MONTHLY PROGRESS REPORT - primeresidencies.lk 5.pdf · 1 monthly progress report- march 2017 prime...

5
PRIME LANDS RESIDENCIES (PVT) LTD #75, D. S. SENANAYAKE MAWATHA, COLOMBO 08 MONTHLY PROGRESS REPORT PRIME RESIDENCIES AQUA No 18/1, Temple Road. Nawala March / 2017

Transcript of MONTHLY PROGRESS REPORT - primeresidencies.lk 5.pdf · 1 monthly progress report- march 2017 prime...

Page 1: MONTHLY PROGRESS REPORT - primeresidencies.lk 5.pdf · 1 monthly progress report- march 2017 prime lands residencies (pvt) ltd #75, d. s. senanayake mawatha, colombo 08 project details

PRIME LANDS RESIDENCIES (PVT) LTD

#75, D. S. SENANAYAKE MAWATHA, COLOMBO 08

MONTHLY PROGRESS REPORT

PRIME RESIDENCIES AQUA No 18/1, Temple Road. Nawala

March / 2017

Page 2: MONTHLY PROGRESS REPORT - primeresidencies.lk 5.pdf · 1 monthly progress report- march 2017 prime lands residencies (pvt) ltd #75, d. s. senanayake mawatha, colombo 08 project details

1

MONTHLY PROGRESS REPORT- MARCH 2017

PRIME LANDS RESIDENCIES (PVT) LTD #75, D. S. SENANAYAKE MAWATHA, COLOMBO 08

PROJECT DETAILS

Project Architect : Arch.Thusara Waidyasekara

Contractor : SEIRRA Construction (Pvt) Ltd

Structural Engineer : Eng.K.V.G.G. Jayantha

Project Commenced Date – 2014/12/02

MEP Engineer : Eng. N.Sooriyaarachchi

Duration – 24 Months

CURRENT STATUS OF THE PROJECT

Floor Work H1 H2 H3 H4 H5 H6 H7

3rd

Door Fixing 100% 100% 100% 100% 100% 100% 100%

Painting 90% 95% 90% 90% 90% 90% 90%

Tilling 100% 100% 100% 100% 100% 100% 100%

Bathroom Fittings 50% 100% 50% 50% 50% 50% 50%

Electrical Fittings 80% 100% 80% 80% 80% 80% 80%

4th

Door fixing 80% 80% 80% 80% 80% 80% 80%

Painting 75% 75% 75% 75% 75% 75% 75%

Tilling 100% 100% 100% 100% 100% 100% 100%

Electrical Wiring 100% 100% 100% 100% 100% 100% 100%

Plumbing 100% 100% 100% 100% 100% 100% 100%

5th

Door frame 100% 100% 100% 100% 100% 100% 100%

Painting 65% 65% 65% 65% 65% 65% 65%

Tilling 100% 100% 100% 100% 100% 100% 100%

Electrical Wiring 100% 100% 100% 100% 100% 100% 100%

Plumbing 100% 100% 100% 100% 100% 100% 100%

6th

Door frame 100% 100% 100% 100% 100% 100% 100%

Painting 65% 65% 65% 65% 65% 65% 65%

Tilling 100% 100% 100% 100% 100% 100% 100%

Page 3: MONTHLY PROGRESS REPORT - primeresidencies.lk 5.pdf · 1 monthly progress report- march 2017 prime lands residencies (pvt) ltd #75, d. s. senanayake mawatha, colombo 08 project details

2

MONTHLY PROGRESS REPORT- MARCH 2017

PRIME LANDS RESIDENCIES (PVT) LTD #75, D. S. SENANAYAKE MAWATHA, COLOMBO 08

6th

Electrical Wiring 100% 100% 100% 100% 100% 100% 100%

Plumbing 100% 100% 100% 100% 100% 100% 100%

Door frame 100% 100% 100% 100% 100% 100% 100%

7th

Painting 65% 65% 65% 65% 65% 65% 65%

Tilling 100% 100% 100% 100% 100% 100% 100%

Electrical Wiring 100% 100% 100% 100% 100% 100% 100%

Plumbing 100% 100% 100% 100% 100% 100% 100%

8th

Door frame 100% 100% 100% 100% 100% 100% 100%

Painting 65% 65% 65% 65% 65% 65% 65%

Tilling 100% 100% 100% 100% 100% 100% 100%

Electrical Wiring 100% 100% 100% 100% 100% 100% 100%

Plumbing 100% 100% 100% 80% 20% 100% 20%

9th

Door frame 100% 100% 100% 100% 100% 100% 100%

Painting 65% 65% 65% 65% 65% 65% 65%

Tilling 80% 100% 80% 80% 80% 10%

Electrical Wiring 100% 100% 100% 100% 100% 100% 100%

Plumbing 100% 100% 100% 100% 100% 100% 100%

10th

Door frame 100% 100% 100% 100% 100% 100% 100%

Painting 65% 65% 65% 65% 65% 65% 65%

Electrical Wiring 100% 100% 100% 100% 100% 100% 100%

Plumbing 60% 60% 60% 60% 60% 60% 60%

11th

Door frame 100% 100% 100% 100% 100% 100% 100%

Wall Putty 100% 100% 100% 100% 100% 100% 100%

Electrical Wiring 80% 80% 80% 80% 80% 80% 80%

Plumbing 50% 50% 50% 50% 50% 50% 50%

Page 4: MONTHLY PROGRESS REPORT - primeresidencies.lk 5.pdf · 1 monthly progress report- march 2017 prime lands residencies (pvt) ltd #75, d. s. senanayake mawatha, colombo 08 project details

3

MONTHLY PROGRESS REPORT- MARCH 2017

PRIME LANDS RESIDENCIES (PVT) LTD #75, D. S. SENANAYAKE MAWATHA, COLOMBO 08

PROJECT PICTURES

FRONT VIEW

FRONT VIEW

FRONT VIEW

SIDE VIEW

3rd FLOOR FINISHING UNITS

3rd FLOOR FINISHING UNITS

Page 5: MONTHLY PROGRESS REPORT - primeresidencies.lk 5.pdf · 1 monthly progress report- march 2017 prime lands residencies (pvt) ltd #75, d. s. senanayake mawatha, colombo 08 project details

4

MONTHLY PROGRESS REPORT- MARCH 2017

PRIME LANDS RESIDENCIES (PVT) LTD #75, D. S. SENANAYAKE MAWATHA, COLOMBO 08

3rd FLOOR FINISHING UNITS

3rd FLOOR FINISHING UNITS

GLASS ROOF

POOL AREA EXTERNAL PAINTING

COMMON AREA TILING

COMMON AREA TILING