McElhanney Victoria Road traffic plan
-
Upload
revelstoke-mountaineer -
Category
Documents
-
view
214 -
download
0
Transcript of McElhanney Victoria Road traffic plan
-
8/18/2019 McElhanney Victoria Road traffic plan
1/99
City of Revelstoke Council Report
File No.: 5460-05/ENG 2015-04
To: His Worship Mayor McKee and Members of City Council
From: Mike Thomas P.Eng. ENV SP – Director of Engineering and Development
Date: 18 April 2016
Subject: Victoria / Mutas Intersection Conceptual Design
RECOMMENDATION:
THAT City staff be directed to proceed to preliminary design of the concept proposed in Appendix A of McElhanney’s Victoria/Mutas Intersection Improvement ConceptualDesign Brief.
CAO Comments:
Approved for Council consideration. AC
Background:
The City engaged McElhanney Consulting Services to provide engineering services on twointersections in Revelstoke. The first project involves the Victoria/Mutas intersection, adjacent to
the Trans Canada Highway and several busy highway commercial businesses. The initialconcept, developed through many years of previous engineering reports, revised with input fromCity staff and Ministry of Transportation and Infrastructure staff, was modified and presented toCouncil and the public in early March 2016, with an excellent level of community involvement.
Following these meetings, stakeholder and public feedback was gathered and reviewed by theconsulting team. The results of the review are presented in the attached Conceptual DesignBrief.
Options / discussion:
Public Questions
McElhanney responded to questions asked through this process, found in sections 3 to 5 of thereport:
- Items Unclear to the Public- Comments with Significant Ministry of Transportation and Infrastructure (MoTI)
Involvement- Comments without Significant MoTI Involvement- Snow Removal
-
8/18/2019 McElhanney Victoria Road traffic plan
2/99
City of Revelstoke Council Report
These sections provide answers to many of the issues heard at the public and stakeholderevents. The snow removal issue for a roundabout was often cited by the public as a reason that
the design would not work, McElhanney contacted over a dozen road authorities that haveroundabouts in snowbelt areas. The quotes from these authorities, provided on pages 9-11 ofthe report, many from communities with comparable annual snowfalls to Revelstoke, speak tothe ability to provide a high level of service and safety at these intersections through properdesign and maintenance practices.
Many verbal comments were received at the open house stating that they supported theconcept.
Traffic Modelling
McElhanney completed traffic modelling for the existing and proposed intersectionconfigurations. Generally, the existing level of service during the peak hour is classed as “E”,modelling indicated that with the proposed upgrades, this would improve to a Level of Service“B” at the Victoria/Mutas Intersection.
Sustainability
One of the requirements of the City was to review the design from a sustainability lens. TheEngineering Department has adopted the Envision Rating System for evaluation ofinfrastructure projects across a range of performance objectives. McElhanney has provided in
Appendix E of the report a brief review of the potential score of this project, noting that theproposed design scores quite highly in Envision due to:
Reducing congestion
Increased pedestrian and cyclist safety Improved stormwater management Reduced Greenhouse Gas Emissions Community and Stakeholder engagement processes Preserving and improving the local character
Recommended Design
Taking the input received from stakeholders and the public, McElhanney made several changesto the design presented to the public in early March. These proposed changes are shown in theattached design sketch and include:
Improved pedestrian access to Tim Hortons, Shell and Super 8 with a sidewalk andcrosswalk.
Improved access to the frontage road for Tim Hortons, Shell and Super 8, particularly forlarger vehicles.
Installation of concrete median restricting turning movements near the Canadian Pacific(CP) underpass.
Inclusion of a modest large vehicle parking area on the frontage road. Removal of the future roundabout at Fraser Drive from the design plans.
-
8/18/2019 McElhanney Victoria Road traffic plan
3/99
City of Revelstoke Council Report
Unresolved in the proposed design are the concerns of the businesses on the east side ofVictoria that are currently accessed off the highway by a left turn off Victoria to the Frontage
Road. The report suggests that these issues could be mitigated with a coordinated signage planfrom MoTI and the City assisting travelers in both directions on the highway to access thesebusinesses at the HWY 23N intersection, or if they have already turned onto Victoria, to take thethird exit at the roundabout ahead.
The proposed design offers the best solution, given the numerous site constraints andcompeting stakeholder demands. It reflects many years of concept designs, community input,and work with consulting engineers, MoTI staff and stakeholders. The primary objectives ofreducing congestion and improving safety are met with this design, with mitigation measures forthe businesses most impacted by the proposed changes.
Next Steps
City staff and McElhanney recommend that the design progress to the preliminary design phaseto ensure that improvements can be started in the fall of 2016. The preliminary design phase willinclude close consultation with MoTI and the Insurance Corporation of BC on ensuring trafficsafety objectives are being met, and discussing potential funding opportunities. The City willendeavour to ensure safe, legal access to all properties is provided and further stakeholderengagement will take place to ensure issues raised are being mitigated or reduced through thedesign process where possible.
Upon approval to proceed, City staff and McElhanney will produce a timeline of design phases,tender period, and construction, with the aim that a portion of the work would be completed inthe Fall of this year, with the remainder in the Spring of 2017. As a preliminary plan, theroundabout at Victoria and Wright Street would be completed in 2016, while the remainder of
the work on the west side of the railway underpass would be completed in 2017.
McElhanney and staff are working on an interim signage and line marking plan with some minorroad works to reduce the congestion around the properties on the West side of Victoria Road.City staff are planning to arrange traffic control for the summer long weekends in 2016 as hasbeen provided in previous years.
Financial / Risk Implications:
Currently, McElhanney’s Class D cost estimate for the work is $2.1M, which is based only onprevious projects of similar scope. This estimate is significantly higher than staff’s pre-projectestimates, which were used to develop the capital budget. If Council is prepared to proceed withthis design but is cautious about the high cost estimate, it is recommended that decision making
on approval of the design, timing of construction and sources of funding be made when a classB estimate can be produced, based on design drawings that will allow for unit price costs to beestimated, this should be available prior to June 2016.
The 2016 capital plan has $1.2M allocated for this project, funded from DCC’s and specificcontributions from neighbouring developments. The City had submitted a grant applicationunder the Gas Tax Strategic Priorities Fund for $1.2M which was unsuccessful. City staff will
-
8/18/2019 McElhanney Victoria Road traffic plan
4/99
City of Revelstoke Council Report
continue to investigate funding opportunities, including MoTI and ICBC, while finalizing thedesign and construction cost estimate.
The consulting and design project budget for the intersection and current status is as follows.Note also that the due dates and budget costs may change if Council provides direction otherthan the recommendation provided.
Task Due Date Budget Spent %
Background Review Feb-16 $20,954 $18,995 91%Feasibility Study/ Conceptualization Mar-16 $23,846 $21,932 92%Preliminary Design May-16 $55,541 - -Detailed Design Jun-16 $18,773 - -Tender Jul-16 $6,602 - -Construction/Post Constr. Dec-16 $123,791 - -
Completion of the Preliminary Design will fill in many of the details required to adequately firmup the cost estimate, allowing Council to adjust budgets or timeframes as required prior toconstruction. Project phasing can also be considered to spread the costs out over several years.
Attachments:
Victoria/Mutas Intersection Improvement Conceptual Design Brief - McElhanney
Respectfully submitted,
Mike Thomas P.Eng. ENV SP – Director of Engineering and Development
-
8/18/2019 McElhanney Victoria Road traffic plan
5/99
"#$%'()%))
Victoria/Mutas Intersection Improvement
Conceptual Design Brief
Prepared for
Mr. Mike Thomas, P.Eng.Director of Engineering and Development ServicesCity of Revelstoke
Prepared by
McElhanney Consulting Services
710 Laval CrescentKamloops BC V2C 5P3
Contact: Elisa Becker, P.Eng., PMP
Tel: 250-434-9526
Email:[email protected]
April 2016 Rev1
Photo from Columbia Shushwap Regional District
-
8/18/2019 McElhanney Victoria Road traffic plan
6/99
*+,-./+0123-04 56-7/47,-+.6 589/.:7876-
;.6,79-30< =74+>6 ?/+7@
A0>7 B "
C0D
-
8/18/2019 McElhanney Victoria Road traffic plan
7/99
*+,-./+0123-04 56-7/47,-+.6 589/.:7876-
;.6,79-30< =74+>6 ?/+7@
A0>7 B $
%E ?0,J>/.36I
The intersection of Victoria Rd/Bend Rd/Mutas Lp is routinely congested in the summer, confusing to
visitors, and is a safety concern. The congestion at the Victoria/Mutas intersection has previously beenstudied extensively by both the City of Revelstoke (City) and the Ministry of Transportation and
Infrastructure (MOTI). Previous studies and analyses include Revelstoke Comprehensive
Transportation Master Plan (2012), Traffic Contributions for Victoria/Mutas Memo (2012), Revelstoke
Crossing Traffic Review (2010), Mutas-Victoria Improvement Cost Estimate (2010), Mutas and Victoria
Draft Concept Sketches (2015), Mutas Service Road Traffic Study (2005), and Revelstoke Access
Management and Mobility Study (2011). These previous studies and analyses conclude that the root
cause of the congestion at this intersection, is due to allowing full movements at an intersection too
close to the highway. Full movements refers to allowing left turns, right turns, and through movements
at Mutas and Victoria. Traffic modelling has clearly indicated that the left turns and through
movements, at this intersection are the primary cause of the congestion. This congestion creates
extensive delays for the highway commercial business traffic and leads to backed-up traffic on thehighway, causing safety concerns for MOTI.
McElhanney was retained by the City of Revelstoke to confirm the feasibility of a preferred option that
had been previously selected, and move forward with design work.
This concept had a concrete median running the length of Victoria in between the Trans-Canada
Highway (TCH) and the CP crossing to eliminate the left turns and crossing traffic. This scenario
required two roundabouts located at the intersections of Victoria/Wright St and Laforme/Fraser, to
allow access to all businesses. Although this would be very effective in removing the problem
movements, it would require people from downtown Revelstoke that frequent these businesses to have
to cross the TCH, use the roundabout to turn around, and then go back through TCH signal to get back
to town. Similarly, highway traffic would have awkward movements. For example, a skier coming fromthe east who intended to stop at Subway/Tim Hortons/Shell/Super 8, would turn left off the highway,
then have to go through the TCH light twice more before continuing to Revelstoke Mountain Resort.
To address these issues, McElhanney modified the concept to allow left turns out of Frontage/Bend
Rd, and into Mutas. This results in virtually unchanged access for Revelstoke residents, improved
service for Revelstoke-bound tourists and business travel. Highway traffic would find much smoother
access to the highway commercial businesses. This also eliminates the integrated need for the second
roundabout at Laforme/Fraser, making this an optional feature only.
For larger vehicles, accessing Bend Road is difficult, and once the median were built, impossible –
due to the substandard geometry for these vehicles, which constantly damage the signs and other
roadside features. The City indicated the desire to disconnect and shorten Bend Rd due to steep
grades, difficulty maintaining the road, accident history, and that the sani dump may be relocated as
part of a separate project. McElhanney was able to take advantage of this closure by improving the
access concept to the east side businesses.
This input and feedback from MOTI were used to adapt the initial design and create the improvement
configuration presented at the stakeholder engagement meetings held in early March.
-
8/18/2019 McElhanney Victoria Road traffic plan
8/99
*+,-./+0123-04 56-7/47,-+.6 589/.:7876-
;.6,79-30< =74+>6 ?/+7@
A0>7 B #
E K-0J7L.0>7876- K-/0-7>N
The City released conceptual improvement configuration drawings to media outlets several days prior
to hosting two stakeholder meetings on March 2, 2016. The first meeting held was with the Mayor,Council, and business owners located at Victoria/Mutas and included a presentation outlining the
design approach, timing, and conceptual level cost estimates. The second meeting was open to the
Revelstoke community and included display boards and a FAQ, with City staff and McElhanney
engineers available to explain the proposed improvements and answer questions. The City collected
written comments from the community and forwarded them to McElhanney. The written public
comments received are located in Appendix C . For easier review, the comments are typed into a list,
located in Appendix D for reference.
Due to the highly technical nature of the traffic operational analysis, a knowledge of specialized
technical methodologies, traffic standards, laws, and engineering practices is needed. Along with
valuable feedback on the concept presented, it is common to receive design suggestions that do not
meet the technical requirements or transportation planning objectives. McElhanney and the City were
very pleased at the level of community engagement for this project and the amount of feedback
received. McElhanney thoroughly analyzed each of the comments and incorporated as much of the
feedback gathered during the stakeholder engagement process as possible to optimize the intersection
improvement configuration
McElhanney feels it important to respond to as much of the feedback as possible, and has grouped
the most commonly suggested ideas into themes to manage this information. The comments below
are intended to explain the related traffic management issues. We note that many verbal comments
received at the open house simply stated support for the concept presented. We also noted that
several people expressed concern that the City must not allow a few influential stakeholders to have
disproportionate influence in determining the best interests of the Community as a whole.
$E 5-784 O6,
-
8/18/2019 McElhanney Victoria Road traffic plan
9/99
*+,-./+0123-04 56-7/47,-+.6 589/.:7876-
;.6,79-30< =74+>6 ?/+7@
A0>7 B F
4. The highway intersection is operationally optimized; MOTI is not planning to make changes to
the physical intersection, or to the signal operation. The Ministry’s interest in this project is for
the improved safety through eliminating backed-up traffic on the highway.
5. This project scope includes improvements to Victoria Road and related accesses and does
not include ideas outside the scope of this project, such as changes to the CP crossing, grade
concerns at the highway, etc.
6. Having an intersection too close to the TCH is not unique to Revelstoke, and the solutions in
other areas often involve locating traffic movements (“conflict points”) further from the highway
to improve stacking distances, which is key to successful improvements in this location.
7. The City was looking to relocate the sani dump independently from this project.
8. Bend Rd has experienced safety and maintenance problems so the City would like it removed
as part of this project.
E ;.8876-4 P+-L K+>6+@+,06- 2QC5 56:.
-
8/18/2019 McElhanney Victoria Road traffic plan
10/99
*+,-./+0123-04 56-7/47,-+.6 589/.:7876-
;.6,79-30< =74+>6 ?/+7@
A0>7 B R
MOTI does not have plans to move the highway in the location of TCH and Victoria. Historic
drawings showing the TCH moved from its current location at the Victoria Rd intersection are
not up-to-date nor part of MOTI’s current plan.
5. Roundabout at Mutas intersection.
A roundabout located at the Victoria/Mutas intersection would be substandard in several ways.
It would be too close to the highway and would provide insufficient stacking distance, resulting
in similar issues (although eased somewhat) to the current situation. Specifically, a red signal
for Victoria NB at the highway would cause backups into the roundabout which could quickly
back up all the way around and into the SB lanes – similar to the current problem. A multi-lane
roundabout would partially resolve this issue, but the increase in size from one to two-lane
roundabouts is substantial and this would not fit in the space available.
A signal at Mutas would have a similar outcome, and is rejected in principle since it would
create forced traffic stacking back onto the TCH.
6. Traffic signal for NB Victoria only.
The purpose of this suggestion is to stop traffic from travelling NB on Victoria before it reaches
Mutas, somewhere north of the CP underpass, to make gaps in NB traff ic for the left turns into
the eastside businesses, and thereby allow the SB backups to clear.
For a traffic signal to be visible past the CP underpass, it would be located near Mutas. With
a red signal stopping NB Victoria traffic, there would be nothing to indicate to SB Victoria
drivers that they have protected turning movements. All they would see is opposing traffic
stopped with no indication of why they are stopped or when they would begin driving again.
For this reason, a second light facing SB Victoria traffic would be required to indicate a green
light allowing the left turn onto Frontage/Bend Rd. This second light would also require a
yellow and red phase to allow NB Victoria traffic to travel into or past the Mutas intersection.
This creates a red light condition for SB Victoria traffic, which is rejected in principle by MOTI.
Not only is this rejected by MOTI, but it is not sound engineering and creates additional
problems instead of solving the root cause of the congestion.
It may be suggested to signalize only the left turn from SB Victoria to Frontage/Bend Rd to
account for this, but leave a constant green through signal for SB traffic. However, this would
require a physical separation of the two lanes which would be confusing if it were feasible to
build, which it is not due to the distance constraints. Further, this retains the left turns stacking
back toward the highway.
Another suggestion may be to signalize the Victoria/Wright St intersection, in order to createthe desired traffic gaps in NB Victoria traffic. This also does not solve the problem, as it does
not affect the cause of the problems, which is traffic that would not be found at this intersection
– NB traffic from town is not a high volume, it just backs up at peak times due to the gridlock
at the Mutas intersection.
Coordinating the signal timings is also problematic because the highway, being the primary
route has much longer green time than the side street – Victoria. The left turn off the highway
(long green phase) would require equally long red time for NB Victoria, which would also have
-
8/18/2019 McElhanney Victoria Road traffic plan
11/99
*+,-./+0123-04 56-7/47,-+.6 589/.:7876-
;.6,79-30< =74+>6 ?/+7@
A0>7 B '
to apply to the Mutas loop and left turns to access SB Victoria. In other words, the left turn into
the eastside businesses would receive priority at the same level as the highway green time,
to the exclusion of all other movements, which would exacerbate things for all other traffic.
Furthermore, the signals at the TCH/Victoria and TCH/Hwy 23 intersections are already
coordinated, so adding an additional signal would require a more sophisticated, costly system
with central management.
FE ;.8876-4 P+-L.3- K+>6+@+,06- 2QC5 56:.
-
8/18/2019 McElhanney Victoria Road traffic plan
12/99
*+,-./+0123-04 56-7/47,-+.6 589/.:7876-
;.6,79-30< =74+>6 ?/+7@
A0>7 B (
Need pedestrian accommodation from TCH to Tim Hortons; consider pedestrian and cyclist
safety.
This is included in the updated configuration.
Regarding the roundabout, Revelstoke receives a lot of snow.
This was a frequent comment and is addressed in a separate section below.
Drivers ignore signs.
This was a frequent comment related to “one way,” “do not enter” and roundabout signs. One
way and do not enter signs are in widespread use in Canada; Revelstoke will not be unique
with these signs and thus this shouldn’t be a concern. Furthermore, for traffic unfamiliar with
a roundabout ahead sign, it is irrelevant as traffic will have to move toward the roundabout.
So, whether or not they ignore the sign, they will have to drive through the roundabout to return
to the TCH.
Drivers can’t see the roundabout so they will choose to stop at the businesses on the west
side of Victoria instead of the east side.
The CP rail underpass blocks immediate view of the proposed Wright Street roundabout.
When drivers enter Victoria Rd and see they can’t turn left to enter the eastside businesses,
given the tight configuration they will have no time to change their minds and turn right into the
businesses on the west side. Customers desiring the east side businesses will have to
proceed to the roundabout to return to the highway, and will find their planned stop easily
accessible on the right.
A positive outcome of the roundabout located beyond the CP rail crossing is it creates a new,
significant opportunity for visitors to see Revelstoke beyond the businesses on the highway.
Grades are too steep at Wright St for a roundabout.
The roundabout grades can be designed within acceptable design standards at this location.
Improve existing blind corners.
The detailed design will incorporate this.
The CP crossing clearance is low.
The CP crossing is 4.42m on Victoria Rd. East of Revelstoke on the TCH the clearance is
4.3m. Logging trucks are known to exceed the 4.42m CP crossing height occasionally, striking
the bridge and losing loads. For this reason, the City is evaluating a traffic bylaw to restrict
over height loads.
We understand that highway trucks are routed onto Victoria and through this location in the
event of highway closures due to avalanches, collisions, etc.
Large vehicles and mill pole trucks need to drive through the roundabout.
-
8/18/2019 McElhanney Victoria Road traffic plan
13/99
*+,-./+0123-04 56-7/47,-+.6 589/.:7876-
;.6,79-30< =74+>6 ?/+7@
A0>7 B G
The intersection improvements, including the roundabout, are designed to accommodate a
WB-20 vehicle. We have contacted the mill to determine their largest vehicle, which is a 60’
Canadian Super B Flat Deck. The WB-20 is the governing vehicle in this case – the WB-20
requires a larger area to maneuver than the mill’s largest vehicle; therefore, the current
improvement configuration accommodates mill truck traffic.
RE K6.P S78.:0<
One of the items the public commented on both in writing and verbally during the open house, was the
ability for the City’s road maintenance crews to effectively remove snow in roundabouts. McElhanney
included in the FAQ a statement that many snowy areas in Canada and America have roundabouts
and are able to maintain them during the winter. It appeared during the stakeholder engagement
process that the public wanted more specific information in order to be confident in the snow removal
process.
McElhanney contacted over a dozen municipalities and provincial/state transportation officials inCanada and America that have roundabouts and are located in snowy areas. We asked them two
simple questions, “Are you able to effectively remove the snow in the roundabouts located at __?” and,
“Any other comments on snow removal in roundabouts?” We were surprised at the overwhelming
number of responses received from our inquiries. The majority of responses confirmed roundabout
snow removal is as easy as or easier than a traditional intersection. America has more examples of
roundabouts in snowy areas, so many of the responses are from American transportation and public
works officials. However, we contacted as many officials from roundabouts located in comparable
snowy areas in Canada as were known and available. For comparison, Revelstoke receives an
average annual snowfall of 355cm based on 13 years of data available on the City’s site.
The following are direct quotes from the officials we contacted:
“We have had similar concerns over roundabouts since we began to implement them through
Jefferson County about a decade ago. Our plow drivers were convinced that concrete curbs
and islands would routinely be destroyed by plowing efforts. Drivers were also concerned
about the intersection being clogged with snow and the difficulty of clearing snow from the
roundabouts. In all actuality, my drivers spend far less time with a roundabout than a
conventional intersection. After years of service, we have not lost any significant concrete due
to plowing efforts. Our engineers have done a great job in designing our roundabouts to calm
traffic while still allowing larger vehicles to navigate around them.” – Andy Rohwer, Senior
Supervisor Jefferson County Colorado Road and Bridge District 3, Evergreen, Colorado
(annual snowfall 346 cm).
“The Michigan Department of Transportation's Superior Region has one modern roundabout
on the state trunkline in Marquette, constructed in 2010, and another planned to begin
construction this spring in nearby Ishpeming. Both of these sites are in the Lake Superior's
lake effect snow belt and get plenty of precipitation every winter -- the average snowfall in
Marquette County is around 4.5 meters. A testimonial from Marquette's Director of Planning
and Community Development, Dennis Stachewicz Jr., probably sums up best how the winter
plowing concerns raised by an initially skeptical public have not been borne out in an article
for "The Bridge" magazine http://michiganltap.org/sites/ltap/files/publications/bridge/Bridge27-
-
8/18/2019 McElhanney Victoria Road traffic plan
14/99
*+,-./+0123-04 56-7/47,-+.6 589/.:7876-
;.6,79-30< =74+>6 ?/+7@
A0>7 B %)
4.pdf Stachewicz said there have been “no problems with snow removal. In fact it might be
better than before. The snow plow guys are pretty happy.” According to the Frequently Asked
Questions on our MDOT website, there is some initial adjustment in procedures for snowplow
crews, but roundabouts generally present no major problems for snow removal. In Wisconsin,
for example, one truck will start on the truck apron and plow around the roundabout to the
outside, while another truck will plow each entry and exit, pushing the snow to the outside.
Roundabouts make it easier to turn snowplows as well.” – Daniel Weingarten,
Communications Representative, Ishpemig, Michigan (roundabout location annual snowfall
450 cm).
“Typically the roundabouts are easier to plow then arterial intersections with turn lanes, since
the plow operator can traverse it multiple times until cleared. Intersections with turn lanes
often involve backtracking to plow. We have had issues with the splitter islands being hit by
snowplows, requiring expensive repairs. These minor issues with deicing and snow removal
are more than made up for by the efficiency and safety of our roundabouts. We’ve had a
combined 30 years of experience with our 3 roundabouts and have yet to have an injury
accident.” – Alex Ariniello, Public Works and Utilities Director, Superior, Colorado (annualsnowfall 165 cm).
“We have not one bit of problem clearing the snow, even with larger snowfalls. The roundabout
has never been closed due to snow.” – Casey Coleman, Public Works, Park City, Utah (annual
snowfall 1,044 cm).
“For snow removal we take it out of the centre and move out and use a big blower for large,
quick snowfall events. In 6 years we have had no issues once we got our technique down.”
Victor Anello, Public Works, Northbay, Ontario (annual snowfall 300 cm).
“The City of Batavia has one single lane roundabout that was constructed in 2009 at the
intersection of NYS Rt. 33 and NYS Rt. 98. I am sure we heard similar concerns as you arecurrently fielding from both the public and staff. Plowing was one of those concerns. We
have not had any issues when it comes to plowing. The expected learning curve was pretty
much non-existent. The drivers picked up the plowing of a circle right the first time through.
We did not have to get any special equipment and used the equipment we currently had in
stock, we did not have to make a special assignment for the roundabout either. We really
appreciate the roundabout. It moves more traffic and reduces congestion. It has eliminated
all T-Bone accidents where this was considered a dangerous intersection prior to the
roundabouts installation. It will take the public sometime to get used to it but most catch on
quick.” – Raymond Tourt, Superintendent of Maintenance, Batavia, New York (annual snowfall
360 cm).
“The City of Steamboat Springs currently has two roundabouts. We do not remove any snow
from the center islands as they are landscaped. All of the snow is plowed away from the center
to the outsides. To answer your question, we are able to effectively plow these. The biggest
issue we have is drainage. Our roundabouts shed the water across the drive lanes which
causes icing issues and premature asphalt failure.” – David Van Winkle, Street
Superintendent, Steamboat Springs, Colorado (annual snowfall 413 cm).
-
8/18/2019 McElhanney Victoria Road traffic plan
15/99
*+,-./+0123-04 56-7/47,-+.6 589/.:7876-
;.6,79-30< =74+>6 ?/+7@
A0>7 B %%
“We have been snow clearing this roundabout for 2-3 years now with no issues. However it
should be noted that the center island has concrete curb and gutter around the entire
circumference which is “mountable” style that allows our snow clearing equipment to go onto
the island while removing snow from the street.” – Jason Phillips, Manager of Roads Division,
St. John’s, Newfoundland (annual snowfall 322 cm).
“Snowplowing was an initial concern with plowing crews when roundabouts were first
constructed. However, plowing snow at a roundabout has generally been a non-issue for
Wisconsin snow removal crews. I have included testimonial in the video found from WisDOT’s
website. Look for the 11:10 video at juncture 7:42 to 8:05
http://wisconsindot.gov/Pages/safety/safety-eng/roundabouts/works.aspx ” – Paul Vraney,
Roadway Design Standards Engineer, Madison, Wisconsin (annual snowfall up to 425 cm).
“Snow removal is really not an issue. We had a couple complaints the first year as we learned
what frequency was needed.” – Dan Werner, Public Works, Middlebury, Vermont (roundabout
location annual snowfall 295 cm).
“Il n’y a aucun problème à enlever la neige. L’équipement utilisé est assé large pour déneiger
le rond-point en un passage. De plus, l’utilisation du sel de voirie fait en sorte que la neige
fond très rapidement. Je vous recommande fortement l’utilisation des ronds-points afin de
faciliter la circulation automobile.” Translation: “There is no problem to remove snow. The
equipment used is large enough to plow the roundabout in one pass. In addition, the use of
road salt causes the snow to melt very quickly. I strongly recommend the use of roundabouts
to facilitate traffic.” – Steeve Seguin, Chef de division voirie et signalization [Head of Highways
and signaling division], Saguenay, Quebec (annual snowfall 342 cm).
We are confident the information on snow removal contained in this memo is sufficient to educate and
reassure the public that effective snow removal in roundabouts is occurring in snowy areas in North
America; and that the City of Revelstoke’s road maintenance crew will be as effective as any of thecrews mentioned above.
'E C/0@@+, 2.I7
-
8/18/2019 McElhanney Victoria Road traffic plan
16/99
*+,-./+0123-04 56-7/47,-+.6 589/.:7876-
;.6,79-30< =74+>6 ?/+7@
A0>7 B %"
The LOS for the existing Victoria/Mutas intersection according to traffic modelling is an E during the
peak hour, peak day. The traffic modelling for the proposed design indicates a significant improvement
to a LOS of B.
It should be noted that until drivers become accustomed to the new traffic pattern and roundabout,
queues longer than those modeled can occur, but even if minor stacking occurs initially, the proposeddesign will significantly reduce congestion and traffic queues at Victoria/Mutas.
The traffic modelling results are in Appendix B.
(E K34-0+60D+
McElhanney reviewed the Envision Rating system as required for the project and rated this proposed
improvement configuration, focusing on the Quality of Life section. While the City doesn’t intend to
seek certified Envision Rating for this project, we will refer to the ranking system for relevant
performance objectives to support decisions throughout the design and construction phases of work,contributing to triple-bottom-line sustainability. The Quality of Life Envision Rating Table is shown
below and the full points table is included in Appendix E along with a discussion of performance
objectives.
The proposed improvement configuration achieves high rating on the Envision Rating Table,
particularly with regard to the following:
Reduces congestion and increases traffic mobility.
Increases pedestrian and cycling safety.
Reduces greenhouse gas emissions since roundabout are documented to reduce GHGs by
33% compared to traditional intersections.
Converting a traditional intersection into a roundabout has been proven to reduce the severityof collisions, and will therefore enhance public safety.
Includes community stakeholder involvement.
Improves stormwater management and climate change adaption by converting unnecessary
impervious road segments to permeable landscaped areas.
Preserves local character through landscape features and drawing visitors further into town.
The full Envision Rating discussion, including additional Envision areas are included in Appendix E .
-
8/18/2019 McElhanney Victoria Road traffic plan
17/99
*+,-./+0123-04 56-7/47,-+.6 589/.:7876-
;.6,79-30< =74+>6 ?/+7@
A0>7 B %$
GE S7,.8876I0-+.64 @./ =74+>6
The recommended improvement configuration is shown in Appendix A. McElhanney incorporated the
valuable feedback gathered during the stakeholder engagement process to optimize the intersectionimprovement configuration, including improved connectivity with the Frontage Rd, accommodation for
large trucks and RVs to turn out of Frontage Rd, a sidewalk for pedestrians crossing from TCH to the
eastside businesses, concrete median restricting turning movements near the CP rail crossing, small
area of large vehicle parking on the Frontage Rd similar to Woodenhead Lp, and deferral of the
potential future roundabout at Fraser Dr. Truck turning templates are located in Appendix A also,
showing the turning movements of a large fuel truck and WB-20 able to make similar movements they
make currently.
We understand the businesses located on the eastside of Victoria are concerned about business
impacts. A mitigation measure may be to work with MOTI to add signage on the highway east of the
Hwy 23 intersection. The signage could have the businesses listed (Shell, Tim Hortons, Subway, and
Super 8) directing traffic to take the “next left” at the Hwy 23 intersection. This would serve two
purposes: mitigate potential impacts to the businesses and reduce vehicular volume at the Victoria Rd
intersection. The recommended improvements would retain their access from Victoria regardless.
Regarding accesses, the Super 8 Motel presently uses Tim Hortons’/Shell’s driveway for access. The
recommended improvement configuration maintains the access in the same location. It is assumed
Super 8 has an access agreement with Tim Hortons/Shell to use the driveway located on Tim
Hortons’/Shell’s property. Should an access within Super 8’s property boundary be necessary in the
future, an access can be added from Bend Rd at the end of the proposed cul-de-sac.
Pedestrian accommodation from TCH to the Tim Hortons/Shell parking lot is shown on the
recommended improvement configuration. There were a number of constraints that guided thepedestrian crossing to its location shown, primarily related to the location of the current TCH crosswalk
and the location of the parking lot driveway. The existing TCH crossing aligns with the middle of the
driveway, so currently pedestrians are directed toward the middle of the driveway, with multiple
directions of traffic to consider. Grades become a challenge further away from both sides of the
driveway, so the pedestrian crossing needs to be very close to the driveway. Although non-
perpendicular crossings are generally avoided in transportation engineering, this is a case of trying to
direct pedestrians to the safest crossing location. When snow covers the zebra line painting, the
physical barriers will direct pedestrians to cross in the proposed location. The type of physical barrier
that allows for snow clearing, and fine tuning of details will occur in the next phase of design.
This proposed configuration incorporates years of previous work on this intersection as well as current
stakeholder feedback, and meets the City of Revelstoke’s primary objectives of reducing congestion
and improving safety. For these reasons, McElhanney recommends proceeding with the current
improvement configuration.
-
8/18/2019 McElhanney Victoria Road traffic plan
18/99
*+,-./+0123-04 56-7/47,-+.6 589/.:7876-
;.6,79-30< =74+>6 ?/+7@
A0>7 B %#
%)E ;.64-/3,-+.6 K7T376,+6>
For sequencing, the roundabout must be complete first, since it is necessary once the medians are in
place on Victoria. Based on the expected timing of Council approval for the proposed improvementconfiguration, we recommend the construction be done in two phases in order for the full intersection
improvements to be complete in time for summer 2017. Phase 1 construction includes the roundabout
and temporary lane changes on Woodenhead proposed by the City. The temporary lane changes are
shown on the sketch located in Appendix F , and comprise exchanging existing parking with temporary
additional lanes. The purpose is to ease traffic flow and provide additional vehicle storage on
Woodenhead until the full intersection improvement configuration is constructed. The temporary lane
changes will help mitigate impacts from the additional Petro-Canada and Starbucks traffic. Phase 2
construction includes the remaining Victoria, Woodenhead Lp, Bend Rd, and Frontage Rd
construction. Phase 1 construction (roundabout and interim lane changes) is planned to be completed
by October 31, 2016. Phase 2 construction is planned for early in the 2017 construction season, so
the full improvements will be in place prior to heavier summertime traffic volumes. Due to constructiontimeframes and avoiding construction at Victoria/Mutas during peak summer times, unless the
roundabout is constructed in 2016, it is unlikely the full intersection improvements will be complete until
end of the construction season in 2017, causing congestion and safety issues to remain for the next
two summers.
We have assessed the risk for only completing part of the roundabout construction before the winter
snowfall ends the construction season. The risk is directly related to schedule, so we have created a
fast-tracked Phase 1 schedule with 3-4 weeks of float during design and construction as a contingency
measure. Obtaining approval by May 2 is critical to completing Phase 1 construction this year. The
following schedule is intended to mitigate the risk associated with completing only a portion of the
roundabout.
City approval for roundabout May 2
Roundabout tender ready June 20
Tender start July 4
Tender close July 25
Commence construction August 1
Construction complete October 31
There are a number of advantages with completing the roundabout this year. It allows drivers to
become accustomed to the roundabout prior to the medians being installed. The Victoria/Wright St
intersection has comparatively low volumes, so construction can take place in late summer, and there
is sufficient room for detours around the construction site.
-
8/18/2019 McElhanney Victoria Road traffic plan
19/99
*+,-./+0123-04 56-7/47,-+.6 589/.:7876-
;.6,79-30< =74+>6 ?/+7@
A0>7 B %F
%%E U7V- K-794
McElhanney recommends information from the contents of this memo be circulated to the public in
response to the stakeholder feedback received. In addition, much work has been done already inareas with roundabouts to educate the public. Of the many videos and online tutorials on roundabout
usage we recommend the following video http://wisconsindot.gov/Pages/safety/safety-
eng/roundabouts/works.aspx provided by the Wisconsin Department of Transportation, due to its
comprehensive coverage on roundabout safety, design, large truck traffic, snow plowing, and public
perception.
The intersection improvement configuration has not changed significantly since the previous Class D
cost estimate was in the range of $2.1M. Once the proposed configuration is approved, McElhanney
will prepare a detailed Class B cost estimate during preliminary design to assist in meeting funding
requirements.
McElhanney recommends the proposed intersection improvement configuration be approved byCouncil and that preliminary design commences. To meet the City’s goal to begin construction on the
improvements this year will require prompt forward movement by all parties involved in this project.
-
8/18/2019 McElhanney Victoria Road traffic plan
20/99
-
8/18/2019 McElhanney Victoria Road traffic plan
21/99
-
8/18/2019 McElhanney Victoria Road traffic plan
22/99
-
8/18/2019 McElhanney Victoria Road traffic plan
23/99
-
8/18/2019 McElhanney Victoria Road traffic plan
24/99
*+,-./+0123-04 56-7/47,-+.6 589/.:7876-
;.6,79-30< =74+>6 ?/+7@
A0>7 B %'
H9976I+V ?
C/0@@+, 2.I7
-
8/18/2019 McElhanney Victoria Road traffic plan
25/99
Vissim Intersection Level of Service Report
Intersection #: 2
Average % Average LOS
Right 128 89 69.5% 70.1
Through 795 551 69.3% 110.7
Left 329 225 68.4% 348.8
B Subtotal 1,252 865 69.1% 168.4 F 11.9
Right 380 367 96.6% 5.2
Through 134 129 96.3% 35.0
Left 221 207 93.7% 35.1
B Subtotal 735 703 95.6% 19.5 B 1.2
Right 125 122 97.6% 5.2
Through 925 920 99.5% 19.7
Left 220 216 98.2% 45.3
B Subtotal 1,270 1,258 99.1% 22.7 C 0.3Right 130 128 98.5% 6.6
Through 206 207 100.5% 48.8
Left 43 43 100.0% 36.0
B Subtotal 379 378 99.7% 33.0 C 0.1
3,636 3,204 88.1% 62.6 E 7.4
TYPE:
Intersection #: 3
Average % Average LOS
Right 153 152 99.3% 2.4
Through 11 12 109.1% 4.7Left 24 22 91.7% 13.8
B Subtotal 188 186 98.9% 3.9 A 0.1
Right 65 65 100.0% 1.2
Through 402 396 98.5% 2.8
Left 38 39 102.6% 3.2
B Subtotal 505 500 99.0% 2.6 A 0.2
Right 57 51 89.5% 192.9
Through 21 18 85.7% 195.8
Left 180 155 86.1% 261.7
B Subtotal 258 224 86.8% 240.7 F 2.2
Right 176 146 83.0% 0.7
Through 318 268 84.3% 2.3
Left 166 143 86.1% 5.9
B Subtotal 660 557 84.4% 2.8 A 4.2
1,611 1,467 91.1% 39.2 E 3.7
TYPE:
Existing Peak Summer Mutas Intersection Design - Revelstoke, BC
Standard Deviation
Hwy 1
(B)
Victoria Rd
(B)
Standard Deviation 6.4SSSC
Victoria Rd
(B)
Hwy 1
(B)
Laforme Blvd
(B)
Total Intersection
Bend Rd (B)
Victoria Rd
(B)
Volume Served Total Delay (sec/veh)Direction Movement
Direction Movement
Volume Served Total Delay (sec/veh)
3.9
Total Intersection
Mutas Loop
(B)
Signal
DemandVolume
Demand
Volume
Hwy 1 / Laforme Blvd-Victoria Rd
Bend Rd-Mutas Loop / Victoria Rd
GEH
GEH
3/18/2016
-
8/18/2019 McElhanney Victoria Road traffic plan
26/99
Vissim Intersection Level of Service Report
Intersection #: 4
Average % Average LOS
Right
Through
Left
SB Subtotal
Right
Through 455 448 98.5% 0.2
Left 62 69 111.3% 1.5
B Subtotal 517 517 100.0% 0.3 A 0.0
Right 46 44 95.7% 1.9
Through
Left 50 51 102.0% 4.1
B Subtotal 96 95 99.0% 3.1 A 0.1
Right 40 35 87.5% 0.5
Through 359 306 85.2% 0.1
Left
Subtotal 399 341 85.5% 0.2 A 3.0
1,012 953 94.2% 0.6 A 1.9
TYPE:
Intersection #: 5
Average % Average LOS
Right
Through
Left
SB Subtotal
Right
Through
Left 19 19 100.0% 23.7
B Subtotal 19 19 100.0% 23.7 C 0.0
Right 126 113 89.7% -0.2
Through
Left 126 114 90.5% 0.1
B Subtotal 252 227 90.1% 0.0 A 1.6
Right 169 168 99.4% 10.2
Through
Left
B Subtotal 169 168 99.4% 10.2 B 0.1
440 414 94.1% 5.2 A 1.3
TYPE:
Mutas Intersection Design - Revelstoke, BC Existing Peak Summer
GEH
Direction Movement GEH
Demand
Volume
Demand
Volume
0.1
Total Delay (sec/veh)
Bend Rd
(B)
Mutas Loop
(B)
Frontage Rd
(B)
Total Intersection
Victoria Rd
(B)
Total Intersection
Volume Served
SSSC
1.5
Standard Deviation
SSSC Standard Deviation
Volume Served
Total Delay (sec/veh)
Victoria Rd
(B)
Direction Movement
Wright St
(B)
Wright St / Victoria Rd
Mutas Loop / Frontage Rd-Bend Rd
3/18/2016
-
8/18/2019 McElhanney Victoria Road traffic plan
27/99
Vissim Intersection Level of Service Report
Intersection #: 6
Average % Average LOS
Right 213 82 38.5% 514.1
Through 34 14 41.2% 270.0
Left 62 24 38.7% 251.2
SB Subtotal 309 120 38.8% 433.0 F 12.9
Right 66 55 83.3% 73.0
Through 999 763 76.4% 228.9
Left 33 27 81.8% 70.8
WB Subtotal 1,098 845 77.0% 213.7 F 8.1
Right 269 272 101.1% 5.7
Through 55 55 100.0% 36.6
Left 40 40 100.0% 156.3
NB Subtotal 364 367 100.8% 26.8 C 0.2
Right 36 124 344.4% 2.4
Through 1,193 1,056 88.5% 7.8
Left 119 152 127.7% 27.2
EB Subtotal 1,348 1,332 98.8% 9.5 A 0.4
3,119 2,664 85.4% 95.8 F 8.5
TYPE:
GEH
Existing Peak Summer
16.7
Total Intersection
Route 23N
(SB)
Hwy 1
(WB)
Bend Rd
(NB)
Hwy 1
(EB)
Standard Deviation
Direction
Mutas Intersection Design - Revelstoke, BC
Demand
VolumeMovement
Volume Served Total Delay (sec/veh)
Signal
Route 23N-Bend Rd / Hwy 1
3/18/2016
-
8/18/2019 McElhanney Victoria Road traffic plan
28/99
Vissim Intersection Level of Service Report
Intersection #: 2
Average % Average LOS
Right 128 90 70.3% 69.8
Through 795 569 71.6% 110.4
Left 329 226 68.7% 353.3
B Subtotal 1,252 885 70.7% 168.3 F 11.2
Right 380 379 99.7% 5.8
Through 134 137 102.2% 34.3
Left 221 217 98.2% 34.9
B Subtotal 735 733 99.7% 19.7 B 0.1
Right 125 126 100.8% 6.5
Through 925 918 99.2% 21.4
Left 220 217 98.6% 50.8
B Subtotal 1,270 1,261 99.3% 25.0 C 0.3Right 130 132 101.5% 7.1
Through 206 205 99.5% 46.8
Left 43 42 97.7% 35.4
B Subtotal 379 379 100.0% 31.7 C 0.0
3,636 3,258 89.6% 63.5 E 6.4
TYPE:
Intersection #: 3
Average % Average LOS
Right 153 155 101.3% 28.1
ThroughLeft 35 32 91.4% 42.7
B Subtotal 188 187 99.5% 30.6 D 0.1
Right 252 223 88.5% 0.7
Through 582 577 99.1% 4.2
Left 49 50 102.0% 4.7
B Subtotal 883 850 96.3% 3.3 A 1.1
Right 258 259 100.4% 29.0
Through
Left
B Subtotal 258 259 100.4% 29.0 D 0.1
Right 176 145 82.4% 0.6
Through 484 415 85.7% 7.3
Left
B Subtotal 660 560 84.8% 5.5 A 4.0
1,989 1,856 93.3% 10.3 B 3.0
TYPE:
Preferred Plan Peak Summer Mutas Intersection Design - Revelstoke, BC
Standard Deviation
Hwy 1
(B)
Victoria Rd
(B)
Standard Deviation 4.0 SSSC
Victoria Rd
(B)
Hwy 1
(B)
Laforme Blvd
(B)
Total Intersection
Rd (B)
Victoria Rd
(B)
Volume Served Total Delay (sec/veh)Direction Movement
Direction Movement
Volume Served Total Delay (sec/veh)
5.3
Total Intersection
Mutas Loop
(B)
Signal
DemandVolume
Demand
Volume
Hwy 1 / Laforme Blvd-Victoria Rd
Rd-Mutas Loop / Victoria Rd
GEH
GEH
3/21/2016
-
8/18/2019 McElhanney Victoria Road traffic plan
29/99
Vissim Intersection Level of Service Report
Intersection #: 4
Average % Average LOS
Right
Through
Left
SB Subtotal
Right
Through 455 447 98.2% 21.6
Left 62 68 109.7% 22.1
B Subtotal 517 515 99.6% 21.7 C 0.1
Right 46 46 100.0% 5.8
Through
Left 50 49 98.0% 5.9
B Subtotal 96 95 99.0% 5.8 A 0.1
Right 40 34 85.0% 17.4
Through 359 320 89.1% 16.9
378 353 93.4% 16.9
B Subtotal 777 707 91.0% 16.9 C 2.6
1,390 1,317 94.7% 18.0 C 2.0
TYPE:
Intersection #: 6
Average % Average LOS
Right 213 87 40.8% 491.5
Through 34 14 41.2% 232.3
Left 62 25 40.3% 259.3
SB Subtotal 309 126 40.8% 416.6 F 12.4
Right 66 55 83.3% 79.6
Through 999 774 77.5% 233.5
Left 33 25 75.8% 73.2
WB Subtotal 1,098 854 77.8% 218.9 F 7.8
Right 269 269 100.0% 6.0
Through 55 56 101.8% 36.2
Left 40 40 100.0% 157.3
NB Subtotal 364 365 100.3% 27.2 C 0.1
Right 36 128 355.6% 2.1
Through 1,193 1,062 89.0% 7.4
Left 119 155 130.3% 26.8
EB Subtotal 1,348 1,345 99.8% 9.1 A 0.1
3,119 2,690 86.2% 97.2 F 8.0
TYPE:
Mutas Intersection Design - Revelstoke, BC Preferred Plan Peak Summer
GEH
Direction Movement GEH
Demand
Volume
Demand
Volume
3.1
Total Delay (sec/veh)
Hwy 1
(WB)
Bend Rd
(NB)
Hwy 1
(EB)
Total Intersection
Victoria Rd
(B)
Total Intersection
Volume Served
Roundabout
11.7
Standard Deviation
Signal Standard Deviation
Volume Served
Total Delay (sec/veh)
Victoria Rd
(B)
Direction Movement
Route 23N
(SB)
Wright St
(B)
Wright St / Victoria Rd
Route 23N-Bend Rd / Hwy 1
3/21/2016
-
8/18/2019 McElhanney Victoria Road traffic plan
30/99
Vissim Intersection Queue Length Report
Intersection #: 2
Average StDev Max StDev
Right 90 0 0 30 9
Through 400 170 142 415 98
Left 105 410 14 450 0
Right 55 5 1 95 13
Through 55 20 2 115 13
Left 55 20 2 115 13
Right 100 0 2 40 98
Through 350 15 1 120 81
Left 100 20 6 140 114
Right 50 0 0 25 9Through 125 20 5 105 22
Left 45 5 0 30 10
Mutas Intersection Design - Revelstoke, BC Existing Peak Summer
Hwy 1 / Laforme Blvd-Victoria Rd
Queue Length (m)
Hwy 1
(B)
Victoria Rd
(B)
Direction MovementQueue
Storage
Hwy 1
(B)
Laforme Blvd (B)
3/18/2016
Intersection #: 3
Average StDev Max StDev
Right
Through 5 5 1 35 3
Left
RightThrough
Left 20 0000
Right
Through 0 140 43 200 3
Left 25 160 25 205 3
Right
Through 55 200 326 350 404
Left
Queue Length (m)
Bend Rd
(B)
Direction Movement
Queue
Storage
Bend Rd-Mutas Loop / Victoria Rd
Victoria Rd
(B)
Mutas Loop
(B)
Victoria Rd
(B)
-
8/18/2019 McElhanney Victoria Road traffic plan
31/99
Vissim Intersection Queue Length Report
Intersection #: 4
Average StDev Max StDev
Right
Through
Left
Right
Through
Left 20 0 0 10 8
Right
Through
Left 80 0 0 20 4
Right 75 0 0 5 5Through
Left
Intersection #: 5
Average StDev Max StDev
Right
Through
Left
Right
Through 115 0 0 15 4
Left
Right
Through
Left
Right
Through 75 5 1 65 15
Left
Mutas Intersection Design - Revelstoke, BC Existing Peak Summer
Bend Rd (B)
Mutas Loop
(B)
Frontage Rd
(B)
Victoria Rd (B)
Direction
MovementQueue
StorageQueue Length (m)
Victoria Rd
(B)
Wright St
(B)
Direction
Wright St / Victoria Rd
Mutas Loop / Frontage Rd-Bend Rd
Movement
Queue
Storage
Queue Length (m)
3/18/2016
-
8/18/2019 McElhanney Victoria Road traffic plan
32/99
Vissim Intersection Queue Length Report
Intersection #: 6
Average StDev Max StDev
Right 50 110 9 135 5
Through 125 60 33 120 29
Left
Right 75 0 0 25 9
Through 380 255 33 410 3
Left 85 0 0 20 8
Right 45 0 0 50 10
Through 100 5 1 70 19
Left
Right 35 0 0 15 9Through 400 5 2 130 28
Left 65 5 2 50 16
Mutas Intersection Design - Revelstoke, BC Existing Peak Summer
Route 23N
(SB)
Hwy 1
(WB)
Bend Rd
(NB)
Hwy 1 (EB)
Route 23N-Bend Rd / Hwy 1
QueueStorage
Queue Length (m)Direction Movement
3/18/2016
-
8/18/2019 McElhanney Victoria Road traffic plan
33/99
Vissim Intersection Queue Length Report
Intersection #: 2
Average StDev Max StDev
Right 90 0 0 30 11
Through 400 160 118 425 98
Left 105 410 11 450 2
Right 55 5 1 120 36
Through 55 20 3 140 28
Left 55 20 3 140 28
Right 100 5 8 140 163
Through 350 15 1 110 17
Left 100 25 13 245 205
Right 50 0 0 25 7Through 125 20 5 100 23
Left 45 5 0 30 7
Mutas Intersection Design - Revelstoke, BC Preferred Plan Peak Summer
Hwy 1 / Laforme Blvd-Victoria Rd
Queue Length (m)
Hwy 1
(B)
Victoria Rd
(B)
Direction MovementQueue
Storage
Hwy 1
(B)
Laforme Blvd (B)
3/21/2016
Intersection #: 3
Average StDev Max StDev
Right
Through 95 15 6 100 10
Left
RightThrough
Left 20 00 0 2
Right 200 15 10 135 47
Through
Left
Right
Through
Left
Queue Length (m)
Rd
(B)
Direction Movement
Queue
Storage
Rd-Mutas Loop / Victoria Rd
Victoria Rd
(B)
Mutas Loop
(B)
Victoria Rd
(B)
-
8/18/2019 McElhanney Victoria Road traffic plan
34/99
Vissim Intersection Queue Length Report
Intersection #: 4
Average StDev Max StDev
Right
Through
Left
Right
Through 200 25 6 170 33
Left
Right
Through 65 0 0 25 7
Left
RightThrough 155 45 20 245 33
Left
Mutas Intersection Design - Revelstoke, BC Preferred Plan Peak Summer
Victoria Rd (B)
MovementQueue
StorageQueue Length (m)
Victoria Rd
(B)
Wright St
(B)
Direction
Wright St / Victoria Rd
3/21/2016
Intersection #: 6
Average StDev Max StDev
Right 50 110 8 135 4
Through 125 50 37 120 30
Left
Right 75 0 0 20 7Through 380 265 23 410 3
Left 85 0 0 20 7
Right 45 0 1 55 18
Through 100 5 1 75 19
Left
Right 35 0 0 15 9
Through 400 5 2 130 24
Left 65 5 2 55 15
Route 23N-Bend Rd / Hwy 1
Route 23N
(SB)
Hwy 1
(WB)
Bend Rd
(NB)
Hwy 1
(EB)
Queue
Storage
Queue Length (m)
Direction Movement
-
8/18/2019 McElhanney Victoria Road traffic plan
35/99
*+,-./+0123-04 56-7/47,-+.6 589/.:7876-
;.6,79-30< =74+>6 ?/+7@
A0>7 B %(
H9976I+V ;
A3D+60< =.,3876-4
-
8/18/2019 McElhanney Victoria Road traffic plan
36/99
-
8/18/2019 McElhanney Victoria Road traffic plan
37/99
5 J
-
8/18/2019 McElhanney Victoria Road traffic plan
38/99
FREQUENTLY ASKED QUESTIONS
City
of Revelstoke Victoria Mutas Intersection
Improvements
1
Q What problems are
we
trying to
solve?
A Traffic backup
on
the highway, congestion, accident potential,
unsafe pedestrian movements,
and
needing
traffic
control people
in
the summer.
2 Q
Is
the roundabout
at
Wright St necessary? A Yes with
the left turn into
Tim Hortons/Shell/Super 8
removed, it allows
traffic
coming from the highway to access Tim
Hortons/Shell/Super
8 safely.
3 Q Who is providing input
into
the intersection improvements?
A
City of Revelstoke, Ministry of
Transportation
and
Infrastructure,
business owners, and the general public. McElhanney is the
transportation
engineering consultant.
4. Q Will this project be solely based on traffic
engineering?
A Traffic
engineering
is
important to
the
improvement of the intersections; however, there are opportunities for attractive streetscaping, improving the
community entrance experience, branding Revelstoke, and inviting people further
into
Revelstoke by
way of
the Wright
St roundabout.
5.
Q Will this
actually
relieve congestion at
Victoria/Bend
Rd/Woodenhead? A Yes it
significantly
reduces
congestion
(caused by
left
turns) as proven by detailed
and
reliable traffic modelling.
6. Q Is
the
roundabout
at
Fraser/Laforme necessary?
A
It
is
not
required
for
the
Victoria/Bend/
Woodenhead
access improvements,
but
it would improve
safety and traffic
flow
north
of
the highway.
7. Q Does the general public like roundabouts? A Sometimes not at first,
but there are many
successful
examples of
the
public
appreciating
roundabouts after
they
get
used to them, such as in Clearwater.
8. Q
Why
not put a roundabout on the highway (like Clearwater)? A The highway intersection is not causing the
problems - the primary cause is left
turns
at Victoria/Bend/Woodenhead,
so
putting a roundabout on the highway
would not
solve
the
problems.
9
Q
Can
a
arge
semi
truck get around
the
roundabouts?
A
Yes
the
roundabouts
are
designed
to
allow
a
20
meter long truck to U-turn around the roundabout.
10. Q
Are
the Revelstoke bears
going to
still be part of the entrance? A The bears are shown in the 3
rendering; final
configuration
will
be discussed
as concepts are developed with
further public
input.
11.
Q What
will
the
roundabout
look
like?
A
Many communities use the centre of
roundabouts
to showcase
local
character and artistry.
12.
Q Why
close
off
Bend Rd? A Closing this
section of
Bend Rd removes
unnecessary traffic conflict
points
and
simplifies intersections.
13. Q What will
happen
to the sani dump? A The City has been evaluating sani
dump
relocation separately
from this project, but no
decisions
have been made.
14.
Q
Why
not
have
a
big
roundabout at Victoria/Bend Rd/Woodenhead? A
It
would
be
too
close
to
the
highway
to meet
current
standards
and
would create additional problems
on
the highway.
15.
Q Are roundabouts appropriate for places
with snow? A
Yes,
there
are
many
roundabouts in the snowy
regions of BC, Alberta, and the northern US,
and
maintenance
crews
effectively maintain them during winter.
16. Q Are we just
moving
the problem
down
the
road? A
No,
removing
left
turns and creating additional
spaces
between accesses eases
the
problem. Also,
by relocating
the
majority of
turning movements
further
away from
the
highway, it provides
more length
of road for traffic
to smooth out.
It s a
proven
transportation design
principle and is the reason
why
the Ministry
has minimum
distances between highways and intersections.
-
8/18/2019 McElhanney Victoria Road traffic plan
39/99
City of Revelstoke
P.O. Box 170, Revelstoke, British Columbia VOE SO
revelstoke ca
Mutas Intersection
and
Corridor Preliminary
esign Review Open House
March2 2016
COMMENTS:
DEVELOPMENT
SERVICES
\
250) 837-3637
PUBLIC WORKS
250) 837-2001
FINANCE
250) 837-2161
FIRE RESCUE
SERVICES
250) 837-2884
PARKS, RECREATION CORPORATE COMMUNITY
CULTURE
ADMINISTRATION ECONOMIC
DEVELOPMEN
250) 837-9351 250) 837-2911 250) 837-5345
-
8/18/2019 McElhanney Victoria Road traffic plan
40/99
City
of
Revelstoke
P.O. Box 170, Revelstoke, British
Columbia VOE
250
revelstoke.ca
Mutas
Intersection
and
Corridor Preliminary
esign Review Open House March 2 2016
COMMENTS:
DEVELOPMENT
SERVICES
250) 837-3637
development
@revel stok e.ca
250) 837-2001
FINAN CE FIRE RESCUE
SERVICES
250) 837-2161 250) 837-2884
[email protected] fire@
evelstoke
.
ca
PARKS, RECREATION CORPORATE
COMMUNITY
CULTURE DMINISTR TION ECONOMIC DEVELOPMEN
250) 837-9351
250) 837-2911 250) 837-5345
admin@
revelstoke
.ca ced@revel stok e.ca
-
8/18/2019 McElhanney Victoria Road traffic plan
41/99
City
of
Revelstoke
P.O. Box 170, Revelstoke, British Columbia VOE 2SO
revels oke. ca
Mutas
Intersection
and
Corridor Preliminary
esign Review Open House March 2
2016
COMMENTS:
- I
DEVELOPMENT
SERVICES
250) 837-3637
developme [email protected]
PUBLIC WORKS
250) 837-2001
W I LL
FINANC E FIRE RESCUE
SERVICES
250) 837-2161 250) 837-2884
[email protected] [email protected]
PARKS, RECREATION CORPORATE COMMUNITY
CULTURE DMINISTR TION
ECONOMIC
DEVELOPMEN
250) 837-9351 250) 837-2911 250) 837-5345
-
8/18/2019 McElhanney Victoria Road traffic plan
42/99
OMMENTScont d
-
8/18/2019 McElhanney Victoria Road traffic plan
43/99
City
of
Revelstoke
P.O. Box 170, Revelstoke, British Columbia VOE 2SO
revelstoke ca
Mutas
Intersection
and
Corridor Preliminary
esign Review
Open House March
2
2016
COMMENTS:
DEVELOPMENT
SERVICES
250) 837-3637
development@revelstoke .ca
PUBLIC WORKS
250) 837-2001
works
@revelstoke .ca
FINAN CE FIRE RESCUE
SERVICES
250) 837-2161 250) 837-2884
finance @revelstoke .ca fire@revelsto ke.ca
PARKS, RECREATION CORPORATE
COMMUNITY
CULTURE DMINISTR TION ECONOMIC DEVELOPMEN
250) 837-9351 250) 837-2911 250) 837-5345
prc@revelstok e.ca admin@revelstoke .ca ced@revelst oke.ca
-
8/18/2019 McElhanney Victoria Road traffic plan
44/99
-
8/18/2019 McElhanney Victoria Road traffic plan
45/99
FREQUENTLY ASKED QUESTIONS
City of Revelstoke
Victoria Mutas
Intersection Improvements
1 Q What problems are we trying
to
solve?
A
Traffic
backup
on
the
highway, congestion, accident potential,
unsafe
pedestrian movements, and needing traffic control people
in
the summer.
2
Q
Is
the
roundabout
at Wright St necessary? A Yes, with the left turn into Tim
Hortons/Shell/Super
8
removed,
it
allows traffic
coming
from the highway to
access
Tim Hortons/Shell/Super 8safely.
3 Q Who is providing input into the intersection improvements?
A
City of Revelstoke, Ministry of
Transportation
and Infrastructure, business owners, and the general public. McElhanney is the transportation
engineering consultant.
4.
Q
Will this
project
be
solely
based
on traffic engineering?
A
Traffic engineering
is
important to the
improvement
of the
intersections;
however, there are
opportunities for
attractive
streetscaping,
improving the
community entrance experience, branding Revelstoke, and
inviting
people further
into
Revelstoke by
way
of
the
Wright
St roundabout.
5. Q Will this
actually
relieve congestion at Victoria/Bend Rd/Woodenhead? A Yes, it significantly reduces
congestion
(caused by
left
turns) as proven
by detailed and
reliable
traffic
modelling.
6. Q
Is
the roundabout at
Fraser/Laforme necessary?
A
It
is not required for the
Victoria/Bend/
Woodenhead
access improvements,
but it would improve
safety
and
traffic
flow north
of
the highway.
7 Q Does the general public like roundabouts? A Sometimes not at first, but
there are
many successful
examples of the public appreciating roundabouts after
they
get used to
them, such
as in Clearwater.
8 Q Why
not put a
roundabout on the
highway
(like Clearwater)?
A
The highway intersection
is not causing
the
problems the
primary
cause is
left
turns
at
Victoria/Bend/Woodenhead, so putting a roundabout on
the
highway
would
not
solve
the problems.
9.
Q
Can
a
arge
semi
truck get around
the
roundabouts? A
Yes, the
roundabouts
are
designed
to
allow
a
20
meter
long truck to U-turn
around
the roundabout.
10. Q
Are
the Revelstoke
bears going to still
be part of the entrance?
A The bears are shown
in
the 3
rendering;
final
configuration will be discussed as concepts are developed with
further
public
input.
11.
Q
What will the roundabout look like? A Many
communities
use
the
centre
of
roundabouts to showcase
local character and
12. Q Why close
off
Bend Rd? A Closing this section
of
Bend
Rd
removes
unnecessary traffic conflict
points
and simplifies intersections.
13. Q What will happen to the sani dump? A The City has been evaluating sani dump relocation separately
from this project, but no
decisions
have been made.
14.
Q
Why not
have
a big roundabout at Victoria/Bend Rd/Woodenhead?
A It
would be too
close to
the
highway to
meet
current standards and
would
create additional
problems
on the
highway.
15. Q Are roundabouts appropriate for places
with
snow? A Yes, there are many roundabouts in the snowy
regions of
BC,
Alberta, and the
northern US, and
maintenance
crews effectively maintain them during winter.
16. Q
Are
we just moving the problem down the
road? A
No, removing left turns and creating additional spaces
between accesses
eases
the problem.
Also,
by relocating the majority of turning movements further away
from
the highway, it provides more length
of
road
for
traffic to smooth out. It s aproven
transportation
design
principle
and
is the
reason why
the Ministry
has minimum
distances
between
highways and intersections.
-
8/18/2019 McElhanney Victoria Road traffic plan
46/99
City of Revelstoke
P.O. Box 170, Revelstoke, British Columbia
VOE SO
revelstoke. ca
Mutas Intersection
and
Corridor Preliminary
esign
Review Open House March2 2016
COMMENTS:
DEVELOPMENT
SERVICES
250) 837-3637
PUBLIC WORKS
250) 837-2001
FINANC E FIRE RESCUE
SERVICES
250) 837-2161 250) 837-2884
[email protected] [email protected]
PARKS, RECREATION CORPORATE COMMUNITY
CULTURE ADMINISTRATION
ECONOMIC
DEVELOPMEN
250) 837-9351 250) 837-2911 250) 837-5345
prc@revelst oke.ca [email protected] [email protected]
-
8/18/2019 McElhanney Victoria Road traffic plan
47/99
COMMENTS cont d
-
8/18/2019 McElhanney Victoria Road traffic plan
48/99
City
of
Revelstoke
P.O. Box 170, Revelstoke, British Columbia
VOE 2SO
revelstoke ca
Mutas Intersection
and
Corridor Preliminary
esign
Review Open
House March 2, 2016
COMMENTS:
DEVELOPMENT
SERVICES
250) 83 7-3637
development@revelstoke .ca
PUBLIC WORKS
250) 837-2001
works
@revelstoke .ca
FINANCE FIRE
RESCUE
SERVICES
250) 837-2161 250) 837-2884
financ e@revelstok e.ca fire@
revelstoke
.ca
PARKS, RECREATION CORPORATE
COMMUNITY
CULTURE
DMINISTR TION ECONOMIC
DEVELOPME
{250 837-9351 {250 837-2911 250) 837-5345
prc
@revelsto ke.ca admin@revelsto ke.ca ced@revelstok e.ca
-
8/18/2019 McElhanney Victoria Road traffic plan
49/99
City
of Revelstoke
P.O. Box 170, Revelstoke, British Columbia VOE 2SO
revels oke. ca
Mutas Intersection
and
Corridor Preliminary
esign
Review Open House
March 2, 2016
COMMENTS:
1 s dest
DEVELOPMENT PUBLIC WORKS FINANCE FIRE RESCUE
PARKS, RECREATION CORPORATE COMMUNITY
SERVICES SERVICES
CULTURE
DMINISTR TION ECONOMIC
DEVELOPMEN
2
5
0)
837-3637 250) 837-2001 25
0)
837-2161 250) 837-2884 250) 83
7-
9351 250) 837-2911 250) 837-5345
[email protected] [email protected] [email protected] [email protected] prc@evels toke.ca [email protected] ced@ evelstoke.ca
-
8/18/2019 McElhanney Victoria Road traffic plan
50/99
-
8/18/2019 McElhanney Victoria Road traffic plan
51/99
City of Revelstoke
P.O. Box 170, Revelstoke, British Columbia
VOE
2SO
revelstoke.ca
Mutas Intersection
and
Corridor Preliminary
esign
Review Open House March 2, 2016
COMMENTS:
A \\ovv
DEVELOPMENT
SERVICES
250) 837-3637
fu
O
PUBLIC WORKS
250) 837-2001
work s@revelstok e.ca
FINAN CE FIRE RESCUE
SERVICES
250) 837-2161 250) 837-2884
[email protected] [email protected]
PARKS, RECREATION CORPORATE COMMUNITY
CULTURE
DMINISTR TION ECONOMIC
DEVELOPME
250) 837-9351 250) 837-2911 250) 837-5345
admin
@revels toke.ca [email protected]
-
8/18/2019 McElhanney Victoria Road traffic plan
52/99
-
8/18/2019 McElhanney Victoria Road traffic plan
53/99
City
of
Revelstoke
P.O. Box 170, Revelstoke, British Columbia VOE
2SO
revelstoke . ca
Mutas Intersection
and
Corridor Preliminary
esign
Review Open House March 2, 2016
COMMENTS:
DEVELOPMENT
SERVICES
250) 837-3637
development@revel stoke .ca
PUBLIC WORKS
250) 837-2001
works@evelstoke.
ca
FINANCE
250) 837-2161
FIRE RESCUE
SERVICES
25
0)
837-2884
I
{ I
PARKS, RECREATION CORPORATE
COMMUNITY
CULTURE DMINISTR TION ECONOMIC DEVELOPMEN
250) 837-9351 250) 837-2911 250) 837-5345
prc@revels toke.c a admin@evelstoke.
ca
ced@revels toke.c a
-
8/18/2019 McElhanney Victoria Road traffic plan
54/99
City
of Revelstoke
P.O. Box 170, Revelstoke, British
Columbia
VOE SO
revelstoke.ca
Mutas
Intersection
and
Corridor Preliminary
esign Review Open House March 2, 2016
COMMENTS:
.r
{
Th l
DEVELOPMENT
SERVICES
250) 837-3637
h
'
PUBLIC
WORKS
250) 837-2001
;
FIN NCE
250) 837-2161
FIRE RESCUE
SERVICES
250) 837-2884
PARKS, RECREATION CORPOR TE COMMUNITY
CULTURE
DMINISTR TION ECONOMIC
DEVELOPME
250) 837-9351 250) 837-2911 250) 837-5345
prc
@evelstoke.ca [email protected] [email protected]
-
8/18/2019 McElhanney Victoria Road traffic plan
55/99
City
of
Revelstoke
P.O. Box 170, Revelstoke, British Columbia VOE 250
revelstoke.ca
Mutas Intersection
and
Corridor Preliminary
esign
Review Open House
March 2,
2016
COMMENTS:
DEVELOPMENT
SERVICES
250) 83 7-3637
PUBLIC WORKS
2
5
0)
83 7-2001
works@reve lst oke.ca
FINANCE
250) 837-2161
FIRE RESCUE
SERVICES
250) 83 7-2884 .
fire@revelst oke.ca
PARKS, RECREATION CORPORATE
COMMUNITY
CULTURE DMINISTR TION ECONOMIC DEVELOPMEN
250)
83
7-9351 250) 837-2911 250) 837-5345
prc@revelsto ke.
ca admin
@revel st oke.ca ced@
revelstoke
.ca
-
8/18/2019 McElhanney Victoria Road traffic plan
56/99
City
of Revelstoke
P.O. Box 170, Revelstoke, British
olumbia VOE 2SO
revelstoke.ca
Mutas
Intersection
and
Corridor Preliminary
esign Review Open House March 2
2016
COMMENTS:
DEVELOPMENT
SERVICES
250) 837-3637
development@revelsto ke.ca
PUBLIC WORKS
250) 837-2001
works
@revel stok e.ca
FINANC E FIRE RESCUE
SERVICES
250) 837-2161 250) 837-2884
[email protected] fire@evel stoke.ca
?-
av
PARKS, RECREATION CORPORATE COMMUNI TY
CULTURE ADMINISTRATION
E ONOMI
DEVELOPME
250) 837-9351 250) 837-2911 250) 837-5345
admin
@revelstoke.ca [email protected]
-
8/18/2019 McElhanney Victoria Road traffic plan
57/99
I .
·- I
·
,
City o Revelst
Mutas Intersection and Corridor Preliminary
esign Review Open
House March2,2016
Is there a possibility
o
creating a large traffic circle that includes the TCH?
Its centre would have to be off-set towards the downtown. The loop around A W, McDonald's,
etc could even be reversed
with
a stop sign for exiting traffic before crossing traffic entering .
from the circle.
Helen Shuttleworth,
250-837-5901
\. t . ;
..
.,
. i .
· 1
I
1··-
' -.__: • t • ; • • :
.I : .
. · . . i ; i \ : . . · . l ..
• L -
·
. :· .
l ;- : 1
., ·· t
i • ..
..
-
8/18/2019 McElhanney Victoria Road traffic plan
58/99
City
of
Revelstok
P.O. Box 170, Revelstoke, British Columbia VOE 250
revelstoke.ca
Mutas Intersection and Corridor Preliminary
esign
Review Open House March 2, 2
1
6
COMMENTS
Firstly, I'm glad to see a competent engineering firm has been hired rather than trying to solve
the problem in house. My comments follow.
How much consideration has been given to the future
of
he Trans Canada Highway? The
engineer asked about this seemed to think it is of no concern - the TCH presently
h s
four lanes
through the intersection
and
nothing will change.
Don't
be
so sure. There will have to be a
second bridge over the Columbia and how will that affect alignment of the highway at the
intersection? and others also recall a past proposal to relocate the Columbia crossing north
of
the Columbia Park district. Surely, the Ministry
of
Transportation has some at least tentative
plans available.
Looking at the plan presented and talking to the presenters, saw no evidence of any original or
out
of
he box thinking. The plan only.massages the current problem. Was there any
brainstorming of
off
the wall ideas? Could the railroad be relocated? Could the restaurants be
relocated? How about the suggestion in the Revelstoke Current a few months ago about entering
Revelstoke at the 23North intersection with a bridge
over
the railroad discharging traffic onto
Victoria Road? And at the open house, talked to a young chap who proposed blocking Victoria
Road at Mutas Road and directing traffic in a loop that would encircle everything between the
railroad and the
TCH
- in effect, a huge traffic circle.
Now, presuming there will be no real change from the current proposal, we have to ensure it will
not be a total disaster, especially
in
winter. The engineers say traffic circles work well
in
Prince
George, Carunore and Calgary. They also work in other places. However, these places either
have no snow or very dry snow. We know that is not the case in Revelstoke and that our snow is
heavy, packs firmly and Is much more slippery and difficult .to drive on then that found in colder
locals. The round-about must be
flat so that
in
snowy conditions, freight trucks that have had to
wait to enter
wi11
be
able to get moving forward again. Also, on that theme, try to ease the grade
on Victoria Road as
it
approaches the TCH. understand trucks commonly have difficulty
getting underway to enter or cross the highway if they've been stopped there'.
Bill Shuttleworth,
250-837-5901,
We can't afford that much
V LST
-
8/18/2019 McElhanney Victoria Road traffic plan
59/99
R
-_. ; \ .
.
01-..y;,n / _
577('4
2 _
--9] I
?3?
l
-
8/18/2019 McElhanney Victoria Road traffic plan
60/99
1
!"##" %&''
()*+, !"##" %&''
-./0, (&)*+,-.,./ .-0.1 2(
1*, 34&)5&6678#)79:"69#5;
-
8/18/2019 McElhanney Victoria Road traffic plan
61/99
-
8/18/2019 McElhanney Victoria Road traffic plan
62/99
1
!"##" %&''
()*+, !"#$ &'(") *+",)-"#$.'(")/-+",)01'+2
-./0, 3"#1(456478 9:9; >, ?"))
23, @A"B CD#"1("BE !",) FA#-GH'BE I(#,H CA)J,-E F"#GK 31LAA
-456.30, 3"#1( 6M 6578
! "#$% #&&%'(%( )*%"+,(%- .%%&/'0 1+- .2 !'&%-3%4&/+' #'( #0-%% 5/&" 42--%'& 6-+6+3#,7
8%0#-(39
:#-;
-
8/18/2019 McElhanney Victoria Road traffic plan
63/99
1
!"##" %&''
()*+, !"#$% '()*+# ,-"#$%.()*+#/0"1((23(45
-./0, 6")317897:; :86
1*, *+?+@(A4+#B
-234.50, C$D1E"0 F@"#
Thank you for the informative presentation at the rec centre on Wednesday night. It is a challengingintersection for sure. I believe, given our budget, that this is the best possible solution for allconcerned. I heard many different plans from residents there but I really believe this plan takes in toconsideration the traveler, the resident and the businesses in the area.
Best regards,
Janis Borden
-
8/18/2019 McElhanney Victoria Road traffic plan
64/99
1
!"##" %&''
()*+, !"#$%&' )%**'+&,+- ./&%001#%-2#/31%$++4#%5
-./0, 6%$7897:; ;(%/"";3 !:(! ' 4+"$ "5 -'9:! +"$? &,'+9 1"$+ (! !:, 3(+1%(+ *,+!,- (+1 !:'-1 (0,+8, (+1 !:,) :(1 '338,3
$'!:!-(+3;"-! !-8*4 &8! 1,(/! $'!: !:, '338, &) :(0'+9 ( 0,-) 3%(// *8-& "+ !:,'+3'1,"5 !:, -"8+1(&"8! $'!: (+ '++,- ;(0,- "- &-'*4 (-,( $:,-, !-(+3;"-! !-8*43*(+ -'1, 8; "+!" &, (&/, !" +(0'9(!, !:, -"8+1 (&"8!< !:,-, '3 (/3" ( -"8+1(&"8! 8; "+ !:,
$() !" @"3!*"(+1 !:, +,$ *(3'+"<
)"8 *"8/1 :(0, ( /""4 (! !:,3, !" 9,! (+ '1,( :"$ !:,) $"8/1 $"-4AB83! (+ '1,( 5"- )"82'*:(-1
-
8/18/2019 McElhanney Victoria Road traffic plan
65/99
1
!"##" %&''
()*+, !"#$ &'(") *+",)-"#$.'(")/-+",)01'+2
-./0, 3"#1(456478 9:56 ;3
1*, "))
23, ?@"A BC#"1("AD 3,=@ E('+"FD !",) G@#-HF'AD I(#,F B@)J,-D G"#HK L"C@)D 3"#= 31M@@
-456.30, N))@-") )@OC CH#A
! "#$%& %'() *# +,() -$.) */,* )0).1#2) '- ,",.) #3 '%%)4,% )2*.,25) *# 6.#2*,4) .#,& 3