Construcción

Page 2: Metal Beam Formwork BTM Catalogue - … · transmitted in any way by any electronic or mechanical procedure, ... BTM provides slab formwork solutions, ... Metal Beam Formwork BTM

IMPORTANT:

Any safety provisions as directed by the appropriate governingagencies must be observed when using our products.

The pictures in this brochure are snapshots of situations atdifferent stages of assembly, and therefore are not completeimages. For the purpose of safety, they should not be deemed asdefinitive.

All of the indications regarding safety and operations containedin this brochure, and the data on stress and loads should berespected. ULMA Construcción’s Technical Department must beconsulted anytime that field changes alter our equipmentinstallation drawings.

Our equipment is designed to work with accessories and elementsmade by our company only. Combining such equipment withother systems is not only dangerous but also voids any or all ourwarrantees.

The company reserves the right to introduce any modificationsdeemed necessary for the technical development of the product.

All rights reserved.Neither all nor part of this document may be reproduced ortransmitted in any way by any electronic or mechanical procedure,including photocopy, magnetic recording or any other form ofinformation storage or retrieval system without the writtenpermission of ULMA Construcción.

Page 3: Metal Beam Formwork BTM Catalogue - … · transmitted in any way by any electronic or mechanical procedure, ... BTM provides slab formwork solutions, ... Metal Beam Formwork BTM

Horizontal Formwork withBTM Beams

The Horizontal Formwork with BTM Beams is a simple andpractical system. Its few components and its ease of

application on site make it a fast and effective formworksystem.

BTM provides slab formwork solutions, and it can be adapted toany layout encountered, whether working in small or large spaces.

The BTM Beams 160 are easy to handle. Light weight andperfectly designed, they can be used to solve any constructionsite problems. The beams are protected on their extremes bycovers, and they resist being damaged by hits and roughtreatment common at the construction site. Galvanicprotection provides rust-proof coating, resulting in highlydurable beams.

The Tripod can be used to plumb the prop quickly in anyposition, thus offering (given the organized use of materials)significantly improved performance and rational solutions atthe construction site.

Weight . . . . . . . 7.7 kg/mlIx . . . . . . . . . . . . . 314 cm4

Wx . . . . . . . . . . . 37.4 cm3

Madm. . . . . . . . . 96,020 kg.cmEx I . . . . . . . . . . 6.6 x 108 kg.cm2

BTM Beam 160:

Mechanicalcharacteristics.

Page 4: Metal Beam Formwork BTM Catalogue - … · transmitted in any way by any electronic or mechanical procedure, ... BTM provides slab formwork solutions, ... Metal Beam Formwork BTM

Assembly

1Phase

Install the props with their corresponding heads (single andbidirectional), supported by the tripods. On the heads, install themain beams (MB). Level the assembly.

3Phase

Install the plywood 1.22 x 2.44m. Position planks parallel to eachother between the plywood in order to shore the slab thereafter.

2Phase

Install the secondary beams (SB) on the MB at the proper distances(610 or 488 mm).

4Phase

This is how the slab will be shored after having removed all thematerials (plywood, beams and some of the props).

MB SB

Page 5: Metal Beam Formwork BTM Catalogue - … · transmitted in any way by any electronic or mechanical procedure, ... BTM provides slab formwork solutions, ... Metal Beam Formwork BTM

Working Loads Table

1. PlywoodIt is recommended to use the 2.44 x 1.22 m, 18 mm thick plywood in order to support the loads.

4. PropsLoad distribution on each prop should be analyzed, and the appropriate prop should be selected based on the HEIGHT and LOAD to be shored. (Use theULMA Construcción PROPS catalog for this purpose).

2. Secondary beams (SB)

3. Main beams (MB)

MB = Main Beams3,000 mm

On 3 or 4 props

Number of secondary Y= 2100 Y= 2700 Y= 3000beams (SB) per piece of plywood

6 Beams (SB) 93 cm 32 cm 21 cm

5 Beams (SB) 72 cm 24 cm 15 cm

MAXIMUM CONCRETE SLAB THICKNESSDistance between MB = Y

MAXIMUM CONCRETE SLAB THICKNESS2400 x 1220 x 18 mm (L = 2440 mm) Plywood

Number of secondary 6 BEAMS (SB) 5 BEAMS (SB)beams (SB) per piece of plywood X = 488 mm X = 610 mm

Slab thickness 52 cm 33 cm

Number of secondary Y= 2100 Y= 2700 Y= 3000beams (SB) per piece of plywood

6 Beams (SB) 62 cm 47 cm 42 cm

5 Beams (SB) 59 cm 44 cm 39 cm

MAXIMUM CONCRETE SLAB THICKNESSZ = 3 Props (every 1.5 m)

Number of secondary Y= 2100 Y= 2700 Y= 3000beams (SB) per piece of plywood

6 Beams (SB) 112 cm 86 cm 76 cm

5 Beams (SB) 87 cm 66 cm 59 cm

MAXIMUM CONCRETE SLAB THICKNESSZ = 4 Props (every 1 m)

Page 6: Metal Beam Formwork BTM Catalogue - … · transmitted in any way by any electronic or mechanical procedure, ... BTM provides slab formwork solutions, ... Metal Beam Formwork BTM

Solutions offered by the system

Components of the System

BTM Beams 160BTM Beam 1 . . . . . . . 1940130 8.5BTM Beam 1.5 . . . . . . 1940131 12.7BTM Beam 2 . . . . . . . 1940132 17BTM Beam 2.5 . . . . . 1940133 21BTM Beam 3 . . . . . . . 1940134 25.5

Code Weight(kg)

Single HeadSingle Head . . . . . . . . . 1940079 0.9

BidirectionalHead

Bidirectional Head . . . . 1940075 3

Code Weight(kg)

TripodTripod . . . . . . . . . . . . . . 1940128 10.5

Code Weight(kg)

PropsECO Prop 1.75 / 3 . . . 2160300 6.2Normal Prop1.75 / 3.1 . . . . . . . . . . 2150000 10Normal Prop2.1 / 3.5 . . . . . . . . . . . 2150500 10.6Strong Prop2.1 / 3.65 . . . . . . . . . . 2154300 13.6Strong Prop3.65 / 5.25 . . . . . . . . . 2154400 18.8

Assembling the Tripod.This permits setting the prop upvertically. It should be used at thebeginning of the assembly.

Assembling the Bidirectional Head.The Bidirectional Head socket is installed onthe Prop. One or two beams can overlap.

Assembling the Single Head.Only one beam can be installed per prop.

Page 7: Metal Beam Formwork BTM Catalogue - … · transmitted in any way by any electronic or mechanical procedure, ... BTM provides slab formwork solutions, ... Metal Beam Formwork BTM
Page 8: Metal Beam Formwork BTM Catalogue - … · transmitted in any way by any electronic or mechanical procedure, ... BTM provides slab formwork solutions, ... Metal Beam Formwork BTM

ECEQ

07

SPAINPhone: +34 943 034900Fax: +34 943 034920www.ulma-c.com

EUROPEULMA Betonschalungenund Gerüste GmbHKronberger Str. 16D-63110 RODGAU-DUDENHOFEN(Germany)Phone: + 49 6106 28677 0Fax: + 49 6106 28677 86www.ulma-c.de

ULMA, S.A.R.L.27, rue Gustave EiffelZ.I. de la Marinière91070 BONDOUFLE (France)Phone: + 33 1 69 11 54 50Fax: + 33 1 69 11 54 54www.ulma-c.fr

ALPI, S.P.A.Zona Industriale EstI-39035 MONGUELFO (BZ)(Italy)Phone: + 39 0474 947 400Fax: + 39 0474 947 499www.alpionline.net

ULMA Kazakhstan01000 ASTANA (Kazakhstan)6/2, Tashenova St. 4th floor, offices 7, 9Phone/Fax: +7 7172 58 05 19Phone: +7 7172 37 93 48www.ulma-c.kz

ULMA Construccion Polska, S.A.03-115 WARSAW (Poland)ul. Klasyków 10Phone: + 48 22 506 70 00Fax: + 48 22 814 31 31www.ulma-c.pl

ULMA Portugal Lda.Zona Industrial - Rua A, s/nVale de Figueira2695 SÃO JOÃO DA TALHALISBON (Portugal)Phone: + 351 219 947 850Fax: + 351 219 558 022www.ulma-c.pt

ULMA Cofraje s.r.l.Sos Chitilei, 200012405 - Sector 1 - BUCHAREST(Romania)Phone: + 40 31 425 13 22 / 23Fax: + 40 31 425 13 24www.ulma-c.ro

ULMA Russia107005 MOSCOW (Russia)9/23, 2nd Baumanskaya St.Phone/Fax: +7 495 777 94 73Phone: +7 495 777 94 72www.ulma-c.ru

ULMA Formwork Ukraine Ltd.01013 KIEV (Ukraine)3, Derevoobrobna St.Phone: +38 44 255 14 92Fax: +38 44 255 14 94www.ulma-c.com

AMERICAULMA Andamios y EncofradosArgentina, S.A.Bernardo de Irigoyen 722 6ACP1072AAP FEDERAL CAPITAL CITY(Argentina)Phone/Fax: + 541 14 3425132www.ulma-c.com.ar

ULMA Brasil - Fôrmas eEscoramentos Ltda.Rua Dr. João Dias Ribeiro, 210Jd. Sagrado Coração de JesusItapevi - SP (Brazil)CEP: 06693-810Phone/Fax: + 55 11 3883 1300Phone/Fax: + 55 11 4619 1300www.ulma-c.com.br

ULMA Chile - Andamios yMoldajes, S.A.Vizcaya nº 325 - Pudahuel(Ruta 68, Camino Noviciado)SANTIAGO (Chile)Phone: + 56 2 5990530Fax: + 56 2 5990535www.ulma-c.cl

ULMA Form Works, Inc.58 Fifth AvenueHawthorne, NEW JERSEY 07506(USA)Phone: + 1 973 636 2040Fax: + 1 973 636 2045www.ulma-c.us

ULMA Cimbras y Andamiosde México S.A. de C.V.Vía Gustavo Baz Prada 2160 Acceso 554060 Col. La LomaTLALNEPANTLA(Mexico State) (Mexico)Phone: + 52 55 5361 6783Fax: + 52 55 2628 3549www.ulma-c.com.mx

ULMA Encofrados Perú, S.A.Av. Argentina 2882LIMA (Peru)Phone: + 51 1 613 6700Fax: + 51 1 613 6710www.ulma-c.com.pe

ASIA-AFRICAULMA Formworks China R.O.#1009 Fortunegate Mall1701 West Beijing RoadSHANGHAI, 200040(P. R. China)Phone: + 86 21 62887070Fax: + 86 21 62885980www.ulma-c.com

ULMA Formworks UAE L.L.C.Plot No. 597-547Dubai investments ParkP.O. Box 282286DUBAI (UAE)Phone: + 971 4 3419970Fax: + 971 4 3418850www.ulma-c.com

ULMA FormworkSingapore PTE. LTD2 Senoko Way758027 SINGAPOREPhone: + 65 6758 2338Fax: + 65 6758 8523www.ulma-c.com