Module 4 Introduction to the Case Study and Scoping
Transcript of Module 4 Introduction to the Case Study and Scoping
Module 4Introduction to the Case Study and Scoping
Slide 1
Scoping and Introduction to the Case Study Agenda
o Introduction to the Case Study
o Design scope – project data, schedule, specialties, budget, and key concerns
o Forms used in scoping
o Scoping meeting questions document
o SWMP Information Request Form
Scoping and Introduction to the Case Study 2
Case Study:Powers Blvd Extension North Site Location
Air Force Academy
North Gate Pkwy
Powers Blvd
Expansion Site
Interstate 25
Voyager Parkway
Colorado Springs
Scoping and Introduction to the Case Study 3
Powers Blvd Expansion Site
North Gate Pkwy
Voyager Pkwy
I-25
1
Air Force Academy
CDOT DBB Development “Process”
Environmental Evaluation/NEPA starts
ConstructionPhase
DesignPhase
Proposed Project
4
Scope
FIR
FOR
AD
Construction
SWMP Development
Process Occurs
Scoping and Introduction to the Case Study
Scoping Phase
1. Design scope – project data, schedule, specialties, budget, and key concerns
2. Design Scoping Review (DSR)- Early review of a project prior to preliminary design
Slide 5
Scoping involves two main steps:
Scoping and Introduction to the Case Study 5
R
CDOT Procedural Directive 512.1 and Project development manual
Stormwater Information
o Involves state and potentially local agencies, design-build contractors or consultant specialists, and the CDOT Project Design Team to complete
o Stormwater information must be obtained by the SWMP Administrator for Design from various sources and incorporated into the SWMP
o How is the information obtained?
Scoping and Introduction to the Case Study 6
Information Sources - Scoping Forms/Documents
o DSR Meeting Questions
o Form 463
o CDOT SWMP Informational Request Document
• Sent to Design Engineer (or can be used to get HQ LA involved with a project)
• Identifies Information Needs
Slide 7Scoping and Introduction to the Case Study 7
2
Scoping and Introduction to the Case Study 8
Powers Boulevard Extension North Scoping Meeting
Case Study: Scoping Meeting
Poll Question
DSR Meeting Participants
o Region Environmental Specialist (or RPEM if not delegated to RES or RWPCM)
o Project Engineer for Design (aka Design Engineer) (RE if not delegated to Design Engineer)
o Hydraulic Engineer
o SWMP Administrator for Design
o Materials Engineer
o Utility Specialists
o ROW Specialists
o Bridge Unit Specialists
o Maintenance Personnel
o Local Agency Representatives
o Landscape Architect
o Others as determined by the RE (e.g Regional Wetland Biologist, etc)
9Scoping and Introduction to the Case Study
Agenda
o Introductionso Project Overviewo Purpose and Needo NEPA Reporto Scheduleo Preliminary Budgeto Designo Public and Agency Inputo Comments and Input
Case Study: Scoping Meeting
Scoping and Introduction to the Case Study 10
Design Engineer
11Scoping and Introduction to the Case Study
• Provides SWMP Administrator for Design with access to project files
• Gives basic design and purpose of the project
• Answers project questions
• Adds SWMP quantities to overall engineering costs.
NEPA specialist
12Scoping and Introduction to the Case Study
• Provides SWMP Administrator for Design with NEPA report
• Gives information and restrictions about wetlands, cultural resources, and threatened and endangered species or wildlife restrictions
• Answers project NEPA questions
• Provides mapping for areas that cannot be impacted by the project
Local Agencies and Other Stakeholders
13Scoping and Introduction to the Case Study
What preliminary information is provided or discussed at the DSR?
15Slide 15
Quiz Time
1. Location of the proposed project
2. Identification of initial environmental concerns
3. Preliminary schedule and budget
4. Engagement of Stakeholders and team members
Scoping and Introduction to the Case Study
Importance of DSR
16
o Reduces risks by ensuring critical issues are addressed
o Scoping sets the stage for further field inventory and prep of FIR documents including the 30-40% draft of the SWMP discussed in the next few modules
Scoping and Introduction to the Case Study
Design Tracking Tool
17
Form 1048 is a review list (tracking tool) intended to be filled out as the project moves through design from scoping to AD.
Scoping and Introduction to the Case Study
Environmental Scoping Checklist
18
The Environmental Scoping Checklist has been developed by some regions
o To identify what topics:
• Have been addressed
• Are ongoing
• Are completed
Scoping and Introduction to the Case Study
SWMP Checklist
19
The SWMP Checklist has been developed by CDOT HQ as a guidance document.
o To provide consistency for CDOT SWMPs
o Allow for easy cross checking for elements
o Support stormwater compliance
Scoping and Introduction to the Case Study
Form 128
20Scoping and Introduction to the Case Study
Signed by RPEM or their designee that SWMP has been completed and meets CDOT requirements
Quiz Time
Who is not required to attend the DSR Meeting?
Slide 21Scoping and Introduction to the Case Study 21
Questions?
22Scoping and Introduction to the Case Study