExpenditureCommitment

Percentage ofAvailable

ExpenditureSource

31/05/2015 56.55% 21,646,890 8.66% Actual30/06/2015 58.00% 23,691,573 9.48% Actual31/07/2015 59.45% 27,426,670

9.48%10.97% Actual

31/08/2015 60.90% 27,861,670 11.14% Actual30/09/2015 62.35% 31,214,254 12.49% Actual31/10/2015 63.80% 33,538,544 13.42% Actual30/11/2015 65.25% 37,740,899 15.10% Actual31/12/2015 66.70% 48,269,952 19.31% Actual31/01/2016 68.15% 48,845,535 19.54% Actual28/02/2016 69.60% 50,144,535 20.06% Actual31/03/2016 71.05% 52,938,748 21.18% Actual30/04/2016 72.50% 58,007,328 23.20% Actual31/05/2016 73.95% 61,427,937 24.57% Actual30/06/2016 75.40% 65,009,653 26.00% Actual31/07/2016 76.85% 70,619,401 28.25% Actual31/08/2016 78.30% 70,846,499 28.34% Actual30/09/2016 79.75% 74,387,379 29.75% Actual31/10/2016 81.20% 78,314,016 31.33% Actual30/11/2016 82.65% 81,725,868 32.69% Actual31/12/2016 84.10% 101,180,236 40.47% Actual31/01/2017 85.55% 102,340,497 40.94% Actual28/02/2017 87.00% 102,921,579 41.17% Actual31/03/2017 88.45% 105,584,628 42.23% Actual30/04/2017 89.90% 109,100,923 43.64% Actual31/05/2017 91.35% 112,475,095 44.99% Actual30/06/2017 92.80% 119.094.262 47.64% Actual31/07/2017 94.25% 124,057,518 49.62% Actual31/08/2017 95.70% 128.416.537 51.37% Actual30/09/2017 97.15% 132,776,084 53.11% Actual31/10/2017 98.60% 136.337.674 54.54% Actual30/11/2017 99.05% 142,023,219 56.81% Actual31/12/2017 100.00% 156,090,198 62.44% Actual

LOAN EXTENSION TIME UP TO DECEMBER 201831/01/2018 86.56% 157,742,185 63.10% Actual28/02/2018 87.69% 158,678,166 63.47% Actual31/03/2018 88.93% 160,428,518 64.17% Actual30/04/2018 90.14% 161,174,355 64.47% Actual31/05/2018 91.39% 163,525,763 65.41% Actual30/06/2018 92.60% 163,525,763 65.41% Actual31/07/2018 93.84% 174.283.884 69.71% Actual31/08/2018 95.09% 175,701,077 70.28% Actual30/09/2018 96.30%31/10/2018 97.55%30/11/2018 98.75%31/12/2018 100.00%

Page 132: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

Appendix D

Quality Assurance Progress

Page 133: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

Appendix D: Quality Assurance Progress

No Activities has been doneStatus/conditionDate of Finish/

completed1. Make site visit report for maintenance period package 07 (Indrapura

– Tapan) , West Sumatera ProvinceAugust 01 to 03,

2018

2. leave August 06, 2018

3. Make site visit report for package 12 (Kambang– Indrapura) , WestSumatera Province

August 07 to 10,2018.

4. Make site visit report for package 14 (Painan– Kambang) , WestSumatera Province.

August 13 to 15,2018.

5. Prepare draft revision PMM edition 3 and internal meeting CTCWINRIP

August 16, 2018.

6. Make request for site visit to package 12 and package 14 and preparedraft revision PMM edition 3

August 20 , 2018.

7. Prepare draft revision PMM edition 3. August 21, 2018.

8. Holiday August 22, 2018.

9. Site visit to package 14 (Painan – Kambang) and package 12(Kambang – Indrapura) Padang, West Sumatera Province

August 23 to 25,2018.

10. Site visit to package 11 (Bantal– Mukomuko) before FHO, BengkuluProvince.

August 27 to 01September, 2018.

Page 134: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

Appendix E

Environmental Progress and Social Progress

Page 135: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Result Comments Budget Alocated,Year StatusTHE WB Approval (A=Studi

LARAP ;B=Implementation LARAP

AWP - 1A. NOL LARAP 04 Jan2013 ; B. NOL Mon Report (MR)18 April 2013, Rev 26 June2013.

2 Padang Sawah - Sp Empat Sumatera Barat Total PAP 451 . No Land affected . Aset affected:building 149 unit = 2.110 M2 ; Fence 2 unit = 341.8 M ;Kiosks BBM: 25 unit; Trees: 873 rod ; Mosque: 2 unit

A. NOL LARAP 13 Jan 2013;

2a Including Air Gadang Bridge Sumatera Barat Total PAP 15. Land affected 2,110 M2 ; Aset affected:building 6 unit = 410 M2 ; Trees 72 rod.

B. NOL MR-1: 19 July2013, MR-2:12 Feb 2015

A. NOL LARAP 04 Jan 2013

B. NOL MR-1: 26 June2013, MR-2: 5 Mar 2014,MR-3: 23 Jun 2014, MR-4:12 Feb 2015, MR-5: 17 Mar2015.

A. NOL LARAP 10 Dec 2012

B.NOL MR-1: 6 Jan 2014,MR-2: 5 Mar 2014, MR-3:12 Feb 2015

AWP - 2A. NOL LARAP 16 Sept2013, and approvalrevision the report 20March 2017;

B= Not Yet

A. NOL LARAP 20November 2013;

B: NOL MR-1: 23 Mar2015. NOL MR-2: 26 Nov2015NOL Larap: Oct 14, 2014

B: NOL WB MonitoringReport-1 (276 PAP) onMarch 8, 2016. MonitoringReport-2 (207 PAP) onAugust 18, 2016.Monitoring Report-3 (89PAP) on Nov 12, 2016,Monitoring Report-4 (61PAP) on Jan 16, 2017,Monitoring Report-5 (20PAP) on June, 2017

A. NOL LARAP 12 Sep 2014;

SOCIAL STATUS & PROGRESS FOR WINRIP, IBRD LOAN NO.8043-ID

SimpleLARAP andAdditional

LARAP

Complete

LARAP Total PAP are change from 227 PAP becomes 261 PAP.261 PAP has received compensation from The LocalGovernment as : Affected Assets: house building =307,05 M2; terace = 672,84M2; fence = 503,85M ;foundation = 8,9 m; pavement = 2,632,01M2; Trees = 82rod, tomb = 7 unit

Rp.286.743.000.APBN, Satker PJN I,Bengkulu, 2013

Complete

1 Krui - Bha

Appendix E : Progress of Social Safeguard Studies on WINRIPas August 31, 2018

Lampung

Complete Ipuh- Bantal4 Bengkulu

PPK/Satker PJN II Lampung has to submit the result of the landcerticification to PMU/WB

Manggopoh - Padang Sawah3 Sumatera Barat

No

Total PAP 1.338 . No affected land . Aset affected:building 115 unit = 668,33 M2; Culvert 661,05 m;concrete & foundations 1.421,60M3 ; Soil embankment5.564,21 M3; Trees 5.324 rod

Rp. 1.147.700.000APBD Prov Sumbar,Dinas PU, 2012/2013;4.9 M from APBD2014

Complete Complete

LARAP Total PAP 2.815 in 21 Pekon. Land affected 28.763,12M2 ; Aset affected : building 882,13 M2; Fence 2.445,41M ; Trees 653 rod ; paddy field 25 plots ; Social & PablicFacilities

CompleteRp.2.340.600.000APBD Prov Sumbar,Dinas PU, 2012

6 Ps Pedati - Kerkap Bengkulu LARAP Total PAP = 637. Affected land = 3,625 M2. Terrace =2,925 M2 ; Fence = 4,169 M, pavement = 4399 m2

RP. 8.049.290.000APBN, Satker PJN I,

Bengkulu, 2014

Complete, certification process for 72 plots

LARAP

LARAP

Sumatera Utara Sp. Rampa - Poriaha5 Rp.2.700.000.000APBN, Satker PJN II,

Sumut, 2017

(1). Up to the end August 2018, the remaining of 7from total 92 Aps already paid by Satker.(2). 6 Aps already relocated to permanent houses

For certification process of 72 Aps is under budgeting allocation onRevision-2 DIPA 2018

Satker conducted design change on the land that be occupied 4 affectedpersons which can not paid by Satker PJN II West Sumatera.

8 Bts. Kota Pariaman - Manggopoh Sumatera Barat LARAP Total PAP: 2,339 change from original 1,282. Partillyaffected building ( houses an kiosks) = 8,352 M2 :Affected fence = 3,673 m : Partially affected otherbuilding (terrace, decker and floors) = 8,771 M2 andtrees = 7,863.

For the remaining ofAPS: Rp 1.5 Billion onFY 2017

complete

7 Indrapura - Tapan (1 Doc Amdal) Sumatera Barat

(1) No more issue. (2) Total PAP = 2.339;Compensated = 2.339; Percent Complete = 100%.

CompleteRp. 5.172.349.955APBN, Satker PJN IILampung, 2011 - 2012

Remedial Action

Approval Status by The World BankSocial Screening

ProvincesLoan Package Name

LARAP For the remaining ofAPs: Rp 0,5 Billion.APBN 2017

Total PAP 878 change original 1,193. Partilly affectedbuilding ( houses an kiosks) = 4,013 M2 : Affectedfence = 19,206 m : Partially affected other building(terrace, decker and floors) = 9,401 M2, and trees =3,290.

B: NOL WB for theMonitoring Report-1 (840Aps) on March 8, 2016.Monitoring Report-2 (926Aps) on May 12, 2016,Monitoring Report-3 (440Aps) on Jan 6, 2017.

(1) No more issue. (2) Total PAP = 878; Compensated= 878; Percent Complete = 100%.

Complete(1) Revision of the Additional LARAP documents(consist 92 Aps) signed by Satker II North SumateraProvince(2) 6 APs has to relocated.

Page 136: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Result Comments Budget Alocated,Year StatusTHE WB Approval (A=Studi

LARAP ;B=Implementation LARAP

No Remedial Action

Approval Status by The World BankSocial Screening

ProvincesLoan Package Name

A. -

A. NOL LARAP 12 Sep 2014;

B: NOL WB for theMonitoring Report-1 onMarch 8, 2016

A. NOL LARAP 20November 2013;

B: NOL WB-1: 2 Dec 2014,NOL WB-2: 12 Feb 2015.NOL WB-3: 26 Nov 2016.NOL WB-4: 28 Oct 2016

NOL Larap: Oct 14, 2014

A. NOL LARAP 20November 2013;B: NOL WB-1: 18 Aug 2015,NOL WB-2: 13 Oct 2015,NOL WB-4: 14 Oct 2016,NOL WB-5: 18 Nov 2016,NOL WB-6: 20 Mar 2017

AWP - 3A. NOL LARAP 19December 2014;

A. NOL LARAP 28 October2013 and NOL revise 05Feb 2014;

B: NOL WB-1: 16 Nov 2015.NOL WB-2: 8 Mar 2016.NOL WB-3: 15 Mar 2016.NOL WB-4: 19 May 2016.NOL WB-5: 18 Aug 2016.NOL WB-6: 16 Nov 2015 onJan 26, 2017, NOL WB-7:16 Nov 2015 on July 14,2017,

Seblat - Ipuh including (1 Amdal) A. NOL LARAP 20November 2013; NOLUpdate LARAP on Jun 7,2016

Satker conducted design change on the land that be occupied 57affected persons which can not paid by Satker

(1). Compensation for the remaing of 50 of the total3.040 APs already paid by Satker. (2). Certification foraffected land (382 plots) not yet be resolved byproject

No more issue, LARAP fully completed.

LARAP

LARAP Total PAP: 3.040 change 2.917 change from original2,564 . Affected land = 88,852 M2. Aset affected :building 111 unit = 2.196 M2 ; Fence 127 unit = 1.575 M; Trees 363 rod ; electricity pole 25 unit

Total PAP 1.820 . Land affected 1.531 plot = 45,831M2.Aset affected : building 340 nit = 3.399 M2 ; Fence 12unit = 1.563 M ; Trees 385 rod, Terrace = 991,607 M2

For the remaining ofAPs: Rp 9 Billion on Fy2017

(1) No more issue, LARAP fully completed, and theremaining of 17 Aps reject the appraisal value. (2). Theremainig of 18 from total 1.820 PAPs alreadycompensated by Satker. (3). Certification for affectedland (321 plots) not yet be resolved by project

16 Bengkulu Total PAP 259 changed from original 316. No affectedland, Affected assets: building= 658 M2 ; Terrace= 98;Fence= 232 M ; Trees 33 rod

Complete

LARAP is under preparation by Balai III Palembang.This package was changed to Bengkunat - Biha

B: NOL MR_1 (126) on Aug1, 2016. NOL MR_2 (62) onNov 14, 2016, NOL MR_3(220) on March 20, 2017,NOL MR_4 (59) on Nov 14,2016, NOL MR_5 (402) onJuly 14, 2017,

B: NOL MR_1 (216) onJune 7, 2016. NOL MR_2(60) on Nov 14, 2016. NOLMR-3 (88) on Feb 13, 2017,NOL MR-4 (265) on June,2017,

9 Rantau Tijang - Kota Agung / Replace toBengkunat - Biha (already completed byAMDAL)

Lampung

(1) No more issue. (2) Total PAP = 2.339;Compensated = 2.339; Percent Complete = 100%.

10 Sp Empat - Sp Air Balam Sumatera Barat LARAP Total PAP 2059 change from original 1,514. Partillyaffected building ( houses an kiosks) = 11,523 M2 :Affected fence = 2,613 m : Partially affected otherbuilding (terrace, decker and floors) = 11,538 M2 andtrees = 4,369

Rp 14.02 Billion. APBDProv Sumbar, DinasPU,

a) Total PAPs 2.915, and already compensated 1.725.b) PPK/Satker PJN I West Sumatera and LocalGovernment is under payment process for theremaining PAP.

11 Bantal - Mukomuko (1 Paket doc AMDAL) Bengkulu LARAP RP. 8.237.443.000APBN Satker PJN I,Bengkulu, 2014

No more issue, LARAP fully completedTotal PAP 243 (updated) . No affected land. Housebuilding = 261.7 M2; kiosks = 147.7 m2, terrace = 412.9m2, Fence = 249 M ; Trees= 36 rod, foundation = 17.2m2, retaining wall = 35.1 m, pavement = 2,937 m2

12 Kambang - Indrapura (1 Doc Amdal) Sumatera Barat LARAP Total PAP 2.873 (update). Partilly affected building (houses an kiosks) = 2,057 M2 : Affected fence =32,741m : Partially affected other building (terrace,decker and floors) = 17,144 M2 and trees = 3,225

For the remaining ofAPs: Rp 16.0 Billion onFY 2017

No more issue, LARAP fully completed.

13 Sp Rukis - Tj Kemuning Bengkulu For the remaining ofAPs: FY 2017: 4.5Billion

LARAP

14 Painan -Kambang (1 doc Amdal) Sumatera Barat SimpleLARAP

Total PAP 2.242. Partilly affected building ( houses ankiosks) = 10,474 M2 : Affected fence 21,735m :Partially affected other building (terrace, decker andfloors) = 20,988 M2 and trees = 1044

For the remaining ofAPs: Rp 4.5 Billion on

FY 2017

(1) Satker will conducts design change on the land that be occupied 17affected persons which is not paid by Satker(2). For certification process of 321 Aps is under budgeting allocation onRevision-4 DIPA 2018

SOCIAL: CompleteSimpleLARAP

15 Sibolga - Bts Tap Sel Sumatera Utara

(1). Satker will conducts design change on the land that be occupied 53affected persons which is not paid by Satker. (2). For certificationprocess of 382 Aps is under budgeting allocation on Revision-2 DIPA2018

Complete

Satker conducted the design change on the land that be occupied 2affected persons which can not paid by Satker PJN II West Sumatera.

ENVIRONMENTAL: Link of Bengkunat-Biha already completed byAMDAL study with environmental permit from the Governor at 2012.WILL DELETEDPPK/Satker PJN I West Sumatera and Local Government are continuingthe process of payments to the remaining of the PAPs

B: NOL WB for theMonitoring Report-1 (840Aps) on March 8, 2016.Monitoring Report-2 (926Aps) on May 12, 2016,Monitoring Report-3 (440Aps) on Jan 6, 2017.

Page 137: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Result Comments Budget Alocated,Year StatusTHE WB Approval (A=Studi

LARAP ;B=Implementation LARAP

No Remedial Action

Approval Status by The World BankSocial Screening

ProvincesLoan Package Name

Air Lalang & Air Guntung Bridge B: NOL MR-1: 12 Feb2015, NOL MR-2 on Jan 5,2016, NOL MR-3 on Nov11, 2016A. NOL LARAP 16 Sept2013

B: NOL Monitoring Report -1 on Jul 2015 and NOL MR-2 on Oct 13, 2015, NOL MR-3 on Jan 5, 2016, NOL MR-4 on Nov 18, 2016, NOLMR-5 on Apr 17, 2017,

A. -

A. NOL LARAP 20November 2013;B: NOL MR-1: 23 Mar2015. NOL MR-2: 26 Nov2015A. NOL LARAP on Dec 19,2014

B: NOL Monitoring Report-1 (670) on Sep 26, 2016,NOL Monitoring Report-2(280) on Apr 17, 2017

A. NOL LARAP on Dec 19,2014

B: NOL MonitoringReport_1 (515) on Oct2015 on Aug 23, 2016, NOLof MR-2 (236) on Jan 24,2017

(1). No more issue, LARAP fully completed. (2). TotalPAP = 908 (updated); Compensated = 908; Percentcomplete = 100%.

APBN, 2015 LARAP is under preparation by Balai III Palembang.

For the remaining ofAPs: Rp 2 Billion on FY2017

(1). FNo more issue, LARAP fully completed. (2). TotalPAP =950 (updated); Compensated =950; Percentcomplete =100%.

Total PAP: 950 (updated), Affected land: 46,579 m2, PTKAI Affected land: 682 m2, Partilly affected building(houses and kiosks) = 528m2, Affected fence = 294m,Irrigation channal: 2.600m.

LARAP Total PAP 556. Affected land = 9,504 M2. Asetaffected : floor = 1,381 M2; Terrace: 652 M2; Fence =3,276 M; Tomb = 18 units; Trees 379 rod; utilities 14unit

Rp.3.349.829.000APBN, Satker PJN IIBengkulu

Complete, certification process for 193 plots

17 Lampung

16 Bengkulu Total PAP 259 changed from original 316. No affectedland, Affected assets: building= 658 M2 ; Terrace= 98;Fence= 232 M ; Trees 33 rod

Complete

18 Mukomuko - Bts. Sumbar / Replace toSorkam - Sibolga

Bengkulu

Sp.Gunung Kemala - Pg. Tampak

SOCIAL: Complete

LARAP Total PAP 2585 (updated) . Land affected 1.926 plot =194.278 M2. Aset affected : building 440 unit = 4.557M2 ; ; Trees 4.267 rod ;paddy field 48.602 clumps.

For the remaining ofAPs: Rp 825 Million onFY 2017

SimpleLARAP

(1). Total PAPs 2,585 (update), and alreadycompensated 2,585. (2). No update for certificationprocess of 2.247 Aps

(1). Satker conducted the design change on the land that be occupied 56affected persons which is not paid by Satker. (2). For certificationprocess of 2.247 Aps is under budgeting allocation on Revision-2 DIPA2018

Satker conducted the design change on the land that be occupied 72affected persons which is not paid by Satker.

21 Lubuk Alung -Kurataji Sumatera Barat SimpleLARAP

Total PAP: 908 (updated), Affected land: 40,612 m2,Partilly affected building (houses and kiosks) = 360.9m2Affected fence = 284m Irrigation channal: 433m

For the remaining ofAPs: Rp 1.5 Billion onFY 2017

Satker conducted the design change on the land that be occupied 6affected persons which is not paid by Satker.

20 Lubuk Alung - Sicincin Sumatera Barat

LARAP

19 Lais- Bintunan Bengkulu

SimpleLARAP

ENVIRONMENTAL: Based on CTC survey for environmental screening isconclusion that this packages need completed by UKL&UPL. WILLDELETEDFor certification process of 193 Aps is under budgeting allocation onRevision-2 DIPA 2018

Page 138: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Status, 31 Aug 2018

Length Width Safeguard RKPPLDoc

Integration ofAmdal/UKL-UPL/SPPLin Design

HIV-AIDsSocialization Quarry Owner

(Km) (m) DocRequirement Status Status Status Status Remarks Status Remarks License Base camp

Management Owner/Env License

5 Sp. Rampa -Poriaha 11,1 6 Complete

UKL-UPL Complete Complete Complete28 Jan 2016 OK period 3 on

March 2018OK

(on going)

The last was submit toPMU&WB.& Period Janto March 2018 submit toPMU & WB 21 May2018

CompleteDone (Infrastructure,housekeeping & B3storage/TPS improved

Contractor/ Complete.(PHO schedule on 8March 2018) current thecontractor buy thematerial from suplierPT.Rogada.

7Indrapura - TapanPHO 28 January2018

19,5 7 CompleteAmdal Complete Complete Complete

6 Sep 2016 OK period 2, onNov 2017

OK(on going) PHO Complete

Office workshop,laboratory building stillexist /oil & solar spilled &spillage of garbage atarea workshop & workermess

TP/Complete

8Bts. Kota Pariaman -Manggopoh PHO31 Dec 2017

46,8 7 CompleteAmdal Complete, Complete Complete

4 Oct 2016 OK period 2 onNov 2017

OK(on going) PHO Complete Suitable as SOP /good TP/

Complete

12 Kambang -Indrapura 55,2 6 Complete

Amdal Complete Complete Complete6 Sep 2016 OK period 2, on

Nov 2017OK

(on going)

Period Jan to March2018 submit toPMU/WB 21 May 2018.

CompleteDone (Infrastructure,housekeeping & TPSimproved

TP/Complete/there new Bupati

decree's to closed thequarry operation & Now

under discussion atprovincial level

13 Sp. Rukis -Tj.Kemuning 56,3 7 Complete

UKL-UPL Complete Complete Complete14 Jan 2016 OK period 2, 31

Aug 2017OK

(on going)

Period Jan to March2018 submit toPMU/WB 21 May 2018.

CompleteDone (Infrastructure,housekeeping & TPSimproved

TP/Complete (PHO

Schedule 15 May2018/Masa Denda

14 Painan - Kambang 31,5 7 CompleteAmdal Complete Complete

Complete29 November

2016OK period 2, on

Nov 2017OK

(on going)

Period Jan to March2018 submit toPMU/WB 21 May 2018

Complete

Done (Infrastructure,housekeeping improved& TPS need additional byeyes wash

TP/Complete/there new Bupati

decree's to closed thequarry operation & Now

under discussion atprovincial level

15 Sibolga - Bts.TapSel 36 7 UKL-UPL Complete, Complete Complete

27 Jan 2016 OK period 2 on31 Aug 2017

OK(on going)

Period Jan to March2018 submit toPMU/WB 21 May 2018

Complete Partially needimprovement

TP/Complete

Seblat - Ipuhincluding 34,5 6

Air Lalang & AirGuntung Bridge 64 m 6

20 Lubuk Alung -Sicincin 14,6 7 Complete

UKL-UPL Complete Complete Complete8 March 2017 OK period 2 on 8

Nov 2017OK

(on going)

Period Jan to March2018 submit toPMU/WB 21 May 2018

Complete Done (Infrastructure,housekeeping)

TP/Complete

21 Lubuk Alung -Kuraijati 16,8 7 Complete

UKL-UPL Complete, Complete Complete8 March 2017 OK period 2 on 8

Nov 2017OK

(on going)

Period Jan to March2018 submit toPMU/WB 21 May 2018

Complete Partially needimprovement

TP/Complete

Masa Denda: Project PHO

Period Jan to March2018 submit toPMU/WB 21 May 2018

OK

OKComplete, Complete9 May 2017Complete period 2,on 8

Nov 2017OK

(on going)

Project Terminated

Contractor/Complete

most of the SOPs arecompliant with little

improvement

CompleteDone (Infrastructure,housekeeping & TPSimproved

Completeperiod 3 on31 Aug 2017

TP/Complete

17Sp.Gunung Kemala -Pg.TampakPHO 27 Dec 2017

CompleteAmdal Complete , Complete

10 Nov 2015

CompleteAmdal

Complete36,8 6

Note :

OK(on going) PHO

16

Pack. No.

Loan PackageName

Amdal/UKL-UPLimplementation

for BLH, WB

RKPPL implementation(Quarterly report)

Status & Progress of Environmental Safeguard on WINRIP

Base Camp

Page 139: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

Appendix F

Procurement Plan & Progress

Page 140: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Procurement Plan of Implementation SupportWestern Indonesia National Roads Improvement Project (WINRIP)Executing Agency: Directorate General of Highways , Ministry of Public Works and Housing.

Ref.No. Contract Description Project Cost

(US$)Procurement

Method

Review byBank

(Prior/Post)Schedule

Preparationof Draft

REOI

EOIadvertised in

MPWWebsite

Dateline ofEOI

Submission

SubmissionRFP to WB WB NOL to RFP

Opening ofFinancialProposal

FinalEvaluation

Report

ContractSign

Service Startdate Consultant Remarks

Allocated Original Addendum Actual Submission WB NOL Submission WB NOL Submission Submission WB NOL Original Addendum

2 Implementation Support

Schedule 14-Nov-10 05-Dec-10 23-Jan-11 12-Feb-11 12-Mar-11 02-Apr-11 23-Apr-12 04-Jun-12 22-Jul-12 05-Aug-12 12-Aug-12 15-Sep-12 29-Sep-12 22-Okt-12 12-Nov-12

Actual 26-Nov-10 07-Jun-11 07-Jul-11 30-Jan-12 07-Mar-12 09-Des-11 06-Mar-12 20-Mar-14 30-Apr-12 14-Jun-12 29-Jun-12 27-Agu-12 03-Sep-12 21-Sep-12 12-Okt-12 05-Nov-12 16-Nov-12

Schedule 11-Dec-11 08-Jan-12 27-Feb-12 26-Mar-12 07-May-12 28-May-12 08-Oct-12 22-Oct-12 05-Nov-12 12-Nov-12 19-Nov-12 26-Nov-12 01-Apr-13 18-Apr-13 02-May-13

Actual 26-Nov-10 07-Jun-11 07-Jul-11 02/04/2012 10-Agu-12 20-Jan-12 23-Mei-12 31-Agu-14 23-Okt-12 20-Des-12 21-Feb-13 05-Mar-13 13-Mar-13 25-Mar-13 19-Apr-13 11-Jun-13 25-Jun-13

Schedule 15-Dec-15 22-Dec-15 19-Jan-16 29-Jan-16 12-Feb-16 05-Feb-16 19-Feb-16 26-Feb-16 08-Apr-16 06-May-16 20-May-16 03-Jun-16 17-Jun-16 15-Jul-16 29-Jul-16 12-Aug-16 26-Aug-16 12

Revised 24-Jun-16 15-Jul-15 04-Aug-16 01-Aug-16 08-Aug-16 18-Aug-16 26-Aug-16 29-Aug-16 28-Sep-16 21-Oct-16 04-Nov-16 21-Nov-16 25-Nov-16 05-Dec-16 16-Dec-16 13-Jan-17 23-Jan-17 11

2nd Revised 02-Nov-16 05-Dec-16 09-Jan-17 23-Jan-17 18-Apr-17 28-Apr-17 10-May-17 17-May-17 14-Jun-17 19-Jun-17 11

Actual 24-Jun-16 15-Jul-15 04-Agu-16 18-Agu-16 23-Sep-16 02-Sep-16 27-Okt-16 02-Nov-16 05-Des-16 12-Jan-17 07-Apr-17 20-Apr-17 15-Mei-17 19-Mei-17 15-Jun-17 07-Jul-17 13-Jul-17 11

T O T A L

Technical Assistance for Development of SlopeStabilization, Design and Management, Western

Indonesia Roadsc

Contract(US$)

(excl. VAT)

USD 1,653,867 +IDR

44,230,796,132

USD 965,940 +IDR

64,346,684,915

aCore Team Consultant (Project Management,Technical Assistant, Enviromental & Social Aspectand Road safety Audit)

5.000.000USD 1,276,700 +

IDR21,415,400,000

bDesign and Supervision Consultant (Design AWP-2 & 3 and Construction Supervision of Civil WorksProject)

10.000.000USD 820,600

+IDR

51,818,705,000

Loanreallocation

Date ofReceipt ofProposals

Prior

Evaluation and Short List Technical EvaluationReport Negotiation & Draft Contract

Prior

Theissuance

RFP to theshortlisted

firms

QCBS

QCBS

PT. Perentjana Djaja,Yongma Eng. Co. Ltdand PT. Epadascon

Permata EngineeringConsultant

Renardet S.A., PT.Cipta Strada, PT. DayaCreasi Mitrayasa, PT.Seecons, PT. Yodya

Karya (Persero)

Serviceperiod until30November2018

Serviceperiod until31 October2018

Updated August 31, 2018

PT. Egis InternationalIndonesia, PT.

Disiplan Consult, PT.Widya Graha Asana.

72,83

65

1.000.000USD 155,300. +

IDR6,577,000,000.

QCBS Prior

Period (Month)

40

42

C:\Users\Tediero Pratama\AppData\Local\Temp\Appendix F Draft Proc Plan WINRIP Consultants 20180831_1AEF8924.xlsx

Page 141: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Procurement Plan of Civil WorksWestern Indonesia National Roads Improvement Project (WINRIP)Executing Agency: Directorate General of Highways , Ministry of Public Works and Housing. Updated August 31, 201813400 Edit 250112

Qualification Schedule Submission Notification Contractor

Sub - Project Link No. Length Criteria Actual of of(Km) IDR (x10⁶) USD million (Pre/Post) Application Qualification IDR

A W P - 11 Krui - Biha Lampung 053.0 25,06 163.534,85 12,20 ICB Pre Prior Schedule 12-Jan-11 09-Feb-11 09-May-11 07-Aug-11 15-Dec-11 09-Feb-12 13-Sep-12 28-Feb-13 01-Mar-13 07-Mar-13 18-Apr-13 05-May-13 19-May-13 18-Jun-13

179.888,33 Revised 17-May-13 27-May-13 08-Jul-13 10-Sep-13 24-Sep-13 14-Nov-13 06-Dec-13 07-Sep-15Actual 25-Jan-11 21-Feb-11 02-Nov-11 28-Dec-11 30-Dec-11 28-Feb-12 25-Jan-13 28-Mar-13 17-May-13 27-Jun-12 31-Oct-12 27-May-13 18-Jul-13 10-Sep-13 18-Sep-13 25-Nov-13 08-Jan-14 09-Oct-15

733 10-Jan-16 149.193.782.000Date of Taking Over Certificate 20-Jan-16

2 Padang Sawah - Sp.Empat West Sumatera 047.2 40,70 228.772,24 17,07 ICB Pre Prior Schedule 12-Jan-11 09-Feb-11 09-May-11 07-Aug-11 15-Dec-11 09-Feb-12 13-Sep-12 28-Feb-13 01-Mar-13 07-Mar-13 18-Apr-13 05-May-13 19-May-13 18-Jun-13Including Air Gadang Bridge 0,10 251.649,47 Revised 17-May-13 27-May-13 08-Jul-13 10-Sep-13 24-Sep-13 14-Nov-13 06-Dec-13 06-Dec-15

Actual 25-Jan-11 21-Feb-11 02-Nov-11 28-Dec-11 30-Dec-11 28-Feb-12 25-Jan-13 28-Mar-13 17-May-13 27-Jun-12 31-Oct-12 27-May-13 18-Jul-13 10-Sep-13 18-Sep-13 06-Dec-13 06-Jan-14 05-Jan-16835 19-Apr-16 247.572.130.000

Date of Taking Over Certificate 14-Apr-16

3 Manggopoh - Padang Sawah West Sumatera 047.1 32,00 167.678,40 12,51 ICB Pre Prior Schedule 12-Jan-11 09-Feb-11 09-May-11 07-Aug-11 15-Dec-11 09-Feb-12 13-Sep-12 28-Feb-13 01-Mar-13 07-Mar-13 18-Apr-13 05-May-13 19-May-13 18-Jun-13184.446,24 Revised 17-May-13 27-May-13 08-Jul-13 10-Sep-13 24-Sep-13 14-Nov-13 06-Dec-13 06-Dec-15

Actual 25-Jan-11 21-Feb-11 02-Nov-11 28-Dec-11 30-Dec-11 28-Feb-12 25-Jan-13 28-Mar-13 17-May-13 27-Jun-12 31-Oct-12 27-May-13 18-Jul-13 10-Sep-13 18-Sep-13 06-Dec-13 06-Jan-14 05-Jan-16805 20-Mar-16 183.452.685.000

Date of Taking Over Certificate 17-Mar-16

4 Ipuh - Bantal Bengkulu 015.1 42,45 247.105,24 18,44 ICB Pre Prior Schedule 12-Jan-11 09-Feb-11 09-May-11 07-Aug-11 15-Dec-11 09-Feb-12 13-Sep-12 28-Feb-13 01-Mar-13 07-Mar-13 18-Apr-13 05-May-13 19-May-13 18-Jun-13271.815,76 Revised 17-May-13 27-May-13 08-Jul-13 10-Sep-13 24-Sep-13 14-Nov-13 06-Dec-13 06-Dec-15

Actual 25-Jan-11 21-Feb-11 02-Nov-11 28-Dec-11 30-Dec-11 28-Feb-12 25-Jan-13 28-Mar-13 17-May-13 27-Jun-12 31-Oct-12 27-May-13 18-Jul-13 10-Sep-13 18-Sep-13 14-Nov-13 13-Jan-14 12-Jan-16820 11-Apr-16 212.290.705.872

Date of Taking Over Certificate 31-May-16

Sub Total AWP - 1 807.090,72 60,23 792.509.302.872A W P - 2 and 3

24317 Sp.Gng Kemala - Pugung Tampak Lampung 061.1 36,15 255.269,25 19,05 ICB Pre Prior Schedule 30-Sep-13 14-Oct-13 30-Sep-13 14-Oct-13 06-Nov-13 18-Dec-13 22-Jan-14 06-Feb-14 10-Feb-14 02-Dec-13 16-Dec-13 17-Feb-14 01-Apr-14 30-Apr-14 14-May-14 7-Jul-14 11-Aug-14 31-Jul-16

Revised 19-May-14 2-Jun-14 9-Jun-14 14-Feb-14 28-Feb-14 16-Jun-14 28-Jul-14 1-Sep-14 15-Sep-14 8-Nov-14 13-Dec-14 1-Dec-16Actual 30-Sep-13 10-Oct-13 30-Sep-13 10-Oct-13 11-Nov-13 30-Dec-13 28-Feb-14 13-Jun-14 25-Jun-14 19-Dec-14 7-Jan-14 4-Jul-14 15-Aug-14 10-Oct-14 14-Oct-14 17-Nov-14 4-Sep-15 23-Aug-17

846 27-Dec-17 211.712.283.000Date of Taking Over Certificate 26-Dec-17

5 Simpang Rampa - Poriaha North Sumatera 015. 9,70 152.870,49 11,41 ICB Pre Prior Schedule 06-Nov-13 20-Nov-13 06-Nov-13 20-Nov-13 22-Nov-13 6-Jan-14 7-Feb-14 21-Feb-14 24-Feb-14 2-Dec-13 16-Dec-13 4-Mar-14 15-Apr-14 19-May-14 2-Jun-14 23-Jul-14 22-Aug-14 12-Feb-16Revised 26-May-14 9-Jun-14 16-Jun-14 2-Jun-14 16-Jun-14 23-Jun-14 4-Aug-14 8-Sep-14 22-Sep-14 15-Nov-14 20-Dec-14 11-Jun-16Actual 07-Nov-13 15-Jul-14 07-Nov-13 18-Nov-13 23-Dec-13 10-Feb-14 9-Jun-14 15-Jul-14 22-Jul-14 18-Jul-14 22-Jul-14 11-Aug-14 22-Sep-14 18-Nov-14 27-Jan-15 17-Mar-15 18-Jun-15 8-Dec-16

995 08-Mar-18 130.143.384.830

11 Bantal - Mukomuko Bengkulu 015.2 50,65 246.499,55 18,40 ICB Pre Prior Schedule 06-Nov-13 20-Nov-13 06-Nov-13 20-Nov-13 22-Nov-13 6-Jan-14 7-Feb-14 21-Feb-14 24-Feb-14 2-Dec-13 16-Dec-13 4-Mar-14 15-Apr-14 19-May-14 2-Jun-14 23-Jul-14 22-Aug-14 11-Aug-16Revised 26-May-14 9-Jun-14 16-Jun-14 2-Jun-14 16-Jun-14 23-Jun-14 4-Aug-14 8-Sep-14 22-Sep-14 15-Nov-14 20-Dec-14 8-Dec-16Actual 07-Nov-13 25-Jun-14 07-Nov-13 18-Nov-13 23-Dec-13 10-Feb-14 16-Jun-14 25-Jun-14 11-Jul-14 21-Jul-14 6-Aug-14 22-Aug-14 3-Oct-14 4-Nov-14 13-Nov-14 18-Dec-14 23-Feb-15 11-Feb-17

824 26-May-17 263.656.603.000Date of Taking Over Certificate 19-May-17

13 Sp Rukis - Tj Kemuning Bengkulu 006.1 56,27 316.304,67 23,60 ICB Pre Prior Schedule 06-Nov-13 20-Nov-13 06-Nov-13 20-Nov-13 22-Nov-13 6-Jan-14 7-Feb-14 21-Feb-14 24-Feb-14 2-Dec-13 16-Dec-13 4-Mar-14 15-Apr-14 19-May-14 2-Jun-14 23-Jul-14 22-Aug-14 11-Aug-16Revised 26-May-14 9-Jun-14 16-Jun-14 2-Jun-14 16-Jun-14 23-Jun-14 4-Aug-14 8-Sep-14 22-Sep-14 15-Nov-14 20-Dec-14 8-Dec-16Actual 07-Nov-13 25-Jun-14 07-Nov-13 18-Nov-13 23-Dec-13 10-Feb-14 16-Jun-14 25-Jun-14 11-Jul-14 21-Jul-14 6-Aug-14 22-Aug-14 3-Oct-14 4-Nov-14 18-Nov-14 18-Dec-14 22-Jul-15 10-Jul-17

1029 15-May-18 305.886.100.000

6 Ps. Pedati - Kerkap Bengkulu 010.0 20,88 92.127,40 6,88 NCB Post Post Schedule 13-Nov-13 27-Nov-13 13-Nov-13 27-Nov-13 04-Dec-13 03-Jan-14 02-Feb-14 16-Feb-14 16-Mar-14 15-Apr-14 9-Jul-15Revised 14-Nov-14 28-Nov-14 5-Dec-14 4-Jan-15 22-Feb-15 8-Mar-15 30-May-16Actual 21-Nov-13 - 19-Nov-14 24-Nov-14 29-Dec-14 - - 3-Mar-15 11-Mar-15 2-Jun-16

690 28-Jan-17 118.444.156.000Date of Taking Over Certificate 30-Jan-17

19 Lais - Bintunan Bengkulu 009.1 10,80 35.886,28 2,68 NCB Post Post Schedule 13-Nov-13 27-Nov-13 13-Nov-13 27-Nov-13 04-Dec-13 03-Jan-14 02-Feb-14 16-Feb-14 16-Mar-14 15-Apr-14 9-Feb-15Revised 14-Nov-14 28-Nov-14 5-Dec-14 4-Jan-15 22-Feb-15 8-Mar-15 1-Jan-16Actual 21-Nov-13 - 19-Nov-14 24-Nov-14 29-Dec-14 - - 3-Mar-15 11-Mar-15 4-Jan-16

478 30-Jun-16 44.419.760.000Date of Taking Over Certificate 30-Jun-16

15 Sibolga - Batas Tapsel North Sumatera 016.1 36,00 376.479,38 28,10 ICB Post Prior Schedule 13-Nov-13 27-Nov-13 27-Dec-13 10-Jan-14 17-Jan-14 28-Feb-14 30-Mar-14 13-Apr-14 11-May-14 10-Jun-14 28-Aug-16Revised 16-Dec-13 30-Dec-13 14-Nov-14 28-Nov-14 15-Jan-15 26-Feb-15 31-Mar-15 14-Apr-15 22-Jun-15 10-Aug-15 27-Oct-17Actual 30-Dec-13 28-Feb-14 18-Dec-14 23-Dec-14 12-Jan-15 23-Feb-15 24/04/2015 7-May-15 3-Jul-15 20-Nov-15 6-Feb-18

954 30-Jun-18

8 Bts.Kota Pariaman - Manggopoh West Sumatera 024.0 46,80 379.034,45 28,29 ICB Post Prior Schedule 14-Jul-14 28-Jul-14 04-Aug-14 18-Aug-14 25-Aug-14 06-Oct-14 10-Nov-14 24-Nov-14 17-Jan-15 16-Feb-15 5-Feb-17Revised 01-Dec-14 15-Dec-14 11-Mar-15 25-Mar-15 1-Apr-15 15-May-15 22-Jun-15 6-Jul-15 11-Sep-15 30-Oct-15 18-Oct-17Actual 18-Dec-14 22-Dec-14 12-May-15 26-May-15 28-May-15 13-Aug-15 9-Oct-15 9-Dec-15 28-Jan-16 23-Mar-16 12-Mar-18

649 31-Dec-17 381.795.000.000Date of Taking Over Certificate 29-Dec-17

10 Simpang Empat - Sp.Air Balam West Sumatera 034.1 61,70 515.842,21 38,50 ICB Post Prior Schedule 14-Jul-14 28-Jul-14 04-Aug-14 18-Aug-14 25-Aug-14 06-Oct-14 10-Nov-14 24-Nov-14 17-Jan-15 16-Feb-15 5-Feb-17Revised 01-Dec-14 15-Dec-14 11-Mar-15 25-Mar-15 1-Apr-15 15-May-15 22-Jun-15 6-Jul-15 11-Sep-15 30-Oct-15 18-Oct-17Actual 18-Dec-14 22-Dec-14 12-May-15 26-May-15 28-May-15 13-Aug-15 9-Oct-15 22-Feb-16

7 Indrapura - Tapan West Sumatera 019.0 19,50 178.600,23 13,33 NCB Post Prior Schedule 14-Jul-14 28-Jul-14 04-Aug-14 18-Aug-14 25-Aug-14 29-Sep-14 3-Nov-14 17-Nov-14 29-Dec-14 28-Jan-15 19-Oct-16Revised 01-Dec-14 15-Dec-14 11-Mar-15 25-Mar-15 1-Apr-15 6-May-15 11-Jun-15 25-Jun-15 21-Aug-15 4-Sep-15 25-May-17Actual 18-Dec-14 22-Dec-14 12-May-15 26-May-15 28-May-15 13-Aug-15 9-Oct-15 12-Oct-15 3-Dec-15 10-Dec-15 30-Aug-17

781 28-Jan-18Date of Taking Over Certificate 28-Jan-18

12 Kambang - Indrapura West Sumatera 017.2 55,20 451.810,58 33,72 ICB Post Prior Schedule 14-Jul-14 28-Jul-14 04-Aug-14 18-Aug-14 25-Aug-14 06-Oct-14 10-Nov-14 24-Nov-14 17-Jan-15 16-Feb-15 5-Feb-17Revised 01-Dec-14 15-Dec-14 11-Mar-15 25-Mar-15 1-Apr-15 6-May-15 11-Jun-15 25-Jun-15 21-Aug-15 4-Sep-15 23-Aug-17Actual 18-Dec-14 22-Dec-14 12-May-15 26-May-15 28-May-15 13-Aug-15 9-Oct-15 26-Nov-15 28-Jan-16 23-May-16 12-May-18

798 29-Jul-18

14 Painan - Kambang West Sumatera 017.1 31,50 267.588,30 19,97 NCB Post Prior Schedule 01-Oct-14 15-Oct-14 01-Oct-14 15-Oct-14 22-Oct-14 26-Nov-14 31-Dec-14 14-Jan-15 25-Feb-15 11-Mar-15 30-Nov-16Revised 10-Jul-15 24-Jul-15 10-Aug-15 24-Aug-15 2-Nov-15 16-Dec-15 13-Jan-16 27-Jan-16 2-Mar-16 16-Mar-16 5-Dec-17Actual 10-Sep-15 22-Oct-15 22-Oct-15 2-Nov-15 5-Jan-16 22-Mar-16 4-Apr-16 1-Jun-16 3-Aug-16 24-Apr-18

684 17-Jun-18

16 Seblat - Ipuh, Including Bengkulu 009.4 34,50 269.559,20 20,12 NCB Post Prior Schedule 01-Oct-14 15-Oct-14 01-Oct-14 15-Oct-14 22-Oct-14 26-Nov-14 31-Dec-14 14-Jan-15 25-Feb-15 11-Mar-15 30-Nov-16Air Lalang & Air Guntung Bridge 0,060 Revised 10-Jul-15 24-Jul-15 10-Aug-15 24-Aug-15 22-Oct-15 19-Nov-15 17-Dec-15 31-Dec-15 4-Feb-16 18-Feb-16 8-Nov-17

Actual 4-Sep-15 22-Oct-15 30-Sep-15 22-Oct-15 22-Oct-15 19-Nov-15 11-Jan-16 24-Aug-16 28-Oct-16 8-Nov-16 30-Jul-18

20 Lubuk Alung - Sicincin West Sumatera 002.0 14,60 131.302,20 9,80 NCB Post Prior Schedule 01-Oct-14 15-Oct-14 01-Oct-14 15-Oct-14 22-Oct-14 26-Nov-14 31-Dec-14 14-Jan-15 11-Feb-15 25-Feb-15 18-Aug-16Revised 10-Jul-15 24-Jul-15 10-Aug-15 24-Aug-15 2-Nov-15 16-Dec-15 13-Jan-16 27-Jan-16 2-Mar-16 16-Mar-16 6-Sep-17Actual 25-Aug-15 22-Oct-15 22-Oct-15 2-Nov-15 5-Jan-16 22-Mar-16 23-Mar-16 1-Jun-16 1-Sep-16 22-Feb-18

533 15-Feb-18

21 Lubuk Alung - Kuraitaji West Sumatera 027.0 16,23 164.629,30 12,29 NCB Post Prior Schedule 01-Oct-14 15-Oct-14 01-Oct-14 15-Oct-14 22-Oct-14 26-Nov-14 31-Dec-14 14-Jan-15 11-Feb-15 25-Feb-15 18-Aug-16Revised 10-Jul-15 24-Jul-15 10-Aug-15 24-Aug-15 2-Nov-15 16-Dec-15 13-Jan-16 27-Jan-16 2-Mar-16 16-Mar-16 6-Sep-17Actual 25-Aug-15 22-Oct-15 22-Oct-15 02-Nov-15 05-Jan-16 22-Mar-16 23-Mar-16 01-Jun-16 1-Sep-16 22-Feb-18

666 28-Jun-18

18 Mukomuko - Batas Sumbar Bengkulu 015.3 25,80 69.233,00 5,17 NCB Post Prior ScheduleRevised

Actual

9 Rantau Tijang - Kota Agung Lampung 026.1 42,00 149.831,00 11,18 NCB Post Prior ScheduleRevisedActual

5A North Sumatera 015. 0,69 65.726,63 4,90 NCB Post Post Schedule 06-Mar-18 20-Mar-18 19-Mar-18 02-Apr-18 16-Apr-18 16-May-18 - - 27-Jun-18 2-Jul-18 150 29-Nov-18015. 0,69 79.780,00 5,95 NCB Post Post Rebidding

Schedule30-Aug-18 20-Sep-18 30-Sep-18 - 12-Oct-18 26-Oct-18 180 23-Apr-19

Actual 13-Mar-18 15-Mar-18 10-Apr-18 18-Apr-18 24-Apr-18 16-May-18Rebidding

Actual 30-Aug-18

21A West Sumatera 027.0 16,23 70.000,00 5,22 NCB Post Post Schedule 20-Aug-18 31-Aug-18 03-Sep-18 - 3-Sep-18 24-Sep-18 15-Oct-18 - 5-Nov-18 19-Nov-18 18-Apr-19Revised

Actual

Sub Total AWP - 2 & 3 4.132.647,47 308,41 2.857.143.616.521

Total AWP - 1 , 2 & 3 4.939.738,19 368,64 3.649.652.919.393USD 272.362.158

Note: USD 190.653.5111 USD = (Exchange rate assumption for RAPBN-P FY 2018, Ministry of Finance)

PT. PP (Persero), Tbk.- PT.Statika Mitrasarana, J.O.

260.100.000.011

PT. Jaya KonstruksiManggala Pratama, Tbk.

PT. Waskita Karya(Persero), Tbk. and PT.

Daya Mulia Turangga, J.O.186.936.750.000

PT. Waskita Karya(Persero), Tbk.

PT. Rodateknindo Purajaya.

86.517.470.000

PT. Jaya KonstruksiManggala Pratama, Tbk.

107.321.260.310

228.899.717.000

199.551.233.000

292.700.000.000

143.688.963.000

33.689.452.000

Invitationfor Bids

Date

BidOpening

DateWB NOLDate

SubmissionDate

PT. Hutama Karya (Persero)and PT. Daya Mulia

Turangga, J.O.

PT. Waskita Karya(Persero), Tbk.

Contract Amount(Incl. VAT10%)Completion

Date

134.909.211.000

PT. Jaya KonstruksiManggala Pratama, Tbk.

WB NOLDate

Submission Date

PQ Document Invitation forPre-

qualification

Evalt.QualificationReport Bidding Document

Commencement Date

Construction

Period(day)

SubmissionDate NOL Date Submission

Date

PT. Jaya KonstruksiManggala Pratama, Tbk.

Amendments

197.936.699.000

Ref. No. Province Procurement Method

Estimated CostEE

(Incl. VAT)

Estimated CostEE

(Incl. VAT)

Rp13.400,00

Bid Evaluation Report ContractSignature

DateWB NOL

CANCELED

CANCELED

640

730

730

730

720

540

720

720

450

WB Prior/Post Rewiew

Design

Submission Date

WB NOLDate

810

720

720

630 PT. Adhi Karya (Persero),Tbk. 129.699.900.000

PT. Lancarjaya MandiriAbadi - PT. Cahaya TunggalAbadi, J.O.

358.650.400.000

630

630 KSO YASA - CONBLOC

720

KSO. PT. Yasa PatriaPerkasa - PT. Multi

Structure211.374.500.000

Amendments

Amendments

Amendments

Amendments

PT. PP (Persero), Tbk.

Amendments

Amendments

Amendments

PT. Nusa KonstruksiEnjiniring, Tbk.

Amendments

Amendments

Amendments

Amendments

Amendments

355.500.000.000

300

Amendments

Amendments

CANCELED

540

Amendments

PT. Multi Structure 126.301.900.000

214.327.429.680

PT. Nindya Karya (Persero) 113.818.300.000540

no bidders pass the qualification

Penanganan Lereng Ruas Sp.Rampa - Poriaha

150Lubuk Alung - Kuraitaji(Penyelesaian)

TERMINATEDAmendments

C:\Users\Tediero Pratama\AppData\Local\Temp\Appendix F Draft Proc Plan WINRIP CivilWorks 20180831_1AED87F5.xlsx

Page 142: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

Appendix G

WINRIP Website & Application Progress

Page 143: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

APPENDIX GManagement Information System (MIS) Status on August, 2018

NO. TASK DESCRIPTION STATUS WORK PLAN1 File Storage

storage.winrip-ibrd.comThe storage server to stored allof soft files of reports anddocuments.

The new version of application has beencompleted on February 2015.

2 DMS (DocumentManagement System)dms.winrip-ibrd.com

The application to record allinformation of letter anddocument files.

The DMS applications is already finalsdeveloped with the addition of features suchas parent-child mechanism, letter comments,and direct notification.

We have improved the uploadfunction, then that DMSapplication can already uploaddocuments with big file size.

3 Websitewww.winrip-ibrd.com

The WINRIP official website. The website has been developed on August2013.

4 WebGISwebgis.winrip-ibrd.com

The spatial data and roadsinformation that overlay intoGoogle Maps.

The application has been developed onOctober 2013.

5 FMIS (FinancialManagementInformation System)fmis.winrip-ibrd.com

The application to monitoring afinancial and physical progressreport.

The programming modules that have beenfinished are as follows: Project Data Financial and Physical Progress Progress Summary History of Financial and Physical Progress User

The programming modules thatnot yet finished are as follows: Consultant Services Reports

6 CHS (ComplaintHandling System)chs.winrip-ibrd.com

The application to accommodatecomplaints from the public.

The application has been developed onJanuary 2014.

7 WINRIP Cloudcloud.winrip-ibrd.com

The WINRIP-Storage server oncloud system.

The cloud system is running online inDecember 2016.

8 CTC Daily ActivitiesReportdar.winrip-ibrd.com

Activity of all CTC personnelevery day.

It was completed on January 19, 2018, and isnow used by all CTC personnel.

Page 144: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

CHECKLIST OF DOCUMENTS IN THE DMS DATABASELast Updated at The End of August 2018

NO PACKAGEACAP ENVIRONMENT FINANCIAL HIGHWAY PROCUREMENT QA RSA SOCIAL TRAINING

PROJECTPMU CTC

CRO CHU TPM AMDAL HIV/AIDS RKPPL SPPL UKL/

UPL IFR AUDIT DED EE RTA BD BEPR CON-TRACT PRAR COW PCM PMER PHO RSTMMR RSA LARAP STUDY

LARAP TIR WIR PMM IR MPR QPR SR PCR

1 Krui - Biha #01#02#03#04#05#06#07#08#09#10#11#12#13#14#15#16#17#18#19#20#21#22

#2013#2014#2015#2016

Loan Agr.PIPPADMTR

#01 #56#02 #57#03 #58#04 #59#05 #60#06 #61#07 #62#08 #63#09 #64#10 #65#11 #66#12#13#14#15#16#17#18#19#20#21#22#23#24#25#26#27#28#29#30#31#32#33#34#35#36#37#38#39#40#41#42#43#44#45#46#47#48#49#50#51#52#53#54#55

#01#02#03#04#05#06#07#08#09#10#11#12#13#14#15#16#17#18

#01#02#03#04#05#06#07

2 Pd Sawah - SpEmpat

3 Manggopoh - PdSawah

4 Ipuh - Bantal

5 Sp Rampa -Poriaha

6 Ps Pedati -Kerkap

7 Indrapura - Tapan

8Bts KotaPariaman -Manggopoh

9 Rantau Tijang -Kota Agung

10 Sp Empat - Sp AirBalam

11 Bantal -Mukomuko

12 Kambang -Indrapura

13 Sp Rukis - TjKemuning

14 Painan -Kambang

15 Sibolga - BtsTapsel

16 Seblat - Ipuh

17 Sp Gn Kemala -Pugung Tampak

18 Mukomuko - BtsSumbar

19 Lais - Bintunan

20 Lubuk Alung -Sicincin

21 Lubuk Alung -Kuraitaji

*(Read the list of glossary on the next page).

Page 145: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

CHECKLIST OF HARD COPY DOCUMENTS IN THE FILE BOX STORAGELast Updated at The End of August 2018

NO PACKAGE

PRE-CONSTRUCTION PROCUREMENT CONSTRUCTION PHO

ACAP ENVIRONMENT HE/RSA SOCIALIMPACT SBD DED BOQ OE GS SS BEPR PRAR KONTRAK PCM PMER RSTMMR ADD AMD PHO RSA

CRO CHU TPM AMDAL HIV/AIDS RKPPL SPPL UKL/

UPLDesignReiew LARAP

1 Krui – Biha 2 Padang Sawah – Sp.Empat (incl. Air

Gadang Bridge) 3 Manggopoh – Padang Sawah 4 Ipuh – Bantal 5 Simpang Rampa – Poriaha 6 Ps. Pedati – Kerkap 7 Indrapura – Tapan 8 Bts.Kota Pariaman – Manggopoh 9 Rantau Tijang – Kota Agung

10 Simpang Empat – Air Balam 11 Bantal – Mukomuko 12 Kambang – Indrapura 13 Sp Rukis – Tj Kemuning 14 Painan – Kambang 15 Sibolga – Batas Tapsel 16 Seblat – Ipuh (incl. Air Lalang & Air

Guntung Bridge)

17 Sp.Gng Kemala – Pugung Tampak 18 Mukomuko – Batas Sumbar

19 Lais – Bintunan 20 Lubuk Alung – Sicincin 21 Lubuk Alung – Kuraitaji

Page 146: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Glossary of the Document Types in the DMS database.

NO DOCUMENT TYPE ABBREVIATION1 Addendum ADD2 Aide Memoire AM3 Amendment AMD4 Analisis Mengenai Dampak Lingkungan AMDAL5 Audit AUDIT6 Bid Document BD7 Bid Evaluation Procurement Report BEPR8 Commencement of Work COW9 Complaint Report CR10 Contract CONTRACT11 Detail Engineering Design DED12 Draft Project Completion Report DPCR13 Engineer Estimate EE14 HIV AIDS Report AIDS15 Inception Report IR16 Interim Financial Report IFR17 Invoice INV18 Land Acquisition Resettlement Action Plan LARAP19 Loan Agreement LA20 Mid Term Review MTR21 Minute of Meeting MOM22 Monthly Progress Report MPR23 Photo PHOTO24 Pre-Construction Meeting PCM25 Procurement Plan PP26 Procurement Readines Assessment Report PRAR27 Project Appraisal Document PAD28 Project Completion Report PCR29 Project Implementation Plan PIP30 Project Management Manual PMM31 Project Monitoring and Evaluation Report PMER32 Provisional Hand Over PHO33 Quarterly Progress Report QPR34 Rencana Kerja Pengelolaan dan Pemantauan Lingkungan RKPPL35 Report RPT36 Road Safety and Traffic Management Monitoring Report RSTMMR37 Road Safety Audit RSA38 Road Technical Analysis RTA39 Surat Pernyataan Pengelolaan Lingkungan SPPL40 Semestral Report SR41 Term of Reference TOR42 Third Party Monitoring TPM43 Training Implementation Report TIR44 Upaya Kelola/Pemantauan Lingkungan UKL-UPL45 Video VIDEO

Page 147: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

NO DOCUMENT TYPE ABBREVIATION46 Wakil Pengamat Masyarakat WPM47 Workshop Implementation Report WIR

Page 148: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

Appendix H

ACAP Training /Dissemination Progress

Page 149: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

Appendix H ACAP Activity ProgressAppendix H1

Activities Progress of Community Representative Observers (CROs) and the Works PlanJanuary 2013 – August 2018

No Subject Activities of Community Representative Observers (CROs) Date of Finish/completed

1. Orientation and studied of WINRIP documents and Development of Works Plan January 2013

2 Prepared of Workshop of Procurement Document Evaluation. February 2013

3. Conducted Workshop of Procurement Document Evaluation for POKJA, Satker/PPK, BalaiBBPJN and PMU.

Febr. 28, 2013 –March 01, 2013

4. Provided of Term of Reference (TOR) of the CRO's Selection and Guidelines for CRO’sSelection

March 1, 2013

5. Provided the Materials (Slide Presentation/Power-point) of General Explanations aboutWINRIP and the CRO’s selection and

March 8, 2013

6. Provided Training Materials for CROs. March 8, 2013

7. Sending an official letter No. Hm.0603/Bp-11/0175/2013, from the Director of Planning asChairman of PMU to Head of BBPJN II & III, about the Selection of CROs/WPM, + TOR andGuidelines Document

March 11, 2013

8 Preparation of Socialization on CROs selection in BBPJN II Padang for package 02 PadangSawah – Simpang Empat and package 03 Manggopoh - Padang Sawah, and Socialization onCROs selection in BBPJN III Palembang for package 01 Krui – Biha and package 04 Ipuh –Bantal.

March 31, 2013

9. Socialization on CROs selection in BBPJN II Padang for package 02 Padang Sawah – SimpangEmpat and package 03 Manggopoh - Padang Sawah

April 9, 2013

10 Socialization on CROs selection in BBPJN III Palembang for package 01 Krui – Biha andpackage 04 Ipuh – Bantal.

April 11, 2013

11. Sent the Invitation letter from Head of BBPJN III to Rector of Universities /Head of Colleges inPalembang, about selection of the CROs for package 01. Krui – Biha (Prov. Lampung) andpackage 04. Ipuh – Bantal (Prov. Bengkulu).

May 17, 2013

12. Sent the Invitation letter from Head of BBPJN II to Rector of Universities /Head of Colleges inPadang, about selection of the CROs for package 02. Padang Sawah – Simpang Empat andpackage 03. Manggopoh - Padang Sawah (Prov. Sumatera Barat).

May 20, 2013

13. Selection of CROs for Packages Krui – Biha Province Lampung and Ipuh – Bantal ProvinceBengkulu, and training for selected CROs in BBPJN III Palembang

May 23, 2013

14. Selection of WPM/CROs for Packages Manggopoh – Padang Sawah and Padang Sawah –Simpang Empat, and training for selected CROs in BBPJN II Padang

May 27, 2013

15. Sending an official letter No. Hm.0603/Bp-11/0175/2013, from the Director of Planning asChairman of PMU to Head of BBPJN II & III, about the Selection of CROs/WPM, + TOR andGuidelines Document

May 28, 2013

16. Guiding the Balai Besar Pelaksanaan Jalan Nasional (Balai) II Padang to compose theApplication Letter for Approval of selected CROs for Package 03. Manggopoh – PadangSawah, package 02. Padang Sawah – Simpang Empat, and Balai III Palembang for Package 01.Krui – Biha Province Lampung and Package 04. Ipuh – Bantal Province Bengkulu.

May 29, 2013

Page 150: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

No Subject Activities of Community Representative Observers (CROs) Date of Finish/completed

17. Compiling summary of the results of Selection the Community Representative Observers(CROs)/ Wakil Pengamat dari Masyarakat (WPM) and the Training activities for selectedCROs for four Packages AWP-1

June 1 - 9, 2013

18. Assist PMU to prepare the Approval letter of selected CROs for four AWP-1 Packages, andprepare of the Decree on Establishment the CROs of AWP-1 WINRIP from Director ofPlanning DGH, as the Chairman of PMU.

June 1 - 9, 2013

19. Monitor and observation the Pre-Bid Meeting and Site Visit activities of Procurement Processthat held by the Procurement Committee, in BBPJN II and III, on 10 June 2013 by CROs inimplementing their tasks on the

June 10 - 16,2013

20. Evaluate of the CROs observation on Pre-Bid Meeting and Site Visit activities Jun.17 - 23, 2013

21. Examine the report of CROs on the monitoring and observation of Pre-Bid Meeting and SiteVisit at the packages of Annual Works Program - 1 (AWP-1) WINRIP.

Modify the template of monitoring the report of the CROs, to be more focused and moresystematically

June 24 - 30,2013

22. Monitor /Observe of Bids Submission and Bids Opening for four packages AWP-1 byCommunity Representative Observers (CROs) for Package 01, 02, 03, and 04

July 18, 2013

23. Monitoring and examined of the CRO’s Report on the monitoring and observation of BidSubmission and Bid Opening activities for four packages of Annual Works Program - 1 (AWP-1) WINRIP, which have been carried out on July 18, 2013

August, 2013

24 Preparation on the Socialization of CROs selection to the Procurement Committee (POKJA) ofSumatera Utara province, for package Simpang Rampa – Poriaha and package Sibolga – BatasTapanuli Selatan

October 2013

25 Monitored /Observed of Procurement progress on Commencement of Bid Winners for fourpackages AWP-1 (Package 01, 02, 03, and 04) and informed to related CommunityRepresentative Observers (CROs).

November 2013

26 Carried out the dissemination of CROs selection to the Procurement Committee (POKJA) ofSumatera Utara province, for package Simpang Rampa – Poriaha. in Balai (BBPJN) I Medanand in Project Management (Satker) Office.

November 19 –20, 2013

27 Carried out the CROs selection for package 17: Simpang Gunung Kemala – Pugung Tampak inLampung..

July 17, 2014

28 Carried out the CROs selection for package 05: Simpang Rampa – Poriaha in North Sumateraprovince.

August 20, 2014

29 Carried out the CROs selection for package 11: Bantal – Mukomuko, and package 13:Simpang Rukis – Tanjung Kemuning in Bengkulu province.

Sept. 1, 2014

30 Ms. Hesti Aulia Sari, ST, CRO for Package 11: Bantal - Mukomuko, meet the invitation of theProcurement Committee (Pokja of Procurement Unit/Unit Layanan Pengadaan BBPJN III,PIU/Satker PJN Region I Bengkulu Province).

Oct. 03, 2014

31 Ms. Hot Maria Angelina, ST, CRO for Package 13: Simpang Rukis - Tanjung Kemuning wasattended Bid-Opening meeting meet the invitation by the Procurement Committee (Pokja ofProcurement Unit/Unit Layanan Pengadaan BBPJN III, PIU/Satker PJN Region II BengkuluProvince).

Oct. 03, 2014

32 Carried out the CROs selection for package 06: pasar Pedati –Kerkap and package 19: Lais -Bintunan in Bengkulu province.

Nov. 27, 2014

33 The elected CROs (Ms. Hot Maria Angelina, ST and Ms. Hesti Aulia Sari, ST) attanded Pre-BidMeeting and site visit for package 06 (Pasar Pedati – Kerkap) and package 19 (Lais –Bintunan), Bengkulu Province

Dec. 05, 2014

34 The Community Development team CTC WINRIP has carried out the selection of CROs forPackage 15: Sibolga – Batas Tapanuli Selatan. The Elected CRO is Ernie Shinta Y. Sitanggang,ST, MT, and Ir. M. Koster Silaen, MT as the substitute CRO (both from Politeknik NegeriMedan / State Polytechnic of Medan)

Dec. 16, 2014,

Page 151: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

No Subject Activities of Community Representative Observers (CROs) Date of Finish/completed

35 The elected CROs for package 06 (Pasar Pedati – Kerkap) and package 19 (Lais – Bintunan)Bengkulu Province was attanded the Bid-Opening Meeting.

Dec. 29, 2014

36 Ir. M. Koster Silaen, MT as the substitute CRO of Package 15: Sibolga – Batas Tapanuli Selatanwas attended the Pre-Bid Meeting.

Jan. 26, 2015

37 Ir. M. Koster Silaen, MT as the substitute CRO of Package 15: Sibolga – Batas Tapanuli Selatanwas attended the Bid Opening Meeting

Feb. 23, 2015

38 The Community Development team CTC WINRIP has carried out the selection of CROs forfour packages WINRIP in West Sumatera province, as follow;6 The appointed CRO for Package 07: Indrapura – Tapan, is Ir. Riswandi, M.Si, and

Apwiddhal, ST, MT as the substitute CRO, both from State Polytechnic of Padang(Politeknik Negeri Padang).

7 The appointed CRO for Package 08: Batas Pariaman – Manggopoh, is M. Nursyaifi Yulius,MT (Mgt), and Ir. Alzahri, MT as the substitute CRO, both from Bung Hatta University ofPadang (Universitas Bung Hatta Padang).

8 The appointed CRO for Package 10: Simpang Empat – Simpang Air Balam, is Ir. Drs. Heldi,M.Si, and Ir. Afrizal Naumar, MT as the substitute CRO, both from Bung Hatta University ofPadang (Universitas Bung Hatta Padang).

9 The appointed CRO for Package 12: Kambang – Indrapura, is Syaiful Amri, SST, MT, and B.Army, ST, MT as the substitute CRO, both from State Polytechnic of Padang (PoliteknikNegeri Padang)

June 12, 2015

39 The appointed CRO Ir. Riswandi, M.Si for Package 07: Indrapura – Tapan, and the appointedCRO Syaiful Amri, SST, MT for Package 12: Kambang – Indrapura were attended the Pre-BidMeeting and Site Visit as invited by the Procurement Committee (Pokja) of PIU/Satker PJNRegion II of West Sumatera ProvinceThe appointed CRO M. Nursyaifi Yulius, MT (Mgt) for Package for Package 08: Batas Pariaman– Manggopoh, , and the appointed CRO Ir. Drs. Heldi, M.Si for Package 10: Simpang Empat –Simpang Air Balam were attended the Pre-Bid Meeting and Site Visit as invited by theProcurement Committee (Pokja) of PIU/Satker PJN Region I of West Sumatera Province.

June. 15-16, 2015

40 The appointed CRO Ir. Riswandi, M.Si for Package 07: Indrapura – Tapan, and the appointedCRO Syaiful Amri, SST, MT for Package 12: Kambang – Indrapura were sent the ObservationReport on Pre-Bid Meeting and Site Visit.

July. 02, 2015

41 The appointed CRO M. Nursyaifi Yulius, MT (Mgt) for Package for Package 08: Batas Pariaman– Manggopoh, , and the appointed CRO Ir. Drs. Heldi, M.Si for Package 10: Simpang Empat –Simpang Air Balam were sent the Observation Report on Pre-Bid Meeting and Site Visit.

July. 10, 2015

42 The CRO for Package 07: Indrapura – Tapan (Ir. Riswandi, M.Si), and the CRO for Package 12:Kambang – Indrapura (Syaiful Amri, SST, MT) were attended the Bid Opening Meeting.

August 13, 2015

43 The CRO for Package for Package 08: Batas Pariaman – Manggopoh (M. Nursyaifi Yulius, MT(Mgt), and the CRO for Package 10: Simpang Empat – Simpang Air Balam (Ir. Drs. Heldi, M.Si)were attended the Bid Opening Meeting.

August 13, 2015

44 Selection of CROs for packages 16 (Sebelat – Ipuh) in Bengkulu province, as follow;10 The appointed CRO for Package 16 is Mr. Besperi, ST, MT, and and Ms. Anggi Nidya Sari,

ST., MT as the substitute CRO. Both of them were from Bengkulu University.

Nov,.4-5, 2015

45 Selection of CROs for packages 14, 20, and 21 in West Sumatera province, as follow;11 The Elected CRO for Package 14 (Painan - Kambang) were Mr. M. Nursyaifi Yulius, MT

(Mgt), and Mr. Ir. Alzahri, MT, as the substitute CRO, both of them were from Bung HattaUniversity.

12 The Elected CRO for Package 20 (Lubuk Alung - Sicincin), were Mr. Ir. Riswandi, M.Si andMr. Syaiful Amri, SST., MT, as the substitute CRO, both of them were from StatePolitechnic of Padang (Politeknik Negeri Padang).

13 The Elected CRO for Package 21 (Lubuk Alung - Kuraitaji) were Mr. Jafril Tanjung, DR. Engand Mr. Ophiyandri, Ph.D as the substitute CRO, both of them were from AndalasUniversity

Nov,.16-17, 2015

Page 152: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

No Subject Activities of Community Representative Observers (CROs) Date of Finish/completed

46 The substitute CRO for Package 16: Sebelat – Ipuh, Ms. Anggi Nidya Sari, ST., MT wasattended the Pre-Bid Meeting and Site Visit as invited by the Procurement Committee (Pokja)of PIU/Satker PJN Region I of Bengkulu Province.

Nov. 05, 2015

47 The substitute CRO for Package 14: Painan - Kambang, Mr. Ir. Alzahri, MT was attended thePre-Bid Meeting and Site Visit as invited by the Procurement Committee (Pokja) ofPIU/Satker PJN Region II of West Province.

Nov. 18, 2015

48 The Elected CRO for Package 20 (Lubuk Alung - Sicincin), Mr. Ir. Riswandi, M.Si, was attendedthe Pre-Bid Meeting and Site Visit as invited by the Procurement Committee (Pokja) ofPIU/Satker PJN Region I of West Sumatera Province.

Nov. 18, 2015

49 The Elected CRO for Package 21 (Lubuk Alung - Kuraitaji), Mr. Jafril Tanjung, DR. Eng, wasattended the Pre-Bid Meeting and Site Visit as invited by the Procurement Committee (Pokja)of PIU/Satker PJN Region I of West Sumatera Province.

Nov. 18, 2015

50 The substitute CRO for Package 16: Sebelat – Ipuh, Ms. Anggi Nidya Sari, ST., MT wasattended the Bid Opening Meeting, invited by the Procurement Committee (Pokja) ofPIU/Satker PJN Region I of Bengkulu Province.

Nov. 19, 2015

51 The substitute CRO for Package 16: Sebelat – Ipuh, Ms. Anggi Nidya Sari, ST., MT, was sentthe observation report on Pre-Bid Meeting and Site Visit

Nov. 25, 2015

52 The CRO for Package 14: Painan - Kambang, Mr. Ir. Alzahri, MT was attended the Bid OpeningMeeting as invited by the Procurement Committee (Pokja) of PIU/Satker PJN Region II ofWest Province.

Jan. 05, 2016

53 The Elected CRO for Package 20 (Lubuk Alung - Sicincin), Mr. Ir. Riswandi, M.Si, was attendedthe Bid Opening Meeting as invited by the Procurement Committee (Pokja) of PIU/Satker PJNRegion I of West Sumatera Province.

Jan. 05, 2016

54 The Elected CRO for Package 21 (Lubuk Alung - Kuraitaji), Mr. Jafril Tanjung, DR. Eng, wasattended the Bid Opening Meeting as invited by the Procurement Committee (Pokja) ofPIU/Satker PJN Region I of West Sumatera Province.

Jan. 05, 2016

55 The Elected CRO for Package 20 (Lubuk Alung - Sicincin), Mr. Ir. Riswandi, M.Si, was sent theObservation Report on Pre-Bid Meeting and Site Visit.

Jan. 06, 2016

56 The CRO for Package 07: Indrapura – Tapan (Ir. Riswandi, M.Si), was sent the ObservationReport on Bid Opening and Bid Winner Announcement.

Jan. 19, 2016

57 The CRO for Package 12: Kambang – Indrapura (Syaiful Amri, SST, MT) was sent theObservation Report on Bid Opening and Bid Winner Announcement.

Jan. 19, 2016

58 The CRO for Package 14: Painan - Kambang, (Mr. Ir. Alzahri, MT) was sent the observationreport on Pre-Bid Meeting and Site Visit.

Jan. 25, 2016

59 The Elected CRO for Package 21 (Lubuk Alung - Kuraitaji), Mr. Jafril Tanjung, DR. Eng, wassent the Observation on Pre-Bid Meeting and Site Visit.

Jan. 29, 2016

60 The CRO for Package for Package 08: Batas Pariaman – Manggopoh (M. Nursyaifi Yulius, MT(Mgt), was sent the Observation Report on Bid Opening and Bid Winner Announcement.

Feb. 17, 2016

61 The CRO for Package 14: Painan - Kambang, (Mr. Ir. Alzahri, MT), was sent the ObservationReport on Bid Opening and Bid Winner Announcement

May 10, 2016

62 The Elected CRO for Package 20 (Lubuk Alung - Sicincin), Mr. Ir. Riswandi, M.Si, was sent theObservation Report on Bid Opening and Bid Winner Announcement

May 10, 2016

63 The Elected CRO for Package 21 (Lubuk Alung - Kuraitaji), Mr. Jafril Tanjung, DR. Eng, wassent the Observation on Bid Opening and Bid Winner Announcement

May 31, 2016

64 The substitute CRO for Package 16: Sebelat – Ipuh, Ms. Anggi Nidya Sari, ST., MT, was sentthe observation report on Bid Opening Meeting and the Announcement of Bid-Winner forPackage 16 (Seblat – Ipuh) in Bengkulu Province

September 2016

65 Appointment of the CROs for procurement process of package 05A (Slope Protection of RoadSegment of Rampa – Poriaha / Mungkur in North Sumatera Province,. The appointed CRO isMrs. Ernie Shinta Sitanggang, ST, MT., as the main CRO, and Mr. Ir. M. Koster Silaen, MT, asthe reserve / replacement

April 24, 2018

Page 153: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

No Subject Activities of Community Representative Observers (CROs) Date of Finish/completed

66 Provide Agreement Letter of establishment the CROs for Package 05A that was signed byDirector of Roads Network Development, Directorate of Highway.

April 25, 2018

67 The appointed CRO, Mrs. Ernie Shinta Sitanggang, ST, MT was attended the Pre-Bid meeting,as the step of procurement process of package 05A, in Balai Besar Pelaksanaan JalanNasional (BBPJN) / National Roads Implementation Agency II Medan

April 27, 2018

Page 154: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

Appendix H.2The Progress of Third Party Monitoring (TPM) Activities and Works Plan for Next Steps

January 2013 – August 2018

No Subject Activities of Third Party Monitoring (TPM) Target Completed

1. Preparation the initial draft of ToR of selection the TPM Dec, 2013 Dec, 2013

2. Providing the TPM selection guidelines. Dec, 2013 Dec, 2013

3. Providing the Training Materials for the TPM Dec, 2013 Dec, 2013

4. Preparing the official letter from the Director of Planning as Chairman ofPMU to Head of BBPJN II & III, about the Selection of TPM. Jan, 2014 Jan. 24, 2014

5. Preparing the official letter from the Director of Planning as Chairman ofPMU to Universities, about the Selection of TPM. Jan., 2014 Jan 29, 2014

6. Preparing the official letter from the Official in Charge/Ketua PelaksanaHarian PMU to Satker/PPK, about the Selection of TPM Jan, 2014 Jan 13, 2014

7.Preparing the official letter from the Official in Charge/Ketua PelaksanaHarian PMU to Universities and Satker/PPK, about the Socialization ofTPM Selection for Package 01, 02, & 03

Feb. 2014 Feb. 07, 2014Feb. 13, 2014

8. Socialization of the TPM selection for package 01: Krui - Biha. Feb. 2014 Febr. 14, 2014

9. Socialization of the TPM selection for package 02: Padang Sawah –Simpang Empat and package 03: Manggopoh – Simpang Empat Feb. 2014 Febr. 18, 2014

10.Preparing the official letter from the Director of Planning as Chairman ofPMU to University of Bengkulu, about the Selection of TPM for package04: Ipuh - Bantal.

Jan, 2014 Febr. 19, 2014

11. Help the PMU on formulating the TPM Evaluation Team March 2014 Febr. 25, 2014

12. Implementation of selection of the TPM for four AWP-1 packages by TPMEvaluation Team March 2014 March 10, 2014

13. Delivery of the Preparatory Training for elected TPM for package 01: Krui– Biha in Lampung June 2014 June 5 - 6, 2014

14Delivery of the Preparatory Training for elected TPM for package 02:Padang Sawah – Simpang Empat, and package 03: Mangopoh – PadangSawah in West Sumatera

June 2014 June 17-18, 2014

15 Delivery of the Preparatory Training for elected TPM for package 04: Ipuh– Bantal in Bengkulu July 2014 July 7 – 8, 2014

16 Approval process of elected TPM July 2014 July 7 – 8, 2014

17 Assist PMU to prepare the Decree on Establishment the TPM of AWP-1WINRIP from Director of Planning DGH, as the Chairman of PMU.

August 2014 Sept. 1, 2014

18

Sending the Coordination Letter from Director of Planning, DirectorateGeneral of Highways to the Head of BBPJN Region I Medan, aboutSelection of the Third Party Monitoring (TPM) for package 05 (SimpangRampa – Poriaha, and package 15 (Sibolga – Tapanuli Selatan border) inNorth Sumatera.

October 2014 Oct, 07, 2014

19

Sent the Information Letter about participation of Third Party Monitoring(TPM) on WINRIP, from Director of Planning, Directorate General ofHighways to the University of Lampung (UNILA) for package 17 (SimpangGunung Kemala – Pugung Tampak) in Lampung Province.

October 2014 Oct, 03, 2014

20

Sent the Information Letter about participation of Third Party Monitoring(TPM) on WINRIP, from Director of Planning, Directorate General ofHighways to the University of Sumatera Utara (USU) for package 05(Simpang Rampa – Poriaha) in North Sumatera Province

October 2014 Oct, 03, 2014

21

Sent the Information Letter about participation of Third Party Monitoring(TPM) on WINRIP, from Director of Planning, Directorate General ofHighways to the University of Bengkulu (UNIB) for package 11 (Bantal –Mukomuko) and package 13 (Simpang Rukis - Tanjung Kemuning) in

October 2014 Oct, 20, 2014

Page 155: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

No Subject Activities of Third Party Monitoring (TPM) Target Completed

Bengkulu Province.

22Selection of the Third Party Monitoring (TPM) for packages 17 (SimpangGunung Kemala – Pugung Tampak) Lampung Province November 2014 Dec. 4, 2014

23 Selection of the Third Party Monitoring (TPM) for packages 11, and 13,Bengkulu Province

December 2014 Dec. 22, 2014

24 Socialization and Explaination of the Third Party Monitoring (TPM) forpackages 05, and 15 in Universitas Graha Nusantara Padang-sidempuan

January 2015 Jan, 28, 2015

25 Socialization and Explaination of the Third Party Monitoring (TPM) forpackages 05, and 15 in Universitas Sumatera Utara Medan

January 2015 Jan, 30, 2015

26The Employment Agreement or Memorandum of Understanding betweenTPM (packages 01, 02, 03, and 04) with the CTC WINRIP (PT. PlannersDjaja) has been signed.

November 2014 Feb. 26, 2015

27Delivery of the Preparatory Training for elected TPM for package 11:Bantal – Mukomuko and package 13: Simp. Rukis – Tj. Kemuning, inBengkulu

January 2015 March 11-12,2015

28 Selection of the Third Party Monitoring (TPM) for packages 05, and 15,Northern Sumatera Province March 2015 April 9, 2015

29 Selection of the Third Party Monitoring (TPM) for packages 06, and 19, inBengkulu Province May 2015 May 5, 2015

30Delivery of the Preparatory Training for elected TPM for package 06:Pasar Pedati – Kerkap and package 19: Lais – Bintunan, in BengkuluProvince

June 2015 June 4-5, 2015

31 The TPM of package 01 (Krui - Biha) has been doing site observations (fieldvisit) for the first phase July 2015

32 TPM package 02 (Padang Sawah - Simpang Empat) and package 03(Mangopoh - Padang Sawah), had conducted a field visit for first phase July 2015

33 The TPM of package 01 (Krui - Biha) has been done site observations (fieldvisit) for the second phase

3rd week ofAugust 2015

34 The TPM of package 04 (Ipuh - Bantal) has been done site observations(field visit) for the first phase

4th of August2015

35 The Community Development Team of CTC WINRIP has monitored theTPM’s Activity on TPM Package 01 Krui - Biha Agt. 19 -21, 2015

36 The Community Development Team of CTC WINRIP has monitored theTPM’s Activity on TPM Package 04 Ipuh - Bantal Agt. 27 -28, 2015

37The Community Development Team of CTC WINRIP has monitored theTPM’s Activity on TPM Package 02 (Padang Sawah – Simpang Empat)package 03 (Manggopoh Padang Sawah)

Sept. 10 - 11,2015

38The TPM of Package 02 (Padang Sawah – Simpang Empat) an package 03(Manggopoh Padang Sawah) had been done site observations (field visit)for the first phase

Sept, 2015

39Delivery of the Preparatory Training for appointed TPM for package 05:Sp. Rampa – Poriaha and package 15: Sibolga – Batas Tapsel in NorthSumatera Province

October 9, 2015

40 Delivery of the Preparatory Training for appointed TPM for package 17:Sp. Gunung Kemala – Pugung Tampak in Lampung Province Oct. 22, 2015

41 TPM package 04 Ipuh – Bantal has submitted their Field Visit MonitoringReport to PMU WINRIP Oct. 27, 2015

42 TPM package 03 Maggopoh – Padang Sawah has submitted their FieldVisit Monitoring Report to PMU WINRIP Nov. 11, 2015

43 TPM package 01 Krui – Biha has submitted their Field Visit MonitoringReport to PMU WINRIP Nov. 26, 2015

44The Community Development Team of CTC WINRIP has monitored theTPM’s Activity on TPM Package 11 (Bantal – Mukomuko) package 13(Simpang Rukis – Tanjung Kemuning) in Bengkulu Province

Dec. 03-04, 2015

Page 156: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

No Subject Activities of Third Party Monitoring (TPM) Target Completed

45 Selection of the Third Party Monitoring (TPM) for packages 07 and 12 inWest Sumatera Province Dec. 22, 2015

46 Selection of the Third Party Monitoring (TPM) for package 16 in BengkuluProvince Dec. 29, 2015

47 Selection of the Third Party Monitoring (TPM) for packages 08 and 10 inWest Sumatera Province Jan. 14, 2016

48The Community Development Team of CTC WINRIP has monitored theTPM’s Activity on TPM Package 04 (Ipuh – Bantal) and package 11 (Bantal– Mukomuko) in Bengkulu Province

Apr. 6-8, 2016

49The Community Development Team of CTC WINRIP has monitored theTPM’s Activity on TPM Package 02 (Padang Sawah – Simpang Empat) andpackage 03 (Manggopoh – Padang Sawah) in West Sumatra Province

Apr. 20-22, 2016

50The Community Development Team of CTC WINRIP has carry out ofSocialization of the TPM for package 14, 20, 21 to Andalas University ofpadang in BBPJN II Padang.

Apr. 27, 2016

51Community Development team has monitored the TPM activity onpackage 06 (Pasar Pedati – Kerkap) and package 19 (Lais – Bintunan) inBengkulu Province.

May 18–20, 2016

52Community Development team has carry out of TPM selection for package20 (Lubuk Alung - Sicincin) and package 21 (Lubuk Alung – Kuraitaji) inWest Sumatera Province

May 26, 2016

53Community Development team has delivered of the Preparatory Trainingfor appointed TPM for package 07and package 08 in West SumateraProvince

June 9, 2016

54Community Development team has monitored the TPM activity onpackage 05 (Simpang Rampa – Poriaha) and package 15 (Sibolga – BatasTapsel) in North Sumatera Province.

June 20–22, 2016

55 Community Development team has monitored the TPM activity onpackage 17 (Simpang Gn. Kemala – Pugung Tampak) in Lampung Province. July 27–29, 2016

56 Community Development team has carry out of TPM selection for package14 (Painan – Kambang) in West Sumatera Province Agt. 11–13, 2016

57 Community Development team has monitored the TPM activity onpackage 06 (Pasar Pedati – Kerkap) in Bengkulu. Agt. 24–26, 2016

58

Community Development team has delivered of the Preparatory Trainingfor appointed TPM for package 12 and package 14 in West SumateraProvince Sept. 27, 2016

59Community Development team has delivered of the Preparatory Trainingfor appointed TPM for package 20 and package 21 in West SumateraProvince

Oct. 13, 2016

60Community Development team has monitored the TPM activity onpackage 07 (Indrapura – Tapan) and package 12 (Kambang – Indrapura) inWest Sumatera Province.

Nov. 16–19, 2016

61 Community Development team has monitored the TPM activity onpackages 13 (Simpang Rukis – Tanjung Kemuning) in Bengkulu Proince. Nov. 28–30, 2016

62 Community Development team has monitored the TPM activity onpackage 05 (Simpang Rampa – Poriaha) in Nort Sumatera Province. Dec. 15 - 17, 2016

63 Community Development team has monitored the TPM activity onpackage 08 (Bt. Kota Pariaman – Manggopoh) in West Sumatera Province. Dec. 22 - 24, 2016

64 Community Development team has monitored the TPM activity onpackage 06 (Ps. Pedati – Kerkap) in Bengkulu Province. Dec. 29 - 31, 2016

65

Community Development team was facilitation TPM for package 04 (Ipuh- Bantal) and package 11 (Bntal – Mukomuko) of Bengkulu Province,meeting with Management of PT. Perentjana Djaja, on topic ofreimbursement of TPM monitoring cost.

Jan. 16, 2017

Page 157: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

No Subject Activities of Third Party Monitoring (TPM) Target Completed

66Community Development team has monitored the TPM activity onpackage 20 (Lubuk Alung – Sicincin) and package 21 (Lubuk Alung –Kuraitaji) in West Sumatera Province.

March 2 - 4, 2017

67 Community Development team has monitored the TPM activity onpackage 14 (Painan – Kambang) in West Sumatera Province. March 15 - 17, 2017

68 Community Development team has monitored the TPM activity onpackage 17 (Simp. Gng Kemala – Pugung Tampak) in Lampung Province. March 22 - 24, 2017

69 Community Development team has monitored the TPM activity onpackage 12 (Kambang – Indrapura) in West Sumatera Province. April 10 - 12, 2017

70 Community Development team has delivered of the Preparatory Trainingfor appointed TPM for package 16 in Bengkulu Province April 27, 2017

71 Develop Report of Preparatory Training for TPM of package 16 (Sebelat -Ipuh) in Bengkulu May 2, 2017

72 Develop Evaluation Report on Implementation of Third Party Monitoring(TPM) from the project beginning up to May 2017 May 4-8, 2017

73Prepare draft Special Report of the Implementation of Anti-CorruptionAction Plan (ACAP) as a part of draft CTC WINRIP Final Report or ProjectCompleting Report

Begin on May 9,2017

74Prepare the response to Supreme Audit Board / Badan PemeriksaKeuangan (BPK) Republic of Indonesia findings on funding the Third PartyMonitoring from Provisional Sums.

May 29-30, 2017

75Community Development team has monitored the TPM activity onpackage 15 (Sibolga – Batas Tapsel) and package 05 (Simpang Rampa –Poriaha) in North Sumatera Province.

June 13 - 17, 2017

76 Community Development team has monitored the TPM activity onpackage 16 (Seblat – Ipuh) in Bengkulu Province. July 26 - 28, 2017

77Community Development team has monitored the TPM activity onpackage 08 (Batas Kota Pariaman – Manggopoh) in West SumateraProvince.

Agt. 28 - 30, 2017

78 Community Development team has monitored the TPM activity onpackage 14 (Painan –Kambang) in West Sumatera Province. Sept. 14 - 16, 2017

79 Community Development team has monitored the TPM Activity forPackage 12 (Kambang – Indrapura) phase 2, in West Sumatera Province. Oct. 04 – 06, 2017

80Community Development team has monitored the TPM Activity forPackage 17 (Simpang Gunung Kemala – Pugung Tampak) phase 3, inLampung Province.

Oct. 16 – 18, 2017

81 Community Development team has monitored the TPM Activity forPackage 20 (Lubuk Alung – Sicincin) phase 2, in West Sumatera Province Oct. 26 – 28, 2017

82 Community Development team has monitored the TPM Activity forPackage 21 (Lubuk Alung – Kuraitaji) phase 2, in West Sumatera Province. Nov. 15 – 17, 2017

83 Community Development team has monitored the TPM Activity forPackage 07 (Indrapura – Tapan) phase 2, in West Sumatera Province Nov. 22 – 24, 2017

84Community Development team has monitored the TPM Activity for thirdphase of Package 08 (Batas Kota Pariaman – Manggopoh), in WestSumatera Province.

Dec. 13 – 15, 2017

85Community Development team has monitored the TPM Activity forsecond phase of Package 13 (Simpang Rukis – Tanjung Kemuning) inBengkulu Province

Dec. 20 - 22, 2017

86 Community Development team has monitored th TPM Activity for thirdphase of Package 07 (Indrapura – Tapan)in West Sumatera Province Jan. 22 – 25, 2018

87 Community Development team has monitored th TPM Activity for thirdphase of Package 20 (Lubuk Alung – Sicincin) in West Sumatera Province Feb. 7 – 9, 2018

Page 158: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

No Subject Activities of Third Party Monitoring (TPM) Target Completed

88Community Development team has monitored the TPM Activity for thirdphase of Package 05 (Simpang Rampa – Poriaha) in North SumateraProvince

Feb. 21 – 23, 2018

89Community Development team has monitored the TPM Activity forsecond phase of Package 15 (Sibolga – Batas Tapsel) in North SumateraProvince

March 21 – 23,2018

90 Community Development team has monitored the TPM Activity forsecond phase of Package 16 (Seblat – Ipuh), in Bengkulu Province.

March 26 – 28,2018

91Community Development team has monitored TPM Activity for secondphase of package 13 (Simpang Rukis – Tanjung Kemuning) in BengkuluProvince.

April 19 – 22, 2018

92 Community Development team has monitored TPM Activity for thirdphase of package 12 (Kambang – Indrapura) in West Sumatera Province. May 03 – 06 2018

93 Community Development team has monitored TPM Activity for secondphase of package 14 (Painan - Kambang) in West Sumatera Province. May 22 – 24 2018

94 Community Development team has monitored TPM Activity for thirdphase of package 15 (Sibolga – Batas Tapsel) in North Sumatera Province. July 11 – 13, 2018

95 Community Development team has monitored TPM Activity for thirdphase of package 16 (Seblat - Ipuh) in Bengkulu Province. July 25 – 27, 2018

Page 159: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

Appendix H.3Works Activities on Complaints Handling Mechanism System (CHS)

March 2013 – August 2018

No Subject of Activities / Item of Tasks on Handling CHS Completion Plan/Progress Condition

1 Review of Minister Decree of Public Works No. 323/2005 concerning the procedures ofHandling input from communities on the environment of the Ministry of Public Works April 18, 2013

2 Preparation of Complaints Register and the complaints address (developing of web site ofWINRIP) and provided ACAP to inputting data in the web site.

Completed on themiddle of Feb. 2014.

3 Preparation of Complaint Handling Procedure (already available on the websiteapplication http://www.winrip-ibrd.com) April 2014

4The completion of the Initial investigation of a complaint Procedure, and the procedurefor the investigation of Complaints, as well as the conclusion of investigation (alreadyavailable on the website application http://www.winrip-ibrd.com)

April 2014

5 Monitored and noted the public complaints via SiPP website and WINRIP website, butuntil December 2014 have no complaint about the WINRIP programs December 2014

6

Clarification of Community complaint for package 02 & 03 by Jejak Media Group (JMG) byMr. Buyung on gravel aggregate materials, routine maintenance, and watering work site(dust pollution). It has been followed up by PPK 09 and PPK 10 to hold a clarificationmeeting, followed by the elements PPK, Supervision Consultant (DSC), and Jejak MediaGroup (JMG).

March 23, 2015

7

Clarification of information of work implementation on package 04: Ipuh - Bantal wasunfavorable, by TPM member (Mr. Hardiansyah, ST, MT). The information obtained fromthe local mass media. The problem is that the people around the location of the packageIpuh - Bantal especially road users complained about the excavation of road widening isleft open for an extended period of time without equipped with signs and safety fence,felt very dangerous, especially when driving at night, and according to the informationsome of the riders had been an accident which the vehicle plunged into the hole dug.This information has been followed up by PPK 01 Bengkulu together with the SupervisionConsultant (DSC Field Team) to instruct the Contractor to install traffic signs and safetyfences in places that endanger of road user

March 26, 2015

8

On May 11, 2015, Mr. Dr. M. Fauzi, ST, MT,, the main observer of the Third PartyMonitoring for Package 11 (Bantal - Mukomuko) Bengkulu Province, conveyinginformation from local newspaper clippings (Koran Rakyat Bengkulu) containing news thata 1.5-year-old toddler fell and nearly drowned in the excavation of the road wideningPackage 11 (Bantal - Mukomuko) which flooded about 80 cm deep. That is because theexcavation is situated in the location residential and not immediately undertaken, andwere not given the signs and safety fence.The complaint was submitted to the PMU and forwarded to the related PIU / PPK to beclarified. Until the end of May there has been no follow-up report to the complaint fromthe PIU / PPK 01 linked.

May 11, 2015

9

The CHS team has been received the copy of complaints letter from Tender Participantson package 08 to the Procurement Committee. Disclaimer of submitted by the tenderparticipants of package 08 (Batas Kot Pariaman – Manggopoh) PT. Adhi Karya (Persero)Tbk – PT. Yasa Patria Perkasa, JO by letter No: ADHI-YASA/12/I/2016 dated January 12,2016, to the Procurement Committee concerning to the results of Bid Evaluation Report(BER) section III, clause 4, point 4.2 (b): Specific Construction Experience in Key Activitiesspecifically on the experience of aggregate base production.

Jan. 15, 2016

10

CHS team has been received the other similar complaint to the Procurement Committeewas submitted by the same tender participant of package 12: Painan – Kambang (PT. AdhiKarya (Persero) Tbk – PT. Yasa Patria Perkasa, JO) by letter No: ADHI-YASA/11/I/2016dated January 4, 2016. The content of complaint was the similar subject i.e. the results ofBid Evaluation Report (BER) section III, clause 4, point 4.2 (b): Specific ConstructionExperience in Key Activities specifically on the experience of aggregate base production

Jan. 15, 2016

Page 160: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

No Subject of Activities / Item of Tasks on Handling CHS Completion Plan/Progress Condition

11

CHS team has been received the complaints from Riki Susanato (Konsorsium Nasional LSMProvinsi Bengkulu) dated February 02, 2016. Riki Susanato and Edy Novriansyah had sent aletter No: 06/Khusus/XII/2015 dated December 11, 2015 on a request for publicinformation related to the documents of WINRIP project in Bengkulu province. But thisrequest was unable to fulfill by Satker PJN Wil. I of Bengkulu Province, especially inrelation to Contract Document / Letter of Agreement between the ProjectImplementation Unit of WINRIP for Bengkulu Province with the Contractors.By not granting of the request of the documents, then Riki Susanto delivered thecomplaint through the Complaint Handling System (CHS) of WINRIP website (www.winrip-ibrd.com). The complaint was submitted to the PMU WINRIP and the relevantstakeholders to immediately follow-up.

Feb. 02, 2016

12

On January 20, 2016, there was a World Bank letter No. 281 on reviewing Bid EvaluationReport (BER) for Package 16: Seblat – Ipuh in Bengkulu Province. World Bank has and havecomments on the Bina Marga proposed rejection of the five lower priced bidders.As a follow up of these comments, on February 10, 2016 has been held DiscussionMeeting to respond to the letter. Meeting followed by elements from the WB, PMU, PokjaPJN Reg. 1 of Bengkulu Province. Clarification should be explained in the revision of BERand sent to World Bank.

January 20, 2016February 10, 2016

13

The Complaint from Civil Society of villages in around the project STA 28+900 (DesaPondok Kandang, Desa Pondok Suguh, dan Desa Karya Mulya) was submitted through aletter of district head (Surat Camat) of Pondok Suguh, No. 620.52/56/K.05/IV/2016 datedApril 11, 2016, sent to the Supervision Consultants (Field Team DSC of Package 04) on therequest of one extra culvert / box culvert again, because the existing culvert in small sizeand its surface less downward, which is predicted when it rains the water could not floweasily or drained from the settlement and the Villages will be flooded.

April 11, 2016

14

Complaint by Buyung Fajri from Jejak Community sent to PMU WINRIP" via [email protected] on subject of performance audit of PT, JAYA KONTRUKSI MP.Tbkthat was Addendum until April 19, 2016 but the work is still ongoing until April 23 2016,how it could happen, we ask for explanation

May 11, 2016,

15

Complaint by Buyung Fajri from Jejak Community sent to PMU WINRIP" via [email protected] on subject evaluation of stone masonry works on bridgeapproach of Air Gadang Bridge in package 02 (Padang Sawah – Simpang Empat) WestSumatera Province. The stone masonry works by contractor PT. JAYA KONTRUKSI MP.Tbkis bed quality, did not match to the specification

May 14, 2016

16

Complaint by Buyung Fajri from Jejak Community sent to PMU WINRIP" via [email protected] and to Menteri PUPERA by e-mail minister of Public Works and onsubject of the National Road in Pasaman Barat - West Sumatra province, many of themwere which seriously damaged.

May 17, 2016

17Complaint by Buyung Fajri from Jejak Community sent to PMU WINRIP" via [email protected] on subject that Air Gadang Bridge until May 31, 2016 is not yet befinished.

May 31, 2016

18

The Community Development Officer and Information Management Specialist wasmeeting with World Bank (Mr. Andri Wibisono) on topic of completeness the WINRIPwebsite included Complaint Handling System (CHS). The main subject is the completenessof the website application program, the completeness data sources, and the applicableand accessible of this website, so everyone can access or find the data that they needs.

August 2, 2016

19

On January 30, 2017 Complaint Unit has received one complaint from someone namedBuyung Fajri from Non-Government Organization “JEJAK Community”. It is complained ofis that, the contract value is not listed on the information board and workers of heavyequipment Operators are not using personal safety (K3) i.e helmet

January 30, 2017

20Complaint Unit has received one complaint from Buyung Fajri from Non-GovernmentOrganization “JEJAK Community” thru email dated February 15, 2017, regarding theimplementation of WINRIP Packages No.21 Lubuk Alung – Kuraitaji

February 15, 2017

Page 161: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

No Subject of Activities / Item of Tasks on Handling CHS Completion Plan/Progress Condition

21On February 16, 2017, Complaint Unit has received one complaint from Buyung Fajri (Non-Government Organization “JEJAK Community”) thru email, regarding the maintenance ofWINRIP Packages No.03 Manggopoh – Padang Sawah

February 16, 2017

22

Complaint Handling Unit of CTC has received public complaints from Buyung Fajri (Non-Government Organization “JEJAK”), thru email on March 5, 14, and 21, 2017, regardingthe condition of retaining wall on approach road of Air Gadang Bridge in Packages No. 02Padang Sawah – Simpang Empat. This package has been PHO on April 14, 2016 is nowentered the maintenance period.

March 5, 14, and21, 2017

23Complaint Handling Unit of CTC has received public complaints from Buyung Fajri (Non-Government Organization “JEJAK”), thru email on March 21, 2017, regarding theimplementation of WINRIP Packages No.21 Lubuk Alung – Kuraitaji

March 21, 2017

24

On April 6, 2017 was complaint from Berita Harian Sumbar http://sumbar.auditpos.com(Non-Government Organization), thru email to the World Bank’s Highway Engineer Mr.Agus Sjamsudin ([email protected]) regarding the implementation of Package20 Lubuk Alung – Sicincin on concrete reinforcement of drainage structure was not inaccordance with the specification, and the bad quality of mortar for retaining wall

April 6, 2017ClarifiedApril 13, 2017

25

Complaint Handling Unit of CTC has received public complaints from Buyung Fajri (Non-Government Organization “JEJAK”), thru email on April 7, 2017 and April 23, 2017,regarding the implementation of WINRIP Packages No.21 Lubuk Alung – Kuraitaji. TheContractor PT. MULTI STRUCTURE ignores the road user's safety.

April 7, 2017April 23, 2017

26Prepare the Response of the complaints from Mr. Buyung Fajri (Non-GovernmentOrganization “JEJAK”) of April 23, 2017 regarding the implementation of WINRIP PackagesNo.21 Lubuk Alung – Kuraitaji

May 2, 2017

27Complaint Handling Unit of CTC has received public complaints thru [email protected] on July 10, 2017, regarding the implementation of package 12(Kambang - Indrapura) in West Sumatera Province, on subject of Asphalt pavement quality.

July 10, 2017

28

The Complaint Handling Unit of PMU has received one public complaints submitted by Mr.Buyung Fajri (Non-Government Organization "JEJAK") thru email([email protected]), regarding the implementation of WINRIP Package No. 12:Kambang – Indrapura in West Sumatera Province.The Subject of complaint is the Contractor PT. LMA - CTA, performs paving/asphaltingwork at the night and during the rain. This would reduce the quality of work is not inaccordance with specifications

August 20, 2017

29 The Complaint Handling Unit has received one complaint from NGO “Portal Bengkulu”regarding implementation of Package 16 (Sebelat – Ipuh) Dec. 19, 2017

30

The public complaints submitted by Mr. Yudha from “Masyarakat Transportasi Indonesia”(Indonesian Transportation Society) of West Sumatera Province, thru WhatsApp to theMinister of Public Works and Housing, on January 30, 2018 regarding the implementationof WINRIP Package No. 21: Lubuk Alung – Kuraitaji in West Sumatera Province.The subject of the complaint is that package 21 (Lubuk Alung - Kuraitaji) should be finished(Professional Hand Over "PHO") or take over on December 31, 2017. The reality ofimplementation progress is only about 50%, even execution time is extended or anaddendum of time. This is an indication that something is wrong with the implementationof the package.Up to May 2018 the PMU/PIU has not provided information on the answer to thecomplaint.

Jan. 30, 2018

Other Activity

1 The establishment of the settlement Commission Handling the Complaint under theInspectorate General of the Ministry of Public Works (Executing Agency) if it necessary

Will establish if there is acase that needs specialhandling

2Preparation of the device for Executing Agency such as: Procedures announcement ofpenalties, procedures for the annual Survey, Procedure Annual Independent Review, theprocess of Auctions

Done by ProcurementSpecialist and theContract ExaminerCommittee

Page 162: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

No Subject of Activities / Item of Tasks on Handling CHS Completion Plan/Progress Condition

3 The development of a code of conduct and actions for Implementing Institutions/Implementing Agency (Bidders, Suppliers, contractors and Consultants) Done by PMU of DGH

4 Support the PMU in the Management and Monitoring of the implementation policy inhandling public complaints

Have been carried outthroughout projectimplementation period

Page 163: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

Appendix H.4Works Activities on Publication / Disclosure Activities

January 2013 – August 2018

No Subject of Activities / Item of Tasks of Publication / Disclosure Completion Plan/Progress Condition

1 Conducted Workshop of Procurement Document Evaluation for POKJA,Satker/PPK, Balai BBPJN and PMU

February 28, 2013– March 01, 2013

2 Conducted Workshop of World Bank Guidelines of Procurement for WINRIP tothe POKJA, Satker/PPK, Balai BBPJN and PMU April 24 – 25, 2013

3 Review training materials on Project Management Manual (PMM), especiallyCHAPTER XI of the anti-Corruption Action Plan (ACAP)

First updating April 29, 2013

4 The second Review of training materials on Project Management Manual(PMM), Chapter I - XII

Second updating onDecember 18, 2013

5 The third Review of training materials on Project Management Manual (PMM),Chapter I - XII

third updating onApril, 2014

6. Preparing Method Transparency to the Public, and Improvement the proceduresto the Public Disclosure through information media (website).

Establishment of InformationSystem (MIS) was finish on

March 2014

7. The updating of Project Management Manual (PMM), Chapter 3, 9, 11, and 13,has been held in Bogor June 2014

8 Delivery of the Preparatory Training for elected TPM for AWP-a packages: 01,02, and 03 June 2014

9 Delivery of the Preparatory Training for elected TPM for AWP-a packages: 04 July 2014

10 The implementation of Dissemination/training of the PMM to Stakeholders forPackages 01, 02, 03, and 04 September 10 - 11 2014

11Inputting / upload / update of data/documents/reports of the CommunityRepresentative Observers (CROs) activities for packages 01, 02, 03, 04, 17, 11,13, 05, 06, 19, and 15 into the WINRIP’s website.

From Augt 2013 – April, 2015

12Inputting / upload / update of data/documents/reports of the Third PartyMonitoring (TPM) activities for packages 01, 02, 03, 04, 17, 11, and 13 into theWINRIP’s website.

From Augt 2013 – April, 2015

13Inputting / upload / update of data/documents/reports of Procurement ofContractors for packages 01, 02, 03, 04, 17, 11, 13, 05, 06, and 19 into theWINRIP’s website.

From Augt 2013 – April, 2015

14Inputting / upload / update of data/documents/reports of Environmentalactivities for packages 01, 02, 03, 04, 17, 11, 13, 05, 06, and 19 into the WINRIP’swebsite.

From Augt 2013 – April, 2015

15Inputting / upload / update of data/documents/reports of Social Safeguard /LARAP for packages 01, 02, 03, 04, 17, 11, 13, 05, 06, and 19 into the WINRIP’swebsite.

From Augt 2013 – April, 2015

16Inputting / upload / update of Progress Report/ Actual Status (fisichal worksand financial) of each package that has been contracted (packages 01, 02, 03,and 04) into the WINRIP’s website.

From Augt 2013 – April, 2015

17 Inputting / upload of Monthly Progress Report (MPR December 2012 – December2014) into the WINRIP’s website. Every Month

Page 164: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

No Subject of Activities / Item of Tasks of Publication / Disclosure Completion Plan/Progress Condition

18 Inputting / upload of Quarterly Progress Report (QPR December 2012 –December 2014) into the WINRIP’s website. Every Three Months

19 Delivery the IFM Training for Stakeholders (Official and staff of Satker, Officialand staff of PPK) packages 01, 02, 03, and 04. 26 – 27 November 2014

20 Publish the Quarterly Newsletter on official website of MPW and WINRIP’swebsite

Every three months forQuarterly Newsletter October –

December 2015

21 Delivery the IFM Training for Stakeholders (Official and staff of Satker, Officialand staff of PPK) packages 05, 11, 13, and 17. Feb. 11 - 12, 2015

22 Report of Technical and Financial Audit Consultants (TFAC) for Packages 02 and03 has been received from TFAC Team Feb. 27, 2015

23

Delivery of the Preparatory Training for elected TPM for package 11: Bantal –Mukomuko and package 13: Simp. Rukis – Tj. Kemuning, in Bengkulu. Thistraining followed the elements of TPM, Satker/PPK, Contractors, SupervisionConsultants, and Balai BBPJN III Palembang.This training is intended to provide an explanation of the scope of duties of TPMand provide information to all elements involved in the implementation of theproject that the community be involved in monitoring the implementation ofthe project which is represented by the TPM, in accordance with the LoanAgreement.

March 11 – 12, 2015

24 Publish the Quarterly Newsletter on official website of MPW and WINRIP’swebsite

Every three months forQuarterly Newsletter January –

March 2015

25Delivery of PMM Socialization to Stakeholders (Balai BBPJN III, PIU/PPK,contractors and Supervision Consultants ‘DSC’) for four Packages (06, 11, 13,and 19) in Bengkulu Province

May 6 – 7, 2015

26

Delivery of the Preparatory Training for elected TPM and Work Plan for manageand monitor the Environment / Rencana Kerja Pengelolaan dan PemantauanLingkungan (RKPPL) for package 06: Ps. Pedati – Kerkap and package 19: Lais –Bintunan, in Bengkulu. This training followed the elements of TPM, Satker/PPK,Contractors, Supervision Consultants, and Balai BBPJN III Palembang.

June 4 – 5, 2015

27 Publish the Quarterly Newsletter on official website of MPW and WINRIP’swebsite

Every three months forQuarterly Newsletter April –

June 2015

28 The Mid-Term Report of the first semester 2015 has been written by the early ofJuly 2015 July, 2015

29 Delivery of PMM Training for Stakeholders (PPK, contractors and SupervisionConsultants ‘DSC’) for Packages 17, 05, and 15 November 23 – 24, 2015

30Inputting / upload / update of data/documents/reports of the CommunityRepresentative Observers (CROs) activities for packages 07, 08, 10, 12, 14, 16,20 and 21 into the WINRIP’s website.

From May – Dec, 2015

31Inputting / upload / update of data/documents/reports of the Third PartyMonitoring (TPM) activities for packages 05, 06, 07, 12, 15, 19 and 16 into theWINRIP’s website.

December, 2015

32Inputting / upload / update of data/documents/reports of Procurement ofContractors for packages 07, 08, 10, 12, 14, 16, 20 and 21 into the WINRIP’swebsite.

From June – Dec, 2015

33 Inputting / upload / update of data/documents/reports of Environmentalactivities for 07, 08, 10, 12, 14, 16, 20 and 21 into the WINRIP’s website. From May – Dec, 2015

34Inputting / upload / update of data/documents/reports of Social Safeguard /LARAP for packages for 07, 08, 10, 12, 14, 16, 20 and 21 into the WINRIP’swebsite.

From May – Dec, 2015

Page 165: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

No Subject of Activities / Item of Tasks of Publication / Disclosure Completion Plan/Progress Condition

35Inputting / upload / update of Progress Report/ Actual Status (physically works,financial and audits) of each package that has been contracted (packages 05, 06,07, 11, 13, 15, 17 and 19) into the WINRIP’s website.

From May – Dec, 2015

36Inputting / upload / update of data/documents/reports of the CommunityRepresentative Observers (CROs) activities for packages 14, 20 and 21 into theWINRIP’s website.

January, 2016

37Inputting / upload / update of data/documents/reports of the Third PartyMonitoring (TPM) activities for packages 14, 20, and 21 into the WINRIP’swebsite.

December, 2015

38 Updated the Project Management Manual (PMM) Chapter III : Planning andProgramming January, 2016

39 Review and Updated of the Project Management Manual (PMM) Chapter IX :Performance Monitoring and Evaluation, March, 2016

40 Review and Updated of the Project Management Manual (PMM) Chapter XI:Anti-Corruption Action Plan (ACAP) April, 2016

41Review and Updated of Power-point presentation of the Project ManagementManual (PMM) Chapter IX : Performance Monitoring and Evaluation, Chapter XI:Anti-Corruption Action Plan (ACAP)

June, 2016

42

The Information Management Specialist and Community Development Officerimmediately follow up the results of the meeting with World Bank to becompleted and perfected. The results of that meeting be used as an ingredientof Kick-off and Wrap-up Meeting, which would then be inserted in the Final AdieMemoire of August 11, 2016

August 11, 2016

43

Delivery of PMM Socialization to Stakeholders (Balai BPJN III, PIU/Satker Region Iand II of West Sumatera, PPK 06 (pack. 20), PPK 10 (Pack. 08 & 21), PPK 14(Pack. 14), PPK 15 (Pack. 07), contractors and Supervision Consultants ‘DSC’) forfour Packages (07, 08, 14, 20, and 21) in West Sumatera Province

Augt. 29 –31, 2016

44 Delivery of TPM Preparatory Training for packages 12 and 14 in Padang, WestSumatera Sept. 26 – 28, 2016

45The CTC (Community Development Team) has been carried out preparatorytraining for Third Party Monitoring (TPM) of packages 20 and 21 in Padang, WestSumatera.

October 13, 2016

46 Review and identify the changing of Project Management Manual (PMM)Modules from Revision-1 version to Revision-2. Oct. 18 - 24, 2016

47Prepare draft of Agreement Letter of Director of Roads Net WorkingDevelopment on establishment of Working Group /Task Force for updating andimprovement of the PMM.

Oct. 25 - 27, 2016

48 Prepare draft proposal of Price Adjustment /Escalation Workshop for theWINRIP Oct. 28 – Nov. 14, 2016

49 During January 2017 all CTC Professional were prepare the updating the ProjectManagement Manual (PMM) January 2017

50During February 2017 all CTC Professional were updated the ProjectManagement Manual (PMM) for revision 2. The Community DevelopmentOfficer was updated Chapters III, IX, XI, and XIII.3.

February 2017

51Prepare the response to Supreme Audit Board / Badan Pemeriksa Keuangan(BPK) Republic of Indonesia findings on funding the Third Party Monitoring fromProvisional Sums, and meeting with BPK.

May 29-30, 2017

52During January 2018 the Community Development Officer was updated theProject Management Manual (PMM) for last final update of Chapters III, IX, XI,and XIII.3.

Jan. 15 – 19, 2018

53 During March 2018 the Community Development Officer in collaboration withInformation Management Specialist was updated the list of Complaint Handling March 2018

Page 166: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

No Subject of Activities / Item of Tasks of Publication / Disclosure Completion Plan/Progress Condition

in website of WINRIP (www.winrip-ibrd.com)

54

On April 2018 the Community Development Officer in collaboration withInformation Management Specialist was updated the data of CROs of Package05A Slope Protection of Roads Segment of Rampa – Poriaha in North SumateraProvince in website of WINRIP (www.winrip-ibrd.com)

April 2018

55 During August 2018 the Community Development Officer was updated theProject Management Manual (PMM) Chapters III, IX, XI, and XIII.3. August 2018

Activities Plan for Next Step

1 Delivering the other training programs of WINRIP shall inline of projectimplementation progress.

Depend on projectimplementation progress

2 Public Expose on ACAP to the civil society forum in each project location (eachpackage)

Before the construction worksstarted

3 Monitoring of the implementation of disclosure and transparency of informationto each package during contraction period.

Plan for three time monitoringto field for each package during

contraction period

Page 167: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

Appendix H.5Status of WINRIP’s Anti-Corruption Action Plan Activity

Edition: August, 2018

RISKAREA NoACTIONS STATUS (as of August 31, 2018)

Enha

nced

Disc

losu

re a

nd T

rans

pare

ncy-

1 MPWH will provide the contact information forcomplaints related to WINRIP in the PIP, PMM, andMPWH website and in the bidding documents.

Complaint Handling System has been established, written in PMM(Chapter 11.4), and published on DGH website(http://binamarga.pu.go.id) linked to WINRIP website(http://www.winrip-ibrd.com).Contact information is provided in the Bidding Documents Chapter 2:Instruction to Bidders (Instruksi Kepada Peserta Lelang - IKP 34).

2 Work Programs and Procurement Plan published onthe official MPWH website and made it available tothe public.

Work Programs and Procurement Plan available in the MPWHwebsite (http://eproc.pu.go.id) and in the WINRIP website (onhttp://www.winrip-ibrd.com, click Pengadaan to see all the data onProcurement Plan, Procurement Information, and List of Contractawarded).- Procurement data for package 05A is under process uploading in to

the website.3 Procurement Plan updated annually. The last version has been sent to the WB at March 12, 2018.

4 Quarterly newsletter published on the official websiteof MPWH, including information concerning the list ofcontracts, implementation progress, project-relatedworkshops and the number, typology, and status ofcomplaints.

Quarterly newsletter is updated every three months. Threenewsletters were published in 2015 (the first one corresponds to theperiod between January and March, 2015); and three newsletterswere also published in 2016. The latest newsletter (January – March,2018) has been published on the WINRIP website(http://www.winrip-ibrd.com) linked to DGH website(http://binamarga.pu.go.id).These newsletters include the summary of the physical worksimplementation progress, the list of the trainings/workshops hold,and other relevant information on contracting aspects.

5 Quarterly newsletter sent by MPWH to the civilsociety forum in each project province in hard copy orthrough an electric mailing system.

The Quarterly Newsletter is always sent to the civil society forum: i.e.Indonesian Road Development Association/ HimpunanPengembangan Jalan Indonesia (HPJI) and Indonesian TransportationSociety/Masyarakat Transportasi Indonesia (MTI) in central level andto the provincial level where the WINRIP project are developed, by e-mail.The latest newsletter of April – June 2018 has been published andbeen sent to the civil society forum by e-mail and by mail in July 2018.

6 Bidding documents, short-list of consultants andrequests for proposals (this provision does not includeactual bids and proposals), issued in accordance withthe procurement provisions of the loan agreement,are available to any member of public promptly uponrequest, subject to payment of a reasonable fee forproducing bidding documents and request forproposals. The documents are available until a yearafter completion of the contract for the goods, worksor services in question.

The Bidding Documents such as: Standard Bidding Document, BidInvitations, Instruction to Bidders, General Specifications, DetailedEngineering Design/Drawing, General Condition of Contracts, SpecialCondition, Bill of Quantity, Owner Estimate, etc, are available onMPWH website (http://eproc.pu.go.id) and some of them were alsouploaded in WINRIP website (http://www.winrip-ibrd.com). Packages 01, 02, 03, 04, 05, 06, 07, 08, 11, 12, 13, 14, 15, 16, 17,

19, 20, and 21 have been already awarded. Packages 09, 10 and 18 were cancelled from list of WINRIP Program. The bidding of Package 05A (Slope Protection of Road Segment in

Rampa – Poriaha / Mungkur in North Sumatera Province, on April27, 2018 is failed. Plan for re-bid on September 2018.

7 Information as follows published in UNDB on-line, andon MPWH website within two weeks of contractaward (after Bank’s no objection): (a) name of eachbidder who submitted a bid; (b) bid prices as read outat the bid opening; (c) name and evaluated prices ofeach bid; (d) name of bidders whose bids wererejected and the reasons for rejection; and (e) name ofthe winning bidders and the prices, as well as theduration and summary scope of the contract awarded.

ICB Contract Award Notices for packages 01, 02, 03, 04, 05, 08, 11,12, 13, 15, and 17 were published in UNDB on-line and on theMPWH website (http://www.PU.go.id).

NCB Contract Award Notices for packages 06, 07, 14, 16, 19, 20,and 21 were published on the MPWH website. Package 05A isunder procurement process.

Page 168: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

RISKAREA NoACTIONS STATUS (as of August 31, 2018)

8 List of all contracts awarded in the three monthspreceding the date of the request by any person orcompany request are available, including the name ofthe contractor/ supplier/ consultant, the contractamount, the number of bidders/proposals, theprocurement method and the purpose of the contract.

All this information is available on the WINRIP website. However, norequest from any person or company has been received.The physical progress data of the under-construction packages hadbeen completed including contract changes such as review design,CCO, technical justification, memorandum, addendum, etc.

9 Final audit reports (financial or otherwise, includingqualified audit reports) and all formal responses of theGovernment in relation to such reports should bepublicly available on the MPWH website within onemonth after the report is accepted as final.

The Final Audit for the years 2012, 2013 2014, and 2015 have beencompleted, and the related reports uploaded on the WINRIP website.Moreover, DGH has sent the audit results response to the Bank.The Final Audit for 2016 had been held by BPK, and the Findings hasbeen followed-up by DGH and the related parties, and the AuditResponse Report has been sent to the Bank by December 18, 2017.The BPK’s Audit Finding Report for 2017, not yet been received bythe DGH.

10 Financial, technical, and physical progress of theproject monitored by an IT system (integrated SiPP) aspublicly accessible project monitoring system.

These reports are available on the WINRIP website: The financial, technical, and physical progress have been

completed with information of contractors’ names, number ofcontract, date of contract, contract volume/amount, duration ofcontract, etc.

The tutorial guidance has been developed and sent by MISspecialist.

The financial progress report is updated every three months as theIFR quarterly report.

The technical and physical progress is updated every month as theMonthly Progress Report, and every three months as the QuarterlyProgress Report.

Enha

nced

Civ

il So

ciety

Ove

rsig

ht

11 Representatives of civil society groups invited toattend the public bid openings and other keyprocurement steps. Community RepresentativeObservers (CROs) invited from local universities orother selected independent institutions. Attendancelist for the procurement/selection process signed.

The CROs for 19 packages (01, 02, 03, 04, 05, 06, 07, 08, 10, 11, 12,13, 14, 15, 16, 17, 19, 20, 21) have been appointed, and haveattended the required meeting (Pre-Bid Meeting and Bid OpeningMeeting). Attendances list are available.

The CRO for package 05A has been appointed on April 24, 2018,and has been attended the Pre-Bid meeting on April 27, 2018.

12 Guidelines on appropriate procedures for the aboveprovided in the PMM.

The Appropriate procedures are written in PMM Chapter 11.2, and inthe TOR of CROs Selection.

13 Third Party Monitoring (TPM) mechanism established.This mechanism includes regular sharing ofinformation with the media.

TPM for 19 packages had been selected (packages 01, 02, 03, 04,05, 06, 07, 08, 10, 11, 12, 13, 14, 15, 16, 17, 19, 20, and 21).

TPM Letter of Agreement for the above-mentioned 19 packageshad been signed.

The Agreement of TPM operational funding between TPM and CTC(PT. Perentjana Djaja) has been signed for the above-mentioned 18packages.

Packages 09, 10, and 18 were cancelled from the list of WINRIPprogram.

TPM for package 05A under preparing to appointing, waiting thecompleting bidding process.

14 Annual Accountability Meetings held. First meetingheld at the province level before procurement ofcontractors or service providers.

The Annual Accountability Meetings were held through the followingactivities: Coordination meeting at the Regional level (Balai- BBPJN) and in

each province. Public Expose of LARAP to the community around the project area. Socialization of projects during selection of CROs and TPM at local

universities near project sites and in the same province. (Detaildates of socialization meeting and training of the CROs and TPM canbe found in the Monthly or Quarterly Report of WINRIP on theWINRIP website).

Public expose and dissemination of information to inhabitantsaround the project is delivered through Project Information Board.

Page 169: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

RISKAREA NoACTIONS STATUS (as of August 31, 2018)

PMM workshop has been carried out in:o Padang on September 12, 2014 for packages 01, 02, 03, and 04.o Bengkulu on May 6 – 7, 2015 for packages 06, 11, 13, and 19.o Bogor on November 24 – 25, 2015 for packages 05, 15, and 17.o Padang on August 29 – 30, 2016, for packages 07, 08, 12, 14, 20,

and 21.o Bengkulu on April 27, 2017 for package 16.

Enha

nced

Com

plai

nts H

andl

ing

Mec

hani

sm

15 Enhanced complaints handling mechanism, whichincludes maintaining project complaint log and filingto monitor status of follow-up of each complaint,established by the MPWH.

A Complaint Handling System has been established, written in PMM(Chapter 11.4), and published on WINRIP website (http://chs.winrip-ibrd.com).

16 Complaints received acknowledged to thecomplainant by the PIU within seven (7) days ofreceipt with a copy to PMU, DGH and then WorldBank. Bid-related complaints received during bidevaluation period responded after the contract award.All complaints handling component included in theMPWH website, and updated on a monthly basis.

24 complaints have been followed up to January, 2018. Complaints are handled by the Secretariat of CHU under PMU

WINRIP. Dispute resolution of complaints will be handled by different

institutions (PPK, Satker, Inspectorate General, Komisi PenyelesaianPengaduan), depending on the type of complaints (i.e. generalmatters, technical matters, or specific matters).

17 Information concerning the alternative conduits forcomplaints (telephone hotline, dedicated emailaddress and PO Box) widely disseminated.

The information of complaint procedures has been disseminated tothe different institutions related to project implementation (PPK,Satker, Contractors, Engineer/ Supervision Consultants) during PMMworkshops and to the CROs & TPM during introductory training.The PPKs published the complaint procedures through their ProjectInformation Board.

18 Strict procedures to ensure anonymity of informants. The procedures ensure anonymity of informants.

19 Recording and appropriate referral of all incomingcomplaints undertaken by MPWH with each casegenerating an automatic, standard format report tothe Bank.

It has been established on the WINRIP website (http://chs.winrip-ibrd.com).

Miti

gatin

g Co

llusio

n, Fo

rger

y an

d Fr

aud

Risk

s

20 “Semi E-Tendering” on the MPWH official publicwebsite used by MPWH for both, works andconsultant services. Key information (see list)published on the official website (www.pu.go.id): (a)invitation for bids; (b) download of biddingdocuments; (c) bid clarifications; (d) minutes of bidopening; (e) information of contract award.

Semi e-procurement was applied before November 2014 and full e-procurement was applied afterward.

21 All specifications defined in the bidding documents,and all clarifications sought through writtencorrespondence and replies sent to all bidders.

Done.

22 Key indicators of submitted bids analyzed by MPWH,through CTC. Short technical report for each group ofbidding (the bidding packages simultaneously invited)prepared and shared with the Bank.

Short technical reports for each contracted package have beenindividually prepared and shared with the Bank except for thepackages under AWP-1 (packages 01, 02, 03, and 04), where a groupreport was prepared.

23 Contracts awarded within original bid validity period. There were six (6) contracts awarded within the original bid validityperiod (packages 04, 06, 11, 13, 17, and 19).

Twelve (12) contracts were awarded after the original bid validityperiod (packages 01, 02, 03, 05, 07, 08, 12, 14, 15, 16, 20, and 21).

Bidding for package 05A is failed bidding, so that should take re-bidprocess.

24 Guidelines for preparation of specifications/selectioncriteria in the bidding documents and request forproposals prepared to ensure compliance with theBank Guidelines.

Done.

25 FIDIC arrangements used by MPWH with theindependent supervision consultant havingresponsibility as the “Engineer” in the works contracts.

Done.

Page 170: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

RISKAREA NoACTIONS STATUS (as of August 31, 2018)

26 Criteria for nominating procurement committeesestablished by MPWH. Each Project ImplementationUnit includes a specified procurement officer andfinancial management officer.

Done.

27 Procedures to maintain proper project andprocurement filing established by MPWH, includingfiling of advertisements, bidding documents/requestfor proposals, clarifications/addenda to biddingdocument/request for proposals, minutes of bidopening, evaluation reports, contract award and finalcontract documents, and also for regular review ofaccounting reports, including all supportingdocuments (i.e. travel report, receipts, etc.).

Done.

28 Regular interim audits conducted by third parties,which include review of procurement process andresults.

Done.

Sanc

tions

and

Rem

edie

s

29 Remedial actions and sanctions for cases of fraud andcorruption that are reported and for which evidence isfound established by MPWH.

No cases of fraud and corruption have been encountered so far.However, in one bidding process a bidder was rejected because thebidding commission considered that some of the submittedinformation was not genuine.

30 Information regarding fraud, corruption, collusionand/or coercive practice cases (resulting in thetermination of the contract and possibly otherpenalties), where lessons are learned and funds areretrieved, widely disseminated.

It will be done if there are such cases.

31 Disbursement to any given contract/locationsuspended or stopped completely if cases ofcorruption not dealt with effectively.

It will be done if there are such cases.

Page 171: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

Appendix I

Performance Indicator

Page 172: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

Appendix I

Project Development Objective Indicators

Indicator Name CoreUnit of

MeasureBaseline(2010)

FY1(2013)target

FY1(2013)actual

FY2(2014)target

FY2(2014)actual

FY3(2015)target

FY3 (2015)actual

FY4(2016)target

FY4 (2016)actual

FY5 (2017)end target

FY5 (2017)end actual

Increase of AADT onproject road sections(all vehicle types)

Number Value 8,241 10,880 11,936 4,140 13,094 12,696 13,990 13,613 14,947

Date 31-Dec-2010

31-Dec-14

March2015

31-Dec-16 31-Dec-2017

Comments 2010 baseline isthe simpleaverage of theAADT of the 19WINRIPsections (page41 of PAD)

Resultsfrom IRMS

Results fromstatic trafficcounts on 6links in 4provinces

Results fromIRMS (from 17packages)

2017 target calculated using the growth forecastsfor four vehicle types on page 39 of the PAD,weighing them by the typical traffic compositionfrom the 2010 Master Plan for Arterial RoadNetwork in Sumatra Island (motorcycles 54.9%, cars24.6%, buses 2.7% and trucks 17.8%)

Indicator Name CoreUnit of

MeasureBaseline(2010)

FY1(2013)target

FY1(2013)actual

FY2(2014)target

FY2(2014)actual

FY3(2015)target

FY3 (2015)actual

FY4(2016)target

FY4 (2016)actual

FY5 (2017)end target

FY5 (2017)end actual

Average vehicleoperating cost for atypical car reduced byat least 5% on projectroads (base yearoperating cost:US$0.19/veh-km)

Percentage Value 0.00 n.a. 3.00 n.a. n.a. 5.00

Date 31-Dec-2010

31-Dec-14

10-Nov-15 9-Aug-1631-Dec-2017

CommentsTarget notassessedbecause noworkscompleted

Target notassessedbecause noworkscompleted

Vehicleoperating costswill be assessedat project end

Indicator Name Core Unit ofMeasure

Baseline(2010)

FY1(2013)target

FY1(2013)actual

FY2(2014)target

FY2(2014)actual

FY3(2015)target

FY3 (2015)actual

FY4(2016)target

FY4 (2016)actual

FY5 (2017)end target

FY5 (2017)end actual

Page 173: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

Average vehicleoperating cost for atypical bus reduced byat least 8% on projectroads (base yearoperating cost:US$0.35/veh-km)

Percentage Value 0.00 n.a. 5.00 n.a. n.a. 8.00

Date 31-Dec-2010

31-Dec-14

10-Nov-15 9-Aug-1631-Dec-2017

Comments Target notassessedbecause noworkscompleted

Target notassessedbecause noworkscompleted

Vehicleoperating costswill be assessedat project end

Indicator Name CoreUnit of

MeasureBaseline(2010)

FY1(2013)target

FY1(2013)actual

FY2(2014)target

FY2(2014)actual

FY3(2015)target

FY3 (2015)actual

FY4(2016)target

FY4 (2016)actual

FY5 (2017)end target

FY5 (2017)end actual

Average vehicleoperating cost for atypical heavy truckreduced by 10% onproject roads (base yearoperating cost: US$0.65veh-km)

Percentage Value 0.00 n.a. 7.00 n.a. n.a. 10.00

Date 31-Dec-2010

31-Dec-14

10-Nov-15 9-Aug-1631-Dec-2017

Comments Target notassessedbecause noworkscompleted

Target notassessedbecause noworkscompleted

Vehicleoperating costswill be assessedat project end

Indicator Name Core Unit ofMeasure

Baseline(2010)

FY1(2013)target

FY1(2013)actual

FY2(2014)target

FY2(2014)actual

FY3(2015)target

FY3 (2015)actual

FY4(2016)target

FY4 (2016)actual

FY5 (2017)end target

FY5 (2017)end actual

Average passengertravel time for lightvehicles reduced by atleast 20% on projectroads (base year speed:51 km/h)

Percentage Value 0.00 0.00 -15.29 5.00 3.7 18.20 20.00

Date 31-Dec-2010

31-Dec-13

31-Dec-14

10-Nov-15 31-Jan-1731-Dec-2017

Comments For 4ongoingworks only

For 9 ongoingworks only

Results from sitesurvey (from 17packages)

Indicator Name Core Unit ofMeasure

Baseline(2010)

FY1(2013)target

FY1(2013)actual

FY2(2014)target

FY2(2014)actual

FY3(2015)target

FY3 (2015)actual

FY4(2016)target

FY4 (2016)actual

FY5 (2017)end target

FY5 (2017)end actual

Average passenger Percentage Value 0.00 0.00 -19.57 5.00 -2.17 13.81 20.00

Page 174: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

travel time for largebuses reduced by atleast 20% on projectroads (base year speed:46 km/h)

Date 31-Dec-2010

31-Dec-13

31-Dec-14

10-Nov-15 31-Jan-1731-Dec-2017

Comments Noavailable

For 4ongoingworks only

For 9 ongoingworks only

Results from sitesurvey (from 17packages)

Indicator Name CoreUnit of

MeasureBaseline(2010)

FY1(2013)target

FY1(2013)actual

FY2(2014)target

FY2(2014)actual

FY3(2015)target

FY3 (2015)actual

FY4(2016)target

FY4 (2016)actual

FY5 (2017)end target

FY5 (2017)end actual

Average passengertravel time for heavytrucks reduced by atleast 20% on projectroads (base year speed:40 km/h)

Percentage Value 0.00 0.00 -17.50 5.00 -6.53 11.76 20.00

Date 31-Dec-2010

31-Dec-13

31-Dec-14

10-Nov-15 31-Jan-1731-Dec-2017

Comments For 4ongoingworks only

For 9 ongoingworks only

Results from sitesurvey (from 17packages)

Intermediate Results Indicators

Indicator Name CoreUnit of

MeasureBaseline(2010)

FY1(2013)target

FY1(2013)actual

FY2(2014)target

FY2(2014)actual

FY3(2015)target

FY3 (2015)actual

FY4(2016)target

FY4 (2016)actual

FY5 (2017)end target

FY5 (2017)end actual

Satisfactory completionof slope protectiondesigns

Number

Value 0.00 0.00 0 3.00

Date 15-Dec-2015

15-Dec-2015

31-Jan-1731-Dec-2017

CommentsStudy incontractingphase

Indicator Name Core Unit ofMeasure

Baseline(2010)

FY1(2013)target

FY1(2013)actual

FY2(2014)target

FY2(2014)actual

FY3(2015)target

FY3 (2015)actual

FY4(2016)target

FY4 (2016)actual

FY5 (2017)end target

FY5 (2017)end actual

Number of km of Kilometers Value 0.00 0.00 0 5 5.38 80 134.54 380 322 640.00

Page 175: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

improved nationalroads in the projectregion as planned/Roads rehabilitated,Rural

Date 31-Dec-2010

31-Dec-13

Dec-14 10-Nov-15 31-Jan-1731-Dec-2017

Comments Rev.Target

Rev.Target

Rev.Target

Rev. Target

Indicator Name CoreUnit of

MeasureBaseline(2010)

FY1(2013)target

FY1(2013)actual

FY2(2014)target

FY2(2014)actual

FY3(2015)target

FY3 (2015)actual

FY4(2016)target

FY4 (2016)actual

FY5 (2017)end target

FY5 (2017)end actual

Number of meters ofimproved bridges

Meters

Value 0.00 0.00 0.00 0.00 0.00 48.00 0.00 96.00 100 160.00

Date 31-Dec-2010

31-Dec-13

0 10-Nov-15 31-Jan-1731-Dec-2017

Comments Rehabilitated,rural

Rev.Target

Rev.Target

Rev.Target

Rev. Target

Indicator Name CoreUnit ofMeasure

Baseline(2010)

FY1(2013)target

FY1(2013)actual

FY2(2014)target

FY2(2014)actual

FY3(2015)target

FY3 (2015)actual

FY4(2016)target

FY4 (2016)actual

FY5 (2017)end target

FY5 (2017)end actual

Satisfactory completionof technical audits forall road projects ofcomponent 1

Percentage

Value 0.00 0.00 0.00 0.00 0.00 20.00 16.00 60.00 63.16 100.00

Date 31-Dec-2010

31-Dec-13

0 31-Jan-1731-Dec-2017

Comments Rev.Target

0 out of 19Rev.Target

3 out of 19Rev.Target

12 out 19; TFACvisit

Indicator Name CoreUnit ofMeasure

Baseline(2010)

FY1(2013)target

FY1(2013)actual

FY2(2014)target

FY2(2014)actual

FY3(2015)target

FY3 (2015)actual

FY4(2016)target

FY4 (2016)actual

FY5 (2017)end target

FY5 (2017)end actual

Satisfactory completionof road safety auditscarried out by CTC orTLKJ for all roadprojects of component1

Percentage

Value 0.00 0.00 0 40 80 90 100 100 100 100.00

Date 31-Dec-2010

31-Dec-13

Dec-14 31-Jan-1731-Dec-2017

Comments 16 out of19

Rev.Target

19 out of 19Rev.Target

18 out of 18 forDetail Eng.Design

Page 176: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

Appendix J

Correspondence

Page 177: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

Appendix J Correspondence

INCOMING LETTERCorrespondence

Date From To Activity

August 1, 2018 DirekturPengembanganJaringan Jalan

DirekturPembangunan Jalan

Penyampaian surat bank duniaterkait usulan draft amendmentNo. 2 dan 3 TA SLOPE; WINRIPLoan IBRD 8043-ID

August 1, 2018 World Bank DirekturPengembanganJaringan Jalan

TFAC Mission for WINRIP PackageNo. 05 and No. 15

August 2, 2018 Direktur PreservasiJalan

DirekturPengembanganJaringan Jalan

Penyampaian dokumen addendumNo. 2 dan 3 kontrak pekerjaan DSC;WINRIP Loan IBRD 8043-ID

August 3, 2018 DirekturPengembanganJaringan Jalan

Direktur PreservasiJalan

Penyampaian surat bank duniaterkait misi TFAC untuk paket No.05 dan No. 15

August 6, 2018 Direktur PreservasiJalan

Kepala BBPJN IIMedan

Penyampaian surat bank duniaterkait misi TFAC untuk paket No.05 dan No. 15; WINRIP Loan IBRD8043-ID

August 6, 2018 Site SupervisionEngineer

Team Leader DSC Quarterly Progress Report No. 12,period of April-June 2018 packageNo. 05

August 6, 2018 Site SupervisionEngineer

Team Leader DSC Monthly Progress Report No. 37,Period of July 2018 package No. 05

August 7, 2018 Direktur PreservasiJalan

DirekturPengembanganJaringan Jalan

Penyampaian laporan tindak lanjutaudit TFAC Paket No. 16; WINRIPLoan IBRD 8043-ID

August 7, 2018 PT. Perentjana Djaja PAP2PHLN Submission of revised draftamendment No. 8 to contract forcore team consultant (CTC);WINRIP Loan IBRD 8043-ID

August 8, 2018 Tarwanto CTC WINRIP Surat keterangan sakit Tarwanto (3Agustus 2018)

August 8, 2018 DirekturPengembanganJaringan Jalan

World Bank Submission of signed addendumcontract No. 2 and 3 of DSC;WINRIP Loan IBRD 8043-ID

August 8, 2018 DirekturPengembanganJaringan Jalan

World Bank Submission of follow up report forTFAC of package No. 16; WINRIPLoan IBRD 8043-ID

August 8, 2018 Leti CTC WINRIP Surat keterangan sakit Leti (4-6 Juli2018)

Page 178: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

Date From To Activity

August 10,2018

BPJN III Padang Direktur PreservasiJalanDirekturPengembanganJaringan Jalan

Revisi penyampaian draftaddendum No. 4 kontrak pekerjaanDSC WINRIP

August 13,2018

DirekturPengembanganJaringan Jalan

Direktur PreservasiJalan

Penyampaian surat bank duniaterkait laporan hasil audit TFACuntuk paket No. 16; WINRIP LoanIBRD 8043-ID

August 13,2018

DirekturPengembanganJaringan Jalan

Direktur PreservasiJalan

Penyampaian surat bank duniaterkait laporan hasil audit TFACuntuk paket No. 11; WINRIP LoanIBRD 8043-ID

August 14,2018

Badan ArbitraseNasional Indonesia

PPK Paket No. 21 Penyelesaian perkara No.41068/VII/ARB-BANI/2018 antaraPT. Multi structure sebagaipemohon melawan PejabatPembuat Komitmen (PPK) 1.5:Paket No. 21 WINRIP

August 14,2018

TriwulandariSusanto

CTC WINRIP Surat keterangan sakit Wulan (2-4Juli 2018)

August 15,2018

Direktur PreservasiJalan

BPJN III Padang Penyampaian surat bank duniatentang laporan hasil audit TFACPaket No. 16; WINRIP Loan IBRD8043-ID

August 15,2018

Direktur PreservasiJalan

BPJN III Padang Penyampaian surat bank duniatentang laporan hasil audit TFACPaket No. 11; WINRIP Loan IBRD8043-ID

August 16,2018

Site SupervisionEngineer

Team Leader DSC Monthly Progress Report No. 24,Period of July 2018 package No. 14

August 16,2018

Site SupervisionEngineer

Team Leader DSC Quarterly Progress Report No. 08,Period of May, June, July 2018package No. 14

August 20,2018

BPJN III Padang Direktur PreservasiJalan

Permohonan fasilitas perizinanstandard bidding document (SBD)WINRIP Paket No. 21A

August 20,2018

Direktur PreservasiJalan

BPJN III PadangBBPJN V PalembangBBPJN II Medan

Penyampaian format dokumenpemeliharaan jalan pada paket-paket WINRIP; WINRIP Loan IBRD8043-ID

August 21,2018

DirekturPengembanganJaringan Jalan

Direktur PreservasiJalan

Penyampaian surat bank duniaterkait usulan pengurangankuantitas pada paket No. 15

August 21, Ka. Biro keuanganPUPR

CTC WINRIP Undangan konsinyasi penyelesaiantindak lanjut temuan LHP BPK-RI TA

Page 179: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

Date From To Activity

2018 2017

August 21,2018

KementerianKeuangan RI

CTC WINRIP Undangan rekonsiliasi pinjamandan hibah

August 23,2018

Direktur PreservasiJalan

BBPJN II Medan Penyampaian surat bank duniaterkait usulan pengurangankuantitas pada paket No. 15;WINRIP Loan IBRD 8043-ID

August 23,2018

Direktur PreservasiJalan

DirekturPengembanganJaringan Jalan

Penyampaian dokumen draftaddendum no. 4 kontrak pekerjaanDSC; WINRIP Loan IBRD 8043-ID

August 23,2018

Direktur PreservasiJalan

DirekturPengembanganJaringan Jalan

Penyampaian perubahan desainpada paket No. 13; WINRIP LoanIBRD 8043-ID

August 24,2018

OIC PMU WINRIP Kasatker PJN Wil. IProvinsi SumateraBarat

Posisi likuiditas pinjaman WINRIPLoan IBRD 8043-ID

August 24,2018

OIC PMU WINRIP OIC PIU WINRIP Penyampaian laporan pemeriksaankualitas untuk paket No. 7 dan 12;WINRIP Loan IBRD 8043-ID

August 28,2018

Lingga Nur Arif CTC WINRIP Surat keterangan sakit Lingga (27Agustus 2018)

August 28,2018

PPK GML OIC PMU WINRIP Penyampaian revisi dokumenlelang ulang paket O5A; WINRIPLoan IBRD 8043-ID

August 28,2018

DirekturPengembanganJaringan Jalan

World Bank Submission of engineering designchanges of package No. 13; WINRIPLoan IBRD 8043-ID

August 29,2018

Site SupervisionEngineer

Team Leader DSC Monthly Progress Report No. 32,Period of July 2018 package No. 15

August 30,2018

Direktur PreservasiJalan

DirekturPengembanganJaringan Jalan

Penyampaian laporan quarterlyrencana kerja pengelolaan danpemantauan lingkungan (RKPPL)Pada paket 05, 12, 13, 14, 15 dan16; WINRIP Loan IBRD 8043-ID

August 31,2018

Satker BPJN III Team Leader DSCWINRIP

Pengawasan konsultan supervisepaket WINRIP Sp. Rampa – Poriahadan Sibolga – Bts. Tapsel

Page 180: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

Report SubmissionDate From To Activity

August 6, 2018 Site SupervisionEngineer

Team Leader DSC Quarterly Progress Report No.12, period of April-June 2018package No. 05

August 6, 2018 Site SupervisionEngineer

Team Leader DSC Monthly Progress Report No. 37,Period of July 2018 package No.05

August 7, 2018 Direktur PreservasiJalan

DirekturPengembanganJaringan Jalan

Penyampaian laporan tindaklanjut audit TFAC Paket No. 16;WINRIP Loan IBRD 8043-ID

August 8, 2018 DirekturPengembanganJaringan Jalan

World Bank Submission of follow up reportfor TFAC of package No. 16;WINRIP Loan IBRD 8043-ID

August 13, 2018 DirekturPengembanganJaringan Jalan

Direktur PreservasiJalan

Penyampaian surat bank duniaterkait laporan hasil audit TFACuntuk paket No. 16; WINRIP LoanIBRD 8043-ID

August 13, 2018 DirekturPengembanganJaringan Jalan

Direktur PreservasiJalan

Penyampaian surat bank duniaterkait laporan hasil audit TFACuntuk paket No. 11; WINRIP LoanIBRD 8043-ID

August 15, 2018 Direktur PreservasiJalan

BPJN III Padang Penyampaian surat bank duniatentang laporan hasil audit TFACPaket No. 16; WINRIP Loan IBRD8043-ID

August 15, 2018 Direktur PreservasiJalan

BPJN III Padang Penyampaian surat bank duniatentang laporan hasil audit TFACPaket No. 11; WINRIP Loan IBRD8043-ID

August 16, 2018 Site SupervisionEngineer

Team Leader DSC Monthly Progress Report No. 24,Period of July 2018 package No.14

August 16, 2018 Site SupervisionEngineer

Team Leader DSC Quarterly Progress Report No.08, Period of May, June, July2018 package No. 14

August 24, 2018 OIC PMU WINRIP OIC PIU WINRIP Penyampaian laporanpemeriksaan kualitas untuk paketNo. 7 dan 12; WINRIP Loan IBRD8043-ID

August 29, 2018 Site SupervisionEngineer

Team Leader DSC Monthly Progress Report No. 32,Period of July 2018 package No.15

August 30, 2018 Direktur PreservasiJalan

DirekturPengembangan

Penyampaian laporan quarterlyrencana kerja pengelolaan dan

Page 181: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

Date From To ActivityJaringan Jalan pemantauan lingkungan (RKPPL)

Pada paket 05, 12, 13, 14, 15 dan16; WINRIP Loan IBRD 8043-ID

MeetingDate From To Activity

August 21, 2018 Ka. Biro keuanganPUPR

CTC WINRIP Undangan konsinyasipenyelesaian tindak lanjuttemuan LHP BPK-RI TA 2017

August 21, 2018 KementerianKeuangan RI

CTC WINRIP Undangan rekonsiliasi pinjamandan hibah

Page 182: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

Outgoing Letter

Correspondence

Date From To ActivityAugust 2, 2018 CTC WINRIP OIC PMU WINRIP Duty Trip Report for Sago –

Painan RoadAugust 9, 2018 CTC WINRIP OIC PMU WINRIP Transmission of Quality

Inspection Report forImplementation of RoadMaintenance within DefectNotification Period of packageNo. 07: Indrapura - Tapan;WINRIP IBRD Loan No. 8043-ID

August 10, 2018 CTC WINRIP OIC PMU WINRIP Submission Draft of ExplanatoryNote for Loan AgreementAmendment of WINRIP; LoanIBRD No.8043-ID

August 10, 2018 CTC WINRIP OIC PMU WINRIP Reflector Attached onGuardrails

August 10, 2018 CTC WINRIP OIC PMU WINRIP Transmission of QualityInspection Report for packageNo. 12: Kambang – Indrapura;WINRIP IBRD Loan No. 8043-ID

August 14, 2018 CTC WINRIP OIC PMU WINRIP Uncompleted Drainage Works

August 14, 2018 CTC WINRIP OIC PMU WINRIP CTC Review of DraftAmendment No. 4 for DSCContract; WINRIP Loan No.8043-ID

August 14, 2018 CTC WINRIP OIC PMU WINRIP Submission of RKPPL QuarterlyImplementation MonitoringReport for WINRIP Packages;WINRIP IBRD Loan 8043-ID

August 20, 2018 CTC WINRIP OIC PMU WINRIP Transmission of QualityInspection Report for packageNo. 14: Painan - Kambang;WINRIP IBRD Loan No. 8043-ID

August 24, 2018 CTC WINRIP OIC PMU WINRIP Traffic Management Issues inPackage No. 05 : Sp. Rampa –Poriaha; WINRIP IBRD Loan No.8043-ID

August 29, 2018 CTC WINRIP OIC PMU WINRIP Submission Draft of ExplanatoryNote for Loan AgreementAmendment of WINRIP; LoanIBRD No.8043-ID

August 29, 2018 CTC WINRIP OIC PMU WINRIP WINRIP: Project progress followup

Page 183: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan

Monthly Progress Report August 2018

Western Indonesia National Roads Improvement Project

Report Submission

Date From To ActivityAugust 2, 2018 CTC WINRIP OIC PMU WINRIP Duty Trip Report for Sago –

Painan RoadAugust 9, 2018 CTC WINRIP OIC PMU WINRIP Transmission of Quality

Inspection Report forImplementation of RoadMaintenance within DefectNotification Period of packageNo. 07: Indrapura - Tapan;WINRIP IBRD Loan No. 8043-ID

August 10, 2018 CTC WINRIP OIC PMU WINRIP Transmission of QualityInspection Report for packageNo. 12: Kambang – Indrapura;WINRIP IBRD Loan No. 8043-ID

August 14, 2018 CTC WINRIP OIC PMU WINRIP Submission of RKPPL QuarterlyImplementation MonitoringReport for WINRIP Packages;WINRIP IBRD Loan 8043-ID

August 20, 2018 CTC WINRIP OIC PMU WINRIP Transmission of QualityInspection Report for packageNo. 14: Painan - Kambang;WINRIP IBRD Loan No. 8043-ID

Meeting

Date From To Activity

Page 184: Monthly Progress Report No. 68 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR... · Kepala Satker Pembinaan Administrasi dan Pelaksanaan