Mainstreaming Integrity throughout Commercial Organizations · Burj Khalifa Dubai, UAE . SELECT...
Transcript of Mainstreaming Integrity throughout Commercial Organizations · Burj Khalifa Dubai, UAE . SELECT...
Mainstreaming Integrity throughout
Commercial Organizations
Jeffrey Sújar
Vice President Europe
• Founded in 1976
• Public Company listed on NYSE
• Over 4,700 Professionals Worldwide
• Over 110 corporate offices covering +35 countries
Hill provides construction consulting services on
some of the most complex projects in the world
“if you can imagine it, we can manage it”
• Has participated in over 10,000 Projects
Assignments with a total Construction
Value of over US$500 Billion
• Global Leader in Independent Project
Management and Construction Claims
“Largest Independent CM Firm in the U.S.”
by ENR 2014
HILL INTERNATIONAL
SELECT EXAMPLES OF PROJECTS CARRIED OUT BY HILL
UN Campus Redevelopment
Geneva, Switzerland
Latvian National Library, Riga, Latvia
Baku Flame Towers Baku, Azerbaijan
Burj Khalifa Dubai, UAE
SELECT EXAMPLES OF PROJECTS CARRIED OUT BY HILL
Constanta By-Pass, Romania
Morine – Merdare Motorway, Kosovo
Piatra Neami, Wastewater Treatment Plant, Romania
Schools Renovation Program, Bucharest, Romania
PUBLIC PRIVATE PARTNERSHIP AGAINST CORRUPTION
INTRODUCTION
• Policies, control mechanisms and law
enforcement are vital elements in stamping out
corruption. But alone they are not enough.
• What needs to evolve is the behavior of all the
various stakeholders involved in the
procurement process.
• The challenge is how to apply these standards
across the diverse cultures in which we operate
IMPLEMENTING INTEGRITY PACT IN THE NATIONAL LIBRARY OF LATVIA
PROJECT
CASE STUDY
NATIONAL LIBRARY OF LATVIA
Idea 1980s – project starts 2003
IP – 2005
Construction starts 2008
Architect: Gunnar Birkerts
SERVICES
Design Management Project Management Support
Construction Supervision (FIDIC)
TOTAL PROJECT VALUE
€175 million
COMPLETION DATE
2013
Hill was involved in two of the project’s phases Design & tender dossier production and works supervision: • Design Management • Preparation of Tender Documents for construction works in accordance with FIDIC (Red
Book) in compliance with Latvian Construction Law • Preparation of master Tender Dossier for IT systems in accordance with FIDIC (Yellow
Book), tendered later to ensure latest systems can be adopted • Library furniture and equipment (FF&E) dossier in accordance with Latvian laws of
procurement.
HOW WAS IT DONE?
IP with the Ministry of
Culture, Anti-Corruption
Declaration for bidders
Monitoring the
construction process
Awareness raising of
contractor and sub-
contractors
Work with stakeholders
. Access to meetings, documents, people
. Regular (weekly) participation in technical meetings
. Monitoring of contract ammendments
. Ad-hoc checks with help of outside expertise
. Surveys of parties
. Accepting complaints
.Acting on suspicious information
. Minister of Culture, Supervisory Board, Parliamentary
Committees .Media relations . Public discussions
SPECIFIC GAINS
Limit scope increase for current
contractor, e.g., sollar panels
Change orders down from 15M to
9.5M EUR, by demanding
involvement of Hill in negotiations
Hill involved in reducing impact of
demanding unilateral application
of indexation clause, worth ~0.9M
EUR per Q
Hill involved in improvement of
FF&E technical project
Hill supports providing trustworthy
information to media &
professionals
FIDIC AS AN ANTI-CORRUPTION INSTRUMENT
Nominated sub-contractors
Value engineering
Variation orders, Interim payments,
determination and conflict
mitigation
Confidentiality agreement
Priority and mention of
documents
Independant supervision
THE LATVIAN NATIONAL LIBRARY