MICE MICO September ‘07
Chris Nelson
Beamline and Hall• Shielded area virtually complete
– SW corner– Replacement West wall concrete ordered, corner pieces about to be ordered– Delivery both ~6 weeks, installation next opportunity– Extra wall near Door and roof subject to survey
• Extra shielding in plinth doorway– Plan using high density blocks, availability ~1 week– Agreement with Paul Wright RPA– Check numbers needed and Order today
• Plinth rails installed & surveyed – Double check needed on alignment measurements
• CKOV stand– Materials and parts ordered by Oxford– Discussion, & Extra small detail drgs lifting, dowel pins etc (being
finished?)– CJN will organise PRR (Peter back next week)
• Triplet baseplates at RAL– Installation details being finalised, hope to install 1-2 weeks time– But Need blockhouse access
• Rolling platform– Review end September– Ordered air skates– First platform required March 08
• Future plans– False floor– Concrete plinth
MICE – platforms and baseplates
CONCEPT – PLATFORM
WITH AIR SKATES CLAMPED
TO BASEPLATE IN INSTALLED
LOCATION. WHEN ACCESS IS REQ’D
THE CLAMPS ARE RELEASED AND
THE TRACKER IS FLOATED TO
A PARKED POSITION.
Mechanical Services
• Water- order being written out
• Other services/gases– Need for detector groups to request any required
services• Compressed air line for when Linde equipment in use• Nitrogen for CKOV (bottle/gas line)?