Onondaga County CSO Abatement Gray Project Update

14
Onondaga County CSO Abatement Gray Project Update

description

Onondaga County CSO Abatement Gray Project Update. 2012 Gray Project Update. Harbor Brook Intercepting Sewer Replacement Project CSO 044 Conveyance Pipeline CSO 022/045 Sewer Separation Projects Clinton CSO Storage Facility Lower Harbor Brook CSO Storage Facility CSO 063 Conveyance Project - PowerPoint PPT Presentation

Transcript of Onondaga County CSO Abatement Gray Project Update

Page 1: Onondaga County CSO Abatement Gray Project Update

Onondaga County CSO Abatement Gray Project Update

Page 2: Onondaga County CSO Abatement Gray Project Update

2

2012 Gray Project Update• Harbor Brook Intercepting Sewer Replacement

Project• CSO 044 Conveyance Pipeline• CSO 022/045 Sewer Separation Projects• Clinton CSO Storage Facility• Lower Harbor Brook CSO Storage Facility• CSO 063 Conveyance Project• Floatables Assessment Plan

Page 3: Onondaga County CSO Abatement Gray Project Update

3

Harbor Brook Intercepting Sewer Replacement Project – ACJ Milestone Date 12/31/2013• Replaces a significant portion

of infrastructure that was originally installed in the early 1900’s.

• 7500 feet of interceptor sewer replacement, 5200 feet of local sewer replacement and 1860 feet of sewer rehabilitation.

• Project green infrastructure elements included tree basins, rain gardens and bio-retention basins.

• Estimated annual CSO capture is 0.9% or 36 million gallons.

• Included separation of CSO 013 (Seymour Street) and CSO 016 (Lydell Street)

Page 4: Onondaga County CSO Abatement Gray Project Update

4

CSO 044 Conveyance Project-ACJ Milestone Date 12/31/2011• 500 foot long 96-inch

diameter conveyance pipe line.

• Conveyance will capture the full 1 year 2 hour storm volume from CSO 044.

• Project incorporated storm water capture for pipe line flushing.

• Final restoration included rain gardens.

• Estimated annual CSO capture is 0.3% or 12 million gallons.

Page 5: Onondaga County CSO Abatement Gray Project Update

5

CSO 022/045 Sewer Separation Project• Combined project into one

construction contract to minimize administration costs.

• CSO 022 – Fayette Street and West Genesee Street near Dinosaur BBQ. (Clinton Lower Main Intercepting Sewer CSO Area)

• CSO 045 – Hudson Street and Crescent Street. (Midland CSO Area)

Page 6: Onondaga County CSO Abatement Gray Project Update

6

Clinton CSO Storage Facility – ACJ Milestone 12/31/2013

• 6.5 million gallon storage capacity - volume of storage was increased by 40%.

• Facility will employ green and innovative technologies to reduce operating costs.

• Very challenging construction▫ Limited site space▫ High chloride

concentration in groundwater

Page 7: Onondaga County CSO Abatement Gray Project Update

7

Clinton CSO Storage Facility (cont.)

Page 8: Onondaga County CSO Abatement Gray Project Update

8

Page 9: Onondaga County CSO Abatement Gray Project Update

9

Page 10: Onondaga County CSO Abatement Gray Project Update

10

Lower Harbor Brook CSO Storage Facility – ACJ Milestone 12/31/2013

• 4.9 million gallon storage capacity – volume of storage was increased by 35%.

• Facility will employ green and innovative technologies to reduce operating costs.

• Very challenging construction▫ Limited site space▫ High chloride

concentration in groundwater

Page 11: Onondaga County CSO Abatement Gray Project Update

11

Page 12: Onondaga County CSO Abatement Gray Project Update

12

Page 13: Onondaga County CSO Abatement Gray Project Update

13

Future Projects• Floatables Control

Plan• CSO 063 (Emerson

Avenue – Harbor Brook CSO Area) Conveyance Pipe Line.

• CSO 061 (Crehange Street – Midland CSO Area) Sewer Separation

Page 14: Onondaga County CSO Abatement Gray Project Update

Questions!

Please Visit:www.SaveTheRain.us