Massey Building-Future Site of Iberia Bank · 2019. 11. 30. · Massey Building-Future Site of...

8
Massey Building-Future Site of Iberia Bank Commercial Office Space 1 Project Name: Massey Building-Future Site of Iberia Bank Project Location: Birmingham, AL Architect: KPS Group, Inc. Contractor: Glenn’s Flooring Existing Substrate: Existing concrete substrate with 3” deep cavity. Contaminants throughout the space with ordinary gypsum in areas. Former patches and repaired areas. Products Used: Schönox SEZ Plus, VD Primer, and Schönox US with roughly 60% sand aggregate added, then final pour of Schönox US Flooring Product: Ceramic tile Completed in 1924, the historic Massey building in Birmingham, AL was named for its original developer, R.W. Massey. Taking inspiration from Spanish Moorish architecture, the building features spiral- fluted columns and pointed elements atop the parapet meant to mimic minarets.

Transcript of Massey Building-Future Site of Iberia Bank · 2019. 11. 30. · Massey Building-Future Site of...

  • Massey Building-Future Site of Iberia Bank Commercial Office Space

    1

    Project Name: Massey Building-Future Siteof Iberia BankProject Location: Birmingham, AL Architect: KPS Group, Inc.Contractor: Glenn’s FlooringExisting Substrate: Existing concretesubstrate with 3” deep cavity. Contaminants throughout the space with ordinary gypsum in areas. Former patches and repaired areas.Products Used: Schönox SEZ Plus, VD Primer, and Schönox US with roughly 60% sand aggregate added, then final pour of Schönox US Flooring Product: Ceramic tile

    Completed in 1924, the historic Massey building in Birmingham, AL was namedfor its original developer, R.W. Massey. Taking inspiration from Spanish Moorish architecture, the building features spiral-fluted columns and pointed elements atop the parapet meant to mimic minarets.

  • Massey Building-Future Site of Iberia Bank Commercial Office Space

    Existing Substrate

    2

    Old plumbing line was exposed. Uneven layers of the existing subfloor were in need of leveling in order to smooth and repair the substrate.

    The deteriorating subfloor covered in old glue was exposing some of the original ceramic tiles.

    Old layers of glue were exposing the original concrete.

    Old layers of ordinary gypsum werepeeling back.

    The concrete was uneven after theoriginal walls were removed to open up the floor plan.

  • Massey Building-Future Site of Iberia Bank Commercial Office Space

    Priming: Schönox VD

    Schönox VD, universal acrylic primer, is applied over the existing concrete subfloor.

    Schönox VD is used to reduce absorption, bind residual dust, and increase adhesion.

    3

  • Massey Building-Future Site of Iberia Bank Commercial Office Space

    Concrete Repair: Schönox SEZ Plus

    4

    The rapid setting screed can be poured or pumped.

    Ready for covering after approximately 24 to 72 hours.

    SEZ Plus cures extremely hard and strong at 6500 PSI.

    SEZ Plus is easy to apply and dries fast even in thicker layers.

    Ready for foot traffic after approximately 3 hours.

    Large trenches were left where walls once stood. SEZ Plus is used to fillthe voids.

    Schönox SEZ Plus, rapid setting screed, is used to repair voids in existing concrete.

  • Massey Building-Future Site of Iberia Bank Commercial Office Space

    Schönox US Pour

    5

    US can be layered in thicknesses up to 2-3/8”.

    Designed for fast leveling in interior and exterior areas.

    Schönox US, cement based self-leveling compound, mixed with sand aggregate is poured over existing concrete.

  • Massey Building-Future Site of Iberia Bank Commercial Office Space

    Schönox US Pour

    6

    Frost resistant in outdoor environments.

    Schönox US can be layered in thicknesses above 1/8” up to 1-1/2˝ without aggregates.

  • Massey Building-Future Site of Iberia Bank Commercial Office Space

    Schönox US Pour

    7

    Schönox US is suitable on cement, gypsum substrates, and water resistant adhesive residues.

    US has compressive strength that cures to 4200 PSI.

    US has very low emissions andcontributes to LEED credits.

  • Massey Building-Future Site of Iberia Bank Commercial Office Space

    Renovated Subfloor by Schönox

    The new subfloor is ready for foot traffic afterapprox. 4 hours.

    Virtually any floor covering can be installed over Schönox US.

    Ready for covering after approx. 24 hours.