MICE-SciFi team, 14 October 2003
SciFi: progress report Progress:
All stations shipped to FNAL … … assembly in progress
Measurements: Effect of radiated RF on VLPCs … OK Light yield, cross talk etc. to come
Updated costing G4MICE:
Progress on debugging new G4MICE
Stations: mechanicalPrototype:
All three stations shipped to FNAL
Lightguides
All lightguides shipped to FNAL
Implementation at FNAL:D0 test stand:
Trigger etc. ready, assembly in progress
RF test done: effect at FULL power ~ 0.5 ADC count increase in width of pedestali.e. an effect of less than 0.05 pe (i.e. OK for MICE)
Assembly:
Assembly:
Assembly:
Cost and schedule Updated cost and schedule in preparation:
Mechanical: revised costing ~prepared. Shows saving and is based on experience with prototype
A. Bross (FNAL) updating electronics costing: ‘Borrow’ D0 spares? Implies negotiation with D0 … Build new VLPC cassettes … cost being evaluated
Schedule: Mechanical: revised following experience with
prototype Electronics: being revised by A. Bross (D0
experience)
Software
Present focus: Gridification: Done: Rapid generation of large data sets RF background generator: under test SciFi simulation: updated: under test SciFi reconstruction: updated: under test
Schedule to provide results for collaboration meeting is tight … but probably will be met
Summary:
Tight … but … still possible!