Mammoet+World+02

20
5/26/2018 Mammoet+World+02-slidepdf.com http://slidepdf.com/reader/full/mammoetworld02 1/20  WORLD MAMMOET 2  O       2       0       0       2 worldwide specialists in heavy lifting and transport VAN SEUMEREN GROUP 

Transcript of Mammoet+World+02

  • 5/26/2018 Mammoet+World+02

    1/20

    WORLDMAMMOET2

    O2002

    w o r l d w i d e s p e c i a l i s t s i n h e a v y l i f t i n g a n d t r a n s p o r t V A N S E U M E R E N G R O U P

  • 5/26/2018 Mammoet+World+02

    2/20

    Does the mission statement make

    any sense?

    The mission statement keeps us eager to improve

    continuously our performance, personally and as a

    team that has versatile and fascinating equipment

    to its disposal. For many jobs, it is required that

    we can act quickly with short lead times. This is

    the main reason that our organizational architec-

    ture counts for regional building blocks, or busi-

    ness units that are fairly autonomous. They man-

    age their own staff, equipment, network and other

    assets. Customers may remind us to our mission

    statement at any time, thus pushing us to the best

    solutions and performance we can offer.

    So Mammoet should be looked upon as a

    federation?

    Not really. If we only had the regional business

    units, like in the Americas, Europe, the Middle

    East or Asia, our results would have been only a

    far cry from what we are now. This is becausethere is a flexible glue between and over these

    business units. Many big jobs have intercontinen-

    tal dimensions that cannot be managed from just

    one regional unit. This is where Mammoet Global

    comes in. It serves both as director for interconti-

    nental projects and as fallback support for region-

    al branches. For instance when exceptional equip-

    ment is required that only generates revenue if

    applied worldwide. Just because of Mammoet

    Global, any customer can get any type of required

    equipment and specialists, even if it does not

    belong to the regional fleets.

    What is the trend in intercontinental

    projects?

    I would summarize this as from factory to foun-

    dation. Think of power generators or steam drums

    that are manufactured in Europe, and must be put

    together in the States. Imagine parts of offshoreplatforms that are constructed around the world,

    but will be assembled into one structure at some

    yard, or at some location in shallow seas.

    Remember the huge investments in green energy

    generation with windmills. All those projects need

    transportation and lifting solutions, synchronized

    with many operations around the world. In fact, if

    we have the ambition to increase our added value

    in the customers chain, we must have the capaci-

    ty for world wide project management. As such,

    Mammoet Global can be considered as the spine

    of our company, with regional business units as

    our head, arms and legs.

    Can you indicate what it means to become

    the best full service provider as indicated

    in the mission statement?

    It means our ambition is to be the best partner

    for our customers they can imagine, solving any

    lifting or transport issue. With being the best,

    I emphasize to be the best in the range of avail-

    able equipment, the best in know-how, crews,

    engineering and maintaining high safety stan-

    dards. Moreover, we push these aspects continu-

    ously. Take for instance the safety standards.

    By having a constant focus on quality and safety

    improvement throughout our organization,

    processes and procedures, we are certified to

    execute very specialized lifting and transport jobs

    in challenging circumstances. Like live petro-

    chemical plants and nuclear power stations.

    Safety is priority number one and thus the

    foundation of our ambition to be the best

    in class.

    Introduction

    As I walk along

    the beach of my

    favourite Dutch

    isle Ameland,

    in a rare of f duty

    moment, many

    thoughts come

    into my mind. It has really been

    an incredible year, just af ter the

    establishment of Mammoet

    new style.

    So many fascinating results have

    been achieved and of course the

    salvage o f the Kursk has brought

    us in the focal point of the inter-

    nationa l press . Yet, I w onder:

    why us?

    I mean, the world is so big, and is

    home to so many brilliant people

    in any branch you can imagine.

    What is it, really, that we apparent-

    ly can offer wh ilst working at the

    cutting edge of our business?

    Its a basic question. Despite the

    roaring of the waves breaking on

    the beach, the wind that blows

    around and the eerie sounds of

    seagulls that seem to play on the

    division between water and air, no

    easy answer pops up. Of coursewe have skilled and experienced

    crews around the world. Of course

    we invest in state of the art equip-

    ment, i n innovative developments,

    in networks and contacts.

    But these are only pieces and

    bits o f the answer.

    At some distance a big crab fights

    its way through the white foam to

    the beach. It chases a small crea-

    ture I cannot identify. Poor little

    fellow. He did n ot make it.

    And suddenly that s it! Imagine

    the little one to have grown by

    predating even smaller organisms

    that in their turn probably feed on

    microscop ic plankton.

    I just witnessed one act in an end-

    less chain, and even the big one

    could end up on my plate tonight

    in that cozy fish restaurant.The food chain. Chains!

    Mammoet as such, with equip-

    ment, st aff, engin eers and assets,

    acts li ke a cha in, but also offers a

    vital part in the chain of its cus-

    tomers. As long as our part is not

    the weakest, we continue to add

    value. Whether it concerns the

    construction or renewal of petro-

    chemical plants, power stations,

    civil works, wind mills or even that

    salvage o f the Russian submarine

    Kursk, our secret comes down

    to the value adding chain.

    My personal mission, alike with

    that of all my colleagues is to offer

    tailor made solutions for any chal-

    lenge in the heavy l ifting and

    transport business.

    This best solution must be safe,feasible, executable and reason-

    able in price. S o, for any cus tomer,

    we determine the best fitting mix

    of engineering, equipment, capaci-

    ty, crews, technology, adaptations

    and ski lls. Bec ause the availab le

    range wi thin all these assets is so

    vast, we are able to act worldwide

    at the specialist s forefront so lving

    the most difficult problems, in

    parallel to many clients that

    require standard ized of f the shelve

    solutions. Both require the best

    support in the ir respective

    circumstances.

    The crab finished its meal.

    Sure, the little fellow will never be

    heard o f anymore. Yet, it played i ts

    part in the li fe cycle, the endless

    chain of processing and renewal

    of life. Strange as it may sound,the crab applied maintenance to

    itself. Otherwise, hell lose his

    strength, and become prey itself.

    Thats another lesson: to stay

    the strongest part of the chain

    requires maintenance of your

    assets, of people, equipment,

    networks . Recent developments

    that you will find in this issue will

    illustrate what I mean.

    I shiver as gusts of rain pour down

    from heavy clouds that rush along

    the sky. A lesson learned in the

    loneliness under the wide-open

    skies. Time to return for some

    personal maintenance in a warm,

    cozy place

    Frans van Seumeren,

    President & CEO Mammoet.

    Mammoet Global:

    spine of the company

    To be the best full

    service provider

    in the global mar-

    ket for engineered

    heavy lifting and

    multimodal trans-

    port, for the

    benefit of our

    customers, shareholders and

    employees.

    A bold Mission Statement thatperfectly embodies the Mammoet

    ambitions. However, words are

    easily written down.

    How do you achieve this goal?

    Roderik van Seumeren, Managing

    director of Mammoet Europe and

    Mammoet Global, admits that

    putting forward a statement doesnt

    necessarily mean that you are

    that best global player.

    MAMMOET WORLDWIDE

    BOARD OF MANAGEMENTBOARD OF MANAGEMENT

    EUROPEEUROPE ASIAASIA

    MAMMOET GLOBALMAMMOET GLOBALAMERICAAMERICASS

    MIDDLE EASTMIDDLE EAST

    EMDEMD

    = strategy/investments/reporting

    = com.projects/availabitity equipment

    Changing chains

    Mammoet World 2002 Page 2

  • 5/26/2018 Mammoet+World+02

    3/20

    The Kursk salvage: the impossible job

    Transport of the Bollard

    Early in January 2002, Mammoet inaugurated its new head office

    in Schiedam, at the former Wilton Feyenoord premises.

    The landmark structure, named The Bollard, is remarkable in

    many respects. It was completely pre-fabricated at Grootint in

    Zwijndrecht, some tens of kilometers upstream of the Maas River.

    Of course, Mammoet itself executed the load-out and transport

    from the yard to its final location. Within weeks after the delivery,

    the plug & play building was ready toreceive the Mammoet staff.

    How do you transport such an extraor-

    dinary building? Its a matter of engi-

    neering. For instance, Mammoet

    designed a special cradle that could

    absorb all dynamic loads during the

    transport. This structure resembles a giant wheel with 14 spokes.

    It accommodated the 2500 tonnes building while 128 axle lines

    of self propelled SPMTs could be maneuvered underneath.

    Before starting the tow, the steel cradle was fixed to the pontoon,

    while 50% of the load remained on the SPMTs that were arranged

    in 9 rows. A major obstacle was the Botlek Bridge. In order to

    clear its top frame, leaving a margin of only 90 centimeters, the

    pontoon had to be ballasted temporarily. At that time, the tide wasat its lowest. The voyage from Grootint to the new Mammoet

    premises took only one day to complete. Ahead of schedule, the

    structure was lowered within 2 millimeters of margin onto the

    foundation. For Mammoet, this unique transport of the first ever

    offshore built building was the second highlight in one week.

    It was achieved in the same week the Kursk was lifted.

    More than 60 international journal-

    ists reported minutely on the salvage

    of the Russian submarine Kursk.

    Among them representatives of AP,

    Itartass, AFP, Reuters, CNN. What

    then, is there to be told yet, that

    hasnt been told before? A project

    unique in history, exhilarating froma technical point of view. But at the

    same time the final stage of a

    tragedy that took the lives of 118

    seamen, leaving so many in grief

    and despair. Mammoet Worldasked

    Jan van Seumeren, Technical direc-

    tor and Jan Kleyn, Principal engi-

    neer, both part of Mammoets

    Product and Development depart-

    ment which designed the technical

    salvage concept, to briefly reflect on

    the Kursk.

    We often work on special devices

    that are required to expand the

    Mammoet equipment fleet, or that

    are needed to address a very specif-

    ic challenge. Recently we completed

    engineering and the construction of

    the Jumping Jack (see back cover,

    ed.). But the Kursk salvage will

    always stay in our minds as an out-

    standing project. Right from the

    beginning, we were convinced that

    we could do the job since we quick-

    ly outlined a concept that would

    work. The 9000 tonnes of the Kursk

    was no exceptional mass, nor was

    the depth of 108 meters. In fact, our

    tremendous experience in all kinds

    of heavy lifting and transport should

    be enough asset to come up with a

    feasible idea. However, since thiswas offshore lifting, we needed a

    reliable partner that could provide us

    with a stable platform or pontoon,

    together with tug capability. This is

    where our partner Smit comes in.

    But the lifting concept was engi-

    neered here. After initial inspections

    it became clear that we could lift

    the main body of the wreckage by

    attaching plugs onto its hull. To

    explain it simpy: these plugs work

    similarly as the one you may apply

    at home to attach an object to the

    wall. Insert these and they automati-

    cally clamp firmly. In this case, the

    plugs penetrated the holes that were

    cut in the hull and then deploy

    clamps that stay fixed under the

    ships steel frame. The plugs were

    connected with bundles of steel

    cables to strand jacks. We calculat-

    ed that 26 plugs, strategically dis-

    tributed over the top of the hull,

    were sufficient. Lifting power was no

    problem at all. We expected that,

    apart from 9000 tonnes for the

    wreckage, possibly another 3000

    tonnes was needed to get the struc-

    ture unlocked from the muddy

    seabed. But our redundancy was farmore than these estimates. In fact,

    we simulated many different scena-

    rios with an advanced computer

    model and from this we learned

    what the margins were. Each strand

    jack could be opera ted independent-

    ly, synchronized with computer con-

    trol. This gave enough margins to

    counteract dynamical loads, should

    they develop in the hull.

    The most challenging aspect was

    of course the weather. Huge waves

    could impair the lifting process.

    To compensate the effect of the

    swell at sea, we designed a kind of

    computer controlled shock absorber.

    This allowed us to control the ten-

    sion on each cable dynamically du-

    ring the lift. The Kursk came loose

    more easily than we expected and

    the operations as such, including

    clamping her under the pontoon

    Giant 4, went without any incident.

    However, it was the first time that

    we lifted a load that we could not

    see at all!

    From the Kursk salvage scrapbook

    Mammoet issued an internal magazine to highlight the processing of the Kursk

    salvage for all its employees. A fragment of this unique story represents a

    tribute to all who contributed to this operation.

    On Sunday 7 October 2001, all plugs have been put in place. The load on the

    strand jacks is gradually increased. We now enter the most delica te part of the

    operation. The Kursk has sunk almost two meters into the mud. Very prudent

    lifting is needed and tha t can be achieved with the advanced computer con-

    trolled system that manages the load on all jacks. At the moment that all jacks

    apply 150 tonnes of power, a small shock is felt onboard the Giant 4. Insiders

    know what this means: the Kursk is about to come loose . That nigh t, at 1.45 am

    Central European Time, the Kursk rises from the sea floor, letting the Giant 4

    to sink a little deeper into the water. The feeling of relief and joy is hard to catch

    in words. Everybody knows that, once in the gri p of the plugs and jacks of

    Mammoet, from now on nothing will go wrong. The lifting operations slowly pro-

    ceed the next day and that evening, the Kursk is secured under the pontoon.

    Lets go to Murmansk! This implied the final stage of bringing the Kursk home.

    We had to deliver the hull in a giant floating dry dock. We knew in advance the

    draft of the Giant / Kursk combination to exceed the limit to sail into this dock.

    In effect, we had to lift the combination about 7 meters. At a Russian shipyard,

    two 100 meter long semi-submersible pontoons were readied in just 9 weeks!

    Named after the wives of Frans and Jan van Seumeren, Gon and Mar, the pon-

    toons were positioned at both sides of the Giant / Kursk and lifted the stack as

    planned. On 21 October, the final stages are completed. Supported by 12 tugs,

    countless Russian sailors that pull ropes and supervised by dozens of navy offi-

    cials, the Kursk reaches her final destination. Shes lowered onto stoppings in

    the dock, after which the plugs retract. A crown of flowers rests on the Kursk,in memory of those tha t finally came home.

    Mammoet World 2002 Page 3

  • 5/26/2018 Mammoet+World+02

    4/20

    Petrochemical

    EUROPEMAMMOET

    Trends in the market

    Although the

    growth in world

    markets tended to

    decrease last year,

    accelerated by the

    unfortunate events

    of 11 September

    2001, many manufacturers of petro-

    chemical products maintained their

    competitive edge. Many are consid-

    ering and realizing substantial expan-

    sions, especially in the Middle East.The general tendency is to increase

    the scale of production plants both in

    existing and new development sites.

    As a result the number and scale of

    required equipment, like vessels,

    reactors, flare stacks and others,

    increases as well. Thus, this larger

    and heavier equipment needs match-

    ing facilities for transport and lifting,

    all the way from their fabrication site

    to the final foundations. Mammoets

    versatile fleet of cranes, transport

    vehicles and specialized systems for

    jacking, skidding and ballasting per-

    fectly matches the needs. Among the

    Mammoet fleet are the five largest

    and strongest cranes in the world.

    It should be noted that the factory-

    to-foundation services not only

    require suitable transport and lifting

    equipment, but also a well organized

    worldwide logistics.

    These mega-projects are not limited

    to regional boundaries, but often

    involve many (sub)contractors locat-

    ed around the world. Moreover, when

    engineers and construction experts

    understand that heavy and large

    items are transportable and and

    liftable they can design new develop-

    ments around our equipment or,

    when we are aware of major new

    design developments, Mammoet can

    develop special handling devices.

    We should consider the develop-

    ments in the Middle East as an

    example. The largest petrochemical

    projects are currently found in Saudi

    Arabia, Qatar, Iran and Kuwait.

    Saudi Arabia and Kuwait have

    become global players and continue

    to increase the size and efficiency of

    their plants are improving their

    already solid market position.

    Activities in Oman, Bahrain and

    Yemen are also picking up pace.

    Mammoet closely observes these

    market developments and will antici-

    pate construction work loads to have

    the right equipment in place for

    heavy transport and lifting projects.

    Robin Koenis,

    Commercial Manager Middle East.

    Highlight

    Our customer realizes the PO-11

    project for the joint venture Lyondell /

    Bayer. It is a complex project, in

    which Mammoet participated with

    several contracts to provide cranes,

    transport equipment and rigging

    crews for of jobs like the construction

    of foundations, the installation of pipe

    racks, steel constructions, piping and

    the installation of storage tanks.

    A specialty was the Equipment

    Erection Contract, covering the com-

    plete logistics of approximately 400

    items, up to 390 t. It comprises

    offloading in the adjacent harbour,

    transport to the site, storage on a lay-

    down area and the final positioning of

    these items, including shimming and

    alignment. Mammoet constructed a

    special transport road with steel

    plates, 950 meters long and 7 meters

    wide, to ease the SPMT transports.

    Also our CC 2800 was used to erect

    a 165 meter high flare stack.

    Highlight

    In March 2001, Mammoet received a request from theHalt preparation Shell-Pernis to prepare a plan for

    exchanging a regenerator head with cyclones, at a weight

    of 350 tons and a reactor in two parts, of 225 tons each.

    After prep aring measurements and drawings , Mammoet

    initially offered to execute this job with the CC-4800

    crane. But after meetings with Shell and engineering

    bureau Jacobs, the weights were adapted and

    Mammoet was asked to replace the whole reactor.

    In mutual consultation, it was decided to apply the PTC

    crane. This compact crane, with a high standard for safe-

    ty and capacity has the advantage that it can be erected

    in very narrow spaces at refineries. Furthermore, the

    crane still can install very heavy items at an enormous

    radius, which improves schedules and reduces site

    movements.

    A short summary of the activit ies:

    1. Transfer of a 409 ton reactor, 285 ton regeneratorcyclone and a 35 ton airgrid with two 400 ton floating

    derricks on SPMTs.

    2. Transport of the reactor by means of 4 x 10 axle lines

    SPMTs, and turntables, transport of the regenerator by

    means of 2 x 12- axle lines SPMTs and transport of the

    airgrid by means of 8 axle lines SPMTs to temporary

    supports.

    3. Exchange of the existing parts.

    4. Lifting the new equipment from the temporary sup-

    ports and installation at the foundations.

    Shell stated that the cooperation went very smoothly in

    every stage of the project and the job was completed to

    their satisfaction.

    Project PO-11 Lyondell

    Location Rotterdam, The Netherlands

    Customer ABB Lummus Global B.V.

    Main equipment CC 2800, SPMTs

    Full service provider at PO-11

    Project DTC Shell Pernis

    Location Pernis / Rotterdam, The Netherlands

    Customer Shell Nederland Raffinaderij B.V.

    Main equipment PTC, LR 1250, SPMTs

    Having the best crane

    Mammoet World 2002 Page 4

  • 5/26/2018 Mammoet+World+02

    5/20

    Highlight

    Mammoet executed two projects at two

    separate plants of the company Ruhr

    Oel. The first project involved the trans-

    portation of a 440 t reactor, whichincluded a Ro-Ro operation from a

    barge in Dorsten. The reactor was then

    transported 12 kilometers over public

    roads to Scholven. Due to the dimen-

    sions (43 meters long, 7,5 meters wide),

    the transport of the reactor was under-

    taken during the night, this as always

    attracted a large crowd.

    Our CC-2800 and a tailing frame placed

    on the SPMTs were used to position the

    reactor onto its foundation in the middle

    of a live plant.

    The second project included the installa-

    tion of column weighing 100 t at Ruhr

    Oels, Horst location. A LR-1450 and a

    130 t capacity tailing crane were rigged

    to lift the column successfully off its

    transport to foundation. These activities

    were also executed in the middle of a

    live plant in a very congested area.

    Highlight

    Mammoet won a contract for the transport of two

    reactors (220 and 280 t) from The Netherlands to the

    Statoil Refinery. The offloading at Sydhavn was exe-

    cuted with a 900 t sheerleg, hired by Kranringen.

    With SPMTs, the 40 meters long load was transport-

    ed from the harbor to the site, through the streets of

    Kalundborg. The actual erection of these reactors

    was done by Kranringen with one of our CC 2600s

    with 200 t superlift configuration, assisted by a 400 t

    tailing crane of Kranringen.

    Highlight

    Mammoet was awarded a contract for the trans-

    port of three reactors from Richardsbay to

    Secunda, a distance of 650 km. About 40 people

    supported the transport, including police officers,

    teams for (dis)connecting power and telephone

    cables, and a crew for first aid and refreshments.

    The heaviest unit (268 Te) was 8 x 9, 10.5 meters.

    The convoy stretched over 100 meters and

    covered 34 axle lines of trailers. At a speed of5 15 km/hr, the distance was covered in 9 days.

    SOUTHAFRICA

    MAMMOET

    Columns on the move

    Project Kalundborg Statoil

    Location Kalundborg, Denmark

    Customer Wiab

    Main equipment CC 2600, SPMTs

    Through the streets of Kalundborg

    Project Secunda

    Location Secunda and Richardsbay, South Africa

    Customer Fluor Daniel

    Main equipment 5 MAN 700 hp transport tractors, conventional trailers

    From Richardsbay to Secunda

    Highlight

    Mammoet Italy won the contract for the transport

    over water and load-out of 8 tanks, using 24 axle lines of SPMTs at the

    Enichem plant in Ravenna. The water transport called for two consecu-

    tive barge trips with 4 tanks each. The load-out was done on a gas

    loading jetty and required high safety precautions. When a tank was

    due or berthed at the jetty, all operations were suspended.

    Upon unloading, six tanks were transported to a storage area at 250

    meter distance and delivered on temporary supports. The remaining two

    tanks were positioned directly on sand foundations. It was a challenge

    to keep the tight schedule as to prevent disruption of operations as

    much as possible. Mammoet succeeded with its professionalism and

    well prepared crew that were working in double shift.

    Last but not least, the plant is located in a former swamp area and thus

    after sunset, mosquitoes showed no mercy for our tired crew.

    Project Hydrocracker / CD Hydro

    Location Gelsenkirchen, Germany

    Customer Fluor Daniel, Ponticelli

    Main equipment CC 2800, LR 1450, SPMTs

    Mammoet World 2002 Page 5

    Project Enichem

    Location Ravenna, Italy

    Customer Alliani

    Main equipment SPMTs en barges

    Tanks & gas

  • 5/26/2018 Mammoet+World+02

    6/20

    Project SM1 Modernization

    Location St. James, Louisiana

    Customer Chevron Phillips Chemical Company

    Main equipment MSG-50 with 69 meter main boom and 43 meter jib, SPMTs

    AMERICAS

    MAMMOET

    Highlight This job was part of the customers Delayed Coker project.

    The Mammoet contract called for the loading onto barges of 65

    modules at two manufacturing sites near Maracaibo, Venezuela.

    Upon arrival at St. Croix, the modules were loaded in and transport-

    ed with SPMTs. The installation and setting of the items was execut-ed with the CC 12600 and a CC 4000 crane.

    Project Hovensa

    Location St. Croix, US Virgin Islands

    Customer Bechtel Corporation

    Main equipment CC 12600, CC 4000

    New building at the Virgin Islands

    Highlight A 670 t recycle column was transported, using two sets of double 14 axle

    line SPMTs. The transport was both over water and land. The remarkable

    lift required the application of our 2000 t tailframe that was supported with

    2 x 12 axle lines SPMTs during the lifting operations performed with the

    Platform Twin Ring HD. Just prior to the lift, this crane could be commis-

    sioned after its arrival from the UK. It took less than 6.5 weeks for derig-

    ging the crane in the UK, the sea transport, inland transport to St. James

    and erection of the crane.

    Project AS 4202 Rebui ld

    Location St. James, Louisiana

    Customer Chevron Phillips Chemical Company

    Main equipment Platform Twin Ring HD, tailing frame, SPMTs

    Highlight As part of a tu rnaround, the 33 meters h igh 450 t Vacuum Distilla tion Column (VDC) had to be

    replaced. This critical piece of equipment processes half of the crude oil at the site. Benicia

    experts already figured out that a gantry lift system should be preferred as to comply with safety

    rules applicable for the live plant. As Valero stated: We wanted to ensure companies bidding on

    this job were 100 percent committed to the safety and success, like we are ourselves.

    Mammoet was selected as contractor. The lift system comprised six tower sections and load

    beams, allowing north/south, east/west, up/down and rotation movements with the rectangular

    footprint of the structure. Each beam could handle 740 t, while loads to the soil were kept at a mini-

    mum, eliminating the need for counter weights.

    Project Valero Vacuum Distillation Column

    Location Benicia, California

    Customer Valero Refining Company

    Main equipment Strand jacks, Gantry system, lifting beams

    Committed to safety

    Lifting record in Louisiana

    Highlight

    With a mass of 840 t and a radius of

    59 meter, this lift set a world record for

    the combined weight / radius-factor.

    For this project, Jumbo Shipping dis-

    patched the vessels from Mumbay, India.

    Mammoet won the contract for the load-in

    with SPMTs and transported the construc-

    tions over the Mississippi dike to the site.

    The vessels were dressed at a storage

    area and finally transported to their foun-

    dations where the MSG positioned them

    properly.

    Mammoet World 2002 Page 6

    Platform Twin Ring HD with tailing frame

  • 5/26/2018 Mammoet+World+02

    7/20

    Highlight The Mammoet strand jack system was applied to

    install Rotary Breakers in one piece. Due to restrict-

    ed access, these objects could not be reached with

    a crane. In addition, Apron Feeders were also

    installed using the jacks. The severe cold weather

    conditions posed challenges to both the equipment

    and our crew.

    Project Shell Muskeg Rover Oilsands

    Location Ft. McMurray, Alberta

    Customer Shell Albian Oil Sands

    Main equipment Strand jacks, gantry system

    Strand jacks & Rotary Breakers

    Highlight Mammoet Canada Western was chosen for this project due to its track

    record and ability to meet project schedules within constraints of safety

    and professionalism. The job involved the road transport of 750 process

    modules from fabricators in Edmonton and Calgary to the Shell downstream

    project located in Fort Saskatchewan and the Upstream Project locationin Muskeg River. In addition, Mammoet performed the transport of large

    Coolers, Vessels, Electrical equipment and Cogeneration equipment.

    The bulk of the oversized cargoes were transported by road between

    Calgary and Edmonton, plus subsequent road transport to and from

    the rail sidings.

    Project Shell Athabasca I

    Location Scotford Ft. Saskatchewan, Alberta

    Customer Shell Downstream Upgrader

    Main equipment Specialized hydraulic trailers, prime movers

    Transport problem? Canadian trailers!

    Highlight Mammoet supplied heavy craneage and on site specialized transporta-

    tion systems for the exclusive onsite crane, rigging and transport of

    items, from start to finish. Thus, several large Reactors, Pressure

    Vessels, Flare Stacks, Coolers and Assembled Process Modules were

    erected and / or installed. The craneage included a lift and lock gantry

    system, strand jack and gantry systems to complete the large scale

    specialized quantities of process equipment that had to be handled.

    The versatility of the PTC, moving on its own crawlers and supported

    by a CC 4800 as tailing device, was essential for Mammoets success.

    A remarkable fact is that all heavy lifts and transports were engineered

    well in advance around our fleet.

    Highlight Mammoet won a contract to receive

    four large reactors up to 4 meters in

    diameter, 34 meters long and with a

    weight of 372 t. Upon arrival in the Port

    of Montreal, these structures were

    loaded onto heavy-duty 12 axle railcarswith large steel turntables, and secured

    for their 4000 km long voyage to

    Northern Alberta. Mammoet was also

    hired to temporarily store the reactors

    on the quay. When available, the reac-

    tors were loaded onto the railcars with

    a high capacity skidding system.

    The long journeyProject Suncor Millenium

    Location Montreal, Quebec

    Customer Suncor Energy

    Main equipment Railcars, skidding system

    Project Shell Athabasca IILocation Scotford Ft. Saskatchewan, Alberta

    Customer Shell Downstream Upgrader / Fluor Daniel

    Main equipment PTC, CC 4800, CC 2800, SPMTs, strand jacks, gantry system

    Engineering around Mammoets fleet

    Mammoet World 2002 Page 7

  • 5/26/2018 Mammoet+World+02

    8/20

    Highlight As part of the construction of a new refiner y, more than

    120 000 t of equipment has to be transported and

    installed. Among them are huge vessels of 900 t (2x), 600 t

    and 700 t. The items arrive in the Port of Guanta and are

    temporarily stored at the customs premises. For most

    items (i.e. less than 70 t), Mammoet arranges road trans-

    port over 40 kms to the construction site at Jose.

    The oversized items travel by barge. Upon arrival, the

    modules are transported to a storage area awaiting further

    dressing. When ready, the Mammoet crane fleet supports

    the final erection and installation. Highlight is to see the

    CC 12600 move along for 4.5 kms with its load!

    Project Hamaca Crude Upgrade

    Location Guanta and Jose, VenezuelaCustomer Fluor Daniel

    Main equipment CC 12600, CC 2600, CC 1400, SPMTs

    Installing 120 000 t of equipment

    ASIA

    MAMMOET

    Highlight Due to Mammoets rich history in Asia in general and Bintulu in particular, the company was

    awarded a contract to provide extensive (heavy)lift and transport services for the expansion

    of the largest LNG facility in the World, the Bintulu LNG facility. Heavy lifts involved the instal-

    lation of the two largest columns of the project weighing 700 t each, with the Manitowoc

    M 1200. CC 4800 and CC 2600 crawler cranes lifted the remaining part of the approximately

    500 items in the heavy lift category. Besides this, some 20 crawler- and hydraulic cranes

    installed the smaller items.

    The Bintulu project team consisted of 100 people which operated and maintained 30 cranes

    and more then 50 axle lines platform trailers. For this very large scale operation, a special

    work shop facility on site was set up, manned 14 hours a day, 7 days a week.

    Project Bintulu LNG facility

    Location Bintulu, Malaysia

    Client Kellog Brown & Root, JGC and Sime Engineering.

    Main Equipment Manitowoc M 1200, CC 4800 and CC 2600 crawler cranes, hydraulic cranes, platform trailers

    Mammoet World 2002 Page 8

    The largest facility in the World

  • 5/26/2018 Mammoet+World+02

    9/20

    Highlight Our customer constructs an expansion at the Masilla premises in the inlands of

    Yemen. Mammoet was contracted for the transport of all heavy items, up to 100 t,

    that were delivered to the harbor of Mukalla in the United Arab Emirates. The road

    from the harbor to the construction site is long, sometimes steep (up to 18% slope)

    and with many (hairpin) turns. Such winding and climbing roads make good and

    easy communications between the drivers essential, such as when to shift a gear.

    The route passed tribal areas, requiring upfront permission of the tribal eldest

    before the transport could come along. To increase safety, the Mammoet transport

    was served by the Yemeni army around the clock, an experience that became busi-

    ness as usual only after a few days. Our contract included the transport and jacking

    of the loads on the site, as to deliver them onto the foundations.

    Highlight

    The refinery partially exploded and isnow being repaired and refurbished.

    Mammoet is the responsible contractor

    for all heavy lifts and transports on the

    site and executes the erection of various

    large items.

    MIDDLE EAST

    MAMMOET

    Highlight The contract calls for receiving 12 heavy loads up to 160 t

    in the United Arab Emirates (UAE), the transport to a stor-

    age area, the reloading of the equipment onto barges and

    all necessary RoRo-operations. The equipment, from Korea,

    Germany and Italy arrived by heavy lift ships in Port Rashid

    or Jebel Ali Port both in Dubai. The cargo in Port Rashid is

    transported 26 kilometer over land to Jebel Ali, stored and

    reloaded prior to the transport across the Persian Gulf to

    Assaluyeh, Iran.

    Highlight

    Mammoet is responsible for the supervision of all heavy lifts up to

    180 t, needed for the erection of columns and vessels.

    Meanwhile, Mammoet completed at Pars 2-3 the lifting of 160

    vessels ranging from 100 to 300 t, 4 boilers with a weight of 300 t

    including the lifting of two 143 meter high Flare Stack with its CC3800, equipped with a 84 meter main boom and 84 meter fly-jib.

    The South Pars Field Development projects in Iran are supplied

    by the giant South Pars field which Iran shares with Qatar, the

    Qataris call the same field the North Field.

    Sofar, Mammoet has been involved with all the gas projects for

    the Iranian South Pars and the Qatari North Field at both sides of

    the Gulf. Mammoet executed the heavy lifting and transportation

    of the South Pars Phases 1, 2 and 3. Also at the Qatari side,

    Mammoet executed all the heavy lifting and transportation for the

    Rasgas by using its CC 4800 Twin Ring. Qatar-Gas projects

    invloved heavy lifts upto 700 t, by using the M 1200.

    Project South Pars 1 Gas Separation Plant

    Location IranCustomer Daelim Industrial Corporation, South Korea

    Main equipment SPMTs, 600 t crawler crane, 450 t cranes, smaller cranes

    Extension of Gas Separation Plant in Iran

    Project South Pars 1 Gas Separation Plant

    Location Iran

    Customer Azarab Industries Co. , Iran

    Main equipment CC 3800, CC 2400, 250 and 450 t crawler cranes

    Project Masilla Expansion Project

    Location Yemen

    Customer Canadian Nexen, Yemen

    Main equipment Prime movers, 12 axle lines conventional trailer

    Through the hills of Yemen

    Project Mina Al Ahmadi Refinery

    Location Kuwait

    Customer Fluor Daniel Engineering, UK

    Main equipment Sennenbogen 5500, CC 1800, 160 t telescopic crane

    Redevelopments in Kuwait

    Mammoet World 2002 Page 9

  • 5/26/2018 Mammoet+World+02

    10/20

    Project Tunnels

    Location Various locations in The Netherlands

    Customer Various governmental organi zations / construction companies

    Main equipment Craneage, transport equipment, barges

    Highlight At Gevelcos ya rd a bat ch of six high power ships engines

    for the German shipbuilding industry have been assem-

    bled. Mammoet first assisted in the local transport of

    parts, made elsewhere, to the assembly hall, using an 8

    axle conventional trailer. The heaviest item was a 125 t

    crankshaft. Gevelco managed to complete an engine in 10

    days by working around the clock. The engines were

    assembled on support beams and support stools, pre-

    installed by Mammoet. Later on, this allowed for self-load-

    ing using the trailer hydraulics.

    A complete engine had a we ight of 660 t and was 11

    meters high. Mammoet then moved the completed stacks

    with 16 axle SPMTs to the quay, presenting the cargo to a

    floating crane that lifted the engines onboard, prior to their

    shipment to Germany.

    EUROPE

    MAMMOET

    Trends in the market

    In many areas,

    civil works are

    picking up pace.

    The infrastructure

    of motorways with

    bridges and tun-

    nels, railways for

    high speed trains, corporate build-

    ings and public facilities such as sta-

    diums are being upgraded and

    expanded. This is especially true in

    Europe but it is also occurring inother parts of the world. Customers

    are increasingly pursuing higher effi-

    ciencies in their projects and are

    looking for expert partners to man-

    age the handling of equipment in

    larger components. Examples of the

    these activities are the insertion of

    large modular ship sections and the

    movement of portal cranes. Many

    contracts are being awarded for the

    factory to foundation concept,

    based on transport, lifting and

    assembly operations. Mammoet,

    both regionally and through Mammoet

    Global, is perfectly suited to address

    these challenges. Mammoet, the

    largest integrated lifting and trans-

    port company with worldwide cover-

    age, has a wide range of equipment

    and personnel at its disposal with

    hundreds of cranes and transport

    vehicles, specialized ballasting sys-

    tems for barges, skidding and sliding

    equipment, jacking and gantry sys-

    tems and dont forget the thousands

    of accessories necessary for this

    kind of work to meet all customer

    expectations. Many projects are

    complex both for technical and logis-

    tics reasons. Customers often have a

    local / regional scope and and there-

    fore understand and recognize the

    vital importance of the local pres-

    ence of Mammoet supported by its

    global expertise.

    Kees van Aarle, Market Segment

    Manager Civil Europe

    Highlight One of Mammoets specialties is to assist the

    positioning and line up of heavy equipment,

    such as Tunnel Boring Machines, needed to

    excavate tunnels. Currently, three different

    tunnels are in various stages of completion.

    One is the Westerschelde tunnel in the

    Province of Zeeland. This 6.6 km long tunnelconnects Zeeuws Vlaanderen to the rest of

    Zeeland and, at its deepest point, is 60 meters

    below sea level. Two other tunnels, the Botlek-

    and the Sophia railway tunnel are part of the

    Betuwe line, the new cargo train link between

    Rotterdam and Germany. The almost 10 meter

    wide, 110 t heavy cutting wheel was delivered

    as one complete structure into the launching

    shaft of these tunnels.

    The Betuwe line

    The Botlek tunnel

    The Sophia railway tunnel

    The Westerschelde tunnel

    Project Ships engines at Gevelco

    Location Rotterdam, The Netherlands

    Customer Gevelco

    Main equipment Conventional trailers, SPMTs

    Ships engines for Germany

    Mammoet World 2002 Page 10

    Civil

    Tunnel developments in Holland

  • 5/26/2018 Mammoet+World+02

    11/20

    Highlight

    The original idea to position this

    520 t bridge, manufactured by

    Fricke on land close to the site, was

    to skid the construction in front of

    its foundation, followed by a crane

    lift. However, considering the weight,

    the radius and the lack of space,

    Mammoet was forced to develop an

    alternative. We decided to skid the

    bridge onto two barges, equipped

    with stools partially constructed

    from standard and MSG ballast con-

    tainers. Because the foundation top

    is about 1.5 meters higher than the

    construction site level, we had to

    jack the construction as well to

    compensate for this difference.

    We used four 300 t strand jacks,

    positioned in pairs on both sides

    of the canal. These jacks lifted the

    bridge such that the barges could

    sail under the construction.

    By de-ballasting them, the bridge

    was lifted further until it could pass

    the top of the foundations.

    Final ballasting then delivered the

    bridge into its final position.

    Highlight

    Due to an expansion of Highway 4 in Germany, a new bridge was

    needed to cross the Mittellandkanal at an angle of 45 degrees.

    The bridge of 390 t was 90 meters long and 8 meters wide, had a 1.5

    meter curve to match the trajectory. This curve complicated the

    maneuvering of the construction, since the center of gravity was no

    longer along the middle axis. The bridge was assembled onshore.Mammoet won the contract for the final positioning of the bridge.

    The bridge was skidded onto a barge, perpendicular to its long axis.

    This barge was then towed to the construction site and turned over

    45 degrees, upon which the jacks were fastened to hoist the bridge

    upwards onto the foundation.

    Highlight

    The purpose of this job was to lift the main girder of a 1000 t Goliath

    Crane while the swivel-assembled legs remained attached. Mammoet

    rigged four masts of the MSG system, held together by four gantry

    girders, a stack of 105 meter high. An LR 1450 assisted in the lift thatsuddenly became spectacular. As the main girder reached 100 meters

    elevation, prior to welding works, the meteorological service forecasted

    a severe gale. Mammoet immediately secured the pending construction

    and the gantry system, as winds gusted to 30 meters / sec. However, no

    movement of the stack could be observed. It illustrates Mammoets quick

    on-site anticipation to changing circumstances, thus meeting safety levels

    at all times. Just to give an idea of what type of equipment is needed

    to realize such track record, we summarize the strand jacks that were

    applied. The number of a specific jack is between brackets: 900 t (4) for

    lifting, 300 t (6) for rigging the main girder, 100 t (12) to secure the

    swivel-assembled legs, small jacks (8) to support the rigging with tethers.

    About 50 kilometer o f rigging cable was used.

    Highlight Mammoet Fostrans won a contract to assist in the con-

    struction of the new Terminal E that will accommodate

    the newest generation of wide body aircraft. The opera-

    tions involve the roof construction and the assembly of

    152 concrete rings. The latter required the development

    of a dedicated lifting frame. With the frame, the struc-

    tures can be rotated and tumbled into the proper

    position. Each ring consists of three parts between

    33 and 61 t. Together, the rings support a glass roof of

    700 meters long.

    Highlight

    The consortium hired two crawler

    cranes and other equipment from

    Mammoet Fostrans. They assistedwith the installation of the 4800 t

    metal framework that supports the

    roof of the stadium above the west-

    ern and eastern platforms.

    Project Gantry Crane

    Location Stocznia Gdynia, Poland

    Customer Konecranes from Finland

    Main equipment Strand jacks, gantry system, LR 1450

    Severe gale in Poland

    Tailor made solutions for bridge installments

    Project Charles de Gaulle Airport

    Location Roissy, France

    Customer Roissy Charles de Gaulle Airport

    Main equipment CC 4200

    New terminal in ParisProject Installation of a bridge at Braunschweig

    Location Braunschweig, Germany

    Customer MAEG S.P.A. and Walter Bau AG

    Main equipment Barges, skidding system, strand jacks

    Braunschweig bridge

    Project Stadium Istanbul

    Location Istanbul, Turkey

    Customer Campenon Bernard France, Tefken Construction Turkey

    Main equipment Liebherr LR 1450, Manitowoc M 888, other cranes

    Heavy roof for stadium

    Project Positioning bridge, Herne

    Location Rhein-Herne Kanal, Germany

    Customer Fricke

    Main equipment Skidding and jacking system

    Mammoet World 2002 Page 11

  • 5/26/2018 Mammoet+World+02

    12/20

    EUROPE

    MAMMOET

    Trends in the market

    Although generally

    expected the late

    2000 and early

    2001 was a diffi-

    cult period for the

    offshore fabrica-

    tion yards in the

    Gulf Coast area. On the positive

    side the drilling and the deep water

    activity picked up. The engineering

    companies are very active with

    deep water development and somenew companies are investing in set-

    ting up their yards adding cranes

    and SPMTs, as well as heavy sys-

    tems. Also on the positive side we

    see more oil companies who want

    the load-out methods to comply

    with the North Sea Standards.

    These methods have generated

    considerable work for Mammoet in

    the past and will give Mammoet a

    chance to show our experience and

    maximize the utilization of our

    equipment. Last year Mammoet

    successfully introduced alternative

    lifting methods for stacking decks

    on top sides, with our tower and

    strand jack system. The deck and

    jacket refu rbish mar ket slowed

    down because of less activity in the

    Gulf Coast. This generally will pick

    up when the installation contractors

    are offshore and use their lift ships

    in between jobs, to pull out older

    platforms. This can be a lucrative

    market and is one of the reasons

    Mammoet USA has opened an

    office in Louisiana, we can react

    faster and more efficiently to

    client needs.

    Piet Nooren,

    Managing Director Mammoet USA.

    Highlight Ever played with construction blocks? Not with these

    oversized structures! In fact, the Ringhorne project com-

    prises four separate jobs that culminate in the delivery

    of a complete production platform the Ringhorne.

    1. Transport at Gothenburg, Sweden, of the 1100 t

    Living Quarters from the construction hall onto

    a barge.

    2. Do the same for the 1700 t and 3500 t DSM and

    DES production units at Grootint, Zwijndrecht

    (The Netherlands).

    3. Repeat it all over again at Heerema, Norway with

    the Topside of 6500 t.

    4. Go to Heerema, Vlissingen (The Netherlands) to pro-

    vide all cranes needed for the assembly of the 7900 t

    jacket and perform the load-out onto a barge when

    ready. This requires low tide, 234 axle lines of SPMTs

    with 936 wheels, and 30 ballasting pumps.

    Offshore

    Grootint, Zwijndrecht

    Heerema, Vlissingen

    Project Ringhorne

    Location Norway, Sweden, Netherlands

    Customer Heerema fabrication Group, Emtunga A.S.

    Main equipment SPMTs, smart jack system, ballast system, barges

    All pieces come together!

    Heerema, Norway

    Gothenburg, Sweden

    Mammoet World 2002 Page 12

    The Ringhorne

  • 5/26/2018 Mammoet+World+02

    13/20

    Highlight Mammoet installed a 450 t multi purpose

    mast on an offshore platform constructed

    by Amfels. This mast was built by Huisman-

    Itrec, with whom we worked closely together

    on the manufacturing of our PTC crane.

    This crane executed the job and was erected

    with 95 meters main boom.

    Highlight

    The Amethyst 4 submersible oilrig was

    built at Halter Marine in Pascagoula.

    It consists of two main pieces: the pon-

    toons and the deck box. Mammoets

    scope of work is to jack up the deck

    box, weigh it, to move it onto a barge

    while managing the ballasting and to

    design the sea fastening for the tow.

    The deck box will be towed to Portland,

    Maine, for the final assembly of the rig.

    When the contract was signed all skid-

    ding equipment was located in

    Schiedam and Malaysia.

    It was dispatched immediately to the

    States to meet the critical time schedule

    for the jacking and load-out operation.

    The deck box was on a quay but theclearance with the ground level was only

    1600mm, posing difficulties to move the

    jacking equipment under the construc-

    tion. A lift was necessary to install the

    skidding system that would perform the

    load out. Another issue was that this

    deck box was not designed to undergo

    a jacking operation. Mammoet was

    requested to come forward with an alter-

    native way to finalize the construction

    and this resulted in the need for the

    transport. Notwithstanding the small

    clearance, Mammoet managed to install

    its Smart Jack System with sixteen

    500 t -climbing jacks.

    The deck box was lifted one meter,

    enough to install the complete skidding

    system, consisting of 28 skid shoes of

    600 t capacity each. The total weight of

    the deck box appeared to be 5000 t.

    On 18 April Mammoet completed the

    load out. When the deck box arrives at

    Portland, Mammoet will jack up the deck

    box to a clearance of 4.6 meters abovethe deck of the barge, again using the

    Smart Jack System but now with 24

    climbing jacks. Finally the deck box will

    be secured to enable the mating to its

    pontoons.

    AMERICAS

    MAMMOETProject Dynamic Offshore

    Location USA

    Customer Dynamic Offshore

    Main equipment SPMTs, strand jacks, gantry system

    Emergency call

    Project Q 4000 multi purpose mast

    Location Brownsville, Texas

    Customer Amfels

    Main equipment PTC

    Old acquaintances

    Project Pascagoula

    Location Pascagoula, Mississippi / Portland, Maine

    Customer Cianbro

    Main equipment Skidding system, smart jack system, weighing system

    Move the unmovable

    Mammoet World 2002 Page 13

    Highlight Dynamic Offshore is a respected customer that main-

    tains ties with Mammoet for over 10 years. One day

    Mammoet received an emergency call: an accident hap-

    pened during a competitors attempt to jack two offshore

    decks of 760 and 550 t. Fortunately no one was hurt, butthe jacking equipment was severely damaged.

    Could Mammoet take over and finish the job?

    In record time, all necessary equipment was mobilized

    from various locations around the world.

    In the end, Mammoet managed to close out this job in

    less than 4 weeks. After the deck had been lifted with

    the jacks, the legs were positioned underneath.

    Upon fastening these legs, the complete structure was

    removed with SPMTs to a storage area. Then the second

    deck was hoisted up 45 meters, making room for the

    stored stack to move under. With the lowering of

    this second deck, the emergency job came to an

    uneventful end.

  • 5/26/2018 Mammoet+World+02

    14/20

    After the successful load-out of the CTOC jacket, Mammoet

    was awarded also for the load-out of the 18,100 t integrated

    deck. (104m x 46m x 34.2m high). Mammoets scope includ-

    ed the provision of 4 units of 900 t strandjacks with a total

    pulling capacity of 3600 t. The distance that had to be

    covered was 162 meters. The job marked the first pulling

    operations in South Korea.

    Project CTOC jacket

    Location Korea

    Customer Samsung Heavy Industries, Technip and Saipem consortium

    Main equipment Strand jacks, ballast system

    Load-outs in South Korea

    Mammoet World 2002 Page 14

    ASIA

    MAMMOET

    Highlight

    Last year, Thailand constructed its first Central Processing

    Platform ever. Our client UCU Alliance awarded B&J Mammoet

    for the load-out of this 925 t piece of equipment. The job was

    executed with 36 axle lines SPMTs and besides the load out,

    B&J Mammoet was responsible for the ballasting & mooring

    services.

    ABB awarded B&J Mammoet for the load-out of a 530 t mod-

    ule and 5 manifolds. The crew and Scheuerle platform trailers

    completed the load-out within a timespan of 24 hours. The 50

    t manifolds were lifted onto the barge. The project was a total

    package including all seafastening design and installation as

    well barge supply, ballast- and intact stability calculations, port

    & agency duties etc. The modules are destined for the tanker

    Berge Helene from Bergesen Norway which will be convert-

    ed into a FPSO.

    Highlight A record setting heavy lift i nvolved hoisting up topsid es of

    more than 11 000 t to a height of 20 meters, using strand

    jacks. The load-out truss, having a weight of 1600 t was

    positioned underneath using SPMTs. Subsequently, the

    complete stack was pulled onto the barge with strand jacks.

    The customer submitted an acknowledgement of satisfac-

    tion, stating the job was executed professionally and effi-

    ciently, on time and without incidents. The cooperation

    between staff and the quality of pre-engineering were of

    outstanding quality. In fact, this smooth load-out and the

    ease with which you skidded this construction along the

    quay onto the pontoon, did not match with all I have

    learned on friction techniques.

    Project Malampaya offshore

    Location Singapore

    Customer Sembawang Marine Offshore Engineering

    Main equipment Strand jacks, SPMTs, skidding

    This is heavy lifting!

    A novelty for ThailandProject Offshore load outs

    Location Thailand

    Customer ABB and UCU Thailan d

    Main equipment SPMTs, platform trailers and LTM 1450

    Highlight Four strand jacks, with a capacity of 2000 t, were

    needed to move a 180 meters long jacket of 7000 t

    over the quay onto a barge. The Mammoet ballasting

    system compensated for the tide differences and the

    load development during the operations.

  • 5/26/2018 Mammoet+World+02

    15/20

    Highlight As part of a s cheduled ma intenance, three steam gener a-

    tors manufactured by MHI (Japan), were to replace old

    equipment at Tihange. Mammoet transported these itemsof 330 t from the quay to the construction site with SPMTs.

    The old generators were lifted out of the hall with our spe-

    cial gantry system and transported to a storage area.

    Having finished this job, the gantry system picked up the

    new items and positioned them onto the foundations.

    Mammoets high safety standards are compatible with those

    required for operations in nuclear power plants.

    Project Tenne T,

    Location Various locations,The Netherla nds

    Customer Smit Transformatoren

    Main equipment SPMTs, barges, jacking system, skidding system

    Transformers transported

    Project Nuclear Power Plant Tihange

    Location Tihange, Belgium

    Customer Westinghouse

    Main equipment SPMTs, jacking system

    Exchange of three steam generators

    EUROPE

    MAMMOET

    Power

    Highlight Smit Transformatoren awarded Mammoet the contract

    for the transport of two phase shifter cross regulating

    transformers. Each phase shifter unit consists of 3 indi-

    vidual 1 phase units, this means 6 units in total. Each of

    the 6 units weighs 370 t and dimensions of 10 x 5 x 6.5

    meters. The units were manufactured at Nijmegen and

    had to be transported by barge to Veendam first.

    From there, the road transport delivered the items to

    Meeden, using 16 axle lines of SPMTs. This road trans-

    port took place at night and required the removal of dou-

    ble wide street signs and lamp posts, while traffic on the

    main road was suspended. Upon arrival at Meeden,

    the items were skidded to their final position and

    jacked down .

    Mammoet World 2002 Page 15

    Trends in the market

    As economies

    around the world

    continue to grow

    more energy is

    needed. At the

    same time, due to

    environmental con-

    cerns, it is not always obvious this

    extra power should be provided

    with fossil fuel, such as oil, coal and

    gas. Instead, alternative sustain-

    able sources like wind and hydroelectric power, are becoming more

    and more popular. At the same time,

    the intense usage of power generat-

    ing equipment requires scheduled

    maintenance for both fossil fuel and

    nuclear power plants.

    Manufacturers are spread around

    the world and as a result power

    work requires transport over great

    distances, be it overseas or over

    land. Again our customers appear to

    seek door-to-door services to col-

    lect all items, deliver to the site and

    assemble into an operational plant.

    The Americas appear to be espe-

    cially active with is increasing activi-

    ty due to expansion , renovation

    and renewals of existing plants.

    Our dedicated, fully owned railcars

    are a valuable part of our ability to

    perform these transports safely

    and efficiently.

    In Europe we have many windmill

    projects in Scandinavia, Ireland,

    Germany and The Netherlands.

    Michel Bunnik,

    Market Segment Manager

    Power Europe.

  • 5/26/2018 Mammoet+World+02

    16/20

    Highlight Mammoet USA unloaded 130 pieces of a so called Cogen unit that were brought

    to the site by railcar. Some modules, like transformers, turbines and generators

    were outsized and had weights between 45 and 240 t.

    The transport from the rail siding to the construction site was tricky because

    a critical bridge was in the transport route. However, the platform trailers and

    SPMTs operated without incidents. A four point lifting gantry and a Liebherr

    LR 1450 did the bulk of the lifting work, assisted by jacking and skidding setups.

    HighlightDick Corporation is constructing two

    power plants in the area and contracted

    Mammoet for the transport of 61 items.

    Among them were 4 generator s (up to 227

    t), 4 turbines (up to 291 t), 5 transformers

    (up to 132 t), 43 modules (up to 125 t)

    and 5 steam drums (up to 132 t). In addi-

    tion, Mammoet provided lift and skidding

    services to get the heaviest items in place.

    The cargo was received from railcars and

    heavy lift vessels at various ports in the

    Boston area. A remarkable fact was that at

    the Mirant Kendall site, the largest items

    had to pass through the Central Artery &

    Tunnel project, the largest construction

    site in the USA! It involves the replacement

    of the elevated Interstate 93 by a tunnel

    under downtown Boston.

    For the passage, Mammoet received per-mission of several private landowners, civil

    contractors and the Massachusetts Bay

    Transportation Authority.

    Also the AES site had its su rprises.

    The transformer cargo needed a 85 km trip

    to the construction site, for which we used

    Scheuerle platform trailers with a transport

    frame in between. This frame reduced the

    height such that we had a free pass under

    bridges along the route, or could go over

    another 33 bridges due to the distributed

    loads on

    the wheels.

    During the turbine transport, SPMTs were

    added to increase maneuverability

    because the route had turns that could

    not be made with conventional trailers.

    Project Murray Energy Facility

    Location Dalton, Georgia

    Customer Fluor Daniel

    Main equipment SPMTs, gantry system, jacking and skidding equipment, LR 1450 crane

    Pieces in Georgia

    Highlight The centerpiece of this project was the transport of two 300 t

    steam drums and their subsequent positioning in a 60 meters

    high structure. Mammoet applied strand jacks for the lifting

    operations. In addition, Mammoet moved 6 Itrex boxes of 200 t

    each from a laydown area to the top of a 25 meter high struc-

    ture. After lifting, a skidding system was used to move the

    boxes into the structure. The lowering onto the support steel

    framework completed this challenging job. It is the first time the

    jacking and skidding techniques were applied for this customer.

    Mammoet is also supplying

    cranes through its joint ven-

    ture company AVS Services

    (Maxim Crane Works is the

    partner) on five other power

    projects in California,

    Oklahoma and Ohio.

    Project Southern Illinois Power Coop. CJB Boiler project

    Location Marion, Illinois

    Customer Foster Wheeler

    Main equipment Strand jacks, gantry system, skidding system

    Heavy drums at 60 meters height

    Project AES Granite Ridge, Mirant Kendall Repowering

    Location Boston, Massachusetts

    Customer Dick Corporation

    Main equipment Railcars, SPMTs, platform trailers

    Challenging transport route for 61 items

    AMERICAS

    MAMMOET

    Mammoet World 2002 Page 16

  • 5/26/2018 Mammoet+World+02

    17/20

    Highlight The Bellingham Power project is located some 30 km west of Boston. But the Port of Albany, were

    18 heavy lift items would arrive, is 250 km away. Mammoet was contracted to transport the genera-

    tors (325 t), turbines (230 t), transformers (165 t) and modules (between 50 and 100 t).

    Most of the distance was covered by rail.

    The two heaviest items were transported on 16 axle dedicated railcars that Mammoet and Alstom

    have available for such transport. But before they could leave, an old timber bridge had to be rein-

    forced, just to carry the weight of this special train. On the site, Mammoet was also responsible for

    installing the heaviest items onto the foundations and applied a skidding system to achieve this.

    Highlight For this project, the following items had to be received from ships hook

    and installed on foundations: a 370 t turbine, a 320 t generator and a 236 t

    transformer. Mammoet initially received a contract for a feasibility study and

    later won the order to actually execute the plan.

    This resulted in complex operations. The cargo was loaded out from the ship

    onto a barge. This barge then moved to a landing site where a special jetty

    had been constructed by B&J Mammoet. Using this, the cargo was loaded

    in and transported by B&J Mammoets conventional platform trailers over

    the road to the construction site. The actual installation was done with a

    hydraulic gantry lift system.

    Highlight The Manjung facility represents one of the largest power

    plants in the country and set a record for main contractor

    Alstom. Various heavy items needed tr ansport and installa-

    tion. Our equipment consisted, at the peak time of the pro-

    ject, of more than 18 cranes rangi ng from 30 till 1000 t.

    The majority of this cranes stayed on the site for more than

    a year as part of an advanced rental contract.

    ASIA

    MAMMOET

    Highlight The contract called for the

    offloading of two new steam gen-

    erators from a barge and transport

    these pieces of 350 t to a laydown

    area. Here, the generators will be

    dressed prior to their installation.

    The exchange takes place during

    a shutdown. Mammoet is sched-

    uled to execute this change-out

    and installation and will also posi-

    tion the two 375 t transformers

    that had been offloaded earlier.

    Project TNB Project

    Location Malaysia

    Customer Tenaga Nasional Berhad

    Main equipment Platform trailers, SPMTs

    Dedicated railcars

    Project Manjung

    Location Selangor, Malaysia

    Customer Alstom Power

    Main equipment CC 4800, LR 1450, smaller cranes

    Manjung, Malaysia

    Project Bang Bo Combined Cycle Power plant

    Location Laem Chabang and Bang Bo, Thailand

    Customer Alstom Power Thailand

    Main equipment Hydraulic gantry, conventional platform trailers

    TNB Project

    Project ANP Bellingham

    Location Albany, New York and Boston, Massachusetts

    Customer Alstom Power Inc.

    Main equipment Railcars, skidding system

    Complex operations for Alstom Power

    Mammoet World 2002 Page 17

  • 5/26/2018 Mammoet+World+02

    18/20

    On 5 March 2002 Frans van Seumeren and Andrea Palumbo,

    CEO of Palumbo S.P.A., signed the contract of the establish-

    ment of Mammoet-Palumbo. Palumbo has over 30 years experi-

    ence in heavy transport, especially related to the oil and natural

    gas industries.

    This equal share joint venture will serve the Italian and adjacent

    Mediterranean markets with transport services for industrial cargo.

    The company, managed by Alberto Galbiati and Carlo Venusino,

    has its own SPMTs available and is based in Milan.

    Trends in the market

    A key f actor to

    Mammoets world-

    wide success in

    establishing and

    expansion of its

    market position in

    various segments,

    like petrochemical, offshore, civil

    and power, is of course to have the

    right fleet of equipment available

    whenever required by the cus-

    tomers. With Mammoet Global man-aging all the bigger projects world-

    wide, good communication - and

    coordination networks are set up

    between and in the regions.

    Clients benefit from this network

    because optimal services regarding

    availability & range of equipment,

    people & know how, quality & safety

    standards can be offered directly

    and according to the standards set

    by Mammoet Global. This enables

    us to serve interregional clients

    everywhere according to our

    Mammoet standards. Another

    aspect of these standards is a solid

    regular maintenance program to

    prevent mishaps and downtime, but

    also the on-time investment in new

    equipment.

    The latter both serves replacements

    and extensions of the fleet capabili-

    ties in transport and lifting services.

    However, with an excellent fleet,

    logistics, safety, crews and know

    how, the continuity of services is

    still not sufficient.

    It is also Mammoets ambition to

    provide benefits to both existing

    and potential customers. These new

    potentials are located in industrial

    development areas and countries

    that can be considered emerging

    markets. Therefore, customers

    expect lifting and transport services

    to be available immediately.

    To speed up its presence and

    deploy its facilities rapidly,

    Mammoet adopted the strategy of

    establishing close co-operations

    with existing players in local mar-

    kets. This cooperation may be

    shaped like a strategic alliance, a

    joint venture , an acquisition o r any

    other mode. Recent examples of

    this strategy are the establishments

    of Mammoet Irga, Mammoet Norge,

    Mammoet Palumbo and Mammoet

    Van Oord.

    Patrick Freericks,

    Director Sales & Marketing.

    Market Developments

    Mammoet and Van Oord ACZ have joined forces.

    The new venture will operate under the name

    Mammoet Van Oord. To this end, a Jack-up

    Installation Barge has been developed and built.

    Apart from Mammoet and Van Oord ACZ, othe r

    shareholders are Hovago Cranes (a member of the

    Baris group) and Marine Construct. The first focus

    of the company will be on the installation of off-

    shore windfarms. Besides the offshore windfarm

    installation market, Mammoet Van Oord is looking

    at offshore lifting and transport activities in the field

    of installation and decommissioning works in the

    oil & gas industry, marine civil construction worksand wreck removal. A vital asset in the new venture

    is the Jack-up Installation Barge Jumping

    Jack(see article on next page).

    The combination between the companies enables

    Mammoet Van Oord to be an EPC contractor for

    the installation of complete offshore windfarms.

    The Jumping Jack enables turn key operations

    when combined with onshore transportation and

    lifting capacities of Mammoet and the installation

    of scour protection around the foundations of the

    wind turbines and the infield and shore export

    cable-lay capacities of Van Oord ACZ. Hence, cus-

    tomers are provided a single point of contact for all

    offshore operations

    Recently, Mammoet Van Oord won a contract for

    the transport and installation of 80 windturbine

    foundations and transition sections for the Danish

    Horns Rev windfarm. The foundations consist ofa monopile, with a diameter of 4 meters, 33 meters

    high and with a weight of 165 t. This Windfarm will

    be built off the Danish North Sea coast under a

    contract of Elsam. Its projected total electrical

    capacity is 160 MW. The Jumping Jack will

    carry ten foundations per transport to the

    construction site.

    To establish a firm position in the

    Norwegian market, Mammoet

    recently acquired the majority of the

    shares of Nilsen & Skifjeld Kran-

    service A.S. The new company is

    split up into two divisions.

    The company Kranringen, which is

    responsible for the day to day mar-

    ket and Mammoet Norge which is

    responsible for the larger projects.

    The office is situated at Skien, in the

    south of Norway, which is a large

    development area. The local pres-

    ence, together with a directly avail-

    able stock of specialized equipment

    that includes SPMTs, various cranes

    upto 120 t and a 400 t floating

    crane, makes Mammoet a full ser-

    vice provider, serving both the high

    and medium/low end of the market

    for lifting and transport services, be

    it onshore or at sea.

    Mammoet-Palumbo enters Italian market

    Developments in Norway

    As of 1 February 2002, the joint venture between Holift, Irga Luperico Torres, and Mammoet has become

    operational. The new company serves the Brazilian market for heavy and outsized lift and transport services.

    All partner s, are family owned companies by origin and

    share a similar background and culture. It is characterized

    by short communication lines, high safety standards and

    dedication to the customer by adding as much value as

    possible through the provided services. The local experi-

    ence with all kinds of power plants and refineries, com-

    bined with Mammoets global expertise that includes the

    power and petrochemical industry, sets the stage for a

    beneficial cooperation. The joint venture initially invested

    in several crawler cranes. The latest investment, the

    LR 1400/2, is on its way and ready to lift in Brasil

    in August.

    Mammoet Irga Do Brasil Ltda

    P LUMBOM O

    Introducing Mammoet Van Oord

    Mammoet World 2002 Page 18

  • 5/26/2018 Mammoet+World+02

    19/20

    The new Mammoet premises at Schiedam (greater Rotter-

    dam area), the Netherlands, is being transferred into a ter-

    minal for heavy lift equipment. The site is situated on the

    shore of the Nieuwe Maas River, the gateway to main port

    Rotterdam. The deep water terminal has direct access to

    all inland river destinations aswell as to the excellent rail-

    and road infrastructure in Europe. Furthermore there is a

    direct sea link to all overseas destinations. The deep-water

    quay is 1 kilometer long and thus may handle several

    cargo ships and barges simultaneously. Of the 85 000

    square meter area, 25 000 square meter will become avail-

    able as storage area for customers, seeking a temporarily

    storage site for items of 50 t and up. It is an excellent facil-

    ity to store turbines, generators and transformers for power

    plants. Also reactors, vessels and steel constructions for

    the petrochemical sector, and offshore equipment can be

    accommodated easily. Mammoet expects the site to

    become fully operational as of the fall of 2002. Two 350 t

    quay cranes will cover the full yard. The offered services

    include load-out and load-in, transshipment, storage,

    warehousing, workshops, assembly, packing, customs

    handling and services as and when required.

    Through our recent acquisition of Joe D. Hughes from

    Brown & Root, it should be noted that a similar terminal is

    under development in Houston, Texas (USA)

    to serve the North American and Mexican

    markets. A fast railway link is available for

    efficient ship train loading and vice versa,

    which may include Mammoet-owned special

    heavy cargo railcars.

    Mammoets Heavy Lift Terminals at Rotterdam and Houston

    MSG 100: Upgrade of MSG lifting system

    On 12 June 2002 the center of Dutch

    Parliament, the Knights Hall at the

    Binnenhof in The Hague, is the scene for

    a special meeting of the Ki ng Willi am I

    Foundation. His Royal Highness PrinceClaus of the Netherlands is Honorary

    President. Representatives from various

    economic sectors, organizations, gov-

    ernmental institutions, previous laureates

    (including Ahold and Heineken) and the

    press wi ll witnes s this y ears Award t o be

    handed ov er to Mammoet . The award

    honors Dutch companies that made sig-

    nificant c ontribution s to econom ic activi -

    ties in The Netherlands, with emphasis

    on performance, policy and actions.

    According t o CEO Frans van Seume ren,this award is of special value since it

    really rec ognizes th e years l ong dedic a-

    tion and perseverance of our staff

    worldwide. I consider this recognition as

    a pricele ss shared value of all our

    Mammoet-family members.

    Mammoets engineering department

    is busy with an upgrade on one of

    the MSG lifting systems. This crane,

    called The MSG-100, will be devel-

    oped mainly for the offshore market.With this ultimate lifting tool, mod-

    ules of over 2,000 tons can be lifted

    and placed onto FPSOs (Floating

    Production and Storage Offshore

    vessel).

    Also modifica tions are upgrades to

    existing jack up rigs and floaters can

    be carried out with the MSG-100.

    Legs of the rig can be lifted as one

    piece even at greater radius.

    The MSG-100 will be fully container-

    ized. The main difference is the

    height of the main boom. In order to

    create a better resistance againstbuckling, the height of the boom is

    increased. The boom will be shipped

    within container dimensions and

    once on site the height will be

    extended. This combines the trans-

    port effectiveness and greater boom

    capacity.

    Four legs of 42 meter length can lift the 91 x 33 x 7

    meter seagoing barge Jumping Jack out of the

    water. It thus creates a very robust and stable

    working platform, permitting operations even in

    severe weather conditions with high waves. As this

    barge was developed by Mammoet engineers, two

    important criteria had to be met. The Jumping

    Jack should provide quick and efficient services,while the installation operations itself are less vul-

    nerable to disruption. The barge can also be quick-

    ly dispatched and brought into position, from one

    construction site to the next. The innovative

    hydraulic winches lift and lower the barge with

    unprecedented speed, even with a full load up to

    4000 Te on its deck. With an onboard crane capa-

    city of 1200 t, it is very versatile in a wide range of

    jobs. When needed, additional cr ane capacity can

    be installed.

    The Jumping Jack makes its maiden trip as this

    Mammoet World is issued.

    A hybrid of the two biggest and

    strongest Mammoet cranes, the

    MSG and the PTC. Thats what

    the Engineering and Product

    Development department is look-

    ing for. In this design, the MSG

    masts are rigged as legs of a

    giant jacking portal. By connect-

    ing these with girders to the main

    boom of the PTC, this leviathan is

    capable of lifting 3000 t with a

    maximum boom length of 108

    meter. In fact, Mammoet is reviv-ing a ten-year-old idea, originally

    invented as an extension of the

    Demag CC 4800 crawler crane.

    But the development of the new

    generation ringer cranes made

    this construction redundant before

    it could be tried out. However, to

    meet the requests in the market

    for positioning columns that are

    still growing in size, with 2500 t as

    a modern run-of-the-mill con-

    struction, Mammoet made an

    inventory of options to address

    these needs on short notice. One

    of the striking advantages of this

    hybrid system is that both the

    MSG masts and the girders can

    be dispatched fully containerized

    to any PTC. Thus, at modest extra

    cost, the lift capacity may be

    increased dramatically. Mammoetexpects the super crane to enter

    service in spring 2003.

    Mammoet wins the King William I Award SC&RA Rigging Job of The Year Award

    At the e nd of Apr il, the S pecializ ed Carriers & Rigging A ssociation (SC&RA)

    held it s annual c onference in Tucson, Arizona (USA). The association has about

    1000 members from 43 countries. All are active in lifting and transport activi-

    ties. Each year, awards of recognition are announced for three categories.

    Mammoets entry, the Kursk salvage, won the award in the category of projectsworth more than US $ 750 000. Wessel Helmens, one of the Project Managers

    on the Kursk Salvage, accepted this prestigious price and succeeded to

    explain the basics of the rigging aspects in only 20 minutes. Spectacular video

    shots convi nced all attendees that this year there could onl y be one winner.

    In its judicium, the jury emphasized the safety, innovation, planning and com-

    plexity aspects of the me morable li fting and rigging job .

    The Jumping Jack rules the waves

    Best of both worlds

    Mammoet World 2002 Page 19

    Fase 1

    Fase 3

    Fase 2

  • 5/26/2018 Mammoet+World+02

    20/20

    Mammoet Trading

    Mammoet continues to be a dominant player

    in the world and regional markets for trading

    cranes and other equipment. It is an estab-

    lished fact that, before reselling such items,

    they comply with Mammoets high internal

    standards concerning safety and performance.

    The demands and supply change quickly.

    This is why Mammoet utilizes increasingly the

    World Wide Web for posting offers and taking

    requests. Relations may apply for a personal-

    ized customer number to get to the non-public

    information pages, showing prices and condi-

    tions. Interested? Please checkout our website

    at www.mammoettrading.com

    Colofon EditorMammoet Holding B.V., Corporate Communications Photography Employees Mammoet Text De Spil B.V.

    Design & Layout Graphic Invention Printing Drukkerij Zuidam & Zonen B.V. Copyright Texts and photos can only be reproduced after permission from the editor.

    EMD

    Facilitating top performance

    To exploit synergy

    potential, best

    economy of scale

    and world wide

    efficiency, the

    Equipment

    Management

    Department (EMD) is responsible for

    various central facility services.

    For instance, the purchase of equip-

    ment is an opportunity to introduce

    better standardization in types, sup-pliers and maintenance procedures.

    This not only refers to cranes or

    trailers, but also to larger parts of

    equipment, like engines and jacking

    systems. One of the facilities is the

    worldwide management of technical

    standards.

    This enhances the exchange and

    cross utilization of equipment

    owned by Mammoet Global, as

    well as the regional business units

    and joint ventures / subsidiaries.

    A striking aspect is the introduc tion

    of online tracking and tracing of

    equipment, by reading out barcodes

    before and after each movement of

    equipment. By doing so, essential

    information about which equipment

    is available at what location, is

    online available. A last example of

    the EMD scope can be found in

    Product Development, which among

    others intends to maintain a project

    governance system that makes

    experiences and solutions, devel-

    oped world wide, to any engineering

    department in the Mammoet Group.

    Jan van Seumeren jr,

    Managing Director EMD.

    It is expected that the market for windmill power

    plants will continue to increase for years to come.

    Apart from the installa tion of new mills, the owner s

    will be confronted with more intense scheduled

    maintenance. This could even involve the exchange

    of the rotor and the generator. Mammoets Product

    Development department engineered and intro-

    duced a small, smart crane that fits the pole of the

    windmill and assists in various assembly tasks.

    Manufacturers consider to provide such crane upon

    ordering a set of windmills, as a kind of standard

    tool. Named after the Greek mythological God of

    the cool western breeze, this Zephyros device is a

    typical example of how Mammoets Product

    Development department potential yields products

    to the benefit of the customer.

    Zephyros: smart crane for windmills

    Mammoet has given the green light to start the construction of an all

    new state of the art Containerized Crawler Crane (CCC). The cranes

    are going to be built by Purple C B.V., a joint venture company with

    Mammoet and Huisman-Itrec B.V. as shareholders. The first batch will

    probably count for two sister cranes, but plans have been prepared to

    extend this series to possibly 10 20 subsequent standardized

    cranes. Key features of this CCC are:

    standard lift capacity of 1250 t

    full crawler maneuverability with full load, including making

    sharp turns

    extremely low surface loads between 20 and 30 t per

    square meters

    fully containerized in approximately 75 standard containers

    with a weight less than 20 t

    advanced computer management and control

    redundant drives hydraulic emergency control that even operates in case of

    a complete electrical failure

    complete rigging on site in a couple of days

    The CCC has been designed by Purple C especially to fill a gap in lift

    capacities between 800 and 1600 t, a range where Mammoet antici-

    pates a quickly developing need for quick rigged and de-rigged

    cranes from various customers in the petrochemical market, the con-

    struction and maintenance of power plants and civil projects.

    According to Klaas Lamphen, Manager Product deve lopment on the

    CCC development, this crane pushes the envelope of safety levels,

    performance and reliability. The CCC can be equipped with a ballast

    trailer, but may also operate without one. This enables the application

    in very small working areas while still maintaining the high safety lim-

    its. The counter weights are included in the container package. He

    expects the first CCC to enter service at about the end of this year.

    Initially, the cranes will be exploit through the Mammoet fleet. It is the

    intention to sell these cranes, in some cases, to third parties.

    Precursor of a new series: the Triple C

    VAN SEUMEREN GROUP worldwide specialists in heavy lifting and transport

    http://www.mammoettrading.com

    Mammoet Trading

    Cranes

    Transport

    Others

    Search order

    Mammoet website

    Contact

    SISpecial

    Offer!

    Finding the right second-hand equipment for your business at the right time and at the right price

    is a daunting experience.

    Normally, your choice is limited to a number of local traders or suppliers, who mostly operate through

    third parties, which often means selling for a less than perfect solution or spending more on new

    equipment instead.

    Lifting quality, to a higher level