Major Mobility Investment Program (MMIP) Update Meeting Documents...Construction South of Windy Hill...

40
1 Major Mobility Investment Program (MMIP) Update Joe Carpenter, P.E. Division Director of P3 Program Delivery Committee October 18, 2017

Transcript of Major Mobility Investment Program (MMIP) Update Meeting Documents...Construction South of Windy Hill...

Page 1: Major Mobility Investment Program (MMIP) Update Meeting Documents...Construction South of Windy Hill Road Express Lanes Nearly Complete I-575 Roadway Construction on Schedule Schedule:

1

Major Mobility

Investment

Program (MMIP)

Update

Joe Carpenter, P.E. Division Director of P3

Program Delivery Committee

October 18, 2017

Page 2: Major Mobility Investment Program (MMIP) Update Meeting Documents...Construction South of Windy Hill Road Express Lanes Nearly Complete I-575 Roadway Construction on Schedule Schedule:

2

Presentation Overview

• Alternative Delivery Background

• Legacy Projects Update

• Major Mobility Investment Program (MMIP)• Program Overview

• Consultant Opportunities

• FY 2018 Project Updates

• Engagement and Collaboration Activities

• Upcoming Activities

Page 3: Major Mobility Investment Program (MMIP) Update Meeting Documents...Construction South of Windy Hill Road Express Lanes Nearly Complete I-575 Roadway Construction on Schedule Schedule:

3

Addressing Transportation Needs –Innovation and Collaboration

Innovative Delivery and Financing

Focus on Connectivity for the Future

Current and Future Regional Collaboration

Page 4: Major Mobility Investment Program (MMIP) Update Meeting Documents...Construction South of Windy Hill Road Express Lanes Nearly Complete I-575 Roadway Construction on Schedule Schedule:

4

Legacy Projects

Page 5: Major Mobility Investment Program (MMIP) Update Meeting Documents...Construction South of Windy Hill Road Express Lanes Nearly Complete I-575 Roadway Construction on Schedule Schedule:

5

Northwest Corridor Construction

Current Bridge

ConstructionSouth of Windy Hill Road

Express Lanes

Nearly CompleteI-575

Roadway

Construction

on Schedule

Schedule:

Opening to traffic

85% Complete

Page 6: Major Mobility Investment Program (MMIP) Update Meeting Documents...Construction South of Windy Hill Road Express Lanes Nearly Complete I-575 Roadway Construction on Schedule Schedule:

6

Northwest Corridor Construction –On Schedule

• 33 complete

• 6 under construction

• 91% (199 of 219) bridge deck spans complete

• 58 complete

• 10 under construction

39 Bridges: 68 Retaining Walls:

Page 7: Major Mobility Investment Program (MMIP) Update Meeting Documents...Construction South of Windy Hill Road Express Lanes Nearly Complete I-575 Roadway Construction on Schedule Schedule:

7

Northwest Corridor Construction

September 2016July 2017

Page 8: Major Mobility Investment Program (MMIP) Update Meeting Documents...Construction South of Windy Hill Road Express Lanes Nearly Complete I-575 Roadway Construction on Schedule Schedule:

8

Northwest Corridor Construction

Nighttime beam setting at I-75/I-285 interchange

Page 9: Major Mobility Investment Program (MMIP) Update Meeting Documents...Construction South of Windy Hill Road Express Lanes Nearly Complete I-575 Roadway Construction on Schedule Schedule:

9

Northwest Corridor Construction

Construction at the I-75/I-285 interchange

Page 10: Major Mobility Investment Program (MMIP) Update Meeting Documents...Construction South of Windy Hill Road Express Lanes Nearly Complete I-575 Roadway Construction on Schedule Schedule:

10

Northwest Corridor Construction

I-75/I-285 Interchange

General Purpose

Express Lanes

Page 11: Major Mobility Investment Program (MMIP) Update Meeting Documents...Construction South of Windy Hill Road Express Lanes Nearly Complete I-575 Roadway Construction on Schedule Schedule:

11

I-85 Extension 10 miles of newly

constructed roadway

Additional auxiliary

lanes will provide

better traffic flow

1 new northbound lane

1 new southbound lane

(HOT 3+)

Schedule:

Opening to traffic

Page 12: Major Mobility Investment Program (MMIP) Update Meeting Documents...Construction South of Windy Hill Road Express Lanes Nearly Complete I-575 Roadway Construction on Schedule Schedule:

12

I-85 Express Lanes Extension

3 bridges• SR 20 widening: 100%

completed

• NB Express Lane over I-985: 17% completed

• I-85 SB over I-985: 39% completed

56% completed

Bridge Construction:

Asphalt

Placement:

9 walls

• 26% completed

Noise Barrier Wall Construction:

Page 13: Major Mobility Investment Program (MMIP) Update Meeting Documents...Construction South of Windy Hill Road Express Lanes Nearly Complete I-575 Roadway Construction on Schedule Schedule:

13

I-85 Express Lanes Extension

Newly widened bridge for I-85 Express Lanes

Page 14: Major Mobility Investment Program (MMIP) Update Meeting Documents...Construction South of Windy Hill Road Express Lanes Nearly Complete I-575 Roadway Construction on Schedule Schedule:

15

I-85 Express Lanes Extension

Asphalt paving and median barrier footing north of SR 20

Buffer

Separated

Page 15: Major Mobility Investment Program (MMIP) Update Meeting Documents...Construction South of Windy Hill Road Express Lanes Nearly Complete I-575 Roadway Construction on Schedule Schedule:

16

I-85 Express Lanes Extension

Median grading north of I-985

Page 16: Major Mobility Investment Program (MMIP) Update Meeting Documents...Construction South of Windy Hill Road Express Lanes Nearly Complete I-575 Roadway Construction on Schedule Schedule:

17

Transform 285/400

Page 17: Major Mobility Investment Program (MMIP) Update Meeting Documents...Construction South of Windy Hill Road Express Lanes Nearly Complete I-575 Roadway Construction on Schedule Schedule:

18

Transform 285/400 Construction

Schedule:

Estimated Construction

Completion

Page 18: Major Mobility Investment Program (MMIP) Update Meeting Documents...Construction South of Windy Hill Road Express Lanes Nearly Complete I-575 Roadway Construction on Schedule Schedule:

19

Current and Upcoming Activities

Current Work:

Mount Vernon Highway

bridge over SR 400

replacement

SR 400 and I-285 site

preparation & tree clearing

Daily Flexible Shoulder

Lane (flex lane) closures

Upcoming Work:

Utility relocations

Grading on SR 400

Construction of drainage and

retaining walls on SR 400

Permanent flex lane

closures

Detours within the I-285/SR

400 interchange

Page 19: Major Mobility Investment Program (MMIP) Update Meeting Documents...Construction South of Windy Hill Road Express Lanes Nearly Complete I-575 Roadway Construction on Schedule Schedule:

20

Existing I-285/SR 400 Interchange

Page 20: Major Mobility Investment Program (MMIP) Update Meeting Documents...Construction South of Windy Hill Road Express Lanes Nearly Complete I-575 Roadway Construction on Schedule Schedule:

21

Proposed I-285/SR 400 Interchange

Bike/Ped

Path

Page 21: Major Mobility Investment Program (MMIP) Update Meeting Documents...Construction South of Windy Hill Road Express Lanes Nearly Complete I-575 Roadway Construction on Schedule Schedule:

22

Project Progress

Page 22: Major Mobility Investment Program (MMIP) Update Meeting Documents...Construction South of Windy Hill Road Express Lanes Nearly Complete I-575 Roadway Construction on Schedule Schedule:

23

Project Progress

Page 23: Major Mobility Investment Program (MMIP) Update Meeting Documents...Construction South of Windy Hill Road Express Lanes Nearly Complete I-575 Roadway Construction on Schedule Schedule:

24

Major Mobility Investment Program (MMIP)

Page 24: Major Mobility Investment Program (MMIP) Update Meeting Documents...Construction South of Windy Hill Road Express Lanes Nearly Complete I-575 Roadway Construction on Schedule Schedule:

25

Major Mobility Investment Program (MMIP)

$11 Billion Program Uses Innovative Delivery and

Public-Private Partnerships

to accelerate projects

11 projects under contract

in 10 years (by 2026)

Page 25: Major Mobility Investment Program (MMIP) Update Meeting Documents...Construction South of Windy Hill Road Express Lanes Nearly Complete I-575 Roadway Construction on Schedule Schedule:

26

MMIP Projects

Page 26: Major Mobility Investment Program (MMIP) Update Meeting Documents...Construction South of Windy Hill Road Express Lanes Nearly Complete I-575 Roadway Construction on Schedule Schedule:

27

One of the Largest Programs in Country

Page 27: Major Mobility Investment Program (MMIP) Update Meeting Documents...Construction South of Windy Hill Road Express Lanes Nearly Complete I-575 Roadway Construction on Schedule Schedule:

28

MMIP Schedule

Page 28: Major Mobility Investment Program (MMIP) Update Meeting Documents...Construction South of Windy Hill Road Express Lanes Nearly Complete I-575 Roadway Construction on Schedule Schedule:

32

FY 2018 Project UpdatesI-85 Widening

I-16 Widening and I-16/I-95 Interchange Improvements

Page 29: Major Mobility Investment Program (MMIP) Update Meeting Documents...Construction South of Windy Hill Road Express Lanes Nearly Complete I-575 Roadway Construction on Schedule Schedule:

33

I-85 Widening• Early MMIP Project

o Provides an additional general purpose lane in each

direction

o Replaces three off-system overpass bridges and two

mainline bridges along I-85

• Status: Apparent Best Proposer Selected

o C.W. Matthews (ICE) - $114.7M

o DBE Goal: 13%

o Best value, variable scope procurement approach

resulting in a 4-mile addition of capacity (16 total miles)

o This advanced project to the next interchange, which is

where the Amazon warehouse is located

o Process allows for multiple segments of traffic to open

early

Page 30: Major Mobility Investment Program (MMIP) Update Meeting Documents...Construction South of Windy Hill Road Express Lanes Nearly Complete I-575 Roadway Construction on Schedule Schedule:

34

I-85 Widening Project

10 Proposed

Noise Walls:

2 Proposed

Retaining Walls:

1 Proposed

Median Walls:

5 Replaced

Bridges:

Total Construction

Costs

$135M

Cost:

1 General Purpose Lane in Each Direction

New Lanes:

Design-Build

Procurement:

Page 31: Major Mobility Investment Program (MMIP) Update Meeting Documents...Construction South of Windy Hill Road Express Lanes Nearly Complete I-575 Roadway Construction on Schedule Schedule:

35

I-16 Widening and I-16/I-95 Interchange Improvement Projects

Status: Procurement Phase

Early MMIP Project

• Reconstruct the busy

I-16/I-95 interchange to

improve safety and traffic

flow

• Widen I-16 from 4-6 lanes

from I-95 to I-516 to ease

congestion

• Opportunity to reconstruct

Dean Forest Road

interchange if funds and

bids align

Interchange

Reconstruction

Page 32: Major Mobility Investment Program (MMIP) Update Meeting Documents...Construction South of Windy Hill Road Express Lanes Nearly Complete I-575 Roadway Construction on Schedule Schedule:

36

I-16/I-95 Improvements

• ITStechnology

• New lighting

Improvements:• I-16:

$319M• Dean Forest DDI:

$28M

Cost:

• Best Value Procurement

• Design-BuildDelivery

Procurement:

9 Walls

Retaining Walls:

• 2 flyover bridges

• 4 mainline bridges

• 2 bridges at

Dean Forest Road

Bridges:

• 2 loop ramps replaced with flyover bridges

• 1 collector-distributor (CD) lane

• 1 general purpose lane in each direction

New Lanes:

Page 33: Major Mobility Investment Program (MMIP) Update Meeting Documents...Construction South of Windy Hill Road Express Lanes Nearly Complete I-575 Roadway Construction on Schedule Schedule:

37

I-16/I-95 Interchange Schematic

Page 34: Major Mobility Investment Program (MMIP) Update Meeting Documents...Construction South of Windy Hill Road Express Lanes Nearly Complete I-575 Roadway Construction on Schedule Schedule:

38

Engagement and Collaboration Actions

Page 35: Major Mobility Investment Program (MMIP) Update Meeting Documents...Construction South of Windy Hill Road Express Lanes Nearly Complete I-575 Roadway Construction on Schedule Schedule:

39

Industry Engagement

IBTTA Annual 85th Annual Meeting

& Exhibition

Page 36: Major Mobility Investment Program (MMIP) Update Meeting Documents...Construction South of Windy Hill Road Express Lanes Nearly Complete I-575 Roadway Construction on Schedule Schedule:

40

Community Collaboration

Page 37: Major Mobility Investment Program (MMIP) Update Meeting Documents...Construction South of Windy Hill Road Express Lanes Nearly Complete I-575 Roadway Construction on Schedule Schedule:

41

Transit Partnership

Page 38: Major Mobility Investment Program (MMIP) Update Meeting Documents...Construction South of Windy Hill Road Express Lanes Nearly Complete I-575 Roadway Construction on Schedule Schedule:

42

Outreach

Readiness

Mentoring

DBE Engagement

Developer/

Design Build

Team

Program

Management

Consultant

(PMC)

General

Engineering

Consultant

(GECs)

Page 39: Major Mobility Investment Program (MMIP) Update Meeting Documents...Construction South of Windy Hill Road Express Lanes Nearly Complete I-575 Roadway Construction on Schedule Schedule:

44

Key Upcoming Activities

Aligning GEC Teams for Success

STIP Approval

Procure Remaining

GEC Contracts

Northwest Corridor Express

Lanes Open

I-85 Express Lanes

Extension Open

Fall 2017 Fall 2017

Winter 2018

Summer 2018 Fall 2018Ongoing

Focus on Delivery

Page 40: Major Mobility Investment Program (MMIP) Update Meeting Documents...Construction South of Windy Hill Road Express Lanes Nearly Complete I-575 Roadway Construction on Schedule Schedule:

45

Program Contact and Information

Joe Carpenter, P.E.

Division Director of P3

Program Information

www.garoads.org

www.dot.ga.gov/BS/Projects/MMIP