Meeting Agenda• Introduction of Project Team• Connective Corridor Project • Onondaga County Sewer
Separation Project • Civic Strip Project• Syracuse University Façade
Improvement Grant Program
Speakers• Linda Dickerson Hartsock,
Syracuse University• Owen Kerney, City of Syracuse• Stephen Harris, City-County
Arborist• Mark Budosh, Barton &
Loguidice for Onondaga County
• University Avenue• East Genesee Street• Forman Park• Armory Square gateway
landscaping• SPARC public art installations• Syracuse Stage Plaza
Connective Corridor Phase One
• CC logisticsConnective Corridor Project Scope• Full reconstruction of the right-of-way: new sidewalks, curbing, parking areas, bicycle lanes, and vehicular travel lanes• Project includes pedestrian amenities, traffic calming features, improved signage, bus stops with pull-offs, energy efficient lighting, landscaping and street trees, green infrastructure, and enhanced intersection and street crossings
Connective Corridor Project Schedule• Final design: May 2013• Project Bid: June 2013• Construction: late July/early August
2013 through summer 2015
• Work will begin at Forman Ave. and progress west
• Project will include winter shutdown from October through March/April
Connective Corridor Tree Removal
Scope• 95 Trees to be removed within
next five weeks• Removal will start at Forman
Ave and proceed west to S. Franklin St.
• Removal will begin the weekend of January 26, 2012
• Work will be performed on weekends by City Crews
Scope• Removal is scheduled for three
consecutive weekends, but is weather dependent
• Trees diameters range from 2–18 inches and the average diameter is 7 inches
• Approximately 170-180 new trees to be planted
Connective Corridor: Tree Removal
Onondaga County Sewer Separation Project
Schedule• Design is underway, and
construction is scheduled to begin after 3/17/13
• Duration of construction is approximately 90 days
• Construction will use daily lane closures and alternating one-way detours. May require occasional road closure along blocks
Project Scope• Installation of approx. 1200 LF of
separated storm sewer pipe• Situated parallel to combined
sewer on W. Fayette Street between S. Salina St. and Creek
• Work will begin at Creek and work east toward S. Salina St.
• Separated storm sewer will connect to new catch basins installed in Connective Corridor project
Scope• Intersections and crosswalks• Street amenities• Activated entries• Lighting treatments along
Jefferson Street Connector• Signage and wayfinding system
Civic Strip
Façade round one: (Completed)
• $625,000 in grants catalyzed improvements to 40 buildings along the Connective Corridor
Façade round two: (Launching spring 2013)
• $250,000 in matching grants• Special focus on lighting iconic
buildings
Façade Improvement Program