Substation Construction project. Project Schedule

download Substation Construction project. Project Schedule

of 12

description

Short presentation over the ongoing progress of the project. Project Schedule

Transcript of Substation Construction project. Project Schedule

Butwal Kohalpur 132 kV Substation Project

Bishnu ChapagaiJanuary 2, 2012CWE NHE Joint Venture

Butwal Kohalpur 132 kV Substation Project

OutlinesIntroductionProposed Project Organization ChartWork ScheduleWork ProgressSummary and Future works

2Introduction Salient Features3Butwal3Introduction Contract Agreement4EmployerNepal Electricity Authority, Grid Development, TLSCD ContractorCWE NHE Joint VentureSigning DateDecember 27, 2010Contract Effective

LC effective in favor of CWE NHE JV (Expected date: January 9, 2012)Completion Period18 months from Contract effective dateContract Amount USD 3.7 million + NPR 158 millionApproved ManufacturersJSB, HEAG and NISSIN (China), AREVA T&D, ABB, STATCON (India), COMMTEL (Finland)

December 27, 2010Proposed Project Organization Chart Core Team5Work Schedule - Highlights 6ACTIVITIESCOMPLETIONExpected date of Contract EffectiveJanuary 9, 2012Civil works of existing S/SMay, 2012Civil works of Kusum S/SSeptember, 2012Equipment Procurement and DeliveryJuly, 2012Erection and Installation worksDecember, 2012Testing & CommissioningJanuary, 2013Request letter for Taking Over CertificateFebruary, 2013Microsoft Project Based on Contract Effective dateWork Progress - Major7Electrical Design/Drawings SLD and Layout of existing S/S approved . SLD and Layout of Kusum to be submitted.Civil Design/DrawingsFoundations and Steel of existing S/S Submitted to NEA. Control Building for Kusum undergoingCivil WorksContractors for four existing S/S selected. Anchor bolts for foundations orderedMajor Equipment from foreign originTransformers and Battery/Charger under manufacturing. GCB inspection on Jan 3, 2012. PA with ABB, COMMTEL and AREVA (11 kV VCB and Panel) in processLocal MaterialsDistribution Line materials for Kusum orderedTopographical Survey in KusumCompletedSoil Exploration works at KusumCompletedSoil Resistivity Test in all five S/SCompletedGantry Structures VerificationCompletedEquipmentsStatusInstrument Transformers, DS and LA HEAG, ChinaRevised Drawings received after a long follow up. Still lots of commentsCapacitor Bank NISSIN, ChinaClarification on Drawings to be accepted by NEARTU ABB, IndiaBOM finalized and Price Schedule to be revisedOLTE COMMTEL, FinlandBOM finalized and PA sent to the party11 kV VCB and CRP SCHNEIDER, IndiaSigned/Sealed PA to be received from manufacturer7Work Progress - Snapshots8

TOPOGRAPHACALSURVEY AT KUSUMWork Progress - Snapshots9SOIL EXPLORATION WORKS AT KUSUM

Work Progress - Snapshots10SOIL RESISTIVITY TEST

Summary and Future works11Work Plan/ScheduleContract Effective dateProgress upto dateDelay in Civil Works in Existing S/SSite Clearance in KusumCivil Contractor Selection for Kusum

Questions and Recommendations..!

THANK YOU

12CWE NHE Joint Venture Butwal Kohalpur 132 kV Substation Project