PRESENTATION BY ENG. M.S.M. KAMAU, CBS, HSC
THE KONZA TECHNO CITY INVESTORS CONFERENCE
HELD ON 7TH – 9TH AUGUST 2012, 9.10AM AT
AMPHITHEATRE, KICC
7/30/2019 Ministry for Roads_Konza Investment 2012
http://slidepdf.com/reader/full/ministry-for-roadskonza-investment-2012 2/11
7/30/2019 Ministry for Roads_Konza Investment 2012
http://slidepdf.com/reader/full/ministry-for-roadskonza-investment-2012 3/11
7/30/2019 Ministry for Roads_Konza Investment 2012
http://slidepdf.com/reader/full/ministry-for-roadskonza-investment-2012 4/11
7/30/2019 Ministry for Roads_Konza Investment 2012
http://slidepdf.com/reader/full/ministry-for-roadskonza-investment-2012 5/11
ROADS NETWORK
7/30/2019 Ministry for Roads_Konza Investment 2012
http://slidepdf.com/reader/full/ministry-for-roadskonza-investment-2012 6/11
1. ATHI RIVER – MACHAKOS TURNOFF
The road section is approximately 23km in length and starts at the Athi River
interchange then runs generally in an Eastern direction up to Kyumvi Township,
which is commonly referred to as Machakos Turnoff. The works envisaged
include:
Construction to bitumen standards of a 2-lane carriageway along the existing
one
Construction of Bypass North-East of Kyumvi Township
7/30/2019 Ministry for Roads_Konza Investment 2012
http://slidepdf.com/reader/full/ministry-for-roadskonza-investment-2012 7/11
Construction of grade separated intersections along the highway for access to
(i) Kenya Meat Commission
(ii) Daystar University
(iii) Kyumvi
(iv) Machakos
Strengthening of existing carriageway as appropriate
7/30/2019 Ministry for Roads_Konza Investment 2012
http://slidepdf.com/reader/full/ministry-for-roadskonza-investment-2012 8/11
2. MACHAKOS TURNOFF – KONZA TECHNOCITY
The road section is approximately 24km in length. It starts South-East of
Kyumvi township where the Bypass meets the old alignment and runs
generally in a southeasterly direction up to Konza. The works envisaged
include:
Construction to bitumen standards of a 2-lane carriageway along the
existing
one
Construction of an interchange where the road accessing the Technocity
intersects the highway
7/30/2019 Ministry for Roads_Konza Investment 2012
http://slidepdf.com/reader/full/ministry-for-roadskonza-investment-2012 9/11
Strengthening of existing carriageway as appropriate
3.PROJECTS STATUS
The current status of the above projects is as follows:
7/30/2019 Ministry for Roads_Konza Investment 2012
http://slidepdf.com/reader/full/ministry-for-roadskonza-investment-2012 10/11
No. DESCRIPTION
PROJECTIONS
Development
Partner supportRemarksDESIGN WORKS
1 Second Carriageway of
Athi River – Machakos
Turnoff
Probable completion July
2013
Probable start January
2014 and completion
December 2016
World Bank under
Kenya Transport
Sector Support
Project (KTSSP) to
support Design andConstruction.
Shortlist of consultants to be
invited to submit proposals for
design and works supervision
awaiting ‘no-objection’ from the
World Bank.
2 Second Carriageway of
Machakos Turnoff –
Konza Technocity
Probable completion
March 2013
Probable start
October 2013 and
completion October 2015
World Bank under
Northern Corridor
TransportImprovement Project
(NCTIP) to support
Design.
Terms of Reference for
procurement of design consultant
as an addendum under preparation.
Construction not earmarked for
support by any partner yet.
7/30/2019 Ministry for Roads_Konza Investment 2012
http://slidepdf.com/reader/full/ministry-for-roadskonza-investment-2012 11/11
END
Q & A