MMO: Payload AIV MMO-SWG #3 [March 2006] -1- C. Noshi/RASC, Kyoto Univ. MMO Mercury Magnetospheric...
-
Upload
osborn-hicks -
Category
Documents
-
view
222 -
download
0
Transcript of MMO: Payload AIV MMO-SWG #3 [March 2006] -1- C. Noshi/RASC, Kyoto Univ. MMO Mercury Magnetospheric...
-1-
MMO: Payload AIVMMO-SWG #3 [March 2006]
C. Noshi/RASC, Kyoto Univ.
MMO
Mercury Magnetospheric Orbiter
AIV (Assembly, Integration, Verification)for BepiColombo MMO Payoads
Y. Kasaba, T. Takashima, H. Hayakawa(JAXA/BepiColombo Project Office)
-2-
MMO: Payload AIVMMO-SWG #3 [March 2006]
2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013
Implementation phase [old Ph-B/C/D]
Payload Selection
Definition phase[old Ph-A/B]
Launch2013.8B
PM (Ph.B) ESA JAXA both
ESA JAXA both
Technical study
Pre-PM1
MMO&MCS STM test
JAXA(ISAS)
ESA
(Calendar year)
PDR 2007.12E
Integrated Test & AIV
FM(Ph.C/D)
Pre-PM2
PRR2005.3B
PRR=Preliminary requirements Rev.PDR=Preliminary Definition Rev. CDR=Critical Design Rev. QR=Qualification Rev.
MMO-FM at ESTEC
(by ESA plan)
MMO-STM at ESTEC
(by ESA plan)
ITT
MMO-STM2009.5M
MMO-EM2010.6B
MMO-FM2011.9B
CDR2009.6E
MIC/EIC2010.3B-6B
Sub-Env test2010.7B-9E
QR 2011.8E
AIV2010.11B-2011.7E
2008.8E
2008.7M-2009.5E@JAXA/ESTEC
STMtest
ComponentDummy
Mercury orbit2019.8 ~ 2years
Now!!
RFP
AO
Overall Schedule (Mar 2006)
Is it OK? Install of STM 2008.8E Install of FM 2010.3B Env. Test 2010.7B-9E
“EM” & “Sub-system level reviews” can benegotiable each by each.
Is it OK? Install of STM 2008.8E Install of FM 2010.3B Env. Test 2010.7B-9E
“EM” & “Sub-system level reviews” can benegotiable each by each.
-3-
MMO: Payload AIVMMO-SWG #3 [March 2006] STM Schedule (Mar 2006)
Calender year1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Design and I/F Definition - -
MMO-PRR (2005 1-3B)BBM Manufacturing & Test - -
MMO-I-PDR (2007 9E) 9E
MMO-PDR (2007 11-12E) 12E
MDP: STM development & test ? ?
MPPE/MAST/WPT: STMmanufacturing & test
- - 4B 8E
MMO: STM IT/test @ ISAS 7M
MMO: STM IT/test @ ESTEC 5E
MCS: STM IT/test @ ESTEC 6B
MMO-I-CDR (2009 5-6E) 2E
MMO-CDR (2009 5-6E) 6E
reviewMMO: MIC/EIC (2010 3B-6B) 3B 6B
MCS: EM IT/test @ ESTEC 6B
MIC/EIC result review?Instrument Env Test (2010 7B-9E) 7B 9E
MMO-I-QR (2011 10B) 10B
MMO: AIV (2010 11B-2011 7E) 11B 7E
MMO-QR (2011 7-8E) 8E
2010 (H22) 2011 (H23)2006 (H18) 2007 (H19) 2008 (H20) 2009 (H21)
<Mile Stone> Payload STM: submission to System 2008 8EMPPE, MSASI (Hood only?), WPT-S, MEFISTO-S, MAST
Payload STM test should be done by 2008 Aug.
MMO-STM test in ISAS will be end in 2009 May.
-4-
MMO: Payload AIVMMO-SWG #3 [March 2006] EM Schedule (Mar 2006)
Calender year1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Design and I/F Definition - -
MMO-PRR (2005 1-3B)BBM Manufacturing & Test - -
MMO-I-PDR (2007 9E) 9E
MMO-PDR (2007 11-12E) 12E
Each: EM Manufacturing / Test(outside of MDP)
- 1B 8E
Each: EM Manufacturing / Test(inside of MDP)
10B 3E - -
MDP: EM IT/test 5B 9E -
MMO Payload: EM IT/test 10B-
12E
-
MMO-I-CDR (2009 5-6E) 2E
MMO-CDR (2009 5-6E) 6E
reviewMMO: MIC/EIC (2010 3B-6B) 3B 6B
MCS: EM IT/test @ ESTEC 6B
MIC/EIC result review?Instrument Env Test (2010 7B-9E)
7B 9E
MMO-I-QR (2011 10B) 10B
MMO: AIV (2010 11B-2011 7E) 11B 7E
MMO-QR (2011 7-8E) 8E
2010 (H22) 2011 (H23)2006 (H18) 2007 (H19) 2008 (H20) 2009 (H21)
<Mile Stone> Payload EM integration test schedule is TBD
PWI: from 2007 Oct. ??MGF: from 2008 Feb. ??Others: from 2008 May ??
-5-
MMO: Payload AIVMMO-SWG #3 [March 2006] Software Schedule (Mar 2006)
Calender year1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Design and I/F Definition - -
MMO-PRR (2005 1-3B)BBM Manufacturing & Test - -
MMO-I-PDR (2007 9E) 9E
MMO-PDR (2007 11-12E) 12E
MDP: CPU design 2B-3E
- -
MDP: Software design / Loadestimation
4B 3E
MDP: DPU test board 4B 9E
MDP: MDP Emulator H/Wdevelopment (& plimitive sensoremulator)
4B 9E
Each: Sensor Emulator develop 10B-
11EMDP: OS development 10B
-11E
MDP: Middleware development 4B 6E
MDP: Application Software test 4B 9E - -
MDP: Software IT test 10B-
12E
-
MMO-I-CDR (2009 5-6E) 2E
MMO-CDR (2009 5-6E) 6E
MMO-I-QR (2011 10B) 10B
MMO: AIV (2010 11B-2011 7E) 11B 7E
MMO-QR (2011 7-8E) 8E
2010 (H22) 2011 (H23)2006 (H18) 2007 (H19) 2008 (H20) 2009 (H21)
<Mile Stone> Software development does not have major milestones.Parts related to EM test will be synchronized to the System.
-6-
MMO: Payload AIVMMO-SWG #3 [March 2006] FM Schedule (Mar 2006)
Calender year1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Payload A/O (2004 4-11)
Design and I/F Definition - -
MMO-PRR (2005 1-3B)BBM Manufacturing & Test - -
MMO-I-PDR (2007 9E) 9E
MMO-PDR (2007 11-12E) 12E
MMO-I-CDR (2009 5-6E) 2E
MMO-CDR (2009 5-6E) 6E
Each: FM Manufacturing / Test(outside of MDP)
- - - - 4B 12E
Each: FM Manufacturing / Test(inside of MDP)
- - - - 4B 9E
MDP: IT/test @ MHI or ISAS 10B-
12EMMO Payload: FM IT/test @ISAS
1M-2M
reviewMMO: MIC/EIC (2010 3B-6B) 3B 6B
MCS: EM IT/test @ ESTEC 6B
MIC/EIC result review?Instrument Env Test (2010 7B-9E)
7B 9E
MMO-I-QR (2011 10B) 10B
MMO: AIV (2010 11B-2011 7E) 11B 7E
MMO-QR (2011 7-8E) 8E
2006 (H18) 2007 (H19) 2008 (H20) 2009 (H21) 2010 (H22) 2011 (H23)
<Mile Stone> Payload FM: submission to System 2010 MarchPayload FM: Environment test 2010 7B-9E
There might be no chance to remove payloads at ESTEC.
-7-
MMO: Payload AIVMMO-SWG #3 [March 2006]
5Days/ 1Week week1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 3W1
PSU,IPD,DPU installation Function Test
EWO,WPT- Pre, SC- Pre installation Function Test
MEFISTO- E, MEFISTO- Pre, AM2P installationSORBET installation Function Test
MGF- I (MGF- O) installation (?) Function Test
Reserved: Repair of each component
Function Test after repairs
MDP- 1,MDP- 2 Set upMDP- 1 Function TestMDP- 2 Function Test
* 4 hours each: for the change of configuration
EM Schedule for MDP (Mar 2006)
Integration test plan for MDP-2 (& MDP-1) with PWI & MGF
Details will be discussed in PWI local meeting in Kanazawa in this week.
~Plan: 13 weeks ~(FM: less)
MDP/Instrument tests by“Emulators with SpW” ?
MDP/Instrument tests by“Emulators with SpW” ?
-8-
MMO: Payload AIVMMO-SWG #3 [March 2006] Action Items in 2006FY
• Definition of the Schedule, Test location, and Responsibility/Members
• Definition of the procurement items from each teamto each team
• Definition of the test items in Component-level test in MDP-level test
in System-level test
• Definition of the Test environment in Component-level testin MDP-level testin System-level test
It will be defined as “MMO Payload Test Plan” (Draft version is in I-IRD etc.)
by JAXA/BepiColombo Project Office.
Please discuss in each team, and clarify your Action Items & Request to System / Other teams in CDD and/or Progress report.
-9-
MMO: Payload AIVMMO-SWG #3 [March 2006]
Sensor SpaceCube etc.
Signal Generator
Spacewire
PC
Ether etc.
GPIB etc.
EM/FM: Test Configuration Concept
System level test @ ISAS (/ ESTEC / Launch site)
Sensor MDP / MDP emulator
Signal Generator
Spacewire
PC
Ether etc.
GPIB etc.
MDP level test @ ISAS / MHI etc.
SpaceCube etc.
Spacewire
Sensor MDP > DMC
Signal Generator
Spacewire
PC
Ether etc.
GPIB etc.
TM/TCGround System
IEEE1553B?
(TLM only!)
Board/unit level test @ each institution
-10-
MMO: Payload AIVMMO-SWG #3 [March 2006]
SpaceCube: present status• SpaceWire Analyzer on SpaceCube
– Under development, Finished until October (distribution or purchase : after Oct. with soft)
– Analyzer will be distributed by MMO-project with SpaceCube
• GSE– Using SpaceCube with SpaceWire Analyzer– Middle ware (User I/F) will be define next year
SpaceWire Analyzer on SpaceCube
PC
RMAP packet content
001101110111
TLM COM Sensor with SpW I/F
SpW
RS232
RMAP HOST RMAP Target
-11-
MMO: Payload AIVMMO-SWG #3 [March 2006]
Space-Cube (TBC) for GSE
• Mini-PC with VGA, USB, Ether, CF-I/F
• SpW port : 3 ports• OS : T-kernel (TRON)• Language : C (C++ ?)• Development : Cross-Compiler on Linux• SpW I/F : special API for SpW I/F prepared• SpW user program : Sample program that is to r
ead and wite SpW packet attached. If necessary, user can develop programs using APIs for SpW.