MONTHLY PROGRESS REPORT - primeresidencies.lk 5.pdf · 1 monthly progress report- march 2017 prime...
Transcript of MONTHLY PROGRESS REPORT - primeresidencies.lk 5.pdf · 1 monthly progress report- march 2017 prime...
PRIME LANDS RESIDENCIES (PVT) LTD
#75, D. S. SENANAYAKE MAWATHA, COLOMBO 08
MONTHLY PROGRESS REPORT
PRIME RESIDENCIES AQUA No 18/1, Temple Road. Nawala
March / 2017
1
MONTHLY PROGRESS REPORT- MARCH 2017
PRIME LANDS RESIDENCIES (PVT) LTD #75, D. S. SENANAYAKE MAWATHA, COLOMBO 08
PROJECT DETAILS
Project Architect : Arch.Thusara Waidyasekara
Contractor : SEIRRA Construction (Pvt) Ltd
Structural Engineer : Eng.K.V.G.G. Jayantha
Project Commenced Date – 2014/12/02
MEP Engineer : Eng. N.Sooriyaarachchi
Duration – 24 Months
CURRENT STATUS OF THE PROJECT
Floor Work H1 H2 H3 H4 H5 H6 H7
3rd
Door Fixing 100% 100% 100% 100% 100% 100% 100%
Painting 90% 95% 90% 90% 90% 90% 90%
Tilling 100% 100% 100% 100% 100% 100% 100%
Bathroom Fittings 50% 100% 50% 50% 50% 50% 50%
Electrical Fittings 80% 100% 80% 80% 80% 80% 80%
4th
Door fixing 80% 80% 80% 80% 80% 80% 80%
Painting 75% 75% 75% 75% 75% 75% 75%
Tilling 100% 100% 100% 100% 100% 100% 100%
Electrical Wiring 100% 100% 100% 100% 100% 100% 100%
Plumbing 100% 100% 100% 100% 100% 100% 100%
5th
Door frame 100% 100% 100% 100% 100% 100% 100%
Painting 65% 65% 65% 65% 65% 65% 65%
Tilling 100% 100% 100% 100% 100% 100% 100%
Electrical Wiring 100% 100% 100% 100% 100% 100% 100%
Plumbing 100% 100% 100% 100% 100% 100% 100%
6th
Door frame 100% 100% 100% 100% 100% 100% 100%
Painting 65% 65% 65% 65% 65% 65% 65%
Tilling 100% 100% 100% 100% 100% 100% 100%
2
MONTHLY PROGRESS REPORT- MARCH 2017
PRIME LANDS RESIDENCIES (PVT) LTD #75, D. S. SENANAYAKE MAWATHA, COLOMBO 08
6th
Electrical Wiring 100% 100% 100% 100% 100% 100% 100%
Plumbing 100% 100% 100% 100% 100% 100% 100%
Door frame 100% 100% 100% 100% 100% 100% 100%
7th
Painting 65% 65% 65% 65% 65% 65% 65%
Tilling 100% 100% 100% 100% 100% 100% 100%
Electrical Wiring 100% 100% 100% 100% 100% 100% 100%
Plumbing 100% 100% 100% 100% 100% 100% 100%
8th
Door frame 100% 100% 100% 100% 100% 100% 100%
Painting 65% 65% 65% 65% 65% 65% 65%
Tilling 100% 100% 100% 100% 100% 100% 100%
Electrical Wiring 100% 100% 100% 100% 100% 100% 100%
Plumbing 100% 100% 100% 80% 20% 100% 20%
9th
Door frame 100% 100% 100% 100% 100% 100% 100%
Painting 65% 65% 65% 65% 65% 65% 65%
Tilling 80% 100% 80% 80% 80% 10%
Electrical Wiring 100% 100% 100% 100% 100% 100% 100%
Plumbing 100% 100% 100% 100% 100% 100% 100%
10th
Door frame 100% 100% 100% 100% 100% 100% 100%
Painting 65% 65% 65% 65% 65% 65% 65%
Electrical Wiring 100% 100% 100% 100% 100% 100% 100%
Plumbing 60% 60% 60% 60% 60% 60% 60%
11th
Door frame 100% 100% 100% 100% 100% 100% 100%
Wall Putty 100% 100% 100% 100% 100% 100% 100%
Electrical Wiring 80% 80% 80% 80% 80% 80% 80%
Plumbing 50% 50% 50% 50% 50% 50% 50%
3
MONTHLY PROGRESS REPORT- MARCH 2017
PRIME LANDS RESIDENCIES (PVT) LTD #75, D. S. SENANAYAKE MAWATHA, COLOMBO 08
PROJECT PICTURES
FRONT VIEW
FRONT VIEW
FRONT VIEW
SIDE VIEW
3rd FLOOR FINISHING UNITS
3rd FLOOR FINISHING UNITS
4
MONTHLY PROGRESS REPORT- MARCH 2017
PRIME LANDS RESIDENCIES (PVT) LTD #75, D. S. SENANAYAKE MAWATHA, COLOMBO 08
3rd FLOOR FINISHING UNITS
3rd FLOOR FINISHING UNITS
GLASS ROOF
POOL AREA EXTERNAL PAINTING
COMMON AREA TILING
COMMON AREA TILING