May 5, 2008 TPTF Texas Nodal Market Implementation Program Update Jerry Sullivan.

13
May 5, 2008 TPTF Texas Nodal Market Implementation Program Update Jerry Sullivan

description

3 3 Texas Nodal Program UpdateMay 5, 2008 Program Status: Summary Nodal Delivery status remains: ERCOT Readiness status is: MP Readiness status is: Cost* ScheduleScope / Quality Green AmberGreenAmber Nodal Delivery EDS1EDS2EDS3EDS4 Green Red Amber Green Current performance trend is acceptable Significant recent improvement Schedule indicators under significant stress Primary Rating Indicators Secondary Indicators *Anticipated approval at May 8 PUC open meeting Issues (EDS): EDS 2 - State Estimator EDS 3 - ACE testing - will return to Amber if TAC approves revised testing approach (current meeting) EDS 4 - Outage Scheduler and System Failover

Transcript of May 5, 2008 TPTF Texas Nodal Market Implementation Program Update Jerry Sullivan.

Page 1: May 5, 2008 TPTF Texas Nodal Market Implementation Program Update Jerry Sullivan.

May 5, 2008TPTF

Texas Nodal Market Implementation

Program Update

Jerry Sullivan

Page 2: May 5, 2008 TPTF Texas Nodal Market Implementation Program Update Jerry Sullivan.

2Texas Nodal Program UpdateMay 5, 2008 2

Agenda

• Program Status

• ERCOT and Market Participant Readiness

• Schedule

– Single Entry Model (NMMS)– Go-Live Plan

• Market Participant Identity Management (MPIM)

• Quality

• Cost

Page 3: May 5, 2008 TPTF Texas Nodal Market Implementation Program Update Jerry Sullivan.

3Texas Nodal Program UpdateMay 5, 2008 3

Program Status: Summary

Nodal Delivery status remains:

ERCOT Readiness status is:

MP Readiness status is:

Cost*ScheduleScope / Quality

Green Amber GreenAmber

Nodal Delivery

EDS1 EDS2 EDS3 EDS4Green Red Red Red

Amber

Amber

Green

Current performance trend is acceptable

Significant recent improvement

Schedule indicators under significant stress

Primary Rating

Indicators

Secondary Indicators

* Anticipated approval at May 8 PUC open meeting

Issues (EDS):EDS 2 - State Estimator EDS 3 - ACE testing - will return to Amber if TAC approves revised testing approach (current meeting)EDS 4 - Outage Scheduler and System Failover

Page 4: May 5, 2008 TPTF Texas Nodal Market Implementation Program Update Jerry Sullivan.

4Texas Nodal Program UpdateMay 5, 2008 4

ERCOT Readiness

ERCOT Readiness status is Amber

• ERCOT Executive Readiness Survey is updated monthly

• Received updates to Transition Plans this past week - the next update is scheduled for June

• Business Process model is being updated in conjunction with procedures development

• Procedure plans have been created for each department and are being monitored and reported in Procedures scorecard

• Steady progress on training

• Staffing plans developed; recruiting ongoing; timeframes established

• Staffing, Procedures and Training progress being updated on Nodal scorecard weekly

• Procedures and Training completion target is by August 31, 2008

Page 5: May 5, 2008 TPTF Texas Nodal Market Implementation Program Update Jerry Sullivan.

5Texas Nodal Program UpdateMay 5, 2008 5

Market Participant Readiness

• Engagement and Training [green] – Vast improvement in last few weeks (see following slides)

• Connectivity and Telemetry [green] – Connectivity metrics complete for most MPs - outliers are new to the program and need to go through EDS process

• Trials Participation [green] – Actively measuring EDS3 and EDS4 trial participation metrics

• Registration and Qualification [amber] due to MP10 (Resource to Node mapping)

– ERCOT received responses from 80 percent (143 of 179) of Resource Entities; scoring based on email from resource indicating acceptance of mapping; missing emails scored amber

– Per the metric, the QSEs responsible for the resource carry the score (12 of 37 QSEs turned amber as a result of this metric)

– In June the standard becomes more stringent: QSEs must ensure that Resources Entities certify the accuracy of the mapping in ERCOT systems

• Looking ahead– Numerous metric milestones are upcoming in next two months:

• MP17 – MP Qualification Activities begins measurement on 6/2

• MP20 - MP Ability to Submit Outage Information begins measurement once it approved by TAC (anticipated 5/8)

Market Participant Readiness status is Green

Page 6: May 5, 2008 TPTF Texas Nodal Market Implementation Program Update Jerry Sullivan.

6Texas Nodal Program UpdateMay 5, 2008 6

Market Participant Readiness

Market Participants with Engagement Status RED*

* Data as of noon 4.30.08

• Denton

• GUES

• LCRA

• Magic Valley

• STEC

• Texas Municipal Power

• Texas-New Mexico Power

TDSPs:

• Affordable Power

• Alliance

• Ambridge

• Andeler

• APNA

• Aquila

• BOA

• Barclays

• Bear

• Blu Power

• Brilliant

• Cargill

• Chain Lakes

• Citadel

• Clearview

• Conoco Philips

• DTE

• Duke

• Electric Now LP

• Epcot

• Fortis

• Freedom

• Gexa

• Himalaya

• Integrys

• Juice

• Just Energy

• Kansas City P&L

• Keystone

• Lehman Brothers

• Liberty

• LPT

• Merrill Lynch

• Mirant

QSEs w/o Resources:

• Morgan Stanley

• National

• Pegasus

• Repower

• Sempra Energy Solutions

• Sitara

• Spark

• Tara

• Texpo

• Trieagle

• UBS

• Urban

• Vantage

• Vega

• W P&L

• WCW (dropped Out)

• ERCOT Account Management made a concerted and effective effort in reaching out to over 70 MPs

• Since 4/18, 49 scorecard updates received, turning scores GREEN for 41 MPs

• For Engagement and Training:

TDSPs and QSEs with Resources segments have turned GREEN

QSEs without Resources improved from RED to AMBER

• Outreach and Updates will continue until Round 4 survey published mid-May

Update and Outlook

• Airtricity

• AEP

• EnergyCo

• FPL

• Fulcrum

• Invenergy

• J Aron

• Sweetwater

• Topaz

• Xtend

QSEs w/ Resources:

(Strike through): represents respondents that turned green since 4/18

Page 7: May 5, 2008 TPTF Texas Nodal Market Implementation Program Update Jerry Sullivan.

7Texas Nodal Program UpdateMay 5, 2008 7

Market Participant Readiness

Market Participants with Training Status RED*

• Alliance

• Andeler

• APN

• Bear

• BLU

• Cargill

• Citadel

• Electric Now LP

• Epcot

• Fortis

• Freedom

• Glacial

• Himalaya

• Integrys

• Kansas City P&L

• Lehman Brothers

• Liberty

• LPT

• Mirant

• National

• Pegasus

• Sitara

• Tara

• Texpo

• UBS

• Urban

• Vantage

• W P&L

• WCW (dropped out)

• Magic Valley

• STEC

QSEs w/o Resources: TDSPs:

QSEs w/Resources: 16% (6 of 37)

QSE w/o Resources: 31% (26 of 84)

TDSPs: 6% (1 of 18)

LSEs: 69% (70 of 102)

* for all MP metrics

Summary: MPs that are RED*

* Data as of noon 4.30.08(Strike through): represents respondents that turned green since 4/18

Page 8: May 5, 2008 TPTF Texas Nodal Market Implementation Program Update Jerry Sullivan.

8Texas Nodal Program UpdateMay 5, 2008 8

Schedule: Single Entry Model (NMMS)

Situation• NMMS deployment to production environment is dependent on ability to ensure data consistency between zonal

and network models

• Ability to test for data consistency between zonal and nodal network models requires EMS to import data from NMMS, via the EMS CIM importer, so that a nodal network model can be generated

• The EMS CIM importer will not be delivered on schedule (May 2)

– Pre-FAT testing was due to be completed on April 25, with FAT completion following by May 2

– Pre-FAT testing still ongoing as of today (April 30)

Impact• Delay in completion of EMS CIM importer will delay deployment of NMMS to production environment

• Length of potential delay is under review

• No impact as yet to Nodal Go-Live of December 1

– Deployment of NMMS to production is not on critical path but data validation (as opposed data consistency) check between zonal and nodal models is on critical path and will be required before 168-Hour Test

– Data validation check requires comparison of multiple network models - Base (i.e., zonal), NMMS, EMS and MMS

Current NMMS (Single Point Entry) Go-Live date (June 2) is delayed due to delay in receipt of the EMS CIM importer

Page 9: May 5, 2008 TPTF Texas Nodal Market Implementation Program Update Jerry Sullivan.

9Texas Nodal Program UpdateMay 5, 2008 9

Go-Live Plan: will encompass key activities/actions post the successful completion of the 168-Hour Test

Key Elements of the plan include: Following completion of 168-Hour Test, ERCOT, QSEs, and TSPs will operate nodal systems 24x7 in parallel with their

zonal systems Two LFC tests, one after the 168-Hour Test and one before Go-Live sequence, plus allowance for two discretionary tests MP & ERCOT 30-day key system environment freeze before Texas Nodal Market Implementation Date (TNMID) QSEs must operate zonal systems for 7 days post TNMID by submitting BES offers, AS offers, and Resource plans, and

maintain operational ability on key zonal systems 30 days post TNMID QSEs’ testing after Go-Live sequence must apply to ERCOT for re-testing 30 days after TNMID Upon cut-over to nodal system operations, nodal backup systems are first contingency; given multiple problems with critical

nodal systems, ERCOT will switch to constant frequency control for up to 12 hrs, then revert to zonal system operations

Next Steps Target Completion Date

Complete ERCOT review April 7th

Present to TPTF for Vote May 22nd

Present to TAC for Vote June 5th

Present to BoD June 17th

Page 10: May 5, 2008 TPTF Texas Nodal Market Implementation Program Update Jerry Sullivan.

10Texas Nodal Program UpdateMay 5, 2008 10

Market Participant Identity Management (MPIM)

• ERCOT to have compliant system in place by early June; required by July 1

• MP users with access to Critical Cyber Assets (CCA) systems must provide attestations as to training and personnel

• Attestations will come from MP User Security Administrator (MP-USA) and will take two forms: the first attesting that the user has completed training requirements in accordance with the CIP-004-1, and the second attesting that the MP has fulfilled all CIP-004-1 requirements or revisions thereof

• MPIM will send notifications to the user and MP-USA on a regular basis regarding need for annual training

ERCOT is subject to and bound by NERC standards, including CIP-004-1, Cyber Security – Personnel and Training

Page 11: May 5, 2008 TPTF Texas Nodal Market Implementation Program Update Jerry Sullivan.

11Texas Nodal Program UpdateMay 5, 2008 11

Quality Assurance

Overall volume of defects, the volume of Severity 1 and 2 defects, and the rate of increase in Severity 3 defects pose risks to the project

Mitigation Measures:1) Defect analysis as a basis for test planning2) Testing emphasis applied to high risk areas/projects3) Shifting emphasis to more comprehensive testing earlier in the software life cycle (i.e., development and pre-FAT vs FAT)

Page 12: May 5, 2008 TPTF Texas Nodal Market Implementation Program Update Jerry Sullivan.

12Texas Nodal Program UpdateMay 5, 2008 12

Cost: Summary

Revised Var. (o)/u Revised Var. (o)/u Project Name Budget Actual Budget Budget Forecast Budget

Commercial Systems (COMS) $ 12.6 $ 13.2 $ (0.6) $ 17.3 $ 17.5 $ (0.2)Congestion Revenue Rights (CRR) 7.2 7.0 0.2 8.1 8.1 - Early Delivery System (EDS) 9.0 8.0 1.0 21.2 21.2 - Electronic Data Warehouse (EDW) 2.2 2.2 - 4.1 4.1 - Enterprise Integration Project (EIP) 15.0 14.9 0.1 20.0 22.0 (2.0)Energy Management System (EMS) 17.2 15.5 1.7 21.5 21.5 - ERCOT Readiness & Transition (ERT) 2.0 1.6 0.4 4.0 4.0 - Integrated Design Authority (IDA) 7.7 7.6 0.1 9.7 9.7 - Infrastructure (INF) 63.5 63.2 0.3 66.5 67.0 (0.5)Integration Testing (INT) 15.3 15.1 0.2 19.7 20.6 (0.9)Market Information System (MER-MIS) 6.1 5.7 0.4 9.3 9.3 - Market Other (MER-OTH) 3.3 3.0 0.3 5.1 5.1 - Market Training (MER-TRN) 5.6 5.3 0.3 9.1 9.1 - Market Management System (MMS) 31.7 29.9 1.8 52.1 54.1 (2.0)Network Model Mgmt System (NMMS) 8.3 8.1 0.2 14.6 14.7 (0.1)Program Control (PC) 7.5 7.8 (0.3) 11.6 11.6 - Subtotal $ 214.2 $ 208.1 $ 6.1 $ 293.9 $ 299.6 $ (5.7) Contingency - - - 15.0 9.3 5.7 Finance Charges 7.3 7.5 (0.2) 10.6 10.6 - Total $ 221.5 $ 215.6 $ 5.9 $ 319.5 $ 319.5 $ -

Nodal ProgramProject Summary

($ Millions)

Through February 2008 Estimate at Complete (EAC)

Page 13: May 5, 2008 TPTF Texas Nodal Market Implementation Program Update Jerry Sullivan.

13Texas Nodal Program UpdateMay 5, 2008 13

Cost: Contingency

Internal External Vendor TravelProject Amount Labor Labor Labor Hardware Software and Misc

EIP - Enterprise Integration Project 2,000,000$ -$ -$ 2,000,000$ -$ -$ -$ INF - Infrastructure 200,000 - - 100,000 - 100,000 - INF - Infrastructure 300,000 - - 300,000 - - - INT - Integration Testing 935,000 200,000 735,000 - - - -

NMMS - Network Model Mgmt System 101,200 - 91,200 - - - 10,000

COMS - Commercial Systems 215,000 215,000

MMS - Market Mgmt System 2,000,000 2,000,000

- - - - - - - Total 5,751,200$ 200,000$ 1,041,200$ 4,400,000$ -$ 100,000$ 10,000$

Contingency 15,000,000$ Funds Used (5,751,200) Remaining Contingency 9,248,800$

Contingency Spending Authorization

Contingency fund now has over $5 million earmarked