MICE MICO September ‘07 Chris Nelson. Beamline and Hall Shielded area virtually complete –SW...

6
MICE MICO September ‘07 Chris Nelson

Transcript of MICE MICO September ‘07 Chris Nelson. Beamline and Hall Shielded area virtually complete –SW...

Page 1: MICE MICO September ‘07 Chris Nelson. Beamline and Hall Shielded area virtually complete –SW corner –Replacement West wall concrete ordered, corner pieces.

MICE MICO September ‘07

Chris Nelson

Page 2: MICE MICO September ‘07 Chris Nelson. Beamline and Hall Shielded area virtually complete –SW corner –Replacement West wall concrete ordered, corner pieces.

Beamline and Hall• Shielded area virtually complete

– SW corner– Replacement West wall concrete ordered, corner pieces about to be ordered– Delivery both ~6 weeks, installation next opportunity– Extra wall near Door and roof subject to survey

• Extra shielding in plinth doorway– Plan using high density blocks, availability ~1 week– Agreement with Paul Wright RPA– Check numbers needed and Order today

• Plinth rails installed & surveyed – Double check needed on alignment measurements

• CKOV stand– Materials and parts ordered by Oxford– Discussion, & Extra small detail drgs lifting, dowel pins etc (being

finished?)– CJN will organise PRR (Peter back next week)

Page 3: MICE MICO September ‘07 Chris Nelson. Beamline and Hall Shielded area virtually complete –SW corner –Replacement West wall concrete ordered, corner pieces.

• Triplet baseplates at RAL– Installation details being finalised, hope to install 1-2 weeks time– But Need blockhouse access

• Rolling platform– Review end September– Ordered air skates– First platform required March 08

• Future plans– False floor– Concrete plinth

Page 4: MICE MICO September ‘07 Chris Nelson. Beamline and Hall Shielded area virtually complete –SW corner –Replacement West wall concrete ordered, corner pieces.
Page 5: MICE MICO September ‘07 Chris Nelson. Beamline and Hall Shielded area virtually complete –SW corner –Replacement West wall concrete ordered, corner pieces.

MICE – platforms and baseplates

CONCEPT – PLATFORM

WITH AIR SKATES CLAMPED

TO BASEPLATE IN INSTALLED

LOCATION. WHEN ACCESS IS REQ’D

THE CLAMPS ARE RELEASED AND

THE TRACKER IS FLOATED TO

A PARKED POSITION.

Page 6: MICE MICO September ‘07 Chris Nelson. Beamline and Hall Shielded area virtually complete –SW corner –Replacement West wall concrete ordered, corner pieces.

Mechanical Services

• Water- order being written out

• Other services/gases– Need for detector groups to request any required

services• Compressed air line for when Linde equipment in use• Nitrogen for CKOV (bottle/gas line)?