Managing Moisture in Taller WoodBuildings -...
Transcript of Managing Moisture in Taller WoodBuildings -...
Calgary Mid-rise Workshop 2016-02-04
Managing Moisture in Taller Wood Buildings
Building Enclosure Design Fundamentals
7 Separates indoors from outdoors, by controlling:
7 Water penetration
7 Condensation
7 Air flow
7 Vapor diffusion (wetting &drying)
7 Heat flow
7 Light and solarradiation
7 Noise, fire, and smoke
7 While at the same time:
7 Transferring structural loads
7 Being durable andmaintainable
7 Being economical & constructible
7 Looking good!
G.Finch - RDH - [email protected] 1
Calgary Mid-rise Workshop 2016-02-04
Building Enclosure Control Functions & Critical Barriers
Water Control – 5&6 Storey Wood-frame
7 Increased height = increased rain deposition at upper floors and cumulative run-down at lower levels
7 Water shedding features become more critical – continuity, drip edges, flashings etc.
7 Increased exposure to moisture during construction (severity & length of time)
7 Need for more robust water penetration control strategy–good practice: drained & ventilated rainscreen
G.Finch - RDH - [email protected] 2
Calgary Mid-rise Workshop 2016-02-04
Keep Wood Dry During Construction
7 Keep wood drying during construction
7 Have seen issues in west where wood assemblies have got too wet during construction and resulted in delays & significant costs to dry out
7 Hence guidance for protection during construction, temporary roofs, immediate roofing, windows, wall/roof water resistive barrier (WRB) pre-application, built-in assembly design & redundancy for drying
Protect Wood from Water – But Not tooLate
7 Ensure adequate rainwater protection for heavy mass timber elements such as CLT, nail-lam, LVL/LSL/PSL, glulams etc. and multi layer plywood assemblies – especially for horizontal surfaces
7 Either choose pre-application of waterproof elements or invest in good site protection
G.Finch - RDH - [email protected] 3
Calgary Mid-rise Workshop 2016-02-04
Construction Practices for Mid-rise Wood Frame
7 Many contractors in west will either intentionally (or unintentionally) invest in site protection so that roofing/waterproofing can be applied in inclement weather onto dry materials
7 Typically observe that walls are seldom covered with a WRB until top floor framing is complete
7 However window sills & rough openings generally covered right away – allow for immediate window install & site close-in as fast as possible
Site Protection & Sequencing
G.Finch - RDH - [email protected] 4
Calgary Mid-rise Workshop 2016-02-04
Site Protection & Sequencing – Far North
Managing Exposure - Wall Assemblies
7 Drained & ventilated rainscreen clad walls have been standard on essentially all mid-rise wood-frame buildings in Pacific Northwest for more than the past decade
7 A minimum code requirement for most western jurisdictions and good practice in all climates for this height & exposure of building
7 Details for drainage & ventilation equally as important!
G.Finch - RDH - [email protected] 5
Calgary Mid-rise Workshop 2016-02-04
Why Rainscreen for Mid-rise Wood?
7 Significantly improves wall assembly & cladding durability – reduces risk
7 Rainscreen cavity also allows for wood-frame construction tolerances to be concealed behind cladding
7 A 3/4” cavity created by vertical strapping/furring most common in mid-rise wood-frame – is above code minimum 3/8” (10 mm)
7 Strapping also helps keep WRB/AB membrane in place during construction
Rainscreen Claddings
G.Finch - RDH - [email protected] 6
Calgary Mid-rise Workshop 2016-02-04
Exterior Insulated Rainscreen Claddings
Water Resistive Barriers in Mid-rise Wood-frame
7 Water Resistive Barrier, WRB (aka sheathing membrane)
7 Secondary plane of moisture protection & innermost plane that can safely manage moisture and drain & dry it back out
7 Many different products available (mechanically fastened, self-adhered, & liquid applied)
7 Many products can also be taped/sealed/applied as air barrier – discussed later
7 Both vapour permeable & impermeable products available– choice depends on insulation placement & wall design
G.Finch - RDH - [email protected] 7
Calgary Mid-rise Workshop 2016-02-04
Care with Impermeable Materials and Wet Wood
7 Need to be careful with the use of vapor impermeable materials over wood that is wet or could get wet in service
7 Self adhered membranes
7 Metal flashings
7 Foam plastic insulations*
7 Vapor diffusion wetting & drying ability for assemblies & details should always be assessed – ensure balance
Vapor Retarders / Barriers
7 Vapor Retarders / Barriers control the diffusion of vapor through an assembly
7 Limit wetting (condensation)
7 At same time there is a desired to promote drying
7 Gets more complicated with exterior/split insulated assemblies & selection of AB/WRB materials and exterior insulation types
G.Finch - RDH - [email protected] 8
Calgary Mid-rise Workshop 2016-02-04
Vapour Control with Wood-frame Exterior Walls
7 Interior vapour barrier
7 Polyethylene, polyamide “Smart Vapour Retarder” or Vapour Retarder paint most common for standard wood-framed walls
› Canada – Poly most common
› US – Vapour Retarder paint or Smart Vapour Retarder more common
7 Vapour control strategies are reassessed in walls with exterior or split insulation
7 Interior vapour barriers do not need to be the primary airbarrier
Other Vapour Retarder / Barrier Materials
7 Concrete, glass, metal, plastics
7 Polyethylene sheet
7 Impermeable peel & stick
7 Vapour barrier paint, smart vapour retarder
7 Wallpaper
7 XPS, EPS & Polyiso
7 Closed-cell sprayfoam
7 Plywood/OSB (at low RH levels)
G.Finch - RDH - [email protected] 9
Calgary Mid-rise Workshop 2016-02-04
400
1200
1600
2000
Perm
eance
(ng/P
asm2
)
800
11.1 m m O S B
12.7 m m Plywo o d
~0.5 to 2 perms
Plywood~20 perms
OSB~6 perms
00 % 2 0 % 4 0 % 6 0 % 8 0 % 1 0 0 %
Relat ive Humidity
See ASHRAE Handbook of Fundamentals & Other Sources for Vapor Permeance with RH
Plywood and OSB - Impact of RH on Vapor Permeance
One Not So Great Practice Developed in BC
DO NOT DO THIS
G.Finch - RDH - [email protected] 10
Calgary Mid-rise Workshop 2016-02-04
Air Barrier Systems, Materials & New Trends
Air Barriers for Mid-rise Wood Buildings
7 Air Barrier Systems must:
7 Be Continuous
7 Be Durable
7 Resist Structural Loads –Sufficient Stiffness & Strength for Design Wind Load
7 Be Airtight
7 Not negatively affect durability or vapor diffusion drying ability
7 Air barrier materials and approaches suitable for low-rise buildings may not be appropriate for mid-rise(5&6 storey) wood-frame
G.Finch - RDH - [email protected] 11
Calgary Mid-rise Workshop 2016-02-04
Many Wood-frame Air Barrier System Options
7 Choice depends on a variety of factors including wall design & builder familiarity with system
7 Common Air Barrier Systems
7 Sealed Polyethylene (mastic & tapes)
7 Airtight Drywall (drywall/gaskets/sealant)
7 Sheathing Membrane (mechanically attached, taped &sealed)
7 Sheathing Membrane (self adhered or liquid applied)
7 Sealed Sheathing Board (sealants/tapes at joints)
7 Spray Polyurethane Foam & sealants
Air Barriers Are Systems
AccessoriesMaterials Components
Whole Building
Airtightness
G.Finch - RDH - [email protected] 12
Calgary Mid-rise Workshop 2016-02-04
Wood-frame Mid-rise Air Barrier Trends
7 Trend towards exterior air barrier approaches (at sheathing plane) utilizing rigidity & simplicity of exterior sheathing
7 Sealed sheathing membrane approach(vapour permeable AB/WRB)
7 Mechanically attached (taped & sealed), $
7 Self-adhered membrane, $$$
7 Liquid/fluid applied,$$$
7 Sealed sheathing approach(plywood/OSB/ext. gypsum AB) w/ loose WRB
7 Sealed sheathing joints (sealant or tapes), $$
7 Use of interior approaches not as common or as effective for mid-rise buildings
7 Sealed poly not appropriate for this height
7 Airtight drywall not widely used
Shift to the Exterior Air Barrier
7 Industry shift in midrise wood buildings from the use of interior airbarrier approaches (poly, drywall) to exterior sheathing approachesas the primary air barrier element
7 BUT! still need to maintain a reasonable degree of airtightness at interior side of cavity insulation (convection suppressor)
7 Vapor barrier/retarder at interior side depending on insulation ratio& type
With enough exterior insulation – risk for condensation at sheathing decreases as does need for interior air tightness
Primary Air Barrier System
Secondary Airtight element
G.Finch - RDH - [email protected] 13
Calgary Mid-rise Workshop 2016-02-04
Airtightness Does Not Happen By Accident
Building Enclosure Assembly Detailing
(WSS)(WRB)
(AB)(VR/VB)
(Insulating Materials)
G.Finch - RDH - [email protected] 14
Calgary Mid-rise Workshop 2016-02-04
Wood-frame Mid-rise Air Barrier System Trends
7 Trend towards exterior air barrier approaches (at sheathing plane) relying on rigidity of wood/gypsum sheathing
7 Sealed sheathing membrane approach
7 Mechanically Attached (Taped & Sealed), $
7 Self-adhered Membranes, $$$
7 Liquid/Fluid Applied, $$$
7 Sealed sheathing approach(plywood/OSB/gypsum)
7 Sealed joints (good sealant or tapes), $$
7 Use of interior approaches not as common for mid-rise
7 Sealed poly not appropriate for height
7 Airtight drywall not widely used
Mechanically Attached Air Barrier Membranes
7 Loose sheet mechanically attached to wall with cap staples/nails and sealed with tapes, self-adheredmembrane and sealants
G.Finch - RDH - [email protected] 15
Calgary Mid-rise Workshop 2016-02-04
Challenges with Mechanically Attached Air Barriers & Wind During Construction
Rigid Support for Mechanically Attached Air Barriers During Construction & In-Service
G.Finch - RDH - [email protected] 16
Calgary Mid-rise Workshop 2016-02-04
Exterior Insulation Sandwich Support for Mechanically Attached Air Barriers
Mechanical Attached Air Barriers & Masonry
G.Finch - RDH - [email protected] 17
Calgary Mid-rise Workshop 2016-02-04
Interfaces & Challenges - Penetrations
Interfaces & Challenges – Balconies & Roofs
G.Finch - RDH - [email protected] 18
Calgary Mid-rise Workshop 2016-02-04
Mechanically Attached Air Barrier Details
7 Pre-stripping AB membrane is often recommended at framing interfaces & roof-wall transitions – but usually forgotten!
Interfaces & Challenges – Parapet Solutions
G.Finch - RDH - [email protected] 19
Calgary Mid-rise Workshop 2016-02-04
Interfaces & Challenges – Parapet Solutions
Sealed Sheathing Approach Air Barrier
7 Joints in sheathing (Plywood, OSB, Gypsum) aresealed with good sealant (usually silicone), strips of self-adhered membrane, or high-quality tapes
G.Finch - RDH - [email protected] 20
Calgary Mid-rise Workshop 2016-02-04
Sealed Sheathing Approach Air Barrier
Sealed Sheathing Approach Air Barrier
G.Finch - RDH - [email protected] 21
Calgary Mid-rise Workshop 2016-02-04
Sealed Interior Sheathing (Pre-fab Wall)
Sealed Sheathing Approach – Water Protection
7 Mechanically attached Water Resistive Barrier (WRB) loosely installed over top of sheathing, but not taped and detailed as the air barrier
G.Finch - RDH - [email protected] 22
Calgary Mid-rise Workshop 2016-02-04
Case Study: Portland, Orchards Passive MURB
Orchards at Orenco, Walsh Construction
Self-Adhered Air Barrier Membranes
7 Self-adhered membranes (typically vapour permeable) applied to exterior wood sheathing along with tapes/self-adhered membranes at interfaces
G.Finch - RDH - [email protected] 23
Calgary Mid-rise Workshop 2016-02-04
Self-Adhered Air Barrier Membranes
Self-Adhered Air Barrier Membranes
Provides benefits of full sided wrapping for ease of detailing, addressing soffit/sloped details and shipping
G.Finch - RDH - [email protected] 24
Calgary Mid-rise Workshop 2016-02-04
Liquid/Fluid Applied Air Barrier Membranes
7 Liquid/Fluid applied membranes (roller, brush or spray)applied to sheathing with sealants/tapes or reinforcingat all joints, gaps, and fasteners
Applying Liquid Applied Air Barrier Membranes
G.Finch - RDH - [email protected] 25
Calgary Mid-rise Workshop 2016-02-04
Joints in Liquid Applied Air Barrier Membranes
“band-aid” joints and butt joints Reinforced tapes, meshes& membranes
Joints in Liquid Applied Membranes
G.Finch - RDH - [email protected] 26
Calgary Mid-rise Workshop 2016-02-04
Hybrid Approaches
7 Liquid applied membrane window rough openings becoming common approach with various air barrier approaches – cost effective & simpler than SAM origami
Air Barrier Challenges & Material Compatibilities
SBPOhouse wrap
“special silicone”
Below grade Granulated SBS membrane
Concrete Foundation wall
Foil faced SAM
Silicone membrane over plywood
Silicone sealant at joints and fastenerholes
Foil-faced SBS
Below grade SBS over Concrete Foundation
Cement board over XPS
G.Finch - RDH - [email protected] 27
Calgary Mid-rise Workshop 2016-02-04
New AB/WRB Materials in a Growing Market
7 Many new self-adhered and liquid applied vapour permeable sheathing membranes available on the market
7 Fills a niche of a combined vapour permeable air-barrier/ WRB on exterior ofwood sheathing in mid-rise wood-frame buildings
7 Current test standardsslowly adapting to thisclass of materials
Lessons Learned So Far with New Membranes
7 Not all products are created equal nor suitable for all substrates/applications
7 Key considerations & potential issues include:
7 Longevity, durability, exposure to UV & heat
7 Compatibility & adhesion with other materials
7 Flexibility and gap/crack bridging ability
7 Curing or adhering in cold weather – big issue in Canada
7 Important properties negatively changing with time
G.Finch - RDH - [email protected] 28
Calgary Mid-rise Workshop 2016-02-04
Wet Weather Challenges?
Compatibility Challenges?
G.Finch - RDH - [email protected] 29
Calgary Mid-rise Workshop 2016-02-04
Long-Term Durability Challenges?
Cold Weather Application Challenges?
G.Finch - RDH - [email protected] 30
Calgary Mid-rise Workshop 2016-02-04
Wood-frame Crack Bridging Challenges?
Vapor permeable self-adhered sheets
Liquids
Liquids
How Well is the Industry Doing – WA State?
G.Finch - RDH - [email protected] 31
Calgary Mid-rise Workshop 2016-02-04
How Well Is the Industry Doing – WAState?
0.10
0.00
0.90
0.80
0.70
0.60
0.50
0.40
0.30
0.20
1.00
4.50
4.00
3.50
3.00
2.50
2.00
1.50
1.00
0.50
0.00
5.00
Liquid Applied Sealed Sheathing (10 Buildings) (11 Buildings)
Sheet Applied (28 Buildings)
Curtain Wall/Window
Wall/Storefront (15 Buildings)
Airt
ight
ness
[cfm
/ft²
@75
Pa]
Airt
ight
ness
[L/(
s·m
²) @
75Pa
]
Leakiest tested
Tightest tested
Median & 1st/3rd
quartilerange
WA StateRequirement
54 Buildings, Oct 2015 RDH SEAData
Passive House Range equivalent ~ 0.6ACH50
Passive House Airtightness
<0.6 ACH @50 Pa~0.035 cfm/ft2 @75 Pa
Self-adhered sheet membrane primary AB, transition to poly at ceiling
G.Finch - RDH - [email protected] 32
Calgary Mid-rise Workshop 2016-02-04
Passive House Airtightness
0.13 ACH @50 Pa~0.014 cfm/ft2 @75 PaSealed sheathing primary AB transition to SA membrane at roof
Maintenance & Renewals Considerations
G.Finch - RDH - [email protected] 33
Calgary Mid-rise Workshop 2016-02-04
Maintenance and Renewals
7 Recognize how the in-service stage of a building’s life can impact maintenance and renewals
7 Architectural design of building is impacted
7 Accessibility and durability
7 Above 4 storeys – can no longer use a ladder!
7 Need to provide fall arrest anchors for Bosun chair, swingstages
7 Boom lifts – movement around the building and structural support provided by garage roof slab
Maintenance and Renewals
7 Dryer vent cleaning
7 Easily accessible from balconies or roof?
7 Additional lint clean-out
7 Condensing units?
7 Durable enclosure components
7 Minimal maintenance claddings & finishes
7 Durable Sealants
7 Corrosion resistant metals
7 Higher quality windows
G.Finch - RDH - [email protected] 34
Calgary Mid-rise Workshop 2016-02-04
Summary
7 Environmental Loads
7 Increase in height = higher wind and rain loads
› More robust air barrier systems
› Improved water penetration control strategy – appropriate assembly, materials and details - rainscreen
› Longer construction duration means more focus on drying and protection from moisture during construction
7 Claddings & Materials
7 Non-combustible claddings & in many cases non-combustible insulation
7 Thermal Performance & Energy Efficiency
7 More structure – less room for insulation, other services
Summary
7 Wood-frame Shrinkage
7 Higher shrinkage in 5&6 storey wood-frame – manage with:› Limit amount of cross grain wood, modified platform framing &
engineered floor joists/headers
› Use dry wood (and keep it dry)
› Horizontal compartmentalization and joints in cladding design
7 Details are critical, plan for appropriate slopes after shrinkage
7 Maintenance & Renewals
7 Access for maintenance is a significant issue – need to design for it & provide suspended access anchors
7 Consider reduction in extent and frequency of maintenance required through choice of components and materials
G.Finch - RDH - [email protected] 35
Calgary Mid-rise Workshop 2016-02-04
Additional Resources
7 Building Enclosure Design Guide –Wood-frame Multi-Unit ResidentialBuildings (HPO, 2011)
7 Currently being updated with latest information & new details, release late 2015
7 Guide for Designing Energy Efficient Building Enclosures (HPO, CWC, FP Innovations, 2013)
7 Illustrated Guide R-22 Effective Walls in Wood-frame Construction in BC (HPO, COV, 2015)
Discussion
GRAHAM FINCH – [email protected] - 604.873.1181
7 rdh.com
G.Finch - RDH - [email protected] 36