Martin Cooper, Los Alamos Co-spokesperson for the EDM Project for presentation to
description
Transcript of Martin Cooper, Los Alamos Co-spokesperson for the EDM Project for presentation to
Collab 6/20/05 #1
EDM
Martin Cooper, Los AlamosCo-spokesperson for the EDM Project
for presentation to
The EDM CollaborationLos Alamos, NMJanuary 22, 2006
Collaboration Business
Collab 6/20/05 #2
EDM Outline
a) Election of new collaborating institutionsb) Excerpts from the critical decision(CD)-0 documentc) Project organizationd) DOE order 413.3e) R&D funding for FY’06f) Work breakdown structureg) Undertaking work package responsibilitiesh) The next collaboration meeting
Collab 6/20/05 #3
EDM EDM Executive Committee
Doug Beck – University of IllinoisBrad Filippone – CaltechBob Golub – North Carolina State UniversityHaiyan Gao – Duke University
Collab 6/20/05 #4
EDM Excerpts from the CD-0 Document
•The CD-0 document has not been released•Excerpts come from a document provided by Jehanne Simon-Gillo, DOE Office of Nuclear Physics
Collab 6/20/05 #5
EDM Election of New Collaborators
Petitioners approved by the EDM Executive CommitteeUniversity of TennesseeArizona State University
RecruitsMITBoston UniversityArgonne National Laboratory
Collab 6/20/05 #6
EDM CD Schedule
Proposed CD schedule (There is a lot of float in CD4 date):
Funding Profile
CD-0 Approve Mission Need Q1 2006
CD-1 Approve Preliminary Baseline Range Q4 2006
CD-2 Approve Performance Baseline Range Q4 2007
CD-3 Approve Start of Construction Q1 2008
CD-4 Approve Start of Operations Q4 2013
Collab 6/20/05 #7
EDM Funding Profile
•These are actual year dollars.•This is the upper part of the DOE TPC range with no slop allowed.•TPC range includes CDR, R&D, design (PED), fabrication, preops (commissioning).•Dollar amounts are in thousands of dollars.•Schedules imply that you can baseline the project in two years after $1.3M of design and R&D efforts. Starting in FY08, EDM would complete final design and start fabrication.•You may decide that the schedule is too aggressive and that CD2 would happen in FY08 instead.
Collab 6/20/05 #8
EDM Funding Profile
Funding Plan with EscalationCollaboration Review: $17,209kDOE Guidance: $18,300kDOE Guidance 2: $18,300k
0
1000
2000
3000
4000
5000
6000
7000
FY'07 FY'08 FY'09 FY'10 FY'11 FY'12
Fiscal Year
$k(A
ctu
al Y
ear)
Collaboration
DOE Guidance
DOE Guidance 2
Collab 6/20/05 #9
EDM Funding Profile
Fiscal Year CoolaborationFunding
Profile
DOE FundingProfile
DOE FundingProfile 2
FY07 2,400 1,300 1,300
FY08 6,800 3,500 5,500
FY09 5,000 4,450 6,850
FY10 2,200 5,000 4,650
FY11 800 3,000 0
FY12 0 1,050 0
Estimated total
project costs:
17,200 18,300 18,300
Collab 6/20/05 #10
EDM Allowable Project Costs
NP general guidance on how to cost labor to a project in the context of existing research core bases at universities and laboratories:
- University scientific labor should be identified, but wages zeroed out, unless the scientist is acting as a project manager. University engineers, designers and technicians contributing to the fabrication of the project should be costed. Graduate students hired specifically to perform technician activities on the project should be costed at the appropriate hourly rate.
- Laboratory scientific labor (research physicist or accelerator physicist) should also be identified and zeroed out unless the individual is performing well-defined engineer, design or technical tasks that are typically only assigned to engineers, technicians and designers, or project management. If a scientist is performing a task that is best performed by a scientist instead of an engineer, technician or designer, then they are generally not part of the project costs.
Collab 6/20/05 #11
EDM Next Steps
• Identify CPM and FPD by the end of the month. • Provide feedback on CD schedule, cost profile (but be
prepared to live with as is) – January-ish• Define what funds you need for CDR – if you want
funds in January, DOE needs your input by December 12th, otherwise you are looking at February.
• Submit updated R&D request- increments of $50K up to $300K DOE dollars and additional for NSF. Present big picture. Identify which ones could be covered with NSF funding – end of December would be good.
• Get your WBS in order- before CD-1 review
Collab 6/20/05 #12
EDM Next Steps
• Start on drafts of management plan, CDR and acquisition strategy that will all be needed for CD1 review- we need to start iterating on management plan about 6 weeks prior to review and the acquisition strategy 8-10 weeks prior to review.
• Do ping David Arakawa (FNPB FPD) for advice on what to generate for CD1.
Collab 6/20/05 #13
EDM Contract Project Manager (CPM)
• The individual responsible to the funding agencies to document the scientific quality, the fiscal responsibility, and the adherence to schedule of the project
• The individual responsible to track the project and to urge the collaborating institutions to meet their commitments
• The individual responsible to prepare the collaboration for the CD reviews
• MDC has petitioned the EDM executive committee for a recommendation to the collaboration to become the CPM
Collab 6/20/05 #14
EDM Organization Chart
DOE Office of Nuclear Physics
Dennis KovarAcquisition Executive
DOE Office of Nuclear Physics
Jehanne Simon-GilloProgram Manager
Los Alamos Site OfficeEugene Colton
Federal Project Director
NSF Nuclear PhysicsBrad Keister
Program Director
DOE/NSFLANL/EDM
LANL Physics DivisionJack Shlachter
Division Leader
LANL EDMMartin Cooper
Contract Project Manager
EDM SpokespersonsMartin Cooper, LANL
Steve Lamoreaux, LANL
Institutional Principal Investigators
EDM Executive CommitteeSpokespersons
Four PIs
EDM Interface to the NSFContract Project Manager
NSF Funded PIs
Integrated Project Team
Subsystem Managers
Work Package Leaders
Collab 6/20/05 #15
EDM Interactions with the NSF
• CPM is the principal contact by DOE mandate• With a CPM from a DOE funded national
laboratory, the CPM can make no impact on the NSF without the direct involvement of the NSF funded PIs
• We must work out a cooperative arrangement between the project and the NSF
Collab 6/20/05 #16
EDM Organization Chart
DOE Office of Nuclear Physics
Dennis KovarAcquisition Executive
DOE Office of Nuclear Physics
Jehanne Simon-GilloProgram Manager
Los Alamos Site OfficeEugene Colton
Federal Project Director
NSF Nuclear PhysicsBrad Keister
Program Director
DOE/NSFLANL/EDM
LANL Physics DivisionJack Shlachter
Division Leader
LANL EDMMartin Cooper
Contract Project Manager
EDM SpokespersonsMartin Cooper, LANL
Steve Lamoreaux, LANL
Integrated Project Team
Subsystem Managers
Work Package Leaders
EDM Safety Officer
Collab 6/20/05 #17
EDM Integrated Project Team
DOE Federal Project Director (Chair) Eugene Colton
DOE Site Contracting Officer TBD
DOE Program Manager for EDM Jehanne Simon-Gillo
DOE Science Program Manager Gene Henry
NSF Program Manager Brad Keister
LANL Contract Project Manager Martin Cooper
LANL Deputy Contract Project Manager John Tapia
LANL Procurement Operations Manager TBD
LANL Chief Engineer Jan Boissevain
LANL ESSH Lead TBD
ORNL Operations Manager TBD
C-AD Assistant Chair for Administration TBD
Collab 6/20/05 #18
EDM DOE Order 413.3
• A roughly 50 page document that sets the rules for DOE procurement of capital equipment
• For projects between $5-20M, 413.3 defines how the project must be executed
Collab 6/20/05 #19
EDM CD Schedule
Proposed CD schedule (There is a lot of float in CD4 date):
Funding Profile
CD-0 Approve Mission Need Q1 2006
CD-1 Approve Preliminary Baseline Range Q4 2006
CD-2 Approve Performance Baseline Range Q4 2007
CD-3 Approve Start of Construction Q1 2008
CD-4 Approve Start of Operations Q4 2013
Collab 6/20/05 #20
EDM Work for CD-1 by June/August 2006
• Strengthen the collaboration• Fill out the organizational chart• MOUs with Subsystem Managers’ Organizations in
draft form• Complete conceptual engineering• Values Engineering Assessment• Complete most of the R&D• Conceptual Design Report (CDR)• Risk Analysis• Alternatives Analysis• WBS (Resource Loaded) and WBS Dictionary• Hazard and Safety Analysis• Preliminary Project Execution Plan• Acquisition Strategy
Collab 6/20/05 #21
EDM CD-1 Priorities
• Funding Profile• Federal Project Director• Gantt Chart for CD-1
Collab 6/20/05 #22
EDM Work for CD-2 by August 2007
• Complete preliminary engineering?• Complete all of the R&D• Get NSF funding in place• Technical Design Report (TDR)• Risk Analysis• WBS and WBS Dictionary• Project Execution Plan• Acquisition Strategy
Collab 6/20/05 #23
EDM Project Safety
• DOE Order 413.3 will be revised to expressly require the highest safety standards
• EDM will be done at a national laboratory - ORNL
• Two stories
Collab 6/20/05 #24
EDM Teleconferences with DOE
• One hour at 11 AM MST on the third Thursday of every month
• On occasion, MDC may call on collaboration members to participate
• Regular participants:• DOE
• Jehanne Simon-Gillo• Wlodek Guryn• Gene Henry• Eugene Colton?
• EDM• Martin Cooper• John Tapia• Bill Louis – LANL NP Program Manager
Collab 6/20/05 #25
EDM Coffee Break
• Enjoy!
Collab 6/20/05 #26
EDM R&D Priorities
Highest Priority1. 3He relaxation time from T = 0.5-4.0 K at the proper concentration, including
a SQUID NMR signal2. Neutron storage time at ~4 K in a cell coated with deuterated polystyrene3. Light collection design with the expectation of ~40 photoelectrons4. Reliable valves5. Understanding the geometric phase systematic error6. 4He dielectric strength at low pressures or for a presurized superfluid
Moderate priority1. Surface HV breakdown of acrylic and the Kerr effect2. 3He evaporator3. 3He injector volume test4. Beamline and measurement cell neutronics Monte Carlo
Quite Useful1. Magnet development2. Atomic magnetometers3. Laser induced flourescence
Collab 6/20/05 #27
EDM The Request - $300k
The following is a prioritized list for a funding request to your office for the EDM project FY'06:• $87k to LANL for engineering and project management/CDR
development• $87k to the University of Illinois for 3He relaxation time/SQUID
measurements and project engineering, split roughly equally• $25k to Duke University for 3He and light detection studies• $50k to North Carolina State University for field gradient systematic
studies• $25k to Caltech for magnet and shielding development• $25k to UC Berkeley for high voltage studies using the Kerr effect.We are postponing neutron guide and fluorescence studies as a cost savings for this year.
Collab 6/20/05 #28
EDM The Request - $300k
The bigger funding picture for EDM funding includes:$100-200k to the universities for R&D, primarily for Caltech and
Illinois, from the NSF. An NSF grant could reduce the DOE load above but would come much later in the FY.
$115k for Paul Huffman and Bob Golub at NCSU as a capital equipment request to Gene Henry. There is complete overlap with the request above and this request to Gene. The LANL commitment to NCSU may inhibit LANL finishing its R&D program.
$50-75k for CDR/project management from Don Rej, head of LANL's Office of Science
$200k for 3He diffusion studies and equipment from LANL LDRD$300k for technicians and engineers from LANL LDRD for R&D (The
balance of LDRD funding pays physicists' salaries.)The Duke and NCSU people wanted me to ask if any granted funds tothem could go directly to TUNL instead of going through LANL.
Collab 6/20/05 #29
EDM The Grant - $150k less $5k
• $00.0k to LANL for engineering and project management/CDR development
• $60.0k to the University of Illinois for 3He relaxation time/SQUID measurements and project engineering, split roughly equally
• $17.0k to Duke University for 3He and light detection studies• $34.0k to North Carolina State University for field gradient
systematic studies• $17.0k to Caltech for magnet and shielding development• $17.0k to UC Berkeley for high voltage studies using the Kerr effect.
Collab 6/20/05 #30
EDM Work Breakdown Structure (WBS)
• Needs to be reviewed to see that it makes sense• Needs to be brought into conformance with DOE standards
• Some complaints from Simon-Gillo• Some complaints from the LANL review committee
Collab 6/20/05 #31
EDM WBS Subsystem Managers
Neutron Beam Line and Shielding
Cryogenics, 3He Systems, Atomic Beam Source and Interface
Magnets and Magnetic Shielding
High Voltage, Measuring Cells, Light System, SQUIDs
Electronics, Computers, Simulations, Data Analysis
Conventional Construction
Integration and Commissioning
Collab 6/20/05 #32
EDM WBS Work Package Leaders
Subsystem Work Package Days Cost ($k)
Leader
Neutron Beam Line and Shielding
Beam Splitter 467 1476
Splitter Magnets 459 242
Spin Precession Magnets 317 132
Beam Line Shielding 44 15
Experimental Hall Shielding 106 105
Collab 6/20/05 #33
EDM WBS Work Package Leaders
Subsystem Work Package Days Cost ($k) Leader
Cryogenics, 3He Systems, Atomic Beam Source and Interface
Upper Cryostat and Radiation Shield 973 994
4He Purifier 450 261
Polarized 3He Storage Region 345 150
Lower Cryostat and Radiation Shield 745 1041
He Tubes & Holding Coils 281 102
He Refrigerator 524 1240
2nd Dilution Refrigerators 820 803
Cryogenic Support Equipment 290 374
Polarized 3He Transport 379 33
Collab 6/20/05 #34
EDM WBS Work Package Leaders
Subsystem Work Package Days Cost ($k) Leader
Magnets and Magnetic Shielding
5 Layer Conventional Shield 502 1001
Superconducting Shield 1016 143
Ferromagnetic Shield 589 79
Magnetic Penetrations 884 49
Constant Field Coil 1022 173
Gradient Coil
Pi/2 Coil 868 30
Dressed Spin Coil 1022 202
3He Polarization Holding Coil 379 173
Field Monitors 913 121
Collab 6/20/05 #35
EDM WBS Work Package Leaders
Subsystem Work Package Days Cost ($k) Leader
High Voltage, Measuring Cells, Light System, SQUIDs
Gain Capacitor 462 73
Electrodes and Corona Dome 402 41
Connecting HV Line 280 20
Kerr Rotation HV Monitor 225 43
Measurement Cells 184 153
Valves 768 812
SQUID System 913 77
Light Guides 248 88
Cryogenic Feed Through 259 39
Photomultiplier Tubes 60 22
Collab 6/20/05 #36
EDM WBS Work Package Leaders
Subsystem Work Package Days Cost ($k) Leader
Electronics, Computers, Simulations, Data Analysis
Electronics & Cables 126 291
Computers 224 87
Data Acquisition
Data Analysis
Neutron Transport Simulation
Neutron Induced Background Simulation
Signal Simulation
Collab 6/20/05 #37
EDM WBS Work Package Leaders
Subsystem Work Package Days Cost ($k) Leader
Conventional Construction
Platforms 180 160
Electrical Plant 305 299
Plumbing 297 340
Mechanical Supports 583 457
Counting House 42 20
Collab 6/20/05 #38
EDM WBS Work Package Leaders
Subsystem Work Package Days Cost ($k) Leader
Integration and Commissioning
Mechanical Assembly of Parts 315 338
Vacuum Checking 42 24
Trial Cool Down and Operation 158 169
Commissioning 118 85
Collab 6/20/05 #39
EDM Undertaking Resonsibilities
• At the next collaboration meeting, as many names as possible need to filled into the list of subsystem managers and work package leaders as possible
• The blanks will tell us tell us where we need to recruit new institutions
• Homework: • Between now and the next collaboration meeting, think
through what your institution can commit to doing• Be prepared to state what responsibility you will
undertake• Negotiate affiliations to team on larger projects
• Do not over commit
Collab 6/20/05 #40
EDM The Next Collaboration Meeting
• Week of March 6-10, 2006• At NCSU