Monthly Progress Report No. 1 Covering Project Activities During January 2013

Transcript of Monthly Progress Report No. 1 -...

Page 1: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report No. 1Covering Project Activities During

January 2013

Page 2: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

PT.PERENTJANADJAJAin subcbnsultancy with ~ Yongma Engineering Co.Ltd and ~PT. Epadascon Permata Engineering ConsultantCTCOffice: JLCiniru VII No. 25, Kebayoran Baru, Jakarta Selatan, 12180

Phone (Fax: (021) 7229823

Cc:1. Acting Director of Planning, DGH2. Head of Sub Directorateof Financing and ForeignCooperation3. KasatkerPembinaanAdministrasidan Pelaksanaan Pengendalian PHLN4. - Head of Section for Foreign Cooperation, Sub Directorate Financing and Foreign Cooperation

Directorateof Planning,Directorate Generalof Highways (Bina Marga), Ministryof PublicWorks5. File

Thank you for your kind attention.

Hereby we submit January Monthly Progress Report WIN RIP Loan IBRD No 8043-ID (document.4,'

attached).

Dear Sir,

Submission of January Monthly Report; WINRIP Loan IBRD No. 8043-10Subject

Attention: Ir. Agusta Ersada Sinulingga , MTOfficer In Charge PMU WINRIP

Directorate General of Highways. Department of Public WorksJI. Patimura 20 Kebayoran BaruJakarta SelatanIndonesia

Jakarta, February 8, 2013: 03_02/BAB/O/M-1.2013: 1 (one) set

No.. Our Ref.

MINISTRY OF PUBLIC WORKSDIRECTORATE GENERAL OF HIGHWAYS

DIRECTORATE OF PLANNINGCore Team Consultant for

Western Indo.nesia National Roads Improvement Project (WIN RIP)IBRD Loan No. 8043-10

..............----------------------------~---~

Page 3: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project

Table of Contents

1 EXECUTIVE SUMMARY................................................................................................... 12 PROJECT DESCRIPTION ............................................................................................... 5

2.1 Background...................................................................................................................... 52.2 Project Development ........................................................................................................ 52.3 Project Objective ............................................................................................................10

3 CONSULTANCY SERVICES ..........................................................................................113.1 CTC Consultants.............................................................................................................11

3.1.1 Scope of Services ..................................................................................................113.1.2 CTC Manning .........................................................................................................123.1.3 CTC Contract..........................................................................................................13

3.2 DSC Consultants.............................................................................................................134 CIVIL WORKS .................................................................................................................14

4.1 Detailed Design Preparation............................................................................................144.2 Procurements..................................................................................................................164.3 Civil Works Implementation .............................................................................................174.4 Civil Works Progress .......................................................................................................174.5 Quality Assurance ...........................................................................................................174.6 Environmental and Social Considerations .......................................................................17

4.6.1 Current Overall Situation .........................................................................................174.6.2 Monitoring of Environmental Aspects During Construction.......................................184.6.3 Design Integration, Road Safety aspects and Monitoring of EnvironmentalStudies ..............................................................................................................................18

4.7 Anti Corruption Issues .....................................................................................................194.7.1 Anti‐Corruption Action Plan (ACAP) .......................................................................194.7.2 Community Representative Observers (CRO) ......................................................194.7.3 Publication/Disclosure ............................................................................................204.7.5 Third Party Monitoring (TPM) .................................................................................25

4.8 Road Safety Audit ..........................................................................................................255 FINANCIAL & MANAGEMENT INFORMATION SYSTEMS ..............................................26

5.1 Draw‐Downs and Future Costs........................................................................................265.2 Disbursement ..................................................................................................................265.3 Management Information System....................................................................................26

5.3.1 General Overview....................................................................................................265.3.2 Database .................................................................................................................275.3.3 Project Progress Monitoring System......................................................................295.3.4 Website ...................................................................................................................29

6 PROJECT PERFORMANCE.............................................................................................316.1 World Bank and GOI Compliance....................................................................................31

Page 4: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project

6.1.1 World Bank Missions..............................................................................................316.1.2 Performance Indicators..........................................................................................31

6.2 Implementation Support Components ............................................................................316.2.1 Core Team Consultant (CTC)................................................................................316.2.2 Design and Supervision Consultant (DSC) ...........................................................326.2.3 Road Sector Institutional Development .................................................................32

6.3 Training ...........................................................................................................................326.4 Anti‐Corruption Issues .....................................................................................................33

6.4.1 Anti Corruption Action Plan (ACAP) ......................................................................336.4.2 Community Representative Observers (CRO)......................................................346.4.3 Disclosure and Transparency ................................................................................346.4.4 Third Party Monitoring (TPM) ................................................................................356.4.5 Complaint Handling System (CHS) .......................................................................35

6.5 Road Safety Audit ..........................................................................................................366.6. Environmental and Social Impact Issues ........................................................................36

6.6.1. LARAP Study Report for Package No.01 : Krui – Biha ........................................366.6.2. LARAP Study Report for Package No.02 : Padang Sawah – Simpang Empat ...366.6.3. LARAP Study Report for Package No.03 : Manggopoh – Padang Sawah..........366.6.4. LARAP Study Report for Package No.04 : Ipuh – Bantal.....................................36

6.7 Management Information Systems ..................................................................................366.8 Quality Assurance ...........................................................................................................376.9 Project Risks and Mitigation Measures............................................................................37

6.9.1 Risks Related to Delays.........................................................................................376.9.2 Financial Risks .......................................................................................................376.9.3 Risks Related to Quality.........................................................................................37

7 ISSUES and RECOMMENDATIONS ................................................................................387.1 Current Situation ............................................................................................................387.2 Action Required..............................................................................................................38

Page 5: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project

APPENDICES

Appendix A : Overall Loan Progress

Appendix B : Highway Design Progress

Appendix C : Environmental & Socio Impact Progress

Appendix D : Procurement Plan & Progress

Appendix E : Training/Dissemination Progress

Appendix F : Performance Indicator

Appendix G : Correspondence

Page 6: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project

ABBREVIATIONS AND ACRONYMS

ACAP : Anti-Corruption Action Plan

AER : Application Evaluation Report

AIP : Australian Indonesia Partnership

AMDAL : Environmental Management (Analisis Mengenai dampak

Lingkungan)

ANDAS : Analisis Dampak Sosial

AWPs : Annual Work Programs

Balai : Regional Office for National Roads Implementation

BAPPENAS : Badan Perencanaan Pembangunan Nasional (National

Development Planning Agency of GOI)

Bappedalda : Regional Environmental Impact Agencies

BBPJN : Balai Besar Pelaksanaan Jalan Nasional (Regional Office

for National Roads Implementation)

BER : Bid Evaluation Report

BLH : Badan Lingkungan Hidup

BPK : Badan Pemeriksaan Keuangan (Audit Board of the

Government of Indonesia)

CAD : Computer Aided Design

CHS : Complaint Handling System

CTC : Core Team Consultant

CHU : Complaint Handling Unit

DIA : Directorate of Implementing Affairs

DOP : Directorate of Planning

DGH : Directorate General of Highways

DMS : Document Management System

DTA : Directorate of Technical Affairs

DGH : Directorate General of Highway

DMS : Document Management System

DSC : Design and Supervision Consultants

EA : Executing Agency

EINRIP : Eastern Indonesian National Roads Improvement Project

EIRTP-1 : Eastern Indonesia Regional Transport Project First Project)

ESAMP : Environmental and Social Assessment Plan

ESS : Environmental and Social Safeguards

FMIS : Financial Management Information System

Page 7: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project

FIDIC : Federation Internationale des Ingenieur Conseils

FMIS : Financial Management Information System

GIS : Geographic Information System

GOI : Government of Indonesia

IA : Implementation Agency

IBRD : International Bank for Reconstruction and Development

IFR : Internal Financial Report

IRMS : Integrated Road Management System

Kabupaten : Regency

KPIs : Key Performance Indicators

LAN : Local Area Network

LARAP : Land Acquisition and Resettlement (Rencana Tindak

Pengadaan Tanah dan Pemukiman Kembali)

MIS : Management Information System

MOF : Ministry of Finance

MPW : Ministry of Public Work

MPRs : Monthly Progress Reports

P2JN : Perencanaan Pengawasan Jalan dan Jembatan Nasional

PDF : Portable Document Format

PMU : Project Management Unit

PAPs : Project Affected Peoples

PMM : Project Management Manual

PMU : Project Management Unit (WINRIP)

POKJA : Bina Marga Project Managers and Procurement Committes

PPC : Project Preparation Consultants

PP3 : Pemantau Pihak ke 3

PPK : Sub Project Manager

PPR : Project Progress Report

QPRs : Quarterly Progress Reports

RKL/RPL : Rencana Pengelolaan/Pemantauan Lingkungan

RS : Road Safety

Satker : Satuan Kerja (Work Unit for Road Project Implementation)

SPPL : Surat Pernyataan Pengelolaan Lingkungan

SRIP : Strategic Road Infrastructure Project

TA : Technical Assistance

TOR : Terms of Reference

UKL/UPL : Upaya Pengelolaan Lingkungan dan Upaya Pemantauan

Lingkungan (Site Specific Environmental and Monitoring

Page 8: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project

Plans

WINRIP : Western Indonesia Roads Improvement Project

WB : World Bank

WP : Work Program

WPs : Works Programs

WPM : Wakil Pengamat dari Masyarakat

Page 9: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project 1

1 EXECUTIVE SUMMARY

Loan 8043-ID Progress

Loan Allocation and Disbursement % to Date

The total disbursement from the loan to the end of January 2013 was USD 800,000.00equivalent to approximately 0.32% of the loan funds. The following table summarizes theindividual disbursements as calculated by CTC but retaining the total disbursement fromClient Connection at the end of January 2013.

Category Description Loan Amountin US$

Totals Disbursed toEnd January 2013

in US$

%Disbursed

1Part 1 Betterment andCapacity Expansion of

National Roads.220,400,000.00 0 0

2Part 2

ImplementationSupport

16,000,000.00 674,177.03 4.21

3

Part 3Road SectorInstitutional

Development

1,000,000.00 0 0

4

Part 4Contingency for

Disaster RiskResponse

0 0 0

Unallocated 12,600,000.00 0 0

LN 8043 DA-A 125,822.97 0

Original Loan Amount 250,000,000.00 800,000.00 0.32

0.00

11%

26%

44%

63%

78%

90%

100%

0.00

10.00

20.00

30.00

40.00

50.00

60.00

70.00

80.00

90.00

100.00

Year

% C

ompl

ete

WINRIP DISBURSEMENT PLAN

Page 10: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project 2

Project Status to End January 2013

Length WidthEstimated Cost(PIP Mar 2012)

(excl. VAT)DED

(Km) (m) (IDR Million) StatusDoc

Requirement

StatusDoc

Requirement

StatusBudget

AllocationStatus

Est'd.Start

Duration(months)

SUMATERA UTARA

5 Sp. Rampa - Poriaha 11.1 6 55,126.60 OK by Bintek UKL/UPLOK

Balai I2011

SLARAPConsultantrecruitment

(Balai 1)Balai 1 100% Not yet started Dec-13 18.00

15 Sibolga - Bts Tap Sel 36 7 129,228.00 Review byBintek

UKL/UPLOK

Balai I2011

LARAPConsultantrecruitment

(Balai 1)Balai 1 Inventory Not yet started Apr-14 21.00

SUMATERA BARAT

Padang Sawah - Sp Empat 40.9 7

Including Air Gadang Bridge 100 m 7

3 Manggopoh - Padang Sawah 32 7 152,434.90 Completed SPPLOK

P2JN2010

1. LARAP2. Monit.LARAPReport

1. NOL WB13 Dec 122. Process

Dinas PUProp

100% Awaiting WBNOL for AER

Oct-13 24.00

7 Indrapura - Tapan 19.5 7 96,921.00 AwaitingDSC

AMDAL Just ANDAL SLARAPConsultantrecruitment

(Balai 2)Balai 2 Inventory Not yet started Feb-15 21.00

8 Bts. Kota Pariaman - Manggopoh 46.8 7 183,268.80 AwaitingDSC

AMDAL ApprovalProcess

LARAPCompleted

P2JN2011

Balai 2 Inventory Not yet started Dec-14 24.00

10 Sp Empat - Sp Air Balam 61.7 7 241,617.20 AwaitingDSC

AMDAL ApprovalProcess

LARAPCompleted

P2JN2011

Balai 2 Inventory Not yet started Dec-14 24.00

12 Kambang - Indrapura 55.2 6 171,948.00 AwaitingDSC

AMDAL InPreparation

SLARAPConsultantrecruitment

(Balai 2)Balai 2 Inventory Not yet started Feb-15 24.00

14 Painan -Kambang 31.5 7 118,993.00 AwaitingDSC

AMDAL InPreparation

SLARAPConsultantrecruitment

(Balai 2)Balai 2 Inventory Not yet started Jul-15 21.00

20 Lubuk Alung - Sicincin 14.6 7 54,557.00 AwaitingDSC

UKL/UPLOK

TLKJ2011

SLARAPConsultantrecruitment

(Balai 2)Balai 2 Inventory Not yet started Oct-15 18.00

21 Lubuk Alung -Kurataji 16.8 7 65,788.00 AwaitingDSC

UKL/UPLOK

TLKJ2011

SLARAPConsultantrecruitment

(Balai 2)Balai 2 Inventory Not yet started Oct-15 18.00

BENGKULU

4 Ipuh- Bantal 42.4 7 226,275.10 Completed SPPLOK

P2JN2010

1. LARAP2. Monit.LARAPReport

1. NOL WB10 Dec 122. Not yetprepared

SAL 2013Administr

Process forLand Acq.

Awaiting WBNOL for AER

Oct-13 24.00

6 Ps Pedati - Kerkap 25 7 72,018.80 Review byBintek

UKL/UPLOK

TLKJ2011

LARAP Underpreparation

Balai 3 Inventory Not yet started Apr-14 18.00

11 Bantal - Mukomuko 50.1 6 157,820.00 Review byBintek

AMDAL InPreparation

LARAP Underpreparation

Balai 3 Inventory Not yet started Apr-14 24.00

13 Sp Rukis - Tj Kemuning 56.3 7 225,481.50 Review byBintek

UKL/UPLOK

P2JN2011

LARAP Underpreparation

Balai 3 Inventory Not yet started Apr-14 21.00

Seblat - Ipuh including 34.5 6

Air Lalang & Air Guntung Bridge 64 m 6

18 Mukomuko - Bts. Sumbar 25.8 6 69,233.00 Review byBintek

UKL/UPLOK

TLKJ2011

SLARAPConsultantrecruitment

(Balai 3)Balai 3 Inventory Not yet started Oct-15 18.00

19 Lais- Bintunan 11.6 7 37,558.00 Review byBintek

UKL/UPLOK

TLKJ2011

LARAPConsultantrecruitment

(Balai 3)Balai 3 Inventory Not yet started Oct-15 18.00

LAMPUNG

1 Krui - Bha 25 7 146,668.00 Completed SPPLOK

P2JN2010

1. LARAP2. Lap MonLARAP

1. NOL WB4 Jan 132. NOL WB

Satker PJNProp

100%Awaiting WBNOL for AER

Oct-13 24.00

36.8 6

30 m 6

9 Rantau Tijang - Kota Agung 42 7 149,831.50 Review byBintek

UKL/UPLOK

TLKJ2011

LARAPConsultantrecruitment

(Balai 3)APBN 2014 Not yet started Jul-15 21.00

2,776,633.60

Sp.Gunung Kemala - Pg. Tampak

Pack.No.

Loan Package Name

Environment Social Land AcquisitionProcuremen

t Status

OKP2JN2010

1. LARAP2. Monit.LARAPReport

1. NOL WB13 Dec 122. Process

Dinas PUProp

50% Awaiting WBNOL for AER

ContractImplementation

Plan

24.002 207,390.20 Completed SPPL&UKL/UPL Bridge

21.00

Oct-13

Inventory Not yet started Jul-15

17 104,238.00 OK by Bintek AMDALOK

TLKJ2011

16 110,237.00 Review byBintek

AMDALIn

PreparationSLARAP

Consultantrecruitment

(Balai 3)Balai 3

Apr-14 21.00LARAPUnder

preparationAPBN/SAL

2013Measurement by BPN

Not yet started

Page 11: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project 3

World Bank Missions

No World Bank missions visited Indonesia during January 2013.

Procurement

All subprojects for WP-1 have been started with prequalification since 30 December 2011 forICB multiple contract. This was an advanced procurement action agreed by both DGH andthe World Bank prior to the CTC establishment. The deadline of Qualification Documentsubmission by the Applicants was on 28 February 2012. There are twenty nine (29)Applicants who submitted and applied their qualification documents for various packageswhich are summarized as follow.

Package No. 1 (Krui – Biha) : 13 Applicants applied. Package No. 2 (Pd. Sawah – Sp. Empat) : 13 Applicants applied. Package No. 3 (Manggopoh – Pd. Sawah) : 18 Applicants applied. Package No. 4 (Ipuh – Bantal) : 12 Applicants applied.

All three (3) Procurement Teams or Pokja evaluated all qualification documents submitted bythose Applicants. Submission of the Application Evaluation Report (AER) to the Bank was on9 May 2012 for two packages (Package No.1 and No.4) and on 20 June 2012 for other twopackages (Package No.2 and No.3). The Bank still reviews the AERs and requested thePokja to submit supporting documents. The latest request from the Bank was for companystatutes information of the Government’s Entity participated in the prequalification. DGH sentthe required documents to the Bank on 15 January 2013.

DGH has also completed the draft of consolidated multiple contract ICB Standard BiddingDocument for four (4) packages under AWP-1. The draft had been submitted to the Bank on8 March 2012. The Bank’s comments had been issued on 12 March 2012. The draft ofconsolidated SBD was revised by DGH accommodating the Bank’s comments and submittedto the Banks on 27 June 2012. Second revision of the draft consolidated SBD, as requestedby the Bank regarding synchronization between drawings and Bill of Quantities by letter dated1 August 2012, was then concurred by the Bank on 31 October 2012.

Potential Problems

The main issue during January 2013 is the procurement of four (4) packages under AWP-1.Prolong discussion on the Application Evaluation Reports (AERs) will have potentially delayon the tender.

The tender could not be started until the AERs are approved by the Bank even the BiddingDocuments are ready to be issued. In the mean time, the existing road conditions of the fourpackages under AWP-1, which are predicted being deteriorated rapidly by the traffic duringalmost a year, shall be properly anticipated.

Another issue is establishment of the Design and Supervision Consultant (DSC). It isrequired to expedite the DSC recruitment process. The DEDs for AWP-2 and AWP-3packages shall be completed soonest and the procurement can be started immediately.

Page 12: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project 4

Action Required

The project managers (PPKs) are required to carefully investigate current condition of theexisting roads to find out whether the DED is needed to revise or not.

It is hopefully that the Bank will be soon approving the proposed consultants rank based onthe Technical Evaluation Report submitted by DGH on 20 December 2012. The opening ofFinancial Proposal will be conducted by the DGH’s Procurement Committee after the Bank’sapproval on the report.

Page 13: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project 5

2 PROJECT DESCRIPTION2.1 Background

The Government of Indonesia wishes to continue the strengthening of the NationalRoad system in Indonesia while the Eastern Indonesia National Roads ImprovementProject (EINRIP which is assisted by AusAID through the Australian IndonesiaPartnership or AIP), is providing support program of National road and bridgeimprovement works in Eastern Indonesia. The Western Indonesia National RoadImprovement Project (WINRIP) will provide similar support for National road and bridgein the Sumatra region of Indonesia. The focus of WINRIP will be roads administereddirectly by the National Government, including those currently classified as Provincial,Kabupaten (District) or non-status roads which are in process of being reclassified asNational roads. In addition, provision will be made for major bridge repair works,rehabilitation, duplication and replacement as necessary to complement the roadbetterment works.

2.2 Project DevelopmentThe Loan Effectiveness Date for the WINRIP is 12 March 2012 and the key project datais shown in the following detail.

Key Project Data WINRIP Loan No. 8043-IDProject Cost US$350 millionOriginal Loan Amount US$250 millionRevised Loan Amount N/ABoard Approval Date 26 May 2011Loan Signing Date 14 December 2011Effectiveness Date 12 March 2012Disbursement (as of 31 January 2013) US$ 0.67 million (0.27%)Original Closing Date 31 December 2017Formally Revised Closing Date N/AEnvironmental Category B-Partial Assessment

The IBRD Loan amount is US$250 million. The Project is intended to finance a part ofthe DGH investment program for national roads with a particular focus on the Westerncorridor of Sumatra. The corridor is one of the three main corridors in Sumatra andconnects the city of Padang (with a population of around one million) to major townsalong the west coast (Bukittinggi, Sibolga and Bengkulu). It also connects throughconnector roads on the West coast to Medan in the northeast and to Pekanbaru in thecentre of the island. The project has four components:

Page 14: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project 6

Project Component 1 : Betterment and Capacity Expansion of National Roads

According to the Loan Agreement, this component will cover three work programs ofbetterment and capacity expansion of approximately 715.6 km including replacement of194 meters of bridges. This civil works program will be executed in three Annual WorkPrograms (AWP), as summarized in Table 2.1. The table shows the IBRD assistedscope and costs of civil works at estimated current (year of implementation) prices,excluding taxes.

Table 2.1 Proposed Physical Works by DGH Program

Type of WorksAWP-1 AWP-2 AWP-3

Km US$mill Km US$

mill Km US$mill

Road Betterment - - 53.10 22.77 - -Capacity Expansion 137.10 79.70 314.60 127.67 207.60 74.58Bridge works 0.100 1.94 - - 0.08 2.06TOTAL(excluding tax @ current prices) 137.20 81.64 367.70 150.45 207.68 76.65

* Contingency costs not included - ** including 194 meters of bridges

The batches of projects are termed Annual Work Programs (AWPs) in line withterminology used in other Bina Marga projects. They are not in fact “annual” programsas such but rather a series of multi-year programs, each commencing in consecutiveyears. Hence, hereinafter it will call as just Work Programs (WPs). It is expected thatimplementation of the first Works Program (WP-1) will commence in the third quarter of2013 and be completed by third quarter or late 2015. The second Work Program (WP-2)is expected to commence in early 2014 and be completed by late 2015 or middle 2016.The third Work Program (WP-3) is expected to commence in early 2015 and becompleted by mid 2017. The loan will be closed on December 2017.

Table 2.2 presents details of the First Works Program (WP-1). The four packages in thisgroup should have been free from any land acquisition issues, but in fact two packages(Krui – Biha and Manggopoh – Padang Sawah) had land issues which were solved bythe DGH properly. Thus, there are no foreseeable impediments to implementation.

Page 15: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project 7

Table 2.2 IBRD Assisted WINRIP Civil Work WP-1

No Province LinkNo. Link Name

Cla

ss

Roa

d Ty

pe

Road Works Bridge Works Total Cost

From

To Leng

th

Trea

tmen

t

Cos

t (20

10)

No

Leng

th

Cos

t (20

10)

2010

Pric

es

Equi

vale

nt

Km Km Km Rp mill m Rpmill Rp mill US$ mill

1 Lampung 053.0 Krui – Biha K1 IU 221.5 246.5 25.0 Bett’nt to7 m. 148,668 148,668 16.52

2 WestSumatra 047.2

PadangSawa –SimpangEmpat

K1 IU 0.0 40.9 40.9 Bett’nt to7 m. 189,810 189,810 21.09

2a WestSumatra 34.1 Air Gadang

Bridge K1 IU NewBridge 1 100 17.580 17,580 1.95

3 WestSumatra 047.1

Manggopoh– PadangSawah

K1 IU 102.2 134.2 32.0 Bett’nt to7 m. 152,435 152,435 16.94

4 Bengkulu 015.3 Ipuh - Bantal K1 IU 0.0 49.7 49.7 Bett’nt to7 m. 226,275 226,275 25.14

It should be noted that all road sub-projects have been subject to economic appraisaland have estimated Economic Internal Rates of Return (EIRR) in excess of 15%. Thesewere selected for inclusion and are subject to completion of environmental and socialscreening, to confirm that there is no land acquisition or resettlement requirementsremain outstanding.

Final Engineering Designs, Engineer’s Estimates and bidding documents have beencompleted for all projects proposed for WP-1.

Sub-projects to be included in WP-2 and WP-3 have also been determined as listed inTable 2.3. Final Engineering Designs and Engineer’s Estimates for all WP-2 and WP-3proposed works require preparation or finalization. In the cases of some projects,preliminary Engineering Designs were prepared during Project preparation which willrequire review and possible amendment by the Design and Supervision Consultant priorto procurement.

The costs presented in Table 2.1 are planning estimates only, and the overall scopeand contents of WP-2 and WP-3 may need to be revised as when revised costs andbudgets are determined.

Page 16: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project 8

Table 2.3 : IBRD Assisted WINRIP Civil Work WP-2 and WP-3

NO. SUBPROJECT LINK NO. AND NAME LENGTH(KM)

COST(RP. MILL)

WIDTH(M)

IMPLEMENTATION PLAN

START DURATION(MONTHS)

WP-2

5. Sumut : Link No. 015.xx,Sp. Rampa – Poriaha 11.1 55,126.6 6.0 May 2013 18

6. Bengkulu : Link No. 010.0,Ps. Pedati – Kerkap 25.0 72,018.8 7.0 May 2013 18

7. Sumbar : Link No. 019.0,Indrapura – Tapan 19.5 96,921.0 7.0 Oct. 2013 21

8. Sumbar : Link No. 024.0,Bts. Pariaman – Manggopoh 46.8 183,286.8 7.0 Oct. 2013 24

9. Lampung : Link No. 026.1,Rantau Tijing - Kota Agung 42.0 149,831.5 7.0 Oct. 2013 21

10. Sumbar : Link No. 034.1,Sp. Empat - Sp. Air Balam 61.7 241,617.2 7.0 Oct. 2013 24

11. Bengkulu : Link No. 015.2,Bantal – Mukomuko 50.1 157,820.0 6.0 Dec. 2013 24

12. Sumbar : Link No. 017.2,Kambang – Indrapura 55.2 171,948.0 6.0 Dec. 2013 24

13. Bengkulu : Link No. 006.1,Simpang Rukis - Tanjung Kemuning 56.3 225,481.5 7.0 Dec. 2013 21

WP-3

14. Sumbar : Link No. 017.1,Painan – Kambang 31.5 118,993.0 7.0 March. 2014 21

15. Sumut : Link No. 016.0,Sibolga - Bts. TapSel 36.0 129,228.0 7.0 March 2014 21

16.Bengkulu : Link No. 009.4,Seblat – Ipuh, including Air Galang and AirGuntung Bridges

34.50.052 110,237.0 6.0 March 2014 21

17. Lampung : Link No. 061.1,Sp. Gunung Kemala - Pugung Tampak

36.80.03 104,238.0 6.0 March 2014 21

18. Bengkulu : Link No. 015.3,Mukomuko - Bts. Sumbar 25.8 69,233.0 6.0 May 2014 18

19. Bengkulu : Link No. 009.1,Lais – Bintuan 11.6 37,558.0 7.0 May 2014 18

20. Sumbar : Link No. 002.0,Lubuk Alung – Sicincin 14.6 54,557.0 7.0 May 2014 18

21. Sumbar : Link No. 027.0Lubuk Alung – Kuraitaji 16.8 65,788.0 7.0 May 2014 18

Project Component 2 : Implementation Support

This component provides consulting services to support project management andimplementation so as to ensure implementation efficiency and overall quality of theworks. It also includes funds for a small amount of training of DGH staff and forincremental operating costs for the project. This will provide support to the MPW for theimplementation of the civil works, including: (a) provision of Core Team Consultants(CTC), Design and Supervision Consultants (DSC) and road safety audits; (b) Project

Page 17: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project 9

management support and technical audits. This is directly related to the implementationof the civil works and covers consulting services for design and supervision of the civilworks in Component 1; management support and technical audits to help improve thequality of construction and support to governance improvements during procurementand implementation; and a series of systematic road safety audits of road designs for allproject roads in Component 1. This is to ensure compliance with road safety standardsand regulations, identify road hazards and undertake remedial treatments for safetyimprovements.

Project Management Core Team Consultants (CTC). The CTC will provide support tothe PMU and DGH in the management of the Project, based in Jakarta. Their tasksinclude financial and progress monitoring and reporting, information management anddissemination, quality assurance and performance review for the Design andSupervision Consultants, implementation and monitoring of the anti-corruption actionplan, support for project monitoring and evaluation, and support for implementation of atraining program to support project management and implementation. The CTC contractNo. 06-20/CTC/TA/LN/8043/1112 was signed on 5 November 2012 by both DGH and aJoin Venture of PT. Perentjana Djaja, Yongma Engineering Co.Ltd., and PT.Epadascon Permata Engineering Consultant.

Design and Supervision Consultants (DSC). A Design and Supervision Consultant(DSC) will be responsible for design of WP-2 and WP-3 civil works and supervision of allcivil works. They will have the role of ‘Engineer’ under a FIDIC-type contract. The tasksinclude the preparation and maintenance of a quality assurance plan, validation andupdating of designs, supervision of all civil works, environmental and social monitoringand management, and support for financial and progress monitoring and reporting. TheDSC will also be responsible for quality assurance of materials and workmanship,certifying whether or not contractors have achieved the required results, as well asdocumentation and reporting based on the financial management plan. They will preparea Quality Assurance system covering all subprojects, and continuously monitor theeffectiveness of their supervision procedures. The team will be contracted and managedby DGH through the Bina Marga Regional Office (Balai II), and will be based in Padang,West Sumatra. The DSC selection is under the finalization of bid evaluation by theProcurement Committee (Pokja) in Balai Besar Pelaksanaan Jalan Nasional II (BBPJN-II) of DGH. The DSC contract is predicted to be signed in June 2013.

Project Component 3 : Road Sector Institutional DevelopmentThis component will provide technical assistance and support to strengthen disaster riskmitigation in the road sector, including capacity building support for the newenvironment/risk mitigation and road safety unit of DGH to conduct disaster riskassessments and planning, risk mapping of land-slides, coastal erosion, earthquake andfloods, and analysis of alternative designs for road segments that pass through criticalenvironmental assets and vulnerable areas. The procurement for consultants under thiscomponent has not yet been started. Preparation for the procurement would becoordinated soon by the PMU WINRIP, the CTC and the DGH.

Page 18: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project 10

Project Component 4 : Contingency for Disaster Risk Response

This special component will provide preparedness and rapid response to disaster,emergency and/or catastrophic events as needed. This provisional zero dollarcomponent will be added under this project to allow for rapid reallocation of loanproceeds from other components under streamlined procurement and disbursementprocedures.

2.3 Project ObjectiveThe main objective of the program will be to increase the effective use of selectedsections of National roads along the Western Sumatra Corridor by reducing roaduser costs, through improving the National road network especially in 4 (four)Provinces of Sumatra (North Sumatra, West Sumatra, Bengkulu and Lampung) and,where desirable, raise the road standard to that set by the Directorate General ofHighways. This will contribute significantly to ensuring that the National road network inthe region provides acceptable standards of service and accessibility, and is capable ofsupporting local and regional economic development.

Page 19: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project 11

3 CONSULTANCY SERVICES3.1 CTC Consultants

3.1.1 Scope of ServicesThe CTC contract services originally were structured in its different project managementelements.

Inception PhaseA key activity during the inception phase will be to establish lines of communicationwith PMU-WINRIP and DSC’s Team Leader as well as with all Provincial ProjectManagers (Satkers) where the first works are to be constructed under WP-1.

Project Management and Support to PMU, including acting DSC until the DSC isestablishedThe Terms of reference identify a number of sub-items to be performed by CTC. Thekey factor that will ensure success is that the CTC must work pro-actively andalongside PMU counterparts and with DSC team in a professional manner based onmutual respect and trust.

Preparation of Work ProgramsThe tendering process for WP 1 sub-projects began as soon as procurementcommittees have been formed and received appropriate training in the procurementprocedures required. The indicative work programs and cost estimates identified forWP-2 and WP-3 are subject to verification, and are likely to change following moredetailed investigations. Further preparation for WP-2 and WP-3 will be managed bythe PMU supported by the CTC.

Financial MonitoringIt will be the role of the CTC to first assess the level of understanding of the financialmanagement, monitoring and reporting procedures by the finance staff at theprovincial and central level and subsequently devise an appropriate trainingprogramme and assist the PMU in training delivery.

Project Progress and Performance MonitoringCTC will monitor the loan project progress and prepare the report in monthly basis. Inthe meantime, GOI and the World Bank have agreed on a set of Key PerformanceIndicators (KPIs) to measure the project’s performance in achieving its stateddevelopment objectives. CTC will therefore first concentrate on the establishment ofprecise definitions, calculation methods and data collection procedures to monitor theKPIs.

Support for the Implementation of the ACAPThe CTC will assist PMU be responsible for ensuring the ACAP is properlyimplemented and for revising the Project Management Manual on an annual basis toincorporate necessary improvements to processes and procedure.

ESAMP and LARAP Implementation MonitoringCTC will closely work with BLH and DSC and will monitor and report the action ofthe Environmental Management Plan on a periodical basis and/or as required.

Training to Support Project Implementation

Page 20: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project 12

CTC is responsible for preparation and management of all training program requiredunder WINRIP.

ReportingCTC is responsible for all reports required under the contract agreement withstandardize forms, charts and tables.

3.1.2 CTC Manning

CTC professional staffs involved in the project as at the end of January 2013 arelistedin the following table:

Position MM Name

Assignment TimeUsed toEnd of

January2013

ContractTime

RemainingStart End

Team Leader 40 Mahbub ur Rahman - - - * 40.00

Senior Highway Eng. 8 Moon, Sung Hyun - - - * 8.00

Senior Road SafetyAudit Engineer 6 Cho, Woo Sung - - - * 6.00

Senior ProcurementSpecialist 18 Wasim ur Rahman - - - * 18.00

Assistant Team Leader 40 Besar Afiat Bowo Nov-2012 Feb-2016 2.37 37.63

Highway Engineer 36 Whiliyanto Nov-2012 Oct-2015 2.37 37.63

Bridge Engineer 5 HarimurtiSuprihartono Jan-2013 May-2013 0.93 4.07

Quality AssuranceEngineer 36 Uray Abdul Manaf - - - * 36.00

Financial ManagementSpecialist 36 Uus Martawijaya Nov-2012 Oct-2015 2.37 33.63

EnvironmentalSpecialist 30 Leti Hermawati Dec-2012 Jun-2015 1.43 28.57

Social ImpactSpecialist 36 M. Sutopo Nov-2012 Oct-2015 2.37 33.63

ProcurementSpecialist-1 12 Darmansiri - - - * 12.00

ProcurementSpecialist-2 12 Rudi Rungkat Nov-2012 Mar-2013 2.37 9.63

ManagementInformation Specialist 30 Agung Lukito - - - * 30.00

CommunityDevelopment Officer 36 Yakobus Jan-2013 Dec-2015 0.90 35.10

Notes: * : Not yet mobilizedFrom this table it can be seen that a number of key personnel have not yet beenmobilized even though the project has already been running for almost three months.

During the CTC mobilization, the DSC has not been established yet. In parallel withthe instruction to speed up the process, detailed engineering design (DED) of somesubprojects of WP-2 and WP-3 were prepared and completed by respective P2JN.

Page 21: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project 13

3.1.3 CTC ContractThe CTC contract for “Western Indonesia National Roads Improvement Project”(Contract No. 06-20/CTC/TA/LN/8043/1112) was signed on 05 November 2012. Thecontract is between the Government of Indonesia represented by the Ministry ofPublic Works, Directorate General of Highways and PT. Perentjana Djaya in jointventure with Yongma Engineering Co.Ltd and PT. Epadascon Permata EngineeringConsultant.

The notice to proceed was issued by letter dated 6 November 2012 from the PPK,and the official starting date of the contract was set at 6 November 2012.

The following table shows a list of contract for the CTC with DGH.

Contract Date USD (Excl. VAT) IDR (Excl. VAT)

Original Contract 5-Nov-2012 1,276,700 21,415,400,000

3.2 DSC Consultants

A Design and Supervision Consultant (DSC) will be responsible for design of WP-2 andWP-3 civil works and supervision of all civil works. They will have the role of ‘Engineer’under a FIDIC-type contract. The tasks include the preparation and maintenance of aquality assurance plan, validation and updating of designs, supervision of all civil works,environmental and social monitoring and management, and support for financial andprogress monitoring and reporting. The DSC will also be responsible for qualityassurance of materials and workmanship, certifying whether or not contractors haveachieved the required results, as well as documentation and reporting based on thefinancial management plan. They will prepare a Quality Assurance system covering allsubprojects, and continuously monitor the effectiveness of their supervision procedures.The team will be contracted and managed by DGH through the Bina Marga RegionalOffice (Balai II), and will be based in Padang, West Sumatra.

Until the end of January 2013, recruitment process for the DSC was still ongoing.

Page 22: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project 14

4 CIVIL WORKS4.1 Detailed Design Preparation

Final Engineering Designs, Engineer’s Estimates and bidding documents have beencompleted for all projects proposed for WP-1.

WP-2 (nine subprojects) and WP-3 (eight subprojects) will be designed by DSC and theconstruction supervision of all the works programs will be performed by the DSC. Duringthe CTC mobilization, the DSC has not been established yet. In parallel with theinstruction to speed up the process, detailed engineering design (DED) of somesubprojects of WP-2 and WP-3 were prepared and completed by respective P2JN.

The indicative work programs and cost estimates identified for WP-2 and WP-3 aresubject to verification, and are likely to change following more detailed investigations.Further preparation for WP-2 and WP-3 will be managed by the PMU supported by theCTC.

Detailed design of selected links for WP-2 and WP-3 subprojects will have beenapproved by DGH. Those final engineering designs shall meet the same qualitystandards and specifications, in terms of detailed content and presentation, as thoseprepared and approved for WINRIP WP-1 shown at Table 4.1 Table Revision of Scopeof Works for Design WP 2 – WP 3

Table 4.1 Revision of Scope of Work for Design WP 2 – WP 3

Pack.No Link Name

Project Implementation PlanMarch 2013 DED

StatusType of Design Length(km)

I

5 Sp. Rampa - Poriaha Full Engineering Design (DED) 11.1 OKBINTEK

6 Ps. Pedati - Kerkap Full Engineering Design (DED) 25.0 REVIEWBINTEK

7 Indrapura - Tapan Full Engineering Design (DED) 19.5 X

8 Bts. Kota Pariaman - Manggopoh Full Engineering Design (DED) 46.8 X

9 RantauTijang - Kota Agung Full Engineering Design (DED) 42.0 REVIEWBINTEK

10 Sp. Empat - Sp. Air Balam Full Engineering Design (DED) 61.7 X

11 Bantal - Mukomuko Full Engineering Design (DED) 50.1 REVIEWBINTEK

12 Kambang - Indrapura Full Engineering Design (DED) 55.2 X

13 SpRukis–TjKemuning Full Engineering Design (DED) 56.3 REVIEWBINTEK

II

14 Painan – Kambang Full Engineering Design (DED) 31.5 X

15 Sibolga – Bts. Tapsel Full Engineering Design (DED) 36.0 REVIEWBINTEK

16 Seblat – IpuhIncl. Air Lalang & Air Gunung Bridge Full Engineering Design (DED) 34.5 -

17 Sp. GunungKemala – Pg. Tampak Incl. WayTaau Bridge Full Engineering Design (DED) 36.8

0.03OK

BINTEK

18 Mukomuko – Bts. Sumbar Full Engineering Design (DED) 25.8 REVIEWBINTEK

Page 23: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project 15

Pack.No Link Name

Project Implementation PlanMarch 2013 DED

StatusType of Design Length(km)

19 Lais – Bintunan Full Engineering Design (DED) 11.6 REVIEWBINTEK

20 LubukAlung - Sicincin Full Engineering Design (DED) 14.6 X

21 LubukAlung - Kurataji Full Engineering Design (DED) 16.8 X

TOTAL 575.3

The DSC shall carry out all the activities necessary for engineering survey, detaileddesign study, design validation and updating including preparation of drawings,prequalification and bidding documents and estimated construction cost for all roads andbridges works for WP-2 and WP-3. However, in parallel with instruction from DGHencouraging P2JN/BBPJN to carry out the Detailed Engineering Design (DED) until DSCis established.

The CTC will then conduct necessary check and review on completed DetailedEngineering Design (DED) prepared by the DSC with steps as shown in Figure 4.2below.

Figure 4.2 Process of Check and Review on Completed DED

Considering the WINRIP procurement plan, the Highway Engineer has started TechnicalDesign Review in advance. Package No.5 Sp.Rampa – Poriaha is reviewing. The SeniorHighway Engineer will be mobilized on 1 February on schedule.

Progress of Technical Design Reviewing up to the end of January 2013 is included asAppendix B.

Page 24: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project 16

4.2 Procurements

Procurement shall be conducted under the Bank’s Procurement Procedures asmentioned in the Loan Agreement. The International Competitive Bidding (ICB) will applyto the packages with the construction estimated cost more than US$ 10 Million to complywith the Bank’s threshold for ICB. According to the GOI regulation, a prequalification shallbe applied for the packages with the construction estimated cost more than IDR 10 Billion.

Therefore, all subprojects for WP-1 have been started with prequalification since 30December 2011 for ICB multiple contract. This was an advanced procurement actionagreed by both DGH and the World Bank prior to the CTC establishment. The deadline ofQualification Document submission by the Applicants was on 28 February 2012. Thereare twenty nine (29) Applicants who submitted and applied their qualification documentsfor various packages which are summarized as follow.

Package No. 1 (Krui – Biha) : 13 Applicants applied. Package No. 2 (Pd. Sawah – Sp. Empat) : 13 Applicants applied. Package No. 3 (Manggopoh – Pd. Sawah) : 18 Applicants applied. Package No. 4 (Ipuh – Bantal) : 12 Applicants applied.

No Singles / JO Legal NameParticipate and Result of the PQ

PackageNo.1

PackageNo.2

PackageNo.3

PackageNo.4

1 PT. Adhi Karya (Persero), Tbk. Applied NA NA Applied2 PT. Adhi Karya - PT. Angkasapuri Konsursindo, JO. NA Applied Applied NA3 PT. Bangun Cipta Konstruksi - PT. Amarta Karya (Persero), JO. Applied NA NA NA4 PT. Brantas Abipraya (Persero) Applied NA Applied NA5 PT. Citra Gading Asritama NA NA NA Applied6 PT. Conbloc Infratecno Applied NA Applied NA7 PT. Duta Graha Indah, Tbk. Applied Applied Applied NA8 PT. Hutama Karya (Persero) NA Applied Applied NA9 PT. Hutama Karya (Persero) - PT. Suci Karya Bad inusa, JO. Applied NA NA Applied

10 PT. Jaya Konstruksi MP, Tbk. Applied Applied Applied A p p l i e d11 Kuk Dong Eng. Corp. - PT. Duta Graha Indah, Tbk., JO. NA NA NA Applied12 PT. Multi Structure Applied Applied Applied Applied13 PT. Nindya Karya (Persero) NA A p p l i e d Applied A p p l i e d14 PT. Nindya Karya (Persero) - PT. Rindang Tigasatu Pratama, JO. Applied NA NA NA15 Pan Asia Corp. - PT. Anugerah Karya Agra Sentosa, JO. Applied NA Applied A p p l i e d16 PT. PP (Persero), Tbk. NA Applied Applied NA17 PT. PP (Persero) Tbk - PT. Tri Citra Perdana JO. Applied NA NA Applied18 PT. Waskita Karya (Persero) NA Applied Applied NA19 PT. Waskita Karya (Persero) - PT. Angkasa Puri Konsursindo, JO. Applied NA NA NA20 PT. Waskita Karya (Persero) - PT. Daya Mulia Turangga, JO. NA NA NA Applied21 PT. Wijaya Karya – PT. Lubuk Minturun Karya Persada, JO. NA Applied Applied Applied22 PT. Yasa Patria Perkasa NA NA Applied NA23 PT. Angkasa Teknik Raya NA Applied Applied NA24 PT. Bangun Cipta - Barettamuda KSO. NA NA Applied NA25 PT. Bumi Rejo Applied NA NA Applied26 PT. Cipta Karya Prima Mandiri NA Applied Applied NA27 PT. Sumber Batu NA Applied NA NA28 Synohidro Co. Ltd. NA Applied Applied NA29 PT. Telaga Megabuana - PT. Mawatindo Road Construction, JO NA NA Applied NA

No. Of applicants submitted the document 13 13 18 12

Note : NA = Not Applied for Prequalification.

Page 25: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project 17

All three (3) Procurement Teams or Pokja evaluated all qualification documentssubmitted by those Applicants. Submission of the Application Evaluation Report (AER) tothe Bank was on 9 May 2012 for two packages (Package No.1 and No.4) and on 20June 2012 for other two packages (Package No.2 and No.3). The Bank still reviews theAERs and requested the Pokja to submit supporting documents. The latest request fromthe Bank was for company statutes information of the Government’s Entity participated inthe prequalification. DGH sent the required documents to the Bank on 15 January 2013.

DGH has also completed the draft of consolidated multiple contract ICB StandardBidding Document for four (4) packages under AWP-1. The draft had been submitted tothe Bank on 8 March 2012. The Bank’s comments had been issued on 12 March 2012.The draft of consolidated SBD was revised by DGH accommodating the Bank’scomments and submitted to the Banks on 27 June 2012. Second revision of the draftconsolidated SBD, as requested by the Bank regarding synchronization betweendrawings and Bill of Quantities by letter dated 1 August 2012, was then finally concurredby the Bank on 31 October 2012.

The WINRIP Procurement Plan is shown in Appendix D.

4.3 Civil Works ImplementationUntil the end of January 2013, there was no subproject contracted.

4.4 Civil Works ProgressNo civil works progress can be reported since there was no subproject contracted untilthe end of January 2013.

4.5 Quality AssuranceThe DSC will be responsible for quality assurance of materials and workmanship,certifying whether or not contractors have achieved the required results, as well asdocumentation and reporting based on the financial management plan. They will preparea Quality Assurance system covering all subprojects, and continuously monitor theeffectiveness of their supervision procedures.

The CTC will give guidance to them preparing quality assurance system includingstandard operation procedures for all work items under the contract based on contractspecification. He will also be responsible to conduct regular monitoring on the qualityassurance for all civil works implementation. A Quality Assurance Engineer of the CTC isplanned to be in charged prior to contract signing of the civil works.

4.6 Environmental and Social Considerations

4.6.1 Current Overall SituationA project category is assigned to each package as either Category A, B or Cdepending on the likely degree of influence on environmental issues with abrief explanation as follows.

Category A project is one which will have a significant negative impact on theenvironment and may have an influence on areas outside the actual project area.A project classified as such requires an AMDAL (ANDAL, RKL/RPL) study.

Page 26: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project 18

Category B project is one which affects the people or the environment to someextent but with a smaller impact than a Category A. The required environmentalanalysis is a UKL/UPL study only.

Category C project has minimal effect on the people or environment and anenvironmental analysis is not required. Standard operational procedures (SOP) areused to handle any minor problem which may arise.

Details of packages that require environmental and social safeguards are given inAppendix C.

The following table provides a summary of the work involved are 21 packages.

WorksProgram

No ofPackag

es

Investigations Approved by RemarksNos Documents BLH World Bank

AWP-1 4 8SPPL (4)Full LARAP (4)

4(SPPL)

4(Full LARAP)

NOLs have been issuedby WB, except for SPPL.

AWP-2 8 17

Simple LARAP (1)Full LARAP (8)AMDAL Study (4)UKL&UPL (4)

4(UKL&UPL)

0(Full LARAP)

1 (one) AMDAL Study forthree packages of AWP-2and AWP-3 (PackageNos. 7, 12 and 14).1 (one) AMDAL Study fortwo packages of AWP-2and AWP-3 (PackagesNo.11 & 16).

AWP-3 9 14Full LARAP (8)AMDAL Study (1)UKL/UPL (5)

5(UKL&UPL)

0(Full LARAP)

Total 21 39 13 4

4.6.2 Monitoring of Environmental Aspects During ConstructionCTC will circulate of environmental monitoring forms to DSC. This set of formsfocused on environmental and social impacts, and amounted to 7 pages. Theseforms were intended to be used every month by the DSC Environmental Specialist.

CTC’s environmental staff will actively advise to DSC on environmental monitoring,but have not directly carried out monitoring, despite the CTC TOR requirement to “toimplement the Environmental and Social Assessment and Management Planfor WINRIP”, which involves monitoring of environmental plans and studies.

After finalizing the Standard Environmental Clauses (SEC), CTC assisted SubditEnvironmental Affairs to produce monitoring forms covering all aspects of thetechnical specifications, and introduced them to participants of environmental trainingincluding P2JN, Project Manager, DSC, Contractors, Pokja etc. There are 69 pagesof forms, covering all aspects of construction.

4.6.3 Design Integration, Road Safety aspects and Monitoring of EnvironmentalStudiesTask 5.8.0 of CTC-2 TOR (Implement the Environmental Sosial Assessment andManagement Plan/ESAMP) and Para 10.9 of the PMM requires ensuring thatenvironmental management aspects of contracts have been implemented in

Page 27: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project 19

accordance with AMDAL, UKL&UPL, SPPL studies and Environmental issues willintegrated to design, Prepare environmental mitigation on construction stage forcontractor (Contractor Program for Executing Environmental Managemen PlanCPEMP/RKPPL). Therefore CTC will propose to visit the site of projects subject tostudies or issues, and ensure that the plans are being implemented. A schedule forthese visits is being discussed with DGH and related Provinces institutions.

4.7 Anti Corruption Issues

4.7.1 Anti‐Corruption Action Plan (ACAP)

Based on Terms of Reference (TOR) of Core Team Consultants (CTC) WINRIP, KeyTask Area 6 stated that CTC WINRIP have to support for implementation of Anti-Corruption Action Plan (ACAP) and monitoring their effectiveness. ACAP for WINRIPwas developed from the previous SRIP experiences. Basically, it has the same maincomponents. Within this plan there are four main pillars as indicated separately below:

a) Community Representative Observers (CRO)b) Publication / Disclosurec) Complaints Handling System (CHS)d) Third Party Monitoring (TPM)

4.7.2 Community Representative Observers (CRO)

The Community Representative Observers, required to observe the actual bid opening,were appointed for WP-1 group. All of the CROs were university staff, selected inaccordance with the World Bank suggestion to request assistance from localuniversities.

CRO is the independent observer who is not related directly or indirectly to theContractors, Consultants, and Suppliers or not be part of the WINRIP’s management,and not a member of any political party.

CROs selection procedures:

a. Review the criteria and qualifications of candidates for the CRO.b. Director of Planning, DGH/ as Chairman of the Project Management Unit,

delegated of the authority to the selection of the CRO to the Head of NationalRoads Implementation Agency (BBPJN) / Head of Procurement Services Unit(Unit Layanan Pengadaan - ULP), hereinafter referred to as Head of Balai.

c. Head of Balai invited CRO candidates from the local universities or colleges.d. Selection of CRO facilitated by Balai (BBPJN) / Procurement Services Unit (Unit

Layanan Pengadaan - ULP).e. Elected CRO and substituted CRO must follow the one day training held by the

PMU / CTC WINRIP.f. Head of Balai reported the result of CRO selection by attaching the Minutes of

Election Meeting and send an approval application letter of the CRO to Directorof Planning DGH as the Chairman of PMU.

g. Based on the report and a written request from the Head of Balai above, theDirector of Planning DGH as the Chairman of PMU signed a Letter of Agreementand the Decree of the Establishment of CROs.

Page 28: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project 20

The duties and obligations of CRO are:

a. CRO must be present in any procurement activity (Pre-Bid Meeting + Site Visit,Bids Submission and Opening of Bids, and Announcement of Bids Winner) byinvitation of the Procurement Committee, and are required to sign the attendancelist

b. If the elected CRO unable to attend on procurement activities, then SubstitutedCRO appointed have to attend these activities.

c. In discharging the Substituted CRO have the same responsibilities as electedCRO.

d. The CRO / Substituted CRO, after attending the Procurement activities, requiredto make a report of his/her activities and submit them to the PMU and CC to therelated Head of Balai.

CRO as the representative of the community is to be independent observers and inperforming their duties voluntarily and not demanding benefits of their works.

In the performance of its duties, the CROs receive transportation cost from their home/ office to the location of procurement meeting, and also he / she also receives perdiem or Out Station Allowance (OSA) and hotel accommodation if necessary to stay.CROs also got additional charged for their reporting costs. The financing standardsadjusted to the General Cost Standard (Standar Biaya Umum) issued by the Ministryof Finance.

The CRO’s financing charged to the Contract for Consulting Services for TechnicalAssistance for Core Team Consultants (CTC) No: 06-20/CTC/TA/LN/8043/1112, dated5 November 2012.

4.7.3 Publication/Disclosure

The second task under ACAP is publication of related ACAP documents for publicdisclosure with easy access to the general public and this is mainly manifest in theACAP segment of the WINRIP website. This ACAP section has been being designedto attain the best possible transparency of the project.

Ministry of Public Work (MPW) will provide necessary information in the ProjectImplementation Plan (PIP), Project Management manual (PMM) on its website, and inthe bidding documents, such as contact point for complaint (mail and e-mail address,phone, fax, text message). The contact will also include the Bank’s Fraud andCorruption Hotline. MPW will hold Annual Accountability Meetings to enhanceaccountability and project information sharing with civil society. The PMM will provideguidelines on disclosure of information related to the project. MPW official website willdisplay critical information on WINRIP to enhance both internal and externalmonitoring of the project:

Work Plan and Procurement Plan. Quarterly newsletter containing information on the list of contracts,

implementation progress, projects related activities, number, types and statusof complaints in each location. The newsletter will also be made available tocivil society in hard copy and through electronic mailing system.

Page 29: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project 21

Mid-Term Review Report, promptly after completion of the mid-term reviewimplementation support is carried out in accordance with the loan agreement;

All final audit reports (financial or otherwise, including qualified audit reports)prepared in accordance with the loan agreement and all formal responses ofthe government in relation to such reports. The publication should be donewithin one month after the report is accepted as final.

Contracts awarded with information on general scope of work (with location),value, and summary information of the awarded firms/ contractors. Thepractice in other projects demonstrates that disclosure of contracts awardedwill help in reducing fraudulent practices

Ministry of Public Works (PU) maintains a website: http://www.pu.go.id/, with a link to'eproc.pu.go.id' for information on semi e-procurement or e-procurement. PMUWINRIP supported by CTC will develop his own website: http://www.winrip-ibrd.com,and with it all the information and data about WINRIP be inputted or uploaded on thissite.

In the application of one of the components of ACAP, the public disclosure andtransparency, it is necessary to spread information and increase the capacity of allstakeholders involved in the implementation of this WINRIP project, through a varietyof relevant training. The trainings have been expressed in the ToR of CTC WINRIPand described in the Project Implementation Plan (PIP).

One of the major risks to effective project implementation and management derivesfrom the likelihood that project management staff does not have adequate training in orexperience of the management of large-scale projects.

Procedures to mitigate these risks include the need to conduct comprehensive trainingof staff in all participating entities involved with the procurement, financial managementand supervision of the project.

In response to this need, an Annual Training Program has been prepared, whichidentifies the major training requirements to be addressed. This program builds onprevious training programs prepared and implemented by DGH to strengthenmanagement staff and support the implementation of loan programs like WINRIP.Activity of training will be carried out and supported in CTC contract, including thebudget which use provisional sum budgets

Internal training of central and regional government staff will be required to supportand strengthening administration and management of the project trhroughout itsimplementation. This will help ensure that procedures for procurement, projectimplementation and monitoring are well understood, to explain the safeguard aspect ofthe project including the Anti-Corruption Action Plan (ACAP) and the Environmentaland Social safeguards (ESS), and to reinforce technical guidelines as required.

Page 30: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project 22

Training will be provided an extension of normal DGH training program as outlined intable below:

No Training Topic Purpose Target Agencies/Units

EstimatedTrainees/

Year

1 Procurement Training(Including Provision of ACAP)

Special Training in procurementfor members of ProcurementCommittees Detailed provision of ACAP

ProcurementCommittees atProvincial Level

30

2 Training In ProjectManagement

Required civil service training Prospective staff forSatkrer (Work Units)

20

3 Refresher Training in ProjectManagement

Feedback to Projectmanagement staff from widerexperience

Satkrer (Work Units) inProvinces

60

4 Application of PMM(including other provisions ofACAP)

Familiarization with ProjectManagement requirements Awareness of particular

requirements of ACAP

Senior Staff ofProvincial Agencies Administrative Staff Technical Staff

60

5 Financial ManagementReporting Training (IFR)follows on from PMMTraining

Procedures for monthly datacollection, consolidation andreporting for procurement,Disbursment; Physical Progress

Staff of Satkers Staff of Provincial

Financial Agencies Technical Staff

30

6 Environmental MonitoringWorkshops

Review of Results ofEnvironmental Special Clauses(ESCs) to be provided by DSC

Provincial WorksAgencies Supervision

Consultants Contractors

30

7 Training of Treasurers(Bravate A Cource)

Basic civil service training frofinancial officers

Project Units (Satker) inProvinces

20

Total Trainees Estimated 250

WINRIP project implementation is planned for 3 (three) years (2013 -2015), thenumber of trainees is 3 x 250 = 750. It is also possible on the way of time, type orduration of training may change tailored to the needs.

The Training Program summarized and described below:

1. Procurement Training: For the Procurement Working Group Committees(POKJA Pengadadaan) of each entity.

To make sure that members of Procurements Committees in each participatingentity are fully familiar with requirements of Perpres 54/2010 and Perpres70/2012 and World Bank Procurement Guidelines, plus provisions of PMMregarding procurement (including the Anti-Corruption Action Plan, ACAP).

The intention is to provide in-depth training once a year, before the maintendering activity, and timed to ensure that this is not delayed.

2. Training in Project Management: Annual course for prospective key staff.

Purpose of Training is to train the candidates for future appointments as keyproject staff in all aspects of Project Management.

Prospective key staffs (Heads of Work Units, Commitment Officers andTreasury), who were do not yet have a certificate in project management. The

Page 31: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project 23

candidates will be selected from officials of the public works agencies(National/Provinces) in the 3 / 4 provinces with WINRIP Subprojects

3. Refresher Training in Project Management: Annual refresher course for keystaff of project units.

Training purpose is to give staff currently occupying key position in Work Units abrief updating in latest developments in project management.

Training target is Key staff: Heads of Work Units, Commitment Officers andTreasurers.

4. Project Management Manual (PMM) Training: Initial training / annual refreshertraining in use of PMM.

To introduce provisions in the PMM to all the elements that are responsible forthe implementation of WINRIP, in order to carry out their duties in accordancewith the need to properly and fully observed during project implementationWINRIP.

All groups participating in project implementation should be included in theaudience addressed by this component

5. Training in Reporting for FMR: Initial training / subsequent refresher training inthe details of monthly financial and other reporting requirements for FMR andother financial management aspects of the project.

The purpose is to provide staff at project level with training in the preparation andsubmission of monthly reports on disbursements, procurement activities andproject progress.

The recipients of this training will include but not limited Staff of the units involved in recording and reporting project performance

information of each project (2 persons per project).

The Chief Financial Officer (Kepala Bagian Keuangan) in each Province (2per entity).

6. Environmental Workshop: Annual workshops to disseminate environmentalmanagement and monitoring procedures to contractors, consultants and keyproject staff.

The training is intended to provide staff and consultants with information on theEnvironmental Special Clauses in works contracts and to enhance theirawareness of their responsibilities both under the project and in the wider contextof all works implementation.

7. Training in Treasury (Brevet A): Annual training for financial staff of projectunits.

To provide staff currently occupying key financial positions in Work Units with fullunderstanding of financial record keeping and compliance with Ministry ofFinance and Treasury standards and procedures.

The training target is the key financial staffs (Treasurers, SPM Issuing Officers,

Page 32: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project 24

and Accountants).

4.7.4 Complaints Handling Mechanism (CHS)

The ACAP as adopted by the Ministry of Public Works for WINRIP states on thesubject of “Complaints handling system”. The Community Development Specialist andthe Management Information Specialist will play a crucial role in the set-up of theComplaints Handling System (CHS) within PMU, in cooperation with the PMU officer(s)in charge of the Complaints Handling Unit (CHU).

CHS essentially has four main components as follows:

Data Entry.

All complaints were expected to be submitted through the WINRIP website but infact, to date, most complaints have been received by letter, either directly orindirectly, although a few were sent by fax or email. However, to attain the bestpossible transparency of the project, complaints submitted manually through letter,facsimile, telephone, e‐ mail or visit to the Public Works regional offices will beentered in the WINRIP website by the CHS team of CTC. The possibility of usingthe ‘short message service’ (SMS) from a cell phone for complaints wasconsidered and it was decided that all SMS messages, although not treated asformal complaints, will be recorded as additional information.

Complaint Registration.

Every submitted complaint is registered and stored into the CHS database,categorized, and sent to the correlated expert for future consultation in order toformulate a response.

Complaint Assessment.

The CHS Team assesses the urgency and complexity of all complaints.Simple complaints are followed by the formulation of a response for PMU’sapproval before uploading the formal response into the WINRIP website.Complex complaints are followed by a thorough investigation.

Field Investigation and Analysis.

In the case of an investigation being required, the CHS team will make field visitsand take necessary action such as discussion with related institutions (Satker,Dinas, Supervision Consultant, etc); invite the complainer; interview thecontractor; etc. Findings will be used for analysis to formulate a conclusion,solution, next action and any further decision.

Problem Solving and taking the Decision.

Complaints that have been investigated have to be studied, analyzed, discussedwith various stakeholders, evaluated the problems and solved the problems/lookfor the solutions, and made the decisions and imposed the sanctions if necessary.All the decisions that have been taken are reported to the PMU and submitted tocomplainant and to all related parties. Furthermore PMU convey the decision and/ or sanctions to the Directorate General of Highways - Ministry of Public Worksand to the World Bank.

Page 33: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project 25

4.7.5 Third Party Monitoring (TPM)

All WINRIP packages are designed to have external parties involved inconducting an independent assessment of the project throughout construction.Project information is accessible through the WINRIP website (under construction),project information booth which is normally maintained in the PPK/Satker/Dinasoffice or, project announcement (billboard) at each site. ACAP requires a third party,from outside the project, to independently monitor the progress of construction work ofeach link and these personnel are provided by universities nearby each package.

It was decided that the best method of recruitment for TPM was through theuniversities closest to each package and PMU mailed invitations asking them toexpress their interest in forming independent monitoring teams of Third PartyMonitors. This concept is based on the fact that Universities/Technical Facultieshave the engineers available for recruitment and Universities could use thisopportunity to be involved in public service. It is hoped that this concept will be moreeffective and more efficient in getting legitimate, competent, independent ThirdParty Monitoring (TPM).

The duties of a TPM included:

a) Report to the PPK for his intended package and obtain copies of all drawingsand contract documentation.

b) Make at least three (3) separate visits to site, with each visit up to four (4)days long, and ascertain that the works are being carried out in compliancewith the drawings and documentation.

c) Prepare and submit a report for the PMU following each visit with their lastreport post PHO.

4.8 Road Safety Audit

As stipulated in the TOR, the CTC shall conduct independent Road Safety Audits (RSA)for all sub-projects. This task is under responsibility of the Senior Road Safety AuditEngineer. The RSA for AWP-1 shall be conducted one time during construction. TheRSA for AWP-2 and AWP-3 shall be conducted each one time during design and eachone time during construction, and make sure that some initial RSA action have to beincorporated in the design for AWP-2 and 3. The purpose of the RSA is to identify theroad safety weaknesses in design during the design and actual construction and makerecommendations for realistic improvements which can be handled within the scope ofthe construction works of the project. The CTC shall compile all the road safetyrecommendations in the Road Safety Audit Reports which shall be part of the technicalreports. The RSA report has to be disseminating in particular to the audited packages.

Page 34: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project 26

5 FINANCIAL & MANAGEMENT INFORMATION SYSTEMS

5.1 Draw‐Downs and Future Costs

Details of the disbursements already made from the loan are listed in the following sub‐section.

5.2 Disbursement

The total disbursement from the loan to the end of January 2013 was USD800,000.00 equivalent to approximately 0.32% of the loan funds. No disbursement duringthe month of January 2013.

The total expenditure to date measured in the term of the World Bank commitment,not including the Special Account advance, is shown in Appendix C. The followingtable summarizes the individual disbursements as calculated by CTC but retainingthe total disbursement from Client Connection at the end of January 2013.

Category Description Loan Amountin US$

TotalsDisbursed toEnd March

in US$

%Disbursed

1

Part 1 Bettermentand CapacityExpansion of

National Roads.

220,400,000.00 0 0

2Part 2

ImplementationSupport

16,000,000.00 674,177.03 4.21

3

Part 3Road SectorInstitutional

Development

1,000,000.00 0 0

4

Part 4Contingency forDisaster Risk

Response

0 0 0

Unallocated 12,600,000.00 0 0

LN 8043 DA-A 125,822.97 0

Original LoanAmount 250,000,000.00 800,000.00 0.32

5.3 Management Information System

5.3.1 General OverviewThe Management Information System tasks will include the followings:

1) Information Systema. Develop and manage a database system to store soft copy documents

into a file storage server.b. Establish a Document Management System (DMS) to provide:

Page 35: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project 27

Letter Database System, used to record all information of incoming andoutgoing letter.

Document Library System, used to record all information of hard copydocuments then store it into library shelves.

c. Create and maintain a WINRIP official website.d. Develop and update a Geographic Information System (GIS) of spatial

and roads information that overlay into Google Maps.e. Develop and manage a Financial Management Information System

(FMIS), the web based application to monitoring financial progress.f. Develop and manage a Progress Monitoring System (PMS), the web

based application to monitoring physical progress.g. Provide a Complaint Handling System (CHS), used and support the ACAP

activities to accommodate complaints from the public via sms gateway,email and website.

2) Data Collection and Document Uploada. Collecting data and updating list of data catalog every month.b. Uploading documents into a file storage server.

3) Technical and Computer Troubleshootinga. Setting up and manage cable network of local area network and internet

connection.b. Setting up and manage hardware problem of the computer, printer, copier

and phone.c. Software installation and cleaning up of computer virus.

5.3.2 Database

A typical workflow in management of incoming and outgoing data will be dividedinto 3 types of data handling, below:

1. Hardcopy, the document is stored in a rack.2. Soft files, saved in the File Storage Server.3. Data information, inputted in database applications.

For further handling that needs to be made an integrated database managementsystem so that all data can be stored properly. The database system will beprepared to store all of WINRIP project information in a systematic, easilytraceable, maintainable, and manageable format as outlined below with thefollowing systems:

a. File Storage Server, used to store all files of reports and other documents.b. Letter Database System, used to record all information of incoming and

outgoing letter.c. Document Library System, used to record all information of hard copy

documents then store it into library shelves.

Page 36: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project 28

Following further review the sub‐folder server file system will be provided toaccommodate the needs of the professional staff as follows:

CODE ROOT 1st FOLDER 2nd FOLDER01 01_Project_Document

01_01 01_01_PIP01_02 01_02_Loan_Agreement01_03 01_03_Loan_Agreement_Extention01_04 01_04_PAD01_05 01_05_PMM01_06 10_06_Aide_Memoire

02 02_General_Contract02_01 02_01_Pre-contract02_02 02_02_Contract02_03 02_03_Mobilization02_04 02_04_Amendment02_05 02_05_Addendum02_06 02_06_MOA

03 03_General_Report03_01 03_01_Inception_Report03_02 03_02_Monthly_Progress_Report03_03 03_03_IFR03_04 03_04_IFR_Q

03_05 03_05_Procurement_Committee_Readiness_Assessment_Report

03_06 03_06_Bid_Evaluation_Procurement_Report03_07 03_07_Draft_Project_Completion_Report03_08 03_08_Project_Completion_Report03_09 03_09_Technical_Report

04_01 04_General_Letter

05 05_General_Documentation05_01 05_01_Meeting05_02 05_02_Workshop05_03 05_03_Training05_04 05_04_Site_Visit

06 06_Office_Manager06_01 06_01_Document06_02 06_02_Operational

07 07_Highway07_01 07_01_General07_02 07_02_Design_Review

07_02_01 Package 1, 2, 3, 407_03 07_03_Auditor

07_03_01 Package 1, 2, 3, 407_04 07_04_Meeting07_05 07_05_Report

08 08_Quality_Assurance08_01 08_01_General08_02 08_02_Meeting08_03 08_03_Report

09 09_Financial09_01 09_01_General09_02 09_01_Meeting09_03 09_01_Report

10 10_Environmental10_01 10_01_General10_02 10_02_Environmental_Review10_03 10_03_Environmental_Studies10_04 10_04_HIV/AIDS10_05 10_05_Monitoring10_06 10_06_Meeting10_07 10_07_Report

11 11_Social_Impact

Page 37: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project 29

CODE ROOT 1st FOLDER 2nd FOLDER11_01 11_01_General11_02 11_02_LARAP_Review11_03 11_03_Monitoring11_04 11_04_Meeting11_05 11_05_Report

12 12_Procurement12_01 12_01_General_Procurement_Notice12_02 12_02_Special_Procurement_Notice12_03 12_03_Bidding

12_03_01 CTC12_03_02 DSC12_03_03 Civil Works12_03_04 Capacity Building

12_03_05 DisasterManagement

12_04 12_04_Meeting12_05 12_05_Report

13 13_Data_and_Information13_01 13_01_General13_02 13_02_Source_Code13_03 13_03_Master_Software13_04 13_04_Meeting13_05 13_05_Report

14 14_Community_Development14_01 14_01_General14_02 14_02_ACAP_Review14_03 14_03_WPM14_04 14_04_PP314_05 14_05_Meeting14_06 14_06_Report

15 15_Supporting_Staff15_01 15_01_Tedi_Okta_Pratama15_02 15_02_Banu_Amanda_Zuhri15_03 15_03_Data_Manager15_04 15_04_Bayu_Rendro

Each folder will only be able to be accessed by responsible and nominated staffmembers to prevent any undesirable alteration or addition to the stored material.Each engineer will save every document into its correct folder which will be backed‐up weekly by the Management Information Specialist on a 1.5 Terabyte external harddisk.

5.3.3 Project Progress Monitoring SystemA Project Progress Monitoring System will be developed to record all of WINRIPpackage progress activities including financial and physical progress.

5.3.4 Website

The WINRIP-CTC website will contain all of the following items:

a) General WINRIP information including copies of all reports i.e. Monthly ProgressReports, Social and Environmental Status Reports and the Road Safety AuditReports.

b) Project list and Project Progress Status including Procurement Plan and BidWinners, and Copies of all Bid Documents.

c) ACAP and Complaint Handling System including contact points, list of

Page 38: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project 30

Community Representation Observers, and list of Third Party Monitors.

d) Announcements (current and archived)

e) Newsletter

f) Documents, (including all reports and bidding documents)

g) Gallery and other important information

h) Package Location Map

i) Response from the CHU will be recorded following contract signing.

During January 2013 there were no activities for the WINRIP website due to latemobilization of the Information Management Specialist.

Page 39: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project 31

6 PROJECT PERFORMANCE6.1 World Bank and GOI Compliance

6.1.1 World Bank Missions

No World Bank missions visited Indonesia during January 2013

6.1.2 Performance IndicatorsGOI and the World Bank have agreed on a set of Key Performance Indicators (KPIs)to measure the project’s performance in achieving its stated development objectives.These KPIs are provided in the World Bank’s Project Appraisal Document (PAD),together with baseline data and targets.

The annual targets for KPIs that are indicated in the Project Appraisal Document arebased on the initial Project Implementation Schedule as shown in Appendix F.

6.2 Implementation Support Components

6.2.1 Core Team Consultant (CTC)

The CTC is responsible to provide support to the PMU and DGH in the managementof the Project, based in Jakarta. The CTC tasks include financial and progressmonitoring and reporting, information management and dissemination, qualityassurance and performance review for the Design and Supervision Consultants(DSC), implementation and monitoring of the anti-corruption action plan, support forproject monitoring and evaluation, and support for implementation of a trainingprogram to support project management and implementation.

The CTC contract No. 06-20/CTC/TA/LN/8043/1112 was signed on 5 November2012 by both DGH and a Joint Venture of PT. Perentjana Djaja, YongmaEngineering Co.Ltd., and PT. Epadascon Permata Engineering Consultant.

The main CTC activities during January 2013 included:

Continue furnishing office facilities. Continue mobilizing CTC personnel. Continue assistance to PMU as and when required. Prepare and submit Inception Report. Prepare draft of the first Monthly Progress Report. Continue review all project documents under the WINRIP. Prepare draft LARAP Monitoring Report for Package No.01 Krui – Biha. Prepare draft LARAP Monitoring Report for Package No.02 Padang Sawah –

Simpang Empat. Prepare draft LARAP Monitoring Report for Package No.03 Manggopoh –

Padang Sawah. Prepare draft LARAP Monitoring Report for Package No.04 Ipuh – Bantal. Prepare WINRIP Procurement Plan. Review WINRIP PMM (Project Management Manual) especially Financial

Management aspects.

Page 40: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project 32

6.2.2 Design and Supervision Consultant (DSC)

The Design and Supervision Consultant (DSC) will be responsible for design of WP 2and WP 3 civil works and supervision of all civil works. They will have the role of‘Engineer’ under a FIDIC-type contract. The tasks include the preparation andmaintenance of a quality assurance plan, validation and updating of designs,supervision of all civil works, environmental and social monitoring and management,and support for financial and progress monitoring and reporting.

The DSC will also be responsible for quality assurance of materials andworkmanship, certifying whether or not contractors have achieved the requiredresults, as well as documentation and reporting based on the financial managementplan. They will prepare a Quality Assurance system covering all subprojects, andcontinuously monitor the effectiveness of their supervision procedures. The team willbe contracted and managed by DGH through the Bina Marga Regional Office (BalaiBPJN II), and will be based in Padang, West Sumatra.

DSC recruitment process is still ongoing. Technical Evaluation Report was completedby the Procurement Team in Balai II Padang, West Sumatra. The report has beensubmitted to the Bank on 20 December 2012. Until the end of January 2013, theBank’s approval for the report was not yet issued.

6.2.3 Road Sector Institutional DevelopmentThis component consists of technical assistance for capacity building for the newenvironment/risk mitigation and road safety unit to enhance its capacity for disasterrisk assessment and planning, risk mapping of land-slides, coastal erosion,earthquake and floods, analysis of alternative road designs for road segmentspassing through critical environmental assets and vulnerable areas.

It is planned so far that there will be three (3) consultants services for:

Capacity Building of Disaster Risks Reduction Capacity Building for Environmental Management Capacity Building for Road Safety

Draft of the respective Terms of Reference has been being prepared by the Sub-Directorate of Environment and Road Safety outlining the proposed scope activitiesfor the component.

During preparation of this Report, the procurement for consultants under thiscomponent has not yet been started. Preparation for the procurement would becoordinated by the PMU, DGH Procurement Team (Pokja) and the CTC.

6.3 Training

The Annual Training Program to support WINRIP will include intensive courses andrefresher training and workshops, highlighting new and poorly-understood aspects of theprocedures and safeguards. It includes a limited range of technical topics, other thanenvironmental management (see the Table WINRIP Training Program in sub-Chapter4.7.3).

Page 41: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project 33

Until January 2013 only one type of training that has been carried out namelyProcurement Training. The Training of Procurement was held in Bandung, on November1 – 2, 2012 organized by PMU/PPC, as soon as after the completion of the WINRIPLoan Agreement, and after the PMU and Procurement Committees for AWP-1 havebeen established.

The Outcome of the procurement activities is the implementation of procurement processis smoothly and successfully. To achieve these outcomes, the Procurement training isnecessary in order to get the output of the qualified and competent of ProcurementCommittee.

However, in addition to the procurement process smoothly and properly, it must alsosatisfy the principles of transparency and accountability that has been agreed in the LoanAgreement, as well as should be also implement the Anti-Corruption Action Plan (ACAP),according to the World Bank's Guidelines on the Prevention and Resistance AgainstFraud and Corruption Act in the Project funded by the World Bank, IDA Credit and Grant,dated October 15, 2006 and was updated in January 2011, and must be in accordancewith Presidential Regulation No. 54 / 2010 and Presidential Regulation No. 70 / 2012.

This training was attended by:

1. Procurement Committees (Pokja Pengadaan) from provinces of Sumatera Barat,Lampung, Bengkulu, and Sumatera Utara,

2. Project Manager (Satker and PPK) from four packages AWP-1 WINRIP (package01. Krui – Biha, package 02. Padang Sawah – Simpang Empat, package 03.Manggopoh – Padang Sawah, and package 04. Ipuh – Bantal),

3. National Roads Implementing Agency / Balai Besar Pelaksanaan Jalan Nasional(BBPJN I Medan, BBPJN II Padang, and BBPJN III Palembang),

4. Project Management Unit (PMU WINRIP) and

6.4 Anti‐Corruption Issues

6.4.1 Anti Corruption Action Plan (ACAP)The main duties of the Community Development Officer are implemented of Anti-Corruption Measures, and Monitoring their Effectiveness. Provide assistance asrequired with the establishment of anti-corruption measures necessary to support theproject, and monitor and report their effectiveness based on the Anti-CorruptionAction Plan (ACAP) agreed between the World Bank and the DGH.

The following tasks particularly need to establish procedures to be undertaken:

Selection of Community Representative Observers (CROs) of civil societygroups to attend the procurements process on key procurement steps includingpre-bid meeting and site visit, bids submission and bids opening, and theannouncement of the bid winner. These CROs will be invited from localuniversities or other selected independent institutions, and will sign theattendance list for the procurement/selection process.

Page 42: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project 34

Establishment of a Third Party Monitoring (TPM) mechanism, whereby themedia and civil society groups can become involved in monitoring the progressof the project. This mechanism will include regular sharing of information withthe media.

Establishment and Management of a Complaints Handling Mechanism (CHM),which includes maintaining project complaint log and filing to monitor status offollow-up of each complaint. This mechanism will include provision for follow upinvestigations of substantial complaints by the Inspectorate General of Ministryof Public Works or third party audit to ensure independence and reliability of thesystem. The CTC assignment concerns the monitoring of the aspects of Anti-Corruption Action Plan (ACAP) implementation and where required act pro-active in resolving issues when such a matter arises. The CommunityDevelopment specialist has a major role in monitoring performance and assistsPMU in the set-up and follow-through of the Complaints Handling Unit (CHU)for the ACAP related incidents

Enhanced Disclosure Provisions and Transparency, Ministry of Public Work(MPW) will provide necessary information in the Project Implementation Plan(PIP), Project Management manual (PMM) on their website, and in the biddingdocuments, such as contact point for complaint (mail and e-mail address,phone, fax, text message). The contact will also include the Bank’s Fraud andCorruption Hotline. MPW will hold Annual Accountability Meetings to enhanceaccountability and project information sharing with civil society. The PMM willprovide guidelines on disclosure of information related to the project. MPWofficial website will display critical information on WINRIP to enhance bothinternal and external monitoring of the project

6.4.2 Community Representative Observers (CRO)

The activities of the Community Development Officer during January 2013 waspreparation of selection of the Community Representative Observers (CROs) mainlyfor 4 (four) Packages of Annual Works Program (AWP-1) WINRIP in region ofNational Roads Implementation Agency (Balai Besar Pelaksanaan Jalan Nasional‘BBPJN’) III Palembang, that are Package: 01. Krui – Biha, Lampung Province andPackage: 04. Ipuh – Bantal, Bengkulu Province, and 2 (two) Packages in region ofNational Roads Implementation Agency (Balai Besar Pelaksanaan Jalan Nasional‘BBPJN’) II Padang, that are Package: 02. Padang Sawah – Simpang Empat, andPackage: 03. Manggopoh - Padang Sawah, (West Sumatera Province)

Activities progress during January 2013, were: Preparation of Term of Reference (TOR) of the CRO's Selection, Provide Standard Format of the CRO's Reports, and Preparation of Guidelines/Manual for Selection of CROs.

6.4.3 Disclosure and Transparency

Activities for Public Disclosures and Transparencies will be done in lines on thetraining of Project Management Manual (PMM) and Financial Monitoring Report

Page 43: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project 35

(FMR) or other relevant trainings. And inputting the data or upload the articles will bedone into the website of WINRIP which will be developed by the ManagementInformation Specialist.

Disclosure and transparency activities have partly been done through ProcurementTraining as reported previously in Section 6.3.

6.4.4 Third Party Monitoring (TPM)

Selection of TPMs will be done by invite the Universities/Colleges who interested toparticipate in Third Party Monitoring. The TPMs for the first four AWP-1 packages arenow being preparing, and will elected before signing the construction contracts.

Some steps of the selection of TPM activities have been done until the end of March2013, and the activities will be done for future time, are as follow:

Preparation the initial draft of ToR of selection the TPM is currently running. Providing the TPM selection guidelines has started in the end of March 2013. Providing the Training Materials for the TPM is ongoing preparing outlines. Sending the official letter from the Director of Planning as Chairman of PMU to

Head of BBPJN II & III, about the Selection of TPM + TOR and GuidelinesDocument

Help the PMU on formulating the TPM Evaluation Team. Socialization of the TPM selection for AWP-1 packages. Implementation of selection of the TPM for AWP-1 packages by TPM

Evaluation Team Delivery of the Training for elected TPM. Approval process of elected TPM Signing of TPM contracts and mobilization of TPM.

During January 2013 there was no activity regarding the Third Party Monitoring(TPM).

6.4.5 Complaint Handling System (CHS)

The implementation of these activities will be collaborated by both CommunityDevelopment Officer and the Management Information System (MIS) Specialist todevelop the system to the WINRIP website. The web will be developed by MISSpecialist soon after his mobilization. These activities is predicted to be completed atthe end of year 2013 or early 2014.

Establishment of Management of a Complaints Handling Mechanism System (CHS)which includes several components that needs to be prepared in connection with themanagement of CHS as follows:

Formation of the Complaints Handling Unit (CHU). Preparation of Complaints Register and the complaints address. Preparation of Complaint Handling Procedure. The completion of the Initial investigation of a complaint Procedure, and the

procedure for the investigation of Complaints, as well as the conclusion ofinvestigation.

Page 44: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project 36

The establishment of the Complaint Handling Commission (Executing Agency). Preparation of the device for Executing Agency. The development of a code of conduct and actions for Implementing

Institutions/ Implementing Agency (Bidders, Suppliers, contractors andConsultants).

Support the PMU in the Management and Monitoring of the implementationpolicy in handling public complaints

In the implementation of Complaint Handling System (CHS) essentially there arefour main components as follows:

Data Entry. Complaint Registration. Complaint Assessment. Field Investigation and Analysis. Problem Solving and Taking the Decision

During January 2013 there was no activity regarding the Complaint HandlingSystem (CHS).

6.5 Road Safety AuditThe Senior Road Safety Audit Engineer has not yet been mobilized. The activity forproject road safety audit will be reported soon after he is in charged.

6.6. Environmental and Social Impact Issues

6.6.1. LARAP Study Report for Package No.01 : Krui – BihaThe report was concurred by the World Bank on 4 January 2013. The MonitoringLARAP Report will be prepared by the CTC.

6.6.2. LARAP Study Report for Package No.02 : Padang Sawah – Simpang Empat

The report was concurred by the World Bank on 13 January 2013. The MonitoringLARAP Report will be prepared by the CTC.

6.6.3. LARAP Study Report for Package No.03 : Manggopoh – Padang SawahThe report was concurred by the World Bank on 4 January 2013. The MonitoringLARAP Report will be prepared by the CTC.

6.6.4. LARAP Study Report for Package No.04 : Ipuh – BantalThe report was concurred by the World Bank on 10 December 2012. The MonitoringLARAP Report will be prepared by the CTC.

6.7 Management Information SystemsThe Information Management Specialist has not yet been mobilized. The activity formanagement information system will be reported soon after his mobilization.

Page 45: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project 37

6.8 Quality Assurance

The Quality Assurance Engineer has not yet been mobilized. The activity for projectquality assurance will be reported soon after he is in charged.

6.9 Project Risks and Mitigation Measures

6.9.1 Risks Related to DelaysSince the detailed engineering design (DED) is under responsibility of the Design andSupervision Consultant (DSC), delay on DSC establishment affected to theprocurement of AWP-2 and AWP-3 sub-projects. As discussed previously above, inparallel with the instruction to speed up the process, detailed engineering design(DED) of some subprojects of WP-2 and WP-3 were prepared and completed byrespective P2JN.

Considering the WINRIP procurement plan, the Highway Engineer has startedTechnical Design Review in advance. Package No.5 Sp.Rampa – Poriaha isreviewing.

6.9.2 Financial RisksThe following factors will be monitored during implementation of the loan project.

Loan Amount Actual Tender Prices Price Adjustment Currency Fluctuation Current Estimated Situation

No risk was detected until preparation of this report since the main program of theloan (civil works implementation) has not yet been started with contract sign.

6.9.3 Risks Related to Quality

The quality of work is inherently tied to the competence of the Contractors and thediligence of the Supervision Teams. The competence or otherwise of contractorsshall be considered at the time of bid evaluation and prior to the award of anycontract.

The quality of supervision however is influenced by the following factors:

Ensuring that supervision staff levels are fully manned with competent,honest, qualified and experienced personnel.

The provision of properly equipped laboratories with properly trainedoperators for each package.

Package supervision comes under the responsibilities of the immediate supervisionteams and the relevant DSC but the Quality Assurance Engineer from CTC, whenmobilized, will periodically monitor their performance.

Page 46: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project 38

7 ISSUES and RECOMMENDATIONS7.1 Current Situation

The main issue during January 2013 is the procurement of four (4) packages underAWP-1. Prolong discussion on the Application Evaluation Reports (AERs) will havepotentially delay on the tender.

The tender could not be started until the AERs are approved by the Bank even theBidding Documents are ready to be issued. In the mean time, the existing roadconditions of the four packages under AWP-1, which are predicted being deterioratedrapidly by the traffic during almost a year, shall be properly anticipated.

Another issue is establishment of the Design and Supervision Consultant (DSC). It isrequired to expedite the DSC recruitment process. The DEDs for AWP-2 and AWP-3packages shall be completed soonest and the procurement can be started immediately.

7.2 Action RequiredThe project managers (PPKs) are required to carefully investigate current condition ofthe existing roads to find out whether the DED is needed to revise or not.

It is hopefully that the Bank will be soon approving the proposed consultants rank basedon the Technical Evaluation Report submitted by DGH on 20 December 2012. Theopening of Financial Proposal will be conducted by the DGH’s Procurement Committeeafter the Bank’s approval on the report.

Page 47: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project

Appendix AOverall Loan Progress

Page 48: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Exchange Rate : $1 equal to IDR 9,750 31 January 2013

Estimated Contractor(s) or Total Est. BudgetStarting Completion Consultant(s) Man-Month WB + GOI Remarks

Date Date Name (Excl. the (PIP) Original Revised Physical Man-Month Physical Man-Month Physical Man-MonthSupp. Staff) (USD, Excl.VAT) (Excl. VAT) (Excl. VAT) ( % ) ( MM ) ( % ) ( MM ) ( % ) ( MM )

1 Betterment and Capacity 314,900,000.00Expansion of NationalRoads

1.A AWP-1 ICB DGH 81,630,000.00 Procurement process (prequalification).

1.B AWP-2 and AWP-3 ICB / NCB DGH 227,100,000.00 Detailed Engineering Design preparation.

1.C Contingency - DGH 6,170,000.00

2 Implementation Support 6,000,000.00

2.A Core Team Consultants (CTC) QCBS DGH 6-Nov-12 15-Feb-16 PT. Perentjana Djaja 556 5,000,000.00 $1,276,700.00 6.791% 37.76 3.914% 21.76 -2.878% -16.00 Ongoing Joint Venture with Rp21,415,400,000.00 Yongma Engineering Co.Ltd. Or US$ equivalent total : PT. Epadascon Permata $3,473,151.28

2.B Design & Superv. Consultants QCBS DGH Recruitment process.

2.C Incremental Operating Cost Varies PMU 1,000,000.00Including Technical Audits

3 Road Sector Institutional 1,000,000.00Development

3.A Capacity Building for NCB DGH 350,000.00 Preparation of TOR.Disaster Risks Reduction

3.B Capacity Building for NCB DGH 350,000.00 Preparation of TOR.Environmental Management

3.C Capacity Building for NCB DGH 300,000.00 Preparation of TOR.Road Safety

4 Contingency for Disaster - DGH -Risk Response

5 Unallocated - DGH 18,100,000.00

Total 340,000,000.00 3,473,151.28 6.791% 37.76 3.914% 21.76 -2.878% -16.00

Appendix - AOVERALL PROGRESS STATUS

Description

WESTERN INDONESIA NATIONAL ROADS IMPROVEMENT PROJECT (WINRIP)IBRD LOAN No. 8043-ID

Proc.MethodCategory

Planned Actual BalancePROGRESS

Respon-sibility

Contract Value/BudgetTotal ( WB + GOI )

Page 49: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

CTC30-Nov-12 31-Dec-12 31-Jan-13 28-Feb-13 31-Mar-13 30-Apr-13 31-May-13 30-Jun-13 31-Jul-13 31-Aug-13 30-Sep-13 31-Oct-13 30-Nov-13

Team Leader 25-Mar-13 0.25 1.25 2.25 3.25 4.25 5.25 6.25 7.25 8.25Senior Highway 1-Feb-13 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00Senior ProcSenior Road Sft 1-May-13 1.00 2.00 3.00 4.00 5.00 6.00 7.00Ass. TL 19-Nov-12 0.33 1.33 2.33 3.33 4.33 5.33 6.33 7.33 8.33 9.33 10.33 11.33 12.33Highway Eng 19-Nov-12 0.33 1.33 2.33 3.33 4.33 5.33 6.33 7.33 8.33 9.33 10.33 11.33 12.33Qualty Ass. Eng 1-Jul-13 1.00 2.00 2.82 3.82 4.82Financial 19-Nov-12 0.33 1.33 2.33 3.33 4.33 5.33 6.33 7.33 8.33 9.33 10.33 11.33 12.33Enviro 17-Dec-12 0.45 1.45 2.45 3.45 4.45 5.45 6.45 7.45 8.45 9.27 10.27 11.27Socio 19-Nov-12 0.33 1.33 2.33 3.33 4.33 5.33 6.33 7.33 8.33 9.33 10.33 11.33 12.33Proc. Speclt-1Proc. Speclt-2 19-Nov-12 0.33 1.33 2.33 3.33 4.35 5.35 6.35 7.35 8.35 9.35 10.35 11.35 12.35MIS 1-May-13 1.00 2.00 3.00 4.00 5.00 6.00 7.00Comm.Devlp. 3-Jan-13 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00

Total Prof 1.65 7.10 14.10 22.10 30.37 39.37 50.36 61.36 73.36 85.36 97.00 109.00 121.00

Ass. HighwayAss. Financial 19-Nov-12 0.33 1.33 2.33 3.33 4.33 5.33 6.33 7.33 8.33 9.33 10.33 11.33 12.33Ass. Env/Socio 19-Nov-12 0.33 1.33 2.33 3.33 4.33 5.33 6.33 7.33 8.33 9.33 10.33 11.33 12.33Ass. MIS 3-Jan-13 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00Ass. Comm. Dev 1-Feb-13 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00Ass. Proc-1 3-Jan-13 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00Ass. Proc-2 3-Jan-13 1.00 2.00 3.00 4.00 5.00 6.00 7.00 8.00 9.00 10.00 11.00

Total Sub Prof 0.66 2.66 7.66 13.66 19.66 25.66 31.66 37.66 43.66 49.66 55.66 61.66 67.66

Grand Total 2.31 9.76 21.76 35.76 50.03 65.03 82.02 99.02 117.02 135.02 152.66 170.66 188.66

Mobilized Total Manmonth Up To

Page 50: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

28-Feb-02

ContractPackage Original Add Actual To Original To Add

(days) (days) (days) (%) (%) Constr. % Escalation %

T O T A L #DIV/0! - #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!

109,670.00

(%)Total (%)Contractor's Time Elapsed This Month

(Eq.Rp.Million) (%)(%)Original

31 January 2013

To dateAddendum

(Eq.Rp.Million) (Eq.Rp.Million) (Eq.Rp.Million)

To date

Appendix - A1

IBRD LOAN No. 8043-ID

ScheduledTIME Contract Sum (Incl. Tax)(in Rp Million) Last Month

SUMMARY OF OVERALL PHYSICAL PROGRESS OF CIVIL WORK AWP-1WESTERN INDONESIA NATIONAL ROADS IMPROVEMENT PROJECT (WINRIP)

Const.PeriodAccumulate Progress of Civil Works

Page 51: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

31 January 2013

NO LINK NAME PACKAGECODE

EFFECTIVELENGTH

(KM)CONTRACTOR ORIGINAL CONTRACT

PRICE (incl. TAX)

CONTRACT PRICE AFTERADDENDUM (Incl. TAX, Excl.

Prc.Escalation)

CONTRACTSIGNED DATE START DATE

ORIGINALCONTRACTDURATION

(DAYS)

CONTRACT DURATIONAFTER ADDENDUM

(DAYS)

PLANNEDPROGRESS

(%)

ACTUALPROGRESS

(%)

CERTIFICATE OFCOMPLETION

ISSUEDCOMMENTS

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

Total for AWP-1 - - #DIV/0! #DIV/0!

Appendix - A2CIVIL WORKS PROGRESS STATUS OF AWP-1

WESTERN INDONESIA NATIONAL ROADS IMPROVEMENT PROJECT (WINRIP)IBRD LOAN No. 8043-ID

Page 52: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project

Appendix BFinancial Progress

Page 53: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Appendix B : Financial Progress

The table below shows total expenditure to date measured in the terms of WorldBank Commitment, not including the special account advance.

DatePercentage

Completion oftime

WBExpenditureCommitment

Percentage ofAvailable

ExpenditureSource

31/03/2012 1.45% - - -30/04/2012 2.90% - - -31/05/2012 4.35% - - -30/06/2012 5.80% - - -31/07/2012 7.25% - - -30/08/2012 8.70% - - -30/09/2012 10.15% - - -31/10/2012 11.60% - - -30/11/2012 13.05% - - -31/12/2012 14.50% 800,000 0.32% Actual31/01/2013 15.95% 800,000 0.32% Actual28/02/2013 17.40%31/03/2013 18.85%30/04/2013 20.30%31/05/2013 21.75%30/06/2013 23.20%31/07/2013 24.65%31/08/2013 26.10%30/09/2013 27.55%31/10/2013 29.00%30/11/2013 30.45%31/12/2013 31.90%31/01/2014 33.35%28/02/2014 34.80%31/03/2014 36.25%30/04/2014 37.70%31/05/2013 39.15%30/06/2014 40.60%31/07/2014 42.05%31/08/2014 43.50%30/09/2014 44.95%31/10/2012 46.40%30/11/2014 47.85%

Page 54: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

DatePercentage

Completion oftime

WBExpenditureCommitment

Percentage ofAvailable

ExpenditureSource

31/12/2014 49.30%31/01/2015 50.75%28/02/2015 52.20%31/03/2015 53.65%30/04/2015 55.10%31/05/2015 56.55%30/06/2015 58.00%31/07/2015 59.45%31/08/2015 60.90%30/09/2015 62.35%31/10/2015 63.80%30/11/2015 65.25%31/12/2015 66.70%31/01/2016 68.15%28/02/2016 69.60%31/03/2016 71.05%30/04/2016 72.50%31/05/2016 73.95%30/06/2016 75.40%31/07/2016 76.85%31/08/2016 78.30%30/09/2016 79.75%31/10/2016 81.20%30/11/2016 82.65%31/12/2016 84.10%31/01/2017 85.55%28/02/2017 87.00%31/03/2017 88.45%30/04/2017 89.90%31/05/2017 91.35%30/06/2017 92.80%31/07/2017 94.25%31/08/2017 95.70%30/09/2017 97.15%31/10/2017 98.60%30/11/2017 99.05%31/12/2017 100.00%

Page 55: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National
Page 56: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project

Appendix CEnvironmental & Social Progress

Page 57: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Length Width

(Km) (m) Result CommentsBudget

Alocated,YearStatus BLH Approval Result Comments

Budget Alocated,YearStatus THE WB Approval

1 Krui - Bha Lampung 25 7 ICB/PriorSPPL Air pollution, trafficcongestion, steepsopes,slopes,sopt soil andrivers and beach, abrasion

APBN(P2JN 2010)

100% YES, 2010 LARAP Total PAP 2.805 in 21 Pekon. Land affected 28.763,12M2 ; Aset affected : building 882,13 M2 ; Fence 2.445,41M ; Plant 653 rod ; paddy field 25 plots ; Social & PablicFacilities

Rp. 5.172.349.955APBN, Satker PJN IILampung, 2011 - 2012

LARAP monitoring report under preparation A. NOL LARAP 04 Jan2013 ; B. NOL

ENV : CTC in preparing detil environmental mitigationon construction stage (discussion process with SubditTLKJ). SOS : (1) CTC will be conducted LARAPmonitoring report.

2 Padang Sawah - Sp Empat Sumatera Barat 40.9 7 Total PAP 15. Land affected 2,110 M2 ; Aset affected:building 6 unit = 410 M2 ; Plant 72 rod.

2a Including Air Gadang Bridge Sumatera Barat 100 m 7 Total PAP 430 . No Land affected . Aset affected: building149 unit = 2.110 M2 ; Fence 2 unit = 341.8 M ; KiosksBBM: 25 unit; Plant: 873 rod ; Mosque: 2 unit

3 Manggopoh - Padang Sawah Sumatera Barat 32 7 ICB/PriorSPPL Air pollution, trafficcongestion, market onstreet, sopt soil and rivers

APBN(P2JN 2010)

100% YES, 2010 LARAP Total PAP 1.338 . No Land affected . Aset affected :building 115 unit = 668,33 M2 ; Culvert 661,05 m ;concrete & foundations 1.421,60 M3 ; Soil embankment5.564,21 M3; Plant 5.324 rod ; paddy field andlemongrass & turmeric = 17.695 clumps ; Mesjid &Market

Rp. 1.147.700.000APBD Prov Sumbar,Dinas PU, 2012/2013

A. NOL LARAP 04 Jan2013 ; B. NOLImplemetation LARAP 18April 2013, Rev 26 June2013.

4 Ipuh- Bantal Bengkulu 42.4 7 ICB/PriorSPPL Geometric, trafficcongestion, steepsopes,slopes,sopt soil andrivers and beach, abrasion

APBN(P2JN 2010)

100% YES, 2011 LARAP Total PAP 178. Land affected 2.730 M2 ; Aset affected :building 141 unit = 1.014 M2 ; Fence 52 unit = 531 M ;cemetery 2 unit ; Plant 32 rod.

Rp.286.743.000. APBN,Satker PJN I, Bengkulu,2013

A. NOL LARAP 10 Dec2012 ; B.-

5 Sp. Rampa - Poriaha Sumatera Utara 11.1 6 NCB/PostUKL&UPL slope stability, waterquality, Run off, bridgesacces, continued trafficaccess & quarry problem

APBN(BBPJN I 2011)

100% YES, 2011 Simple LARAP 1 PAP with aset affected : 1 kios BBM. Agree to relocatethe kios. relocate to the beside her house. relocatingcosts be the responsibility of the project

Rp.53.000.000. APBN,Satker PJN II, Sumut,2014

LARAP study- under bidding under preparation - ENV : r opose to site visit for finding environmentalissues on field. SOS : CTC will be reviewed LARAPreport

6 Ps Pedati - Kerkap Bengkulu 25 7 NCB/PostUKL&UPL Comersil areas, trafficcongestion, market on thestreet, air pollution &noise,

APBN(TLKJ 2011)

100% YES, 2011 LARAP

-

APBN Satker PJN I,Bengkulu, 2014

LARAP study - under bidding preparation A. -B.-

ENV : Environmental issues will integrated to design,Prepare environmental mitigation on constructionstage for contractor (RKPPL).Propose to site visit forfinding environmental issues on field. SOCIAL: CTC willbe conducted LARAP monitoring report

7 Indrapura - Tapan (1 Doc Amdal) Sumatera Barat 19.5 7 ICB/PriorAMDAL Sensitive forest areas,social issues, slopestability, water quality,waste management, airpollution, squater on ROWetc

APBN(TLKJ 2012)

50% Not Yet Simple LARAP &

-

APBD Prov Sumbar,Dinas PU,

LARAP study - under bidding preparation A. -B.-

Environmental issues will integrated to design, Prepareenvironmental mitigation on construction stage forcontractor (RKPPL).Propose to site visit for findingenvironmental issues on field.

8 Bts. Kota Pariaman - Manggopoh Sumatera Barat 46.8 7 ICB/PriorAMDAL Comersil areas, market,public facilities, Airpollution, trafficcongestion, market onstreet, sopt soil and rivers

APBN(BBPJN II 2011)

55% Not yet LARAP

-

APBD Prov Sumbar,Dinas PU,

Larap study - under bidding preparation A. -B.-

Environmental issues will integrated to design, Prepareenvironmental mitigation on construction stage forcontractor (RKPPL).

9 Rantau Tijang - Kota Agung (Replace) Lampung 42 7 ICB/PriorUKL&UPL Sensitive areas, resident,air pollution, trafficcongestion, steepsopes,slopes,sopt soil andrivers and beach, abrasion

APBN(TLKJ 2011)

100% YES, 2012 LARAP

- - -

A. -B.-

Environmental issues will integrated to design, Prepareenvironmental mitigation on construction stage forcontractor (RKPPL). Propose to site visit for findingenvironmental issues on field.

10 Sp Empat - Sp Air Balam Sumatera Barat 61.7 7 ICB/PriorAMDAL Sensitive forest areas,social issues, slopestability, water quality,waste managemnt, bridgetraffic access & quarryproblem

APBN(BBPJN II 2011)

60% Not yet LARAP

-

APBD Prov Sumbar,Dinas PU,

Larap study - under bidding preparation A. -B.-

Environmental issues will integrated to design, Prepareenvironmental mitigation on construction stage forcontractor (RKPPL).

11 Bantal - Mukomuko (1 Paketdoc AMDAL)

Bengkulu 50.1 6 ICB/PriorAMDAL Sensitive areas, socialissues, market on thestreet, geometric, wastemanagemnt, continuedtraffic access, etc

APBN(TLKJ 2011)

55% Not Yet LARAP

-

APBN Satker PJN I,Bengkulu, 2014

Larap study - under bidding preparation A. -B.-

ENV : Propose to site visit for finding environmentalissues on field. SOCIAL:

12 Kambang - Indrapura (1 Doc Amdal) Sumatera Barat 55.2 6 ICB/PriorAMDAL Resident, productive land,Catcment areas,rivers,slope stability, squater onthe street, land acquisition.

APBN(TLKJ 2011)

50% Not Yet LARAP

-

APBD Prov Sumbar,Dinas PU,

Larap study - under bidding preparation A. -B.-

Input RKL&RPL integration to design doc.

ENV : Propose to site visit for finding environmentalissues on field. SOCIAL: (1) CTC will be conductedLARAP monitoring report

Appendix C : ENVIRONMENTAL STATUS & PROGRESS FOR WINRIP, IBRD LOAN NO.8043-IDas per 31 January, 2013

one link,sensitiveareas/resident,public,facilities, squater,market,sopt soil and rivers

ENV : Propose to site visit for finding environmentalissues on field. SOCIAL: (1) CTC will be conductedLARAP monitoring report

AWP - 2

SPPL&UKL/UPL

Bridge

LARAP Rp.2.340.600.000 APBDProv Sumbar, Dinas PU,2012

APBN(P2JN 2010)

100%

Remedial Action

AWP - 1

No Loan Package Name Provinces

Proc

Approval Status by Environmental Agency (BLH)Environmental Screening Social Screening Approval Status by The World Bank

YES, 2010ICB/Prior LARAP monitoring report under preparation A. NOL LARAP 13 Jan2013 ; B. NOLImplemetation LARAP 19July 2013

LARAP monitoring report under preparation

Page 58: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Length Width

(Km) (m) Result CommentsBudget

Alocated,YearStatus BLH Approval Result Comments

Budget Alocated,YearStatus THE WB Approval

Remedial ActionNo Loan Package Name Provinces

Proc

Approval Status by Environmental Agency (BLH)Environmental Screening Social Screening Approval Status by The World Bank

13 Sp Rukis - Tj Kemuning Bengkulu 56.3 7 ICB/PriorUKL/UPL one link,sensitive/steepsopes,slopes,sopt soiland rivers, squater onthe street, resident,productive land.

APBN(P2JN 2011)

100% YES, 2011 LARAP

-

APBN, Satker PJN IBengkulu, 2014

Larap study - under bidding preparation A. -B.-

ENV : Environmental issues will integrated to design,Prepare environmental mitigation on constructionstage for contractor (RKPPL). Propose to site visit forfinding environmental issues on field. SOCIAL:

14 Painan -Kambang (1 doc Amdal) Sumatera Barat 31.5 7 ICB/PriorAMDAL Sensitive forest areas,social issues, slopestability, water quality,waste managemnt,continued traffic access &quarry problem

APBN(TLKJ 2011)

50% Not Yet Simple LARAP

-

APBD Prov Sumbar,Dinas PU,

Larap study - under bidding preparation A. -B.-

Environmental issues will integrated to design, Prepareenvironmental mitigation on construction stage forcontractor (RKPPL).Propose to site visit for findingenvironmental issues on field.

15 Sibolga - Bts Tap Sel Sumatera Utara 36 7 ICB/PriorUKL/UPL resident, comersil areas,geometric etc.

APBN(BBPJN I 2011)

100% YES, 2011 LARAP

-

APBN, Satker PJN II,Sumut, 2014

Larap study - under bidding preparation A. -B.-

Environmental issues will integrated to design, Prepareenvironmental mitigation on construction stage forcontractor (RKPPL).Propose to site visit for findingenvironmental issues on field.

Seblat - Ipuh including (1 Amdal) 34.5 6 Air Lalang & Air Guntung Bridge 64 m 6

Sp.Gunung Kemala - Pg. Tampak 36.8 6

Way Tauu Bridge 30 m 6

18 Mukomuko - Bts. Sumbar (Replace) Bengkulu 25.8 6 NCB/PostUKL&UPL one link,sensitive/steepsopes,slopes,sopt soil andrivers

APBN(TLKJ 2011)

100% YES, 2011 LARAP- - -

Site visit to finding environmental issues on field,propose schedule the first of July 2013

19 Lais- Bintunan Bengkulu 11.6 7 NCB/PostUKL&UPL one link,sensitive/airpollution, trafficcongestion, squater on thestreet, etc

APBN(TLKJ 2011)

100% YES,2011 LARAP

-

APBN, Satker PJN IILampung, 2014

Larap study under bidding preparation A. -B.-

ENV: Environmental issues will integrated to design,Prepare environmental mitigation on constructionstage for contractor (RKPPL).Propose to site visit forfinding environmental issues on field. SOCIAL:

20 Lubuk Alung - Sicincin Sumatera Barat 14.6 7 NCB/PostUKL&UPL sensitive areas/resident,land acquisition, steepsopes,slopes,sopt soil andrivers

APBN(TLKJ 2011)

100% YES, 2011 Simple LARAP

-

APBD Prov Sumbar,Dinas PU,

Larap study - under bidding preparation A. -B.-

Environmental issues will integrated to design, Prepareenvironmental mitigation on construction stage forcontractor (RKPPL).

21 Lubuk Alung -Kurataji Sumatera Barat 16.8 7 NCB/PostUKL&UPL one link,sensitive/steepsopes,slopes,sopt soil andrivers

APBN(TLKJ 2011)

100% YES, 2011 Simple LARAP

-

APBD Prov Sumbar,Dinas PU,

Larap study - under bidding preparation A. -B.-

Environmental issues will integrated to design, Prepareenvironmental mitigation on construction stage forcontractor (RKPPL).

ENV : Environmental issues will integrated to design,Prepare environmental mitigation on constructionstage for contractor (RKPPL).Propose to site visit forfinding environmental issues on field. SOCIAL:

Not Yet

AWP - 3

AMDAL sensitive areas/steepsopes,slopes,sopt soil andrivers and beach, abrasion

Simple LARAP

Environmental issues will integrated to design, Prepareenvironmental mitigation on construction stage forcontractor (RKPPL).Propose to site visit for findingenvironmental issues on field.

sensitive areas/resident,land acquisition, steepsopes,slopes,sopt soil andrivers and beach, abrasion

APBN(TLKJ 2011)

LARAP Total PAP 1.885 . Land affected 1.926 plot = 194.278 M2.Aset affected : building 440 unit = 4.557 M2 ; ; Plant4.267 rod ;paddy field 48.602 clumps.

RP.57.414.485 .000APBN, Satker PJN IILampung, 2014

(1). Formation of the Appraisal team on process.(2). Preparation of Measurements and Inventoryfor Affected Assets

A. NOL LARAP 16September 2013B.-

17 Lampung ICB/Prior YES, 2012

APBN(TLKJ 2011)

100%

16 Bengkulu ICB/Prior

AMDAL

55%

-

APBN Satker PJN I,Bengkulu, 2014

Larap study - under bidding preparation A. -B.-

Page 59: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project

Appendix DProcurement Plan & Progress

Page 60: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

#REF! Procurement Plan of Implementation Support and Road Sector Institutional Development#REF! Western Indonesia National Roads Improvement Project#REF! Name of Executing Agency: Directorate General of Highways , Ministry of Public Works.

Ref. No. Contract DescriptionProject Cost (US$) 0 Procurement MethodReview by Bank (Prior/Post)Schedule WB provide agreement to REOIEOI advertised in newspaperSubmission RFP to WBWB NOL to RFPEvaluation and Short List0 Date of Receipt of ProposalsTechnical Evaluation Report00 0 Allocated Contract 0 0 Actual 0 0 0 0 SubmissionWB NOL 0 SubmissionWB NOL0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 02 Implementation Support0 0 0 0 0 0 0 0 0 0 0 0 0 0

a Core Team Consultant (Project Management, Technical Assistant, Enviromental & Social Aspect and Road safety Audit)5000000 0 QCBS Prior Schedule 40496 40517 40566 40586 40614 40635 41022 41064 411120 0 0 0 0 0 Actual 40508 40701 40938 40975 40886 40974 41029 41074 41089

b Design and Supervision Consultant (Design AWP-2 & 3 and Construction Supervision of Civil Works Project)10000000 0 QCBS Prior Schedule 40888 40916 40966 40994 41036 41057 41190 41204 412180 0 0 0 0 0 Actual 40508 40701 41001 41131 40928 41052 41205 41263 413263 Road Sector Institutional Development (DGH)0 0 0 0 0 0 0 0 0 0 0 0 0 00 Capacity Building for DGH Environment/1000000 0 QCBS Prior Schedule 41426 41440 41468 41482 41482 41498 41533 41554 415680 Risk Mitigation and Road Safety Unit0 0 0 0 0 0 0 0 0 0 0 0 0 00 (developing roadmap, norm, standard, procedure, criteria for disaster risk management in road sector, risk analysis and standad implementation)0 0 0 0 Actual 0 0 0 0 0 0 0 0 00 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

T O T A L 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0Note: TOR of packages for Part 3 of Loan Agreement (Road Sector Institutional Development DGH) will send for approval to WB on May 2013.0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 00 0 0 0 0 0 0 0 0 0 0 0 0 0 0 00 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Page 61: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Edit 28 March 2013 0Opening of Financial ProposalFinal Evaluation ReportNegotiation & Draft Contract0 Contract SignService Start datePeriod (Month)Completion DateRemarks

0 SubmissionSubmissionWB NOL 0 0 0 0 00 0 0 0 0 0 0 0 00 0 0 0 0 0 0 0 0

41126 41133 41167 41181 41204 41225 0 0 041148 41155 41173 41194 41218 41229 40 42401 041225 41232 41239 41365 41382 41396 0 0 041338 41346 41358 41383 0 0 42 0 0

0 0 0 0 0 0 0 0 041582 41589 41603 41617 41631 41645 0 0 0

0 0 0 0 0 0 0 0 00 0 0 0 0 0 0 0 00 0 0 0 0 0 0 0 00 0 0 0 0 0 0 0 00 0 0 0 0 0 0 0 00 0 0 0 0 0 0 0 00 0 0 0 0 0 0 0 00 0 0 0 0 0 0 0 0

Page 62: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Procurement Plan of Implementation Support and Road Sector Institutional DevelopmentWestern Indonesia National Roads Improvement ProjectName of Executing Agency: Directorate General of Highways , Ministry of Public Works. Edit 28 March 2013

Ref.No. Contract Description Project Cost

(US$)Procurement

Method

Review byBank

(Prior/Post)Schedule

WB provideagreement

to REOI

EOIadvertised innewspaper

SubmissionRFP to WB

WB NOL toRFP

Date ofReceipt ofProposals

Opening ofFinancialProposal

FinalEvaluationReport

ContractSign

Service Startdate

Period(Month)

Completion Date Remarks

Allocated Contract Actual Submission WB NOL Submission WB NOL Submission Submission WB NOL

2 Implementation Support

Schedule 14-Nov-10 05-Dec-10 23-Jan-11 12-Feb-11 12-Mar-11 02-Apr-11 23-Apr-12 04-Jun-12 22-Jul-12 05-Aug-12 12-Aug-12 15-Sep-12 29-Sep-12 22-Oct-12 12-Nov-12

Actual 26-Nov-10 7-Jun-11 30-Jan-12 7-Mar-12 9-Dec-11 6-Mar-12 30-Apr-12 14-Jun-12 29-Jun-12 27-Aug-12 3-Sep-12 21-Sep-12 12-Oct-12 5-Nov-12 16-Nov-12 40 Feb-16

Schedule 11-Dec-11 08-Jan-12 27-Feb-12 26-Mar-12 07-May-12 28-May-12 08-Oct-12 22-Oct-12 05-Nov-12 12-Nov-12 19-Nov-12 26-Nov-12 01-Apr-13 18-Apr-13 02-May-13

Actual 26-Nov-10 7-Jun-11 4/2/2012 10-Aug-12 20-Jan-12 23-May-12 23-Oct-12 20-Dec-12 21-Feb-13 5-Mar-13 13-Mar-13 25-Mar-13 19-Apr-13 42

3 Road Sector Institutional Development(DGH)Capacity Building for DGH Environment/ Schedule 01-Jun-13 15-Jun-13 13-Jul-13 27-Jul-13 27-Jul-13 12-Aug-13 16-Sep-13 07-Oct-13 21-Oct-13 04-Nov-13 11-Nov-13 25-Nov-13 09-Dec-13 23-Dec-13 06-Jan-14

Risk Mitigation and Road Safety Unit

(developing roadmap, norm, standard, procedure,criteria for disaster risk management in roadsector, risk analysis and standad implementation)

Actual

Note: TOR of packages for Part 3 of Loan Agreement (Road Sector Institutional Development DGH) will send for approval to WB on May 2013.

Negotiation & DraftContract

T O T A L

aCore Team Consultant (Project Management,Technical Assistant, Enviromental & SocialAspect and Road safety Audit)

Design and Supervision Consultant (DesignAWP-2 & 3 and Construction Supervision of CivilWorks Project)

10,000,000

1,000,000

b

QCBS

QCBS

Evaluation and Short List

QCBS Prior

5,000,000 Prior

Prior

Technical EvaluationReport

Page 63: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Appendix E : Procurement Plan of Civil WorksWestern Indonesia National Roads Improvement Project (WINRIP)Name of Executing Agency: Directorate General of Highways , Ministry of Public Works. Update 28 March 20139000 Edit 250112

Qualification Schedule Submission Notification

Sub - Project Link No. Length Criteria Actual of of(Km) IDR (x10⁶) USD million IDR (x10⁶) (Pre/Post) Application Qualification

A W P - 11 Krui - Biha Lampung 053.0 25.00 ICB 148,668.00 16.52 Pre Schedule 12-Jan-11 09-Feb-11 09-May-11 07-Aug-11 15-Dec-11 09-Feb-12 13-Sep-12 28-Feb-13 01-Mar-13 07-Mar-13 18-Apr-13 05-May-13 19-May-13 18-Jun-13 720

Actual 25-Jan-11 21-Feb-11 02-Nov-11 28-Dec-11 30-Dec-11 28-Feb-12 25-Jan-13 28-Mar-13 17-May-13 27-May-13 08-Jul-132 Padang Sawah - Sp.Empat West Sumatera 047.2 40.90 ICB Schedule 12-Jan-11 09-Feb-11 09-May-11 07-Aug-11 15-Dec-11 09-Feb-12 13-Sep-12 28-Feb-13 01-Mar-13 07-Mar-13 18-Apr-13 05-May-13 19-May-13 18-Jun-13 720

Including Air Gadang Bridge 0.10 Actual 25-Jan-11 21-Feb-11 02-Nov-11 28-Dec-11 30-Dec-11 28-Feb-12 25-Jan-13 28-Mar-13 17-May-13 27-May-13 08-Jul-133 Manggopoh - Padang Sawah West Sumatera 047.1 32.00 ICB 152,434.90 16.94 Pre Schedule 12-Jan-11 09-Feb-11 09-May-11 07-Aug-11 15-Dec-11 09-Feb-12 13-Sep-12 28-Feb-13 01-Mar-13 07-Mar-13 18-Apr-13 05-May-13 19-May-13 18-Jun-13 720

Actual 25-Jan-11 21-Feb-11 02-Nov-11 28-Dec-11 30-Dec-11 28-Feb-12 25-Jan-13 28-Mar-13 17-May-13 27-May-13 08-Jul-134 Ipuh - Bantal Bengkulu 015.1 42.40 ICB 226,275.10 25.14 Pre Schedule 12-Jan-11 09-Feb-11 09-May-11 07-Aug-11 15-Dec-11 09-Feb-12 13-Sep-12 28-Feb-13 01-Mar-13 07-Mar-13 18-Apr-13 05-May-13 19-May-13 18-Jun-13 720

Actual 25-Jan-11 21-Feb-11 02-Nov-11 28-Dec-11 30-Dec-11 28-Feb-12 25-Jan-13 28-Mar-13 17-May-13 27-May-13 08-Jul-13Sub Total AWP - 1 734,768.30 81.64A W P - 2 and 3

90 2015 Simpang Rampa - Poriaha North Sumatera 015. 11.10 NCB 55,126.00 6.13 Post Schedule 01-May-13 15-May-13 22-May-13 05-Jun-13 12-Jun-13 17-Jul-13 16-Aug-13 30-Aug-13 20-Sep-13 540

Actual

11 Bantal - Mukomuko Bengkulu 015.2 50.10 ICB 157,820.00 17.54 Pre Schedule 11-Jul-13 01-Aug-13 08-Aug-13 22-Aug-13 29-Aug-13 13-Oct-13 12-Nov-13 26-Nov-13 27-Nov-13 02-Dec-13 16-Jan-14 02-Feb-14 16-Feb-14 18-Mar-14 720Actual

13 Sp Rukis - Tj Kemuning Bengkulu 006.1 56.30 ICB 225,481.00 25.05 Pre Schedule 11-Jul-13 01-Aug-13 08-Aug-13 22-Aug-13 29-Aug-13 13-Oct-13 12-Nov-13 26-Nov-13 27-Nov-13 02-Dec-13 16-Jan-14 02-Feb-14 16-Feb-14 18-Mar-14 630Actual

15 Sibolga - Batas Tapsel North Sumatera 016.1 36.00 ICB 129,228.00 14.36 Pre Schedule 11-Jul-13 01-Aug-13 08-Aug-13 22-Aug-13 29-Aug-13 13-Oct-13 12-Nov-13 26-Nov-13 27-Nov-13 02-Dec-13 16-Jan-14 02-Feb-14 16-Feb-14 18-Mar-14 630Actual

17 Sp.Gng Kemala - Pugung Tampak Lampung 061.1 36.80 ICB 104,238.00 11.58 Pre Schedule 11-Jul-13 01-Aug-13 08-Aug-13 22-Aug-13 29-Aug-13 13-Oct-13 12-Nov-13 26-Nov-13 27-Nov-13 02-Dec-13 16-Jan-14 02-Feb-14 16-Feb-14 18-Mar-14 630Including Way Taau Bridge(**) 0.03 Actual

6 Ps. Pedati - Kerkap Bengkulu 010.0 25.00 NCB 72,018.00 8.00 Post Schedule 20-Oct-13 10-Nov-13 17-Nov-13 01-Dec-13 08-Dec-13 12-Jan-14 11-Feb-14 25-Feb-14 18-Mar-14 540Actual

8 Bts.Kota Pariaman - Manggopoh West Sumatera 024.0 46.80 ICB 183,268.00 20.36 Pre Schedule 12-Mar-14 02-Apr-14 09-Apr-14 23-Apr-14 30-Apr-14 14-Jun-14 14-Jul-14 28-Jul-14 29-Jul-14 03-Aug-14 17-Sep-14 04-Oct-14 18-Oct-14 17-Nov-14 720Actual

10 Simpang Empat - Sp.Air Balam West Sumatera 034.1 61.70 ICB 241,617.00 26.85 Pre Schedule 12-Mar-14 02-Apr-14 09-Apr-14 23-Apr-14 30-Apr-14 14-Jun-14 14-Jul-14 28-Jul-14 29-Jul-14 03-Aug-14 17-Sep-14 04-Oct-14 18-Oct-14 17-Nov-14 720Actual

7 Indrapura - Tapan West Sumatera 019.0 19.50 ICB 96,921.00 10.77 Pre Schedule 14-May-14 04-Jun-14 11-Jun-14 25-Jun-14 02-Jul-14 16-Aug-14 15-Sep-14 29-Sep-14 30-Sep-14 05-Oct-14 19-Nov-14 06-Dec-14 20-Dec-14 19-Jan-15 630Actual

12 Kambang - Indrapura West Sumatera 017.2 55.20 ICB 171,948.00 19.11 Pre Schedule 14-May-14 04-Jun-14 11-Jun-14 25-Jun-14 02-Jul-14 16-Aug-14 15-Sep-14 29-Sep-14 30-Sep-14 05-Oct-14 19-Nov-14 06-Dec-14 20-Dec-14 19-Jan-15 720Actual

9 Rantau Tijang - Kota Agung Lampung 026.1 42.00 ICB 149,831.00 16.65 Schedule 14-May-14 04-Jun-14 11-Jun-14 25-Jun-14 28-Nov-14 12-Jan-15 11-Feb-15 25-Feb-15 26-Feb-15 03-Mar-15 17-Apr-15 04-May-15 18-May-15 17-Jun-15 630Actual

14 Painan - Kambang West Sumatera 017.1 31.50 ICB 118,993.00 13.22 Pre Schedule 14-May-14 04-Jun-14 11-Jun-14 25-Jun-14 28-Nov-14 12-Jan-15 11-Feb-15 25-Feb-15 26-Feb-15 03-Mar-15 17-Apr-15 04-May-15 18-May-15 17-Jun-15 630Actual

16 Seblat - Ipuh, Including Bengkulu 009.4 34.50 ICB 110,237.00 12.25 Pre Schedule 14-May-14 04-Jun-14 11-Jun-14 25-Jun-14 28-Nov-14 12-Jan-15 11-Feb-15 25-Feb-15 26-Feb-15 03-Mar-15 17-Apr-15 04-May-15 18-May-15 17-Jun-15 630Air Lalang & Air Guntung Bridge 0.052 Actual

18 Mukomuko - Batas Sumbar Bengkulu 015.3 25.80 NCB 69,233.00 7.69 Post Schedule 14-May-14 04-Jun-14 11-Jun-14 25-Jun-14 09-Jun-15 14-Jul-15 13-Aug-15 27-Aug-15 17-Sep-15 540Actual

19 Lais - Bintunan Bengkulu 009.1 11.60 NCB 37,558.00 4.17 Post Schedule 14-May-14 04-Jun-14 11-Jun-14 25-Jun-14 09-Jun-15 14-Jul-15 13-Aug-15 27-Aug-15 17-Sep-15 540Actual

20 Lubuk Alung - Sicincin West Sumatera 002.0 14.60 NCB 54,557.00 6.06 Post Schedule 14-May-14 04-Jun-14 11-Jun-14 25-Jun-14 09-Jun-15 14-Jul-15 13-Aug-15 27-Aug-15 17-Sep-15 540Actual

21 Lubuk Alung - Kuraitaji West Sumatera 027.0 16.80 NCB 65,788.00 7.31 Post Schedule 14-May-14 04-Jun-14 11-Jun-14 25-Jun-14 09-Jun-15 14-Jul-15 13-Aug-15 27-Aug-15 17-Sep-15 540Actual

Sub Total AWP - 3 2,043,862.00 227.10

Total AWP - 1 , 2 & 3 2,778,630.30 308.74

207,390.30 Pre

Pre

Invitation forPre-

qualification

Evalt.QualificationReport

RequestDate

Appr'd/NOL Date

SubmittedDate

Appr'd/NOL Date

23.04

ContractAmount

Design Bidding Document(including qualification)Estimated Cost Contractor

Name

Construction

Period(day)

Appr'd/NOL Date

Invitationfor Bids

Date

BidOpening

Date

Bid Evaluation Report

NOL Date

ContractSignature

DateSubmittedDate

Ref. No. Province Procurement Method Request

Date

EstimatedCost

Page 64: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Appendix D : Procurement Plan of Civil WorksWestern Indonesia National Roads Improvement Project (WINRIP)Name of Executing Agency: Directorate General of Highways , Ministry of Public Works. Update 31 January 20139000 Edit 250112

Qualification Schedule Submission Notification

Sub - Project Link No. Length Criteria Actual of of(Km) IDR (x10⁶) USD million IDR (x10⁶) (Pre/Post) Application Qualification

A W P - 11 Krui - Biha Lampung 053.0 25.00 ICB 148,668.00 16.52 Pre Schedule 12-Jan-11 09-Feb-11 09-May-11 07-Aug-11 15-Dec-11 09-Feb-12 13-Sep-12 28-Feb-13 01-Mar-13 07-Mar-13 18-Apr-13 05-May-13 19-May-13 18-Jun-13 720

Actual 25-Jan-11 21-Feb-11 02-Nov-11 28-Dec-11 30-Dec-11 28-Feb-12 25-Jan-132 Padang Sawah - Sp.Empat West Sumatera 047.2 40.90 ICB Schedule 12-Jan-11 09-Feb-11 09-May-11 07-Aug-11 15-Dec-11 09-Feb-12 13-Sep-12 28-Feb-13 01-Mar-13 07-Mar-13 18-Apr-13 05-May-13 19-May-13 18-Jun-13 720

Including Air Gadang Bridge 0.10 Actual 25-Jan-11 21-Feb-11 02-Nov-11 28-Dec-11 30-Dec-11 28-Feb-12 25-Jan-133 Manggopoh - Padang Sawah West Sumatera 047.1 32.00 ICB 152,434.90 16.94 Pre Schedule 12-Jan-11 09-Feb-11 09-May-11 07-Aug-11 15-Dec-11 09-Feb-12 13-Sep-12 28-Feb-13 01-Mar-13 07-Mar-13 18-Apr-13 05-May-13 19-May-13 18-Jun-13 720

Actual 25-Jan-11 21-Feb-11 02-Nov-11 28-Dec-11 30-Dec-11 28-Feb-12 25-Jan-134 Ipuh - Bantal Bengkulu 015.1 42.40 ICB 226,275.10 25.14 Pre Schedule 12-Jan-11 09-Feb-11 09-May-11 07-Aug-11 15-Dec-11 09-Feb-12 13-Sep-12 28-Feb-13 01-Mar-13 07-Mar-13 18-Apr-13 05-May-13 19-May-13 18-Jun-13 720

Actual 25-Jan-11 21-Feb-11 02-Nov-11 28-Dec-11 30-Dec-11 28-Feb-12 25-Jan-13Sub Total AWP - 1 734,768.30 81.64A W P - 2 and 3

90 2015 Simpang Rampa - Poriaha North Sumatera 015. 11.10 NCB 55,126.00 6.13 Post Schedule 01-May-13 15-May-13 22-May-13 05-Jun-13 12-Jun-13 17-Jul-13 16-Aug-13 30-Aug-13 20-Sep-13 540

Actual

11 Bantal - Mukomuko Bengkulu 015.2 50.10 ICB 157,820.00 17.54 Pre Schedule 11-Jul-13 01-Aug-13 08-Aug-13 22-Aug-13 29-Aug-13 13-Oct-13 12-Nov-13 26-Nov-13 27-Nov-13 02-Dec-13 16-Jan-14 02-Feb-14 16-Feb-14 18-Mar-14 720Actual

13 Sp Rukis - Tj Kemuning Bengkulu 006.1 56.30 ICB 225,481.00 25.05 Pre Schedule 11-Jul-13 01-Aug-13 08-Aug-13 22-Aug-13 29-Aug-13 13-Oct-13 12-Nov-13 26-Nov-13 27-Nov-13 02-Dec-13 16-Jan-14 02-Feb-14 16-Feb-14 18-Mar-14 630Actual

15 Sibolga - Batas Tapsel North Sumatera 016.1 36.00 ICB 129,228.00 14.36 Pre Schedule 11-Jul-13 01-Aug-13 08-Aug-13 22-Aug-13 29-Aug-13 13-Oct-13 12-Nov-13 26-Nov-13 27-Nov-13 02-Dec-13 16-Jan-14 02-Feb-14 16-Feb-14 18-Mar-14 630Actual

17 Sp.Gng Kemala - Pugung Tampak Lampung 061.1 36.80 ICB 104,238.00 11.58 Pre Schedule 11-Jul-13 01-Aug-13 08-Aug-13 22-Aug-13 29-Aug-13 13-Oct-13 12-Nov-13 26-Nov-13 27-Nov-13 02-Dec-13 16-Jan-14 02-Feb-14 16-Feb-14 18-Mar-14 630Including Way Taau Bridge(**) 0.03 Actual

6 Ps. Pedati - Kerkap Bengkulu 010.0 25.00 NCB 72,018.00 8.00 Post Schedule 20-Oct-13 10-Nov-13 17-Nov-13 01-Dec-13 08-Dec-13 12-Jan-14 11-Feb-14 25-Feb-14 18-Mar-14 540Actual

8 Bts.Kota Pariaman - Manggopoh West Sumatera 024.0 46.80 ICB 183,268.00 20.36 Pre Schedule 12-Mar-14 02-Apr-14 09-Apr-14 23-Apr-14 30-Apr-14 14-Jun-14 14-Jul-14 28-Jul-14 29-Jul-14 03-Aug-14 17-Sep-14 04-Oct-14 18-Oct-14 17-Nov-14 720Actual

10 Simpang Empat - Sp.Air Balam West Sumatera 034.1 61.70 ICB 241,617.00 26.85 Pre Schedule 12-Mar-14 02-Apr-14 09-Apr-14 23-Apr-14 30-Apr-14 14-Jun-14 14-Jul-14 28-Jul-14 29-Jul-14 03-Aug-14 17-Sep-14 04-Oct-14 18-Oct-14 17-Nov-14 720Actual

7 Indrapura - Tapan West Sumatera 019.0 19.50 ICB 96,921.00 10.77 Pre Schedule 14-May-14 04-Jun-14 11-Jun-14 25-Jun-14 02-Jul-14 16-Aug-14 15-Sep-14 29-Sep-14 30-Sep-14 05-Oct-14 19-Nov-14 06-Dec-14 20-Dec-14 19-Jan-15 630Actual

12 Kambang - Indrapura West Sumatera 017.2 55.20 ICB 171,948.00 19.11 Pre Schedule 14-May-14 04-Jun-14 11-Jun-14 25-Jun-14 02-Jul-14 16-Aug-14 15-Sep-14 29-Sep-14 30-Sep-14 05-Oct-14 19-Nov-14 06-Dec-14 20-Dec-14 19-Jan-15 720Actual

9 Rantau Tijang - Kota Agung Lampung 026.1 42.00 ICB 149,831.00 16.65 Schedule 14-May-14 04-Jun-14 11-Jun-14 25-Jun-14 28-Nov-14 12-Jan-15 11-Feb-15 25-Feb-15 26-Feb-15 03-Mar-15 17-Apr-15 04-May-15 18-May-15 17-Jun-15 630Actual

14 Painan - Kambang West Sumatera 017.1 31.50 ICB 118,993.00 13.22 Pre Schedule 14-May-14 04-Jun-14 11-Jun-14 25-Jun-14 28-Nov-14 12-Jan-15 11-Feb-15 25-Feb-15 26-Feb-15 03-Mar-15 17-Apr-15 04-May-15 18-May-15 17-Jun-15 630Actual

16 Seblat - Ipuh, Including Bengkulu 009.4 34.50 ICB 110,237.00 12.25 Pre Schedule 14-May-14 04-Jun-14 11-Jun-14 25-Jun-14 28-Nov-14 12-Jan-15 11-Feb-15 25-Feb-15 26-Feb-15 03-Mar-15 17-Apr-15 04-May-15 18-May-15 17-Jun-15 630Air Lalang & Air Guntung Bridge 0.052 Actual

18 Mukomuko - Batas Sumbar Bengkulu 015.3 25.80 NCB 69,233.00 7.69 Post Schedule 14-May-14 04-Jun-14 11-Jun-14 25-Jun-14 09-Jun-15 14-Jul-15 13-Aug-15 27-Aug-15 17-Sep-15 540Actual

19 Lais - Bintunan Bengkulu 009.1 11.60 NCB 37,558.00 4.17 Post Schedule 14-May-14 04-Jun-14 11-Jun-14 25-Jun-14 09-Jun-15 14-Jul-15 13-Aug-15 27-Aug-15 17-Sep-15 540Actual

20 Lubuk Alung - Sicincin West Sumatera 002.0 14.60 NCB 54,557.00 6.06 Post Schedule 14-May-14 04-Jun-14 11-Jun-14 25-Jun-14 09-Jun-15 14-Jul-15 13-Aug-15 27-Aug-15 17-Sep-15 540Actual

21 Lubuk Alung - Kuraitaji West Sumatera 027.0 16.80 NCB 65,788.00 7.31 Post Schedule 14-May-14 04-Jun-14 11-Jun-14 25-Jun-14 09-Jun-15 14-Jul-15 13-Aug-15 27-Aug-15 17-Sep-15 540Actual

Sub Total AWP - 3 2,043,862.00 227.10

Total AWP - 1 , 2 & 3 2,778,630.30 308.74

Ref. No. Province Procurement Method

Estimated Cost EstimatedCost

ContractAmount

Design Bidding Document(including qualification) Invitation for

Pre-qualification

Construction

Period(day)

SubmittedDate

Appr'd/NOL Date

SubmittedDate NOL Date Request

DateAppr'd

/NOL DateRequest

DateAppr'd

/NOL Date

Evalt.QualificationReport Invitation

for BidsDate

BidOpening

Date

Bid Evaluation Report ContractSignature

Date

ContractorName

207,390.30 23.04 Pre

Pre

Page 65: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project

Appendix ETraining/Dissemination Progress

Page 66: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Appendix E : Training/Dissemination Progress

No Activities has been done

Status/condition

Date of Finish/completed

1. Orientation and studied of WINRIP documents and DevelopedWorks Plan

January 31, 2013

Page 67: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project

Appendix FPerformance Indicator

Page 68: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Project Development Objective: The development objective is to increase the effective use of selected sections of national roads along the Western Sumatera Corridor by reducing

road user costs.

PDO Level Results Indicators*

Co

re Unit of Measure Baseline

(2010)

Cumulative Target Values** Frequency Data Source/

Methodology

Responsibility

for Data

Collection YR 1 YR 2 YR3 YR 4 YR5

Indicator One:

Average passenger travel times reduced by

at least 20% on project roads.

(i) For light vehicles with base year Speed

of 51 km/h

(ii) 46 km/h for large buses

(iii) 40 km/h heavy trucks

Km/h

0 % --- --- 5 % --- 20 % Mid-term

and ICR

Travel speed

survey

PMU/CTC

Indicator Two:

Average vehicle operating cost for a

typical car, bus and heavy truck reduced

by at least 5%, 8%, and 10% respectively,

on project roads

(i) For light vehicles with base year

Vehicle Operating Cost of $US0.19 per

veh-km

(ii) $US0.35 veh-km for large buses

(iii) $US0.65 veh-km for heavy trucks

$US/km

0 %

0%

0%

--- --- 3 %

5%

7%

--- 5 %

8%

10%

Mid-term

and ICR

Road condition

and travel speed

surveys. And

use of HDM-IV

VOC estimation

Model

PMU/CTC

Indicator Three:

Increase of AADT on project road sections

as per forecast

AADT PAD-Annex 7 AADT

Increases

as per

forecast

ICR

Traffic surveys

PMU/CTC

INTERMEDIATE RESULTS

Intermediate Result (Component One): Betterment and Capacity Expansion of National Roads

Intermediate Result indicator One:

Number of kilometers of improved

national roads in the project region as

planned.

km

0 km 50

km

100

km

300

km

500

km

715 km Semi-

Annually

Reports from

PMU

PMU/CTC

Intermediate Result indicator Two:

Number of meters of improved bridges

meter

0 m 0 m 100

m

130

m

160

m

194 m Semi-

Annually

Reports from

PMU

PMU/CTC

Appendix F : WINRIP Performance Indicators

Page 69: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

PDO Level Results Indicators*

Co

re Unit of Measure Baseline

(2010)

Cumulative Target Values** Frequency Data Source/

Methodology

Responsibility

for Data

Collection YR 1 YR 2 YR3 YR 4 YR5

Intermediate Result (Component Two): Implementation Support

Intermediate Result indicator One:

Satisfactory completion of technical audits

for all road projects of component 1

0 %

20 %

40 %

60 %

80 %

100 %

Semi-

Annually

Reports from

PMU

PMU/CTC

Intermediate Result indicator Two:

Satisfactory completion of road safety

audits for all road projects of component 1

0 %

20 %

40 %

60 %

80 %

100 %

Semi-

Annually

Reports from

PMU

PMU/CTC

Intermediate Result (Component Three): Road Sector Institutional Development

Intermediate Result indicator One:

% of Environment unit staff trained and

capacitated to mitigate disaster risk related

to road network

0%

20 %

40 %

50%

75%

100%

Semi-

Annually

Reports from

PMU and Bank

Supervision

PMU/CTC

Page 70: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Monthly Progress Report January 2013

Western Indonesia National Roads Improvement Project

Appendix GCorrespondence

Page 71: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Appendix G : Correspondence during January 2013

Incoming Letter

Date From To Activity18 January 2013 Direktur Bina

Pelaksanaan Wilayah IDirektur Bina Program /Ketua PMU WINRIP

Penyampaian RevisiAplication EvaluationReport (AER) Paket AWP-1, WINRIP IBRD Loan No.8043-ID

23 January 2013 Direktur Bina Program Direktur Bina PelaksanaanWilayah I

PenyampaianPersetujuan Bank DuniaTerhadap DokumenLARAP Paket Krui – Bihadi Provinsi ; WINRIP LoanIBRD 8043-ID

25 January 2013 Director of Planning :Harris H. Batubara

Task Team Leader WINRIPIndonesia SustainableDevelopment DepartmentEast Asia and Pacific : Mr.Mitsuyoshi Asada

Submission of RevisedApplication EvaluationReport (AER) for AWP-1Packages ; WINRIP LoanIBRD 8043-ID

Page 72: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National

Out Going Letter

Date To From Activity21 January 2013 Head of Sub Directorate of

System and ControllingRegion I as Officer InCharge PMU WINRIP :Ir. Agusta ErsadaSinulingga, MT

CTC WINRIP Submission ofEnvironmental and SocialSafeguard Studies Status ;WINRIP Loan IBRD No. 8043-ID

Page 73: Monthly Progress Report No. 1 - dms.winrip-ibrd.comdms.winrip-ibrd.com/data/C2_IS/C2.02_CTC/C2.02.03_RPT/WINRIP_DOC_MPR...Monthly Progress Report January 2013 Western Indonesia National