Maintenance of buried corrugated steel bridges in … · Maintenance of buried corrugated steel...
Transcript of Maintenance of buried corrugated steel bridges in … · Maintenance of buried corrugated steel...
Maintenance of buried corrugated steel bridges
in regional Victorian railway
By: Ali Chaboki- V/Line
Principal Engineer – Structures
Network Engineering – Asset Management
8th Australian Small Bridges Conference – 2017
1
Introduction
About 400 buried corrugated steelpipes (Armco- trade mark) have beeninstalled in the V/Line network in 129locations
They were a cost effective solution forthe railway back in the 70s and 80s
Most are considered to be nearingtheir expected life
The issue with most locations is the zinccoating loss and corrosion has started
The asset management of these pipesand assessment of their reliability isdiscussed in this presentation
8th Australian Small Bridges Conference - 2017
2
Topics V/Line network
Armco pipes in the V/Line network
Armco pipes – Asset management perspectives
Corrosion rate in zinc Layer and steel
Critical thickness/section loss
Case study- Morwell River
Remediation and replacement of corrosion-damaged pipes
Conclusion
8th Australian Small Bridges Conference – 2017
3
V/Line
8th Australian Small Bridges Conference - 2017
4
• V/Line is largest regional public transport operator, in 2016-17 more than
19.3 million train and coach passenger trips were taken
• In addition to being a passenger service operator, V/Line maintains,
3,520 kilometres of rail track used by passengers and freight rail services
• About 1200 bridges and 5000 culverts are being maintained by V/Line
Facts about the ARMCO pipes in V/line network They were a cost effective solution for the railway back in the 70s and 80s
Number of locations: 129 locations, 400 pipes
Total Area : 41,000m2 – now 28,000 m2
Biggest Diameters : 5.5 meters
Longest pipe : 60 m (Parwan Creek)
Minimum diameter 0.6 m
Thickness 3 -5 mm
2…15,071
m2
Area of Armco pipes in the
V/line Network (2010)
Total Area (41,284 m2)
Pas…8th Australian Small Bridges Conference - 2017
6
6,245
4,5814,860
11,446
3,2202,946 2,830
1,4211,125
458 339
1,058
151 217 183 75 34 68 26
4,888
3,187
2,362
8,119
2,4622,122
574
1,4211,124
4580
1,059
151 2170 75 0 68 26
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
Arm
co
pip
e t
ota
l A
rea
(m
2)
Line section
Line vs Armco pipe Area
original Area
remained Area
Facts about the ARMCO pipes in V/line network – cont’d
Risks to effective asset management
Not Knowing What You Have
Under Maintenance
Improper Risk Management
Improper Asset Lifecycle Management (ALM)
8th Australian Small Bridges Conference - 2017
7
An appropriate and accurate residual life prediction for an asset is
essential for cost effective and timely maintenance planning and
scheduling.
How Armco pipes fail
Consequences of failure
Likelihood of failure
Residual capacity
Effect of corrosion and section loss of their reliability
AM- Asset Management Perspectives
Assessment and evaluation of the rusted pipes:
Most are considered to be nearing their expected life –nominally between 30 to 50 years depending on environmental conditions.
The actual condition information of Armco pipes is less than accurate.
After a sudden line closure in 2013, because of an urgent defect, to manage the risks, we considered the more precise assessment, more frequent assessment
8th Australian Small Bridges Conference - 20178
Possible Defects
Zinc coating loss
Rusting, corrosion and delamination specially at the invert
Severe deformation, bulging and out of roundness
Undermining of the track formation
due to corrosion, the moment of inertia and the cross-sectional area of the
wall are decreased with a resulting reduction in pipe strength.
In addition, this will increase the deformation of the pipe and soil under the
sleeper.
Risk management
• More effective assessment- more frequent inspection
• Life extension – asset life management
• Rehabilitation of defective pipes (short term, mid term and long term
mitigation and remedial plan)
Defects : zinc coating loss3 different exposures
Atmospheric exposure 1.5 μm/y - AS/NZS 4680
Exposure to water and sediment mostly at invert – to be discussed AS 2041
Exposure to fill material behind the pipe 2-4 μm/y - AS 2041 - depends on the soil PH, drainage
8th Australian Small Bridges Conference - 2017
10
Discussion : Exposure to water and
sediment : 25 to 30 years after installation of pipes, corrosion appeared on their invertZinc coating loss is about 3- 5
microns/year -75-micron initial thickness
based on AS 2041, “the invert of the structure below the usual waterline may, under certain conditions, be subject to abrasion and corrosion.”
NDT-Thickness assessment- Report sample
8th Australian Small Bridges Conference - 2017
11
Corrosion rate of exposed steel
Original
thickness
Corrosion
later
thickness
Zinc layer
loss
Expected
life of the
zinc layer
Corrosion
rate of bare
steel
Expected time to
loose 25% of the
section
Estimated Total
effective lifetime
3 mm 75- 85
micron
3 -5 micron 25-30 years 40-50
micron
12-15 years 35-45 years
5 mm 85 micron 3 -5 micro 25-30 years 40-50
micron
25-35 years 50-65 years
8th Australian Small Bridges Conference - 2017
12
• Residual lifetime? • Reliability of assets• Risk
The corrosion of bare unprotected steel without any protection is about 40-50 micron per year-
Critical thickness/section loss: Case study- Morwell River
8th Australian Small Bridges Conference - 2017
13
Critical thickness/section loss: Case study- Morwell River
8th Australian Small Bridges Conference - 2017
14
Thickness Buckling
load (kn)
Factor of
safety
4 mm 800 2.5
2.5 – lower part 500 1.3
1 mm lower part 210 0.7
Failure mode 1: Severely deformed and weak pipe:
8th Australian Small Bridges Conference - 2017
15
Failure mode 2: Major crushing
Maximum allowable section
loss
Based on the investigation, the factor of safety varies
from asset to asset, however, maximum 25% section
loss of thickness in large area can reduce the pipe
hoop and flexural strength about 40%.
Pipes have been designed using ASD. Factor of safety
is about 60%
However, is railway industry, dynamic factor load will
reduce this safety margin.
8th Australian Small Bridges Conference - 2017
16
Possible Remedial ActionsTemporary props
Plastic lining (Spiral or sprayed)
Polyvinyl Chloride Sleeve
Fold and Form
New Steel Plate
Relining with a pipe
8th Australian Small Bridges Conference - 2017
17
3 Major Remedial options V/line used in the past
1: Half/Invert Lining with reinforced shotcrete
8th Australian Small Bridges Conference - 2017
18
3 - Major Remedial Options we used in the past
2: Full lining with reinforcement shotcrete +
shear connectors- large culverts (Dia > 2 m)
8th Australian Small Bridges Conference - 2017
19
3 - major Remedial Options we used in the past
Replacement of the pipe with concrete pipes – Dia <2 m
8th Australian Small Bridges Conference - 2017
20
Long term planning
More effective Inspection and Assessment – ultrasonic and more
frequent inspections- NIWI-2707.10
Risk assessment
Plan to manage the risk including the replacement of
medium and small ones and lining of small ones
8th Australian Small Bridges Conference - 2017
21
Thank for Your Attention
8th Australian Small Bridges Conference - 2017
22
Any question ?