Manpower
Optimization &
Increase Efficiency
of staff under SSE/Bridge
of Engineering Department over Jodhpur & Bikaner Division
(No. G/HQ/WS/463/13/ENGG./JU/2017-18)
GUIDED BY STUDIED BY
PRADEEP KUMAR MALIK 1 D K SHARMA, CWSI/JP
Sr. ADGM & AWSO/NWR/JP 2 R R K SINGH, CWSI/JP
3 AJIT KUMAR, WSI/JP
WORK STUDY ORGANIZATION
NORTH WESTERN RAILWAY
JAIPUR
Page 2 of 23
EXECUTIVE SUMMARY
Sr. No. 13
Study No.
G/HQ/WS/463/13/Engg./JU/2017-18
Subject
Manpower optimization and increase efficiency of
staff under SSE(Bridge) of Engineering department
over Jodhpur & Bikaner division.
Area Jodhpur & Bikaner division.
Division Jodhpur & Bikaner
Department Engineering
Terms of Reference Assessment of Man Power requirement
Present Cadre
Sanctioned Cadre 63
On Roll 34
Vacancy 29
Projected Cadre 47
Projected Surplus
Man Power 16
Total No. of
Recommendations 01
Financial Implication
Rs. 74.78 Lac per annum
Month of Circulation November, 2017
Page 3 of 23
INDEX
Chapter
No. Contents Page No.
I Introduction 4
II Acknowledgement 5 -
III Synopsis 6 7
IV Cadre, Duties and its jurisdictions 8 10
V Critical Analysis 11 19
VI Meeting with officer’s level 20 21
VII Conclusion and Recommendations 22 -
VIII Financial Implications 23 -
Page 4 of 23
CHAPTER-I
INTRODUCTION
Benchmarking is a continuous process of comparing different units and
identifying which one is the best in the business, followed by learning how this
excellence was achieved and then setting out to improve the efficiency of those units,
which were left behind. If this concept is implemented, it will result in large
reduction in the cost and make significant contribution in improving the efficiency of
various Divisions of the Railways.
Jodhpur & Bikaner division are major divisions of North Western Railway.
There are one Bridge Inspector depot available at JU. Painting and major erection
works are being done through contract and hence the workload of the bridge staff has
got reduced to a greater extent. This study has been undertaken to assess the staff
requirement for the reduced workload.
The SSE/Bridges is vested with the responsibility of maintaining the
superstructure of bridges (Span 12.2 m and above) and other installations in his
jurisdiction. The SSE/Bridges has to maintain the following:
i) Superstructure of Bridges (Span 12.2 m and above) that hold the
Permanent Way.
(a) Steel Girders b) PSC/RCC Girders
ii) W/S Crane Girder
iii) EOT Crane
iv) Turn Table
The inspection & maintenance work of FOB has now been shifted to
SSE/Works. Other maintenance activities, including maintenance of
substructure of bridges, are carried out by the Divisional staff.
Page 5 of 23
CHAPTER-II
ACKNOWLEDGEMENT
The Work study team expresses sincere thanks to Sh. Shikhar Maru Dy
CE/(Bridge Line)/NWR/JP, Sh. R. B. Meena, AEN/Bridge/JU, Sh. R. S.
Manjhi Sr. Section Engineer/Bridge/JU & R. K. Goyal, Sr. Section
Engineer/Bridge/JU and staff of Bridge Engineering department for the
cooperation extended by them in conducting the study.
METHODOLOGY ADOPTED
The following techniques of method study as well as work measurement
have been applied to conduct the study:-
i) Data collection and its critical analysis to arrive at factual status of
present working.
(PCE/NWR/JP letter no. 318/1/ ETKM dated 04.06.2007 was referred
for assessment of workload in terms of ETKMs) Annexure-C.
ii) Hold discussions at various levels with a view to produce fruitful results.
iii) Sample check and spot observations.
iv) Reassessment of manpower requirement by applying Indian Railway
Benchmark and Indian Railway Average Benchmark.
Page 6 of 23
CHAPTER-III
SYNOPSIS
Indian Railway is one of the biggest transportation organizations among all
other transport organizations in the country. In fact the Railway is backbone of the
country’s transport systems. In the recent times, Railway is facing tremendous
competition from road and air. Indian Railways has begun to loose out freight traffic
to the Roadways since the last decade, despite its inherent advantages of being
environment friendly and more reliable. Today the Railway’s freight share stands at
approximately 35% against 64% two decades ago. This slow down in freight loading
has eroded Railways’ revenue. In the time of competition transport system should not
only be agile, prompt and amenable but also financially viable. In order to bring
economy in expenditure, optimum utilization of manpower, machine and material
will have to be ensured.
Indian Railways’ prime motto is to provide the cheap and best transportation
services to their users at a desired level of safety, security and punctuality. Being a
large organization it plays a vital role in the Indian economy. These days, Indian
economy is facing tough time, so it is the collective responsibility of every
government organization to keep close watch on its expenditure and check the
outflow of revenue accordingly.
In Railways, the process of absorption of modernization has started and is still
in progress in every sphere of the system. The air brake stock has been replaced by
conventional stock, steam traction replaced by diesel and diesel by electric stock,
piecemeal loading replaced by block rake loading/ point to point loading, old type of
special mechanical interlocking replaced by Route Relay Interlocking and semaphore
type signals replaced by color light signals. As a result, certain activities have
become fully redundant/ obsolete for the existing system. These technological up
Page 7 of 23
gradations have shown considerable improvement in the efficiency and manpower
productivity in Railways.
Keeping in view all these points, SDGM has approved to conduct work study
of staff under SSE/Bridge/Jodhpur & Bikaner with a view to assess the staff
requirement as per the existing workload.
During the conduct of study, the team picked up/collected requisite data of all
the activities carried out in SSE/(Bridge)/JU over Jodhpur & Bikaner division. To
arrive at the actual requirement of staff, the team held discussions at various levels
and kept practicability in view.
Page 8 of 23
CHAPTER-IV
CADRE DUTIES AND ITS JURDICTIONS
4.1 Cadre Position of Bridge Staff:-
4.2.0 PRESENT SCENARIO
Dy. CE/Bridge Line/JP is over all in charge of entire Bridge staff over JU &
BKN division, assisted by AEN/Bridges/JU. There is one Bridge Depot based
at Jodhpur which is under the direct supervision of SSE/Bridge/JU. The
SSE/Bridge inspection is assisted by JE/Bridge, Technicians and Bridgeman
staff.
4.2.1 MAIN DUTIES OF BRIDGE INSPECTOR AND OTHER STAFF:-
Duties of Bridge Inspector:
He is responsible for carrying out the detailed inspection of:
i) All welded, PSC, RCC, Composite girders & ROBs and their bearings.
ii) Girders kept under observation once a year or at intervals specified by the
Chief Bridge Engineer.
iii) Technical inspections of Super structure including bearings of all steel
grinders of span 12.2m and above, RCC, PSC once in five years on a planned
S.N Category
GP Pay
Level
Sanction O. R Vac.
1 SSE/Bridge 4600 7 2 2 0
2 JE/Bridge 4200 6 1 0 1
3 MCF/Bridge 4200 6 2 0 2
4 Bridge Tech. Gr.I 2800 5 5 1 4
5 Bridge Tech. Gr.II 2400 4 2 3 +1
6 Bridge Tech. Gr.III 1900 2 2 2 0
7 Bridgeman 1800 1 49 26 23
Total staff 63 34 29
Page 9 of 23
basis, welded girders once in three years and distressed bridges every year or
once in three months, as per the category defined.
iv) Other nominated steel structures like OHE Cranes are being inspected by him
once in a year.
v) He has to record the details of each one of the inspection items in the bridge
register maintained for the purpose.
vi) He has to maintain the following structures in good condition by taking
immediate action to carry out necessary repairs, painting, oiling and greasing,
etc.
(a) Superstructure and bearing of all steel bridges of span 12.2m and
above, PSC girders.
(b) Other steel structures as specified by Chief Engineer.
(c) He is responsible for erection of steel grinders and PSC girders for all
major bridges,
(d) He is responsible for the accountal and periodical verification of
stores, tools and plants in his charge.
4.3.0 JURIDICTION OF SSE/BRIDGE/JU:-
Jodhpur Division:
a) SMR-BLDI Section
b) FL-DNA Section
c) RKB-JSM Section
d) LN-MJ Section
e) MTD-JU Section
f) SMR-BME Section
Page 10 of 23
4.3.1 EOT CRANE:
1 EOT Crane at Workshop and C&W JU/BGKT 8 Nos.
2 EOT Crane at Workshop and C&W JU/BGKT 2 Nos. under
construction
4.4.0 Bikaner Division:
a) BKN-HMH-BTI Section
b) SOG-APH Section
c) HMH-SDLP Section
d) RE-HSR-BTI Section
e) ROK-BNW Section
f) RE-SDLP Section
4.4.1 EOT CRANE:
1 EOT Crane at Workshop and C&W JU/BGKT 2 Nos.
4.4.2 SSE/Bridge/JU office functions from 8.00 hrs. to 12.00 hrs & 13.00 hrs. to
17.00 hours on all days except Sundays in the month from Sept. to March and
7.00 hrs. to 12.00 hrs. & 14.00 hrs. to 17.00 hours on all days except Sundays
in the month from April to August. The Artisan staff report for duty in the
morning and they are allocated work on weekly basis, depending upon the
regular needs and regular inspection programme as per the chart given by the
Headquarters.
Page 11 of 23
CHAPTER-V
CRITICAL ANALYSIS
5.0.0 Bridge Engineering department of JP, JU & Division is working under the control of
Dy. CE/Bridge line/NWR. To arrive at a factual conclusion on requirement of Bridge
staff of Jodhpur & Bikaner division, the team applied on-the-spot observations and
held discussions at various levels and applied Bench Marking.
5.1.0 APPLYING BENCH MARKING NORMS:-
Since manpower is the biggest component of expenditure of Indian Railway,
rightsizing of manpower to reduce unit costs is an effective way to increase
efficiency of Indian Railway. Railway Board’s vide letter No. 2016/E&R /2(8)/1
Dated 06.06.2017 has also desired to optimize the manpower of Jaipur and
Jodhpur division of North Western Railway as per average Benchmarking of
Indian Railway.
Benchmarking offers us a solution for reduction and redistribution of staff and can be
a very handy tool for rightsizing of Indian Railway.
Benchmarking is the continuous process of comparing different units; identifying
those who are the best, then learning how this excellence was achieved and then
setting out to improve the efficiency of those which are trailing behind.
Bench marking is being implemented not only on Indian Railway, but also on units
other than the Railways. Even for those Technical staff, for which specific yard
sticks are derived, bench marking is being exercised, because the yard sticks were
framed in olden days according to the then working pattern. Now in this competitive
world of computer era with new technology, those yard sticks are outdated.
Therefore, bench marking is being observed everywhere.
Page 12 of 23
5.2.0 THE REQUIREMENT OF STAFF AS PER BENCH MARKS NORMS:-
5.2.1 Calculation for No. of ITKM maintained in Jodhpur Division:-
a) Water way of Major & Important Bridges(Steel Bridges)
S.N. Section Water way in M
1. FL-DNA Section 317.20
2. MTD-JU Section 24.40
3. SMR-BLDI Section 1823.9
4. SMR-BME Section 61.00
5. RKB-JSM Section 36.60
Sub-Total 2263.1
b) Water way of Major & Important Bridges (PSC Bridges)
S.N. Section Water way in M
1. FL-DNA Section 207.40
2. LN-MJ Section 414.80
3. SMR-BLDI Section 353.80
Sub-Total 976.0
c) ROB & EOT Crane etc.
S.N. Section Water way in M
1. FL-DNA Section 97.75
2. JU-MTD Section 163.31
3. RKB-JSM Section 62.73
4. JU-LN Section 50.70
5. LN-MJ Section 80.76
6. SMR-BLDI Section 18.60
Page 13 of 23
7. SMR-BME Section 40.10
8. SMR-MBF Section 97.45
9. BKN-MTD Section 47.00
10. EOT Crane 201.0
11 Newly constructed ROBs 1192.20
Sub-Total 2051.6
Total 5290.70
d) Calculation of ITKM of Jodhpur Division.
a) 100M of waterway of major & important Bridge per
Track
= 3 ITKM
b) 3239.10 m of water ways of Major & Important Bridges = 3239.10x 3/100
= 97.173
= Say 98 ITKM
c) 100 M of water way of Minor Bridge, Tunnel, FOB,
ROB etc per Track
= 2 ITKM
d) 2051.60 m of water ways of minor Bridges, FOB, ROB
etc
= 2051.6 x 2/100
= 41.032
= Say 41 ITKM
No. of ITKM maintained by JU division (b+d) = 98+41
= 139 ITKM
Page 14 of 23
5.2.2 Calculation for No. of ITKM maintained in Bikaner Division:-
a) Water way of Major & Important Bridges (Steel Bridges)
S.N. Section Water way in M
1. SOG-BKN Section 122.0
2. SOG-APH Section 170.80
3. BTI-SOG Section 146.40
4. RE-HSR Section 18.30
5. HSR-BTI Section 219.60
6. ROK-BNW Section 50.60
7. HMH-SDLP Section 318.20
TOTAL 1045.9
b) Water way of Major & Important Bridges (PSCBridges)
S.N. Section Water way in M
1. RE-SDLP Section 243.80
TOTAL 243.80 say 244.0
c) ROB & EOT Crane etc.
S.N. Section Water way in M
1. BKN-BTI Section 227.53
2. RE-BTI Section 377.56
3. RTGH-RE Section 52.48
4. LGH-PLC Section 15.30
5. HMH-SDLP Section 68.21
6. Newly constructed ROBs 1245.32
7. EOT Crane 106.0
TOTAL 2092.4
Page 15 of 23
d) Calculation of ITKM of Bikaner Division.
a) 100M of waterway of major & important Bridge per
Track
= 3 ITKM
b) 1289.9 m of water ways of Major & Important Bridges = 1289.90x 3/100
= 38.697
= Say 39 ITKM
c) 100 M of water way of Minor Bridge, Tunnel, FOB,
ROB etc per Track
= 2 ITKM
d) 2092.4 m of water ways of minor Bridges, FOB, ROB
etc
= 2092.40 x 2/100
= 41.848
= Say 42 ITKM
No. of ITKM maintained by JP division (b+d) = 39+42
= 81 ITKM
5.2.3 CURRENT BENCH MARK OF JU DIVISION:-
No. of ITKM is maintained by JU & BKN division = (139+81)=220
On Roll Staff Cadre of the division = 34
Current Bench Mark = 34/220 Men/ITKM
= 0.15 Men/ITKM
5.2.4 Staff required as per Bench Mark norms:-
As per Railway Board letter no. 2006/E&R/2800/Rly/Imp./Vol.V/Corr.
Dated 20.05.2009 Bench marking norms of Bridge staff under SSE/Bridge/JU
are as under :-
Norms IR Avg BM Current Benchmark Division IRBM
Divisions < 500
ITKM
0.12/ITKM BVP 0.02/ITKM
Divisions > 500
ITKM
0.09/ITKM BSP,NGP,MAS,WAT 0.04/ITKM
Page 16 of 23
JU Division comes under the category of Division < 500 ITKM. If current
Benchmarking, as above, is taken into consideration the minimum staff
requirement comes out to = 220 x 0.02 = 4.40 men Say 5 men. However, if
the calculation of staff requirement is done in a liberal way and IR Average
of April, 2017 is taken into consideration, the staff requirement comes out to
=220 x 0.12= 26.4 Say 27 men.
Staff Sanctioned = 63
Staff required = 27
Surplus = 36
Thus, 63 - 27 = 36 posts are in excess to the requirement with respect to
required posts considering IR average benchmarking.
5.3.0 The requirement of staff as per work load:
5.3.1 The staff requirement has been arrived based on the practice followed by other
divisions for similar work and the work study reports which were already
approved by headquarters. The requirement of man days for each activity such
as inspection, painting, greasing and other miscellaneous works is tabulated in
the following paragraphs.
5.3.2 The work load is assessed based on the following:
i) Inspection of Girders
ii) Inspection of other structures
iii) Painting of Girders
iv) Painting of other structures
v) Greasing of Girders
vi) Miscellaneous activity
vii) Workshop
Page 17 of 23
5.3.3 Schedule of Inspection:
PSC Girders - Once in a year
Welded Girders - Once in three years
Riveted Girders - Once in five years
5.3.4 Painting:
Steel Girders - Once in five years
5.3.5 Calculation of Man days requirement:
Jodhpur division:
SN Activity Scope Man days
per 100
m of
waterway
Total man
days
required
Total man
days required
considering
journey
period(x1.25)
Total man days
required
considering
future increase
in scope of
work (x1.25)
1
General inspection
(80% of total water
way of all bridges)
4086.16 50 2043.1 2553.9 3192.31
2
Detailed inspection
(20% of riveted
girders)
1021.54 100 1021.5 1276.9 1596.16
3
Detailed inspection
(20% of riveted
girders)
650.199 100 650.2 812.7 1015.94
4
Oiling & Greasing
(33% of steel bridges
without E.B
565.775 100 565.8 707.2 884.02
5 Patch painting (5% of
steel girders) 113.155 40 45.3 56.6 70.72
6 Repairs (5% of total
linear waterway) 222.1925 100 222.2 277.7 347.18
7 Special works (2% of
total waterway) 102.154 100 102.2 127.7 159.62
8 Supervision of painting
by contractual work 452.62 20 90.5 113.2 141.44
9 Watchmen - - - 712.0 712
Total Man days required 4740.7 6637.9 8119.39
Page 18 of 23
Bikaner division:
SN Activity Scope Man days
per 100
m of
waterway
Total man
days
required
Total man
days required
considering
journey
period(x1.25)
Total man
days required
considering
future increase
in scope of
work (x1.25)
1
General inspection
(80% of total water
way of all bridges)
2705.84 50 1352.9 2029.4 2536.73
2
Detailed inspection
(20% of riveted
girders)
676.46 100 676.5 1014.7 1268.36
3
Detailed inspection
(20% of riveted
girders)
233.508 100 233.5 350.3 437.83
4
Oiling & Greasing
(33% of steel bridges
without E.B
261.475 100 261.5 392.20 490.27
5 Patch painting (5% of
steel girders) 52.295 40 20.9 31.4 39.22
6 Repairs (5% of total
linear waterway) 222.1925 100 222.2 333.3 416.61
7 Special works (2% of
total waterway) 67.646 100 67.6 101.5 126.84
8
Supervision of
painting by
contractual work
209.18 20 41.8 62.8 78.44
Total Man days required 2877.0 4315.4 5394.29
Page 19 of 23
5.3.6 Manpower calculation for Jodhpur & Bikaner Division:
Division Total
Man
days
required
Total
manpower
required as
per
workload
ITKM Total
manpower
required
as per
IRBM
Sanctioned
cadre
On
Roll
Vacancy Current
Benchmark
Jodhpur 8119.39 27.90 139.00 16.68
63 34 39 0.15 Bikaner 5394.29 18.54 81.00 9.72
5.3.7 No. of man days availed per year:-
No. of days per year = 365
Less deduction
CL = 10
National holiday = 12
Rest/Sundays = 52
Total = 74
Net man days available per year = 365 – 74
= 291
a). Requirement of staff for SSE/Bridge/JU & BKN
Total man days required = (8119.39+5394.29)=13513.68
No. of man days available per year = 291
No. of man required per day = 13513.68/291
= 46.43 Say 47
Page 20 of 23
CHAPTER-VI
MEETING WITH OFFICER’S LEVEL
Page 21 of 23
Page 22 of 23
CHAPTER-VII
CONCLUSION & RECOMMENDATION
7.0.0 On the basis of above work study the conclusion and Recommendation is
as under:-
7.1.1 Current Benchmarking of Indian Railway comes out to 0.12. In comparison
of Indian Railway Average Benchmark of Jodhpur and Bikaner division is at
much higher side i.e 0.38
7.1.2 Some of the important bridges in Western Railway are located in coastal
area along with the effect of chemical effluent which causes severe corrosion
in steel girders. Therefore more Staff are deputed for cleaning & patch
painting throughout the year. Whereas, Jodhpur and Bikaner division lies in
dry desert area of India where there is lesser chances of corrosion in steel
girders. So, less staff will be required in compare to Western Railway.
7.1.3 In Jodhpur and Bikaner division, the cleaning and patch painting work has
almost been outsourced.
7.1.4 The Benchmark of Western Railway is lowest in Indian Railway but if we
taken in account the Indian Railway Average Benchmarking the requirement
of staff comes to 16, against a sanctioned cadre of 39.
7.2.1 Recommendation: -
After thorough analysis of ITKM, Bridge section of Jodhpur & Bikaner Division,
the work study team is of the opinion that as per ITKM 27 staff are quite sufficient
to handle the existing workload. Keeping the lenient view, the existing workload
and in future additional workload, Dy. CE/Br. Line/JP has desired to hold 47 posts
of Bridge Section. Thus, 63 – 47 = 16 posts) (16 vacant post of Bridgeman of
GP-1800) are surplus which may be surrendered forthwith.
Page 23 of 23
CHAPTER-VIII
FINANCIAL SAVINGS
8.0 Financial Savingss: -
With the proposal of surrender of 16 posts of Group ‘C’ (GP-1800) the recurring
savings per annum in money value amount to as given below:-
S.
No. Designation
Grade
Pay
Mean
pay of
pay
matrix
DA @
5%
Total
Money
value
No.
of
posts
Total
saving/
month
Total
saving/
year
1 Bridgeman 1800 37450 1498 38948 16 623168 7478016
Total recurring savings per annum comes to approx. Rs.74.78 Lac.